CN101532807B - 抽水蓄能电站尾水预留岩坎爆破安全防护方法 - Google Patents

抽水蓄能电站尾水预留岩坎爆破安全防护方法 Download PDF

Info

Publication number
CN101532807B
CN101532807B CN 200810236889 CN200810236889A CN101532807B CN 101532807 B CN101532807 B CN 101532807B CN 200810236889 CN200810236889 CN 200810236889 CN 200810236889 A CN200810236889 A CN 200810236889A CN 101532807 B CN101532807 B CN 101532807B
Authority
CN
China
Prior art keywords
steel
stoplog
stoplog gate
gate
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 200810236889
Other languages
English (en)
Other versions
CN101532807A (zh
Inventor
唐健
胡代清
陈秋
杨洪涛
彭福元
沙保卫
李凤丹
冯钢声
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUBEI BAILIANHE PUMPED STORAGE Co Ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Original Assignee
HUBEI BAILIANHE PUMPED STORAGE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUBEI BAILIANHE PUMPED STORAGE Co Ltd filed Critical HUBEI BAILIANHE PUMPED STORAGE Co Ltd
Priority to CN 200810236889 priority Critical patent/CN101532807B/zh
Publication of CN101532807A publication Critical patent/CN101532807A/zh
Application granted granted Critical
Publication of CN101532807B publication Critical patent/CN101532807B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)
  • Barrages (AREA)

Abstract

抽水蓄能电站尾水预留岩坎爆破安全防护方法,涉及一种水下岩坎爆破安全防护方法。爆破岩坎外建水气泡帷幕和多孔叠梁门,水气泡帷幕由多根钢管组成,每根钢管上钻两排孔,每根钢管与空压机的送气管相连。多孔叠梁门由钢框架加竹排构成,每孔叠梁门两侧是工字钢,工字钢两侧通过钢板、膨胀螺栓固定在圆形分流支墩上,单扇叠梁门通过槽钢、工字钢、角钢焊接连接,在叠梁门进水面铺设一层竖向竹跳板,同时在单孔叠梁门顶部与两侧分流墩顶部安装安全网。本发明采用设立水气泡帷幕加钢框架加竹排以及安全网方案代替叠梁门方案,设计科学合理,防止了爆破对拦污栅及尾水闸门造成的破坏与影响,方便清渣,制造、安装工期短,制造、安装、拆除费用低。

Description

抽水蓄能电站尾水预留岩坎爆破安全防护方法
技术领域
本发明涉及一种水下岩坎爆破安全防护方法。
背景技术
一般而言,大型水电站尾水系统的施工主要采用预留岩坎方法,该方法在施工初期可以节约施工时间、降低工程成本造价,但在尾水系统施工完成后,必须将预留岩坎拆除,拆除时就涉及到水下爆破以及安全防护问题。
由于岩坎紧邻已建成的引水洞及其附属建筑物,尤其距下库出(进)水口已浇底板砼约15.0m;距拦污栅槽最近约38m;距尾水闸门槽最近约82m;岩坎与保留边墙相连,距右岸西干渠2#取水口52m;进厂交通洞从西干渠隧洞下方穿越,二者垂直距离仅17m左右;拆除爆破区距下游侧的右岸坝肩最小距离约200m,坝体内防渗墙水平距离约200m;距正在运行的左岸电站机组约430m。爆破拆除时,如不采取有效的安全防护措施,在爆破振动、水中冲击波的作用下,将对尾水检修门、拦污栅产生巨大的冲击压力,威胁厂房施工安全。
深孔水下爆破产生的水击波主要是:炸药爆炸产生的冲击波冲出填塞冲向水中的冲击波转为水击波。水下爆破的水击波除由冲击波转的水击波外。还有炸药爆炸产生的地震波在水底界面处折射于水中形成的水击波。
发明内容
本发明的目的是针对上述现状,旨在提供一种设计科学合理、工期短、成本低的抽水蓄能电站尾水预留岩坎爆破安全防护方法。
本发明目的的实现方式为,抽水蓄能电站尾水预留岩坎爆破安全防护方法,在距爆破岩坎5±1m处建水气泡帷幕,在距水气泡帷幕20±5m处建多孔叠梁门,
水气泡帷幕由20±3根钢管组成,每根钢管上钻两排孔,孔的间排距为50~70mm,每根钢管与空压机的送气管相连,
多孔叠梁门由钢框架加竹排构成,每孔叠梁门两侧是工字钢,工字钢两侧通过钢板、膨胀螺栓固定在圆形分流支墩上,圆形支墩紧靠下水库进出口拦污栅,工字钢间距7.2±0.4m米,单扇叠梁门通过槽钢、工字钢、角钢焊接连接,在叠梁门进水面铺设一层竖向竹跳板,竹跳板通过铁丝固定在门上,同时在单孔叠梁门顶部与两侧分流墩顶部通过铁丝安装两层安全网和一层安全防护绿色隔网。
本发明采用设立水气泡帷幕加钢框架加竹排以及安全网方案代替叠梁门方案,有以下优点:
1)设计科学合理,防止了爆破对拦污栅及尾水闸门造成的破坏与影响;
2)将挡渣位置前移,避免了叠梁门挡渣方案中有将近10米区域很难清渣的现象,大大方便了爆破后清渣,也为机组水泵工况启动创造了良好的条件;
3)大大缩短了制造、安装工期,将原60天工期减少到20天;
4)制造、安装、拆除费用由原来300多万降低到不到60万。
附图说明
图1是本发明防护布置图
图2是钢框架加竹排结构示意图
图3是钢框架加竹排结构单扇门制作示意图
图4是钢框架加竹排结构安装示意图
图5是图4中A部分放大示意图
具体实施方式
参照图1,在距爆破岩坎5±1m处建水气泡帷幕,在距水气泡帷幕20±5m处建多孔叠梁门。爆破岩坎2建在下水库1的爆破位置。下水库设有下水库进出口挡水闸门12。
水气泡帷幕由20±3根钢管3组成,管长20m,管距3m,每根管上钻两排φ1.5mm孔,孔的间排距为50~70mm,每根钢管与空压机的送气管相连。在点火前5min,用2台9m3/min,2~4×105Pa空压机4对每根钢管送气,使每米钢管风量大于0.008m3/s,当爆破后的水击波射到水和气泡两相帷幕层时,由于气泡的可压缩性,使水击波的部分能量转换压缩气泡的内能,使气泡的内压升高。当水击波的波头过后,波头压力低于气泡的压力时,两相中储存的势能产生二次脉冲动压力,再次释放能量,使透过水与气泡层后的水压波压力峰值衰减,一般衰减40~100倍。
为满足《水利水电工程钢闸门设计规范》要求,本发明在下库十二根圆形分流支墩9前缘相间布置十孔简易叠梁门,简易叠梁门为钢框架加竹排结构。参照图2、3、4、5,每孔叠梁门由五扇组成,每扇之间通过钢丝绳连接,共十扇,合计五十节。每扇最上节叠梁门有吊耳17,使每扇叠梁门能通过钢丝绳垂直悬挂在缆绳上,以便以后拆除方便。
每孔叠梁门两侧是多根工字钢13,工字钢立在底坎上,间距7.2±0.4m米,两侧通过钢板10、膨胀螺栓8固定在圆形分流支墩9与底坎处,圆形支墩9紧靠下水库进出口拦污栅11,钢框架加竹排结构6顶部与两侧分流墩顶部通过铁丝安装外包防护网7,单扇叠梁门19通过槽钢14、工字钢15、角钢16焊接连接,在每扇叠梁门19进水面铺设一层竖向竹跳板18,竹跳板通过铁丝固定在门上。
在每孔叠梁门下端沿门角处迎水面布置木材堆5,减少死角处,避免死角处杂物清理困难的问题发生。
单扇叠梁门外形尺寸6.77m×1.6m×0.25m,重1.020吨,每孔叠梁门合计高度8米。每孔叠梁门两侧是工十二根30号工字钢,工字钢长8m,间距6.8米。工字钢两侧与圆形分流支墩9间通过18套M18×100的钢板10、膨胀螺栓8均布固定。
圆形分流支墩9顶部高程85.5m,底坎高程
Figure G2008102368898D00032
69m,每孔叠梁门镶与相邻工字钢间垂直立在底坎上。单孔叠梁门顶部与两侧分流墩顶部通过铁丝将两层安全网、一层安全防护网7,即绿色隔网,用于拦截爆破振动、水击波、涌浪、飞石以及杂物等的侵入。

Claims (4)

1.抽水蓄能电站尾水预留岩坎爆破安全防护方法,其特征在于在距爆破岩坎5±1m处建水气泡帷幕,在距水气泡帷幕20±5m处建多孔叠梁门,
水气泡帷幕由20±3根钢管组成,每根钢管上钻两排孔,孔的间排距为50~70mm,每根钢管与空压机的送气管相连,
多孔叠梁门由钢框架加竹排构成,每孔叠梁门由五扇叠梁门组成,每扇叠梁门之间通过钢丝绳连接,每孔叠梁门两侧是工字钢,工字钢两侧通过钢板、膨胀螺栓固定在圆形分流支墩上,圆形支墩紧靠下水库进出口拦污栅,每孔叠梁门的工字钢间距7.2±0.4m,单扇叠梁门通过槽钢、工字钢和角钢焊接连接,在叠梁门进水面铺设一层竖向竹跳板,竹跳板通过铁丝固定在每扇叠梁门上,同时在单孔叠梁门顶部与两侧分流墩顶部通过铁丝安装两层安全网和一层安全防护绿色隔网。
2.根据权利要求1所述的抽水蓄能电站尾水预留岩坎爆破安全防护方法,其特征在于水气泡帷幕的钢管(3)长20m,管距3m,每根管上钻两排φ1.5mm孔。
3.根据权利要求1所述的抽水蓄能电站尾水预留岩坎爆破安全防护方法,其特征在于在下库十二根圆形分流支墩(9)前缘相间布置十孔简易叠梁门,每孔叠梁门由五扇组成,之间通过钢丝绳连接。
4.根据权利要求1所述的抽水蓄能电站尾水预留岩坎爆破安全防护方法,其特征在于在每孔叠梁门下端沿门角处迎水面布置木材堆(5)。
CN 200810236889 2008-12-18 2008-12-18 抽水蓄能电站尾水预留岩坎爆破安全防护方法 Active CN101532807B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200810236889 CN101532807B (zh) 2008-12-18 2008-12-18 抽水蓄能电站尾水预留岩坎爆破安全防护方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200810236889 CN101532807B (zh) 2008-12-18 2008-12-18 抽水蓄能电站尾水预留岩坎爆破安全防护方法

Publications (2)

Publication Number Publication Date
CN101532807A CN101532807A (zh) 2009-09-16
CN101532807B true CN101532807B (zh) 2012-12-26

Family

ID=41103551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200810236889 Active CN101532807B (zh) 2008-12-18 2008-12-18 抽水蓄能电站尾水预留岩坎爆破安全防护方法

Country Status (1)

Country Link
CN (1) CN101532807B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104089551A (zh) * 2014-04-11 2014-10-08 中国水利水电第十一工程局有限公司 老闸定向倾斜倒塌爆破拆除施工方法

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102419140A (zh) * 2011-11-25 2012-04-18 中铁十二局集团第三工程有限公司 多元立体安全防护方法
CN105865281A (zh) * 2016-04-27 2016-08-17 杨毅 一种紧邻电站、升压站横向明挖控制爆破施工方法
CN106759157B (zh) * 2016-12-12 2018-12-14 武汉大学 一种用于混凝土重力坝坝踵抗水下接触爆炸的防护装置
CN106679523B (zh) * 2016-12-29 2017-12-26 武汉大学 一种用于消除水下近距离爆破冲击波的空气隔层装置
CN107883824B (zh) * 2017-10-20 2019-05-10 武汉大学 水下爆破冲击波防护装置
CN107764146A (zh) * 2017-11-14 2018-03-06 武汉科技大学 用于阻隔深水爆破冲击波的气泡帷幕发生装置及其使用方法
CN112013731A (zh) * 2020-07-16 2020-12-01 中国电建集团中南勘测设计研究院有限公司 一种预留岩坎的拆除方法
CN114152163B (zh) * 2021-12-30 2023-03-31 江苏龙源振华海洋工程有限公司 一种海上风机安装用礁石地基爆破防护装置

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2316625Y (zh) * 1997-05-23 1999-04-28 崔彪 高效能控制爆破劈裂管
EP1944432A1 (de) * 2007-01-11 2008-07-16 Sälzer Sicherheitstechnik GmbH Explosionshemmendes Bauelement

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2316625Y (zh) * 1997-05-23 1999-04-28 崔彪 高效能控制爆破劈裂管
EP1944432A1 (de) * 2007-01-11 2008-07-16 Sälzer Sicherheitstechnik GmbH Explosionshemmendes Bauelement

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
任玉清等.黄河小峡水电站导流明渠左岩坎预裂爆破.《云南水力发电》.2005,第21卷(第6期), *
刘美山等.彭水电站导流洞出口岩坎爆破拆除设计与施工.《云南水力发电》.2005,第21卷(第2期), *
张文煊等.大朝山水电站导流洞围堰及岩坎爆破拆除.《爆破》.2000,第17卷 *
罗盛发.尾水出口预留岩坎拆除施工.《贵州水力发电》.2004,第18卷(第1期), *
胡耀武等.福建某船厂注水式干船坞工程坞口前沿大方量岩坎爆破施工技术.《中国港湾建设》.2001,(第5期), *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104089551A (zh) * 2014-04-11 2014-10-08 中国水利水电第十一工程局有限公司 老闸定向倾斜倒塌爆破拆除施工方法

Also Published As

Publication number Publication date
CN101532807A (zh) 2009-09-16

Similar Documents

Publication Publication Date Title
CN101532807B (zh) 抽水蓄能电站尾水预留岩坎爆破安全防护方法
CN112983047B (zh) 一种适用于爆破拆除中的静力切割拆除方法
CN110725597A (zh) 混凝土筒仓顶部环梁施工平台搭设结构以及搭设方法
CN102322074B (zh) 一种导管架基础结构及施工方法
CN105871309A (zh) 一种浮动式水上光伏发电系统
US4764052A (en) Stability optimized perforated breakwaters
CN106192879B (zh) 一种圆台式浮式防波堤
CN109150069A (zh) 网状支撑漂浮式光伏电站
CN215442042U (zh) 海上风电单桩基础防冲刷装置
CN113175004B (zh) 海上风电单桩基础防冲刷装置及方法
CN107376642B (zh) 一种scr法烟气脱硝反应器
CN207934063U (zh) 管廊工程钢筋混凝土支墩的快速安拆定型模板
CN203487802U (zh) 斜向自爬升保护屏单元体系统
CN102912769A (zh) 拉索支墩钢构坝
CN202881911U (zh) 拉索支墩钢构坝
CN101235674A (zh) 无声无震爆破砼支撑梁方法
CN205934877U (zh) 一种引水隧洞的集石坑结构
CN206655300U (zh) 一种新型联合排渗装置
CN206408598U (zh) 一种能重复利用的消力池检修装置
CN110820701A (zh) 水利水电进水口布置结构
CN105672190B (zh) 一种水库坝前拦鱼警示缆索结构
CN108533314B (zh) 一种矿山采空区封闭方法及其应用系统
CN204000814U (zh) 钢护筒植桩平台
CN220266526U (zh) 一种叠合式土岩界面导流汇聚槽
CN217480184U (zh) 一种尾矿基坑用抗污水腐蚀生态混凝土防护系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE GRID XINYUAN CO., LTD. HUBEI BAILIANHE PUMPE

Effective date: 20130905

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: HUBEI BAILIANHE PUMPED STORAGE COMPANY LTD.

Effective date: 20130905

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 438600 HUANGGANG, HUBEI PROVINCE TO: 100031 XICHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20130905

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Patentee after: State Grid Corporation of China

Patentee after: State Grid Xinyuan Co., Ltd.

Patentee after: Hubei Bailianhe Pumped Storage Company Ltd.

Address before: Huanggang City, Hubei province 438600 lotus Township, Luotian County

Patentee before: Hubei Bailianhe Pumped Storage Company Ltd.