CN101770605A - R & D project plan management method and system - Google Patents

R & D project plan management method and system Download PDF

Info

Publication number
CN101770605A
CN101770605A CN200810187388A CN200810187388A CN101770605A CN 101770605 A CN101770605 A CN 101770605A CN 200810187388 A CN200810187388 A CN 200810187388A CN 200810187388 A CN200810187388 A CN 200810187388A CN 101770605 A CN101770605 A CN 101770605A
Authority
CN
China
Prior art keywords
project
task
entity
module
personal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200810187388A
Other languages
Chinese (zh)
Inventor
梁辉
卢志奋
洪学琦
宋少良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENZHEN BRONZE WARE SOFTWARE SYSTEM CO Ltd
Original Assignee
SHENZHEN BRONZE WARE SOFTWARE SYSTEM CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN BRONZE WARE SOFTWARE SYSTEM CO Ltd filed Critical SHENZHEN BRONZE WARE SOFTWARE SYSTEM CO Ltd
Priority to CN200810187388A priority Critical patent/CN101770605A/en
Publication of CN101770605A publication Critical patent/CN101770605A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a project plan management system, comprising: a project management database which comprises a project plan module, a project task module and an individual task module; a client for inputting the data relating to individual task to the individual task module in the project management database; an application server which is used for interacting with a data storage system and updating the data of the project plan module and the project task module according to the data relating to the project task that is input to the project management database by the client. The invention also discloses a project plan management method. The advantages of the system and the method provided by the invention are as follows: real-time collaboration of the project plan and the individual task can be realized, the task conflict is avoided, the timeliness and the accuracy of R & D project progress tracking are increased, and the cost of the R & D project is effectively decreased.

Description

A kind of R ﹠ D project plan management method and system
Technical field
The present invention relates to the computer information management, especially, relate to the method or the system of a kind of using computer network and database technique R ﹠ D project plan management.
Background technology
A research and development of products project scheduling needs many people's cooperations to finish, and relates generally to technician, marketing personal, tester, manufacturer, customer service personnel etc.These personnel often are distributed in different geographic areas.At present, the unit that researches and develops uses Project, Word, Excel, the PowerPoint of the OFFICE of Microsoft to wait merely and links up, can't realize upgrading in time of development of projects data, thereby cause project monitoring untimely, the work that need the lot of data distribution simultaneously, gathers directly influences the development project efficiency of managing.
The above-mentioned process of the formulation of existing development project plan and tracing management is very loaded down with trivial details and Data Update is untimely, usually only can realize with the week being the tracking and the monitoring of unit, and can't follow the tracks of and control the progress of the project scheduling and project task in real time and carry out effectively working in coordination with for example adjustment of the coupling of progress information and the project scheduling or project task data.
On the other hand, a research staff can bear the task of a plurality of projects usually simultaneously, and the managerial personnel of each project often are different personnel; Simultaneously, the research staff also needs to bear the task from functional department.The present research and development plan and the management mode of task can't realize task, functional department's task collaborative of each project, the result often causes concrete research staff to bear simultaneously from seriously conflict between the task of each side and these tasks, finally causes plan target to finish on time.
Therefore, present development project plan and personal task management method can't realize the real-time of development project plan and personal task and effectively work in coordination with, also be difficult to the conflict of personal task between the solution project and the conflict of project task and functional department's task.
Summary of the invention
Fundamental purpose of the present invention provides a kind of project management method and system, utilize computer networking technology, data storage technology and corresponding technology carry out the project scheduling and project task in real time, collaborative effectively, improve promptness and accuracy that the research and development plan is followed the tracks of and monitored, effectively avoid the conflict between development project plan, functional department plan, the personal task.
According to an aspect of the present invention, provide a kind of project management system, comprising: project management database comprises project scheduling module, project task module and personal task module; Client is in the data input personal task module relevant with personal task; Application server according to the data of client input personal task module, upgrades the data of project scheduling module and project task module.
According to an aspect of the present invention, a kind of project management method based on computer network is provided, be used for the project management system that constitutes by client that connects by computer network and application server, this method comprises: create project management database, project management database comprises project scheduling module, project task module and personal task module are in the personal task module of client with the data cuit management database relevant with project task; Server upgrades the data of project scheduling module and project task module according to the data relevant with project task of described client input.
According to such scheme, by network technology and data-storage system, realize the seamless related of development project plan and personal task, efficiently solve problems such as the project scheduling disconnects with personal task in the present research and development management, Data Update is untimely, project scheduling tracking is untimely.Simultaneously, by the personal task conflict checking mechanism of collaborative pond module, can effectively avoid the conflict of personal task between the project; Also efficiently solve the inconsistent problem of data by data storage technology and coordination technique, and then improved the operational paradigm of development project integral body.
Description of drawings
Fig. 1 shows the structured flowchart of project management system according to an embodiment of the present invention;
Fig. 2 shows the schematic flow sheet of project management method according to an embodiment of the present invention;
Fig. 3 shows the more detailed schematic flow sheet according to project management method shown in Figure 2;
Fig. 4 shows the model synoptic diagram of entity design according to an embodiment of the present invention;
Fig. 5 shows and realize project scheduling entity and the collaborative treatment scheme of personal task entity in project management system shown in Figure 1.
Embodiment
As shown in Figure 1, project management system according to an embodiment of the present invention comprises application server 1, data-storage system 2, computer network 3, one or more client device (can be computer terminal) 4.A plurality of client devices 4 link to each other with application server 1 by computer network 3, operate by Microsoft IE or other web browsers for the user.Can carry out data communication between application server 1 and the data-storage system 2, and can realize by identical or different network servo host.
In one embodiment, application server 1 can comprise project plan management module 11, personal task administration module 12, collaborative pond module 10.To describe in detail one by one above-mentioned each module below.
1. the project plan management module 11
Project plan management module 11 is used for project scheduling entity and project scheduling template entity are carried out lifecycle management, and realizes the templating of project scheduling entity and the instantiation of project scheduling template entity.Wherein, project scheduling entity can be one or more, and project scheduling template entity can be one or more.
A project scheduling entity can comprise one or more project task entities.A project scheduling template entity can comprise one or more project task entities.Each project scheduling entity, project scheduling template entity, project task entity all have a unique sign ID.
11 pairs of project scheduling entities of project plan management module carry out lifecycle management, include but not limited to: the establishment of project scheduling entity, editor, the statistical operation of preserving, duplicate, delete, make progress.When creating project scheduling entity, the project plan management module can be from external system lead-in item plan entity, or obtains project scheduling entity by the instantiation of project scheduling template; The project plan management module also can export to external system to the project scheduling entity of native system; Or with project scheduling physical templateization.
In addition, project plan management module 11 also can be carried out maintenance and management to project scheduling attributes of entities information.Project scheduling entity also can comprise following every information: project scheduling unique ID, plan title, real work amount, completion rate, deviation ratio.
Project plan management module 11 is further used for the project task entity that comprises in the project scheduling entity is operated, and includes but not limited to: newly-built task, editor's task, replication task, change task, deletion task, release tasks, audit task operating.The project plan management module is further used for the project task attributes of entities information in the project scheduling entity is carried out maintenance and management.In order to realize working in coordination with, the project task entity includes but not limited to following every information: the unique ID of project task entity, ps, plan completion date, planned workload, actual starting date, actual finish date, real work amount, completion rate, deviation ratio, task owner, task participant.
In addition, project plan management module 11 also can be carried out lifecycle management to project scheduling template entity, includes but not limited to: the establishment, editor, preservation, ordering, issue, the deletion action that export to external system, project scheduling template entity from external system lead-in item plan template entity, the project scheduling template entity of native system.The project plan management module further also can be carried out maintenance and management to project scheduling template attributes of entities information.Project scheduling template entity includes but not limited to following every information: project scheduling template unique ID, plan template title.
Project plan management module 11 is further used for the project task entity that comprises in the project scheduling template entity is operated, and includes but not limited to: newly-built task, editor's task, replication task, deletion task operating.The project plan management module is further used for the project task attributes of entities information in the project scheduling template entity is carried out maintenance and management.The task entity includes but not limited to following every information: the unique ID of project task entity, ps, plan completion date.
2. the personal task administration module 12
Personal task administration module 12 is used for operator's personal task is carried out lifecycle management, includes but not limited to: receive personal task, feedback task progress, submit task operating to.
Personal task administration module 12 also is used to compile all the personal task entities that need finish that belong to this operator, specifically comprises two generic tasks: from the personal task entity of project scheduling entity, the personal task entity of non-project scheduling entity (this part task generally is the interim personal task from functional department).
Personal task administration module 12 also is used for the personal task entity of non-project scheduling entity is carried out lifecycle management, includes but not limited to: establishment, modification, change, issue, review operations.
Personal task administration module 12 is further used for personal task attributes of entities information is carried out maintenance and management.In order to realize working in coordination with, the personal task entity need include but not limited to following every information: the unique ID of personal task entity, ps, plan completion date, planned workload, actual starting date, actual finish date, real work amount, completion rate, deviation ratio, task owner, task participant.
Personal task administration module 12 is further used for the personal task conflict rule based on system definition, the inspection that when at every turn carrying out corresponding operating, conflicts automatically at the personal task entity, and when finding that personal task meets conflict rule, point out to entry/exit conflicts.
3. collaborative pond module 10
Collaborative pond module 10 is used for the conversion of the personal task entity of project task entity in personal task administration module 12 of finished item planning management module, the progress information of the project task entity of project plan entity is collaborative in the progress information that realizes the personal task entity in the personal task module and the project plan management module 11, and is used for realizing the working in coordination with of project task entity progress information of the progress information of project scheduling entity of project plan management module 11 and project scheduling entity.
The attaching relation that collaborative pond module 10 also is used to define between the entity.As mentioned above, each project scheduling entity, each project task entity, each personal task entity all have a unique sign ID.Identify the corresponding relation of can identify project task entity and project scheduling entity by these unique ID.Project task entity project scheduling entity unique ID is by reference realized related with project scheduling entity; And project scheduling entity can obtain corresponding project task entity according to the unique ID of self by retrieve data storage system 2.
Collaborative pond module 10 also is used for defining the collaborative corresponding relation of the progress information of the project task entity of project plan entity in progress information and the project plan management module 11 of personal task entity of personal task module 12, includes but not limited to: the real work amount attribute of the real work amount attribute correspondence project task entity of the deviation ratio attribute of the corresponding project task entity of deviation ratio attribute of the completion rate attribute of the corresponding project task entity of the completion rate attribute of personal task entity, personal task entity, personal task entity.
Collaborative pond module 10 also is used for defining the collaborative corresponding relation of the progress information of project plan entity in the progress information of project task entity of project plan management module 11 project plan entity and the project plan management module 11, includes but not limited to: the completion rate attribute of project scheduling entity gathers the mean value (mean value of all task completion rates of completion rate=in the works with respect to the completion rate attribute of project task entity.The task completion rate can be the ratio of the workload that has dropped into the estimation amount of work of plan target of the real-time feedback of operator), the deviation ratio attribute of project scheduling entity gathers mean value (deviation ratio=(task actual finish time-task scheduling deadline)/(task scheduling deadline-task scheduling start time) with respect to the deviation ratio attribute of project task entity, if there is not actual finish time, then actual finish time is the time when pre-treatment), the real work amount attribute of project scheduling entity is with respect to the value that gathers of the real work amount attribute of project task entity.These information can be kept in the data-storage system automatically, and feed back to the project administrator client in real time.Project administrator can carry out the adjustment of the project scheduling and project task and personal task according to these information.
Two kinds of Synergistic methods of the progress information of the project task entity of project plan entity in the progress information that collaborative pond module 10 also is used for providing the personal task entity of realizing the personal task module and the project plan management module (real-time collaborative and regularly work in coordination with); And provide the progress information that realizes the project scheduling entity in the project plan management module two kinds of Synergistic methods, i.e. real-time collaborative and regularly working in coordination with the project task entity progress information of project scheduling entity.
For the real-time collaborative of inter-entity, can by the project plan management module provide at the corresponding operating of project scheduling entity and project task entity and trigger, or by the personal task administration module provide at the corresponding operating of personal task entity and trigger.Collaborative for the timing of inter-entity, for example, can by application server 1 every day the official hour point automatically perform co-operating and realize.
The Synergistic method that collaborative pond module 10 also is used between each entity of unified Definition project management system of the present invention.According to an embodiment of the invention, collaborative between project task entity in the data storage system 2 and the personal task entity included but not limited to following rule:
Figure G2008101873885D0000051
The collaborative Sample Rules of table 1 personal task entity and project task entity
Collaborative pond module 10 also is used for working in coordination with between unified Definition project task entity and the project scheduling entity, includes but not limited to following rule:
Figure G2008101873885D0000061
The collaborative Sample Rules of table 2 project task entity and project scheduling entity
Below, specifically describe the realization project scheduling and member's personal task synergizing method according to exemplary embodiment of the invention.This method can be applicable to comprise in the project management system of project plan management module, personal task administration module, collaborative pond module.As shown in Figure 2, this method can may further comprise the steps:
A. in project plan management module 11, create project scheduling entity and project task entity, and issue project task entity (S210);
B. the collaborative pond module 10 project task entities according to issue are converted to personal task entity (S220) with the project task entity;
C. at different operators, personal task administration module 12 gathers and shows all personal task entities relevant with this operator.The operator is according to the actual development situation of personal task, and the actual development situation of timely online feedback personal task, described progress include but not limited to that the completion rate of personal task entity, real work amount drop into information (S230);
D. the progress information of the gathering of progress information, personal task entity that collaborative pond module 10 realizes the personal task entities collaborative to project task entity progress information, simultaneously, also, realize collaborative (S240) of project task entity progress information and project scheduling entity progress information based on the attaching relation of project task entity and project scheduling entity.
An example of said method is more specifically described below in conjunction with Fig. 3.
Referring to Fig. 3, step S210 can comprise:
S211: utilize project plan management module 11 that the establishment mode of the multiple project scheduling is provided, select by the founder of the project scheduling.
S212: if the user selects from external system lead-in item plan entity, then application server 1 is a new project scheduling entity automatically with its importing and is unique sign ID of its distribution.Simultaneously, import the project task entity in this project scheduling entity, and based on the clear and definite project task entity of unique ID of the project scheduling entity that the imports attaching relation to project scheduling entity;
S213: if the user selects based on project scheduling template entity set-up project scheduling entity, then application server 1 is created a new project scheduling entity automatically and is distributed a unique sign ID for it.Simultaneously, the project task entity information that application server 1 comprises based on project scheduling template entity is created new project task entity, and based on the unique ID of the project scheduling entity of the new establishment attaching relation of task entity to project scheduling entity of identifying project;
S214: provide edit tool by the project task attributes of entities information in planning management person editor and the adjustment project scheduling entity, issue the project task entity to task owner and participant then.This attribute information includes but not limited to: task names, ps, plan completion date, planned workload, task owner, task participant.
Step S220 can comprise:
S221: check rule based on the personal task conflict of system definition, at the inspection that conflicts of newly-built personal task entity.
S222: in case find conflict, then give the entry/exit conflicts information to the operator, the operator can select to ignore conflict, perhaps based on the conflict information project task solid data is adjusted, and adjusts the back and issues the project task entity to task owner and participant.
S223: if do not find conflict, the operator selects to ignore conflict even perhaps find conflict, then collaborative pond module 10 can be tied to task owner and task participant with the project task entity, thereby realizes carrying out the conversion of project task entity to the personal task entity.
Step S230 can comprise:
S231: the actual development information of the corresponding personal task of operator's online feedback.Described progress information includes but not limited to: task execution date, the actual amount of devoting oneself to work, the current completion rate of task; These information are added the personal task data module in the project management database in real time, and are handled by the personal task administration module of application server 1.
In addition, when personal task is actual when finishing, the operator can report to the personal task data module of project management database by online submission personal task, and handled by the personal task administration module of application server 1.
Below, with reference to Fig. 4 and Fig. 5, method and system of the present invention is elaborated in conjunction with an exemplary embodiment.
Present embodiment is the example according to a kind of embodiment of project management system of the present invention and method thereof, can realize development project plan and member's task cooperation.In the present embodiment, the data-storage system that uses is MySQL, and the service system that application server adopts is Tomcat, and system development platform uses JAVA.
Fig. 4 shows entity design model according to an exemplary embodiment of the present invention, comprises project scheduling entity, project task entity and personal task entity, the relevant executor of task, task progress information every day, plan template entity and plan template task entity.
Being described below of each field in the designing a model of project scheduling entity:
ID, type (varchar (36)), project scheduling entity unique ID;
Name, type (varchar (64)), project scheduling entity title;
Rate, type (int), completion rate of the plan;
WarpRate, type (int), plan deviation rate;
PlanStartDate, type (datetime), ps;
PlanEndDate, type (datetime), plan Close Date;
Status, type (varchar (2)), state.
Being described below of each field in the designing a model of project task entity and personal task entity:
ID, type (varchar (36)), task entity unique ID;
Name, type (varchar (128)), task entity title;
PlanID, type (varchar (36)), the project scheduling ID of ownership;
Status, type (varchar (2)), state;
Rate, type (int), task completion rate;
WarpRate, type (int), task deviation ratio;
OwnerID, type (varchar (36)), task owner ID;
PlanStartDate, type (datetime), ps;
PlanEndDate, type (datetime), plan Close Date;
PlanDuration, type (int), plan time;
PlanEffort, type (float), planned workload;
RealStartDate, type (datetime), actual starting date;
RealEndDate, type (datetime), physical end date;
RealDuration, type (int), actual construction time;
RealEffort, type (float), real work amount.
Being described below of each field in the designing a model of executor's information of project task entity and personal task entity:
ID, type (varchar (36)), the unique ID of executor's information;
TaskID, type (varchar (36)), corresponding task entity ID;
UserID, type (varchar (36)), executor ID;
Role, type (varchar (2)), executor's type specifically is divided into task owner and task participant.
Being described below of each field during progress information every day of project task entity and personal task entity designs a model:
ID, type (varchar (36)), every day progress information unique ID;
TaskID, type (varchar (36)), corresponding task entity ID;
ReportDay, type (datetime), task executions date;
Rate, type (int), task completion rate;
Effort, type (float), the task amount of devoting oneself to work;
CreatorID, type (varchar (36)), founder ID;
CreatedTime, type (datetime), creation-time.
Being described below of each field in the designing a model of project scheduling template entity:
ID, type (varchar (36)), project scheduling template entity unique ID;
Name, type (varchar (64)), project scheduling entity title;
Status, type (varchar (2)), state;
PlanStartDate, type (datetime), ps;
PlanEndDate, type (datetime), plan Close Date.
Being described below of each field in the designing a model of task entity in the plan template:
ID, type (varchar (36)), task entity unique ID;
Name, type (varchar (128)), task entity title;
PlanID, type (varchar (36)), the project scheduling template ID of ownership;
Owner, type (varchar (36)), task owner's title;
Participator, type (varchar (128)), task participant's List Names;
PlanStartDate, type (datetime), ps;
PlanEndDate, type (datetime), plan Close Date;
PlanDuration, type (int), plan time;
PlanEffort, type (float), planned workload.
Fig. 5 shows and realize project scheduling entity and the collaborative processing procedure of personal task entity in project management system according to the above embodiment of the present invention.
