CN101476309A - 超高混凝土面板堆石坝坝体预压反台填筑施工方法 - Google Patents

超高混凝土面板堆石坝坝体预压反台填筑施工方法 Download PDF

Info

Publication number
CN101476309A
CN101476309A CNA2009100605709A CN200910060570A CN101476309A CN 101476309 A CN101476309 A CN 101476309A CN A2009100605709 A CNA2009100605709 A CN A2009100605709A CN 200910060570 A CN200910060570 A CN 200910060570A CN 101476309 A CN101476309 A CN 101476309A
Authority
CN
China
Prior art keywords
dam body
dam
upstream
reclamation
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2009100605709A
Other languages
English (en)
Inventor
周厚贵
杨启贵
孙役
李昌彩
王亚文
王章忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group Co Ltd
Original Assignee
China Gezhouba Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group Co Ltd filed Critical China Gezhouba Group Co Ltd
Priority to CNA2009100605709A priority Critical patent/CN101476309A/zh
Publication of CN101476309A publication Critical patent/CN101476309A/zh
Pending legal-status Critical Current

Links

Images

Abstract

一种超高混凝土面板堆石坝坝体预压反台填筑施工方法,首先进行一期坝体垫层、基层及堆石体的填筑;再按上游高下游低的正台阶形状进行了坝体的二期填筑,形成度汛经济断面;坝体度汛后,继续采用堆石料进行三期填筑,使三期填筑后的断面下游高于上游,使坝体下游区堆石坝在施工期即得到沉降,再完成堆石坝体其他分期的填筑,直至坝体达到设计高程。本发明改变了以往为追求施工进度,以施工工序复杂的前区为主的填筑布置,大大改善了坝体蓄水期的位移分布,使上游坝坡最大水平位移从100cm降至50cm(上游坡中部),沿坝坡水平分布比较均匀,这种位移的分布,减小了堆石料和垫层料中产生的差异变形,对改善面板的支撑条件起到较大作用。

Description

超高混凝土面板堆石坝坝体预压反台填筑施工方法
技术领域
本发明涉及到超高面板堆石坝填筑施工领域。
技术背景
一般的堆石坝的施工工艺,较为追求施工进度,以施工工序复杂的前区为主,基于坝体运行水荷载从坝体上游堆石体向坝体下游堆石坝传递,坝体堆石体干密度呈现从坝体上游区向坝体下游区逐步增大、孔隙率呈现从坝体上游区向坝体下游区逐步减小的趋势,坝体下游区沉降变形空间大于坝体上游区,这样就使坝体上下游堆石体的总体沉降规律不一致,导致坝体堆石体产生不均衡沉降变形,对坝体混凝土面板运行产生不利的影响,甚至导致混凝土面板产生裂缝,对蓄水期的堆石坝体安全运行产生不安全影响。
发明内容
本发明的目的就是要提供一种能够增加坝体运行安全,减少坝体施工干扰的高混凝土面板堆石坝坝体预压反台填筑施工方法。
本发明的目的是这样实现的:一种超高混凝土面板堆石坝坝体预压反台填筑施工方法,按照超高堆石坝分期填筑的要求,分期进行堆石坝的填筑,首先进行一期坝体垫层、基层及堆石体的填筑;其次,为保证坝体能在一个枯水期内填筑到防汛断面的要求,按上游高下游低的正台阶形状进行了坝体的二期填筑,形成度汛经济断面;坝体度汛后,继续采用堆石料进行三期填筑,使三期填筑后的断面下游高于上游,使坝体下游区堆石坝在施工期即得到沉降,再按照分期填筑的要求,完成堆石坝体其他分期的填筑,直至坝体达到设计高程。
本发明所提供的超高混凝土面板堆石坝坝体预压反台填筑施工方法,根据坝体施工分区和填筑程序,使坝体填筑前后区均衡上升,在进行坝面施工分区时,首先进行下游堆石区和次堆石区、主堆石区范围内的填筑,然后进行垫层、基层的填筑,突出均衡上升填筑、后区为主的施工分区,使坝体横断面上后区超高于前区,这种填筑方式改变了传统的前高后低填筑方式,经过坝体实际沉降证明,这种填筑方式有效的改善了坝体不均匀变形。通过理论上的非线性有限元的计算比较,新的填筑施工方法大大改善了坝体蓄水期的位移分布,使上游坝坡最大水平位移从100cm降至50cm(上游坡中部),沿坝坡水平分布比较均匀,这种位移分布情况,减小了堆石料和垫层料中产生的差异变形,对改善面板的支撑条件起到较大作用。
附图说明
下面结合附图和实施例对发明作进一步说明。
图1是本发明的分期填筑进展图。
具体实施方式
本发明的原理如下:基于坝体运行水荷载从坝体上游堆石体向坝体下游堆石坝传递,坝体堆石体干密度呈现从坝体上游区向坝体下游区逐步增大、孔隙率呈现从坝体上游区向坝体下游区逐步减小的趋势,坝体下游区沉降变形空间大于坝体上游区,如果对坝体下游区采取预先超高填筑后,使坝体下游区堆石体在施工期即得到沉降,这样就使坝体上下游堆石体的总体沉降规律趋向一致,从而达到减小因坝体堆石体沉降变形不均衡而产生的对面板变形不利的影响,从而达到有效控制坝体不均匀变形的目的。
实施例:
反台填筑主要施工步骤:如图1所示:
首先进行一期坝体垫层、基层及堆石体的填筑,形成一期
Figure A200910060570D0004184526QIETU
200-
Figure A200910060570D0004184526QIETU
208-
Figure A200910060570D0004184526QIETU
210的坝体;
为保证坝体能在一个枯水期内填筑到防汛断面的要求,按上游高下游低的正台阶形状进行了坝体的二期填筑,形成
Figure A200910060570D0004184526QIETU
282-
Figure A200910060570D0004184526QIETU
265-
Figure A200910060570D0004184526QIETU
258-
Figure A200910060570D0004184526QIETU
236的渡汛经济断面;坝体渡汛后,继续采用堆石料进行三期填筑,使三期填筑后的断面下游高于上游,得到
Figure A200910060570D0004184526QIETU
296-
Figure A200910060570D0004184526QIETU
307-
Figure A200910060570D0004184526QIETU
302的反台断面,使坝体下游区堆石坝在施工期即得到2-3个月的沉降期,再按照分期填筑的要求,完成堆石坝体四期
Figure A200910060570D0004184526QIETU
360-
Figure A200910060570D0004184526QIETU
350-
Figure A200910060570D0004184526QIETU
347.5填筑,直至坝体达到
Figure A200910060570D0004184526QIETU
405的设计高程。

Claims (2)

1、一种超高混凝土面板堆石坝坝体预压反台填筑施工方法,其特征在于:按照超高堆石坝分期填筑的要求,分期进行堆石坝的填筑,首先进行一期坝体垫层、基层及堆石体的填筑;其次,为保证坝体能在一个枯水期内填筑到防汛断面的要求,按上游高下游低的正台阶形状进行了坝体的二期填筑,形成度汛经济断面;坝体度汛后,继续采用堆石料进行三期填筑,使三期填筑后的断面下游高于上游,使坝体下游区堆石坝在施工期即得到沉降,再按照分期填筑的要求,完成堆石坝体其他分期的填筑,直至坝体达到设计高程。
2、根据权利要求1所述的超高混凝土面板堆石坝坝体预压反台填筑施工方法,其特征在于:坝体下游区堆石坝在施工期得到的沉降时间为2-3个月。
CNA2009100605709A 2009-01-15 2009-01-15 超高混凝土面板堆石坝坝体预压反台填筑施工方法 Pending CN101476309A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2009100605709A CN101476309A (zh) 2009-01-15 2009-01-15 超高混凝土面板堆石坝坝体预压反台填筑施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2009100605709A CN101476309A (zh) 2009-01-15 2009-01-15 超高混凝土面板堆石坝坝体预压反台填筑施工方法

Publications (1)

Publication Number Publication Date
CN101476309A true CN101476309A (zh) 2009-07-08

Family

ID=40837084

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2009100605709A Pending CN101476309A (zh) 2009-01-15 2009-01-15 超高混凝土面板堆石坝坝体预压反台填筑施工方法

Country Status (1)

Country Link
CN (1) CN101476309A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102002928A (zh) * 2009-08-31 2011-04-06 中国水电顾问集团贵阳勘测设计研究院 一种硬岩与软岩混合的面板坝堆石料
CN101691744B (zh) * 2009-09-30 2012-02-01 葛洲坝集团第五工程有限公司 混凝土面板堆石坝过水预沉降施工方法
CN101718086B (zh) * 2009-11-05 2012-04-11 河海大学 一种混凝土-堆石混合坝及其施工方法
CN102561271A (zh) * 2012-01-11 2012-07-11 河海大学 一种高聚物注浆土石坝及其施工方法
CN103046516A (zh) * 2012-12-29 2013-04-17 中国葛洲坝集团股份有限公司 一种堆石坝砾石土心墙底部的填筑方法
CN105386448A (zh) * 2015-10-08 2016-03-09 中国水利水电第十二工程局有限公司 一种堆石坝坝坡处理中倒坡的填筑施工方法

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102002928A (zh) * 2009-08-31 2011-04-06 中国水电顾问集团贵阳勘测设计研究院 一种硬岩与软岩混合的面板坝堆石料
CN101691744B (zh) * 2009-09-30 2012-02-01 葛洲坝集团第五工程有限公司 混凝土面板堆石坝过水预沉降施工方法
CN101718086B (zh) * 2009-11-05 2012-04-11 河海大学 一种混凝土-堆石混合坝及其施工方法
CN102561271A (zh) * 2012-01-11 2012-07-11 河海大学 一种高聚物注浆土石坝及其施工方法
CN102561271B (zh) * 2012-01-11 2015-04-08 河海大学 一种高聚物注浆土石坝的施工方法
CN103046516A (zh) * 2012-12-29 2013-04-17 中国葛洲坝集团股份有限公司 一种堆石坝砾石土心墙底部的填筑方法
CN103046516B (zh) * 2012-12-29 2015-04-01 中国葛洲坝集团股份有限公司 一种堆石坝砾石土心墙底部的填筑方法
CN105386448A (zh) * 2015-10-08 2016-03-09 中国水利水电第十二工程局有限公司 一种堆石坝坝坡处理中倒坡的填筑施工方法

Similar Documents

Publication Publication Date Title
CN101476309A (zh) 超高混凝土面板堆石坝坝体预压反台填筑施工方法
CN105297685B (zh) 一种基座混凝土面板堆石坝及其施工方法
CN203546678U (zh) 一种沥青混凝土心墙堆石坝结构
CN106284205B (zh) 一种模袋边梗的尾砂水力冲填筑坝的方法
CN103015399B (zh) 可液化地基的抗震减灾系统及地基处理方法
CN102071675A (zh) 一种联合排水堆载预压和深层搅拌桩加固软土地基的方法
CN103397617A (zh) 挤压墙式土工膜面板坝
CN104863096A (zh) 一种沥青混凝土防渗面板老化修补的加铺层施工方法
CN108842724B (zh) 一种细粒尾矿及高浓度不分选尾矿快速筑坝方法
CN103628488A (zh) 一种尾矿坝子坝的筑坝方法
CN201981551U (zh) 铁筋生态挡墙与混凝土挡墙组合的支挡结构
CN202090324U (zh) 一种新型过水围堰
CN204875834U (zh) 液化沙土结构
CN101581087B (zh) 高面板堆石坝坝体填筑时空预沉降控制法
CN103741651A (zh) 一种混凝土齿槽消力池及其施工方法
Yi et al. Tailings dam stability analysis of the process of recovery
CN102900092A (zh) 深厚覆盖层上修建面板堆石坝的人工复合地基及施工方法
CN206829167U (zh) 一种带泄流孔的现浇箱梁支架筏板基础
CN210262945U (zh) 一种胶凝砂砾石支墩坝结构
CN103437326A (zh) 一种复合材料坝
CN204590034U (zh) 一种坝基高压灌浆结构
CN203475394U (zh) 一种复合材料坝
CN106120663A (zh) 一种混凝土面板堆石坝
CN104196010A (zh) 一种面板堆石坝强制预沉降施工方法
CN204023604U (zh) 一种光伏电站水坠砂基础

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20090708