CN101629456A - Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss - Google Patents

Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss Download PDF

Info

Publication number
CN101629456A
CN101629456A CN200910305737A CN200910305737A CN101629456A CN 101629456 A CN101629456 A CN 101629456A CN 200910305737 A CN200910305737 A CN 200910305737A CN 200910305737 A CN200910305737 A CN 200910305737A CN 101629456 A CN101629456 A CN 101629456A
Authority
CN
China
Prior art keywords
steel truss
bracing frame
assembling
assembly unit
pairs
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910305737A
Other languages
Chinese (zh)
Other versions
CN101629456B (en
Inventor
赵海健
周浩东
孙炼斌
吴晓刚
周长义
付平平
阮鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING URBAN CONSTRUCTION JINGGONG STEEL STRUCTURE ENGINEERING Co Ltd
Original Assignee
BEIJING URBAN CONSTRUCTION JINGGONG STEEL STRUCTURE ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING URBAN CONSTRUCTION JINGGONG STEEL STRUCTURE ENGINEERING Co Ltd filed Critical BEIJING URBAN CONSTRUCTION JINGGONG STEEL STRUCTURE ENGINEERING Co Ltd
Priority to CN2009103057373A priority Critical patent/CN101629456B/en
Publication of CN101629456A publication Critical patent/CN101629456A/en
Application granted granted Critical
Publication of CN101629456B publication Critical patent/CN101629456B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a three-dimensional steel truss assembling support frame shaped like a Chinese character qie and a construction method for assembling the steel truss. The three-dimensional support frame shapes like a Chinese character qie and comprises two pairs of upright posts at the front and rear parts, two lower-boom jig-frame rods, two upper-boom trimmers, an operating platform and a pull rod, wherein the two lower-boom jig-frame rods are respectively arranged in parallel at the root parts of the two pairs of upright posts; the two upper-boom trimmers are respectively arranged in parallel at the top parts of the two pairs of upright posts; the operating platform is connected between the two upper-boom trimmers; the pull rod is connected between the two pairs of upright posts at the front and rear parts; locating holes are arranged in the middle part of the operating platform; and the edge of the locating hole is connected with a locating block for controlling the axle position of the steel truss. The technique for assembling the supporting the steel truss solves the problem of high-altitude location and assembly of the steel member, provides a more safe and reliable assembling platform for operators during high-altitude operation, and is widely applied in the field of assembling steel structures.