At step S1, when operator A entered project management system by client 4, application server 1 can give different identity authorities according to different operators.
If confirm the authority that this operator A has the project scheduling to create, then this operator can create the project scheduling by the inlet (as function key) of creating the project scheduling.Be provided for creating the page of the project scheduling at the client 4-1 of operator A, can supply schedule properties information such as operator's cuit plan title, plan descriptor.
Creating the project scheduling can directly finish in project management system by calling the project scheduling template entity in the data-storage system 2, the application software of PROJECT that also can be by being similar to the OFFICE of Microsoft and so on is created, and imports in the project management system then.
After new project plan success, at step S2, application server 1 provides project scheduling entity information display page.As an example, can be divided three classes the information of a project scheduling entity, be respectively: base attribute, task, authority.
Base attribute mainly comprises project scheduling title, founder, creation-time, ps, plan Close Date, actual starting date, physical end date, planned workload, real work amount, descriptor etc.
Task mainly comprises: title, and state, completion rate, deviation ratio, the person liable, modification time, the amount of devoting oneself to work, plan time, planned start time, is estimated workload etc. at the plan concluding time.
Authority information is mainly used in the operating right of flexible control different operating person at this plan, and corresponding authority operations such as increase, modification, deletion are provided.
By modes such as click task function keys, enter the plan target attribute page.Operator A (hereinafter referred to as founder A) can create new plan target entity at task property pages face, information such as the task names of the task that clarifies a plan entity, ps, plan Close Date, planned workload, person liable, participant.
At step S3, the founder A of the project scheduling can send the instruction of issue project task according to the development of projects situation.Application server 1 is sent to the part task in the release plan or whole task respectively corresponding task owner and task participant's client according to this instruction.
At step S4, carry out the task conflict inspection by the personal task administration module based on the personal task conflict rule of system definition by application server 1.For example: conflict rule can be defined as: can not bear 5 above tasks simultaneously for each person every day; Average for each person every day estimation task workload can not be above 8 hours.
At step S5, if find task conflict, the prompting that then conflicts, founder A reminds based on conflict, creating of task revised, and repeating step S1-S5
At step S6 and S7, after the task issue, the collaborative pond module 10 by application server 1 is tied to person liable and participant with the task entity.The related personnel can view my task, thus the conversion of the task of realizing a plan and personal task.When personnel revised the task entity information, application system can be upgraded data-storage system immediately.Personnel can check the project scheduling, search for corresponding plan target information from data-storage system, thereby finished item plan target entity is to the conversion of personal task entity and working in coordination with of personal task entity information and project scheduling task entity information.
The current state that the founder of the task executions people and the project scheduling can this task of real time inspection can be set, and task is operated accordingly.Any operation that everyone carries out task all can be by timely record, and can be checked by default related personnel.
At step S8, founder A enters project management system by client 4-1, can real time inspection and the project scheduling entity created in step S1 and step S2 of monitoring and the current state of progress of project task entity.
At step S9 and S10, after the task issue, when operator B entered project management system by client 4-2, its task to be processed can be searched for according to the identity information of operator B by this system, and task is presented in the personal task module of client 4-2.
Task owner and task participant can receive assignment instructions automatically, and are kept in the task list of my client.Operator B regularly in the personal task module of data-storage system feedback oneself bear the progress (information such as task execution date, task completion rate, the amount of devoting oneself to work) of task.Each feedback all can trigger collaborative pond module 10 and carry out real-time collaborative.These information can in time be checked by other staff by collaborative pond module.
At step S11 and S12, the task owner can be by collaborative pond mechanism, and each task of real time inspection participant's progress information is with the whole performance that sets the tasks.For example, this collaborative pond mechanism can be, when task participant feeds back progress, application server 1 is saved to progress information in the personal task module of data storage system automatically, when the person liable checked mission bit stream, application server 1 can be searched for all progresses of this task automatically, and showed.Setting the tasks when reaching the submission condition, the task submit operation interface that can provide to its client by the personal task administration module 12 of application server 1 submits to finishing of task to give founder A.
After submission, this task enters pending state.Two kinds of situations can be arranged: at the planning management module creation, just audit in project plan management module 11.At the personal task module creation, just audit in personal task administration module 12.Correspondingly, the project plan management module 11 of application server 1 or personal task administration module 12 can remind founder A that submitting to of task is examined automatically.Simultaneously, project task module and personal task module in 10 pairs of data storage systems 2 of collaborative pond module of application server 1 are carried out real-time collaborative, realize the coupling of personal task entity information and project scheduling task entity information.
At step S13 and S14, founder A is sent to the prompting of its client according to application server 1, and this task is examined, and whether the affirmation task reaches the standard of finishing.When definite this task has reached standard, then close this task.
Do not reach the standard of finishing if set the tasks, then the uncompleted information of this task of input in the project task module of data-storage system 2.Application server 1 sends the not information by examining of task to task leader's client, and feeds back unsanctioned reason.
The collaborative pond module 10 of application server 1 is carried out real-time collaborative according to the information of this task in the project task module of data-storage system 2, so that personal task entity information and project scheduling task entity information coupling.
From the foregoing description as can be known, by by network technology, data storage technology, search technique, entity associated technology, based on real-time collaborative and regularly collaborative two kinds of patterns and personal task conflict checking mechanism, can effectively realize the effectively collaborative of development project plan, functional department's task, research and development personal task, the information that thoroughly solves in traditional R ﹠ D project plan management is transmitted correctness untimely, that data aggregation gathers difficulty, data and is difficult to guarantee, exist a large amount of situations such as task conflict.Therefore, can improve the promptness that development project management information is transmitted, effectively reduce the cost of development project simultaneously.
The above; only for the preferable embodiment of the present invention, but protection scope of the present invention is not limited thereto, and anyly is familiar with those skilled in the art in the technical scope that the present invention discloses; the variation that can expect or replacement all should be encompassed within protection scope of the present invention.Therefore, protection scope of the present invention should be as the criterion with the protection domain of claim.

