CN101614304B - 热力盾构隧道热力管道固定传力支架 - Google Patents

热力盾构隧道热力管道固定传力支架 Download PDF

Info

Publication number
CN101614304B
CN101614304B CN2009103051998A CN200910305199A CN101614304B CN 101614304 B CN101614304 B CN 101614304B CN 2009103051998 A CN2009103051998 A CN 2009103051998A CN 200910305199 A CN200910305199 A CN 200910305199A CN 101614304 B CN101614304 B CN 101614304B
Authority
CN
China
Prior art keywords
thermodynamic
tunnel
pipe
force transfer
fixing force
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009103051998A
Other languages
English (en)
Other versions
CN101614304A (zh
Inventor
贾嘉陵
张玉成
牛小化
孙知音
胡嵩
朱玉明
杨森林
李晋才
张丽丽
马静
安峰
蔡瑞
孟庆龙
王武京
韩化龙
李春阳
王善志
赵晨阳
吴传峰
沈瑞鹤
刘明
李景强
冷维超
高健
关伟
刘峥
颜琨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN2009103051998A priority Critical patent/CN101614304B/zh
Publication of CN101614304A publication Critical patent/CN101614304A/zh
Application granted granted Critical
Publication of CN101614304B publication Critical patent/CN101614304B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

一种热力盾构隧道热力管道固定传力支架,间隔分布于隧道内壁,隧道由预制管片组合而成,所述隧道内壁由双拱形固定件固定两圈环梁,两圈环梁之间固定有两根或四根立柱,每根立柱的两端支撑在隧道内壁两侧,每两根立柱的前后两侧各连接有一个用于穿过热力管道的受力框架。本发明解决了热力盾构隧道中热力管道的固定问题,使热力管道能够承受管道轴向和侧向的水平推拉力。在水平推力作用下,固定支架系统可以均匀地将水平推力传递到6个预制管片。预制管片在外力作用下均匀移动,同时使预制管片间不产生相对位移。

Description

热力盾构隧道热力管道固定传力支架
技术领域
本发明涉及一种热力管道的定位装置。
背景技术
在热力供暖运行过程中,沿热力管道轴向(X轴向)和侧向产生(Y轴向)会产生水平推力,X向水平推力设计值为800KN,Y向力设计值为500KN,所以必须采用管道固定传力支架来承受热力管道X和Y向的水平推力。传统热力浅埋暗挖隧道是先施工热力管道支架再灌注隧道的二次衬砌结构,这种传统的支架很容易固定在隧道的二次衬砌结构中。但是,在热力盾构隧道热力管道的施工工艺中,热力盾构隧道施工完毕后,无二次衬砌结构,因此,热力管道与隧道之间的固定就成为新的技术难题。
发明内容
本发明提供一种热力盾构隧道热力管道固定传力支架,要解决热力盾构隧道中热力管道的固定问题。
本发明解决其技术问题所采用的技术方案是:这种热力盾构隧道热力管道固定传力支架,间隔分布于隧道内壁,隧道由预制管片组合而成,所述热力管道固定传力支架包括环梁、固定件、立柱和受力框架,所述隧道内壁由双拱形固定件固定两圈环梁,两圈环梁之间固定有两根或四根立柱,每根立柱的两端支撑在隧道内壁两侧,每两根立柱的前后两侧各连接有一个用于穿过热力管道的受力框架。
所述受力框架由两片方形框体,以及方形框体之间的连杆构成,方形框体的两侧边分别焊接在两立柱侧面。
所述位于中部的两立柱在受力框架上下两侧带有两个固定卡环。
所述环梁由双拱形固定件及螺栓与预制管片内壁固定。
所述双拱形固定件与环梁以及预制管片之间有硫化硅胶垫层。
本发明的有益效果如下:
与传统热力浅埋暗挖隧道比较,热力盾构隧道是先施工隧道管片然后施工固定支架,可以保证热力管道的稳固定位。本发明解决了热力盾构隧道中热力管道的固定问题,使热力管道能够承受管道轴向和侧向的水平推拉力。在水平推力作用下,固定支架系统可以均匀地将水平推力传递到6个预制管片。预制管片在外力作用下均匀移动,同时使预制管片间不产生相对位移。
附图说明
下面结合附图和实施例对本发明进一步说明。
图1是本发明横截面的结构示意图。
图2是图1B-B剖面的结构示意图。
图3是图1A-A剖面的结构示意图。
图4是受力框架的结构示意图。
图5是环梁横截面的结构示意图。
图6是固定件、环梁、预制管片连接的结构示意图。
图7是本发明的立体结构示意图。
附图标记:1-预制管片、 2-环梁、3-固定件、4-立柱、5-受力框架、6-固定卡环、7-螺栓、8-硫化硅胶垫层。
具体实施方式
实施例参见图1-3所示,这种热力盾构隧道热力管道固定传力支架,间隔分布于隧道内壁,隧道由6个预制管片1组合而成,预制管片组成,长1200mm,所述热力管道固定传力支架包括环梁2、固定件3、立柱4和受力框架5,所述隧道内壁由双拱形固定件3固定两圈环梁2,两圈环梁之间固定有两根或四根立柱4,每根立柱4的两端支撑在隧道内壁两侧,每两根立柱的前后两侧各连接有一个用于穿过热力管道的受力框架5。
钢立柱的尺寸是400X400X20(mm)。钢立柱的材料是Q235钢材。
参见图3-4所示,受力框架5由两片方形框体,以及方形框体之间的连杆构成,方形框体的两侧边分别焊接在两立柱侧面。
参见图5所示,环梁的横截面可以为矩形。环梁尺寸:200X100X10(mm)。环梁的材料是铸钢ZG200-400。
参见图6所示,所述环梁由双拱形固定件3及螺栓7与预制管片内壁固定。所述双拱形固定件3与环梁以及预制管片之间垫有硫化硅胶垫层8。固定件尺寸:200X1200X10(mm)。固定件材料是铸钢ZG200-400。
参见图7所示,两圈环梁之间固定有两根立柱4,立柱的两端支撑在隧道内壁两侧,每两根立柱的前后两侧各连接有一个用于穿过热力管道的受力框架5,两立柱4在受力框架上下两侧带有两个固定卡环6,热力管道穿过受力框架而定位。

Claims (4)

1.一种热力盾构隧道热力管道固定传力支架,间隔分布于隧道内壁,隧道由预制管片(1)组合而成,其特征在于:所述热力管道固定传力支架包括环梁(2)、固定件(3)、立柱(4)和受力框架(5),所述隧道内壁由双拱形固定件(3)固定两圈环梁(2),两圈环梁之间固定有两根或四根立柱(4),每根立柱(4)的两端支撑在隧道内壁两侧,每两根立柱的前后两侧各连接有一个用于穿过热力管道的受力框架(5);
所述受力框架(5)由两片方形框体,以及方形框体之间的连杆构成,方形框体的两侧边分别焊接在两立柱侧面。
2.根据权利要求1所述的热力盾构隧道热力管道固定传力支架,其特征在于:所述位于中部的两立柱(4)在受力框架上下两侧带有两个固定卡环(6)。
3.根据权利要求1所述的热力盾构隧道热力管道固定传力支架,其特征在于:所述环梁由双拱形固定件(3)及螺栓(7)与预制管片内壁固定。
4.根据权利要求1所述的热力盾构隧道热力管道固定传力支架,其特征在于:所述双拱形固定件(3)与环梁以及预制管片之间有硫化硅胶垫层(8)。
CN2009103051998A 2009-08-05 2009-08-05 热力盾构隧道热力管道固定传力支架 Expired - Fee Related CN101614304B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103051998A CN101614304B (zh) 2009-08-05 2009-08-05 热力盾构隧道热力管道固定传力支架

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103051998A CN101614304B (zh) 2009-08-05 2009-08-05 热力盾构隧道热力管道固定传力支架

Publications (2)

Publication Number Publication Date
CN101614304A CN101614304A (zh) 2009-12-30
CN101614304B true CN101614304B (zh) 2011-01-12

Family

ID=41494128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103051998A Expired - Fee Related CN101614304B (zh) 2009-08-05 2009-08-05 热力盾构隧道热力管道固定传力支架

Country Status (1)

Country Link
CN (1) CN101614304B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101761344B (zh) * 2010-01-14 2012-05-30 华南理工大学 一种盾构隧道预制管片的制备方法
CN104265306B (zh) * 2014-07-30 2016-10-26 广州电力设计院 一种市政盾构隧道
CN108915768B (zh) * 2018-08-28 2023-11-14 北京城建设计发展集团股份有限公司 热力盾构隧道内热力管道固定传力支架系统
CN111456770B (zh) * 2018-12-05 2021-12-14 莆田城厢振达宸贸易有限公司 地铁施工移动式隧道管片支撑装置
CN110056370A (zh) * 2019-03-27 2019-07-26 中建三局集团有限公司 一种盾构始发及到达端管片与后浇环梁连接装置

