CN101707353B - 一种发电机与变压器反时限过励磁保护方法 - Google Patents
一种发电机与变压器反时限过励磁保护方法 Download PDFInfo
- Publication number
- CN101707353B CN101707353B CN 200910232180 CN200910232180A CN101707353B CN 101707353 B CN101707353 B CN 101707353B CN 200910232180 CN200910232180 CN 200910232180 CN 200910232180 A CN200910232180 A CN 200910232180A CN 101707353 B CN101707353 B CN 101707353B
- Authority
- CN
- China
- Prior art keywords
- time lag
- inverse time
- over excitation
- lag over
- transformer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Emergency Protection Circuit Devices (AREA)
- Protection Of Transformers (AREA)
Abstract
本发明公开了一种发电机变压器反时限过励磁保护方法,通过对给定的反时限过励磁动作特性曲线进行分段处理,给定的反时限过励磁动作特性曲线由输入的多组(一般为8~10组)定值得到,在根据电压和频率计算出过励磁倍数后,采用分段Lagrange多项式插值法求出过激磁保护在该励磁倍数对应的动作时间。从而实现高精度反时限过励磁保护。
Description
技术领域
本发明涉及一种发电机与变压器反时限过励磁保护方法及采用该方法的装置。
背景技术
发电机和变压器均具有一定的过励磁能力,过励磁倍数越高时允许的时间越短,即具有反时限特性,所以需采用反时限过励磁保护。发电机组反时限过励磁保护,一般通过对给定的反时限过励磁动作特性曲线进行分段处理,给定的反时限过励磁动作特性曲线由输入的多组(一般为8~10组)定值得到,如附图1所示,在根据电压计算出过励磁倍数后,采用分段线性插值法求出对应的动作时间,实现反时限。线性插值算法运算量较小,易于程序实现,但其插值误差大,影响了发电机组反时限过励磁保护的动作时间精度。
“CN200310106434.1”提出了一种基于最小二乘法拟合的变压器反时限过励磁保护方法,但其运算量大,不便于程序实现。
发明内容
本发明的目的是:采用高精度插值算法对反时限过励磁动作特性曲线进行分段处理,减少插值误差,提高发电机组过励磁保护动作时间的精度。本发明提供一种基于Lagrange多项式插值法的发电机组反时限过励磁保护方法。
本发明采取的技术方案是:发电机组与变压器反时限过励磁保护方法,通过对给定的反时限过励磁动作特性曲线进行分段处理,给定的反时限过励磁动作特性曲线由输入的m组定值(ti,ni)(i=0,1,…,m-1)得到,m一般取8~10,如图1所示,在根据电压计算出过励磁倍数后,采用分段Lagrange多项式插值法求出对应的动作时间,减少插值误差,实现高精度发电机组反时限过励磁保护。
尤其是保护装置通过检测发电机机端电压或变压器电压,计算发电机或变压器的过励磁倍数n,将当前过励磁倍数计算值与给定的m组定值(ti,ni)(i=0,1,…,m-1)比较,当判断当前过励磁倍数值n位于某两组过励磁定值nk和nk+1(k=0,1,...,m-3)之间,采用Lagrange多项式插值法,求得对应的动作时间值t(n),考虑到定值组数不多(一般8~10组),为便于程序处理,采用Lagrange二次多项式插值,插值计算式如下:
式②中:n为过励磁倍数计算值,t(n)动作时间插值结果,(tk,nk)、(tk+1,nk+1)和(tk+2,nk+2)为相邻三组定值,lk(n)、lk+1(n)和lk+2(n)为Lagrange二次多项式插值系数。
本发明的有益效果是:采用Lagrange多项式插值法对反时限过励磁动作特性曲线进行分段处理,减少插值误差,提高发电机组反时限过励磁保护动作时间精度。与以往基于线性插值的反时限过励磁保护方法相比,本发明能够更好地与设备过励磁特性曲线相匹配,反时限过励磁保护的动作时间更为精确,且运算量不大,便于程序实现。
附图说明
图1是由8组定值构成的机组反时限过励磁曲线示意图,图中n0~n7为过励磁倍数,t0~t7为与之相对应的动作时间。
具体实施方式
以下结合附图对本发明作进一步说明:在保护对象处安装TV(对于变压器,可取变压器高压侧TV或变压器低压侧TV,对于发电机,取发电机机端TV)的电压幅值计算值为U,频率计算值为f,则过励磁倍数n计算式为:
式①中,UN为TV额定电压,fN为额定频率。
将当前过励磁倍数n计算值与给定的m组定值(ti,ni)(i=0,1,…,m-1)比较,当判断过励磁倍数值n位于某两组过励磁定值nk和nk+1(k=0,1,...,m-3)之间,采用Lagrange多项式插值法,求得对应的动作时间值t(n),考虑到定值组数不多(一般8~10组),为便于程序处理,采用Lagrange二次多项式插值,插值计算式如下:
式②中:n为过励磁倍数计算值,t(n)动作时间插值结果,(tk,nk)、(tk+1,nk+1)和(tk+2,nk+2)为相邻三组定值,lk(n)、lk+1(n)和lk+2(n)为Lagrange二次多项式插值系数。
采用Lagrange多项式插值法对反时限过励磁动作特性曲线进行分段处理,减少了插值误差,提高发电机组反时限过励磁保护动作时间精度。与以往基于线性插值的反时限过励磁保护方法相比,本发明能够更好地与设备过励磁特性曲线相匹配,反时限过励磁保护的动作时间更为精确,且运算量不大,便于程序实现。
Claims (1)
1.一种发电机与变压器反时限过励磁保护方法,其特征是:通过对给定的反时限过励磁动作特性曲线进行分段处理,给定的反时限过励磁动作特性曲线由输入的多组定值得到,在根据电压和频率计算出过励磁倍数后,采用分段Lagrange多项式插值法求出过励磁保护在该励磁倍数对应的动作时间;保护装置通过检测发电机机端电压或变压器电压,计算发电机或变压器的过励磁倍数n,根据由m组定值(ti,ni)(i=0,1…,m-1)给定的反时限过励磁动作特性曲线,ni为机组过励磁倍数整定值,ti为对应ni的动作时间整定值,采用分段Lagrange多项式插值法求出对应的动作时间,实现高精度反时限过励磁保护;m组定值(ti,ni)(i=0,1…,m-1),m取8~10。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200910232180 CN101707353B (zh) | 2009-12-02 | 2009-12-02 | 一种发电机与变压器反时限过励磁保护方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200910232180 CN101707353B (zh) | 2009-12-02 | 2009-12-02 | 一种发电机与变压器反时限过励磁保护方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101707353A CN101707353A (zh) | 2010-05-12 |
CN101707353B true CN101707353B (zh) | 2012-05-23 |
Family
ID=42377555
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200910232180 Active CN101707353B (zh) | 2009-12-02 | 2009-12-02 | 一种发电机与变压器反时限过励磁保护方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101707353B (zh) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102354952B (zh) * | 2011-09-30 | 2014-05-07 | 国电南京自动化股份有限公司 | 半波积分累积式反时限过励磁保护方法 |
CN102510256B (zh) * | 2011-10-31 | 2015-08-05 | 上海电气电站设备有限公司 | 一种便捷绘制发电机特性曲线的方法 |
CN104518481A (zh) * | 2013-10-08 | 2015-04-15 | 山东迪生电气股份有限公司 | 一种提高发变组过电压保护灵敏度的方法 |
CN104124666B (zh) * | 2014-07-25 | 2017-10-20 | 苏州汇川技术有限公司 | 一种永磁同步电机的温升保护方法和系统 |
CN104614616B (zh) * | 2015-02-05 | 2017-05-03 | 华北电力科学研究院有限责任公司 | 发变组保护定值与励磁限制器定值的匹配检测方法及装置 |
CN104811024A (zh) * | 2015-04-23 | 2015-07-29 | 许继集团有限公司 | 一种换流变有载调压基准电压补偿方法 |
CN105891738B (zh) * | 2016-05-30 | 2018-09-21 | 南京国电南自电网自动化有限公司 | 用于过激磁保护的频率折算测量电路及过激磁保护方法 |
CN106501747B (zh) * | 2016-09-21 | 2019-02-22 | 国网天津市电力公司 | 一种电流互感器励磁特性试验的数据处理方法 |
CN108199350B (zh) * | 2017-11-27 | 2019-11-05 | 上海电气电站设备有限公司 | 一种发电机过激磁限制保护方法 |
CN113872154B (zh) * | 2021-09-29 | 2024-06-28 | 中广核研究院有限公司 | 发变组过励磁保护装置、方法及发变组设备 |
-
2009
- 2009-12-02 CN CN 200910232180 patent/CN101707353B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN101707353A (zh) | 2010-05-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101707353B (zh) | 一种发电机与变压器反时限过励磁保护方法 | |
CN101917006B (zh) | 电力系统频率安全性在线监视与评估方法 | |
EP2779350B1 (en) | Direct current transmission and distribution system and method of operating the same | |
CN1715946A (zh) | 电容式电压互感器暂态误差数字校正方法 | |
JP2012251817A (ja) | 絶縁劣化監視システム | |
CN105116361A (zh) | 一种基于多项式插值和幂函数分段拟合的电流互感器稳态误差计算方法 | |
CN105069545A (zh) | 一种面向电网调度操作的实时风险评估方法 | |
JP6174271B2 (ja) | 系統安定化制御装置及び方法 | |
CN101933211B (zh) | 用于运行风能装置的方法 | |
EP2490311B1 (en) | Method and apparatus for detecting earth fault | |
RU2538214C1 (ru) | Способ дифференциальной защиты электроустановки | |
CN107294135B (zh) | 一种含分布式电源接入的电网的自适应电流保护方法 | |
CN102170121B (zh) | 带修正电压互感器的消谐器 | |
CN102368674B (zh) | 一种开关磁阻电机转子位置解算方法及系统 | |
CN104267298B (zh) | 一种双绕组电力变压器的参数计算方法 | |
CN105353233A (zh) | 一种变压器在线运行能力检测方法和装置 | |
CN110320445B (zh) | 一种用于110kV及以上母线的线损异常判别方法 | |
CN104050375B (zh) | 一种提升电压互感器运行状态计量精度的优化选型方法 | |
CN108256153B (zh) | 一种基于避雷器机电暂态仿真建模方法和系统 | |
CN106371047B (zh) | 一种低功率铁芯线圈电流互感器的饱和判定方法 | |
KR20110052340A (ko) | 노심상태에 대응하는 국부과출력 정지설정치를 평가하기 위한 방법 | |
CN103995199A (zh) | 基于奇异值分解方法的配电系统中dfacts装置间交互影响度检测方法 | |
CN110729936B (zh) | 一种计及饱和特性的发电机实用参数辨识模型及其辨识方法 | |
CN104123459A (zh) | 一种基于无功损耗偏差的线路半容纳参数估计方法 | |
CN103078335A (zh) | 一种tcr型无功补偿装置模型辨识方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |