CN101709561A - Unblocked cloverleaf intersection at traffic crossroad - Google Patents

Unblocked cloverleaf intersection at traffic crossroad Download PDF

Info

Publication number
CN101709561A
CN101709561A CN200910312299A CN200910312299A CN101709561A CN 101709561 A CN101709561 A CN 101709561A CN 200910312299 A CN200910312299 A CN 200910312299A CN 200910312299 A CN200910312299 A CN 200910312299A CN 101709561 A CN101709561 A CN 101709561A
Authority
CN
China
Prior art keywords
road surface
layer
crossroad
floor
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910312299A
Other languages
Chinese (zh)
Other versions
CN101709561B (en
Inventor
郑勤民
洪峻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zheng Qinmin
Original Assignee
FUJIAN ZHONGFU CONSTRUCTION SUPERVISION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FUJIAN ZHONGFU CONSTRUCTION SUPERVISION Co Ltd filed Critical FUJIAN ZHONGFU CONSTRUCTION SUPERVISION Co Ltd
Priority to CN2009103122993A priority Critical patent/CN101709561B/en
Publication of CN101709561A publication Critical patent/CN101709561A/en
Application granted granted Critical
Publication of CN101709561B publication Critical patent/CN101709561B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to an unblocked cloverleaf intersection at a traffic crossroad. Two layers or more than two layers of roadways are built at the crossroad, wherein the first layer of pavements are distributed on the most bottom surface of the crossroads in a cross manner; the middle of a road in a straight direction is provided with a pavement A at the first layer for vehicles to go straight; are pavements A1 and A2 at the second layer are arranged at the left side and the right side of the pavement A at the first layer; the center of the crossroads is provided with a ring-shaped viaduct; a pavement B at the first layer is arranged at the most bottom layer in the vertical direction of the pavement A at first layer; the middle of the pavement B at the first layer is provided with a pavement at the third layer; pavements B1 and B2 at the second layer are arranged at the left side and the right side of the pavement at the third layer; and a curved rod communicating the pavements B1 and B2 at the second layer is arranged between the pavements B1 and B2 at the second layer. The invention enables the vehicles to run on own roads, so the condition of cross running can not happen, thereby increasing the traffic flow of the current roads and reducing and even avoiding fuel air pollution created by the vehicles due to waiting for pass.

