CN103194982B - Construction method for short cantilever support at bridge side span cast-in-situ segment - Google Patents

Construction method for short cantilever support at bridge side span cast-in-situ segment Download PDF

Info

Publication number
CN103194982B
CN103194982B CN201310096357.XA CN201310096357A CN103194982B CN 103194982 B CN103194982 B CN 103194982B CN 201310096357 A CN201310096357 A CN 201310096357A CN 103194982 B CN103194982 B CN 103194982B
Authority
CN
China
Prior art keywords
cantilever support
short cantilever
cast
situ segment
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310096357.XA
Other languages
Chinese (zh)
Other versions
CN103194982A (en
Inventor
李勇
钱江
王俊伟
彭园
侯兆隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
China Communications Road and Bridge North China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, China Communications Road and Bridge North China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201310096357.XA priority Critical patent/CN103194982B/en
Publication of CN103194982A publication Critical patent/CN103194982A/en
Application granted granted Critical
Publication of CN103194982B publication Critical patent/CN103194982B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a construction method for a short cantilever support at the bridge side span cast-in-situ segment. Two rows of steel plates are embedded on two sides of a cast-in-situ segment box girder of a pier top plane along the bridge direction, the short cantilever support is fabricated in advance and comprises a cross steel beam, longitudinal steel beams perpendicular to the cross steel beam are welded at two ends of the cross steel beam respectively, and diagonal bars are welded between the cross steel beam and the longitudinal steel beams; the longitudinal steel beams of the short cantilever support are welded on an embedded steel plate at the pier top; the cross steel beam of the short cantilever support is suspended outside the pier top plane; rows of bricks are laid on the pier top plane in the horizontal bridge direction at intervals of 70cm; square timbers spanning the bricks are laid on the top surfaces of the bricks in the longitudinal bridge direction at intervals of 70cm; and the short cantilever support, the bricks and the square timbers form a cast-in-situ segment template support system on which follow-up processes of side span cast-in-situ segment construction are performed through the conventional method.

Description

Construction method for short cantilever support at bridge side span cast-in-situ segment
Technical field
The present invention relates to a kind of bridge side span cast-in-situ section construction method, be applied to large-span continuous girder bridges end bay Cast-in-Situ Segment section construction field.
Background technology
Along with the development of bridge Construction Technology, large-span continuous beam Reinforced Concrete Bridge is used widely, and its end bay cast-in-place section construction affects construction quality and the programming of bed rearrangement bridge.At present, end bay cast-in-place section construction method mostly adopts full framing or shelf bracket construction, in work progress, will first set up full framing or shelf bracket, then carry out the operations such as pier top installation form, reinforcing bar binding, prestress pipe installation, concreting.Existing construction method, support or bracket to set up cost relatively high, man-hour is longer, not quick detachable, affects the duration of whole bridge.
Summary of the invention
The object of the invention is to, improve the support in the construction of current bridge side span cast-in-situ section or the structure of bracket, provide a kind of construction method for short cantilever support at bridge side span cast-in-situ segment to reduce costs, the reduction of erection time.
Technical scheme of the present invention is as follows:
A kind of construction method for short cantilever support at bridge side span cast-in-situ segment, is characterized in that:
(1) in the both sides of pier top plane Cast-in-Situ Segment case beam, along bridge to pre-buried two row's steel plates, described pre-embedded steel slab is fixed by dowel and pier top reinforcement welding;
(2) make a kind of short cantilever support in advance, described short cantilever support comprises a gooseneck, at the two ends of described gooseneck, welds a steel longeron vertical with described gooseneck respectively, between described gooseneck and steel longeron, is welded with hound;
(3) utilize tower crane that described short cantilever support entirety is winched to Dun Ding, and by the steel longitudinal beam welding of short cantilever support on the pre-embedded steel slab of Dun Ding; The gooseneck of short cantilever support is suspended from outside the plane of pier top;
(4), in the plane of pier top, between two steel longerons of short cantilever support, direction across bridge lays a row and parallel the laying bricks of short cantilever support gooseneck every 70cm; At described end face of laying bricks, vertical bridge is to laying one every 40cm across the described lumps of wood of laying bricks; Described short cantilever support, to lay bricks and the lumps of wood forms Cast-in-Situ Segment formwork bracing system jointly;
(5) on described Cast-in-Situ Segment formwork bracing system, carry out the subsequent handling of end bay cast-in-place section construction according to a conventional method, comprise the installation of template construction, reinforcing bar binding and prestress pipe, pouring concrete.
Short cantilevered support structure of the present invention is simple, and cost is low, quick for installation, is applied to the construction of end bay Cast-in-Situ Segment, can shorten the construction period to a great extent, increase economic efficiency, and can guarantee that quality control on construction meets the requirement of associated specifications.
Accompanying drawing explanation
Fig. 1 is the arrangement figure of pier top pre-embedded steel slab
Fig. 2 is the structural representation of short cantilever support that the present invention designs and adopts
Fig. 3 is the view after short cantilever support is arranged on Dun Ding
Fig. 4 is the arrangement schematic diagram of laying bricks
Fig. 5 display be the arrangement schematic diagram of the lumps of wood
Fig. 6 is the Cast-in-Situ Segment structural representation after installation form
Detailed description of the invention
Below by way of a specific embodiment, method of the present invention is described in detail.The present embodiment is used for explaining and non-limiting method of the present invention.
Certain two-wire grand bridge structure of main bridge is single box single chamber And of Varying Depth box girder with variable cross section, and curve parameter at the bottom of beam Duan Liang is second-degree parabola, and box section height, by the 5.25m of span centre, is gradient to the 9m of beam root.Case beam establishes the horizontal wall inscription of 2%, the wide 11.56m of case back, bottom width 7m.The cast-in-place segment length 3.75m of end bay, adopts C55 concreting, and about 99.3m measures in total side 3.
End bay Cast-in-Situ Segment adopts method of the present invention, and work progress is as follows:
As shown in Figure 1, in the both sides of pier top 1 Cast-in-Situ Segment case beam, along bridge to pre-buried two row's steel plates 2.In the present embodiment, the steel plate of pre-buried employing 60 × 30cm, the arrangement of steel plate puts 6 pieces for often arranging, and the arrangement pitch of adjacent pre-embedded steel slab is 55cm.Pre-embedded steel slab is fixed by dowel and pier top reinforcement welding.
At the processing space short cantilever support of processing and fabricating in advance, the structure of short cantilever support as shown in Figure 2, comprises a gooseneck 3, at the two ends of described gooseneck 3, weld a steel longeron 4 vertical with described gooseneck respectively, between described gooseneck and steel longeron, be welded with hound 5.
As a kind of embodiment, described gooseneck comprises two i iron arranged side by side, is welded to connect between two i iron arranged side by side by least 3 pieces of junction steel plates 6.Steel longeron described in every root, is made up of two i iron arranged side by side.
In the present embodiment, the gooseneck of short cantilever support adopts the i iron I45a of 2 10.5m, and every root steel longeron adopts 2 length to be the i iron I45a of 3.7m, and two hounds adopt the i iron I28a of 2.6m.
Short cantilever support adds man-hour, and first 2 2I45a section longitudinal beams are welded on gooseneck two ends by design attitude, joint is welded with stiffener, then at the steel longeron I28a long with welding 2.6m between gooseneck as hound, to strengthen the stability of bracket; Again between two i iron of composition gooseneck, be welded with the junction steel plate 6 of 20 × 20cm.After above-mentioned parts are welded into an entirety, namely short cantilever support machines.
After short cantilever support completes, utilize tower crane whole to lift to on-the-spot Dun Ding, and be welded on the pre-embedded steel slab 2 of Dun Ding by the steel longeron 4 of short cantilever support by design attitude, the gooseneck 3 of short cantilever support is suspended from outside the plane of pier top, as shown in Figure 3.
As shown in Figure 4 and Figure 5, in the plane of pier top, between two steel longerons 4 of short cantilever support, direction across bridge lays every 70cm that a row is parallel with gooseneck 3 lays bricks 7, and laying bricks 7 is highly 60cm; Lay bricks 7 end face, vertical bridge to lay every 40cm one across described lay bricks 7 the lumps of wood 8.In the present embodiment, the specification of the lumps of wood 8 is 10 × 10cm.Every root lumps of wood 8 at least lays bricks 7 across two rows.
Described short cantilever support, to lay bricks and the lumps of wood forms Cast-in-Situ Segment formwork bracing system.
On Cast-in-Situ Segment formwork bracing system, carry out the subsequent handling of the end bay cast-in-place section constructions such as the installation of template construction, reinforcing bar binding and prestress pipe, pouring concrete according to a conventional method successively.Described conventional method, as the construction methods such as full framing conventional at present or shelf bracket the installation of template construction, reinforcing bar binding and prestress pipe, the pouring concrete that adopt similar, belong to prior art, do not describe in detail at this, be only summarized as follows:
1, template construction
(1) bed die
Bed die is arranged on Cast-in-Situ Segment formwork bracing system.End bay Cast-in-Situ Segment bed die adopts bamboo slab rubber to add 10 × 10cm lumps of wood back cord and manufactures big-size formwork, and at processing space concentrated processing, tower crane lifting is installed to scene.
(2) internal mold
Internal mold adopts light weight steel frame, and δ=20mm bamboo glue pattern plate makes panel, establishes support in case, steel pipe scaffold spacing 0.6m*0.6m, and step pitch is 1.2m.
(3) external mold
Outer side mold adopts the set shaped steel formwork of 6mm steel facing+8cm channel-section steel back cord+10cm channel-section steel truss, and at processing space concentrated processing, tower crane lifting is installed to scene.
(4) mould is held
Adopt steel form, end mould has reinforcing bar and prestress pipe to stretch out, and status requirement is accurate.
Figure 6 shows that the Cast-in-Situ Segment structural representation after template 9 installation.
2, the installation of reinforcing bar binding and prestress pipe:
(1) colligation of reinforcing bar
Beam body reinforcing bar overall binding in template, first carries out base plate and web reinforcement colligation, then installs internal mold, after internal mold is debugged, carries out the colligation of roof steel bar.
(2) installation of prestress pipe
The prestressing force of end bay Cast-in-Situ Segment comprises longitudinal and transverse, perpendicular three dimension prestressing pipeline, the installation that the installation of pipeline should be applicable in reinforcing bar binding installation process.
3, pouring concrete:
End bay Cast-in-Situ Segment beam body adopts primary concreting, and about 99.3m measures in total side 3.Web concrete is built by horizontal slice, and lift height is no more than 30cm.
4, concrete curing and dabbing:
Form removal when concrete strength reaches design strength more than 50%; After beam section end side form is removed, artificial dabbing concrete surface in time, ensures that exposed parts is fresh coarse aggregate, is beneficial to next sections concrete better bonding.

Claims (6)

1. a construction method for short cantilever support at bridge side span cast-in-situ segment, is characterized in that:
(1) in the both sides of pier top plane Cast-in-Situ Segment case beam, along bridge to pre-buried two row's steel plates, described pre-embedded steel slab is fixed by dowel and pier top reinforcement welding;
(2) make a kind of short cantilever support in advance, described short cantilever support comprises a gooseneck, at the two ends of described gooseneck, welds a steel longeron vertical with described gooseneck respectively, between described gooseneck and steel longeron, is welded with hound;
(3) utilize tower crane that described short cantilever support entirety is winched to Dun Ding, and by the steel longitudinal beam welding of short cantilever support on the pre-embedded steel slab of Dun Ding; The gooseneck of short cantilever support is suspended from outside the plane of pier top;
(4), in the plane of pier top, between two steel longerons of short cantilever support, direction across bridge lays a row and parallel the laying bricks of short cantilever support gooseneck every 70cm; At described end face of laying bricks, vertical bridge is to laying one every 40cm across the described lumps of wood of laying bricks; Described short cantilever support, to lay bricks and the lumps of wood forms Cast-in-Situ Segment formwork bracing system;
(5) on described Cast-in-Situ Segment formwork bracing system, carry out the subsequent handling of end bay cast-in-place section construction according to a conventional method, comprise the installation of template construction, reinforcing bar binding and prestress pipe, pouring concrete.
2. construction method for short cantilever support at bridge side span cast-in-situ segment according to claim 1, is characterized in that: described pre-embedded steel slab adopts the steel plate of 60 × 30cm, and often arrangement puts 6 pieces, and adjacent two block plate spacing are 55cm.
3. construction method for short cantilever support at bridge side span cast-in-situ segment according to claim 1, is characterized in that: described gooseneck comprises two i iron arranged side by side, is welded to connect between described two i iron arranged side by side by least 3 pieces of junction steel plates; Steel longeron described in every root, is made up of two i iron arranged side by side.
4. construction method for short cantilever support at bridge side span cast-in-situ segment according to claim 1, is characterized in that: the height of often laying bricks described in row is 60cm.
5. construction method for short cantilever support at bridge side span cast-in-situ segment according to claim 1, is characterized in that: described in every root, the lumps of wood is at least laid bricks across two rows.
6. construction method for short cantilever support at bridge side span cast-in-situ segment according to claim 1, is characterized in that: described lumps of wood specification is 10 × 10cm..
CN201310096357.XA 2013-03-25 2013-03-25 Construction method for short cantilever support at bridge side span cast-in-situ segment Active CN103194982B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310096357.XA CN103194982B (en) 2013-03-25 2013-03-25 Construction method for short cantilever support at bridge side span cast-in-situ segment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310096357.XA CN103194982B (en) 2013-03-25 2013-03-25 Construction method for short cantilever support at bridge side span cast-in-situ segment

Publications (2)

Publication Number Publication Date
CN103194982A CN103194982A (en) 2013-07-10
CN103194982B true CN103194982B (en) 2015-02-25

Family

ID=48717788

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310096357.XA Active CN103194982B (en) 2013-03-25 2013-03-25 Construction method for short cantilever support at bridge side span cast-in-situ segment

Country Status (1)

Country Link
CN (1) CN103194982B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669138B (en) * 2014-01-04 2015-07-01 邹中宝 Extrusion rod device for high-pressure hole extruder
CN106087777B (en) * 2016-08-03 2017-10-31 杭州江润科技有限公司 The construction method of high pier long cantilever Cast-in-place Bent Cap combined type formwork system
CN108755448B (en) * 2018-08-16 2023-06-23 中铁四局集团有限公司 Tool and method for positioning, installing and dismantling large-span continuous rigid frame suspension irrigation end template
CN110565526A (en) * 2019-07-29 2019-12-13 南昌大学 Conveniently-disassembled side-span cast-in-place support suitable for bridge and construction method
CN111058381A (en) * 2019-11-25 2020-04-24 中建四局贵州投资建设有限公司 Construction method for side-span cast-in-place section of continuous rigid frame bridge
CN115323917B (en) * 2022-03-07 2024-06-04 陕西西建路桥工程有限公司 Construction method of bridge side span cast-in-situ section short cantilever bracket

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2632922B2 (en) * 1988-05-16 1997-07-23 大成建設株式会社 Bridge construction method
JP2008240410A (en) * 2007-03-28 2008-10-09 Kawasaki Heavy Ind Ltd Bridge construction method, steel structure, and bridge
CN101469534A (en) * 2007-12-28 2009-07-01 上海市基础工程公司 Pier top load bearing bracket construction technique
CN201567533U (en) * 2009-09-28 2010-09-01 中交二公局第六工程有限公司 Assembly and disassembly-type bracket for cast-in-place of continuous beam
CN202247687U (en) * 2011-09-19 2012-05-30 曹新恒 Universal cast-in-situ trestle for bridge
CN102535339A (en) * 2011-12-07 2012-07-04 中铁十九局集团第七工程有限公司 Bracket of thin-wall hollow high-pier cantilever pouring continuous beam and construction method thereof
CN102691266A (en) * 2012-06-03 2012-09-26 中交第四公路工程局有限公司 Construction method for ultrahigh combined support for bridge side span cast-in-situ section

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2632922B2 (en) * 1988-05-16 1997-07-23 大成建設株式会社 Bridge construction method
JP2008240410A (en) * 2007-03-28 2008-10-09 Kawasaki Heavy Ind Ltd Bridge construction method, steel structure, and bridge
CN101469534A (en) * 2007-12-28 2009-07-01 上海市基础工程公司 Pier top load bearing bracket construction technique
CN201567533U (en) * 2009-09-28 2010-09-01 中交二公局第六工程有限公司 Assembly and disassembly-type bracket for cast-in-place of continuous beam
CN202247687U (en) * 2011-09-19 2012-05-30 曹新恒 Universal cast-in-situ trestle for bridge
CN102535339A (en) * 2011-12-07 2012-07-04 中铁十九局集团第七工程有限公司 Bracket of thin-wall hollow high-pier cantilever pouring continuous beam and construction method thereof
CN102691266A (en) * 2012-06-03 2012-09-26 中交第四公路工程局有限公司 Construction method for ultrahigh combined support for bridge side span cast-in-situ section

Also Published As

Publication number Publication date
CN103194982A (en) 2013-07-10

Similar Documents

Publication Publication Date Title
CN103194982B (en) Construction method for short cantilever support at bridge side span cast-in-situ segment
CN203188121U (en) Cast-in-place bridge floor suspending mold of half-through or through arch bridge
CN102505708B (en) Construction method of tunnel at oversized cross section open cut area in track traffic
CN206053131U (en) Precast floor slab steel reinforcement cage component and floor
CN110700105B (en) Synchronous construction method for high pier column and tie beam and template used in same
CN102605717A (en) Pier-top longitudinal support scaffolding method
CN104060761A (en) U-shaped steel-concrete composite section beam and construction method of section beam
CN102146658A (en) Locally uncombined suspension bridge steel-concrete combined bridge deck system and construction method of combined bridge deck system
CN101672108A (en) Steel plate-brickwork combination stressed building component and production method thereof
CN105064196A (en) Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite simple supported girder bridge and construction method thereof
CN104175398A (en) Manufacturing mould and method of reinforcement cage of precast box beam
CN105064200A (en) Prestressed ferroconcrete combined simply-supported beam bridge with preprocessed assembled fish-bellied truss frame and construction method of prestressed ferroconcrete combined simply-supported beam bridge
CN203546994U (en) Prefabricated superimposed floor slab and floor-slab layer
CN203394027U (en) Semi-assembled construction system for frame-shear wall tube structure
CN108316150B (en) Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
CN103321153A (en) Construction method for medium and small span trough girder bridge
CN203639804U (en) Continuous rigid frame bridge based on steel truss and concrete slab composite beam
CN105040823A (en) Partition plate and floor beam connecting structure for scissors staircase and construction method of partition plate and floor beam connecting structure
CN112593632A (en) Fabricated beam-slab structure suitable for large-span high-clearance building and construction method thereof
CN205224266U (en) Overlength super large area bottom plate post -cast strip structure
CN109680833B (en) Self-supporting prefabricated steel reinforced concrete wall plate component, wall, structural system and manufacturing method
CN104453228A (en) Construction method of large-span super-large-section steel plate wall beam
CN105442737A (en) Novel composite heat insulation floor board and construction method thereof
CN202990244U (en) Dual-T shaped composite beam with prestress concrete filled steel tube core bar
CN102454298B (en) Large-sized reinforced concrete construction of frame beam method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant