CN101748893B - Method for manufacturing high-rise building balcony boards - Google Patents
Method for manufacturing high-rise building balcony boards Download PDFInfo
- Publication number
- CN101748893B CN101748893B CN 200910265821 CN200910265821A CN101748893B CN 101748893 B CN101748893 B CN 101748893B CN 200910265821 CN200910265821 CN 200910265821 CN 200910265821 A CN200910265821 A CN 200910265821A CN 101748893 B CN101748893 B CN 101748893B
- Authority
- CN
- China
- Prior art keywords
- balcony
- boards
- fence
- floor
- rise building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a method for manufacturing high-rise building balcony boards. The method comprises the steps of prefabricating a balcony rail board, casting a balcony bottom board in situ and forming the prefabricated rail board and the cast-in-situ balcony bottom board into a whole by pouring, tamping and solidifying concrete. The process has the advantages that a balcony is formed by utilizing a prefabricated glass fiber reinforced cement board as a balcony upper-part rail board, pouring and tamping concrete directly acting on the bottom of the balcony, welding anchoring reinforcing steel bars and pouring concrete so as to solidify the balcony upper-part rail board and the bottom of the balcony into a whole, thus the method ensures that no outside scaffolds need to be built during operation and construction personnel do not need to perform outdoor high-altitude operation, thereby saving cost and time for building scaffolds and decorating the outer sides of balcony boards and guaranteeing the safety of the construction personnel.
Description
Technical field
The present invention relates to a kind of preparation method of high-rise building balcony boards, be specifically related to the glass fiber-reinforced cement board of a kind of usefulness as the balcony slab exterior sheathing, after the moulding directly as the preparation method of the high-rise building balcony boards of balcony slab lateral surface free removal.
Background technology
The preparation method of traditional high-rise building balcony boards is cast-in-place, inside and outside formwork.Because high-rise balcony is cast-in-place, outside just need set up external scaffolding at it, for the dismounting of template be used in combination, this method has following 2 shortcoming: a, balcony outside to scaffold erecting, building and dismantling of its scaffold is time-consuming, the prolongation duration; B, because constructor construction relates in the aerial operation of outdoor height, security incident appears easily, cause very big threat for constructor's life security.
Summary of the invention
Main task of the present invention is to provide a kind of preparation method of high-rise building balcony boards, is specially to adopt prefabricated and cast-in-place combination, realizes the preparation method of a kind of high-rise building balcony boards of raising workman construction safety.
In order to solve above technical problem, the preparation method of a kind of high-rise building balcony boards of the present invention, its high-rise building balcony boards by on the outer ledge of balcony floor vertically fixedly balcony fence be made; It is characterized in that: described balcony fence is prefabricated glass fiber-reinforced cement board, and is reserved with the grappling reinforcing bar with the fixing side of balcony floor; Described balcony floor is cast-in-place balcony floor; When making whole high-rise building balcony boards, use earlier the concreting balcony floor, and stay its grappling reinforcing bar outside, be connected and fixed place's disturbing concrete in balcony floor of building and balcony fence then, balcony fence is vertically placed this bearing, and grappling reinforcing bar and the welding of balcony floor grappling muscle is fixing; Respectively establish the template that accompanies the edge angle steel at the inside and outside side of balcony fence, upper end and left and right sides again, with securing member balcony fence is clamped stuck disturbing concrete to bearing at the angle steel place of template and solidify.
The advantage of above technology is: utilize the glass fiber-reinforced cement board of making in advance to do balcony top breast board, act directly on the casting and compacting of concrete of balcony bottom, bottom anchor bar welding and concrete pouring and balcony, be frozen into one, form balcony, like this, need not to set up external scaffolding in operation, the constructor also need not to carry out outdoor work high above the ground, both save scaffold and balcony slab lateral surface decoration cost and time, and can also guarantee constructor's safety.
Description of drawings
Fig. 1 is the high building structure schematic diagram of Hot work in progress of the present invention;
Fig. 2 is the structural representation of the balcony of highrise building Hot work in progress of the present invention.
