CN101736698A - Accurate positioning method for cable-stayed bridge pylon cable guide pipe - Google Patents
Accurate positioning method for cable-stayed bridge pylon cable guide pipe Download PDFInfo
- Publication number
- CN101736698A CN101736698A CN 200910259817 CN200910259817A CN101736698A CN 101736698 A CN101736698 A CN 101736698A CN 200910259817 CN200910259817 CN 200910259817 CN 200910259817 A CN200910259817 A CN 200910259817A CN 101736698 A CN101736698 A CN 101736698A
- Authority
- CN
- China
- Prior art keywords
- guide pipe
- cable guide
- cable
- internal mold
- steel internal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200910259817 CN101736698B (en) | 2009-12-15 | 2009-12-15 | Accurate positioning method for cable-stayed bridge pylon cable guide pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200910259817 CN101736698B (en) | 2009-12-15 | 2009-12-15 | Accurate positioning method for cable-stayed bridge pylon cable guide pipe |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101736698A true CN101736698A (en) | 2010-06-16 |
CN101736698B CN101736698B (en) | 2011-05-04 |
Family
ID=42460685
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200910259817 Active CN101736698B (en) | 2009-12-15 | 2009-12-15 | Accurate positioning method for cable-stayed bridge pylon cable guide pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101736698B (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493334A (en) * | 2011-11-30 | 2012-06-13 | 上海市城市建设设计研究总院 | Bearing platform cable-stayed precast assembled column bearing platform structure and assembling and positioning process thereof |
CN103132455A (en) * | 2013-03-12 | 2013-06-05 | 中铁四局集团第二工程有限公司 | Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method |
CN103952980A (en) * | 2014-05-15 | 2014-07-30 | 中交第三公路工程局有限公司 | Installing and positioning method of main tower ropeway pipe of cable-stayed bridge |
CN104264588A (en) * | 2014-09-23 | 2015-01-07 | 中交第二航务工程局有限公司 | Cable duct locating device |
CN105113411A (en) * | 2015-08-03 | 2015-12-02 | 中铁港航局集团有限公司 | Method for mounting and rapidly and accurately positioning main tower cable guide pipe of cable-stayed bridge |
CN109208477A (en) * | 2018-10-17 | 2019-01-15 | 中铁大桥局集团第五工程有限公司 | Adjustable positioning device and application method for cable guide pipe nozzle centralized positioning |
CN106638318B (en) * | 2016-11-25 | 2019-03-15 | 中铁大桥局集团第五工程有限公司 | The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point |
CN110470287A (en) * | 2019-07-30 | 2019-11-19 | 中铁大桥局集团第五工程有限公司 | Cable-stayed bridge cable guide pipe localization method |
CN114016405A (en) * | 2021-11-26 | 2022-02-08 | 中铁二局集团有限公司 | Method for installing pylon cable guide pipe of cable-stayed bridge |
CN114960426A (en) * | 2022-04-20 | 2022-08-30 | 西安科技大学 | Steel inner die for concrete bridge tower anchoring area and construction method thereof |
CN117906466A (en) * | 2024-03-15 | 2024-04-19 | 中交第一航务工程局有限公司 | Center position retest method for anchor backing plate of embedded cable conduit at beam end of concrete cable-stayed bridge |
-
2009
- 2009-12-15 CN CN 200910259817 patent/CN101736698B/en active Active
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493334A (en) * | 2011-11-30 | 2012-06-13 | 上海市城市建设设计研究总院 | Bearing platform cable-stayed precast assembled column bearing platform structure and assembling and positioning process thereof |
CN103132455A (en) * | 2013-03-12 | 2013-06-05 | 中铁四局集团第二工程有限公司 | Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method |
CN103132455B (en) * | 2013-03-12 | 2015-06-10 | 中铁四局集团第二工程有限公司 | Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method |
CN103952980A (en) * | 2014-05-15 | 2014-07-30 | 中交第三公路工程局有限公司 | Installing and positioning method of main tower ropeway pipe of cable-stayed bridge |
CN103952980B (en) * | 2014-05-15 | 2016-06-08 | 中交第三公路工程局有限公司 | A kind of Cable stayed Bridge Main Tower cableway pipe installation and locating method |
CN104264588A (en) * | 2014-09-23 | 2015-01-07 | 中交第二航务工程局有限公司 | Cable duct locating device |
CN104264588B (en) * | 2014-09-23 | 2016-06-29 | 中交第二航务工程局有限公司 | Cable guide pipe positioner |
CN105113411A (en) * | 2015-08-03 | 2015-12-02 | 中铁港航局集团有限公司 | Method for mounting and rapidly and accurately positioning main tower cable guide pipe of cable-stayed bridge |
CN106638318B (en) * | 2016-11-25 | 2019-03-15 | 中铁大桥局集团第五工程有限公司 | The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point |
CN109208477A (en) * | 2018-10-17 | 2019-01-15 | 中铁大桥局集团第五工程有限公司 | Adjustable positioning device and application method for cable guide pipe nozzle centralized positioning |
CN109208477B (en) * | 2018-10-17 | 2023-11-28 | 中铁大桥局集团第五工程有限公司 | Adjustable positioning device for positioning center of orifice of cable duct and use method |
CN110470287A (en) * | 2019-07-30 | 2019-11-19 | 中铁大桥局集团第五工程有限公司 | Cable-stayed bridge cable guide pipe localization method |
CN110470287B (en) * | 2019-07-30 | 2021-08-10 | 中铁大桥局集团第五工程有限公司 | Cable-stayed bridge cable guide pipe positioning method |
CN114016405A (en) * | 2021-11-26 | 2022-02-08 | 中铁二局集团有限公司 | Method for installing pylon cable guide pipe of cable-stayed bridge |
CN114960426A (en) * | 2022-04-20 | 2022-08-30 | 西安科技大学 | Steel inner die for concrete bridge tower anchoring area and construction method thereof |
CN117906466A (en) * | 2024-03-15 | 2024-04-19 | 中交第一航务工程局有限公司 | Center position retest method for anchor backing plate of embedded cable conduit at beam end of concrete cable-stayed bridge |
CN117906466B (en) * | 2024-03-15 | 2024-05-24 | 中交第一航务工程局有限公司 | Center position retest method for anchor backing plate of embedded cable conduit at beam end of concrete cable-stayed bridge |
Also Published As
Publication number | Publication date |
---|---|
CN101736698B (en) | 2011-05-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101736698B (en) | Accurate positioning method for cable-stayed bridge pylon cable guide pipe | |
CN102102444B (en) | Assembling and positioning construction method of large steel casting members | |
CN201560398U (en) | Inner steel mould for accurately positioning tower column cable sleeves of cable-stayed bridge | |
CN103556836B (en) | Spherical reticulated shells assembling and construction method under restricted clearance condition | |
CN107806205B (en) | Mounting structure and mounting method of lining-free steel dome | |
CN104141318B (en) | A kind of Large-diameter Steel tubing string suspension column construction method of installation | |
AU2011253650A1 (en) | Installing method for anchor cage and installing method for industrial equipment | |
CN104074364A (en) | Steel casting funnel-shaped structure pre-assembling positioning construction method | |
CN204001428U (en) | A kind of Large-diameter Steel tubing string suspension column is installed pre-buried location structure and suspension column structure thereof | |
CN105780995A (en) | Curved surface space pipe truss structure and mounting method thereof | |
CN103088843B (en) | Pipe gallery embedded iron parts construction method of installation | |
CN107246026B (en) | Tower equipment foundation bolt embedding construction mold and embedding method thereof | |
CN105317052A (en) | Tower crane foundation bolt fixing method | |
CN114717954B (en) | Ultra-high concrete tower column construction method based on three-dimensional space coordinate positioning | |
CN209891234U (en) | Accurate positioning mechanism for embedded foundation bolt of steel pipe column concrete foundation | |
CN105648923A (en) | Stay cable saddle positioning device and positioning method thereof | |
CN110748156B (en) | Sliding positioning top supporting structure of large silo and construction method thereof | |
CN104863259A (en) | Upside-down construction method for large-span ultra-high signal-layer cylindrical architectural steel structure | |
CN115788083A (en) | Automatic quick installation correcting unit of steel column | |
CN113232447B (en) | Positioning assembly for mounting sculpture panel and mounting method of sculpture panel | |
CN205343431U (en) | Prefabricated wall body grout sleeve strip solid matter exposes accurate positioning die of reinforcing bar | |
CN112112186B (en) | Installation method of split jacket foundation on offshore converter station | |
CN210598177U (en) | Assembling jig frame for space special-shaped steel pipe truss | |
CN105064681A (en) | Installing method of steel structure foundation screw bolt | |
CN105643791A (en) | Accurate positioning die for prefabricated wall body grouting sleeve stripy closely spaced exposed steel bar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: CCCC ROAD AND BRIDGE CONSTRUCTION CO., LTD. Free format text: FORMER OWNER: ROAD + BRIDGE GROUP INTERNATIONAL CONSTRUCTION CO., LTD. Effective date: 20120718 |
|
C41 | Transfer of patent application or patent right or utility model | ||
TR01 | Transfer of patent right |
Effective date of registration: 20120718 Address after: 101100 auspicious garden 19, Beijing, Tongzhou District Co-patentee after: Road & Bridge International Co., Ltd. Patentee after: China Communications Road and Bridge North China Engineering Co., Ltd. Address before: 101100 auspicious garden 19, Beijing, Tongzhou District Co-patentee before: CRBC International Co., Ltd. Patentee before: China Communications Road and Bridge North China Engineering Co., Ltd. |