CN101363273A - High altitude rootless construction platform and construction method thereof - Google Patents

High altitude rootless construction platform and construction method thereof Download PDF

Info

Publication number
CN101363273A
CN101363273A CNA200810079240XA CN200810079240A CN101363273A CN 101363273 A CN101363273 A CN 101363273A CN A200810079240X A CNA200810079240X A CN A200810079240XA CN 200810079240 A CN200810079240 A CN 200810079240A CN 101363273 A CN101363273 A CN 101363273A
Authority
CN
China
Prior art keywords
unrooted
seat board
altitude
cylindrical shell
junction plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA200810079240XA
Other languages
Chinese (zh)
Other versions
CN101363273B (en
Inventor
杨雷平
平玲玲
秦连根
许建林
付文斌
史杰
常亚军
李晋杰
贾旭斌
雷秀清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Sanjian Group Co Ltd
Original Assignee
Shanxi No3 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi No3 Construction Engineering Co filed Critical Shanxi No3 Construction Engineering Co
Priority to CN200810079240XA priority Critical patent/CN101363273B/en
Publication of CN101363273A publication Critical patent/CN101363273A/en
Application granted granted Critical
Publication of CN101363273B publication Critical patent/CN101363273B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a high-altitude rootless construction platform and a building method thereof, which solves the technical problem of high safety risk of the platform when a large-scale section cantilever steel beam is used for bearing. The high-altitude rootless construction platform comprises a reinforced concrete cylinder (1), a platform mechanism, an upper cable stayed mechanism and a lower knee-braced mechanism. The platform mechanism, the upper cable stayed mechanism and the lower knee-braced mechanism are fixedly connected with the reinforced concrete cylinder (1) by a plurality of inner rootless bed plates and outer rootless bed plates which are evenly and fixedly arranged on the circumference of the reinforced concrete cylinder (1), each outer rootless bed plate A (2) is fixedly provided with a cantilever (6), a plurality of cantilevers are radially arranged on the circumference of the reinforced concrete cylinder (1), a plurality of sandalwood strips (17) are arranged between every two adjacent cantilevers and are provided with planks (20). The building method of the high-altitude rootless construction platform is also provided. The building method is a good choice of the reinforced concrete high-altitude cantilever structure construction for construction enterprises.

