CN101392536A - Composite foundation of composite pile with different stiffness - Google Patents

Composite foundation of composite pile with different stiffness Download PDF

Info

Publication number
CN101392536A
CN101392536A CNA200810121621XA CN200810121621A CN101392536A CN 101392536 A CN101392536 A CN 101392536A CN A200810121621X A CNA200810121621X A CN A200810121621XA CN 200810121621 A CN200810121621 A CN 200810121621A CN 101392536 A CN101392536 A CN 101392536A
Authority
CN
China
Prior art keywords
pile
composite
rigid
flexible
composite foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA200810121621XA
Other languages
Chinese (zh)
Inventor
朱奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNA200810121621XA priority Critical patent/CN101392536A/en
Publication of CN101392536A publication Critical patent/CN101392536A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a composite foundation with compound piles in different rigidities. The composite foundation comprises a rigid pile, a flexible pile, soil and mattress layers, wherein the rigid pile adopts a long pile; the end of the rigid pile is placed in a deep force bearing layer; the rigid pile is weak in load transfer capability; the flexible pile adopts a short pile; the end of the flexible pile is placed in a shallow force bearing layer; and the rigid pile and the flexible pile adopt the mattress layers with different variable-thickness materials. Compared with the prior composite foundation, the composite foundation with compound piles in different rigidities adopts the long pile as the rigid pile which is large in effective pile length and embodies bearing capacity, and adopts the short pile as the flexible pile small in effective pile length. The composite bearing structure with the long pile and the short pile can greatly save material cost on the basis of no reduction of the bearing capacity so as to effectively utilize the bearing potential of pile bodies in the composite foundation, thereby adapting to the feature that the additional stress of the foundation decreases from the top down.

Description

Composite foundation of composite pile with different stiffness
Technical field
The present invention relates to a kind of composite foundation of composite pile with different stiffness.
Background technology
Conventional piles bluk recombination ground adopts single stake, the rigidity of stabilization zone complex is identical, because under load action, subsidiary stress increases along with the degree of depth and reduces in the ground, the ground strain also reduces gradually, required foundation stiffness is corresponding to diminish, and adopts single pile composite foundation easily to cause two kinds of bad tendencies: bottom stabilization zone rigidity is excessive to seem waste or top stabilization zone insufficient rigidity and causes the degree of safety deficiency.In addition, there is difference in the Stress Transfer ability of different-stiffness stake, and the rigid pile Stress Transfer degree of depth is dark, and the flexible pile Stress Transfer degree of depth is short, has the effective length phenomenon in stake aspect bearing capacity and the sedimentation, and the effective length of rigid pile is far longer than the effective length of flexible pile.
Summary of the invention
Technical problem to be solved by this invention is to overcome the deficiencies in the prior art, provides a kind of and can produce the composite foundation of composite pile with different stiffness that becomes rigidity.
For this reason, the invention provides a kind of composite foundation of composite pile with different stiffness, this composite foundation comprises rigid pile, flexible pile, soil and mattress layer, rigid pile adopts long stake, rigid pile stake end places darker bearing stratum, and a little less than the rigid pile Load Transfer ability, rigid pile is taked stub, rigid pile stake end places more shallow bearing stratum, and described rigid pile, flexible pile are taked thickening degree different materials mattress layer.
Compare the big rigid pile of effective length that will embody supporting capacity in the composite foundation of composite pile with different stiffness provided by the invention with the conventional composite ground and adopt long stake, and the little flexible pile of effective length adopts stub, the structure of this long stake and stub combination carrying can be saved material cost greatly on the basis that does not reduce supporting capacity, thereby more effectively utilize the carrying potential of pile body in the composite foundation, adapted to the feature that the ground subsidiary stress from top to bottom reduces.
Compare with the processing of conventional composite ground, the main advantage of this new technology has 3 points: one, engineering cost can save 20%~35%; Two, adopt this technology can handle complicated ground situation effectively, reduce traditional pile foundation soil compaction stake bad environment effect, help guaranteeing construction quality; Three, the duration of a project can shorten for 1/3~1/4 time, was fit to coastal Deep Thick Soft Ground Area and used, and had very high promotional value.This class composite foundation is applicable to multistory building and small sized multiple story building, and is especially more suitable for the building that basement is arranged.
Description of drawings
Fig. 1 composite foundation of composite pile with different stiffness schematic diagram.
Fig. 2 composite foundation of composite pile with different stiffness strip foundation form figure that lays out pile.
Fig. 3 composite foundation of composite pile with different stiffness raft foundation form figure that lays out pile.
Fig. 4 is A-A sectional drawing of Fig. 3.
The specific embodiment
As shown in Figure 1, composite foundation of composite pile with different stiffness is meant by rigid pile 5, flexible pile 6 and inter-pile soil body deformability coordinate to bear jointly the composite foundation of load, in the composite foundation of composite pile with different stiffness provided by the invention, composite foundation comprises rigid pile 5, flexible pile 6, soil and mattress layer, rigid pile 5 is the higher stakes of material stiffness, rigid pile 5 adopts long stake, because its rigid pile 5 is longer, therefore its end places darker bearing stratum, flexible pile 6 is the lower stakes of material stiffness, flexible pile 6 is taked stub, and the stake of flexible pile 6 is grown up long less than the stake of rigid pile greatly, because flexible pile 6 is shorter, therefore its end places more shallow bearing stratum, described rigid pile 5, flexible pile 6 is taked thickening degree different materials mattress layer, and mattress layer 3 thickness of cushion cap 1 following rigid pile 5 upper ends are 300mm, and mattress layer 3 adopts grit material; Flexible pile 6 place's mattress layer thickness 4 are 100mm, and mattress layer 4 adopts rubble to add the coarse sand material.Also have the thick pea gravel concreten leveling layer 2 of 100mm in addition among Fig. 1, leveling layer below 2 except that the mattress layer of flexible pile 6 and rigid pile 5 top bit other position mattress layers be 200mm.Rigid pile 5 can be reinforced concrete pile or piling bar in the present embodiment, its top absolute altitude is lower than flexible pile 6 top absolute altitude 200mm, after adopting this mode to adjust the height of piles with different, reduce the stress concentration of rigid pile 5 on the one hand, make flexible pile 6 and soil load-bearing passively on the other hand, having increased native normal stress, thereby improved pile side friction, can be cement mixing pile or lime pile at this flexible pile 6.
Below in conjunction with accompanying drawing two kinds of embodiment of the present invention are described in detail:
Composite foundation provided by the invention can adopt strip foundation and two kinds of forms of raft foundation, and as Fig. 2, Fig. 3, shown in Figure 4, when adopting strip foundation, the basis is long-pending suitable big with soil contact face, thereby increases native load share ratio.Rigid pile 5 should be arranged in the building controls sedimentation and stablize on the major control active position, as the edge stake, angle point stake and the upper load ability that are positioned at building play direct acting, and rigid pile 5 general arrangement centers of gravity should be consistent with the building centre of form.Flexible pile 6 compensates bearing capacity according to the upper load size.
When adopting raft foundation, rigid pile 5 and flexible pile 6 arrange that evenly spaced apart, looking different situations has quincunx and two kinds of arrangement forms of rectangle.Be provided with beam at rigid pile 5 positions, make lattice raft plate, avoid rigid pile 5 stress to concentrate and damage.
Total settlement of the present invention comprises the decrement and the substratum sedimentation of inter-pile soil body, and the substratum sedimentation can adopt traditional layerwise summation method to calculate, and this method can be found in the composite foundation document.The stabilization zone decrement is taked the composite modulus method, and composite modulus calculates takes following formula
E c = ( m 1 H r E r λ r · γ r th λ r + λ r λ r th λ r + γ r + H d E d + m 2 H f E f λ f · γ f th λ f + λ f λ f th λ f + γ f + H d E d + 1 - m 1 - m 2 H r E S + H d E d ) H r
E in the formula cComposite modulus for composite foundation of composite pile with different stiffness; m 1Be rigid pile 5 replacement ratios; m 2Be flexible pile 6 replacement ratios; E rModulus of deformation for rigid pile 5; E fModulus of deformation for flexible pile 6; E sModulus of compressibility for soil; E dBe the mattress layer modulus; H rFor 5 of rigid pile long; H fFor 6 of flexible piles long; H dBe mattress layer thickness; λ rrH r, μ rBe native parameter of 5 week of rigid pile; λ ffH f, μ fBe native parameter of 6 week of flexible pile; γ r = n r H r A r E r , n rBe 5 native parameters of end of rigid pile; γ f = n f H f A f E f , n fBe 6 native parameters of end of flexible pile; All native parameters of stake and the native calculation of parameter of stake end can be found in the pile foundation document.
Bearing capacity formula of the present invention can be taked following formula
f sp , k = β 1 m 1 R 1 A p 1 + β 2 m 2 R 2 A p 2 + β 3 ( 1 - m 1 - m 2 ) f sk
F in the formula Sp, kBe the Bearing Capacity of Composite Foundation characteristic value; m 1Be rigid pile 5 replacement ratios; m 2Be flexible pile 6 replacement ratios; f S, kBe the inter-pile soil characteristic load bearing capacity; R 1Be rigid pile 5 bearing capacity of single pile characteristic values; R 2Be flexible pile 6 bearing capacity of single pile characteristic values; A P1Section area for rigid pile 5; A P2Section area for flexible pile 6; β 1Be rigid pile 5 bearing capacity performance degree, numerical value is got between 0.85~1.0, β 2Be flexible pile 6 bearing capacity performance degree, numerical value is got between 0.7~0.8, β 3Be inter-pile soil bearing capacity performance degree, numerical value is got between 0.9~1.0.During engineering was used, soil property was poor more, the stake replacement ratio is high more, building is important more, and bearing capacity performance degree is got high value; Otherwise get low value.
The present invention includes following construction sequence: first construction rigid pile 5 flexible pile 6 of constructing again, but rigid pile 5 and flexible pile 6 continuous productive processes, when partially rigid stake 5 construction finish reserve work plane after, just can organize flexible pile 6 construction of marching into the arena, thereby to shorten the construction period greatly than the conventional composite foundation construction period.
Detection mode of the present invention will adopt the composite foundation static load test, and composite foundation static load test area is taked the identical fritter equivalent area of replacement ratio, and stock mould is set around mattress layer, and mattress layer should pass through precompressed before loading.The static load test curve is gradual shape usually, determines the Bearing Capacity of Composite Foundation characteristic value according to sedimentation and bearing plate relative deformation value 0.002~0.003 corresponding bearing capacity.