Description

Unblocked cloverleaf intersection at traffic crossroad
Technical field:
The present invention relates to a kind of unblocked cloverleaf intersection at traffic crossroad.
Background technology:
The modern city traffic relies on traffic lights transport solution problem, the effect of traffic lights is exactly to adopt the mode of blocking up, letting out to solve the increasing magnitude of traffic flow, but this mode is when the magnitude of traffic flow acquires a certain degree, as: in the peak on and off duty time, just highlight its drawback, even the traffic police appears to coordinate to dredge, still cause the phenomenon of blocking up.China is a populous nation, and along with improving constantly of living standards of the people, car owning amount constantly increases per capita, and the phenomenon of traffic congestion is more and more serious.The traffic problems of crossroad have become traffic police department serious problems anxious to be solved.
Summary of the invention
The object of the present invention is to provide a kind ofly under the situation that does not need traffic lights, can solve crossroad access block up problem and the rational unblocked cloverleaf intersection at traffic crossroad of road design.
Technical scheme of the present invention is as follows: the road surface that two layers or more is set at the place, crossroad of road; The first floor road surface is crossing distribution bottom surface at the parting of the ways, and the road surface is the wideest; Be provided with direct lane as the motor vehicle on first floor A road surface in the middle of the road of a craspedodrome direction; On the right side on first floor A road surface is second layer A1 road surface, is the bend of turning left or turn right as the vehicle that is come by this direction running; The initiating terminal on second layer A1 road surface is positioned on the first floor A road surface, initiating terminal from second layer A road surface, center position along the crossroad, improve gradually on its road surface, the end on second layer A1 road surface is connected with the annular viaduct of center, crossroad and is on the sustained height, and peaks; The center is provided with belt viaduct at the parting of the ways.In the left side of this direct lane is second layer A2 road surface, it is the vehicle pass-through road that comes as by other three direction runnings, its structure and second layer A1 road surface are identical, and form the autos only road of the both sides that are symmetrically distributed in first floor A road surface with second layer A1 road surface; Be current bicycle or pedestrian's road on the first floor road surface in the outside on second layer A1 and A2 road surface; Two opposite side (that is: along the axis of annular viaduct, second layer A1 and A2 road surface are symmetrical distribution) that second layer A1 and A2 road surface are symmetrically distributed in the crossroad respectively along the warp or the parallel of crossroad.
The bottom on the vertical direction on first floor A road surface is first floor B road surface, first floor A road surface and first floor B road surface are positioned on the same horizontal plane, so be referred to as the first floor road surface, they locate to intersect at the parting of the ways, are provided with the 3rd layer of road surface in the middle on first floor B road surface.
The initiating terminal on the 3rd layer of road surface drops on the first floor B road surface, raise gradually on center position, its road surface along the crossroad, the annular viaduct that the end on the 3rd layer of road surface and center, crossroad are provided with connects as one and is on the sustained height, and the 3rd layer of road surface is the craspedodrome passage as the vehicle that travels in the direction.The end on the 3rd layer of road surface is the road surface peak.
Be provided with second layer B1 road surface on the right side on the 3rd layer of road surface, second layer B1 road surface is curved the travelling of turning left or turn right as the vehicle that is come by this direction running; The initiating terminal on second layer B1 road surface is positioned on the first floor B road surface, initiating terminal from second layer B1 road surface, along the center position of crossroad, improve gradually on its road surface, and the annular viaduct that the end on second layer B1 road surface and center, crossroad are provided with connects as one and is on the sustained height.The end on second layer B1 road surface is the road surface peak.
Be provided with road surface as second layer B2 in the left side on the 3rd layer of road surface, second layer B2 road surface can be used as by other three direction runnings and the vehicle pass-through road that comes, its structure and second layer B2 road surface are identical, and form the autos only road that is symmetrically distributed in both sides, the 3rd layer of B road surface with second layer B2 road surface.
Also be provided with the bend that is communicated with second layer B1 road surface and second layer B2 road surface on second layer B1 between the initiating terminal on second layer B1 and B2 road surface and annular viaduct and the B2 road surface, second layer B1 and B2 road surface be positioned at the 3rd layer about road surface both sides and be parallel to each other.Bend is positioned at the below on the 3rd layer of road surface, and the height between bend and the 3rd layer of road surface is enough to make vehicle pass-through.Two opposite side (that is: along the axis of annular viaduct, second layer B1 and B2 road surface are symmetrical distribution) that second layer B1 and B2 road surface are symmetrically distributed in the crossroad respectively along the warp or the parallel of crossroad.
The initiating terminal on second layer B road surface is than the more close crossroad of initiating terminal on the 3rd layer of road surface, is enough to make vehicle pass-through to guarantee the height between bend and the 3rd layer of road surface.
Be made as current bicycle or pedestrian's road in the outside on second layer B1 and B2 road surface.
The present invention compared with prior art can solve the traffic jam issue that travels and caused because of the intersection of vehicle in the crossroad, road design is reasonable, can guarantee respectively to take their own roads to the vehicle that travels, do not produce the situation of travelling of intersecting, thereby improved the vehicle flowrate of existing road, reduced and even avoid vehicle to pollute because of waiting as long for the current fuel-air that causes.The building construction of the present invention by adopting steelframe to combine with concrete can be that structure of the present invention is more rationally compact, and steadiness is stronger.
Description of drawings:
Fig. 1 is the plan structure schematic diagram of an embodiment of the present invention.