Claims (10)

1. project management system comprises:
Project management database comprises project scheduling module, project task module and personal task module;
Client is imported the data relevant with personal task in the described personal task module;
Application server is imported the data of described personal task module according to described client, upgrades the data of project scheduling module and project task module.
2. project management system according to claim 1, wherein said application server comprises:
The project plan management module, mutual with project management database, create project scheduling entity and project task entity, and manage the information and the attribute of this project scheduling entity and project task entity;
The personal task administration module, mutual with project management database and project plan management module, the information and the attribute of establishment and management personal task entity; And
Collaborative pond module, project task entity in the described project plan management module is converted to personal task entity in the described personal task administration module, the progress information of personal task entity and the progress of project task entity are worked in coordination with, and the progress information of project scheduling entity and project task entity progress information are worked in coordination with.
3. project management system according to claim 2, wherein said collaborative pond module also comprises the collision detection module, detects conflicting of plan target entity and personal task entity according to predetermined conflict rule.
4. project management system according to claim 2, wherein said personal task entity information has following corresponding relation with the project task entity information: the completion rate attribute of the corresponding project task entity of completion rate attribute of personal task entity, the real work amount attribute of the corresponding project task entity of real work amount attribute of the deviation ratio attribute of the corresponding project task entity of the deviation ratio attribute of personal task entity and personal task entity.
5. project management system according to claim 2, the progress information of the progress information of wherein said project task entity and project scheduling entity has following corresponding relation: the completion rate attribute of project scheduling entity with respect to the deviation ratio attribute that gathers mean value, project scheduling entity of the completion rate attribute of project task entity with respect to the real work amount attribute that gathers mean value, project scheduling entity of the deviation ratio attribute of project task entity the value that gathers with respect to the real work amount attribute of project task entity.
6. project management system according to claim 2, wherein said collaborative pond module comprises:
First cooperative module receives the progress information of personal task entity in real time or periodically, and the progress information of described personal task entity and project task entity is complementary; With
Second cooperative module according to the operating result of first cooperative module, is complementary the progress information of described project scheduling entity and described project task entity progress information.
7. according to each described project management system of claim 1-6, wherein said project plan management module also comprises project scheduling template entity supervisor module, is used for creating and management project plan template entity.
8. project management system according to claim 7, wherein said establishment and management project plan template entity comprise: export to external system with external system lead-in item plan template entity with the project scheduling template entity of native system.
9. project management method based on computer network is used for the project management system that is made of client that connects by computer network and application server, and described method comprises:
Create project management database, described project management database comprises project scheduling module, project task module and personal task module,
The data relevant with project task are imported in the personal task module of described project management database by described client;
Described server upgrades the data of project scheduling module and project task module according to the data relevant with project task of described client input.
10. method according to claim 9 also comprises, detects conflicting of plan target entity and personal task entity according to predetermined conflict rule.
CN200810187388A 2008-12-30 2008-12-30 R & D project plan management method and system Pending CN101770605A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810187388A CN101770605A (en) 2008-12-30 2008-12-30 R & D project plan management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810187388A CN101770605A (en) 2008-12-30 2008-12-30 R & D project plan management method and system