The specific embodiment
The construction of the balcony of highrise building as shown in Figure 1, balcony is in the high-altitude, and the balcony outside constructs if will arrive the outdoor balcony that carries out outdoor, danger coefficient is higher.The present invention is to provide a kind of preparation method that need not the high-rise building balcony boards of outdoor construction, the structure of its high-rise building balcony boards is: be fixed on the balcony floor 2 by balcony fence 1 and constitute.
In order to reach above-mentioned structure and to need not at outdoor construction, the present invention adopts following method to make, and concrete preparation method is as follows:
Through above-mentioned two steps, respectively prefabricated balcony fence 1 and cast-in-place balcony floor 2 substeps are made.Next, two parts are watered to smash be one, form whole balcony slab.Its step is as follows:
With balcony fence 1 bearing's casting and compacting of concrete, this bearing's operated by rotary motion is reserved the position of grappling muscle 4 in balcony bottom 2 on the balcony bottom 2 of moulding; Smash concrete balcony fence 1 place and vertically place balcony fence 1 watering, during placement, balcony fence 1 is reserved under the side direction of grappling reinforcing bar 3, and will reserve grappling reinforcing bar 3 and reservation grappling muscle 4 and be connected as a single entity by welding.At the same time, the upper end of balcony fence 1, the interior outside and about accompany the template 6 of upper end edge angle bar 5 respectively, angle bar 5 places in template 6 clamp with securing member 7, solidify balcony fence 1 and balcony floor 2 as a whole until the concrete of building, unload removing template 5 then and securing member 6 gets final product, the whole balcony after the moulding as shown in Figure 2.This method only needs the maintenance net to get final product, and does not need external scaffolding, and this processing step is simple, easy operating.
Claims (1)
1. the preparation method of a high-rise building balcony boards, its high-rise building balcony boards by on the outer ledge of balcony floor vertically fixedly balcony fence be made; It is characterized in that: described balcony fence is prefabricated glass fiber-reinforced cement board, and is reserved with the grappling reinforcing bar with the fixing side of balcony floor; Described balcony floor is cast-in-place balcony floor; Being made as of whole high-rise building balcony boards: use earlier the concreting balcony floor, and stay its grappling reinforcing bar outside, be connected and fixed place's disturbing concrete in balcony floor of building and balcony fence then, balcony fence is vertically placed this bearing, and grappling reinforcing bar and the welding of balcony floor grappling reinforcing bar is fixing; Respectively establish the template that accompanies the edge angle steel at the inside and outside side of balcony fence, upper end and left and right sides again, with securing member balcony fence is clamped stuck disturbing concrete to bearing at the angle steel place of template and solidify.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200910265821 CN101748893B (en) | 2009-12-28 | 2009-12-28 | Method for manufacturing high-rise building balcony boards |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200910265821 CN101748893B (en) | 2009-12-28 | 2009-12-28 | Method for manufacturing high-rise building balcony boards |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101748893A CN101748893A (en) | 2010-06-23 |
CN101748893B true CN101748893B (en) | 2011-06-22 |
Family
ID=42476459
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200910265821 Active CN101748893B (en) | 2009-12-28 | 2009-12-28 | Method for manufacturing high-rise building balcony boards |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101748893B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101892706B (en) * | 2010-07-09 | 2012-06-27 | 浙江大学 | Current building renovation external energy-saving balcony structure system |
CN102720360B (en) * | 2011-05-19 | 2015-04-01 | 陈永生 | Combination device of secondary high building supported lifted and poured cement formwork and building material lifting and lifting box |