Fig. 2 is the A-A sectional view of Fig. 1.
Fig. 3 is the B-B sectional view of Fig. 1.
Fig. 4 is the C-C sectional view of Fig. 1.
Fig. 5 is an another kind of structural representation of the present invention.
Label declaration: the 1st, first floor A road surface, 1-1 craspedodrome passage, the 2nd, second layer A1 road surface, the 3rd, second layer A2 road surface, the 4th, annular viaduct, the 5th, first floor B road surface, the 6th, second layer B1 road surface, the 7th, second layer B2 road surface, 8 is the 3rd layer of road surface, the 9th, and bend, the 10th, isolate body of wall, the 11st, support column, the 12nd, overline bridge, the 13rd, overline bridge exit and entrance, 14 loopholes, 15 overline bridge passages, 16 through holes, 17 guardrails, the road of 18 bicycles or People's Bank of China
The specific embodiment:
Shown in Fig. 1-4, below annular viaduct 4, be provided with People's Bank of China's overpass 12, be provided with People's Bank of China's overpass exit and entrance 13 below the one or more than one road surfaces in the second layer A1, the A2 that locate near the crossroad, B1, B2 road surface.
As shown in Figure 5, passage Zhao People's Bank of China overpass 12 as bicycle or pedestrian, also can not be arranged between first floor road surface and the annular viaduct, and change the subway that is arranged under the first floor road surface into, or the other than ring type viaduct highway section on the road surface (place, non-crossroad) is provided with People's Bank of China's overpass separately.
On first floor A road surface, be provided with each two in the track that the both direction of making a return journey travels, totally four tracks; On second layer A1, A2, B1, B2 road surface, respectively be provided with two traveling lanes in the same way; On the 3rd layer of road surface, be provided with each two in the track that the both direction of making a return journey travels, totally four tracks.
On first floor A road surface 1 with the intersection on second layer A1 and A2 road surface 2,3, the position of formed difference in height is provided with and isolates body of wall 10; Segmentation is provided with support column 11 below second layer A1 and A2 road surface 2,3, with the safety that guarantees the road surface and firm, can bear vehicle current of enough weight, and the design of concrete support column can be according to the national design standard design of road and bridge.
The place that is not provided with support column 11 below second layer A1 and A2 road surface 2,3 is the hollow out place, the place of the hollow out place below second layer A1 and A2 road surface 2,3, close crossroad is provided with People's Bank of China's overpass exit and entrance 13, this passage upwards increases gradually along the crossroad direction, peak to place, crossroad (being People's Bank of China's overpass 12 places), the below of described People's Bank of China overpass is the craspedodrome passage 1-1 on first floor A road surface 1, on the bridge floor of overline bridge, be provided with loophole 14, make the craspedodrome passage 1-1 also can daylighting, increase the brightness of craspedodrome passage; It above People's Bank of China's overpass annular viaduct 4.
Described People's Bank of China overpass 12 is the microscler road surface parallel with first floor A road surface, respectively is provided with a loophole 14 at the two ends of overline bridge 12, is the overline bridge passage 15 of pedestrian or bicycle between two loopholes 14.The both sides of overline bridge passage 15 are communicated with People's Bank of China overpass exit and entrance, make pedestrian or bicycle can by overline bridge exit and entrance and overline bridge passage 15 arrive any one with sidewalk that this crossroad links to each other on.Part or all of and the overline bridge passage 15 of two loopholes is positioned at through hole 16 belows in the middle of the annular viaduct, makes overline bridge 12 very bright.Between overline bridge 12 and the annular viaduct 4 (annular viaduct) enough height are arranged, be enough to allow pedestrian, bicycle etc. pass through.
In order to ensure driving and pedestrian's safety, be provided with guardrail 17 on the interior ring edge and/or the outer annular edge edge of annular viaduct.Described annular viaduct is annular or oval ring or arc.
In order to ensure road safety, below second layer road surface, the 3rd layer of road surface and overline bridge, be equipped with support column.
Travelling of unblocked cloverleaf intersection at traffic crossroad of the present invention can be adopted following circuit: first, second as shown in the figure, third, four crossings of fourth, but the through vehicles at first crossing from first floor A road surface, pass passage traveled straight to the third crossing of overline bridge below; The curved vehicle of turning right at first crossing (is provided with two tracks) from second layer A2 road surface and goes upward to the outer side line of annular viaduct, can realize directly turning right being bent to the second crossing; The curved vehicle of turning left at first crossing goes upward to the interior side line of annular viaduct from second layer A2 road surface, and along interior side line turn right earlier curved to second layer B2 road surface, then the negotiation of bends by below, the 3rd layer of road surface to second layer B1 road surface, up and by annular viaduct, arrive third crossing, along on the normal road surface that second layer B2 road surface goes downwards to third crossing is connected at third crossing.Third crossing is identical with first crossing vehicle pass-through route.
The through vehicles at second crossing from the 3rd layer of road surface go upward to annular viaduct, walk around the driver right side annular viaduct bend, drive to the fourth crossing the 3rd layer of road surface, go downwards to normal road surface that the fourth crossing is connected on; The second crossing turn right curved vehicle from the outer side line on second layer B1 road surface be up to annular viaduct and turn right to the second layer A1 road surface at third crossing, go downwards to normal road surface that third crossing is connected on;
The second crossing turn left curved vehicle from the interior side line on second layer B1 road surface be up to annular viaduct, along the interior side line on the second layer B1 road surface annular viaduct bend that travelled, after travelling to the second layer B2 road surface at fourth crossing, along second layer B1 road surface on the negotiation of bends between second layer B1, the B2 road surface, going up the annular viaduct between fourth crossing and the first crossing again, from the normal road surface that second layer A2 road surface goes downwards to the first crossing is connected at first crossing.The fourth crossing is identical with second crossing vehicle pass-through route.

