CN101457590A - 一种提高钢结构建筑及其脚手架稳定性的施工方法 - Google Patents

一种提高钢结构建筑及其脚手架稳定性的施工方法 Download PDF

Info

Publication number
CN101457590A
CN101457590A CNA2007101722429A CN200710172242A CN101457590A CN 101457590 A CN101457590 A CN 101457590A CN A2007101722429 A CNA2007101722429 A CN A2007101722429A CN 200710172242 A CN200710172242 A CN 200710172242A CN 101457590 A CN101457590 A CN 101457590A
Authority
CN
China
Prior art keywords
scaffold
construction
steel structure
layer
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007101722429A
Other languages
English (en)
Other versions
CN101457590B (zh
Inventor
冯振源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN2007101722429A priority Critical patent/CN101457590B/zh
Publication of CN101457590A publication Critical patent/CN101457590A/zh
Application granted granted Critical
Publication of CN101457590B publication Critical patent/CN101457590B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种提高钢结构建筑及其脚手架稳定性的施工方法。其特征在于:在施工中,首先将搭建一层脚手架,然后将一层钢结构分块吊装就位,并在形成整体前依靠脚手架作为靠山,再将本层的钢结构分块环形连接,并与本层的脚手架可靠连接;循环上述步骤直至顶层钢结构分块环形连接,从顶层依此往下拆除脚手架。本发明的优点是在建筑施工中,可以避免脚手架的不稳定及保证钢结构分块施工的可靠安全。

Description

一种提高钢结构建筑及其脚手架稳定性的施工方法
技术领域
本发明涉及一种提高钢结构建筑及其脚手架稳定性的施工方法。
背景技术
目前在一些钢结构框架的高层建筑施工建造中,需要在建筑框架外围搭建脚手架以方便施工,但是一旦建筑物的高度很高,则由钢管、搭扣搭建而成的脚手架稳定性较差,需要另外的结构予以固定,如与建筑物的已建成结构连接等,而钢结构自身在建筑结构的搭建时,其结构的稳定性也是比较差的,因此如何在高层钢结构建筑过程中保持脚手架及钢结构自身的稳定性是我们需要解决的问题。
发明内容
本发明的目的是解决现有技术中在建造高层钢结构建筑时,脚手架及钢结构自身在搭建时所存在的稳定性差的问题,提供一种提高钢结构建筑及其脚手架稳定性的施工方法。本发明设计一种提高钢结构建筑及其脚手架稳定性的施工方法,其特征在于:在施工中,首先将搭建一层脚手架,然后将一层钢结构分块吊装就位,并在形成整体前依靠脚手架作为靠山,再将本层的钢结构分块环形连接,并与本层的脚手架可靠连接;循环上述步骤直至顶层钢结构分块环形连接,从顶层依此往下拆除脚手架。本发明的优点是在建筑施工中,可以避免脚手架的不稳定及保证钢结构分块施工的可靠安全。
下面结合实例对本发明作详细说明。
具体实施方式
在施工中,首先在地面上搭建最下层脚手架,然后在地基面上将最下层的钢结构分块逐块吊装就位,并在形成整体前依靠最下层的脚手架作为靠山,再将最下层的钢结构分块进行环形连接,连接后再与最下层的脚手架进行可靠连接,然后在最下层的基础上循环上述步骤,直至完成顶层钢结构分块的环形连接,开始从顶层依此往下拆除脚手架。
具体施工时,根据现在的脚手架的材料及搭建的工艺,一般一层脚手架的高度在7米到15米,最高的一层可以选用19米的高脚手架,由于钢结构分块受到安装位置、加工工厂、交通运输及吊装塔吊的限制,可以根据实际情况进行处理,但是通常钢结构分块的高度一般小于脚手架的高度。

Claims (1)

1、一种提高钢结构建筑及其脚手架稳定性的施工方法,其特征在于:在施工中,首先将搭建一层脚手架,然后将一层钢结构分块吊装就位,并在形成整体前依靠脚手架作为靠山,再将本层的钢结构分块环形连接,并与本层的脚手架可靠连接;循环上述步骤直至顶层钢结构分块环形连接,从顶层依此往下拆除脚手架。
CN2007101722429A 2007-12-13 2007-12-13 一种提高钢结构建筑及其脚手架稳定性的施工方法 Expired - Fee Related CN101457590B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007101722429A CN101457590B (zh) 2007-12-13 2007-12-13 一种提高钢结构建筑及其脚手架稳定性的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007101722429A CN101457590B (zh) 2007-12-13 2007-12-13 一种提高钢结构建筑及其脚手架稳定性的施工方法

Publications (2)

Publication Number Publication Date
CN101457590A true CN101457590A (zh) 2009-06-17
CN101457590B CN101457590B (zh) 2012-07-04

Family

ID=40768692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007101722429A Expired - Fee Related CN101457590B (zh) 2007-12-13 2007-12-13 一种提高钢结构建筑及其脚手架稳定性的施工方法

Country Status (1)

Country Link
CN (1) CN101457590B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102235092A (zh) * 2010-04-22 2011-11-09 上海市机械施工有限公司 悬挂式钢结构分层吊装施工工艺
CN103669886A (zh) * 2013-12-20 2014-03-26 上海市机械施工集团有限公司 环形钢结构安装中的安装方法

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1085764C (zh) * 1999-12-30 2002-05-29 王康强 高层建筑钢结构安装的施工方法
CN1676816A (zh) * 2004-04-03 2005-10-05 龙贤明 多功能建筑模架组合件

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102235092A (zh) * 2010-04-22 2011-11-09 上海市机械施工有限公司 悬挂式钢结构分层吊装施工工艺
CN102235092B (zh) * 2010-04-22 2015-01-28 上海市机械施工有限公司 悬挂式钢结构分层吊装施工工艺
CN103669886A (zh) * 2013-12-20 2014-03-26 上海市机械施工集团有限公司 环形钢结构安装中的安装方法

Also Published As

Publication number Publication date
CN101457590B (zh) 2012-07-04

Similar Documents

Publication Publication Date Title
KR19990072014A (ko) 위에서지면으로건축물을건설하는리프트업공법
CN104631822A (zh) 高层钢筋混凝土电梯井施工方法
CN102777030A (zh) 一种电梯井道模板施工平台搭设方法
CN105178199A (zh) 一种墩柱施工方法及墩柱模板
CN104895335A (zh) 一种吊柱的安装方法
CN101457590B (zh) 一种提高钢结构建筑及其脚手架稳定性的施工方法
CN203834926U (zh) 清水混凝土地下室外墙模板支模结构
CN103485574A (zh) 一种造粒塔塔顶钢筋混凝土结构施工方法
CN104989111A (zh) 钢结构高层吊装施工方法
CN206110635U (zh) 支腿自动翻转式整体提升电梯井操作平台
CN107419907B (zh) 一种炼钢塔楼钢结构平台的交错安装焊接方法
CN208280592U (zh) 自动爬升式井道筒模板装置
CN109113335A (zh) 女儿墙模板支架和施工方法
CN206844621U (zh) 一种剪力墙结构的电梯井道内可提升式自稳支撑作业平台
CN107268971B (zh) 一种超高层建筑物的双重自提升式外爬架及应用方法
CN102561196A (zh) 高墩翻模施工工艺
CN104499706A (zh) 电梯井模板平台及其施工方法
CN108979152A (zh) 用于大跨度钢桁架高空分段拼装的胎膜及其施工方法
CN103112766A (zh) 悬置于房屋建筑地下室顶板上方的施工电梯及其施工方法
CN202706495U (zh) 爬梯式空中吊篮
CN102777026A (zh) 一种贝雷架构建超长后浇板支撑体系的方法
CN203924652U (zh) 一种预制楼梯间周边剪力墙的施工平台
CN102733612B (zh) 电动葫芦轨道安装方法
CN113802858A (zh) 钢结构屋面瓦反吊施工方法
CN206034874U (zh) 一种电梯井组合式整体提升操作平台

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: SHANGHAI MECHANIZED CONSTRUCTION CO., LTD.

Free format text: FORMER NAME: SHANGHAI CITY MACHINERY CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Patentee after: Shanghai Mechanized Construction Group Co., Ltd.

Address before: 201802 Shanghai City, Jiading District Nanxiang Town, Shanghai Yi Road No. 1255

Patentee before: Shanghai Mechanized Construction Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120704

Termination date: 20191213

CF01 Termination of patent right due to non-payment of annual fee