Claims (6)

1, a kind of composite foundation of composite pile with different stiffness, it is characterized in that: this composite foundation comprises rigid pile, flexible pile, soil and mattress layer, rigid pile adopts long stake, rigid pile stake end places darker bearing stratum, flexible pile is taked stub, flexible pile stake end places more shallow bearing stratum, and described rigid pile, flexible pile are taked thickening degree different materials mattress layer.
2, composite foundation of composite pile with different stiffness according to claim 1 is characterized in that: flexible pile is cement mixing pile or lime pile.
3, composite foundation of composite pile with different stiffness according to claim 1 and 2 is characterized in that: rigid pile is reinforced concrete pile or piling bar.
4, composite foundation of composite pile with different stiffness according to claim 1 and 2, it is characterized in that: reduce the high 100mm of rigid pile stake top mark, increase the high 100mm of flexible pile stake top mark, strengthen rigid pile position mattress layer thickness 100mm, reduce flexible pile position mattress layer thickness 100mm; Rigid pile position mattress layer adopts the low material of modulus, and flexible pile position mattress layer adopts the high material of modulus.
5, composite foundation of composite pile with different stiffness according to claim 4 is characterized in that: rigid pile position mattress layer adopts grit material; Flexible pile position mattress layer adopts rubble to add the coarse sand material.
6, composite foundation of composite pile with different stiffness according to claim 1 and 2 is characterized in that: rigid pile is reinforced concrete pile or piling bar, and rigid pile stake top absolute altitude is lower than flexible pile stake top absolute altitude 200mm.
CNA200810121621XA 2008-10-15 2008-10-15 Composite foundation of composite pile with different stiffness Pending CN101392536A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA200810121621XA CN101392536A (en) 2008-10-15 2008-10-15 Composite foundation of composite pile with different stiffness

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA200810121621XA CN101392536A (en) 2008-10-15 2008-10-15 Composite foundation of composite pile with different stiffness

Publications (1)

Publication Number Publication Date
CN101392536A true CN101392536A (en) 2009-03-25

Family

ID=40493030

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA200810121621XA Pending CN101392536A (en) 2008-10-15 2008-10-15 Composite foundation of composite pile with different stiffness

Country Status (1)

Country Link
CN (1) CN101392536A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155022A (en) * 2011-04-25 2011-08-17 上海市城市建设设计研究院 Construction method for immersed tube tunnel pile foundation
CN102493470A (en) * 2011-11-16 2012-06-13 中铁三局集团有限公司 Foundation treatment method for simulating rigidly enlarged foundation
CN102839648A (en) * 2012-09-19 2012-12-26 山东大学 Low intensity rigid pile-water permeability concrete pile novel binary composite foundation and treatment method of composite foundation
CN102839683A (en) * 2012-09-19 2012-12-26 山东大学 Discrete pile-water permeability concrete pile novel binary composite foundation and treatment method of composite foundation
CN102839647A (en) * 2012-09-19 2012-12-26 山东大学 Stirring pile-permeable concrete pile compound foundation and treatment method thereof
CN103046532A (en) * 2012-12-31 2013-04-17 中国建筑西南勘察设计研究院有限公司 Variable stiffness leveling prestressed pipe pile compound foundation
CN103510533A (en) * 2012-06-15 2014-01-15 中国石油化工股份有限公司 Rigidity-variable round raft foundation of steel storage tank
CN104631252A (en) * 2015-02-15 2015-05-20 浙江大学 Method for controlling cumulative settlement of pile-supported subgrade strengthening pile
CN105862535A (en) * 2016-04-28 2016-08-17 宁波高新区围海工程技术开发有限公司 Dredger fill solidification pile roadbed and construction method thereof
CN113073639A (en) * 2021-04-13 2021-07-06 兰州大学 Stepped loess foundation reinforcing method and built variable-rigidity combined pile composite foundation

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155022A (en) * 2011-04-25 2011-08-17 上海市城市建设设计研究院 Construction method for immersed tube tunnel pile foundation
CN102493470A (en) * 2011-11-16 2012-06-13 中铁三局集团有限公司 Foundation treatment method for simulating rigidly enlarged foundation
CN103510533A (en) * 2012-06-15 2014-01-15 中国石油化工股份有限公司 Rigidity-variable round raft foundation of steel storage tank
CN103510533B (en) * 2012-06-15 2015-09-02 中国石油化工股份有限公司 Rigidity-variable round raft foundation of steel storage tank
CN102839683A (en) * 2012-09-19 2012-12-26 山东大学 Discrete pile-water permeability concrete pile novel binary composite foundation and treatment method of composite foundation
CN102839647A (en) * 2012-09-19 2012-12-26 山东大学 Stirring pile-permeable concrete pile compound foundation and treatment method thereof
CN102839647B (en) * 2012-09-19 2015-05-27 山东大学 Stirring pile-permeable concrete pile compound foundation and treatment method thereof
CN102839648B (en) * 2012-09-19 2015-08-12 山东大学 Low-intensity rigid pile-permeable concrete stake dual compound foundation and processing method
CN102839648A (en) * 2012-09-19 2012-12-26 山东大学 Low intensity rigid pile-water permeability concrete pile novel binary composite foundation and treatment method of composite foundation
CN102839683B (en) * 2012-09-19 2015-09-16 山东大学 Granular pile-permeable concrete stake dual compound foundation and processing method
CN103046532A (en) * 2012-12-31 2013-04-17 中国建筑西南勘察设计研究院有限公司 Variable stiffness leveling prestressed pipe pile compound foundation
CN104631252A (en) * 2015-02-15 2015-05-20 浙江大学 Method for controlling cumulative settlement of pile-supported subgrade strengthening pile
CN105862535A (en) * 2016-04-28 2016-08-17 宁波高新区围海工程技术开发有限公司 Dredger fill solidification pile roadbed and construction method thereof
CN105862535B (en) * 2016-04-28 2018-06-19 宁波高新区围海工程技术开发有限公司 A kind of construction method of barged-in fill curing stake roadbed
CN113073639A (en) * 2021-04-13 2021-07-06 兰州大学 Stepped loess foundation reinforcing method and built variable-rigidity combined pile composite foundation

Similar Documents

Publication Publication Date Title
CN101294396A (en) Different-stiffness composite pile composite foundation and processing method
CN101392536A (en) Composite foundation of composite pile with different stiffness
US8173241B2 (en) Sandwich system
CN102561132B (en) Plate supporting type embankment structure for post-construction settlement controlling of deep soft soil foundation on high-grade highway
CN101307609A (en) Deviation rectifying method for pile foundation architecture inclination
CN107268573A (en) The composite construction of soft soil foundation
CN114319472A (en) Construction method for settlement, reinforcement and lifting of residential building foundation
JP5318918B2 (en) Construction method of embankment on soft ground and its embankment structure
CN101200888A (en) Construction method of composite foundation
CN102535500A (en) Reducing and sinking pile-supported embankment for treating soft soil foundation under large-area stacked load at ground and design method for reducing and sinking pile-supported embankment
CN207919486U (en) A kind of deep water soft soil foundation quay wall structure
JP5014759B2 (en) Ground improvement method
CN210507403U (en) Construction structure of soft foundation treatment transition section of plastic drainage plate and CFG pile
CN103074885B (en) Method for foundation settlement control
CN201254728Y (en) Pile and earthwork cellular chamber composite foundation
JP4874739B2 (en) Construction method of embankment on soft ground and its embankment structure
CN104652462B (en) The pre-thrust-type mattress layer in building compound foundation pile top
CN216689341U (en) Composite foundation treatment structure with combined effect of soil compaction piles and CFG piles
CN107747307A (en) A kind of high-moisture percentage deep & thick silt treatment process of composite foundation
CN211973356U (en) Soft soil foundation dyke structure
CN208685585U (en) A kind of storage terrace settlement Control system
CN210368867U (en) Superimposed structure of homogeneity earth dam and rock-fill dam
CN100999172B (en) Construction method of artificial landscape mountain
CN207419517U (en) Composite foundation reinforcement rockfill barrier wall structure
CN113073639A (en) Stepped loess foundation reinforcing method and built variable-rigidity combined pile composite foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20090325