Publications (1)

Publication Number Publication Date
CN101770605A true CN101770605A (en) 2010-07-07

Family

ID=42503455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810187388A Pending CN101770605A (en) 2008-12-30 2008-12-30 R & D project plan management method and system

Country Status (1)

Country Link
CN (1) CN101770605A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102938103A (en) * 2012-10-19 2013-02-20 北京神舟航天软件技术有限公司 Plan information synchronizing system and method in project managing process
CN103150620A (en) * 2011-12-07 2013-06-12 徐翔 Project decomposition processing method and system
CN103413197A (en) * 2013-07-19 2013-11-27 广东电网公司佛山供电局 Method and system for monitoring electric power marketing work plan
CN103745288A (en) * 2013-08-13 2014-04-23 北京航空航天大学 Knowledge-based cooperative method of complex product development process
CN105930979A (en) * 2016-05-05 2016-09-07 扶绥供电公司 Index closed-loop control early warning platform
CN106850848A (en) * 2017-03-14 2017-06-13 广东小天才科技有限公司 Data management implementation method and data management platform based on data management platform
CN106910044A (en) * 2017-02-27 2017-06-30 努比亚技术有限公司 Project process based reminding method and system
CN107169675A (en) * 2017-06-12 2017-09-15 北京光大隆泰科技有限责任公司 Quality task creating method, apparatus and system
CN107220817A (en) * 2017-06-28 2017-09-29 天津海天云创科技服务有限公司 One kind research and development data flow management system for tracking
CN107480886A (en) * 2017-08-15 2017-12-15 上海数聚软件系统股份有限公司 Mission bit stream processing method
CN107609721A (en) * 2016-07-11 2018-01-19 上海新昇半导体科技有限公司 Project task distribution method, device, computer equipment and project management system
CN107844952A (en) * 2017-11-01 2018-03-27 江苏鸿信系统集成有限公司 A kind of project task notification management method and system
CN107943522A (en) * 2017-10-27 2018-04-20 链家网(北京)科技有限公司 A kind of project delay rate computation processing method and device
CN111435496A (en) * 2019-01-14 2020-07-21 上海汽车集团股份有限公司 Knowledge and project management method and device
CN113051152A (en) * 2021-02-20 2021-06-29 武汉木仓科技股份有限公司 Task data generation method and device and processing equipment
CN113467907A (en) * 2021-06-21 2021-10-01 北京达佳互联信息技术有限公司 Task processing method and device, electronic equipment and storage medium
CN113778032A (en) * 2021-09-03 2021-12-10 深圳市至诚峰汇科技有限公司 Production and processing industry standard system digital transformation management system platform

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103150620A (en) * 2011-12-07 2013-06-12 徐翔 Project decomposition processing method and system
CN102938103A (en) * 2012-10-19 2013-02-20 北京神舟航天软件技术有限公司 Plan information synchronizing system and method in project managing process
CN103413197A (en) * 2013-07-19 2013-11-27 广东电网公司佛山供电局 Method and system for monitoring electric power marketing work plan
CN103745288A (en) * 2013-08-13 2014-04-23 北京航空航天大学 Knowledge-based cooperative method of complex product development process
CN103745288B (en) * 2013-08-13 2016-11-09 北京航空航天大学 A kind of Knowledge based engineering Complex Product Development process synergic method
CN105930979A (en) * 2016-05-05 2016-09-07 扶绥供电公司 Index closed-loop control early warning platform
CN107609721A (en) * 2016-07-11 2018-01-19 上海新昇半导体科技有限公司 Project task distribution method, device, computer equipment and project management system
CN106910044A (en) * 2017-02-27 2017-06-30 努比亚技术有限公司 Project process based reminding method and system
CN106850848A (en) * 2017-03-14 2017-06-13 广东小天才科技有限公司 Data management implementation method and data management platform based on data management platform
CN107169675A (en) * 2017-06-12 2017-09-15 北京光大隆泰科技有限责任公司 Quality task creating method, apparatus and system
CN107220817A (en) * 2017-06-28 2017-09-29 天津海天云创科技服务有限公司 One kind research and development data flow management system for tracking
CN107480886A (en) * 2017-08-15 2017-12-15 上海数聚软件系统股份有限公司 Mission bit stream processing method
CN107943522A (en) * 2017-10-27 2018-04-20 链家网(北京)科技有限公司 A kind of project delay rate computation processing method and device
CN107844952A (en) * 2017-11-01 2018-03-27 江苏鸿信系统集成有限公司 A kind of project task notification management method and system
CN111435496A (en) * 2019-01-14 2020-07-21 上海汽车集团股份有限公司 Knowledge and project management method and device
CN111435496B (en) * 2019-01-14 2023-10-03 上海汽车集团股份有限公司 Knowledge and project management method and device
CN113051152A (en) * 2021-02-20 2021-06-29 武汉木仓科技股份有限公司 Task data generation method and device and processing equipment
CN113467907A (en) * 2021-06-21 2021-10-01 北京达佳互联信息技术有限公司 Task processing method and device, electronic equipment and storage medium
CN113778032A (en) * 2021-09-03 2021-12-10 深圳市至诚峰汇科技有限公司 Production and processing industry standard system digital transformation management system platform

Similar Documents

Publication Publication Date Title
CN101770605A (en) R & D project plan management method and system
CN106296378B (en) XBRL-based intelligent financial cloud platform system, construction method and service implementation method
CN107341643B (en) Visual process display method and system
US7236844B1 (en) Web accessible real time system and software for agile and lean manufacturing
US20220172300A1 (en) Systems and method for combined account reconciliation and variance/flux analysis
US20040015821A1 (en) System and method for interactive collaborative process management and project management
US20030187865A1 (en) Computer system for maintenance resource optimization
CN103034920A (en) System and method for controlling operations of manufacturing facility
CN111523812A (en) Model life cycle management method and system, equipment and storage medium
CN115169011A (en) Editing system and application system of airplane assembly outline
CN111523810A (en) Enterprise-level model management method, system, device and storage medium
CA2869731A1 (en) Wireless coverage infrastructure design
CN103136161A (en) On-line management method of checking and tracking of job schedule abnormalities
Randell On discrete-event simulation and integration in the manufacturing system development process
NOVIKOV et al. Improving the enterprise resource planning system based on digital modules of the industry 4.0 concept
CN111523808B (en) Model centralized management method, system, equipment and storage medium
CN115456380A (en) Intelligent manufacturing digital integrated analysis system based on enterprise
CA2814433A1 (en) System and method for interface management
CN113407161B (en) Collaborative research and development management system for complex equipment
Sun et al. A simulation‐based integrated virtual testbed for dynamic optimization in smart manufacturing systems
KR20150061165A (en) Method and system of collaboration for commercial and offshore project using workflow
Kuzmina et al. BI solutions as a tool for the management of quality of company’s project activities
CN109214659B (en) Accounting trigger device
Lin et al. Design for usability on supply chain management systems implementation
CN114862153A (en) Data processing method and device based on micro-service system, electronic equipment and medium

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20100707