CN101514541B CN2009100216772A CN200910021677A CN101514541B CN 101514541 B CN101514541 B CN 101514541B CN 2009100216772 A CN2009100216772 A CN 2009100216772A CN 200910021677 A CN200910021677 A CN 200910021677A CN 101514541 B CN101514541 B CN 101514541B
Authority
CN
China
Prior art keywords
leveling
bearing
bridge
support
pinner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009100216772A
Other languages
Chinese (zh)
Other versions
CN101514541A (en
Inventor
王亮
池平平
张超民
赵春锋
苏红岭
陈向军
马建会
田占良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority to CN2009100216772A priority Critical patent/CN101514541B/en
Publication of CN101514541A publication Critical patent/CN101514541A/en
Application granted granted Critical
Publication of CN101514541B publication Critical patent/CN101514541B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a one-time leveling method for the installation of a large bridge support, the bridge support, as an important constituent part of a beam bridge structure, is a force transferring device arranged at the support location of a bridge-span structure and a bridge pier or the supporting position of a bridge abutment. As the large bridge support limits the operating space on the top of a pier column, the support is difficult to meet the leveling demand during construction. At present, dry hard mortar is used as an anchorage leveling grouting material of the bridge support during the erection of the bridge, so normative level and standard are hardly reached, leaving potential safety hazards to post-operation of the bridge. The invention embeds in advance a plurality of leveling bolts in a pad stone to rotatably level the bolts so that the height of the topmark thereof is consistent in scale height of bottom surface of a lower filler plate of the support; the support is suspended on the leveling bolts and is regulated to be consistent with the axial line of the pad stone; a bonding material is poured between the pad stone and the support. The invention can, without being impacted by inconsistent compression of the dry hard mortar, level the support via the leveling bolts at one time, thus avoiding the defect of current method that repeated loading/unloading and leveling are required.

Description

But large-scale bridge support is installed the method for one-time leveling
Technical field
The present invention relates to the leveling method that a kind of large-scale bridge support is installed, but specifically be the method that a kind of large-scale bridge support is installed one-time leveling, belong to the highway engineering construction technical field.
Background technology
Bridge pad is an important component part of beam bridge girder construction, is the load transfer device that is provided with in the supporting place of bridge span structure and bridge pier or abutment.Along with the development of highway construction, bridge beam body and bridge pad are increasing, and supporting capacity and the deformability to bridge pad also constantly proposed new requirement simultaneously, and its construction and installation technical requirements is more and more higher.Because bridge pad is bigger, pier stud top operational space is limited, and bearing leveling when construction is difficult to reach requirement.Bridge erection at present adopts dry mortar as the bridge pad levelling grouting agent that casts anchor, so bearing also just is difficult to reach the standard level standard, stays serious potential safety hazard for the operation of bridge later stage.
Summary of the invention
But the objective of the invention is to disclose the method that a kind of large-scale bridge support is installed one-time leveling, to overcome existing in prior technology deficiency and defective.
The technical solution adopted in the present invention is:
A. pre-buried four leveling bolts in pinner;
B. rotating the leveling bolt makes its top mark high consistent with bearing lower bolster bottom surface absolute altitude;
C. bearing is hung on pre-buried good leveling bolt, it is consistent with the pinner axis to adjust bearing;
D. infusion and binding material between pinner and bearing.
Beneficial effect of the present invention: since in the pinner concrete pre-buried leveling bolt, be not subjected to inconsistent influence of stiff mortar decrement, can make the bearing one-time leveling, avoided existing property method to need repeatedly to load and unload repeatedly the defective of levelling by the leveling bolt, improve construction quality, saved cost.
Description of drawings
Accompanying drawing is installed status architecture generalized section after the leveling for the present invention.
Reference numeral is: bearing 1, leveling bolt 2, pinner 3, bearing crab-bolt preformed hole 4, bearing lower bolster 5.
The specific embodiment
Below in conjunction with drawings and Examples the present invention is done and to describe in further detail:
A. select four leveling bolts (2) according to the size of bearing (1), with the whole screw mandrel of leveling bolt (2) nut of all screwing on, determined the physical dimension of bearing lower bolster (5), build the preceding bearing crab-bolt preformed hole (4) of reserving of pinner (3), four leveling bolts (2) that will have nut are embedded in the pinner (3), make the nut of leveling bolt (2) exceed pinner (3) end face, the pre-buried position of leveling bolt (2) guarantees at bearing lower bolster (5) in length and breadth in scope;
B. reach 20Mpa when above at pinner (3) concrete strength, at first rotate pre-buried four leveling bolts (2), make its top mark high consistent with bearing lower bolster (5) bottom surface absolute altitude;
C. bearing (1) is hung on pre-buried good leveling bolt (2), it is consistent with pinner (3) axis to adjust bearing (1);
D. between pinner (3) and bearing (1), pour into the gravity gravity flowing levelling mortar.

Claims (2)

1. but large-scale bridge support is installed the method for one-time leveling, it is characterized in that by the following technical solutions:
1.a pre-buried four leveling bolts (2) in pinner (3);
1.b rotation leveling bolt (2) makes its top mark high consistent with bearing lower bolster (5) bottom surface absolute altitude;
1.c bearing is hung on pre-buried good leveling bolt (2), and it is consistent with pinner (3) axis to adjust bearing (1);
1.d infusion and binding material between pinner (3) and bearing (1).
2. but large-scale bridge support according to claim 1 is installed the method for one-time leveling, it is characterized in that by the following technical solutions:
2.a the size according to bearing (1) is selected four leveling bolts (2), with the whole screw mandrel of leveling bolt (2) nut of all screwing on, determined the physical dimension of bearing lower bolster (5), build the preceding bearing crab-bolt preformed hole (4) of reserving of pinner (3), four leveling bolts (2) that will have nut are embedded in the pinner (3), make the nut of leveling bolt (2) exceed pinner (3) end face, the pre-buried position of leveling bolt (2) guarantees at bearing lower bolster (5) in length and breadth in scope;
2.b reach 20Mpa when above at pinner (3) concrete strength, at first rotate pre-buried four leveling bolts (2), make its top mark high consistent with bearing lower bolster (5) bottom surface absolute altitude;
2.c bearing (1) is hung on pre-buried good leveling bolt (2), and it is consistent with pinner (3) axis to adjust bearing (1);
2.d perfusion gravity gravity flowing levelling mortar between pinner (3) and bearing (1).
CN2009100216772A 2009-03-25 2009-03-25 One-time leveling method for installation of large bridge support Expired - Fee Related CN101514541B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100216772A CN101514541B (en) 2009-03-25 2009-03-25 One-time leveling method for installation of large bridge support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100216772A CN101514541B (en) 2009-03-25 2009-03-25 One-time leveling method for installation of large bridge support

Publications (2)

Publication Number Publication Date
CN101514541A CN101514541A (en) 2009-08-26
CN101514541B true CN101514541B (en) 2010-09-01

Family

ID=41039149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100216772A Expired - Fee Related CN101514541B (en) 2009-03-25 2009-03-25 One-time leveling method for installation of large bridge support

Country Status (1)

Country Link
CN (1) CN101514541B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101922141B (en) * 2010-07-16 2012-05-23 中交第一公路工程局有限公司 Structure and construction method of bearing pad stone
CN102286926A (en) * 2011-08-25 2011-12-21 重庆新科建设工程有限公司 Mounting process of cast-in-place bridge pot rubber bearing
CN103900779A (en) * 2012-12-25 2014-07-02 中国直升机设计研究所 External impact manufacture apparatus
CN103243651B (en) * 2013-04-24 2015-02-25 山东科技大学 Method for fixedly installing and leveling base of metal upright column of bridge guardrail
CN104249981B (en) * 2014-09-15 2016-12-07 太仓市金达机械厂 Crossbeam level(l)ing device
CN104249982B (en) * 2014-09-15 2016-11-23 太仓市金达机械厂 A kind of crossbeam level(l)ing device
CN104562924B (en) * 2014-12-31 2016-08-24 郑州航空工业管理学院 Bridge pad from jacking backing plate replacing options
CN106988225A (en) * 2017-05-18 2017-07-28 陕西中咨土木工程技术研究院有限公司 A kind of self-adapting regulation method and its structure for solving bridge pad initial deformation
CN108824203A (en) * 2018-07-09 2018-11-16 贵州新联爆破工程集团有限公司 A kind of gradient precast beam support leveling device
CN111958776A (en) * 2019-06-24 2020-11-20 上海建工建材科技集团股份有限公司 Shield segment mold separable pouring cover plate and construction method thereof
EP3994312B1 (en) * 2019-07-04 2024-04-03 Vestas Wind Systems A/S Method of forming a wind turbine foundation
CN110409625A (en) * 2019-07-22 2019-11-05 武汉一冶建筑安装工程有限责任公司 Pier stud support installation method
CN114319092A (en) * 2022-01-14 2022-04-12 中国铁建大桥工程局集团有限公司 Connecting device, bridge and mounting method of connecting device

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
JP特开2006-312842A 2006.11.16
宋顺忱,王召祜.客运专线铁路桥梁调高盆式橡胶支座( TGPZ)设计简介.铁道标准设计.2007,(2),全文. *
李勤铭.客运专线桥梁盆式橡胶支座安装施工技术.铁道建筑.2008,(5),全文. *
翁文福.重庆轻轨盖梁锚箱支座施工技术.路基工程 .2005,(6),全文. *

Also Published As

Publication number Publication date
CN101514541A (en) 2009-08-26

Similar Documents

Publication Publication Date Title
CN101514541B (en) One-time leveling method for installation of large bridge support
CN110409317B (en) Swivel spherical hinge and mounting method thereof
CN208362897U (en) One kind falling beam support system
CN107059645A (en) A kind of Long span variable cross-section precast segmental beam assembling construction structure and construction method
CN203452266U (en) Fixing and leveling structure of H section steel column
KR20150057581A (en) Level adjusting apparatus for precast slab and precast slab construction method using therewith
CN101899814B (en) Dispersed cable saddle structure for bridge
CN102296813A (en) Construction method for steel column base and steel column base structure thereof
JP2012102601A (en) Height-adjustable bearing device for structure and height adjustment method of bearing device for structure
CN103791795B (en) Bridge static loading experiment displacement monitor
CN113863166B (en) Reverse order construction method for swivel-first and mounting support
CN104931338B (en) The fixing device and its making and use method of arbitrarily angled rebound test concrete test block
CN103061249A (en) Quick positioning construction device and construction method for steel-pipe column of bridge
CN101736690A (en) Installation and leveling technology adopting expansion bolt auxiliary supporting seat
CN204609319U (en) A kind of large-tonnage tensioning construction adjusting device
CN102953328A (en) Support leveling device for sloping precast beam and method for installing support by using support leveling device
CN105696796A (en) Cantilever scaffold steel girder anchoring method
CN108517786B (en) Replaceable swivel spherical hinge and installation method thereof
CN212641529U (en) Anti-crack prestressed enlarged footing anti-floating anchor rod and anti-crack prestressed anti-floating anchor rod
CN204402496U (en) A kind of vertical shaft steel strand jack hangs slip-form lifting device
CN109537472B (en) Precast beam end bottom die rotating hinge device and application method thereof
CN204151670U (en) Pressure-adjusting type bridge bearing pad
CN113235400A (en) Adjustable slot-in type prefabricated pier stud and bearing platform connecting structure and construction method
CN106480793B (en) A kind of prefabricated floating plate ballast construction method
CN208981019U (en) Ladder type prefabricated plate with auxiliary block

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100901

Termination date: 20140325