CN101581087B - 高面板堆石坝坝体填筑时空预沉降控制法 - Google Patents

高面板堆石坝坝体填筑时空预沉降控制法 Download PDF

Info

Publication number
CN101581087B
CN101581087B CN2009100626851A CN200910062685A CN101581087B CN 101581087 B CN101581087 B CN 101581087B CN 2009100626851 A CN2009100626851 A CN 2009100626851A CN 200910062685 A CN200910062685 A CN 200910062685A CN 101581087 B CN101581087 B CN 101581087B
Authority
CN
China
Prior art keywords
dam
dam body
stage
deformation
rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009100626851A
Other languages
English (en)
Other versions
CN101581087A (zh
Inventor
周厚贵
邓银启
王章忠
王亚文
曹生荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gezhouba Dam Xinjiang Engineering Bureau (limited)
China Gezhouba Group No 3 Engineering Co Ltd
Original Assignee
GEZHOUBA CONSTRUCTION ENGINEERING Co Ltd
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GEZHOUBA CONSTRUCTION ENGINEERING Co Ltd, China Gezhouba Group Co Ltd filed Critical GEZHOUBA CONSTRUCTION ENGINEERING Co Ltd
Priority to CN2009100626851A priority Critical patent/CN101581087B/zh
Publication of CN101581087A publication Critical patent/CN101581087A/zh
Application granted granted Critical
Publication of CN101581087B publication Critical patent/CN101581087B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本发明公开了一种高面板堆石坝坝体填筑时空预沉降控制法,在堆石坝体一、二期填筑之间间隔近5个月,给一期堆石坝体一定的沉降期;在二期堆石坝体填筑完成后,才进行混凝土一期面板的施工,同时以后区超高前区的空间控制方式进行三期反台填筑;三至五期之间采取连续高强度填筑方式将堆石体填筑至防浪墙平台高程;五、六期堆石坝体之间间隔近20个月,才将堆石坝体填筑到坝顶设计高程,完成超高堆石坝施工,间隔期间进行二期混凝土面板浇筑,待堆石坝体填筑到坝顶设计高程后,再进行三期混凝土面板施工和防浪墙施工。

Description

高面板堆石坝坝体填筑时空预沉降控制法 
技术领域
本发明涉及一种坝体填筑施工领域,特别是一种高面板堆石坝坝体填筑时空预沉降控制法。 
背景技术
一般的堆石坝的施工工艺,较为追求施工进度,以施工工序复杂的前区为主,基于坝体运行水荷载从坝体上游堆石体向坝体下游堆石坝传递,坝体堆石体干密度呈现从坝体上游区向坝体下游区逐步增大、孔隙率呈现从坝体上游区向坝体下游区逐步减小的趋势,坝体下游区沉降变形空间大于坝体上游区,这样就使坝体上下游堆石体的总体沉降规律不一致,导致坝体堆石体产生不均衡沉降变形,对坝体混凝土面板运行产生不利的影响,甚至导致混凝土面板产生裂缝,对蓄水期的堆石坝体安全运行产生不安全影响。 
发明内容
本发明所要解决的技术问题是提供一种高面板堆石坝坝体填筑时空预沉降控制法,可以增加坝体运行安全,减少坝体不均匀沉降变形对混凝土面板等防渗结构产生的不良影响。 
为解决上述技术问题,本发明所采用的技术方案是:一种高面板堆石坝坝体填筑时空预沉降控制法,包括以下步骤: 
1)一方面,从时间上给高堆石坝体的沉降变形提供通道,通过分期间歇填筑,在施工期给堆石坝体预留出足够的沉降变形时间,待堆石坝体完成一定的沉降变形后才开始面板混凝土施工,减少因堆石体变形对面板混凝土的影响; 
2)另一方面,从空间上根据堆石体加荷后会产生瞬间变形以及堆石体干密度从坝体下游区向上游区逐步增大、孔隙率从下游区向上游区逐步减小的趋势,下游区沉降变形空间远大于上游区的特点,在坝体分期填筑中,通过堆石体填筑空间形状的控制,在堆石坝体下游区实施超上游区的连续均衡高强度反台填筑,在施工期充分加大堆石坝体下游区的沉降变形,为控制堆石坝体上、下游区的不均匀沉降变形,从填筑的空间形状上提供通道。 
基于上述分期间歇和反台填筑方法,通过连续均衡高强度填筑碾压,在施工期就加大堆石体的ε0瞬时变形和ε(t)延时变形,时空两方面控制超高堆石坝体不均匀沉降变形。 
反台填筑方法,是使坝体横断面上的下游区超高于上游区,这种填筑方式改变了传统的前高后低填筑方式,经过坝体实际沉降证明,这种填筑方式有效的改善了坝体不均匀变形。通过理论上的非线性有限元的计算比较,新的填筑施工方法改善了坝体蓄水期的位移分布,使上游坝坡最大水平位移从100cm降至50cm(上游坡中部),沿坝坡水平分布比较均匀,这种位移分布情况,减小了堆石料和垫层料中产生的差异变形,对改善面板的支撑条件起到较大作用。 
本发明提供的一种高面板堆石坝坝体填筑时空预沉降控制法,根据堆石体变形规律:ε=ε0+ε(t),其中ε0为瞬时变形,ε(t)为随时间增长的变形。根据堆石体变形既有填筑加载瞬间变形ε0,又是时间的函数ε(t)的特点,就从时间和空间两方面控制堆石坝体的沉降变形,在施工期通过合理的填筑分期间隔和坝体的填筑空间形状,尽可能加大堆石坝体在施工期的沉降变形,减少将来坝体运行期的不均匀变形,待堆石坝体沉降变形达到一定程度后,才进行坝体混凝土面板浇筑,将堆石坝体在运行期的变形控制在混凝土面板能承受的范围内,避免了凝土面板裂隙的产生,保障了高面板堆石坝体的安全稳定运行。 
附图说明
下面结合附图和实施例对本发明作进一步说明。 
图1是本发明的分期填筑及面板施工进展图。 
具体实施方式
在高面板堆石坝坝体填筑施工中,一方面,从时间上给高堆石坝体的沉降变形提供通道,通过分期间歇填筑,在施工期给堆石坝体预留出足够的沉降变形时间,待堆石坝体有了一定的沉降变形后才开始面板混凝土施工,减少因堆石体变形对面板混凝土的影响; 
另一方面,从空间上根据堆石体加荷后会产生瞬间变形以及堆石体干密度从坝体下游区向上游区逐步增大、孔隙率从下游区向上游区存在逐步减小的趋势,下游区沉降变形空间远大于上游区的特点,在坝体分期填筑中,通过堆石体填筑空间形状的控制,在堆石坝体下游区实施超上游区的连续均衡高强度反台填筑,在施工期充分加大堆石坝体下游区的沉降变形,为控制堆石坝体上、下游区的不均匀沉降变形,从填筑的空间形状上提供通道。基于上述合理的分期间歇和科学的反台填筑方式,通过连续均衡高强度填筑碾压,在施工期就加大堆石体的ε0瞬时变形和ε(t)延时变形,从时空两方面控制超高堆石坝体不均匀沉降变形,为混凝土面板施工提供合适的时机,将堆石坝体在运行期的变形控制在混凝 土面板能承受的范围内,这就为控制高堆石坝体的安全稳定运行提供了技术保障。 
实施案例: 
表1高堆石坝体时空预沉降控制法填筑分期及间歇表 
Figure G2009100626851D00031
高面板堆石坝坝体填筑时空预沉降控制法的主要施工步骤,如图1和表1所示: 
在图1中,标记2为上游,标记10为下游。总体上,将坝体填筑分六期进行,即 
Figure G2009100626851D00032
Figure G2009100626851D00033
的一期施工区9、 的二期正台填筑施工区8、 
Figure G2009100626851D00035
的三期反台填筑施工区7、 
Figure G2009100626851D00036
的四期施工区6、 
Figure G2009100626851D00037
的五期施工区5和六期施工区11;将混凝土面板施工分三期进行,即一期面板1、二期面板3和三期面板4。 
在堆石坝体一、二期之间间隔近5个月,三至五期堆石坝体填筑之间采取连续高强度施工,五、六期堆石坝体填筑之间间隔近20个月之后,才将堆石坝体填筑到坝顶高程。具体过程是:在堆石坝体一期施工区9、二期正台填筑施工区8之间间隔近5个月,给一期堆石坝体长达12个月的沉降期,这种沉降变形已经包括了全部的ε0瞬时变形和绝大部分的ε(t)延时变形;在二期堆石坝体填筑完成后,才进行混凝土一期面板1的施工,这样就保证了面板施工后堆石坝体的继续沉降变形在混凝土面板的可承受范围之内,不会因沉降变形而引起裂缝。沉降时间根据当地地质情况经过精密测算和多次实验,在保证施工安全和质量的同时,又不会过度延长工期。 
同时以下游区高度超过上游区高度的空间形状控制方式进行三期反台填筑;三至五期 之间采取连续高强度填筑方式将堆石坝体填筑至防浪墙平台高程,五、六期填筑之间间歇近20个月,这样保证了堆石坝体整体的均匀沉降,在间隔期间进行二期混凝土面板浇筑,然后将堆石坝体填筑到坝顶设计高程,再进行三期混凝土面板施工和防浪墙施工,完成高堆石坝坝体填筑施工。 

Claims (1)

1.一种高面板堆石坝坝体填筑时空预沉降控制法,其特征在于:
1)一方面,从时间上给高堆石坝体的沉降变形提供通道,通过分期间歇填筑,在施工期给堆石坝体预留出足够的沉降变形时间,待堆石坝体完成一定的沉降变形后才开始面板混凝土施工,减少因堆石体变形对面板混凝土的影响;
2)另一方面,从空间上根据堆石体加荷后会产生瞬间变形以及堆石体干密度从坝体上游区向下游区逐步增大、孔隙率从上游区向下游区逐步减小的趋势,下游区沉降变形空间远大于上游区的特点,在坝体分期填筑中,通过堆石体填筑空间形状的控制,在堆石坝体下游区实施超上游区的连续均衡高强度反台填筑,在施工期充分加大堆石坝体下游区的沉降变形,为堆石坝体上、下游区的不均匀沉降变形控制,从填筑的空间形状上提供通道;
基于上述分期间歇和反台填筑方式,通过连续均衡高强度填筑碾压,在施工期就加大堆石体的ε0瞬时变形和ε(t)延时变形,时空两方面控制超高堆石坝体不均匀沉降变形。
CN2009100626851A 2009-06-13 2009-06-13 高面板堆石坝坝体填筑时空预沉降控制法 Active CN101581087B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100626851A CN101581087B (zh) 2009-06-13 2009-06-13 高面板堆石坝坝体填筑时空预沉降控制法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100626851A CN101581087B (zh) 2009-06-13 2009-06-13 高面板堆石坝坝体填筑时空预沉降控制法

Publications (2)

Publication Number Publication Date
CN101581087A CN101581087A (zh) 2009-11-18
CN101581087B true CN101581087B (zh) 2011-01-19

Family

ID=41363391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100626851A Active CN101581087B (zh) 2009-06-13 2009-06-13 高面板堆石坝坝体填筑时空预沉降控制法

Country Status (1)

Country Link
CN (1) CN101581087B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359784A (zh) * 2020-11-17 2021-02-12 中国电建集团成都勘测设计研究院有限公司 一种高土心墙坝岸边接触粘土空间差异设置型式
CN114481766B (zh) * 2021-12-28 2023-04-28 中交一航局第三工程有限公司 一种水稳基层钢线法施工控制方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1773022A (zh) * 2005-11-05 2006-05-17 陶钧炳 软基快速筑堤方法与技术

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1773022A (zh) * 2005-11-05 2006-05-17 陶钧炳 软基快速筑堤方法与技术

Also Published As

Publication number Publication date
CN101581087A (zh) 2009-11-18

Similar Documents

Publication Publication Date Title
CN105297685B (zh) 一种基座混凝土面板堆石坝及其施工方法
CN203546678U (zh) 一种沥青混凝土心墙堆石坝结构
CN104652371B (zh) 以旧坝为基础建立的过水胶凝堆石坝及其施工方法
CN202989867U (zh) 一种废旧轮胎护面组合式钢结构谷坊
CN205382466U (zh) 一种混凝土面板堆石坝
CN101476309A (zh) 超高混凝土面板堆石坝坝体预压反台填筑施工方法
CN101581087B (zh) 高面板堆石坝坝体填筑时空预沉降控制法
CN104131530A (zh) 一种急流软基恶劣环境下堤防护岸结构
CN202090324U (zh) 一种新型过水围堰
CN205917662U (zh) 一种防开裂混凝土面板堆石坝
CN203742622U (zh) 一种构建承载结构的防渗组件
CN102900092B (zh) 深厚覆盖层上修建面板堆石坝的人工复合地基及施工方法
CN107761668A (zh) 一种滨海滨库造地型护岸结构及其建筑方法
CN107165151A (zh) 一种水电站工程中沉降差的控制方法
CN106192909A (zh) 一种降低面板应力应变水平的面板堆石坝和方法
CN206015619U (zh) 一种降低面板应力应变水平的面板堆石坝
CN205369167U (zh) 水中抛填砂砾石料低坝坝体
CN105369786B (zh) 导流隧洞改建生态放水洞的弧形闸门闸室结构及布置方法
CN103485312B (zh) 一种碾压混凝土坝与河床建基面衔接的施工工艺
CN205617317U (zh) 沥青混凝土心墙与混凝土基座的连接结构
CN110158547A (zh) 一种胶凝砂砾石支墩坝
CN104631425B (zh) 一种加快粉煤灰排渗固结的方法
CN202730719U (zh) 一种堆石坝量水堰
CN204570611U (zh) 一种防治发电厂房尾水渠基础不均匀沉降的结构
CN204343268U (zh) 一种底板平滑过渡的消力池结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GEZHOUBA XINJIANG ENGINEERING BUREAU CO., LTD.

Free format text: FORMER OWNER: CHINA GEZHOUBA GROUP CO., LTD.;SANXIA UNIVERSITY

Effective date: 20110509

Free format text: FORMER OWNER: GEZHOUBA CONSTRUCTION ENGINEERING CO., LTD.

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 443002 NO. 1, QINGBO ROAD, YICHANG CITY, HUBEI PROVINCE TO: 830049 NO. 918,XINHUA SOUTH ROAD, URUMQI CITY, XINJIANG UYGHUR AUTONOMOUS REGION

TR01 Transfer of patent right

Effective date of registration: 20110509

Address after: 830049 No. 918 Xinhua South Road, the Xinjiang Uygur Autonomous Region, Urumqi

Patentee after: Gezhouba Dam Xinjiang Engineering Bureau (limited)

Address before: 443002 Hubei province Yichang City Road No. 1

Co-patentee before: Gezhouba Construction Engineering Co., Ltd.

Patentee before: China Gezhouba Group Co., Ltd.

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160525

Address after: 710000 Shaanxi province Xi'an Chanba Ecological District Su Shaanxi international financial center building A

Patentee after: CHINA GEZHOUBA GROUP NO.3 ENGINEERING CO., LTD.

Patentee after: Gezhouba Dam Xinjiang Engineering Bureau (limited)

Address before: 830049 No. 918 Xinhua South Road, the Xinjiang Uygur Autonomous Region, Urumqi

Patentee before: Gezhouba Dam Xinjiang Engineering Bureau (limited)