Description

A kind of high-altitude unrooted operation platform and building method thereof
Technical field
The present invention relates to a kind of high-altitude operation platform, particularly a kind of construction support platform and building method thereof of reinforced concrete construction building.
Background technology
Along with the progress of society, basic variation is also taking place in the various building of construction field, because the needs of building architectural design and functional characteristics are chosen structure outside the steel concrete high-altitude and increased gradually.Exist certain degree of difficulty at choosing structure construction outside the steel concrete high-altitude, difficult point is mainly chosen support system and the construction operation platform scheme in the structure construction outside steel concrete, traditional way has two kinds substantially: the first adopts steel pipe scaffold class instrument to set up whole supporting support body; It two is to adopt large-scale shaped steel to choose girder steel outward to make support platform.Above-mentioned two kinds of methods all have certain limitation and drawback, and first kind of situation is that safety is reliable, but the instrument input amount is big, labor intensive is bigger; Second kind of situation is that input amount is less, but has security risk and restricted application.Therefore at choose outside the steel concrete high-altitude structure need a kind of not only construction safety reliably, but also drop into economical rationality and the extensive construction operation platform of the scope of application.
Summary of the invention
The instrument input amount was big when a kind of high-altitude operation platform provided by the invention and building method thereof had solved the supporting support body that adopts steel pipe scaffold class instrument to set up integral body, labor intensive is bigger, and adopt large-scale shaped steel to choose girder steel outward and make the big technical problem of support platform security risk, improved the construction efficiency of construction organization effectively, not only construction safety reliably, but also drop into economical rationality and the scope of application is extensive, be that a kind of enterprise in charge of construction carries out choosing one of fine method of structure construction outside the steel concrete high-altitude.
The present invention overcomes the above problems by following scheme:
The present invention not only provides a kind of high-altitude operation platform, and the building method of this platform also is provided.
A kind of high-altitude unrooted operation platform, comprise steel concrete cylindrical shell 1, platform mechanism, go up oblique machine drawing structure and declivity support mechanism, described platform mechanism is at the seat board A2 outside the cylindrical shell excircle evenly is set with a plurality of unrooteds of the same absolute altitude place of described steel concrete cylindrical shell 1, evenly be set with seat board A3 in a plurality of unrooteds along the cylindrical shell inner periphery, one end of a semi girder 6 and a unrooted junction plate A5 weld together, high-strength split bolt A4 is with unrooted junction plate A5, seat board A3 is fixed together in outer seat board A2 of unrooted and the unrooted, all fixedly install on the outer seat board A2 of each unrooted and be connected with a semi girder 6, make many semi girders be the distribution of radiation shape along the excircle of steel concrete cylindrical shell 1, be provided with many wingceltis bars 17 between per two semi girders that face mutually, the paralell of being made up of semi girder and wingceltis bar 17 is provided with bed board 20; Outside described each unrooted seat board A2 above steel concrete cylindrical shell 1 on same absolute altitude place be set with outside a plurality of unrooteds seat board B8 in the seat board B7 and a plurality of unrooted, an end and a unrooted junction plate B10 who goes up diagonal member 11 welds together, and high-strength split bolt B9 is fixed together seat board B8 in unrooted junction plate B10, the outer seat board B7 of unrooted and the unrooted; Outside described each unrooted seat board A2 below steel concrete cylindrical shell 1 on same absolute altitude place be set with outside a plurality of unrooteds seat board C13 in the seat board C12 and a plurality of unrooted, one end of a following hound 16 and a unrooted junction plate C15 weld together, and high-strength split bolt C14 is fixed together seat board C13 in unrooted junction plate C15, the outer seat board C12 of unrooted and the unrooted; The other end of described semi girder 6 and the described other end and the described other end of hound 16 down of going up diagonal member 11 weld together, and the angle α between semi girder 6 and the last diagonal member 11 is 30 degree, and the angle β between semi girder 6 and the following hound 16 is 30 degree.
The described angle r that is at grade between two semi girders 6 that face mutually that radiation shape distributes is 18 degree.
Described platform mechanism periphery is provided with guard rail standpipe 18 and guard rail 19.
A kind of method of building the described high-altitude of claim 1 unrooted operation platform comprises the following steps:
A, when the structure construction of steel concrete cylindrical shell 1, adopt transit accurately will descend, in, the vertical absolute altitude of the outer seat board of last three groups of unrooteds and the interior seat board of unrooted draws survey, the template of cylindrical shell 1 install and the reinforcing bar binding process in three groups of unrooteds in outside seat board and the unrooted seat board fixedly secure, assurance does not produce displacement when guaranteeing concreting;
B, after concrete strength reaches design strength 75%, the radiation shape support body of being made up of radiation shape semi girder 6, following hound 16, unrooted junction plate A5 and unrooted junction plate C15 that adopts high-strength split bolt 4,14 to make in advance is connected with the outer seat board C12 of unrooted with the outer seat board A2 of unrooted, the Tightening moment of high-strength split bolt 4,14 is not less than controlling value, and finishes the installation of whole radial pattern semi girder support bodys one by one;
After c, radiation shape support body all are connected and fixed, the ring-type purlin 17 that to make in advance and number with high-strength connecting bolt is connected with radiation shape semi girder, the Tightening moment of high-strength connecting bolt is not less than controlling value, with being connected and fixed of ring-type purlin, carry out the installation of operation platform bed board 20 simultaneously, every operation platform bed board 20 and ring-type purlin 17 are for spot welding is connected, and every spot welding number is no less than 9 points, one by one with ring-type purlin 17 and 20 installations of operation platform bed board;
After d, the high-altitude unrooted operation platform substructure installation, weld the outer end of the body of tiltedly trying to stop people from fighting each other that the last diagonal member 11 made in advance and unrooted junction plate B10 are welded into one and the end of radiation shape semi girder 6, be fixed together with the high-strength split bolt 9 outer seat board B7 of body and unrooted that will tiltedly try to stop people from fighting each other, the Tightening moment of high-strength split bolt 9 is not less than controlling value, diagonal member on all 11 is connected finish successively;
E, with 19 fixed installations of peripheral guard rail standpipe 18 and guard rail.
The present invention for the construction of choosing structure outside the steel concrete high-altitude provide a kind of not only construction safety reliably, but also drop into economical rationality and the extensive construction operation platform of the scope of application.Solved the technical problem of choosing structure construction supporting system and construction operation platform outside the steel concrete high-altitude, more traditional constructure scheme can be saved and drop into 15~25%, overall economic efficiency and social benefit are obvious, are a kind of good selections of choosing structure construction outside the enterprise in charge of construction organization steel reinforced concrete high-altitude.
Description of drawings:
Accompanying drawing 1 is an integral planar schematic diagram of the present invention
Accompanying drawing 2 is encorbelment structural representations of beam of unrooted
Accompanying drawing 3 is structural representations of unrooted junction plate
Accompanying drawing 4 is high-altitude unrooted operation platform process flow diagrams
The specific embodiment
A kind of high-altitude unrooted operation platform, comprise steel concrete cylindrical shell 1, platform mechanism, go up oblique machine drawing structure and declivity support mechanism, described platform mechanism is at the seat board A2 outside the cylindrical shell excircle evenly is set with a plurality of unrooteds of the same absolute altitude place of described steel concrete cylindrical shell 1, evenly be set with seat board A3 in a plurality of unrooteds along the cylindrical shell inner periphery, one end of a semi girder 6 and a unrooted junction plate A5 weld together, high-strength split bolt A4 is with unrooted junction plate A5, seat board A3 is fixed together in outer seat board A2 of unrooted and the unrooted, all fixedly install on the outer seat board A2 of each unrooted and be connected with a semi girder 6, make many semi girders be the distribution of radiation shape along the excircle of steel concrete cylindrical shell 1, be provided with many wingceltis bars 17 between per two semi girders that face mutually, the paralell of being made up of semi girder and wingceltis bar 17 is provided with bed board 20; Outside described