CN103900428A - 一种用于水下淤泥层扰动爆破的钻孔装药方法 - Google Patents
一种用于水下淤泥层扰动爆破的钻孔装药方法 Download PDFInfo
- Publication number
- CN103900428A CN103900428A CN201410123634.6A CN201410123634A CN103900428A CN 103900428 A CN103900428 A CN 103900428A CN 201410123634 A CN201410123634 A CN 201410123634A CN 103900428 A CN103900428 A CN 103900428A
- Authority
- CN
- China
- Prior art keywords
- hole
- powder
- charge
- powder stick
- borehole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Earth Drilling (AREA)
Abstract
一种用于水下淤泥层扰动爆破的钻孔装药方法,其步骤为:(1)搭设并固定钻孔平台;(2)安装定位导向管;(3)在定位导向管内下入钢套管;(4)进行淤泥层的钻进;(5)钻进至基岩;(6)清孔并在孔内下放装药套管;(7)试装药;(8)装药并标识;(9)按顺序将药卷分段固定在装药半管上;(10)将药卷逐段放入孔底;(11)检查药卷数量,确定装药位置;(12)做好导爆索、导爆管标识和固定;(13)封堵。本发明能确保淤泥孔的钻孔质量、精度以及精准地装药到位,方便过程中的质量检查和控制,保证淤泥孔的扰动爆破效果,直接利用水下淤泥孔周边的水体作为封堵材料对药卷上部剩余的水下淤泥孔的空间进行封堵,不需加工制作,成本低廉,封堵严密,保证封堵质量。
Description
技术领域
本发明涉及一种钻孔装药方法,尤其涉及一种水下淤泥层扰动爆破的钻孔装药方法。
背景技术
位于水库区水面以下深水中的淤泥扰动爆破炮孔一般钻孔装药难度大,钻孔精度不宜控制,其质量好坏直接关系到淤泥扰动爆破效果。目前多采用干地挖孔装药爆破或水下用跟管钻机边钻孔边下钢套管,然后在套管内直接装药爆破的方法,在施工时没有采用定位导向管,偏斜率难于控制在0.2%以内。在套管内直接装药爆破,损失钢套管,费用较高,可靠度较低,装药多采用直接下放或绑在竹片上下放,药卷一般不分段,对于较深的爆破孔,因药卷较长难以顺利完成装药,导致装药质量下降。封堵的现行工艺一般采用黄泥和砂子混合物或砂子、岩粉进行封堵,需要单独加工制作,而且爆破孔位于水下时,封堵材料经水浸泡后,封堵作用下降,达不到预期的效果,过程中质量检查和控制比较困难,尤其对是厚层深淤泥孔的扰动爆破,很难保证装药到位,从而影响爆破效果。
发明内容
针对上述不足或问题,本发明提供了一种水下淤泥层扰动爆破的钻孔装药技术,较好地解决了水下淤泥孔钻孔装药问题。
解决上述问题所采取的技术措施是:
一种用于水下淤泥层扰动爆破的钻孔装药方法,其特征在于:
(1)搭设并固定钻孔平台:钻孔前在水平上搭设钻孔平台,并固定牢靠;
(2)安装定位导向管:测量放线后,安装定位导向管;
(3)在定位导向管内下入钢套管:利用定位导向管,在定位导向管内垂直下入钢套管,使其插入库底淤淤积层相对较稳定处,固定钢套管,管口处安装管夹子,套管间采用丝扣连接,连接处采用焊接钢筋条的方法防止丝扣脱扣,并用钢丝绳将套管串连在一起;
(4)进行淤泥层的钻进:采用地质钻机,采用归心钻进或常规牙轮钻进工艺进行淤泥层的钻进;
(5)钻进至基岩:钻到基岩面后,换金刚石钻头,采用长钻具、低轴压、慢转速、小泵量等钻进工艺,钻进至基岩以下0.5m;
(6)清孔并在孔内下放装药套管:采用高压风水对于钻孔要进行清孔处理,然后在孔内下放PPR装药套管,下放到位固定好后,依次取出钢套管、定位导向管;
(7)试装药:采用与药卷相似的沙袋进行试孔,然后选择的一个代表性的淤泥孔进行试装药;
(8)装药并标识:按照各淤泥孔的装药组合依次装药,将每个待装药孔加工好的分段药放在孔的附近平台上,并进行标识;
(9)按顺序将药卷分段固定在装药半管上:装药时,按照先装底药,再依次装底部药卷、下部起爆体药包、中部药包、上部起爆体、上部药卷的顺序,将药卷分段固定在用PPR管制成的装药半管上,并采用马蹄扣系紧导爆索,药卷分段长度为1.5~2.0m;
(10)将药卷逐段放入孔底:采用吊绳方法缓慢将药卷逐段放入孔底,随放随将吊绳与药卷、装药半管用胶布缠紧固定,当每段药卷下放至露出水面剩50cm左右时,接好下一段药卷,并绑好导爆管、导爆索、吊绳,再缓慢下放,直至放入全部药卷;
(11)检查药卷数量,确定装药位置:药卷下放过程中,设专人记录检查放入的药卷数量,用吊锤法检查药包长度,确定装药位置,并进行记录;
(12)做好导爆索、导爆管标识和固定:各个淤泥孔内引出的导爆索、导爆管均应做好标识,用胶布将外露的导爆索、导爆管固定在外露的PPR管管口上,并注意端头的防水;
(13)封堵:直接利用水下淤泥孔周边的水体作为封堵材料对药卷上部剩余的水下淤泥孔的空间进行封堵,封堵高程与水位高程相同。
本发明的有益效果:本发明较好地解决了水下淤泥孔钻孔装药问题,能够确保每个淤泥孔的钻孔质量、精度,以及精准地装药到位,并方便过程中的质量检查和控制,从而保证了淤泥孔的扰动爆破效果。采用高压风水对钻孔进行清孔处理,在孔内下放装药套管,节省了材料,降低了成本;采用分段装药,可将较深的爆破孔分成若干装药单元,使深孔装药变得简单、方便,便于操作,能够充分保证装药质量;直接利用水下淤泥孔周边的水体作为封堵材料对药卷上部剩余的水下淤泥孔的空间进行封堵,封堵高程与水位高程相同,不需要进行任何加工制作,成本低廉,且封堵严密,能够充分保证封堵质量。
具体实施方式
下面结合实施例对本发明做详细描述。
一种用于水下淤泥层扰动爆破的钻孔装药方法,其具体步骤是:
(1)搭设并固定钻孔平台:钻孔前在水平上搭设钻孔平台,并固定牢靠,确保平台不受水流、风浪、水位升降而产生摆动或位移;
(2)安装定位导向管:测量放线后,安装长度为8~12m的定位导向管,定位导向管与钻孔平台通过法兰联接,利用高精度测斜仪及角度调整机构保证定位导向管处于铅直状态,偏斜率控制在0.2%以内;
(3)在定位导向管内下入钢套管:利用定位导向管,在定位导向管内垂直下入钢套管,钢套管用卷扬悬吊起来后,通过定位导向管缓慢下放,当管底部距库底淤积层上面0.2-0.5m后,调整钢套管使其呈垂直状态后迅速下放,使其插入库底淤积层中,当钢套管在淤积层下降缓慢时,利用钻机卷扬反复上下起放钢套管,靠冲击力使其下入淤积层相对较稳定处,利用高精度测斜仪在管中部及底部测量钢套管的偏斜和弯曲情况,垂直度满足技术要求后,固定钢套管,不满足技术要求则拔出钢套管重新下入,管口处安装管夹子,套管间采用丝扣连接,连接处采用焊接钢筋条的方法防止丝扣脱扣,并用φ13-15的钢丝绳将套管串连在一起,以防套管脱落;
(4)进行淤泥层的钻进:采用地质钻机,采用归心钻进或常规牙轮钻进工艺进行淤泥层的钻进,钻进过程中采用高精度陀螺测斜仪随时进行钢套管、孔底顶角和方位角的多点测斜,控制淤泥孔的孔斜不大于1%;
(5)钻进至基岩:钻到基岩面后,换金刚石钻头,采用长钻具、低轴压、慢转速、小泵量等钻进工艺,钻进至基岩以下0.5m;
(6)清孔并在孔内下放装药套管:采用高压风水对于钻孔要进行清孔处理,然后在孔内下放厚度为11.4mm的PPR装药套管,下放到位固定好后,依次取出钢套管、定位导向管,节省材料,降低成本;
(7)试装药:采用与药卷相似的沙袋进行试孔,探其孔内是否有杂物,并测量其孔深,当确定孔内无杂物后,选择的一个代表性的淤泥孔进行试装药,检验装药工艺是否满足要求,然后再正式进行装药;
(8)装药并标识:按照各淤泥孔的装药组合依次装药,将每个待装药孔加工好的分段药放在孔的附近平台上,并进行标识,注明药卷的对应孔号并在装药半管上标注清楚,检查药卷数量、规格、导爆管的安装位置等是否满足要求;
(9)按顺序将药卷分段固定在装药半管上:装药时,按照先装底药,再依次装底部药卷、下部起爆体药包、中部药包、上部起爆体、上部药卷的顺序,将药卷分段固定在用50mmPPR管制成的装药半管上,并采用马蹄扣系紧导爆索,药卷分段长度为1.5~2.0m;
(10)将药卷逐段放入孔底:采用吊绳方法缓慢将药卷逐段放入孔底,随放随将吊绳与药卷、装药半管用胶布缠紧固定,并注意不得与导爆管、导爆索缠绕或交叉,以防吊绳用力时损坏导爆管、导爆索,根据下放药卷的情况,当每段药卷下放至露出水面剩50cm左右时,接好下一段药卷,并绑好导爆管、导爆索、吊绳,再缓慢下放,直至放入全部药卷;采用分段装药,可将较深的爆破孔分成若干装药单元,使深孔装药变得简单、方便,便于操作,能够充分保证装药质量;
(11)检查药卷数量,确定装药位置:药卷下放过程中,设专人记录检查放入的药卷数量,用吊锤法检查药包长度,确定装药位置,并进行记录;
(12)做好导爆索、导爆管标识和固定:各个淤泥孔内引出的导爆索、导爆管均应做好标识,用胶布将外露的导爆索、导爆管固定在外露的PPR管管口上,并注意端头的防水;
(13)封堵:直接利用水下淤泥孔周边的水体作为封堵材料对药卷上部剩余的水下淤泥孔的空间进行封堵,封堵高程与水位高程相同,不需要进行任何加工制作,成本低廉,且封堵严密,能够充分保证封堵质量。
Claims (1)
1.一种用于水下淤泥层扰动爆破的钻孔装药方法,其特征在于:
(1)搭设并固定钻孔平台:钻孔前在水平上搭设钻孔平台,并固定牢靠;
(2)安装定位导向管:测量放线后,安装定位导向管;
(3)在定位导向管内下入钢套管:利用定位导向管,在定位导向管内垂直下入钢套管,使其插入库底淤淤积层相对较稳定处,固定钢套管,管口处安装管夹子,套管间采用丝扣连接,连接处采用焊接钢筋条的方法防止丝扣脱扣,并用钢丝绳将套管串连在一起;
(4)进行淤泥层的钻进:采用地质钻机,采用归心钻进或常规牙轮钻进工艺进行淤泥层的钻进;
(5)钻进至基岩:钻到基岩面后,换金刚石钻头,采用长钻具、低轴压、慢转速、小泵量等钻进工艺,钻进至基岩以下0.5m;
(6)清孔并在孔内下放装药套管:采用高压风水对于钻孔要进行清孔处理,然后在孔内下放PPR装药套管,下放到位固定好后,依次取出钢套管、定位导向管;
(7)试装药:采用与药卷相似的沙袋进行试孔,然后选择的一个代表性的淤泥孔进行试装药;
(8)装药并标识:按照各淤泥孔的装药组合依次装药,将每个待装药孔加工好的分段药放在孔的附近平台上,并进行标识;
(9)按顺序将药卷分段固定在装药半管上:装药时,按照先装底药,再依次装底部药卷、下部起爆体药包、中部药包、上部起爆体、上部药卷的顺序,将药卷分段固定在用PPR管制成的装药半管上,并采用马蹄扣系紧导爆索,药卷分段长度为1.5~2.0m;
(10)将药卷逐段放入孔底:采用吊绳方法缓慢将药卷逐段放入孔底,随放随将吊绳与药卷、装药半管用胶布缠紧固定,当每段药卷下放至露出水面剩50cm左右时,接好下一段药卷,并绑好导爆管、导爆索、吊绳,再缓慢下放,直至放入全部药卷;
(11)检查药卷数量,确定装药位置:药卷下放过程中,设专人记录检查放入的药卷数量,用吊锤法检查药包长度,确定装药位置,并进行记录;
(12)做好导爆索、导爆管标识和固定:各个淤泥孔内引出的导爆索、导爆管均应做好标识,用胶布将外露的导爆索、导爆管固定在外露的PPR管管口上,并注意端头的防水;
(13)封堵:直接利用水下淤泥孔周边的水体作为封堵材料对药卷上部剩余的水下淤泥孔的空间进行封堵,封堵高程与水位高程相同。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410123634.6A CN103900428B (zh) | 2014-03-31 | 2014-03-31 | 一种用于水下淤泥层扰动爆破的钻孔装药方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410123634.6A CN103900428B (zh) | 2014-03-31 | 2014-03-31 | 一种用于水下淤泥层扰动爆破的钻孔装药方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103900428A true CN103900428A (zh) | 2014-07-02 |
CN103900428B CN103900428B (zh) | 2015-08-05 |
Family
ID=50991902
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410123634.6A Active CN103900428B (zh) | 2014-03-31 | 2014-03-31 | 一种用于水下淤泥层扰动爆破的钻孔装药方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103900428B (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104197797A (zh) * | 2014-08-29 | 2014-12-10 | 中国水利水电第六工程局有限公司 | 一种用于隧洞爆破开挖时有渗水爆破孔的装药装置 |
CN104964623A (zh) * | 2015-07-01 | 2015-10-07 | 叶建军 | 大面积或大体积混凝土预埋炮孔布置方式及拆除爆破方法 |
CN105370208A (zh) * | 2015-10-29 | 2016-03-02 | 广东宏大广航工程有限公司 | 一种水下钻爆船及其钻孔施工方法 |
CN105737696A (zh) * | 2014-12-10 | 2016-07-06 | 庄静波 | 一种河道爆破方法 |
CN111472776A (zh) * | 2020-04-09 | 2020-07-31 | 方莹 | 一种气体致裂管的水下膨胀裂岩施工工艺 |
CN111706257A (zh) * | 2020-03-31 | 2020-09-25 | 中铁大桥局集团第二工程有限公司 | 一种水下岩石钻孔爆破导向架装置及其施工方法 |
CN112432882A (zh) * | 2020-11-18 | 2021-03-02 | 华侨大学 | 一种近海水下高压稀释淤泥孔稳定角预测方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1996029567A1 (en) * | 1995-03-23 | 1996-09-26 | Bofors Liab Ab | Method and arrangement for supplying reinforcing charges to boreholes |
CN1776348A (zh) * | 2005-11-22 | 2006-05-24 | 裘尧云 | 水下炸礁的方法及专用工具 |
CN200944036Y (zh) * | 2006-07-04 | 2007-09-05 | 裘尧云 | 水下炸礁专用套管 |
CN101608885A (zh) * | 2009-07-08 | 2009-12-23 | 长江重庆航道工程局 | 山区河流水下钻孔爆破施工方法 |
WO2010144952A1 (en) * | 2009-06-15 | 2010-12-23 | Technological Resources Pty. Limited | Method and apparatus for charging explosives |
-
2014
- 2014-03-31 CN CN201410123634.6A patent/CN103900428B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO1996029567A1 (en) * | 1995-03-23 | 1996-09-26 | Bofors Liab Ab | Method and arrangement for supplying reinforcing charges to boreholes |
CN1776348A (zh) * | 2005-11-22 | 2006-05-24 | 裘尧云 | 水下炸礁的方法及专用工具 |
CN200944036Y (zh) * | 2006-07-04 | 2007-09-05 | 裘尧云 | 水下炸礁专用套管 |
WO2010144952A1 (en) * | 2009-06-15 | 2010-12-23 | Technological Resources Pty. Limited | Method and apparatus for charging explosives |
CN101608885A (zh) * | 2009-07-08 | 2009-12-23 | 长江重庆航道工程局 | 山区河流水下钻孔爆破施工方法 |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104197797A (zh) * | 2014-08-29 | 2014-12-10 | 中国水利水电第六工程局有限公司 | 一种用于隧洞爆破开挖时有渗水爆破孔的装药装置 |
CN105737696A (zh) * | 2014-12-10 | 2016-07-06 | 庄静波 | 一种河道爆破方法 |
CN104964623A (zh) * | 2015-07-01 | 2015-10-07 | 叶建军 | 大面积或大体积混凝土预埋炮孔布置方式及拆除爆破方法 |
CN105370208A (zh) * | 2015-10-29 | 2016-03-02 | 广东宏大广航工程有限公司 | 一种水下钻爆船及其钻孔施工方法 |
CN111706257A (zh) * | 2020-03-31 | 2020-09-25 | 中铁大桥局集团第二工程有限公司 | 一种水下岩石钻孔爆破导向架装置及其施工方法 |
CN111472776A (zh) * | 2020-04-09 | 2020-07-31 | 方莹 | 一种气体致裂管的水下膨胀裂岩施工工艺 |
CN112432882A (zh) * | 2020-11-18 | 2021-03-02 | 华侨大学 | 一种近海水下高压稀释淤泥孔稳定角预测方法 |
Also Published As
Publication number | Publication date |
---|---|
CN103900428B (zh) | 2015-08-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103900428B (zh) | 一种用于水下淤泥层扰动爆破的钻孔装药方法 | |
CN102287195B (zh) | 浅埋暗挖大跨度隧道下穿既有高速铁路施工方法 | |
CN105422078B (zh) | 围岩采动破坏范围分段测试方法 | |
CN104329076B (zh) | 一种测斜孔渗压计装置及安装方法 | |
CN103075149B (zh) | 下行超深钻孔快速测定煤层瓦斯压力的方法及其装置 | |
CN100434653C (zh) | 煤层气井爆破式洞穴完井工艺方法 | |
CN102966111B (zh) | 一种在深水急流无覆盖层陡峭裸岩上的钢管桩锚固施工方法 | |
CN107975375B (zh) | 一种城市隧道微型钢管桩加固软弱地基施工方法 | |
CN103334770A (zh) | 一种长大反坡隧道超高水压富水破碎带施工方法 | |
CN109252868A (zh) | 软硬不均地层盾构施工孤石及基岩凸起处理方法 | |
CN103835651A (zh) | 一种单孔定向钻进局部注浆反井钻井工艺 | |
CN112031017A (zh) | 一种适用于裸岩地质条件下深水桩基钢护筒施工方法 | |
CN107246007B (zh) | 一种cfg桩的施工方法 | |
CN103835648A (zh) | 一种通过地面注浆改善岩层性能反井钻井工艺 | |
CN101793153A (zh) | 盾构近距离穿越大口径管线的施工方法 | |
CN109763483A (zh) | 一种厚第四系深埋采空塌陷破碎地层上行式分段注浆工艺 | |
CN106595548A (zh) | 一种隧道内掌子面围岩内部的位移测量方法 | |
CN105696550A (zh) | 一种辅助加固地下连续墙成槽的三轴搅拌桩施工方法 | |
CN109736779A (zh) | 一种本煤层水力致裂的压裂半径测量方法 | |
CN104389563A (zh) | 一种非金属连续油管两层分注工艺管柱装置 | |
CN109162635A (zh) | 一种新的测压钻孔施工工艺 | |
CN105823546B (zh) | 一种大直径冻结立井爆破振动监测、减振方法及系统 | |
CN110672062A (zh) | 一种监测基岩沉降量监测点的埋设方法 | |
US10392885B2 (en) | Method and apparatus for plugging a well | |
CN102777169A (zh) | 瓦斯压力俯角测量方法及系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |