CN101228322B - 隧道施工方法 - Google Patents

隧道施工方法 Download PDF

Info

Publication number
CN101228322B
CN101228322B CN2006800271331A CN200680027133A CN101228322B CN 101228322 B CN101228322 B CN 101228322B CN 2006800271331 A CN2006800271331 A CN 2006800271331A CN 200680027133 A CN200680027133 A CN 200680027133A CN 101228322 B CN101228322 B CN 101228322B
Authority
CN
China
Prior art keywords
tunnel
construction according
tunnel construction
lock block
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2006800271331A
Other languages
English (en)
Other versions
CN101228322A (zh
Inventor
莫迪凯·尤戈尔
什洛莫·李伯曼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HASIDA BOTZER
OFER NAAMAN
Original Assignee
HASIDA BOTZER
OFER NAAMAN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HASIDA BOTZER, OFER NAAMAN filed Critical HASIDA BOTZER
Publication of CN101228322A publication Critical patent/CN101228322A/zh
Application granted granted Critical
Publication of CN101228322B publication Critical patent/CN101228322B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明提供了一种隧道施工方法,具体为在山体(12)的山坡(10)中修建一段半山峒的方法,其包括以下步骤:在所述待挖半山峒的上边缘之上沿所述段(16)形成一锁定固块(18);插入锁定构件(22),使其和所述锁定固块相交,并将其伸入所述山体中;挖掘所述锁定固块以下和以外的山体部分,形成所述半山峒的洞顶和洞底部分;重复挖掘程序,直到形成整段所述半山峒。

Description

隧道施工方法
技术领域
本发明涉及隧道施工方法,具体涉及一种在尤其是山坡的地面下修建或加宽半山峒的方法。
背景技术
本领域的技术人员皆知,在山坡上修建或加宽公路将带来许多问题,尤其是对环境包括森林造成的损害等,且可能引起山体滑坡。为了克服上述问题,人们发明了半山峒的修建方式,在实际施工中,必须支撑起此半山峒的洞顶,然而,到目前为止尚未找到一个完美的解决方法。如图1所示,修建一般隧道2时,两个反方向的压力(如箭头F、F1所示)被施于隧道的顶部,从而达到平衡。因此,根据挖掘隧道所在的地面的类型,有时需要将加固土钉6插入到地面中。使用此土钉6时,将其相对隧道弧形顶板垂直地插入到地面中,如图所示。因此,由于半山峒的洞顶没有中心反向力,上述隧道施工方法并不可行。目前所采用的明显的解决方法是采取一些侧撑或支杆,使其伸展在隧道基板(例如公路和洞顶)之间,由此提供与洞顶成自由角度的支撑力,但这种支撑支杆的缺点却是显而易见的。
发明内容
本发明的一个主要目的是克服现存于半山峒施工技术中的缺点,提供一种无需在隧道开口侧面使用支撑支杆的半山峒施工方法。
本发明的另一目的是提供一种半山峒施工方法,其中将锁定构件插入洞顶以上的地面中,用于牢牢支撑所述洞顶。
因此,根据本发明,提供了一种在山坡上修建半山峒的方法,其包括以下步骤:
a)在所述待挖半山峒的上边缘之上沿所述段形成一锁定固块;
b)插入锁定构件,使其和所述锁定固块相交,并将其伸入所述山体中;
c)挖掘所述锁定固块以下和以外的山体部分,形成所述半山峒的洞顶和洞底部分;
d)重复步骤c),直到形成整段所述半山峒。
附图说明
现将结合某些优选实施例并参照以下图示对本发明加以描述,以加深对本发明的理解。
对于以下图示,须知其细节的展示只是为了方便讨论本发明的优选实施例而举出的例子,目的在于使读者更容易理解本发明的原理和概念并最大程度地利用本发明。因此,在此并没有为了解释本发明而过多地显示本发明的详细结构,对图示的具体说明将使所属领域的技术人员清楚本发明的各种形式是如何付诸实践的。
在各图示中:
图1(现有技术)为一般隧道施工的图示;
图2为本发明的半山峒施工方法中第一阶段的剖面图;
图3为本发明的半山峒施工方法中第二阶段的剖面图;
图4为本发明的半山峒施工方法中第三阶段的剖面图;
图5为本发明的半山峒施工方法中第四阶段的剖面图,其中有针对滑落岩石的额外保护措施。
具体实施方式
下面参照各施工阶段,对本发明所提供的在山坡上修建一段隧道的施工方法进行说明。图2描述了该施工方法的第一阶段,图中山体12的山坡部分为10。在确定了距平面14(例如所建隧道段的公路面)的洞顶高度后,做一个小的凹陷16(例如L形的凹陷),并将锁定固块18置于凹陷16的底部20上。锁定固块18最好为柱状体,例如预制钢筋混凝土板。或者可为现浇钢筋混凝土的锁定固块。接着,使锁定构件22(通常是高负荷土钉或预应力锚锁)穿过锁定固块18打入或钻入山体12的山坡中。锁定构件22较长,目的是使伸入长度远远大于所建隧道宽度,以便提供支撑力。同样,如图所示,锁定构件与锁定固块18的平面成不同角度发散型分布,角度范围从略小于山坡10的一般角度到略大于90°。锁定构件22为所建隧道提供了达到平衡所必需的压力,该压力在一般隧道施工中通常是由“反向的半山峒”提供的,如图1所示。
对于待挖半山峒的山体12的山坡10上的地面而言,如果其包含不稳定材料例如碎裂或风化的石头、填充式土壤等,则建议首先使用已知技术固定地面,例如注入可凝固的化学物质或任何加固材料,又或者以网格形式打入锚锁或土钉。
用锁定固块18和锁定构件22将所述半山峒以上的地面固定后,即可开始从头至脚(如箭头E所示)挖掘半山峒,如图3所示。做好一段洞顶部分24时,可根据地面类型加入穿过锁定构件22的土钉26,从而在半山峒上方形成加固网。可于插入土钉26之前或之后,将喷射混凝土28施加到洞顶上。重复挖掘、继而插入土钉26(同时用喷射混凝土覆盖半山峒洞顶)的程序,直到挖掘完并形成整个半山峒,如图4所示。于是喷射混凝土28可被适当的贴面所覆盖,从而为半山峒的洞顶提供更高的强度。
如图5所示,图中是一个形成在山体12的山坡10中的半山峒,其组成了扩展公路30。在岩石或土壤存在滑落危险的情况下,可将一个形状似帽舌的突出部件32接到锁定固块18的前端,其中突出部件32可采取不同形状:其形状可使滑落的岩石保持其运动继而越过公路30到达山坡10的另一部分34,也/或可采取槽形以挡住滑落的土壤或岩石。
本领域的技术人员易知,本发明不仅限于前述图示实施例的具体细节,且在不脱离本发明的精神或主要特性的前提下,本发明可实施为其他特定形式。因此从任何角度来说都应将所述实施例视作示例性而非限制性的,从而由所附权利要求书而非前述说明来指出本发明的范围;且因此任何改变,只要其属于权利要求等效物的含义和范围,就应视作属于本发明。