Description

Solid and formula steel truss assembly unit bracing frame and steel truss assembling and construction method thereof
Technical field
The present invention relates to a kind of bracing frame and steel truss assembling and construction method thereof of construction steel structure assembly unit engineering.
Background technology
The steel truss assembly unit of winding up belongs to work high above the ground, and work progress high and medium location assembly unit difficulty is big, and construction technology mainly is by setting up A-frame (seeing accompanying drawing 1), wind up by many covers A-frame sub-truss, the auxiliary girder location at present; But because A-frame is a two-dimensional structure, self stability is poor, so need drawknot between support and the support, to guarantee to form stabilization element, set spacing can not be excessive simultaneously, otherwise unstability appears in pull bar between support easily; This has increased the steel using amount in the engineering undoubtedly, has increased the difficulty of construction of engineering, has increased the construction cost of engineering.
Summary of the invention
Invention provides a kind of solid and formula steel truss assembly unit bracing frame, solve existing bracing frame instability, and the engineering steel amount is big, the technical problem of working security difference.
The technical solution adopted for the present invention to solve the technical problems is:
This solid and formula steel truss assembly unit bracing frame, it is characterized in that: this bracing frame is solid and font structure, the two pairs of vertical rods before and after comprising, be connected to the parallel and lower edge moulding bed bar put of two of two column roots, be connected to the parallel and joist that winds up put of two of two column tops, be connected in two wind up between the joist operating platform and be connected in pull bar between the two pairs of vertical rods in front and back, described operating platform middle part has locating hole, and the edge of locating hole is connected with the locating piece that is used to control the steel truss axial location.
Above-mentioned locating piece can be positioned at the middle part of the joist that winds up, and two wind up the locating piece of four symmetries on the joist.
About the aforesaid operations platform can be divided into two, two operating platforms laterally are connected the column outside respectively.
A pull bar can respectively be arranged at middle part and top between the two pairs of vertical rods in above-mentioned front and back.
Lower edge moulding bed bar, the joist that winds up, vertical rod and pull bar can be H shaped steel or i iron.
The steel truss assembling and construction method of this application solid and formula steel truss assembly unit bracing frame is characterized in that construction sequence is as follows:
Step 1: the lower edge moulding bed bar of arranging bracing frame at two banjo fixing butt jointing positions of steel truss;
Step 2: after lower edge moulding bed bar deploys, lifting steel truss lower chord;
Step 3: the steel truss lower chord installs, and lifting is the joist that winds up of steel truss fixedly, the assembly unit bracing frame;
Step 4: the lifting of a Pin steel truss upper chord and steel truss web member, upper chord becomes whole back hoisted in position with its straight web member at installation on ground, the constructor is in place by the auxiliary steel truss upper chord of the operating platform at bracing frame top, by locating piece control installation accuracy.After steel truss was in place, member can break off relations;
Step 5: the lifting of the 2nd Pin steel truss upper chord and web member, upper chord becomes whole back hoisted in position with its straight web member at installation on ground;
Step 6: the 3rd Pin steel truss lifting, an end is connected with truss, and an end is pulled wind and is fixed by leading the chain drawknot;
Step 7: install by expansion around the middle mind-set, require the pre-arch camber value of panel point is checked, guarantee the installation accuracy of postorder.
Beneficial effect of the present invention is as follows:
And formula bracing frame shape such as its word by the moulding of several shaped steel assembly weldings, are arranged in the butt joint node place of structure, can adjust rod member height and cross section specification according to the height and the weight of structure.The constructor controls installation accuracy by locating piece, winds up in place by the auxiliary steel truss of the operating platform at moulding bed top.After steel truss was in place, member can break off relations, and had improved the efficient of lifting operation; Especially hang time manyly in structure, under the few situation of hanging device, and formula steel truss assembly unit support technology can improve the lifting efficient of loop wheel machine greatly, satisfies daily demand of hanging time.Because bracing frame is a three-dimensional structure, so its stability will be higher than the A-frame of two-dimensional structure far away; Each bracing frame itself is exactly a stable cell cube, satisfies in rod member rigidity under the condition of self amount of deflection, only arranges in joint, rod member two ends to get final product.Save rolled steel dosage to greatest extent, controlled the construction cost of engineering, and be easy to construction.
And formula steel truss assembly unit support technology has solved location, steel member high-altitude, packing problem, provides a more safe and reliable platform for lining for the constructor in work high above the ground simultaneously.Can be widely used in the steel structure assembling construction field.
Description of drawings
The present invention is further described below in conjunction with drawings and Examples.
Fig. 1 is the structural representation of existing triangular support bracket.
Fig. 2 is a structural representation of the present invention.
Fig. 3 is the schematic diagram of construction sequence one, step 2.
Fig. 4 is the schematic diagram of construction sequence three.
Fig. 5 is the schematic diagram of construction sequence four, step 5.
Fig. 6 is the schematic diagram of construction sequence six.
Fig. 7 is the schematic diagram of construction sequence seven.
Reference numeral: 1-vertical rod, 2-lower edge moulding bed bar, 3-locating piece, 4-wind up joist, 5-operating platform, 6-pull bar, 7 bracing frames, 8 steel truss lower chords, 9 steel truss upper chords, 10 steel truss web members.
The specific embodiment
Embodiment is referring to shown in Figure 2, this solid and formula steel truss assembly unit bracing frame, this bracing frame is solid and font structure, the two pairs of vertical rods 1 before and after comprising, be connected to the parallel and lower edge moulding bed bar 2 put of two of two column roots, be connected to the parallel and joist 4 that winds up put of two of two column tops, be connected in two wind up between the joist 4 operating platform 5 and be connected in pull bar 6 between the two pairs of vertical rods in front and back, a pull bar 6 is respectively arranged at middle part and top between the two pairs of vertical rods 1 in front and back.About operating platform is divided into two, two operating platforms laterally are connected the column outside respectively.Operating platform middle part has locating hole, and the edge of locating hole is connected with the locating piece 3 that is used to control the steel truss axial location, and locating piece 3 is positioned at the middle part of the joist 4 that winds up, and two wind up the locating piece 3 of four symmetries on the joist 4.
Lower edge moulding bed bar 2, the joist 4 that winds up, vertical rod 1 and pull bar 6 are H shaped steel or i iron.
Adopt steel truss assembling construction process of the present invention as follows:
Step 1: the lower edge moulding bed bar 2 of arranging bracing frame 7 at two banjo fixing butt jointing positions of steel truss;
Step 2: after lower edge moulding bed bar 2 deployed, lifting steel truss lower chord 8 was referring to shown in Figure 3;
Step 3: the steel truss lower chord installs, and lifting is the joist that winds up of steel truss fixedly, and the assembly unit bracing frame is referring to shown in Figure 4;
Step 4: the lifting of a Pin steel truss upper chord 9 and steel truss web member 10, upper chord becomes whole back hoisted in position with its straight web member at installation on ground, the constructor is in place by the operating platform 5 auxiliary steel truss upper chords at bracing frame top, by locating piece 3 control installation accuracies.After steel truss was in place, member can break off relations; Referring to shown in Figure 5;
Step 5: the lifting of the 2nd Pin steel truss upper chord and web member, upper chord becomes whole back hoisted in position with its straight web member at installation on ground;
Step 6: the 3rd Pin steel truss lifting, an end is connected with truss, and an end is pulled wind and is fixed by leading the chain drawknot; Referring to shown in Figure 6.
Step 7: install by expansion around the middle mind-set, require the pre-arch camber value of panel point is checked, guarantee the installation accuracy of postorder, referring to shown in Figure 7.

Claims (6)

1. solid and formula steel truss assembly unit bracing frame, it is characterized in that: this bracing frame is solid and font structure, two pairs of vertical rods (1) before and after comprising, be connected to the parallel and lower edge moulding bed bar (2) put of two of two column roots, be connected to the parallel and joist that winds up (4) put of two of two column tops, be connected in the operating platform (5) between two joists that wind up (4) and be connected in pull bar (6) between the two pairs of vertical rods in front and back, described operating platform middle part has locating hole, and the edge of locating hole is connected with the locating piece (3) that is used to control the steel truss axial location.
2. solid according to claim 1 and formula steel truss assembly unit bracing frame, it is characterized in that: above-mentioned locating piece (3) is positioned at the middle part of the joist that winds up (4), and two wind up the locating piece (3) of four symmetries on the joist (4)
3. solid according to claim 1 and formula steel truss assembly unit bracing frame is characterized in that: about the aforesaid operations platform is divided into two, two operating platforms laterally are connected the column outside respectively.
4. solid according to claim 1 and formula steel truss assembly unit bracing frame, it is characterized in that: a pull bar (6) is respectively arranged at middle part between the two pairs of vertical rods in above-mentioned front and back (1) and top.
5. solid according to claim 1 and formula steel truss assembly unit bracing frame is characterized in that: lower edge moulding bed bar (2), the joist that winds up (4), vertical rod (1) and pull bar (6) are H shaped steel or i iron.
6. steel truss assembling and construction method of using solid and formula steel truss assembly unit bracing frame is characterized in that construction sequence is as follows:
Step 1: the lower edge moulding bed bar (2) of arranging bracing frame (7) at two banjo fixing butt jointing positions of steel truss;
Step 2: after lower edge moulding bed bar (2) deploys, lifting steel truss lower chord (8);
Step 3: the steel truss lower chord installs, and lifting is the joist that winds up of steel truss fixedly, the assembly unit bracing frame;
Step 4: the lifting of a Pin steel truss upper chord (9) and steel truss web member (10), upper chord becomes whole back hoisted in position with its straight web member at installation on ground, the constructor is in place by the auxiliary steel truss upper chord of the operating platform (5) at bracing frame top, by locating piece (3) control installation accuracy.After steel truss was in place, member can break off relations;
Step 5: the lifting of the 2nd Pin steel truss upper chord and web member, upper chord becomes whole back hoisted in position with its straight web member at installation on ground;
Step 6: the 3rd Pin steel truss lifting, an end is connected with truss, and an end is pulled wind and is fixed by leading the chain drawknot;
Step 7: install by expansion around the middle mind-set, require the pre-arch camber value of panel point is checked, guarantee the installation accuracy of postorder.
CN2009103057373A 2009-08-18 2009-08-18 Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss Expired - Fee Related CN101629456B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103057373A CN101629456B (en) 2009-08-18 2009-08-18 Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103057373A CN101629456B (en) 2009-08-18 2009-08-18 Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss

Publications (2)

Publication Number Publication Date
CN101629456A true CN101629456A (en) 2010-01-20
CN101629456B CN101629456B (en) 2010-10-13

Family

ID=41574719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103057373A Expired - Fee Related CN101629456B (en) 2009-08-18 2009-08-18 Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss

Country Status (1)

Country Link
CN (1) CN101629456B (en)

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155096A (en) * 2011-03-02 2011-08-17 攀钢集团冶金工程技术有限公司 Enormous-span steel tube house truss assembling construction method
CN102877636A (en) * 2012-10-23 2013-01-16 中国第二重型机械集团(德阳)万信工程设备有限责任公司 Built-in truss used during installation of C-shaped plates and hoisting method for same
CN102889001A (en) * 2012-11-06 2013-01-23 南通建筑工程总承包有限公司 Device for adjusting butt joint dislocation of chord member of pipe truss structure
CN102912972A (en) * 2012-10-31 2013-02-06 中建三局第二建设工程有限责任公司 Multifunctional lifting steel platform switching jig and construction method
CN102936962A (en) * 2012-11-20 2013-02-20 永升建设集团有限公司 Construction method of slanting cantilever steel structure supported by temporary steel frame
CN103276909A (en) * 2013-04-16 2013-09-04 中建钢构有限公司 Arc-shaped grid structure assembly method and grid structure assembly jig frame used by same
CN103866987A (en) * 2014-03-26 2014-06-18 安徽杭萧钢结构有限公司 Jig frame structure for truss assembling and method for assembling truss with jig frame structure
CN105401691A (en) * 2015-11-23 2016-03-16 中建钢构有限公司 Temporary supporting device for shuttle-shaped space truss and assembly method of shuttle-shaped space truss
CN106121237A (en) * 2016-08-31 2016-11-16 中建四局第建筑工程有限公司 Large-span steel arch without outer construction method for supporting and assembled welding positioner
CN106812212A (en) * 2017-02-16 2017-06-09 中国建筑第八工程局有限公司 Unit truss quick-assembling support and unit truss assembling method
CN106917509A (en) * 2017-04-07 2017-07-04 中国十七冶集团有限公司 The accumulation slippage list truss structure arch camber control of long-span roofing truss and discharging method
CN108149582A (en) * 2018-01-19 2018-06-12 中国建筑第八工程局有限公司 For installing the support equipment of large-scale component and its method for supporting
CN108731647A (en) * 2018-03-14 2018-11-02 江苏恒久钢构有限公司 A kind of truss installa-tion docking measurement method
CN109707100A (en) * 2019-02-21 2019-05-03 金川集团股份有限公司 A kind of device and arch camber method of the automatic arch camber of parallel chord truss
CN109898871A (en) * 2019-04-11 2019-06-18 中国二十二冶集团有限公司 Inclined in two-way steel column mounting and positioning device and localization method
CN110067393A (en) * 2019-05-27 2019-07-30 湖南省第六工程有限公司 The lateral assembled moulding bed of face arch truss
CN110792261A (en) * 2019-11-15 2020-02-14 黄艳梅 Steel structure engineering site construction installation splicing pre-positioning equipment and installation method
CN111779286A (en) * 2020-07-24 2020-10-16 中冶建工集团重庆钢结构有限公司 Construction method for assembling planar truss on site
CN114635548A (en) * 2022-02-18 2022-06-17 中铁五局集团建筑工程有限责任公司 Rapid and accurate assembling device and method for hyperbolic space inverted triangular steel truss
CN114700672A (en) * 2022-05-07 2022-07-05 鑫源富金属制品(漳州)有限公司 Truss welding auxiliary device
CN115075383A (en) * 2022-08-04 2022-09-20 上海市机械施工集团有限公司 Assembling method and assembling support for grid structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5676358A (en) * 1995-11-02 1997-10-14 Alpine Engineered Products, Inc. Variable height jig stop assembly and alignment plates for truss table
CN2484376Y (en) * 2001-07-10 2002-04-03 江苏中联建设技术工贸联合公司 Square type supporting apparatus
CN100513727C (en) * 2007-11-13 2009-07-15 中国京冶工程技术有限公司 Prestressed bracing arrangement

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155096B (en) * 2011-03-02 2012-08-08 攀钢集团工程技术有限公司 Enormous-span steel tube house truss assembling construction method
CN102155096A (en) * 2011-03-02 2011-08-17 攀钢集团冶金工程技术有限公司 Enormous-span steel tube house truss assembling construction method
CN102877636A (en) * 2012-10-23 2013-01-16 中国第二重型机械集团(德阳)万信工程设备有限责任公司 Built-in truss used during installation of C-shaped plates and hoisting method for same
CN102912972B (en) * 2012-10-31 2014-11-05 中建三局第二建设工程有限责任公司 Multifunctional lifting steel platform switching jig and construction method
CN102912972A (en) * 2012-10-31 2013-02-06 中建三局第二建设工程有限责任公司 Multifunctional lifting steel platform switching jig and construction method
CN102889001B (en) * 2012-11-06 2015-03-25 江苏中南建筑产业集团有限责任公司 Device for adjusting butt joint dislocation of chord member of pipe truss structure
CN102889001A (en) * 2012-11-06 2013-01-23 南通建筑工程总承包有限公司 Device for adjusting butt joint dislocation of chord member of pipe truss structure
CN102936962A (en) * 2012-11-20 2013-02-20 永升建设集团有限公司 Construction method of slanting cantilever steel structure supported by temporary steel frame
CN103276909A (en) * 2013-04-16 2013-09-04 中建钢构有限公司 Arc-shaped grid structure assembly method and grid structure assembly jig frame used by same
CN103276909B (en) * 2013-04-16 2015-10-28 中建钢构有限公司 The assembled moulding bed of rack of arch-shaped space truss assembling method and use thereof
CN103866987A (en) * 2014-03-26 2014-06-18 安徽杭萧钢结构有限公司 Jig frame structure for truss assembling and method for assembling truss with jig frame structure
CN105401691A (en) * 2015-11-23 2016-03-16 中建钢构有限公司 Temporary supporting device for shuttle-shaped space truss and assembly method of shuttle-shaped space truss
CN106121237B (en) * 2016-08-31 2018-08-07 中建四局第一建筑工程有限公司 Large-span steel arch without outer construction method for supporting and assembled welding positioner
CN106121237A (en) * 2016-08-31 2016-11-16 中建四局第建筑工程有限公司 Large-span steel arch without outer construction method for supporting and assembled welding positioner
CN106812212A (en) * 2017-02-16 2017-06-09 中国建筑第八工程局有限公司 Unit truss quick-assembling support and unit truss assembling method
CN106917509A (en) * 2017-04-07 2017-07-04 中国十七冶集团有限公司 The accumulation slippage list truss structure arch camber control of long-span roofing truss and discharging method
CN106917509B (en) * 2017-04-07 2018-12-25 中国十七冶集团有限公司 The accumulation slippage list truss structure arch camber control of long-span roofing truss and discharging method
CN108149582A (en) * 2018-01-19 2018-06-12 中国建筑第八工程局有限公司 For installing the support equipment of large-scale component and its method for supporting
CN108731647A (en) * 2018-03-14 2018-11-02 江苏恒久钢构有限公司 A kind of truss installa-tion docking measurement method
CN109707100A (en) * 2019-02-21 2019-05-03 金川集团股份有限公司 A kind of device and arch camber method of the automatic arch camber of parallel chord truss
CN109898871A (en) * 2019-04-11 2019-06-18 中国二十二冶集团有限公司 Inclined in two-way steel column mounting and positioning device and localization method
CN110067393A (en) * 2019-05-27 2019-07-30 湖南省第六工程有限公司 The lateral assembled moulding bed of face arch truss
CN110792261A (en) * 2019-11-15 2020-02-14 黄艳梅 Steel structure engineering site construction installation splicing pre-positioning equipment and installation method
CN110792261B (en) * 2019-11-15 2021-06-15 北汇绿建集团有限公司 Steel structure engineering site construction installation splicing pre-positioning equipment and installation method
CN111779286A (en) * 2020-07-24 2020-10-16 中冶建工集团重庆钢结构有限公司 Construction method for assembling planar truss on site
CN114635548A (en) * 2022-02-18 2022-06-17 中铁五局集团建筑工程有限责任公司 Rapid and accurate assembling device and method for hyperbolic space inverted triangular steel truss
CN114635548B (en) * 2022-02-18 2024-04-05 中铁五局集团建筑工程有限责任公司 Rapid and accurate assembling device and method for hyperbolic space inverted triangle steel truss
CN114700672A (en) * 2022-05-07 2022-07-05 鑫源富金属制品(漳州)有限公司 Truss welding auxiliary device
CN114700672B (en) * 2022-05-07 2023-10-20 鑫源富金属制品(漳州)有限公司 Truss welding auxiliary device
CN115075383A (en) * 2022-08-04 2022-09-20 上海市机械施工集团有限公司 Assembling method and assembling support for grid structure
CN115075383B (en) * 2022-08-04 2024-04-26 上海市机械施工集团有限公司 Assembling method and assembling bracket for grid structure

Also Published As

Publication number Publication date
CN101629456B (en) 2010-10-13

Similar Documents

Publication Publication Date Title
CN101629456B (en) Three-dimensional steel truss assembling support frame shaped like a Chinese character qie and construction method for assembling steel truss
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN110700572B (en) Height-adjustable supporting base and using method thereof
CN103352428A (en) Suspension bridge cable bent tower beam non-support construction method
CN105442853B (en) A kind of long-span deformed Elements of Space Grid Truss and landing Steel Structure Installation construction method
CN103321156B (en) Foldable through-tunnel bridge girder erection machine rear support leg and application thereof
CN102277980B (en) Device for integrally jacking roof of single-layer industrial factory building and construction method thereof
CN201526151U (en) Three-dimensional zigzag-shaped steel truss assembled support frame
CN102777050B (en) Assembly type jig frame for longspan pipe truss roof girder
CN203034345U (en) Coal transporting trestle of integral continuous steel truss
CN203530864U (en) Large-span concrete continuous beam bridge side span folding device
CN107268987B (en) Cross type adjustable climbing machine position reaction frame and construction method thereof
CN205444935U (en) Special -shaped steel space frame construction and installation structure of complicated large -span department
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN201943350U (en) Supporting steel frame for die holder of high-altitude large span overhanging structure
CN213061723U (en) Rib walking jacking device
CN202144681U (en) Oar-type steel well frame
CN205387943U (en) Tunnel lining trolley
CN106368322A (en) Installing method of bidirectional symmetric oblique steel posts used between super high-rise building transfer stories
CN203113226U (en) Formwork support system with towering asymmetric concrete cantilever structure
CN206971394U (en) The automatic lifting system of Steel Structure Installation
CN205134533U (en) Complicated special -shaped steel mesh frame and steel skeleton construction and installation structure
CN218292929U (en) Support frame of hoop on civil engineering structure beam
CN203271193U (en) Large overhang stand with space structure
CN219826306U (en) Assembled steel structure support with regulatory function

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101013