CN101672108B - Steel plate-brickwork combination stressed building component and production method thereof - Google Patents
Steel plate-brickwork combination stressed building component and production method thereof Download PDFInfo
- Publication number
- CN101672108B CN101672108B CN2009100352599A CN200910035259A CN101672108B CN 101672108 B CN101672108 B CN 101672108B CN 2009100352599 A CN2009100352599 A CN 2009100352599A CN 200910035259 A CN200910035259 A CN 200910035259A CN 101672108 B CN101672108 B CN 101672108B
- Authority
- CN
- China
- Prior art keywords
- steel plate
- masonry
- encased steel
- section
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明涉及钢板-砌体组合受力建筑构件及其生产方法,属于结构工程技术领域,其通过在既有墙体的墙面上安装板面设置有通孔的墙面外包钢板后,拆除墙面外包钢板相邻的部分既有墙体以分别形成托换梁和支承柱的砌体,然后再在砌体的断面上安装断面外包钢板,将断面外包钢板和墙面外包钢板焊接封闭以形成外包钢板壳体,最后在砌体和外包钢板壳体之间压力灌注结构胶即可形成。因此本发明采用既有墙体作为砌体,并在该既有墙体两墙面通过安装钢板进行加固,从而避免构筑过程中进行湿作业,有效地缩短施工工期;另一方面还减少现有技术中混凝土浇筑所需要的大量模板和脚手架支撑,节约施工成本;同时还避免构件截面偏大影响建筑物美观和使用。
The invention relates to a steel plate-masonry composite stress-bearing building component and a production method thereof, which belongs to the technical field of structural engineering. After installing a steel plate with through holes on the wall surface of the existing wall, the wall is removed. The adjacent part of the surface cladding steel plate has an existing wall to form the masonry of the underpinning beam and the support column, and then install the section cladding steel plate on the section of the masonry, and weld and close the section cladding steel plate and the wall cladding steel plate to form The outsourcing steel plate shell can be formed by pressure pouring structural glue between the masonry and the outsourcing steel plate shell. Therefore, the present invention adopts the existing wall as the masonry, and installs steel plates on the two walls of the existing wall for reinforcement, thereby avoiding wet work in the construction process and effectively shortening the construction period; on the other hand, reducing the existing A large number of formwork and scaffolding support required for concrete pouring in the technology saves construction costs; at the same time, it also avoids the large cross-section of components from affecting the beauty and use of buildings.
Description
技术领域 technical field
本发明涉及一种钢板-砌体组合受力建筑构件及其生产方法,应用于既有砌体承重结构房屋在进行大空间改造时,需要对承重墙进行拆除时增设的托换梁、柱,属于结构工程技术领域。The invention relates to a steel plate-masonry composite stress-bearing building component and a production method thereof, which is applied to underpinning beams and columns added when the load-bearing wall needs to be removed when the existing masonry load-bearing structure house is undergoing large-scale renovation, It belongs to the technical field of structural engineering.
背景技术 Background technique
为了满足既有砌体承重结构房屋在使用功能上的大空间需求,需要部分承重砌体(多数为砖)墙被抽除进行空间扩展,导致原来墙体承受荷载的传递路线发生变化,必须设置有效的托换梁、柱受力构件,才能确保结构的安全和正常使用。In order to meet the large space requirements of the existing masonry load-bearing structure buildings, part of the load-bearing masonry (mostly brick) walls need to be removed for space expansion, resulting in changes in the original load-bearing transmission route of the walls, which must be set Effective underpinning of beams and columns under stress can ensure the safety and normal use of the structure.