each unrooted seat board A2 above steel concrete cylindrical shell 1 on same absolute altitude place be set with outside a plurality of unrooteds seat board B8 in the seat board B7 and a plurality of unrooted, an end and a unrooted junction plate B10 who goes up diagonal member 11 welds together, and high-strength split bolt B9 is fixed together seat board B8 in unrooted junction plate B10, the outer seat board B7 of unrooted and the unrooted; Outside described each unrooted seat board A2 below steel concrete cylindrical shell 1 on same absolute altitude place be set with outside a plurality of unrooteds seat board C13 in the seat board C12 and a plurality of unrooted, one end of a following hound 16 and a unrooted junction plate C15 weld together, and high-strength split bolt C14 is fixed together seat board C13 in unrooted junction plate C15, the outer seat board C12 of unrooted and the unrooted; The other end of described semi girder 6 and the described other end and the described other end of hound 16 down of going up diagonal member 11 weld together, and the angle α between semi girder 6 and the last diagonal member 11 is 30 degree, and the angle β between semi girder 6 and the following hound 16 is 30 degree.
The described angle r that is at grade between two semi girders 6 that face mutually that radiation shape distributes is 18 degree.
Described platform mechanism periphery is provided with guard rail standpipe 18 and guard rail 19.
A kind of method of building the described high-altitude of claim 1 unrooted operation platform comprises the following steps:
A, when the structure construction of steel concrete cylindrical shell 1, adopt transit accurately will descend, in, the vertical absolute altitude of the outer seat board of last three groups of unrooteds and the interior seat board of unrooted draws survey, the template of cylindrical shell 1 install and the reinforcing bar binding process in three groups of unrooteds in outside seat board and the unrooted seat board fixedly secure, assurance does not produce displacement when guaranteeing concreting;
B, after concrete strength reaches design strength 75%, the radiation shape support body of being made up of radiation shape semi girder 6, following hound 16, unrooted junction plate A5 and unrooted junction plate C15 that adopts high-strength split bolt 4,14 to make in advance is connected with the outer seat board C12 of unrooted with the outer seat board A2 of unrooted, the Tightening moment of high-strength split bolt 4,14 is not less than controlling value, and finishes the installation of whole radial pattern semi girder support bodys one by one;
After c, radiation shape support body all are connected and fixed, the ring-type purlin 17 that to make in advance and number with high-strength connecting bolt is connected with radiation shape semi girder, the Tightening moment of high-strength connecting bolt is not less than controlling value, with being connected and fixed of ring-type purlin, carry out the installation of operation platform bed board 20 simultaneously, every operation platform bed board 20 and ring-type purlin 17 are for spot welding is connected, and every spot welding number is no less than 9 points, one by one with ring-type purlin 17 and 20 installations of operation platform bed board;
After d, the high-altitude unrooted operation platform substructure installation, weld the outer end of the body of tiltedly trying to stop people from fighting each other that the last diagonal member 11 made in advance and unrooted junction plate B10 are welded into one and the end of radiation shape semi girder 6, be fixed together with the high-strength split bolt 9 outer seat board B7 of body and unrooted that will tiltedly try to stop people from fighting each other, the Tightening moment of high-strength split bolt 9 is not less than controlling value, diagonal member on all 11 is connected finish successively;
E, high-altitude unrooted operation platform entire infrastructure installation, after peripheral guard rail standpipe 18 and guard rail 19 be connected and fixed (it highly is not less than 1.5m), high-altitude unrooted operation platform has just been finished, after whole tie points and pad etc. are checked, can carry out choosing outside the steel concrete high-altitude use of structure support system and job platform.
As the high-altitude unrooted operation platform of choosing structure support system and construction operation outside the steel concrete high-altitude, after outside finishing the steel concrete high-altitude, choosing whole construction contents (comprising template installation, reinforcing bar binding, concreting, concrete curing, form removable etc.) of structure, high-altitude unrooted operation platform carries out the dismounting of high-altitude unrooted operation platform according to the reverse process flow process in the installation process, remove the unrooted seat board and be retained in the reinforced concrete structure China and foreign countries, miscellaneous part all can be reused.

Claims (4)

1, a kind of high-altitude unrooted operation platform, comprise steel concrete cylindrical shell (1), platform mechanism, go up oblique machine drawing structure and declivity support mechanism, it is characterized in that: described platform mechanism is at the seat board A (2) outside the cylindrical shell excircle evenly is set with a plurality of unrooteds of the same absolute altitude place of described steel concrete cylindrical shell (1), evenly be set with seat board A (3) in a plurality of unrooteds along the cylindrical shell inner periphery, one end of a semi girder (6) and a unrooted junction plate A (5) weld together, high-strength split bolt A (4) is with unrooted junction plate A (5), seat board A (3) is fixed together in outer seat board A (2) of unrooted and the unrooted, all fixedly install on the outer seat board A (2) of each unrooted and be connected with a semi girder (6), make many semi girders be the distribution of radiation shape along the excircle of steel concrete cylindrical shell (1), be provided with many wingceltis bars (17) between per two semi girders that face mutually, the paralell of being made up of semi girder and wingceltis bar (17) is provided with bed board (20); Same absolute altitude place outside described each unrooted on the steel concrete cylindrical shell (1) of the top of seat board A (2) is set with outside a plurality of unrooteds seat board B (8) in the seat board B (7) and a plurality of unrooted, an end and a unrooted junction plate B (10) who goes up diagonal member (11) welds together, and high-strength split bolt B (9) is fixed together seat board B (8) in unrooted junction plate B (10), the outer seat board B (7) of unrooted and the unrooted; Same absolute altitude place outside described each unrooted on the steel concrete cylindrical shell (1) of the below of seat board A (2) is set with outside a plurality of unrooteds seat board C (13) in the seat board C (12) and a plurality of unrooted, one end of a following hound (16) and a unrooted junction plate C (15) weld together, and high-strength split bolt C (14) is fixed together seat board C (13) in unrooted junction plate C (15), the outer seat board C (12) of unrooted and the unrooted; The other end of described semi girder (6) and the described other end and the described other end of hound (16) down of going up diagonal member (11) weld together, and the angle α between semi girder (6) and the last diagonal member (11) is 30 degree, and the angle β between semi girder (6) and the following hound (16) is 30 degree.
2, a kind of high-altitude according to claim 1 unrooted operation platform is characterized in that: the described angle r that is at grade between two semi girders (6) that face mutually that radiation shape distributes is 18 degree.
3, a kind of high-altitude according to claim 1 and 2 unrooted operation platform, it is characterized in that: described platform mechanism periphery is provided with guard rail standpipe (18) and guard rail (19).
4, a kind of method of building the described high-altitude of claim 1 unrooted operation platform comprises the following steps:
A, when the structure construction of steel concrete cylindrical shell (1), adopt transit accurately will descend, in, the vertical absolute altitude of the outer seat board of last three groups of unrooteds and the interior seat board of unrooted draws survey, the template of cylindrical shell (1) install and the reinforcing bar binding process in three groups of unrooteds in outside seat board and the unrooted seat board fixedly secure, assurance does not produce displacement when guaranteeing concreting;
B, after concrete strength reaches design strength 75%, the radiation shape support body of being made up of radiation shape semi girder (6), following hound (16), unrooted junction plate A (5) and unrooted junction plate C (15) that adopts high-strength split bolt (4,14) to make in advance is connected with the outer seat board C (12) of unrooted with the outer seat board A (2) of unrooted, the Tightening moment of high-strength split bolt (4,14) is not less than controlling value, and finishes the installation of whole radial pattern semi girder support bodys one by one;
After c, radiation shape support body all are connected and fixed, the ring-type purlin (17) that to make in advance and number with high-strength connecting bolt is connected with radiation shape semi girder, the Tightening moment of high-strength connecting bolt is not less than controlling value, with being connected and fixed of ring-type purlin, carry out the installation of operation platform bed board (20) simultaneously, every operation platform bed board (20) is connected for spot welding with ring-type purlin (17), every spot welding number is no less than 9 points, one by one with ring-type purlin (17) and operation platform bed board (20) installation;
After d, the high-altitude unrooted operation platform substructure installation, weld the outer end of the body of tiltedly trying to stop people from fighting each other that the last diagonal member (11) made in advance and unrooted junction plate B (10) are welded into one and the end of radiation shape semi girder (6), be fixed together with high-strength split bolt (9) the outer seat board B (7) of body and unrooted that will tiltedly try to stop people from fighting each other, the Tightening moment of high-strength split bolt (9) is not less than controlling value, diagonal member on all (11) is connected finish successively;
E, with the fixed installation of peripheral guard rail standpipe (18) and guard rail (19).
CN200810079240XA 2008-08-20 2008-08-20 High altitude rootless construction platform and construction method thereof Active CN101363273B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810079240XA CN101363273B (en) 2008-08-20 2008-08-20 High altitude rootless construction platform and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810079240XA CN101363273B (en) 2008-08-20 2008-08-20 High altitude rootless construction platform and construction method thereof

Publications (2)

Publication Number Publication Date
CN101363273A true CN101363273A (en) 2009-02-11
CN101363273B CN101363273B (en) 2010-06-02

Family

ID=40389853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810079240XA Active CN101363273B (en) 2008-08-20 2008-08-20 High altitude rootless construction platform and construction method thereof

Country Status (1)

Country Link
CN (1) CN101363273B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107035130A (en) * 2017-06-05 2017-08-11 中国建筑第二工程局有限公司 Single column high-altitude operation platform and outrigger platform
CN113389365A (en) * 2021-07-01 2021-09-14 江苏中南建设装饰有限公司 Protective structure is kept apart to assembled stereoplasm
CN114508169A (en) * 2022-01-26 2022-05-17 淮安市博彦土木工程科学研究院有限公司 Fabricated platform based on concrete single-cantilever beam and construction method thereof

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2191248Y (en) * 1994-04-09 1995-03-08 电力工业部电力建设研究所 Steel structure platform for chimney slip form construction
WO1999050137A1 (en) * 1998-03-28 1999-10-07 William Kernaghan Scaffold support bracket
JP2000328777A (en) * 1999-05-13 2000-11-28 Otis Elevator Co Elevator installing scaffold structure
US6340070B1 (en) * 2000-05-22 2002-01-22 John W Villareal, Jr. Adjustable cantilever scaffolding
CN201053200Y (en) * 2007-06-28 2008-04-30 宏润建设集团股份有限公司 Assembled
CN201265253Y (en) * 2008-08-20 2009-07-01 山西省第三建筑工程公司 High-altitude no-base construction platform

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107035130A (en) * 2017-06-05 2017-08-11 中国建筑第二工程局有限公司 Single column high-altitude operation platform and outrigger platform
CN113389365A (en) * 2021-07-01 2021-09-14 江苏中南建设装饰有限公司 Protective structure is kept apart to assembled stereoplasm
CN113389365B (en) * 2021-07-01 2022-11-15 江苏中南建设装饰有限公司 Protective structure is kept apart to assembled stereoplasm
CN114508169A (en) * 2022-01-26 2022-05-17 淮安市博彦土木工程科学研究院有限公司 Fabricated platform based on concrete single-cantilever beam and construction method thereof
CN114508169B (en) * 2022-01-26 2022-12-27 江苏华磊建设集团有限公司 Fabricated platform based on concrete single-cantilever beam and construction method thereof

Also Published As

Publication number Publication date
CN101363273B (en) 2010-06-02

Similar Documents

Publication Publication Date Title
CN202139833U (en) Cantilever scaffold for building construction
CN103243961B (en) Titanium plate steel inner tank reversed construction device for chimney of thermal power station
CN102535845A (en) Construction method of bearing frame of corridor structure
CN107989447A (en) A kind of large-scale earthing concrete tank dome steel support structure and installation method
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN101100902A (en) Inclined drawing steel truss high-supported formwork structure system and construction method thereof
CN110886227B (en) Main tower cast-in-place lower cross beam support system and construction method
CN105155431A (en) Rapid repair method for three-stand-column structure bridge with damaged lateral stand columns and undamaged beam and slab structure
CN203475806U (en) Tool type anchoring bolt assembly used for fixing shape steel cantilever beam in construction sites
CN207974601U (en) A kind of large size earthing concrete tank dome steel support structure
CN101363273B (en) High altitude rootless construction platform and construction method thereof
CN103321155B (en) Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN106150085B (en) A kind of stiffened column Formwork Installation Method
CN206873307U (en) Movable type bridge justifies pier stud work high above the ground operating platform
CN103233426A (en) Bailey beam support free of buttress in soft foundation and supporting method thereof
CN214993171U (en) Bridge bent cap construction is with assembled sectional shelf-unit platform
CN106320183A (en) Assembly type bent cap formwork system
CN205257790U (en) Fixed high -low leg handle portal crane
CN103993739B (en) The construction method of granulation tower spraying layer stiff beam
CN206448549U (en) The beam slab double deck type bracing members frame of encorbelmenting of steadiness can be improved
CN201265253Y (en) High-altitude no-base construction platform
CN211006341U (en) Assembled strength nature skeleton suitable for mound tower reinforcing bar location
CN112726411A (en) Integral dragging construction method for single-hole large cantilever steel truss girder
CN104404883A (en) Inner working platform for rapid construction of bridge pier and construction method using inner working platform
CN102619335A (en) Construction method of large-height small-sized cast-in-place concrete beam slab

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 046011 No. 6, Lane West, Taihang West Street, Shanxi, Changzhi

Patentee after: SHANXI THIRD CONSTRUCTION Co.,Ltd.

Address before: 046011 No. 6, Lane West, Taihang West Street, Shanxi, Changzhi

Patentee before: SHANXI NO.3 CONSTRUCTION ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP02 Change in the address of a patent holder

Address after: No.266 Taihang East Street, Changzhi City, Shanxi Province 046000

Patentee after: SHANXI THIRD CONSTRUCTION Co.,Ltd.

Address before: 046011 No. 6, Lane West, Taihang West Street, Shanxi, Changzhi

Patentee before: SHANXI THIRD CONSTRUCTION Co.,Ltd.

CP02 Change in the address of a patent holder