CN101224603A - Demoulding method of 55mPHC tubular pile - Google Patents

Demoulding method of 55mPHC tubular pile Download PDF

Info

Publication number
CN101224603A
CN101224603A CNA2007100366107A CN200710036610A CN101224603A CN 101224603 A CN101224603 A CN 101224603A CN A2007100366107 A CNA2007100366107 A CN A2007100366107A CN 200710036610 A CN200710036610 A CN 200710036610A CN 101224603 A CN101224603 A CN 101224603A
Authority
CN
China
Prior art keywords
whole
tubular pile
pile tube
stripping
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007100366107A
Other languages
Chinese (zh)
Other versions
CN100579751C (en
Inventor
魏德新
周郁兵
王宗成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Hand In Third Board Third Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
Original Assignee
CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd filed Critical CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority to CN200710036610A priority Critical patent/CN100579751C/en
Publication of CN101224603A publication Critical patent/CN101224603A/en
Application granted granted Critical
Publication of CN100579751C publication Critical patent/CN100579751C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a stripping method of a 55m PHC tubular pile, which includes the following steps: 1. the bolts on a matchboard of an overall steel mold of the whole PHC tubular pile are removed, and then an upper die of the steel mold is lifted away; 2. a plurality of semi-round stripping roller frames are arranged, and each stripping roller frame corresponds to a roller on a lower die; 3. the pile and the lower die are rotated, the lower die is led to face upwards, and the PHC tubular pile is supported by a semi-round stripping roller bracket; 4. the lower die and the stripping roller frame are separated and the lower die is lifted away; 5. the whole PHC tubular pile is lifted to a storage yard. The invention has the advantages that: the method integrates a shoulder pole beam, a wire rope lifting tool and the stripping roller frame, thus simplifying the complex stripping process, and the PHC tubular pile is not impacted during the whole stripping process; the operation is safe during the whole stripping process and the efficiency is high.