目前,关于砌体承重结构进行大空间改造的工程,传统上采用比较成熟的托换梁、柱受力构件为钢筋混凝土结构、钢与混凝土等的组合结构。一般来说,现有技术在施工工艺上比较完善且安全可靠,但是,由于存在混凝土施工部分以及不能充分考虑原有墙体参加工作,其存在如下不足之处:(1)存在混凝土施工部分,混凝土的正常养护时间需要得到保证,即使采用增加了早强等外加剂的混凝土,也需要一段时间后才能进行拆模,正常投入使用,因此,这种采用混凝土湿作业形成的托换梁、支承柱受力构件,养护时间较长,延长了施工工期;(2)新增加的梁、柱截面部分绝大多数是外包在残留砌体墙的外部,要么是在其满足一定技术要求后,嵌在墙体内部,现有技术中新增加的梁、柱不考虑残留砌体部分参与工作,同时为了满足混凝土的施工质量,新增加梁、柱的截面尺寸不能过小,直接影响建筑物美观和使用;(3)混凝土的浇筑成形需要大量的模板和脚手架支撑,增加施工成本,同时易造成施工现场拥挤、发生安全事故,极大地危及施工人员安全。At present, for large-scale transformation projects of masonry load-bearing structures, relatively mature underpinning beams and columns are traditionally used as reinforced concrete structures or composite structures of steel and concrete. Generally speaking, the existing technology is relatively complete and safe and reliable in construction technology. However, due to the existence of concrete construction parts and the inability to fully consider the original wall to participate in the work, it has the following shortcomings: (1) there is a concrete construction part, The normal curing time of concrete needs to be guaranteed. Even if the concrete with admixtures such as early strength is used, it will take a period of time before the formwork can be removed and put into use normally. Therefore, this kind of underpinning beam and support formed by concrete wet operation Column stress components, the maintenance time is longer, prolonging the construction period; (2) Most of the newly added beam and column sections are outsourced to the outside of the residual masonry wall, or are embedded after they meet certain technical requirements. Inside the wall, the newly added beams and columns in the prior art do not consider the residual masonry part to participate in the work. At the same time, in order to meet the construction quality of the concrete, the cross-sectional dimensions of the newly added beams and columns should not be too small, which directly affects the appearance and quality of the building. (3) The pouring and forming of concrete requires a large amount of templates and scaffolding support, which increases construction costs, and simultaneously easily causes congestion at the construction site, safety accidents, and greatly endangers the safety of construction personnel.
发明内容 Contents of the invention
本发明针对现有技术的不足,提供一种钢板-砌体组合受力建筑构件。其采用既有的部分墙体作为内芯,并在该既有的部分墙体的外侧安装钢板进行加固,从而避免钢板-砌体组合受力构件的构筑过程中进行湿作业,有效地缩短施工工期;同时,还减少现有技术中混凝土浇筑所需要的大量模板和脚手架支撑架,节约施工成本;此外还避免出现构件截面偏大影响建筑物美观和使用。Aiming at the deficiencies of the prior art, the present invention provides a steel plate-masonry composite stress-bearing building component. It uses the existing part of the wall as the inner core, and installs steel plates on the outside of the existing part of the wall for reinforcement, so as to avoid wet work during the construction of the steel plate-masonry composite stress member and effectively shorten the construction period. At the same time, it also reduces the large number of templates and scaffolding support frames required for concrete pouring in the prior art, saving construction costs; in addition, it also avoids the appearance and use of buildings that are affected by the large cross-section of components.
为了实现以上的技术目的,本发明采用以下的技术方案:In order to realize above technical purpose, the present invention adopts following technical scheme:
一种钢板-砌体组合受力建筑构件,包括外包钢板壳体和砌体。所述砌体用待进行大空间改造以形成托换梁、支承柱的既有墙体制作而成,所述外包钢板壳体设置于砌体的外围,且外包钢板壳体上开设有用于灌注结构胶的通孔,且外包钢板壳体和砌体之间通过紧固件以及通孔灌注结构胶连接成一体。A steel plate-masonry composite stress-bearing building component includes an outer-wrapped steel plate shell and masonry. The masonry is made of existing walls to be transformed into underpinning beams and supporting columns in a large space. The outsourcing steel plate shell is arranged on the periphery of the masonry, and the outsourcing steel plate shell is provided with holes for pouring There are through holes for structural glue, and the outsourcing steel plate shell and masonry are connected as a whole through fasteners and through holes poured with structural glue.
外包钢板壳体包括墙面外包钢板和断面外包钢板。墙面外包钢板为两块,该两墙面外包钢板相对设置于构筑成砌体的既有墙体的两墙面上,且两墙面外包钢板与置于其间的砌体通过紧固件固定连接,而断面外包钢板安装在砌体的断面上,且断面外包钢板与墙面外包钢板焊接封闭成一体。在施工过程中,应该先进行钢板焊接后灌注结构胶,不得颠倒施工顺序。The outsourcing steel plate shell includes the wall surface outsourcing steel plate and the section outsourcing steel plate. There are two outsourcing steel plates on the wall, and the two wall outsourcing steel plates are relatively arranged on the two wall surfaces of the existing wall body constructed into masonry, and the two wall outsourcing steel plates and the masonry placed in between are fixed by fasteners connected, and the cross-section outsourcing steel plate is installed on the section of the masonry, and the cross-section outsourcing steel plate and the wall surface outsourcing steel plate are welded and closed into one. During the construction process, the steel plate should be welded first and then the structural glue should be poured, and the construction sequence should not be reversed.
所述墙面外包钢板与砌体之间设置水泥砂浆层,该水泥砂浆层粘接在砌体上,且该水泥砂浆层上设置用于灌注结构胶的沟槽。同时,结构胶可沿沟槽由紧固件穿孔渗透进内部砌体。A cement mortar layer is arranged between the wall-covered steel plate and the masonry, and the cement mortar layer is bonded to the masonry, and grooves for pouring structural glue are arranged on the cement mortar layer. At the same time, the structural adhesive can permeate into the internal masonry through the fastener perforation along the groove.
所述紧固件为双头螺栓,且该双头螺栓的螺帽与螺杆之间采用焊接固定。The fastener is a stud bolt, and the nut and the screw rod of the stud bolt are fixed by welding.
根据以上的技术方案,可以实现以下的有益效果:According to the above technical scheme, the following beneficial effects can be achieved:
1.本发明所述的钢板-砌体组合受力建筑构件采用既有墙体来制作砌体,则一方面没有混凝土施工的湿作业,可以缩短施工工期,另一方面还减少现有技术中混凝土浇筑所需要的大量模板和脚手架支撑,节约施工成本,同时还避免出现构件截面偏大影响建筑物美观和使用,另外,构成托换梁、支承柱砌体的既有墙体与外包钢板壳体协同工作,充分发挥残留墙体的贡献,有效地节约了材料成本;1. The steel plate-masonry combined stressed building component of the present invention adopts the existing wall body to make the masonry, then on the one hand there is no wet operation of concrete construction, the construction period can be shortened, and on the other hand, it can reduce A large number of formwork and scaffolding support required for concrete pouring saves construction costs, and at the same time avoids the large cross-section of components affecting the appearance and use of the building. The body works together to give full play to the contribution of the residual wall, effectively saving the cost of materials;
2.本发明墙面外包钢板与置于该墙面外包钢板之间的砌体通过紧固件固定连接,且墙面外包钢板与断面外包钢板通过焊接封闭,则进一步加强外包钢板壳体与砌体之间的紧固连接,有效地提高两者之间的协同工作;2. The wall surface outsourcing steel plate of the present invention and the masonry placed between the wall surface outsourcing steel plates are fixedly connected by fasteners, and the wall surface outsourcing steel plate and the section outsourcing steel plate are closed by welding, then further strengthen the outsourcing steel plate shell and the masonry. The fast connection between the bodies can effectively improve the collaborative work between the two;
3.墙面外包钢板与砌体之间设置水泥砂浆层,该水泥砂浆层粘接在砌体上,且该水泥砂浆层上设置用于灌注结构胶的沟槽,则可以方便结构胶的灌注,有利于外包钢板壳体与砌体之间连接成一体,从而加强两者的协同工作;3. A cement mortar layer is set between the wall outsourcing steel plate and the masonry. The cement mortar layer is bonded to the masonry, and the cement mortar layer is provided with a groove for pouring structural adhesive, which can facilitate the pouring of structural adhesive , which is conducive to the connection between the outsourcing steel plate shell and the masonry, so as to strengthen the cooperative work of the two;
4.灌注结构胶可以通过水泥砂浆层的沟槽,沿着紧固件穿孔渗透到内部砌体里面,可以增强内部砌体的整体性和强度。4. The poured structural adhesive can pass through the groove of the cement mortar layer and penetrate into the internal masonry along the fastener perforation, which can enhance the integrity and strength of the internal masonry.
本发明的另一发明目的是提供一种钢板-砌体组合受力建筑构件的生产方法,涉及待进行大空间改造以形成托换梁以及支承柱的既有墙体,通过在既有墙体的墙面上安装板面设置有通孔的墙面外包钢板后安装紧固件,拆除墙面外包钢板相邻的部分既有墙体以分别形成托换梁和支承柱内的砌体,然后再在砌体的断面安装断面外包钢板,将断面外包钢板和墙面外包钢板焊接封闭以形成外包钢板壳体,最后在砌体和外包钢板壳体之间压力灌注结构胶,即可形成钢板-砌体组合受力建筑构件。Another object of the present invention is to provide a production method of a steel plate-masonry composite stress-bearing building component, which involves the existing wall to be reconstructed in a large space to form underpinning beams and support columns, through the existing wall Install the wall surface with through-hole steel plate on the wall surface and install the fasteners, remove the existing wall adjacent to the wall surface steel plate to form the underpinning beam and the masonry in the supporting column respectively, and then Then install the section outsourcing steel plate on the section of the masonry, weld and seal the section outsourcing steel plate and the wall surface outsourcing steel plate to form an outsourcing steel plate shell, and finally pressure pour structural glue between the masonry and the outsourcing steel plate shell to form a steel plate- Masonry composite stressed building components.
上述钢板-砌体组合受力建筑构件的生产方法包括以下步骤:(1)对即将用于构筑托换梁以及支承柱砌体的既有墙体两面进行粉刷层清除,接着在已清除粉刷层的既有墙体两表面分别涂抹水泥砂浆层,然后于水泥砂浆凝固前,在水泥砂浆层的表层设置用于灌注结构胶的沟槽;(2)通过紧固件将两墙面外包钢板分别固定连接在水泥砂浆层的外侧;(3)拆除支承柱相邻的部分既有墙体以获取支承柱砌体,并对断面有残缺的采用混凝土进行修补、抹平,在支承柱砌体的断面安装断面外包钢板,同时拆除托换梁底部相邻的部分既有墙体以获取托换梁砌体,断面处理同支承柱,在该托换梁砌体底部断面设置断面外包钢板,该断面外包钢板与墙面外包钢板采用焊接封闭以形成外包钢板壳体;(4)托换梁、支承柱两者节点处的外包钢板对接满焊,且在托换梁与支承柱之间安装加强肋板;(5)用压力设备通过外包钢板壳体上设置的通孔灌注结构胶,以填充水泥砂浆层与外包钢板壳体之间的间隙,以及通过紧固件穿孔填实内部砌体的间隙;(6)在外包钢板壳体表面做防锈、防火保护层。The production method of the above-mentioned steel plate-masonry composite stress-bearing building component comprises the following steps: (1) remove the plaster layer on both sides of the existing wall that will be used to construct the underpinning beam and the support column masonry, and then remove the plaster layer on the removed plaster layer. The two surfaces of the existing wall are respectively coated with cement mortar layer, and then before the cement mortar solidifies, grooves for pouring structural glue are set on the surface of the cement mortar layer; Fixedly connected to the outside of the cement mortar layer; (3) Remove the existing wall adjacent to the support column to obtain the support column masonry, and use concrete to repair and smooth the section with incomplete parts. The section is equipped with a section-wrapped steel plate, and at the same time, the existing wall adjacent to the bottom of the underpinning beam is removed to obtain the underpinning beam masonry. The section treatment is the same as that of the supporting column. The outsourcing steel plate and the wall outsourcing steel plate are welded and closed to form an outsourcing steel plate shell; (4) the outsourcing steel plate at the joints of the underpinning beam and the supporting column is fully welded, and reinforcing ribs are installed between the underpinning beam and the supporting column (5) Use pressure equipment to pour structural glue through the through holes set on the outer steel plate shell to fill the gap between the cement mortar layer and the outer steel plate shell, and to fill the gap between the internal masonry through the holes of the fasteners ; (6) Do anti-rust and fire protection layer on the surface of outsourcing steel plate shell.
所述紧固件在墙面外包钢板上采用梅花形或者矩形分布,且在托换梁跨中受压区域以及支承柱两柱端区域的紧固件间距是15t~20t,而其余位置紧固件的间距是30t~60t,t表示钢板厚度,托换梁跨中受压区域为托换梁中部受压部位,长度为托换梁跨度的三分之一,而柱端区域则指分别与柱顶和柱脚相距400mm~500mm的区域。The fasteners are distributed in a quincunx shape or a rectangle on the outer steel plate of the wall, and the distance between the fasteners in the mid-span compression area of the underpinning beam and the two column ends of the support column is 15t-20t, while the other positions are fastened The spacing between the parts is 30t~60t, t represents the thickness of the steel plate, the compression area in the middle span of the underpinning beam is the compression area in the middle of the underpinning beam, and the length is one-third of the span of the underpinning beam, and the area at the end of the column refers to the The area where the distance between the top of the column and the foot of the column is 400mm to 500mm.
根据以上的技术方案,可以实现以下的有益效果:According to the above technical scheme, the following beneficial effects can be achieved:
1.施工过程中,由于墙面外包钢板先与既有墙体紧固连接,以形成整体参与工作,然后再进行墙面外包钢板周围的既有墙体整体拆除,所以不需要支护模板和安全支撑;1. During the construction process, because the steel plate on the wall surface is fastened to the existing wall first to form a whole to participate in the work, and then the existing wall around the steel plate on the wall surface is removed as a whole, so there is no need for support formwork and safety support;
2.外包钢板壳体由于自身厚度很薄,因此,托换梁、支承柱的截面尺寸对外观影响很小;2. Due to the thin thickness of the outsourcing steel plate shell, the cross-sectional size of the underpinning beam and supporting column has little influence on the appearance;
3.由于外包钢板壳体包括焊接成一体的墙面外包钢板和断面外包钢板,且外包钢板壳体安装于砌体外围,所以可以根据需要把支撑承柱截面做成矩形、T形或L形,类似于薄壁柱形式。3. Since the outsourcing steel plate shell includes the wall outsourcing steel plate and section outsourcing steel plate welded together, and the outsourcing steel plate shell is installed on the periphery of the masonry, the cross section of the supporting column can be made into a rectangle, T shape or L shape as required , similar to a thin-walled column form.
附图说明 Description of drawings
图1是本发明所述钢板-砌体组合受力建筑构件的结构示意图;Fig. 1 is the structural representation of the steel plate-masonry composite stressed building component of the present invention;
图2是图1中的A-A视图;Fig. 2 is A-A view among Fig. 1;
图3是图1中B-B视图;Fig. 3 is B-B view among Fig. 1;
图4是本发明所述钢板-砌体组合受力建筑构件的构筑流程图;Fig. 4 is the construction flowchart of the steel plate-masonry composite stressed building component of the present invention;
其中,支承柱1 柱端区域11 托换梁2 跨中受压区域21 双头螺栓3 混凝土修补层4 断面外包钢板51 墙面外包钢板52 通孔53 水泥砂浆层6 砌体7 加强肋板8。Among them,
具体实施方式 Detailed ways
以下将结合附图详细地说明本发明的技术方案。The technical solutions of the present invention will be described in detail below in conjunction with the accompanying drawings.
如图1至3所示,本发明所述的钢板-砌体组合受力建筑构件,包括外包钢板壳体和砌体7,所述砌体7用待进行大空间改造以形成托换梁2或者支承柱1的既有墙体制作而成,所述外包钢板壳体设置于砌体7的外围,且外包钢板壳体上开设有用于灌注结构胶的通孔53,且外包钢板壳体和砌体7之间通过紧固件以及通孔53灌注的结构胶连接成一体。As shown in Figures 1 to 3, the steel plate-masonry composite stress-bearing building member according to the present invention includes an outsourcing steel plate shell and a
外包钢板壳体包括墙面外包钢板52和断面外包钢板51,墙面外包钢板52为两块,该两墙面外包钢板52相对设置于构筑成砌体7的既有墙体的两墙面上,且两墙面外包钢板52与置于其间的砌体7通过紧固件固定连接,所述紧固件为双头螺栓3,且该双头螺栓3的螺帽与螺杆之间采用焊接固定,从而可以有效地防止螺帽的脱落,而断面外包钢板51安装在砌体7的断面上,且断面外包钢板51与墙面外包钢板52焊接封闭成一体。The outsourcing steel plate shell includes a wall surface
所述墙面外包钢板52与砌体7之间设置水泥砂浆层6,该水泥砂浆层6粘接在砌体7上,且水泥砂浆层6上设置用于灌注结构胶的沟槽,另外,断面外包钢板51与拆除部分既有墙体所留下的墙体断面之间设置有混凝土修补层,以将墙体断面修补平整。A
如图4所示,本发明所述钢板-砌体组合受力建筑构件的生产方法,涉及待进行大空间改造以形成托换梁2以及支承柱1的既有墙体,通过在既有墙体的墙面上安装板面设置有通孔53的墙面外包钢板52后安装紧固件,拆除墙面外包钢板52相邻的部分既有墙体以分别形成托换梁2和支承柱1内的砌体7,然后再在砌体7的断面安置断面外包钢板51,并将断面外包钢板51和墙面外包钢板52焊接封闭以形成外包钢板壳体,最后在砌体7和外包钢板壳体之间压力灌注结构胶,即可形成钢板-砌体7组合受力建筑构件。As shown in Fig. 4, the production method of the steel plate-masonry composite stressed building member according to the present invention involves the existing wall body to be transformed into a large space to form the
上述钢板-砌体7组合受力建筑构件的生产方法包括以下步骤:(1)根据托换梁2、支承柱1的截面尺寸,将需要的墙面外包钢板52、断面外包钢板51和双头螺栓3准备好;(2)对需要用于构筑托换梁2以及支承柱1砌体7的既有墙体两面进行粉刷层清除,接着在已清除粉刷层的既有墙体两表面分别涂抹水泥砂浆层6,然后于水泥砂浆凝固前,在水泥砂浆层6的表层设置用于灌注结构胶的沟槽,且沟槽为正交斜向沟槽;(3)通过紧固件将两墙面外包钢板52分别固定连接在水泥砂浆层6的外侧,本发明采取对拉螺栓将置于墙面两侧的墙面外包钢板52拧紧固定,且用电焊焊死螺帽防止松动,考虑到托换梁2跨中受压区域以及支承柱1的柱端更容易因局部压曲失稳而受到破环,则紧固件在墙面外包钢板52上采用梅花形或者矩形分布,且在托换梁2跨中受压区域以及支承柱1两柱端区域的紧固件间距是15t~20t,而其余位置紧固件的间距是30t~60t,t表示钢板厚度,托换梁2跨中受压区域为托换梁2中部受压部位,长度为托换梁2跨度的三分之一,而柱端区域则指分别与柱顶和柱脚相距400mm~500mm的区域;(4)拆除支承柱1相邻的部分既有墙体以获取支承柱1砌体7,并于支承柱1砌体7的断面安装断面外包钢板51,该断面外包钢板51与墙面外包钢板52之间采用焊接封闭以形成外包钢板壳体,另外,拆除支承柱1相邻的部分既有墙体时,为保持断面的平整,本发明在断面上涂抹混凝土修补层,以方便断面外包钢板51与砌体7断面之间的有效连接,而且还节约结构胶的用量;拆除托换梁2底部相邻的既有墙体以获取托换梁2砌体7,断面处理同支承柱1,并在该托换梁2砌体7底部断面设置断面外包钢板51,同样将断面外包钢板51与墙面外包钢板52之间采用焊接封闭以形成外包钢板壳体;(5)托换梁2、支承柱1两者节点处的外包钢板对接满焊,且在托换梁2与支承柱1之间安装加强肋板8;(6)用压力设备通过外包钢板壳体上设置的通孔53灌注结构胶,以填充砌体7与外包钢板壳体之间的间隙,以及沿紧固件穿孔渗透填实内部砌体7的间隙;(7)在外包钢板壳体表面做防锈、防火保护层。The production method of the above-mentioned steel plate-
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009100352599A CN101672108B (en) | 2009-09-27 | 2009-09-27 | Steel plate-brickwork combination stressed building component and production method thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009100352599A CN101672108B (en) | 2009-09-27 | 2009-09-27 | Steel plate-brickwork combination stressed building component and production method thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101672108A CN101672108A (en) | 2010-03-17 |
| CN101672108B true CN101672108B (en) | 2012-08-15 |
Family
ID=42019493
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2009100352599A Expired - Fee Related CN101672108B (en) | 2009-09-27 | 2009-09-27 | Steel plate-brickwork combination stressed building component and production method thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101672108B (en) |
Families Citing this family (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101818578B (en) * | 2010-03-26 | 2012-02-01 | 建研科技股份有限公司 | Disaster prevention and reinforcement method for brick house |
| CN101906882B (en) * | 2010-07-06 | 2011-12-07 | 华南理工大学 | Method for carrying out earthquake-resistance and strengthening on traditional masonry structure by using steel parts |
| CN102003080B (en) * | 2010-11-24 | 2012-08-29 | 北京市建筑设计研究院 | Anti-seismic reinforcing structure and method of old brickwork building |
| CN102661010B (en) * | 2012-05-16 | 2014-05-07 | 东南大学 | Composite shear wall |
| CN102704703A (en) * | 2012-05-30 | 2012-10-03 | 东南大学 | Method for underpinning large-space wall by using pre-stressed carbon fiber composite cable |
| CN104847130B (en) * | 2015-05-19 | 2017-04-05 | 江苏南通三建集团有限公司 | A kind of ruggedized construction and its construction method of existing structure beam |
| CN108360838B (en) * | 2018-03-16 | 2023-07-25 | 湖南科技学院 | Steel-concrete support bracket and construction method thereof |
| CN109812047A (en) * | 2019-03-26 | 2019-05-28 | 中建四局第一建筑工程有限公司 | One kind is to pull-type steel plate shear force wall strengthening construction structure and method |
| CN110748193A (en) * | 2019-10-22 | 2020-02-04 | 武汉华科永信建筑工程有限公司 | Construction process for chiseling bearing wall |
| CN114045952B (en) * | 2021-11-15 | 2023-11-10 | 上海方寻减振科技有限公司 | Reinforced masonry buttress for damper and application |
| CN117418718A (en) * | 2023-11-21 | 2024-01-19 | 湖北省建筑科学研究设计院股份有限公司 | A construction method for large space renovation of brick-concrete structure houses |
-
2009
- 2009-09-27 CN CN2009100352599A patent/CN101672108B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN101672108A (en) | 2010-03-17 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101672108B (en) | Steel plate-brickwork combination stressed building component and production method thereof | |
| CN105484142B (en) | A kind of pin-connected panel precast segment concrete hollow slab beam structure and preparation method thereof | |
| CN204435673U (en) | Integrated frame column template structure | |
| CN107401217B (en) | A kind of beamless hollow floor-chamber concrete-filled steel tube shear wall combined structure system and method | |
| CN110847050B (en) | Large-span prefabricated corrugated steel web composite beam top and bottom plate synchronous pouring template and application method thereof | |
| CN108060747A (en) | A kind of construction and production method of New Thin-walled steel core concrete column with ribbing | |
| CN102182303A (en) | Oblique annular closed structural template supporting method | |
| CN104453270B (en) | The bracing means of a kind of deformed bar concrete component and construction method | |
| CN104153463B (en) | Assembled integrated frame system and construction method thereof | |
| CN210976588U (en) | Template reinforcing system for double shear walls at deformation joint | |
| CN104797762B (en) | Building and construction method thereof | |
| CN115419166A (en) | Support-free connecting joint for prefabricated beam column of assembled concrete frame structure and construction method | |
| CN108643382A (en) | The construction method that fabricated shear wall plate vertically connects | |
| CN220724829U (en) | Double-sided overlapped assembled bridge pier suitable for construction of high and cold and earthquake active areas | |
| CN203625776U (en) | Arch spring anchoring structure for concrete-filled steel tube arch bridge | |
| CN109112967B (en) | Tower beam thrust connection device and quick construction method for self-anchored suspension bridge | |
| CN104453235A (en) | Convertor station firewall construction technology | |
| CN116876832A (en) | A construction method for super high-rise building elevator shaft masonry combined with steel structural columns | |
| CN110685404A (en) | Construction method of prefabricated combined structure constructional column | |
| CN212336412U (en) | An assembled wall connection structure | |
| CN104032862A (en) | Assembly-type steel beam joint L-shaped mixed coupled wall and construction method thereof | |
| CN211597390U (en) | Reinforcement connection structure of vertical reinforcement in prefabricated shear wall | |
| CN108930406A (en) | Construction method for large-formwork narrow-space wall based on integral assembly | |
| CN211949113U (en) | A prefabricated floor slab splicing structure | |
| WO2023123319A1 (en) | Fabricated shear wall |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120815 Termination date: 20150927 |
|
| EXPY | Termination of patent right or utility model |