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3915015A1 (de) * 1988-05-26 1989-12-07 Hoesch Ag Verbindungsschelle
JP2001182493A (ja) * 1999-12-28 2001-07-06 Sumitomo Rubber Ind Ltd 可撓性継手およびそれを用いたシールドトンネルの施工方法
CN2846504Y (zh) * 2005-10-17 2006-12-13 东南大学 基坑钢支撑变形调节装置
GB2430948A (en) * 2005-10-07 2007-04-11 Tyco Europe Metal Framing Ltd Tunnel Lining Bracket
EP1798584A1 (en) * 2005-12-19 2007-06-20 Telect, Inc. Latching trough-coupling system
GB2445672A (en) * 2007-01-15 2008-07-16 Tyco Europe Metal Framing Ltd Tunnel Lining Bracket
CN201474702U (zh) * 2009-08-05 2010-05-19 北京市政建设集团有限责任公司 热力盾构隧道热力管道固定传力支架

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3915015A1 (de) * 1988-05-26 1989-12-07 Hoesch Ag Verbindungsschelle
JP2001182493A (ja) * 1999-12-28 2001-07-06 Sumitomo Rubber Ind Ltd 可撓性継手およびそれを用いたシールドトンネルの施工方法
GB2430948A (en) * 2005-10-07 2007-04-11 Tyco Europe Metal Framing Ltd Tunnel Lining Bracket
CN2846504Y (zh) * 2005-10-17 2006-12-13 东南大学 基坑钢支撑变形调节装置
EP1798584A1 (en) * 2005-12-19 2007-06-20 Telect, Inc. Latching trough-coupling system
GB2445672A (en) * 2007-01-15 2008-07-16 Tyco Europe Metal Framing Ltd Tunnel Lining Bracket
CN201474702U (zh) * 2009-08-05 2010-05-19 北京市政建设集团有限责任公司 热力盾构隧道热力管道固定传力支架

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
丁磊.动物园站盖挖逆作中桩(柱)施工技术.《北京市政第一届地铁与地下工程施工技术学术研讨会》.2005,第23卷(第增刊(2)期),209-212. *
乐贵平等.地铁盾构法隧道管片设计的几个问题.《市政技术》.2003,第21卷(第5期),325-329. *
李明.高压富水地层盾构隧道联络通道冻结法施工时隧道结构的支护方式研究.《中国优秀硕士学位论文全文数据库》.2008,全文. *
王召民.山区管道顶管施工技术.《中国优秀硕士学位论文全文数据库》.2007,全文. *

Also Published As

Publication number Publication date
CN101614304A (zh) 2009-12-30

Similar Documents

Publication Publication Date Title
CN101614304B (zh) 热力盾构隧道热力管道固定传力支架
AU2017415961A1 (en) Prefabricated dual-steel-tube concrete shear wall, and assembly method therefor
CN101761344A (zh) 一种盾构隧道预制管片及其制备方法
CN104818775A (zh) 一种新型预制装配式框架结构
CN104372967B (zh) 一种自然通风冷却塔用斜支柱结构及其施工方法
CN103628572A (zh) 一种用于逆作法工程中梁柱节点
CN201474702U (zh) 热力盾构隧道热力管道固定传力支架
CN203640061U (zh) 地下室钢筋混凝土柱节点连接结构
CN108915768B (zh) 热力盾构隧道内热力管道固定传力支架系统
CN205369043U (zh) 大跨径钢箱梁顶推施工用临时支撑结构
CN204212058U (zh) 用于钢砼组合桁架梁施工中的钢桁梁拼装支架
CN109778702B (zh) 跨既有城市立交钢箱梁顶推施工方法
CN203546618U (zh) 一种桥梁现浇混凝土模板八字支撑架
CN202482766U (zh) 大跨度连续梁施工支架结构
CN201835390U (zh) 一种圆管混凝土柱梁柱刚接节点
CN210033436U (zh) 一种盾构隧道轻型保圆支撑体系
CN113774925A (zh) 深基坑围护桩水平内撑转换结构的施工方法
CN211646041U (zh) 一种石拱桥加固结构
CN210439163U (zh) 一种适用于连续梁可拆装斜拉托梁支撑结构
CN204000936U (zh) 基于扣件式钢管地锚桁架的地下室外墙单面支模体系
CN216275722U (zh) 深基坑围护桩水平内撑转换结构
CN203320701U (zh) 一种多向穿心钢牛腿、环梁、钢管混凝土柱梁节点
CN206859260U (zh) 管廊抗大推力支架结构
CN107476200B (zh) 一种满堂支架错位套搭结构及方法
CN104278640B (zh) 用于钢砼组合桁架梁施工中的钢桁梁拼装支架

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110112

Termination date: 20120805