Claims (9)

1. a unblocked cloverleaf intersection at traffic crossroad is characterized in that: the road surface that two layers or more is set at the place, crossroad of road;
(1) the first floor road surface is crossing distribution bottom surface at the parting of the ways, and is the wideest on the road surface; Be provided with direct lane as the motor vehicle on first floor A road surface in the middle of the road of a craspedodrome direction;
(2) being second layer A1 road surface on the right side on first floor A road surface, is the bend of turning left or turn right as the vehicle that is come by this direction running; The initiating terminal on second layer A1 road surface is positioned on the first floor A road surface, and from the initiating terminal on second layer A1 road surface, along the center position of crossroad, improve gradually on its road surface, and the end on second layer A1 road surface is connected with the annular viaduct of center, crossroad; The center is provided with annular viaduct at the parting of the ways;
(3) be second layer A2 road surface in the left side of this direct lane, it is the vehicle pass-through road that comes as by other three direction runnings, its structure and second layer A1 road surface are identical, and form the autos only road of the both sides that are symmetrically distributed in first floor A road surface with second layer A1 road surface; Be current bicycle or pedestrian's road on the first floor road surface in the outside on second layer A1 and A2 road surface; Two opposite side that second layer A1 and A2 road surface are symmetrically distributed in the crossroad respectively along the warp or the parallel of crossroad;
(4) bottom on the vertical direction on first floor A road surface is first floor B road surface, first floor A road surface and first floor B road surface are positioned on the same horizontal plane, so be referred to as the first floor road surface, they locate to intersect at the parting of the ways, are provided with the 3rd layer of road surface in the middle on first floor B road surface;
The initiating terminal on (5) the 3rd layers of road surface drops on the first floor B road surface, improves gradually along the center position of crossroad, the 3rd layer of road surface, and the annular viaduct that the end on the 3rd layer of road surface and center, crossroad are provided with connects as one;
(6) be provided with second layer B1 road surface on the right side on the 3rd layer of road surface, second layer B1 road surface is curved the travelling of turning left or turn right as the vehicle that is come by this direction running; The initiating terminal on second layer B1 road surface is positioned on the first floor B road surface, initiating terminal from second layer B1 road surface, along the center position of crossroad, improve gradually on its road surface, and the annular viaduct that the end on second layer B1 road surface and center, crossroad are provided with connects as one; The end on second layer B1 road surface is the road surface peak;
(7) be provided with second layer B2 road surface in the left side on the 3rd layer of road surface, second layer B2 road surface can be used as by other three direction runnings and the vehicle pass-through road that comes, its structure and second layer B1 road surface are identical, and form the autos only road that is symmetrically distributed in the 3rd layer of both sides, road surface with second layer B1 road surface;
(8) also be provided with the bend that is communicated with second layer B1 road surface and second layer B2 road surface on second layer B1 between the initiating terminal on second layer B1 and B2 road surface and annular viaduct and the B2 road surface, second layer B1 and B2 road surface be positioned at the 3rd layer about road surface both sides and be parallel to each other; Bend is positioned at the below on the 3rd layer of road surface, and the height between bend and the 3rd layer of road surface is enough to make vehicle pass-through;
(9) second layer B1 and B2 road surface two opposite side that are symmetrically distributed in the crossroad respectively along the warp or the parallel of crossroad;
(10) initiating terminal on second layer B road surface is than the more close crossroad of initiating terminal on the 3rd layer of road surface;
(11) be made as current bicycle or pedestrian's road in the outside on second layer B1 and B2 road surface.
2. unblocked cloverleaf intersection at traffic crossroad according to claim 1 is characterized in that: be provided with each two in the track that the both direction of making a return journey travels on first floor A road surface, totally four tracks; On second layer A1, A2, B1, B2 road surface, respectively be provided with two traveling lanes in the same way; On the 3rd layer of road surface, be provided with each two in the track that the both direction of making a return journey travels, totally four tracks.
3. unblocked cloverleaf intersection at traffic crossroad according to claim 1 and 2, it is characterized in that: below annular viaduct, be provided with People's Bank of China's overpass, be provided with People's Bank of China's overpass exit and entrance below the one or more than one road surfaces in the second layer A1, the A2 that locate near the crossroad, B1, B2 road surface.
4. unblocked cloverleaf intersection at traffic crossroad according to claim 3 is characterized in that: be provided with the isolation body of wall in the intersection on first floor A road surface and second layer A1 and A2 road surface, the position of their formed differences in height; Segmentation is provided with support column below second layer A1 and A2 road surface.
5. unblocked cloverleaf intersection at traffic crossroad according to claim 4, it is characterized in that: the place that is not provided with support column below second layer A1 and A2 road surface is the hollow out place, the place of the hollow out place below second layer A1 and A2 road surface, close crossroad is provided with People's Bank of China's overpass exit and entrance, this passage upwards increases gradually along the crossroad direction, and the place peaks to the crossroad; The below of described People's Bank of China overpass is the craspedodrome passage on first floor A road surface; It above People's Bank of China's overpass annular viaduct.
6. unblocked cloverleaf intersection at traffic crossroad according to claim 2, it is characterized in that: described People's Bank of China overpass is the microscler road surface parallel with first floor A road surface, respectively being provided with a loophole at the two ends of overline bridge, is the overline bridge passage of pedestrian or bicycle between two loopholes; The both sides of overline bridge passage are communicated with People's Bank of China overpass exit and entrance; Part or all of and the overline bridge passage of two loopholes is positioned at the through hole below in the middle of the annular viaduct; Between overline bridge and the annular viaduct enough height are arranged, be enough to allow pedestrian, bicycle etc. pass through.
7. unblocked cloverleaf intersection at traffic crossroad according to claim 4 is characterized in that: interior ring edge and/or outer annular edge edge at annular viaduct are provided with guardrail.
8. unblocked cloverleaf intersection at traffic crossroad according to claim 4 is characterized in that: be equipped with support column below second layer road surface and the 3rd layer of road surface and overline bridge passage.
9. unblocked cloverleaf intersection at traffic crossroad according to claim 4 is characterized in that: described annular viaduct is annular or oval ring or arc.
CN2009103122993A 2009-12-25 2009-12-25 Unblocked cloverleaf intersection at traffic crossroad Expired - Fee Related CN101709561B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103122993A CN101709561B (en) 2009-12-25 2009-12-25 Unblocked cloverleaf intersection at traffic crossroad

