CN101608885A - 山区河流水下钻孔爆破施工方法 - Google Patents

山区河流水下钻孔爆破施工方法 Download PDF

Info

Publication number
CN101608885A
CN101608885A CNA2009101042833A CN200910104283A CN101608885A CN 101608885 A CN101608885 A CN 101608885A CN A2009101042833 A CNA2009101042833 A CN A2009101042833A CN 200910104283 A CN200910104283 A CN 200910104283A CN 101608885 A CN101608885 A CN 101608885A
Authority
CN
China
Prior art keywords
sleeve pipe
ship
underwater drilling
construction method
powder charge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2009101042833A
Other languages
English (en)
Other versions
CN101608885B (zh
Inventor
李红勇
李春军
代显华
姚勇
罗宏
罗磊
谢达建
周在友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHANGJIANG CHONGQING WATERWAY ENGINEERING BUREAU
Original Assignee
CHANGJIANG CHONGQING WATERWAY ENGINEERING BUREAU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHANGJIANG CHONGQING WATERWAY ENGINEERING BUREAU filed Critical CHANGJIANG CHONGQING WATERWAY ENGINEERING BUREAU
Priority to CN 200910104283 priority Critical patent/CN101608885B/zh
Publication of CN101608885A publication Critical patent/CN101608885A/zh
Application granted granted Critical
Publication of CN101608885B publication Critical patent/CN101608885B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明公开了一种山区河流水下钻孔爆破施工方法,包括钻爆船定位、水下钻孔、装药堵塞、爆破网络连接和移船爆破步骤,其中:钻爆船定位采用岸缆定位法,在水下钻孔前先在钻孔位置竖直安装套管,钻具通过套管下到钻孔位置进行钻孔,本发明能够解决钻爆船布缆定位、水下钻孔、水下装药、移船爆破等施工环节的施工难点,钻具在套管的保护下进行钻孔,可避免水流冲击造成偏位和卡钻,同时套管在装药时还起到导向作用,本发明能减轻水的浮力、流速和风浪,水的渗透作用和压力等对施工过程以及爆破器材的性能、装药的设置与固定产生的影响,实现准确定位并爆破。

Description

山区河流水下钻孔爆破施工方法
技术领域
本发明涉及一种爆破施工方法,特别是一种山区河流水下钻孔爆破施工方法。
背景技术
水下爆破是指在水面下、水底土岩表面或水下岩层内部的爆破。民用一般用于炸除礁石,疏通航道,加深港口,在水下挖基坑、沟槽及开设引水洞等。
水下钻孔爆破是水下炸礁的主要施工方法,具有炸药消耗量少、施工工效高、爆破有害效应小的特点,广泛的应用于航道整治工程、港口码头港池开挖等工程施工。而对于山区河流水下钻孔爆破时,水的浮力、流速、风浪,水的渗透作用和压力,都将对爆破器材的性能、装药、船舶定位、钻孔固定、爆破产生影响。特别是激流河段、落差大(纵比降大)滩险和潮差大的海域,船舶固定、套管定位、施工与通航的矛盾、保证装药成功率是钻爆能否成功的关键。
因此,进行水下钻孔爆破通常需要解决钻爆船布缆定位、水下钻孔套管固定、水下装药、移船爆破等施工环节的施工难点。
发明内容
有鉴于此,本发明的目的是提供一种山区河流水下钻孔爆破施工方法,能够在山区河流等激流河段保持稳固、精确的船位,以便确定钻孔孔位,能够减小流水对钻具和药柱的影响。
本发明的山区河流水下钻孔爆破施工方法,包括钻爆船定位、水下钻孔、装药堵塞、爆破网络连接和移船爆破步骤,其中:
钻爆船定位:采用岸缆定位法,所述缆分为主缆和横缆,主缆一端逆流锚固与岸相对固定,一端与船固定设置;所述横缆为至少两根分别固定设置在钻爆船两侧,横缆另一端锚固与岸相对固定;
在水下钻孔前安放套管:在钻孔位置设置套管,所述套管分为管脚和管身,所述管脚下端加工成端面锯齿形,管脚通过锯齿形端面与钻孔位置相对固定,固定后的套管为竖直安装;所述套管管身上设置花管段,所述花管段管壁上设置多个径向通孔,花管段下端部距管脚下端的距离大于等于1.8米;
水下钻孔:钻具通过套管下到钻孔位置,进行钻孔。
进一步,所述花管段长度为1.5-2.5米;
进一步,所述管身与管脚之间以可拆分的方式固定连接;
进一步,所述主缆为两根,以人字形结构分别锚固在两岸或一侧岸边;横缆为四根,其中船艏两根、船艉两根分别锚固于两岸,布置横缆时,先布置船艏两根横缆,后布置船艉两根横缆;
进一步,所述跨过主航道一侧的主缆或/和横缆采用锚链沉入水底的方式锚固;
进一步,所述装药堵塞步骤中,包括测量孔深、装药、检查线路和炮孔堵塞步骤,在装药前将需装入的药柱用壁厚在0.2mm以下的塑料管进行外包装;在炮孔堵塞步骤中,首先在套管内插入内套管;
进一步,套管底部采用提头钢缆牵引,用于抵抗水流作用力,提头钢缆上端固定在船艏设置的绞锚机上,通过绞锚机松紧提头钢缆来调整套管偏差;
进一步,在爆破网络连接步骤中,炮线捆扎在绳上,所述炮线长于绳,使炮线以松弛的状态捆扎在绳上;所述炮线连接在托线浮筒上,所述托线浮筒设置在爆破区上游20-50米处。
本发明的有益效果是:本发明的山区河流水下钻孔爆破施工方法,采用具有可靠的绞缆系缆设施的钻爆船,在激流河段保持稳固、精确的船位,以便确定钻孔孔位;通过套管进行水下钻孔和装药,利于穿过激流水层,减小流水对钻具和药柱的影响;能够解决钻爆船布缆定位、水下钻孔、水下装药、移船爆破等施工环节的施工难点,钻具在套管的保护下进行钻孔,可避免水流冲击造成偏位和卡钻,同时套管在装药时还起到导向作用,本发明能减轻水的浮力、流速和风浪,水的渗透作用和压力等对施工过程以及爆破器材的性能、装药的设置与固定产生的影响,实现准确定位并爆破。
附图说明
下面结合附图和实施例对本发明作进一步描述。
图1为本发明的原理方框图;
图2为本发明套管结构示意图;
图3为本发明套管花管段插入内套管结构示意图;
图4为本发明钻爆船定位示意图。
具体实施方式
图1为本发明的原理方框图,图2为本发明套管结构示意图,图3为本发明套管花管段插入内套管结构示意图,图4为本发明钻爆船定位示意图,如图所示:本实施例的山区河流水下钻孔爆破施工方法,包括钻爆船定位、水下钻孔、装药堵塞、爆破网络连接和移船爆破步骤,其中:
钻爆船定位:采用岸缆定位法,所述缆分为两根主缆3和四根横缆4,两根主缆以人字形结构组合,一端逆流分别锚固在两岸,一端与钻爆船6固定设置;横缆4为四根,其中船艏两根分别固定设置在钻爆船6两侧,船艉两根分别固定设置在钻爆船6两侧,布置横缆4时,先布置船艏两根横缆,后布置船艉两根横缆;跨过主航道一侧的横缆4采用锚链沉入水底的方式锚固,采用锚链沉底的方法作为跨江横缆,可解决施工与通航之间的矛盾。
在水下钻孔前安放套管:在钻孔位置设置套管,可进行定点测量孔位、孔深,保证了钻孔的准确性;套管分为管脚1和管身2,管身2与管脚1之间通过螺纹以可拆分的方式固定连接,方便管脚或管身的更换;管脚1下端加工成端面锯齿形,深入钻孔位置后增大与河床的摩擦力,利于在激流中稳定套管,使管脚1与钻孔位置相对固定,固定后的套管为竖直安装,便于钻孔和装药;套管管身2上设置花管段21,花管段21的管壁上设置多个径向通孔22,花管段21下端部距管脚1下端的距离等于1.8米,花管段21长度为2米,采用花管结构便于压缩空气和钻孔石渣排出;套管底部还采用提头钢缆牵引,抵抗水流作用力;提头钢缆上端固定在船艏设置的绞锚机上,通过绞锚机松紧提头钢缆来调整套管偏差,可稳固套管。
水下钻孔:钻具通过套管下到钻孔位置,进行钻孔;开孔时,宜采用小风量旋转冲击,钻孔过程中,边提升钻杆,边送风吹水,以便钻孔中的石渣排除孔外;钻孔钻至设计深度后,反复多次提升和下落钻杆,清洗钻孔,以防碎石或淤沙堵孔;
装药堵塞步骤中,还包括测量孔深、装药、检查线路和炮孔堵塞步骤,本实施例中,测量孔深采用塑料装药杆顺套管插入孔底,装药杆长度减去套管长度即为钻孔深度;
在装药前将需装入的药柱用壁厚在0.2mm以下的塑料管进行外包装,本实施例中为0.2mm的PVC管,保护药柱在装药过程中不被破坏,确保了爆破的可靠性;而在炮孔堵塞步骤中,首先在套管内插入内套管5,保证堵塞精度并防止堵塞物被水流从花管段21处被冲走;起爆体内设置两发并联雷管,确保能够顺利起爆;
在爆破网络连接步骤中,炮线捆扎在绳上,炮线长于绳,使炮线以松弛的状态捆扎在绳上,防止外力使炮线断开,影响爆破正常进行;所述炮线连接在托线浮筒上,托线浮筒设置在爆破区上游50米处。
最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。

Claims (8)

1.一种山区河流水下钻孔爆破施工方法,包括钻爆船定位、水下钻孔、装药堵塞、爆破网络连接和移船爆破步骤,其特征在于:其中:
钻爆船定位:采用岸缆定位法,所述缆分为主缆(3)和横缆(4),主缆(3)一端逆流锚固与岸相对固定,一端与船固定设置;所述横缆(4)为至少两根分别固定设置在钻爆船两侧,横缆(4)另一端锚固与岸相对固定;
在水下钻孔前先安放套管:在钻孔位置设置套管,所述套管分为管脚(1)和管身(2),所述管脚(1)下端加工成端面锯齿形,管脚(1)通过锯齿形端面与钻孔位置相对固定,固定后的套管为竖直安装;所述管身(2)上设置花管段(21),所述花管段(21)管壁上设置多个径向通孔(22),花管段(21)下端部距管脚(1)下端的距离大于等于1.8米。
水下钻孔:钻具通过套管下到钻孔位置,进行钻孔。
2.根据权利要求1所述的山区河流水下钻孔爆破施工方法,其特征在于:所述花管段(21)长度为1.5-2.5米。
3.根据权利要求2所述的山区河流水下钻孔爆破施工方法,其特征在于:所述主缆(3)为两根,以人字形结构分别锚固在两岸或一侧岸边;横缆(4)为四根,其中船艏两根、船艉两根分别锚固于两岸,布置横缆(4)时,先布置船艏两根横缆,后布置船艉两根横缆。。
4.根据权利要求3所述的山区河流水下钻孔爆破施工方法,其特征在于:所述管身(2)与管脚(1)之间以可拆分的方式固定连接。
5.根据权利要求4所述的山区河流水下钻孔爆破施工方法,其特征在于:所述跨过主航道一侧的主缆(3)或/和横缆(4)采用锚链沉入水底的方式锚固。
6.根据权利要求1至5任一权利要求所述的山区河流水下钻孔爆破施工方法,其特征在于:所述装药堵塞步骤中,包括测量孔深、装药、检查线路和炮孔堵塞步骤,在装药前将需装入的药柱用壁厚在0.2mm以下的塑料管进行外包装;在炮孔堵塞步骤中,首先在套管内插入内套管(5)。
7.根据权利要求6所述的山区河流水下钻孔爆破施工方法,其特征在于:套管底部采用提头钢缆牵引,用于抵抗水流作用力,提头钢缆上端固定在船艏设置的绞锚机上,通过绞锚机松紧提头钢缆来调整套管偏差。
8.根据权利要求7所述的山区河流水下钻孔爆破施工方法,其特征在于:在爆破网络连接步骤中,炮线捆扎在绳上,所述炮线长于绳,使炮线以松弛的状态捆扎在绳上;所述炮线连接在托线浮筒上,所述托线浮筒设置在爆破区上游20-50米处。
CN 200910104283 2009-07-08 2009-07-08 山区河流水下钻孔爆破施工方法 Active CN101608885B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910104283 CN101608885B (zh) 2009-07-08 2009-07-08 山区河流水下钻孔爆破施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910104283 CN101608885B (zh) 2009-07-08 2009-07-08 山区河流水下钻孔爆破施工方法

Publications (2)

Publication Number Publication Date
CN101608885A true CN101608885A (zh) 2009-12-23
CN101608885B CN101608885B (zh) 2013-03-20

Family

ID=41482723

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910104283 Active CN101608885B (zh) 2009-07-08 2009-07-08 山区河流水下钻孔爆破施工方法

Country Status (1)

Country Link
CN (1) CN101608885B (zh)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102086754A (zh) * 2010-12-31 2011-06-08 中铁港航工程局有限公司 一种深水钻孔方法
CN102155889A (zh) * 2010-12-31 2011-08-17 中铁港航工程局有限公司 一种深水深孔水下起爆网路的贴身防护方法
CN103148750A (zh) * 2013-03-22 2013-06-12 武汉爆破有限公司 一种用于模拟战场的水下微差爆破网路
CN103822553A (zh) * 2014-02-27 2014-05-28 中国水利水电第六工程局有限公司 一种用于水下岩塞爆破的预裂孔钻孔装药方法
CN103900428A (zh) * 2014-03-31 2014-07-02 中国水利水电第六工程局有限公司 一种用于水下淤泥层扰动爆破的钻孔装药方法
CN104748632A (zh) * 2015-04-03 2015-07-01 核工业井巷建设公司 一种水下岩塞爆破施工方法
CN105370208A (zh) * 2015-10-29 2016-03-02 广东宏大广航工程有限公司 一种水下钻爆船及其钻孔施工方法
CN105737696A (zh) * 2014-12-10 2016-07-06 庄静波 一种河道爆破方法
CN105737698A (zh) * 2016-03-22 2016-07-06 中铁隧道集团二处有限公司 一种适用于桥底水下混凝土构筑物拆除的钻孔爆破方法
CN106288996A (zh) * 2016-08-24 2017-01-04 广西新港湾工程有限公司 一种水下沟槽预裂爆破施工方法
CN107726935A (zh) * 2017-10-13 2018-02-23 中国建筑土木建设有限公司 大角度斜面坚硬岩层的桩基施工方法
CN109654966A (zh) * 2018-12-21 2019-04-19 四川港航建设工程有限公司 河航道整治生态炸礁疏浚体系及施工方法
CN110736400A (zh) * 2019-10-22 2020-01-31 长江重庆航道工程局 一种考虑岩石内部构造的水下钻孔爆破振速计算方法
CN111472776A (zh) * 2020-04-09 2020-07-31 方莹 一种气体致裂管的水下膨胀裂岩施工工艺
CN113218264A (zh) * 2021-06-02 2021-08-06 广西新港湾工程有限公司 一种水运工程网路安全施工方法
CN115369888A (zh) * 2022-08-31 2022-11-22 中交一公局集团有限公司 一种深水裸岩基坑成型方法
CN116123952A (zh) * 2023-03-03 2023-05-16 中铁四局集团第二工程有限公司 嵌入式设置沉井深水基础水下爆破施工方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0281722A1 (en) * 1987-03-10 1988-09-14 Nobel Kemi AB A blasting system for underwater use
CN1556366A (zh) * 2003-12-31 2004-12-22 大连理工大学 提高条形炸药爆破能量利用率的爆破方法
CN1776348A (zh) * 2005-11-22 2006-05-24 裘尧云 水下炸礁的方法及专用工具
CN1884962B (zh) * 2006-07-04 2010-11-17 裘尧云 水下复杂地质礁岩炸礁的方法
CN1920472A (zh) * 2006-09-28 2007-02-28 郑炳旭 水下爆破聚能弹及水下布设方法

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102086754A (zh) * 2010-12-31 2011-06-08 中铁港航工程局有限公司 一种深水钻孔方法
CN102155889A (zh) * 2010-12-31 2011-08-17 中铁港航工程局有限公司 一种深水深孔水下起爆网路的贴身防护方法
CN102086754B (zh) * 2010-12-31 2013-07-31 中铁港航工程局有限公司 一种深水钻孔方法
CN103148750A (zh) * 2013-03-22 2013-06-12 武汉爆破有限公司 一种用于模拟战场的水下微差爆破网路
CN103822553A (zh) * 2014-02-27 2014-05-28 中国水利水电第六工程局有限公司 一种用于水下岩塞爆破的预裂孔钻孔装药方法
CN103900428A (zh) * 2014-03-31 2014-07-02 中国水利水电第六工程局有限公司 一种用于水下淤泥层扰动爆破的钻孔装药方法
CN103900428B (zh) * 2014-03-31 2015-08-05 中国水利水电第六工程局有限公司 一种用于水下淤泥层扰动爆破的钻孔装药方法
CN105737696A (zh) * 2014-12-10 2016-07-06 庄静波 一种河道爆破方法
CN104748632A (zh) * 2015-04-03 2015-07-01 核工业井巷建设公司 一种水下岩塞爆破施工方法
CN104748632B (zh) * 2015-04-03 2016-05-04 核工业井巷建设公司 一种水下岩塞爆破施工方法
CN105370208A (zh) * 2015-10-29 2016-03-02 广东宏大广航工程有限公司 一种水下钻爆船及其钻孔施工方法
CN105737698A (zh) * 2016-03-22 2016-07-06 中铁隧道集团二处有限公司 一种适用于桥底水下混凝土构筑物拆除的钻孔爆破方法
CN106288996A (zh) * 2016-08-24 2017-01-04 广西新港湾工程有限公司 一种水下沟槽预裂爆破施工方法
CN106288996B (zh) * 2016-08-24 2018-05-25 广西新港湾工程有限公司 一种水下沟槽预裂爆破施工方法
CN107726935A (zh) * 2017-10-13 2018-02-23 中国建筑土木建设有限公司 大角度斜面坚硬岩层的桩基施工方法
CN107726935B (zh) * 2017-10-13 2021-02-12 中国建筑土木建设有限公司 大角度斜面坚硬岩层的桩基施工方法
CN109654966A (zh) * 2018-12-21 2019-04-19 四川港航建设工程有限公司 河航道整治生态炸礁疏浚体系及施工方法
CN109654966B (zh) * 2018-12-21 2021-03-09 四川港航建设工程有限公司 河航道整治生态炸礁疏浚体系及施工方法
CN110736400A (zh) * 2019-10-22 2020-01-31 长江重庆航道工程局 一种考虑岩石内部构造的水下钻孔爆破振速计算方法
CN110736400B (zh) * 2019-10-22 2022-09-13 长江重庆航道工程局 一种考虑岩石内部构造的水下钻孔爆破振速计算方法
CN111472776A (zh) * 2020-04-09 2020-07-31 方莹 一种气体致裂管的水下膨胀裂岩施工工艺
CN113218264A (zh) * 2021-06-02 2021-08-06 广西新港湾工程有限公司 一种水运工程网路安全施工方法
CN115369888A (zh) * 2022-08-31 2022-11-22 中交一公局集团有限公司 一种深水裸岩基坑成型方法
CN116123952A (zh) * 2023-03-03 2023-05-16 中铁四局集团第二工程有限公司 嵌入式设置沉井深水基础水下爆破施工方法
CN116123952B (zh) * 2023-03-03 2023-07-18 中铁四局集团第二工程有限公司 嵌入式设置沉井深水基础水下爆破施工方法

Also Published As

Publication number Publication date
CN101608885B (zh) 2013-03-20

Similar Documents

Publication Publication Date Title
CN101608885B (zh) 山区河流水下钻孔爆破施工方法
Nilsen et al. Stability and water leakage of hard rock subsea tunnels
CN102953341B (zh) 一种设置于深水急流无覆盖层陡峭裸岩上的高位栈桥结构
CN107356168B (zh) 一种深水倾斜裸岩基础水下爆破施工方法
CN102966111B (zh) 一种在深水急流无覆盖层陡峭裸岩上的钢管桩锚固施工方法
CN106839907B (zh) 水下爆破施工方法
CN109654966B (zh) 河航道整治生态炸礁疏浚体系及施工方法
CN102979039B (zh) 一种在深水急流无覆盖层陡峭裸岩上的高位栈桥施工方法
CN109098661B (zh) 水电站河谷的双向成对跨江大顶角斜孔钻探方法
CN102809328B (zh) 一种水下石方数码电子雷管精确控制爆破方法
CN105370208A (zh) 一种水下钻爆船及其钻孔施工方法
CN105735210B (zh) 隧洞式仿自然鱼道结合鱼闸的布置结构及其使用方法
CN102518470A (zh) 环形截水巷处理冻结管防治水方法
CN107130918A (zh) 大坝帷幕灌浆冲击造孔施工方法
CN106351241A (zh) 紧临既有线大跨度连续梁深水基础施工方法
CN110924864A (zh) 海上输水管道定向钻牵引施工方法
CN113585346A (zh) 近海内河交汇区的沉管基槽处理工艺及沉管安装工艺
Lu et al. Norwegian experience in subsea tunnelling.
CN110823027A (zh) 一种堤防的防洪爆破扒口结构及其设置方法
Palmstrøm et al. New milestones in subsea blasting at water depth of 55m
CN114991668A (zh) 开发井浅层气钻井表层开路钻井的施工装置及其施工方法
TW201544660A (zh) 深層海洋水引水方法及引水隧道系統
CN106120802A (zh) 紧临既有线大跨度连续梁深水基础水下基坑开挖施工方法
CN102979090A (zh) 一种在深水急流无覆盖层陡峭裸岩上固定钢护筒的施工方法
Halvorsen et al. Design of unlined headrace tunnel with 846 m head at Lower Kihansi, Tanzania. Filling Experience

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant