CN101509264A - One-step pore-creating, segmenting high pressure cement grout construction method - Google Patents
One-step pore-creating, segmenting high pressure cement grout construction method Download PDFInfo
- Publication number
- CN101509264A CN101509264A CNA2009101196564A CN200910119656A CN101509264A CN 101509264 A CN101509264 A CN 101509264A CN A2009101196564 A CNA2009101196564 A CN A2009101196564A CN 200910119656 A CN200910119656 A CN 200910119656A CN 101509264 A CN101509264 A CN 101509264A
- Authority
- CN
- China
- Prior art keywords
- grouting
- grout
- hole
- high pressure
- pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000011440 grout Substances 0.000 title claims abstract description 23
- 239000004568 cement Substances 0.000 title claims abstract description 17
- 238000010276 construction Methods 0.000 title claims abstract description 11
- 239000004576 sand Substances 0.000 claims abstract description 9
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 9
- 238000012856 packing Methods 0.000 claims abstract description 8
- 230000011218 segmentation Effects 0.000 claims description 18
- 229920002472 Starch Polymers 0.000 claims description 11
- 235000019698 starch Nutrition 0.000 claims description 11
- 239000008107 starch Substances 0.000 claims description 11
- 239000002002 slurry Substances 0.000 claims description 5
- 238000004873 anchoring Methods 0.000 claims description 4
- 235000013336 milk Nutrition 0.000 claims description 2
- 239000008267 milk Substances 0.000 claims description 2
- 210000004080 milk Anatomy 0.000 claims description 2
- 230000006378 damage Effects 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 12
- 238000004140 cleaning Methods 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 4
- 238000005553 drilling Methods 0.000 abstract description 2
- 238000005406 washing Methods 0.000 abstract description 2
- 238000001914 filtration Methods 0.000 abstract 1
- 238000002347 injection Methods 0.000 abstract 1
- 239000007924 injection Substances 0.000 abstract 1
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 6
- 238000010586 diagram Methods 0.000 description 6
- 229910052742 iron Inorganic materials 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 238000007569 slipcasting Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000011083 cement mortar Substances 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
- Soil Conditioners And Soil-Stabilizing Materials (AREA)
Abstract
An one-time pore-creating and subsection high pressure cement injection construction method, and the biggest characteristic of the method is that drainage pocket type mud jacking block mode is developed and applied and fine sand pocket is provided with filtration loss function; the method also has some new characteristics that grout is stopped from passing, big grouting pressure difference can be borne, destroying by washing by high pressure water is possible, and the like, and the method is used for a grouting subsection packing blocker and a grouting grout-feeding separator; the following construction procedures of repeatedly installing a driller, repeatedly deepening drilling, repeatedly cleaning bottom of hole, repeatedly cleaning cement stones in the hole, repeatedly installing an orifice blocker and grout-feeding pipes in a lifting and lining hole, and the like can be eliminated; the method has the advantages of reducing a lot of assistant workload, increasing construction speed severalfold, greatly lowering over 10%-20% of construction cost and having huge economic effect.
Description
Technical field
The present invention relates to the job practices of a kind of one-step pore-creating, segmenting high pressure cement grout.
Background technology
Very universal with cement consolidation by grouting ground, leak stopping and making cement grouted cut off wall, it is job practices commonly used now that stage-cementing is from top to bottom blocked in the aperture, and its flow process is: 1. open grout hole, finish the orifice tube that pre-buried aperture is blocked, wait to coagulate 24 hours.2. finish first section cementation (I) (I
1Rigging up is finished first section grout hole boring → I
2Inlet pipe → I in aperture obstruction and the hole is installed
3With finish first section cementation → I than the grouting pressure of low pressure
4Take out inlet pipe in aperture obstruction and the hole).3. finish second section cementation (II) (II
1Rigging up, is finished second section grout hole boring → II at cement calculus in the cleaning bottom of hole
2Inlet pipe → II in aperture obstruction, the hole is installed
3Full hole section cementation → II
4Take out inlet pipe in aperture obstruction, the hole) → 4. the 3rd section cementation (III) (repetition II
1, II
2, II
3, II
4Step).Can continue the plurality of sections construction until finishing the section grouting of whole hole.
Summary of the invention
One-step pore-creating, the flow process of segmenting high pressure cement grout method is from top to bottom:
1. boring once reaches grouting whole hole depth → 2. and installs 1 little progress slurry iron pipe, fine sand bag by grouting segmentation requirement advance to starch separator, drainage pocket type grouting segmentation packer and finish aperture drainage formula mud jacking anchoring and block in the hole, wait to coagulate more than 4 hours → 3. first section cementation (I ') (I '
1Control 1.0MPa following mud jacking pressure is pressed into the drainage pocket type grouting segmentation packing obstruction between first, second grout compartment, and mud jacking is more than 10 minutes → I '
2The control grouting pressure surpasses 1.5MPa, finishes grouting → I ' by the grouting technique requirement
3Remove cement paste in the inlet pipe and get through the fine sand bag separator that destroys between first section inlet pipe and the second section inlet pipe with the 10MPa water under high pressure, make it no longer produce compartmentation) → 4. second section cementation (II ') (repeat I '
1, I '
2, I '
3Step).Can continue the plurality of sections construction until finishing the section grouting of whole hole.
The contrast Step II
1, II
2, II
3, II
4With step I '
1, I '
2, I '
3Two kinds of different job practices flow processs are as can be known: one, and the constructing operation step is simplified greatly, and back work amount and non-cutting time significantly reduce; They are two years old, the former is in the milk, and to block all be in the aperture, all there is the grouting problem that repeats in each grouting, being prone to fault and aperture in the hole blocks improving grouting pressure very sensitive, but there are not these problems in the latter, the grouting pressure of raising reality that can be bold during the grouting of deep hole section and the difficult hole internal fault that produces produce better the reinforcing and anti-seepage effect to the cementation meeting.
Description of drawings
Fig. 1 injected hole schematic diagram;
Fig. 2 inserts in injected hole and advances to starch iron pipe, fine sand bag and advance to starch separator, drainage pocket type grouting segmentation packer and finish schematic diagram after aperture drainage formula mud jacking blocks;
First section slip casting schematic diagram of Fig. 3;
Fig. 4 water under high pressure breaks through the schematic diagram behind the separator between first section and second section;
Second section slip casting schematic diagram of Fig. 5;
Fig. 6 final stage slip casting schematic diagram.
1 injected hole, 2 advance to starch iron pipe, and 3 aperture drainage formula mud jacking anchorings are blocked, 4 drainage pocket types grouting segmentation packer, 5 fine sand bags advance to starch separator, 6 pulp eyes, 7 segmentation packings are blocked.
The specific embodiment
(1) rig is once finished grout hole.
(2) install by grouting segmentation requirements that 1 little progress slurry steel pipe, fine sand bag advance to starch separator, drainage pocket type grouting segmentation packer in the hole, finish the aperture obstruction of grouting, treat with fixed attention more than 4 hours with drainage pocket type mud jacking anchoring obstruction mode.
(3) begin first section cementation from top to bottom, at first the drainage pocket type grouting segmentation packer that is pressed between first, second grout compartment with the following mud jacking pressure of 1.0MPa produces segmentation packing obstruction, and effectively producing the packing obstruction needs mud jacking more than 10 minutes.Then improve grouting pressure to more than the 1.5MPa, the bar on the generation cement paste puncture inlet pipe pulp eye enters grout compartment and begins cementation.
(4) first sections grouting finish, and use inlet pipe in the above water under high pressure scour hole of 10.0MPa immediately.Cement paste in the inlet pipe is all rinsed well, with water under high pressure fine sand bag separator is destroyed and get through, eliminate compartmentation, prepare second section cementation cement paste.
(5) second sections grouting.The grouting segmentation packer that the following mud jacking pressure of the same 1.0MPa of use is pressed between second, third grout compartment produces segmentation packing obstruction, then boosts above second section cementation of beginning more than the 1.5MPa.
(6) repeat (3), (4) method step, up to the cementation task of finishing whole hole section.
The maximum characteristics of this new method are, Application and Development drainage pocket type mud jacking block new technology and The fine sand bag has the leak-off effect, can stop cement mortar poor by also bearing big grouting pressure, Have concurrently again and can the new feature such as be destroyed by high pressure water washing, as grouting segmentation packing disabler and Grouting advances to starch separator, do not repeat rigging up in place, repeatedly add gun drilling, repeat cleaning bottom of hole, Repeat cement calculus in the cleaning bottom of hole, repeat to install the aperture disabler and work constructions such as pulling out in the hole pulp-inlet pipe Program is economized and have been subtracted a lot of back work amounts, becomes several times raising speed of application, significantly reduction Construction cost has great economic effect more than 10%~20%.
Claims (6)
1, the job practices of a kind of one-step pore-creating, segmenting high pressure cement grout is characterized in that, comprises following construction sequence: the first step, and use rig once to finish grout hole; In second step, install by packer grouting requirements and to advance to starch separator and grouting segmentation packer between inlet pipe in the hole, grout compartment and the grout compartment, and finish the aperture obstruction of grouting; The 3rd step, begin first section cementation from top to bottom, at first carry out mud jacking, making the grouting segmentation packer between first and second grout compartments produce segmentation packing obstruction under the slurries pressure, then improve grouting pressure, make cement paste puncture bar on the inlet pipe pulp eye and enter grout compartment and begin cementation; The 4th step, after first section grouting finishes, use inlet pipe in the water under high pressure scour hole immediately, the cement paste in the inlet pipe is all rinsed well, and the separator destruction of advancing to starch between grout compartment and the grout compartment is got through; In the 5th step, repeat the 3rd, the 4th step, up to the cementation of finishing whole hole section.
2, job practices as claimed in claim 1 is characterized in that, the separator that advances to starch between grout compartment and the grout compartment is that the fine sand bag advances to starch separator, and grouting segmentation packer is a drainage pocket type grouting segmentation packer.
3, job practices as claimed in claim 1, the aperture that it is characterized in that being in the milk are blocked the anchoring of employing drainage formula mud jacking and are blocked.
As claim 1 or 2 or 3 described job practicess, it is characterized in that 4, in the 3rd step, at first carry out mud jacking, the slurries pressure of this moment is below the 1.0MPa.
As claim 1 or 2 or 3 described job practicess, it is characterized in that 5, in the 3rd step, then improve grouting pressure, the slurries pressure of this moment is more than the 1.5MPa.
As claim 1 or 2 or 3 described job practicess, it is characterized in that 6, in the 4th step, with inlet pipe in the water under high pressure scour hole, the pressure of water is more than the 10.0MPa.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101196564A CN101509264B (en) | 2009-03-25 | 2009-03-25 | One-step pore-creating, segmenting high pressure cement grout construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101196564A CN101509264B (en) | 2009-03-25 | 2009-03-25 | One-step pore-creating, segmenting high pressure cement grout construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101509264A true CN101509264A (en) | 2009-08-19 |
CN101509264B CN101509264B (en) | 2011-12-07 |
Family
ID=41001785
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009101196564A Active CN101509264B (en) | 2009-03-25 | 2009-03-25 | One-step pore-creating, segmenting high pressure cement grout construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101509264B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102787602A (en) * | 2012-08-31 | 2012-11-21 | 中国水利水电第七工程局成都水电建设工程有限公司 | Curtain grouting technique |
CN103485345A (en) * | 2013-09-26 | 2014-01-01 | 葛洲坝集团基础工程有限公司 | Construction method for covering layer closed porthole high-pressure curtain grouting |
CN103898873A (en) * | 2014-03-25 | 2014-07-02 | 安徽水安建设集团股份有限公司 | Water seepage plugging construction method of shaft construction seams under high water head |
CN104594370A (en) * | 2014-11-27 | 2015-05-06 | 中国电建集团贵阳勘测设计研究院有限公司 | High-pressure combined flushing grouting method and structure in karst region |
CN106869132A (en) * | 2017-02-22 | 2017-06-20 | 中国水利水电第九工程局有限公司 | A kind of upper uphole Curtain Grouting Construction method |
CN109973098A (en) * | 2019-01-08 | 2019-07-05 | 中铁二院工程集团有限责任公司 | A kind of goaf grouting reinforcing caving zone drilling construction method |
CN113174927A (en) * | 2021-03-31 | 2021-07-27 | 山东高速岩土科技有限公司 | Reinforcement construction method of micro pile for soft soil foundation |
CN114232631A (en) * | 2021-12-02 | 2022-03-25 | 福建省天硕建设发展有限公司 | Dynamic water foundation pit cofferdam systematic grouting process |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108589938B (en) * | 2018-04-10 | 2020-10-20 | 李旺雷 | Cement grouting plugging process |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003193503A (en) * | 2001-12-27 | 2003-07-09 | Kanto Regional Development Bureau Ministry Of Land Infrastructure & Transport | Method for filling cavity caused under sluice |
CN1324200C (en) * | 2005-03-04 | 2007-07-04 | 赵延龙 | Seepage control consolidation method and apparatus for reciprocating high-pressure injection grouting foundation |
CN101338563B (en) * | 2008-08-27 | 2010-06-02 | 中国水利水电第八工程局有限公司 | Sleeve grouting method and grouting device thereof |
-
2009
- 2009-03-25 CN CN2009101196564A patent/CN101509264B/en active Active
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102787602A (en) * | 2012-08-31 | 2012-11-21 | 中国水利水电第七工程局成都水电建设工程有限公司 | Curtain grouting technique |
CN103485345A (en) * | 2013-09-26 | 2014-01-01 | 葛洲坝集团基础工程有限公司 | Construction method for covering layer closed porthole high-pressure curtain grouting |
CN103898873A (en) * | 2014-03-25 | 2014-07-02 | 安徽水安建设集团股份有限公司 | Water seepage plugging construction method of shaft construction seams under high water head |
CN103898873B (en) * | 2014-03-25 | 2015-12-30 | 安徽水安建设集团股份有限公司 | To Construction of Silo seam infiltration leak-blocking construction method under high water head |
CN104594370A (en) * | 2014-11-27 | 2015-05-06 | 中国电建集团贵阳勘测设计研究院有限公司 | High-pressure combined flushing grouting method and structure in karst region |
CN106869132A (en) * | 2017-02-22 | 2017-06-20 | 中国水利水电第九工程局有限公司 | A kind of upper uphole Curtain Grouting Construction method |
CN109973098A (en) * | 2019-01-08 | 2019-07-05 | 中铁二院工程集团有限责任公司 | A kind of goaf grouting reinforcing caving zone drilling construction method |
CN113174927A (en) * | 2021-03-31 | 2021-07-27 | 山东高速岩土科技有限公司 | Reinforcement construction method of micro pile for soft soil foundation |
CN114232631A (en) * | 2021-12-02 | 2022-03-25 | 福建省天硕建设发展有限公司 | Dynamic water foundation pit cofferdam systematic grouting process |
Also Published As
Publication number | Publication date |
---|---|
CN101509264B (en) | 2011-12-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101509264B (en) | One-step pore-creating, segmenting high pressure cement grout construction method | |
CN101666234B (en) | Fracture rock no-slurry-blocking wall compound grouting construction method | |
CN104790873B (en) | Soft rock layer jet is oriented to the integrated drilling method of the anti-collapse hole of pore-forming reaming | |
CN100591866C (en) | Drifting sand layer and gravel stratum water-moving double-liquid high pressure slip-casting water-blocking construction method | |
CN106761835B (en) | A kind of Karst Tunnel leak segmenting slip casting construction method | |
CN101525881B (en) | Structure of karst strata pile holes protecting wall and method for constructing pile holes | |
CN106088094B (en) | High mountain strid Method of Arch Dam Foundation is segmented stage grouting method | |
CN107747312B (en) | Method for drilling and grouting construction of gravel stratum | |
CN108661650A (en) | A kind of rich water magmatic body area depth pozo shaft construction method | |
CN103806479A (en) | Pile foundation combined grouting reinforcement construction method combining waterproof curtain | |
CN103485345A (en) | Construction method for covering layer closed porthole high-pressure curtain grouting | |
CN108119143A (en) | A kind of vertical shaft working surface cement soluble glass paste combines grouting method with chemical grout double-round curtain | |
CN112746849B (en) | Shaft water-carrying digging and building method | |
CN105134127B (en) | A kind of anti-collapse grouting reinforcement device and its application method | |
CN103362117A (en) | Full-section grouting method for grouting section | |
CN103643994A (en) | Method for controlling water inrush and sand inrush under coal mine | |
JP6867662B1 (en) | Multi-stage simultaneous injection device | |
CN107217987A (en) | Colliery flood administers well boring method | |
CN108590716A (en) | A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method | |
CN110241837A (en) | A kind of construction method for preventing basement bottom board from cracking under high artesian geological conditions | |
CN101251020A (en) | Subsection hole-drilling repeatedly slip-casting method | |
CN107461182B (en) | Layered fracturing sand prevention method | |
CN109915071A (en) | A kind of down-hole coal bed floor grouting reinforcement process based on three steps, three speed | |
CN103132528B (en) | Chemical grouting technology | |
CN207813564U (en) | A kind of cyclic permutation grouting device of drilling pipe-fixing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
DD01 | Delivery of document by public notice |
Addressee: Li Wanglei Document name: payment instructions |
|
DD01 | Delivery of document by public notice |