Claims (8)

1.一种隧道施工方法,所述方法包括以下步骤:
a)在待挖半山峒的上边缘之上区域形成一锁定固块;
b)插入锁定构件,使其和所述锁定固块相交,并将其伸入山体中;
c)挖掘所述锁定固块以下和以外的山体部分,形成所述半山峒的洞顶和洞底部分;
d)重复步骤c),直到形成整段所述半山峒。
2.根据权利要求1所述的隧道施工方法,其特征在于:在步骤a)之前,在所述待挖半山峒上边缘之上的山坡中形成一凹陷。
3.根据权利要求1所述的隧道施工方法,其特征在于:在步骤c)之后,沿着和所述半山峒的所述洞顶几乎垂直的方向将土钉插入所述洞顶部分中。
4.根据权利要求1所述的隧道施工方法,其特征在于:在步骤c)之后,将喷射混凝土施加到所述洞顶部分。
5.根据权利要求1所述的隧道施工方法,其特征在于:在步骤d)之后,将喷射混凝土施加到整段所述半山峒的洞顶。
6.根据权利要求1所述的隧道施工方法,其特征在于:在步骤a)之前或之后,在所述待挖半山峒的山体的山坡的地面注入可凝固的化学物质或任何加固材料,或者以网格形式打入锚锁或土钉。
7.根据权利要求1所述的隧道施工方法,其特征在于:将一贴面施加到所述半山峒的所述洞顶上。
8.根据权利要求1所述的隧道施工方法,其特征在于:将一突出部件接到所述锁定固块的暴露面,从而阻止滑落的土壤和岩石。
CN2006800271331A 2005-07-26 2006-07-26 隧道施工方法 Expired - Fee Related CN101228322B (zh)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
IL169878 2005-07-26
IL169878A IL169878A (en) 2005-07-26 2005-07-26 Method for tunnel construction
PCT/IL2006/000867 WO2007013074A1 (en) 2005-07-26 2006-07-26 A method for tunnel construction

Publications (2)

Publication Number Publication Date
CN101228322A CN101228322A (zh) 2008-07-23
CN101228322B true CN101228322B (zh) 2010-12-22

Family

ID=37229059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2006800271331A Expired - Fee Related CN101228322B (zh) 2005-07-26 2006-07-26 隧道施工方法

Country Status (8)

Country Link
US (1) US20080205989A1 (zh)
EP (1) EP1910625A1 (zh)
JP (1) JP2009503294A (zh)
CN (1) CN101228322B (zh)
CA (1) CA2615102A1 (zh)
EA (1) EA200800409A1 (zh)
IL (1) IL169878A (zh)
WO (1) WO2007013074A1 (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259455B (zh) * 2019-05-14 2021-01-22 中铁十八局集团有限公司 一种高山峡谷陡溪隧道蛇缠式环绕便道施工方法
CN113047846A (zh) * 2021-03-10 2021-06-29 北京永创众信建筑设计有限公司 一种由斜坡掘进隧道的施工方法

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1517495A (zh) * 2003-01-24 2004-08-04 诺比利费拉里有限责任公司 地下工程、隧道及坑道的连续实现方法,一般包括通过引导冲孔而获得的加固工程、密封工程以及排水工程

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2528374B2 (ja) * 1990-04-09 1996-08-28 株式会社フジタ 山なみ道路の構築方法
FR2663666B1 (fr) * 1990-06-22 1996-08-30 Marcel Matiere Structure couverte en elements prefabriques.
JPH0786240B2 (ja) * 1990-11-28 1995-09-20 株式会社藤井基礎設計事務所 ハーフトンネルの構造とハーフトンネルの構築方法
JPH0718174B2 (ja) * 1990-12-14 1995-03-01 富山県 トンネル坑口部の構築法
JP3355414B2 (ja) * 1992-12-17 2002-12-09 大成建設株式会社 法面における走行路の施工方法
JP3138950B2 (ja) * 1992-12-17 2001-02-26 大成建設株式会社 法面における走行路の施工方法
JP3100922B2 (ja) * 1997-05-28 2000-10-23 株式会社宮地鐵工所 鋼・コンクリート合成ロックシェッド

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1517495A (zh) * 2003-01-24 2004-08-04 诺比利费拉里有限责任公司 地下工程、隧道及坑道的连续实现方法,一般包括通过引导冲孔而获得的加固工程、密封工程以及排水工程

Non-Patent Citations (10)

* Cited by examiner, † Cited by third party
Title
JP平3-290503A 1991.12.20
JP平4-198593A 1992.07.17
JP特开平10-331115A 1998.12.15
JP特开平6-137084A 1994.05.17
JP特开平6-185004A 1994.07.05
JP特开平6-185294A 1994.07.05
林蔚深.宝成线略广段明洞棚洞工程设计及其特点.铁道建筑 8.1985,(8),15-20.
林蔚深.宝成线略广段明洞棚洞工程设计及其特点.铁道建筑 8.1985,(8),15-20. *
蒋树屏,刘元雪.傍山隧道的一种新型结构研究.现代隧道技术 2004年增刊.2004,(2004年增刊),19-23.
蒋树屏,刘元雪.傍山隧道的一种新型结构研究.现代隧道技术 2004年增刊.2004,(2004年增刊),19-23. *

Also Published As

Publication number Publication date
JP2009503294A (ja) 2009-01-29
US20080205989A1 (en) 2008-08-28
CA2615102A1 (en) 2007-02-01
WO2007013074A1 (en) 2007-02-01
CN101228322A (zh) 2008-07-23
EA200800409A1 (ru) 2009-12-30
EP1910625A1 (en) 2008-04-16
IL169878A (en) 2010-06-16

Similar Documents

Publication Publication Date Title
KR100571102B1 (ko) 시공성이 개선된 프리스트레스트 가시설 공법의 장치
KR100855098B1 (ko) 단부 수직 트러스형 버팀보 구조 및 이를 이용한 공법
CN101215815B (zh) 适于陡峻山区的整体式悬挑结构复合道路的修筑方法
KR101103142B1 (ko) 옹벽구조체 및 그 시공방법
KR100949781B1 (ko) 옹벽 구조물 및 그 시공방법
CN211773698U (zh) 一种桩锚支护结构
KR100831332B1 (ko) 토목공사용 지하 흙막이벽 및 그의 시공방법
KR20200126199A (ko) 블록식 보강토 옹벽 및 그 시공방법
KR101149895B1 (ko) 터널 필라부 보강블록
KR20140013497A (ko) 절토지 네일링 보강사면 연결 탑다운 블록식 보강토옹벽 공법
KR20080100740A (ko) 지하합벽의 연속시공을 위한 가설 개방형 판재를 이용한흙막이벽의 역타지지구조 및 이를 적용한 건축물 지하합벽의 연속 시공방법
CN101228322B (zh) 隧道施工方法
KR101077348B1 (ko) 옹벽과 그 시공방법
CN112921986A (zh) 一种装配式地下结构及其与基坑一体化施工方法
KR100862387B1 (ko) 지압형 영구 앵커의 탑다운 시공을 위한 긴장용 키트와이를 이용한 지압형 영구 앵커의 탑다운 시공 방법
KR102111153B1 (ko) Pc강연선을 이용한 옹벽패널 구조물
KR20080025219A (ko) 데크플레이트를 사용한 지하벽체의 시공방법 및 지하벽체시공을 위한 데크플레이트
KR102218755B1 (ko) 보강토옹벽 시공 및 보수방법
KR20090013554A (ko) 역타형 수직 절취 사면 보강 옹벽의 시공방법
KR100440091B1 (ko) 블록식 옹벽의 축조구조 및 그의 시공방법
KR100667183B1 (ko) 철근다단 보강 고압그라우팅공법 및 공법에 사용되는 패커
CN209324377U (zh) 拱盖法暗挖地铁车站拱脚加固结构
KR102505365B1 (ko) 터널 숏크리트 낙하 방지용 지보재
KR101809554B1 (ko) 키락블록과 쉬트파일체를 이용한 구조물
KR200223114Y1 (ko) 암 절취사면용 옹벽 보강구조

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101222

Termination date: 20110726