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103122993A CN101709561B (en) 2009-12-25 2009-12-25 Unblocked cloverleaf intersection at traffic crossroad

Publications (2)

Publication Number Publication Date
CN101709561A true CN101709561A (en) 2010-05-19
CN101709561B CN101709561B (en) 2011-03-23

Family

ID=42402367

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103122993A Expired - Fee Related CN101709561B (en) 2009-12-25 2009-12-25 Unblocked cloverleaf intersection at traffic crossroad

Country Status (1)

Country Link
CN (1) CN101709561B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747658A (en) * 2012-06-26 2012-10-24 赵树峰 Trunk road L-shaped crankle and branch road connection combined barrier-free all-round transportation hub
WO2013159434A1 (en) * 2012-04-28 2013-10-31 Leung Valiant Yuk Yuen Intelligent crossroad parking multicross straight chain hub-type pendulum flyover
CN104963252A (en) * 2015-03-27 2015-10-07 张文泉 Urban multilayer roundabout viaduct
CN105178123A (en) * 2015-09-10 2015-12-23 甘肃澳华建筑规划设计有限责任公司 Cross overpass
CN112095378A (en) * 2020-10-13 2020-12-18 辽宁工程技术大学 Full-intercommunication three-dimensional traffic system without traffic lights at crossroads
CN113152183A (en) * 2021-04-13 2021-07-23 李益安 Five-fork road two-layer overpass

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013159434A1 (en) * 2012-04-28 2013-10-31 Leung Valiant Yuk Yuen Intelligent crossroad parking multicross straight chain hub-type pendulum flyover
CN102747658A (en) * 2012-06-26 2012-10-24 赵树峰 Trunk road L-shaped crankle and branch road connection combined barrier-free all-round transportation hub
CN102747658B (en) * 2012-06-26 2014-10-22 赵树峰 Trunk road L-shaped crankle and branch road connection combined barrier-free all-round transportation hub
CN104963252A (en) * 2015-03-27 2015-10-07 张文泉 Urban multilayer roundabout viaduct
CN105178123A (en) * 2015-09-10 2015-12-23 甘肃澳华建筑规划设计有限责任公司 Cross overpass
CN112095378A (en) * 2020-10-13 2020-12-18 辽宁工程技术大学 Full-intercommunication three-dimensional traffic system without traffic lights at crossroads
CN113152183A (en) * 2021-04-13 2021-07-23 李益安 Five-fork road two-layer overpass

Also Published As

Publication number Publication date
CN101709561B (en) 2011-03-23

Similar Documents

Publication Publication Date Title
CN102239296B (en) A nonstop traffic system using half (1/2) cloverleaf and traffic method applied with the same
CN102425090B (en) Urban three-dimensional road for aggregating and utilizing land and avoiding traffic jam
US20070237576A1 (en) Signal-free roadway interchange
CN101709561B (en) Unblocked cloverleaf intersection at traffic crossroad
CN102747661B (en) Based on the structure and uses thereof of the torsional mode overpass bridge in urban road
CN201245803Y (en) Crossroad overhead passage for relieving traffic congestion
WO2007112643A1 (en) A roadway structure without traffic lights for an urban non-stop quick traffic system
CN207073044U (en) Bridge tunnel composite cross crossing road
CN106192642A (en) A kind of multi-functional cross overpass
CN100494571C (en) Symmetrical viaduct
CN105155374A (en) Multifunctional cross-shaped overpass
CN101387095B (en) Full interchange crossroad
CN101338541B (en) Crossing elevated passage for relaxing traffic jam
CN102127886A (en) Multifunctional tunnel and road parking area
CN108978384A (en) A kind of ground straight trip viaduct
CN205775678U (en) A kind of multi-functional cross overpass
CN101487214A (en) Humanized multifunctional intersection for urban crossroad
CN1908304A (en) Crossroad access bridge
CN102797207A (en) Urban two-layer interchange overpass formed by crossing one-way traffic and one-way traffic
CN203451962U (en) Intersection fast-slow diverging cross road structure
CN201024365Y (en) Crossroads
CN201317903Y (en) Lane tunnel bridge at crossing
CN202194042U (en) Traffic junction utilizing lane changing way
CN101962927A (en) Combined structure of four homodromous turning L-shaped arch bridges
CN1335430A (en) Cross-shape double-layered non-cross overpass

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Free format text: FORMER OWNER: ZHENG QINMIN

Effective date: 20120112

Owner name: ZHENG QINMIN

Free format text: FORMER OWNER: FUJIAN ZHONGFU ENGINEERING CONSTRUCTION SUPERVISION CO., LTD.

Effective date: 20120112

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 350013 FUZHOU, FUJIAN PROVINCE TO: 350000 FUZHOU, FUJIAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120112

Address after: 350000, No. three, 20, Fu Yu District, Hongshan Town, Gulou District, Fujian, Fuzhou 503

Patentee after: Zheng Qinmin

Address before: 350013, Times Square, No. 89 Fu Xin Road, Fujian, Fuzhou 601

Co-patentee before: Zheng Qinmin

Patentee before: Fujian Zhongfu Construction Supervision Co., Ltd.

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110323

Termination date: 20131225