Description

A kind of release method of 55mPHC pile tube
Technical field:
The present invention relates to the release method of PHC pile tube, particularly a kind of release method of 55mPHC pile tube.
Background technology:
Nineteen twenty has invented centrifugal process by Australian W.R HUME and has made the concrete product production technology, Japan has introduced this technology in next year, be used to make reinforced concrete pipe pile, began to make centrifugal concrete pile (Reinforced Spun High Stregth Concrete Piles is called for short the PC stake) in 1934.1967-1970 Japan has developed prestressed high strength concrete centrifuge tube stake (Pretesioned SpunHigh Stregth Concrete Piles is called for short the PHC pile tube).The PHC pile tube is the Architectural Equipment that extensively is employed at present in the heavy construction construction.The concrete-pile that uses in Japan almost is the PHC stake at present, this external American-European countries, as the U.S., France, Germany, Italy, the former Soviet Union, though and the start-up time of every country in Southeast Asia is later, but development is very fast closely during the last ten years, the pile tube of especially big specification,, its output and product specification are all above Japan.
China just begins to produce centrifugal concrete pipe (RC stake) as far back as nineteen forty-four; The sixties, developed prestressed reinforced concrete pipe pile (PC stake), and produced the PC stake of Ф 400 and Ф 550 in batches, the seventies development and production the post stressed concrete pile tube; Developed pretensioned prestressing high-strength concrete tubular pile (PHC stake) and pretensioning prestressed concrete thin-wall pipe pile (PTC stake) the late nineteen eighties, and begun to apply.
In recent years along with the requirement of construction is more and more higher, the pile tube length that water project uses is more and more longer, yet prior art can only be accomplished 50m for single-unit pile tube length, and generally be 30m, the just necessary pile extension of stake that surpasses 30m so, because pile extension can bring a lot of problems, particularly pile breaking phenomenon often takes place in PHC stake injection process, as dragon's pool port, Nanjing two, in the third stage of the project, design φ 800PHC pile tube is driven piles in December, 2005, in the piling process, serious pile breaking phenomenon has taken place, almost all interrupted, and all occurred near the joint, adopted φ 1000 pile tubes that broken pile still takes place near joint afterwards.According to statistics, PHC pile tube broken pile of 70% in the piling process occurs near the joint.Factors such as concrete process for sinking, geological conditions make some difference to broken pile, but the distinctive joint construction of PHC pile tube and this type of broken pile have bigger relation.
The release method of PHC stake at present generally is earlier patrix to be laid down, and utilizes loop wheel machine rotation counterdie then, and the PHC stake is rolled out from counterdie, and such release method is very easy to cause the damage of PHC stake and punching block.External also have a release method that adopts vacuum cup, after patrix is laid down, with vacuum cup with the PHC pile tube hold, handling is to the pile tube stockyard, this method is more loaded down with trivial details, cost is also high.
Summary of the invention:
Technical problem to be solved by this invention is to provide a kind of release method of 55mPHC pile tube, and this release method can successfully successfully take off the 55mPHC pile tube from punching block.
Technical problem to be solved by this invention can be achieved through the following technical solutions:
A kind of release method of 55mPHC pile tube is characterized in that, comprises the steps:
1, earlier the Bolt dismantling on the matchboard in the whole punching block of whole PHC pile tube is got off, hang away the patrix in the punching block;
2, several demoulding turning rolls are installed, each demoulding turning rolls is corresponding with the running wheel on the counterdie;
3, rotation pile tube and counterdie make counterdie up, and the PHC pile tube is supported on the demoulding turning rolls;
4, counterdie and demoulding turning rolls are separated, hang away counterdie;
5, at last whole PHC pile tube hung the stockyard.
The advantage of the inventive method is: this method oversimplifies loaded down with trivial details in the past knockout course in conjunction with shoulder pole girder and steel wire rope suspender and demoulding turning rolls, and whole knockout course, the PHC pile tube can not impacted, and is fool proof in the operation in the whole knockout course, and the efficient height.
Description of drawings:
Fig. 1 is the schematic diagram of the step 1 of release method of the present invention.
Fig. 2 is the schematic diagram of the step 2 of release method of the present invention.
Fig. 3 is the schematic diagram of the step 3 of release method of the present invention.
Fig. 4 is the schematic diagram of the step 4 of release method of the present invention.
Fig. 5 is the schematic diagram of the step 5 of release method of the present invention.
Fig. 6 is the structural representation of demoulding turning rolls of the present invention.
Fig. 7 is the left view of Fig. 6.
Fig. 8 is the vertical view of Fig. 6.
The specific embodiment:
Further specify the present invention below in conjunction with accompanying drawing.
As Fig. 1-shown in Figure 5, a kind of release method of 55mPHC pile tube comprises the steps:
1, earlier the Bolt dismantling on the matchboard in the whole punching block of whole PHC pile tube is got off, hang away the patrix in the punching block;
2, several demoulding turning rolls 1 are installed, each demoulding turning rolls 1 is corresponding with the running wheel 21 on the counterdie 2;
3, rotation counterdie 2 makes counterdie 2 overturn 180 ° up, and left-hand thread is on PHC pile tube 3;
4, counterdie 2 and demoulding turning rolls 1 are separated, hang away counterdie 2;
5, at last whole PHC pile tube 3 hung the stockyard.
Referring to Fig. 6, Fig. 7 and Fig. 8, demoulding turning rolls 1 comprises running wheel 11 and two matchboards 12, and running wheel 11 is half garden shape, two ends with respectively with the welding of two matchboards 12, on two matchboards 12, offer bolt slot 121.
More than be one of embodiments of the present invention,, do not spend performing creative labour, on the basis of the foregoing description, can do multiple variation, can realize purpose of the present invention equally for those skilled in the art.But this variation obviously should be in the protection domain of claims of the present invention.

Claims (1)

1. the release method of a 55mPHC pile tube is characterized in that, comprises the steps:
(1), earlier the Bolt dismantling on the matchboard in the whole punching block of whole PHC pile tube is got off, hang away the patrix in the punching block;
(2), several demoulding turning rolls are installed, each demoulding turning rolls is corresponding with the running wheel on the counterdie;
(3), rotation pile tube and counterdie, make counterdie up, the PHC pile tube is supported on the demoulding turning rolls;
(4), counterdie and demoulding turning rolls separately, hang away counterdie;
(5), at last whole PHC pile tube hung the stockyard.
CN200710036610A 2007-01-18 2007-01-18 Demoulding method of 55mPHC tubular pile Active CN100579751C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710036610A CN100579751C (en) 2007-01-18 2007-01-18 Demoulding method of 55mPHC tubular pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710036610A CN100579751C (en) 2007-01-18 2007-01-18 Demoulding method of 55mPHC tubular pile

Publications (2)

Publication Number Publication Date
CN101224603A true CN101224603A (en) 2008-07-23
CN100579751C CN100579751C (en) 2010-01-13

Family

ID=39856917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710036610A Active CN100579751C (en) 2007-01-18 2007-01-18 Demoulding method of 55mPHC tubular pile

Country Status (1)

Country Link
CN (1) CN100579751C (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102423906A (en) * 2011-12-09 2012-04-25 江苏中技桩业有限公司 Turning mechanism in process of discharging finished pile from mold
CN108098985A (en) * 2017-12-01 2018-06-01 福州市鸿生建材有限公司 A kind of pretensioned prestressed concrete pipe pile technique

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102423906A (en) * 2011-12-09 2012-04-25 江苏中技桩业有限公司 Turning mechanism in process of discharging finished pile from mold
CN108098985A (en) * 2017-12-01 2018-06-01 福州市鸿生建材有限公司 A kind of pretensioned prestressed concrete pipe pile technique

Also Published As

Publication number Publication date
CN100579751C (en) 2010-01-13

Similar Documents

Publication Publication Date Title
CN206957257U (en) Spigot-and-socket edge protection column
CN100579751C (en) Demoulding method of 55mPHC tubular pile
CN104131700A (en) Method and formwork for pouring door and window cast-in-place beam
CN209799317U (en) Can have enough to meet need use pre-buried ring of scaffold frame of encorbelmenting
CN205875654U (en) Novel scaffold frame device
CN202247938U (en) Wedge-shaped foundation bolt preformed hole core formwork device
CN216042984U (en) Collapse-prevention steel pipe tower with stable base
CN214834824U (en) Large-scale modularization template demolding structure
CN104358411A (en) Device for early removal and quick removal of building formwork
CN109881667B (en) Construction platform for pouring cast-in-place pile concrete and construction method thereof
CN211229458U (en) A operation platform for cylinder mound concrete placement construction
CN209816838U (en) A construction platform for pouring bored concrete pile concrete
CN210105280U (en) Quick square tube and round tube double-clamp scaffold
CN209163831U (en) A kind of vcehicular tunnel gutter liner tool-typed formwork
CN102975282A (en) Method for forming unnonuniformly reinforcement-arranged precast pile
CN103882856B (en) A kind of pre-tensioning system centrifugal concrete pile and manufacture method with steel strand
CN213329047U (en) Geotechnical engineering unilateral isolation foundation pit supporting structure
CN219882827U (en) Precast beam pedestal
CN216239148U (en) Assembled steel concrete frame shear force wall
CN216578491U (en) Production device of prestressed concrete pile
CN220352874U (en) Steel sleeve box template for water pile group concrete bearing platform
CN217299017U (en) A supplementary mould for barricade backfill filter material
CN215441957U (en) Foundation pit slope supporting structure
CN203821375U (en) Pre-tensioning method centrifugal concrete pile with steel strands
CN219343216U (en) Template fixing structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090320

Address after: 3, Riverside Road, Xiaguan District, Jiangsu, Nanjing: 210011

Applicant after: China hand in the third board Third Engineering Co., Ltd.

Co-applicant after: China Construction Third Engineering Division Co., Ltd.

Address before: 3, Riverside Road, Xiaguan District, Jiangsu, Nanjing: 210011

Applicant before: China Communications Third Navigational Bureau 2nd Engineering Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant