CN101220595A - Application method of novel post-tensioned pre-stress soil blocking pile - Google Patents

Application method of novel post-tensioned pre-stress soil blocking pile Download PDF

Info

Publication number
CN101220595A
CN101220595A CNA2008100260037A CN200810026003A CN101220595A CN 101220595 A CN101220595 A CN 101220595A CN A2008100260037 A CNA2008100260037 A CN A2008100260037A CN 200810026003 A CN200810026003 A CN 200810026003A CN 101220595 A CN101220595 A CN 101220595A
Authority
CN
China
Prior art keywords
concrete
steel strand
retaining pile
soil blocking
blocking pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008100260037A
Other languages
Chinese (zh)
Inventor
丁仕辉
陆岸典
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong No 2 Hydropower Engineering Co Ltd
Original Assignee
Guangdong No 2 Hydropower Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No 2 Hydropower Engineering Co Ltd filed Critical Guangdong No 2 Hydropower Engineering Co Ltd
Priority to CNA2008100260037A priority Critical patent/CN101220595A/en
Publication of CN101220595A publication Critical patent/CN101220595A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

A novel application method of post-tensioned prestressing retaining pile is characterized in that after getting rid of a distance sleeve, the end of a bond-free stranded wire of the retaining pile structure is connected with a metal anchor head which is formed by squeezing and connecting a metal sleeve and the bond-free stranded wire without distance sleeve; the bond-free stranded wire in the retaining pile is isolated by the distance sleeve and cement freestone concrete; the whole stranded wire in the sleeve is packed by the cement freestone concrete; the bond-free stranded wire is colligated on a constructional steel bar cage and is combined with pouring concrete to form a concrete retaining pile after being arranged in a hole; when reaching the designed tension intensity value, the concrete enforces prestressing force to the retaining pile and uses a special anchor device for anchoring so as to improve the soil resisting ability of the retaining pile. The obvious progress and beneficial effects lie in improving the reinforcement arrangement of the concrete retaining pile, reducing the configuration of ordinary bearing steel bars in the retaining pile by using high-intensity stranded wire, thus greatly enhancing the soil resistance ability of the retaining pile to a large extent without increasing the structure size and achieving the purpose of reducing engineering cost and constructing conveniently.

Description

The application process of novel post-tensioned pre-stress soil blocking pile
Technical field
The present invention relates to shelves soil stake, the particularly application process of novel post-tensioned pre-stress soil blocking pile in the civil engineering.
Background technology
In known technology, use steel concrete soil blocking pile carries out side slope or pattern foundation pit supporting structure is a kind of supporting method commonly used, its principle is a bending resistance of utilizing the steel concrete soil blocking pile to provide, resists the soil pressure of side slope or foundation ditch, reaches the engineering purpose of side slope and foundation ditch periphery soil stabilization.
The steel concrete soil blocking pile is made up of reinforcing bar and concrete, and the soil blocking pile of cast in situs moulding can be divided into mechanical hole building stake and hand excavated pile.The mud off pore-forming is adopted in machinery pore-creating more, pore-creating to the projected depth clear hole, put reinforcing cage, downcomer concreting pile; Manually digging hole adopts pea gravel concreten retaining wall pore-forming more, to the projected depth clear hole, put reinforcing cage, concreting pile, treat that concrete reaches design strength and requires after, just can come into operation.The steel concrete soil blocking pile of the cast in situs moulding of this long-term extensive use, its weak point are that the reinforced steel bar strength of use is restricted, and often need to expend a large amount of steel concrete and satisfy designing requirement.
Summary of the invention
Purpose of the present invention is intended to overcome the deficiencies in the prior art and a kind of application process that reduces the novel post-tensioned pre-stress soil blocking pile of engineering cost, convenient construction is provided.
The object of the present invention is achieved like this: a kind of application process of novel post-tensioned pre-stress soil blocking pile comprises cement bonded sand stone concrete 1, distributing bar cage 2, steel strand support 3, no bonding steel strand 4, stake substrate anchor head 5, stake top anchorage head 6, no bonding steel wire bundle 7, reinforcing cage stirrup 8, the vertical muscle 9 of reinforcing cage, steel strand separation sleeve 10, steel wire 11; It is characterized in that, be connected with metal anchor head 5 after no bonding steel strand 4 ends of soil blocking pile structure remove separation sleeve, it is to be formed by connecting by metallic sheath and the steel strand extruding of removing separation sleeve; No bonding steel strand 4 in the soil blocking pile use steel strand separation sleeve 10 that itself and cement bonded sand stone concrete 1 are isolated, steel strand total length cement-free sand-stone concrete 1 bonds in the cover, do not have bonding steel strand 4 by the design flow colligation on distributing bar cage 2, it is inserted Kong Zhonghou and forms the concrete soil blocking pile with the concrete of building, when concrete reaches design stretch-draw intensity level, soil blocking pile is applied prestressing force and uses Special ground tackle with its anchoring, to improve the retaining soil ability of soil blocking pile.
Marked improvement of the present invention and beneficial effect are: the reinforcement manner that is to improve the steel concrete soil blocking pile, in soil blocking pile, reduce the configuration of common steel bar stress, and replace high strength steel strand, and make under the situation that does not increase physical dimension, significantly improve the retaining soil ability of soil blocking pile; Reach the purpose that reduces engineering cost, convenient construction, to overcome the deficiency of known technology.
Description of drawings
Fig. 1 is constructing structure figure of the present invention;
Fig. 2 is a connecting relation figure between no bonding steel wire bundle, steel strand support, reinforcing cage, the concrete for 1-1 of the present invention cuts open figure;
Fig. 3 is no sizing steel wire bundle detail drawing (is example with every Shu Yousan root steel hinge line);
Fig. 4 is that 2-2 sectional drawing of the present invention is the connecting relation figure between a stake substrate anchorage head, steel strand, reinforcing cage, the concrete;
Fig. 5 is steel strand stake substrate anchoring detail drawing of the present invention (is example with every Shu Yousan root steel strand, radical difference, anchor type is identical)
In Fig. 1~Fig. 5, cement bonded sand stone concrete 1, distributing bar cage 2, steel strand support 3, non-bending steel cable 4, stake substrate anchor head 5, stake top anchorage head 6 do not have bonding steel wire bundle 7, reinforcing cage stirrup 8, the vertical muscle 9 of reinforcing cage, steel strand separation sleeve 10, steel wire 11.
The specific embodiment
With reference to Fig. 1~Fig. 5, (a) according to soil blocking pile stress condition situation, the arrangement of reinforcement of calculating stake and the configuration quantity of steel strand, position etc.; (b) soil blocking pile pore-forming; (c) make reinforcing cage; (d) on reinforcing cage, dispose steel strand, and a stake end anchorage head is installed by certain direction; (e) reinforcing cage that will configure steel strand is inserted in the hole according to set direction, and fixing; (f) build pile concrete, and treat that it reaches the prestressing force desirable strength; (g) stake top ground tackle is installed, steel strand is applied prestressing force by design load, and locking; (h) stake top anchorage head is carried out the sealing off and covering anchorage protection, technology is finished.

Claims (1)

1. the application process of a novel post-tensioned pre-stress soil blocking pile comprises cement bonded sand stone concrete (1), distributing bar cage (2), steel strand support (3), does not have bonding steel strand (4), stake substrate anchor head (5), stake top anchorage head (6), do not have bonding steel wire bundle (7), reinforcing cage stirrup (8), the vertical muscle (9) of reinforcing cage, steel strand separation sleeve (10), steel wire (11); It is characterized in that, be connected with metal anchor head (5) after no bonding steel strand (4) end of soil blocking pile structure removes separation sleeve, it is to be formed by connecting by metallic sheath and the steel strand extruding of removing separation sleeve; No bonding steel strand (4) in the soil blocking pile use steel strand separation sleeves (10) that itself and cement bonded sand stone concrete (1) are isolated, steel strand total length cement-free sand-stone concrete (1) bonds in the cover, do not have bonding steel strand (4) and press the design flow colligation on distributing bar cage (2), it is inserted Kong Zhonghou and forms the concrete soil blocking pile with the concrete of building, when concrete reaches design stretch-draw intensity level, soil blocking pile is applied prestressing force and uses Special ground tackle with its anchoring, to improve the retaining soil ability of soil blocking pile.
CNA2008100260037A 2008-01-24 2008-01-24 Application method of novel post-tensioned pre-stress soil blocking pile Pending CN101220595A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008100260037A CN101220595A (en) 2008-01-24 2008-01-24 Application method of novel post-tensioned pre-stress soil blocking pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008100260037A CN101220595A (en) 2008-01-24 2008-01-24 Application method of novel post-tensioned pre-stress soil blocking pile

Publications (1)

Publication Number Publication Date
CN101220595A true CN101220595A (en) 2008-07-16

Family

ID=39630644

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008100260037A Pending CN101220595A (en) 2008-01-24 2008-01-24 Application method of novel post-tensioned pre-stress soil blocking pile

Country Status (1)

Country Link
CN (1) CN101220595A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101942833A (en) * 2010-09-30 2011-01-12 建研地基基础工程有限责任公司 Frameless unbonded post-tensioned prestressed uplift filling pile and construction method thereof
CN102322060A (en) * 2011-06-29 2012-01-18 安徽省建设工程勘察设计院 Composite prestressing retaining pile
CN102409672A (en) * 2011-08-18 2012-04-11 从卫民 Tube pile provided with posttensioned prestressing steel noose hole and posttensioned prestressing pulling tube pile
CN103174134A (en) * 2013-04-01 2013-06-26 中铁隧道勘测设计院有限公司 Prestressed concrete pile with recoverable steel strands and construction method
CN103276738A (en) * 2013-05-28 2013-09-04 广东水电二局股份有限公司 Method for optimizing retaining structure reinforcing bars of foundation pit
CN105256834A (en) * 2014-03-21 2016-01-20 刘献刚 Building structure of underground space
CN105256826A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN107326897A (en) * 2017-07-28 2017-11-07 宁波冶金勘察设计研究股份有限公司 Armored concrete diaphram wall

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101942833A (en) * 2010-09-30 2011-01-12 建研地基基础工程有限责任公司 Frameless unbonded post-tensioned prestressed uplift filling pile and construction method thereof
CN102322060A (en) * 2011-06-29 2012-01-18 安徽省建设工程勘察设计院 Composite prestressing retaining pile
CN102409672A (en) * 2011-08-18 2012-04-11 从卫民 Tube pile provided with posttensioned prestressing steel noose hole and posttensioned prestressing pulling tube pile
CN103174134A (en) * 2013-04-01 2013-06-26 中铁隧道勘测设计院有限公司 Prestressed concrete pile with recoverable steel strands and construction method
CN103174134B (en) * 2013-04-01 2015-06-24 中铁隧道勘测设计院有限公司 Prestressed concrete pile with recoverable steel strands and construction method
CN103276738A (en) * 2013-05-28 2013-09-04 广东水电二局股份有限公司 Method for optimizing retaining structure reinforcing bars of foundation pit
CN105256826A (en) * 2014-01-24 2016-01-20 刘献刚 Building structure of underground space
CN105256834A (en) * 2014-03-21 2016-01-20 刘献刚 Building structure of underground space
CN105256835A (en) * 2014-03-21 2016-01-20 刘献刚 Building structure of underground space
CN105275012A (en) * 2014-03-21 2016-01-27 刘献刚 Building structure of underground space
CN107326897A (en) * 2017-07-28 2017-11-07 宁波冶金勘察设计研究股份有限公司 Armored concrete diaphram wall

Similar Documents

Publication Publication Date Title
CN105803925B (en) Quick connection method for prefabricated steel pipe constraint type steel concrete pier columns and cover beam
CN101220595A (en) Application method of novel post-tensioned pre-stress soil blocking pile
CN104153287B (en) There is the section assembling concrete frame bridge pier system and method for self-resetting capability
CN207194006U (en) A kind of prefabricated concrete retaining wall
CN106381804B (en) A kind of precast assembly bridge pier and its Joining Technology using U-shaped reinforcement fabrication
CN109024721B (en) Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN101718098B (en) Micro-pile combined dug composite foundation and construction method thereof
CN103806451B (en) A kind of anchorage type foundation ditch strengthening structure and construction method thereof
CN102808414A (en) Bonded post-tensioned prestressed anchoring construction method for cast-in-place concrete structure
KR200407182Y1 (en) Precasted concrete plate
CN201605588U (en) Structure for reinforcing and fixing slope surface of prestress anchoring frame beam
KR101493495B1 (en) reinforcement structure for PHC pile and constructing method of PHC pile using thereof
KR102111153B1 (en) Retaining Wall Panel Structure using PC Strand
CN207314353U (en) A kind of supporting construction applied to foundation pit
CN206512591U (en) A kind of pile pier integral structure
CN202247914U (en) Fitting-slope foundation structure for rocky slope
CN210066763U (en) Foundation pit side wall structure reinforcing and supporting device
KR20120025945A (en) Reinforcement assembly of concrete file and building foundation
CN204626424U (en) Step polygon for Channel slope plants raw building block
CN102121248A (en) Method for reinforcing and fixing sloping surface of prestressed anchorage element
KR101131631B1 (en) Assembling bridge construction method using Prestressed concrete girder with plural steel wires disposed at shear surface of tension port
CN204326067U (en) From anchoring prestress soldier pile
CN201567574U (en) Prestressed anchorage anchor pier slope reinforcing and fixing structure
CN207268110U (en) One kind tree pond Fence structure
CN204875689U (en) River levee crown brick and embankment protective structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Open date: 20080716