CN107345438B (en) * | 2017-05-17 | 2019-04-09 | 西咸新区矩阵住宅工业有限公司 | It is a kind of to realize that structure turns over the construction method of the prefabricated assembled awning of eaves based on EPS insulation board |
CN109025301A (en) * | 2018-08-06 | 2018-12-18 | 武汉冶建筑安装工程有限责任公司 | It floats window side plate construction method |
CN116104213A (en) * | 2023-04-13 | 2023-05-12 | 北京建工四建工程建设有限公司 | Balcony prefabricated hanging plate system and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2414131Y (en) * | 1999-07-06 | 2001-01-10 | 马书林 | Reinforced concrete balcony |
CN2765979Y (en) * | 2005-01-27 | 2006-03-22 | 万科企业股份有限公司 | Assembled balcony |
DE102006044958A1 (en) * | 2006-09-22 | 2008-04-03 | Kki Enterprises Gmbh | Prefabricated part for an overhanging balcony slab has a restraining body designed as a prefabricated component with tie-rods and a precast concrete slab |
CN101565967A (en) * | 2008-04-25 | 2009-10-28 | 谭齐阳 | Composite heat-preservation balcony and construction method thereof |
-
2009
- 2009-12-28 CN CN 200910265821 patent/CN101748893B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2414131Y (en) * | 1999-07-06 | 2001-01-10 | 马书林 | Reinforced concrete balcony |
CN2765979Y (en) * | 2005-01-27 | 2006-03-22 | 万科企业股份有限公司 | Assembled balcony |
DE102006044958A1 (en) * | 2006-09-22 | 2008-04-03 | Kki Enterprises Gmbh | Prefabricated part for an overhanging balcony slab has a restraining body designed as a prefabricated component with tie-rods and a precast concrete slab |
CN101565967A (en) * | 2008-04-25 | 2009-10-28 | 谭齐阳 | Composite heat-preservation balcony and construction method thereof |
Non-Patent Citations (1)
Title |
---|
JP特开平8-128107A 1996.05.21 |
Also Published As
Publication number | Publication date |
---|---|
CN101748893A (en) | 2010-06-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105317137B (en) | Precast wall body, wallboard and its construction method and prefabricated panel production method | |
CN103615053B (en) | Monolithic reinforced concrete structure post empiricism engineering method | |
CN104963289B (en) | A kind of abnormity pier stud mass concrete overall time pouring construction method | |
CN108343148B (en) | A kind of frame structure system and its construction method | |
CN101748893B (en) | Method for manufacturing high-rise building balcony boards | |
CN105133755B (en) | A kind of construction method and shear wall structure of reinforcement welding rack composite shear wall | |
CN103469825A (en) | Prefabricated water-resistant post-pouring belt formwork and installation method | |
CN206267422U (en) | A kind of assembly concrete superposed column | |
CN104947846B (en) | A kind of prefabricated integral frame light filling lining and preparation method thereof | |
CN109487955A (en) | A kind of precast concrete column in-situ cast-in-place construction method | |
CN101858119A (en) | Reinforced concrete hollow floor slab and construction method | |
CN104712086B (en) | Assembled type concrete hollow composite floor slab and manufacturing method thereof | |
CN205224332U (en) | Prefabricated wall body and prefabricated wallboard | |
CN110344844A (en) | A kind of track engineering section of track well construction method | |
CN102767378B (en) | Double-column type tunnel portal method for bent frame construction tunnel | |
CN117005687A (en) | Construction method of PC (polycarbonate) component of assembled building | |
CN105804396B (en) | A kind of non-type, template system precast stair bench and construction can be had enough to meet the need | |
CN208152311U (en) | A kind of two-sided folded type steel shear wall | |
CN108301510B (en) | A kind of bean column node and its construction method | |
CN110359612A (en) | A kind of novel two-way ribs profiled steel sheet combination floor of assembled | |
CN206438766U (en) | One kind is without support beam board post poured band template system | |
CN115749043A (en) | Assembled building wallboard connected node structure | |
CN106320662B (en) | Decorating outer wall of building ultra-wide concrete wire construction method | |
CN210507768U (en) | Novel prefabricated balcony | |
CN208934250U (en) | A kind of assembled exempts to tear round beam column concrete blinding open |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |