CN101200881A - Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process - Google Patents

Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process Download PDF

Info

Publication number
CN101200881A
CN101200881A CNA2007100603742A CN200710060374A CN101200881A CN 101200881 A CN101200881 A CN 101200881A CN A2007100603742 A CNA2007100603742 A CN A2007100603742A CN 200710060374 A CN200710060374 A CN 200710060374A CN 101200881 A CN101200881 A CN 101200881A
Authority
CN
China
Prior art keywords
existing
slideway
framework
girder
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007100603742A
Other languages
Chinese (zh)
Other versions
CN100464026C (en
Inventor
陈野
桑明宇
邹永红
张兵
张唯
苏在林
黄欣
张思兵
冯从
赵国兵
杨昌军
何国军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CNB2007100603742A priority Critical patent/CN100464026C/en
Publication of CN101200881A publication Critical patent/CN101200881A/en
Application granted granted Critical
Publication of CN100464026C publication Critical patent/CN100464026C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a girder replacement construction method of the existing railway line bridges, which applies a method of incremental launching framework. The girder replacement construction method is fulfilled according to seven steps: (1) A split slideway is respectively arranged on one side of the existing line and a framework is respectively prefabricated on the split type slideway; (2) Temporary rest piers are arranged under the existing line bridge and used to upbear a track skeleton, and the locking of seamless lines and the installation of a crossarm track are carried out on the two sections of a grider-replaced section; (3) The temporary rest piers are used to upbear the girder body of the existing line, and the bearings under the existing girder are disassembled; (4) the prefabricated framework is connected with the existing girder by a steel stranded wire; (5) A continuous jack is utilized to tow the steel stranded wire to haul the cascaded framework and the existing girder to the position required by the design; (6) The bearing side under the bottom plate of the prefabricated framework is grouted and reinforced; (7) After dropping the track and replenishing ballast, the line is resumed. The present invention has the advantages that the construction is safe and stable, the cost is reduced, the construction procedures are simplified, the construction period is shortened and the engineering cost is saved.

Description

Railway existing line bridge successively incremeantal launching method framework method changes beam construction method
Technical field:
The present invention relates to a kind of construction techniques, the special bridge successively incremeantal launching method of particularly a kind of railway existing line framework method changes beam construction method.
Background technology:
At present railway existing line bridge what change that beam construction method generally adopts is to set up the back parados, precast frame on slide plate adds the method for top iron jacking repeatedly with jack.There is following defective in this method: 1, need the disintegration seamless railway, therefore can't guarantee to block the requirement of 6 hours engineering times; The 2nd, top power apparatus requirement is very big; The 3rd, the construction plant is limited.
Summary of the invention:
Purpose of the present invention just is to overcome above-mentioned the deficiencies in the prior art, and provides a kind of railway existing line bridge successively incremeantal launching method framework method to change beam construction method, and this method need not to disintegrate seamless railway, speed of application soon, is not subjected to the restriction of construction plant.
Technical scheme of the present invention is: a kind of railway existing line bridge successively incremeantal launching method framework method changes beam construction method, it is characterized in that: finish according to the following step: 1. in existing line one side, the split slideway is set respectively, at split slideway difference precast frame; 2. set up temporary rest pier in existing line bridge bottom, hold up the section of track with temporary rest pier; And carry out gapless track locking and the cross-arm rail is installed at two sections that change the beam section; 3. support existing line beam body with temporary rest pier, remove bearing at the bottom of the existing beam; 4. with steel strand precast frame is connected with existing beam; 5. the position that utilizes continuous jack traction steel strand that the framework that is cascaded and existing beam are dragged to designing requirement; 6. at precast frame floor below bearing surface grouting and reinforcing; 7. rail, benefit quarrel recovery circuit fall.
The present invention can also adopt following technical measures:
Above-mentioned split slideway is made up of the attached slideway of main skid and two settings in parallel; The slideway surface is provided with cystosepiment, and slide block is set on the cystosepiment; Slideway and counter-force seat are connected as a single entity.
Advantage of the present invention is: 1, need not the gapless track that disintegrates in the construction, guaranteed to change the stability and safety of beam construction, once change beam 6 hours times spent only, reduced the influence to railway operation to greatest extent.2, adopt steel strand series connection Vierendeel girder and existing beam, utilize the continuous jacking of jack only to help Stability Analysis of Structures safety, and saved the input of the shaped steel that is rigidly connected, when having reduced cost, simplified construction sequence.3, in the technology of setting up slideway on the mud soft soil foundation and on slideway, pouring into a mould the Vierendeel girder concrete in mass, strengthen Bearing Capacity of Composite Foundation, shortened the duration.4, utilize gapless track to make somebody a mere figurehead technology, saved engineering cost.
Description of drawings:
Fig. 1 is the connection diagram of slideway and counter-force seat.
Fig. 2 is the sectional schematic diagram of slideway.
The specific embodiment:
Railway existing line bridge successively incremeantal launching method framework method changes beam construction method
Overall constructure scheme:
1, in existing line one side, the split slideway is set respectively, at split slideway difference precast frame.
1. slideway construction: this frame bridge is totally 3 holes, and 3 groups of slideways are arranged in every hole, and every group of slideway is made up of a main skid and two attached slideways, establishes counter-force seat 2 at prefabricated slideway 1 other end of framework.Sliding layer adopts polytetrafluoroethylene (PTFE) slide block 3 between slideway and framework, and slide block is of a size of 300 * 300 * 10mm, spacing 1.1m, the middle thick cystosepiment 4 of 15mm of filling.
The high-pressure rotary jet grouting pile pile foundation construction is adopted in substrate, and according to the different situations of slideway basis bearing load, existing beam segment base plinth movably adopts the rectangular plate type cushion cap, and the taper girder grillage is adopted in all the other locations.
The rotary churning pile stake directly is 600mm, and stake is long to be 11.4m, and bearing course at pile end is the completely decomposed glutenite, and Bearing Capacity of Composite Foundation detects through wide iron scientific research institution and reaches 613KPa, and 485KPa meets design requirement.
Slideway end face width is 50cm, and both sides are arranged 50 * 50mm angle steel usually, and end face flushes with the slideway top, and 2mm thick corrosion resistant plate in upper berth is anchored on the angle steel, and slide block is fixed on the base of frame 20mm steel plate.
Counter-force seat and slideway are linked to be integral body.The pile foundation support table basis is adopted on counter-force seat basis.Pile foundation 5 adopts the digging hole filling pile of ¢ 1600mm (not comprising dado thickness), the long 9.5m of stake, steel bar concrete grade C30; Cushion cap 6 adopts the C30 steel bar concrete, and appearance and size is 300 * 300 * 200cm.Counter-force seat column 7 is selected 4 32b i iron for use, is linked to be with the welding of 2cm steel plate.
2. framework is prefabricated.
A, according to on-site actual situations, the 1st hole framework is prefabricated in high line left side, the 2nd, 3 holes are prefabricated in frame right.When prefabricated, with the working space of existing bridge pier maintenance 1m.
B, framework are prefabricated on slideway, adopt the sand bed die between slideway at the bottom of the framework in the 80cm scope, on smear the thick M10 cement mortar of 5cm, treat the framework concrete strength reach design strength 100% after, with artificial removing sand bed die, clear up slide plane simultaneously, must keep clean and be coated with full butter.
C, steel strand duct, three slideway tops are the bellows of ¢ 100mm with internal diameter.
2, set up temporary rest pier in existing line bridge bottom.Set up temporary rest pier under the existing beam, buttress adopts universal rod body assembled, and long 10m is wide 2 meters, high 6 meters, and adopts reinforcement measure.
3, carry out the gapless track locking and the cross-arm rail is installed at two sections that change the beam section.54m buffer area (satisfy 200 times of longitudinal gradient gradients) is set changing beam section both sides, its outer 50m track strengthening district that is provided with, 1 evening before formally changing beam, block circuit, tight a bolt and lock reinforcing section, and cross-arm rail (P50 relayable rail) is installed changing under the beam section rail, arrange by spacing 8 sleepers, the cross-arm rail pads with sleeper, and shop insulation rubber cushion is isolated between two rails.The cross-arm rail connects existing line and framework top ballast tub, so that during dilatory translation, the existing line section of track carries out the transition on the cross-arm rail in the ballast tub of framework top by pulley.
4, construction is blocked in dilatory translation.
1. the section of track is built on stilts
Before the framework translation, take off the plate rail pillow end, remove the buffer area rail fastening simultaneously,, pulley (high 17cm) is installed between the section of track and cross-arm rail changing the beam section section of track with the built on stilts about 20cm of gear type track jack jack-up changing beam section circuit ballast aggregate.
2. remove joint of bridge place ballast aggregate and lid seam plate.
3. back timber.
8 manual hydraulic jacks of 250t are used in every hole on existing pier cap, remove the bearing nut, and the existing beam body of jacking simultaneously (top 100mm height) supports at the bottom of the mounting rail, and the jack oil return falls to being placed on beam on the universal rod body buttress.
4. dilatory translation.
A, treat that old back liter, the beam that falls are finished after, send and can draw the translation order by the construction commander in chief.
B, receive order after, jack by the manual synchronous translation of control box culvert and universal rod body support motion 10cm, check box culvert, universal rod body support on the translation slideway and the situation of relevant each several part whether normal.
C, start automatic integral translation.The automatic button of operation master station carries out the translation continuously automatically of translation beam, in the translation process, observes synchronous influence to framework in the translation process; Note oil pressure maximum, minimum value in the record translation process; Should monitor the stepping track of box culvert constantly revises with in good time correction with peripherals detector.
D, integral translation translation in about 3 hours put in place, adjust.
E, employing manual operation all unload up to all steel strand, remove equipment, finish construction.
5., circuit recovers on the bridge
(1), with gear type track jack jack-up rail, remove pulley and horizontal dawn rail, make the existing section of track fall to being placed in the framework ballast tub, first-class two ends buffer area fastener.
(2),, spread beam seam lid seam plate, and return ballasting within the time in previous step.
(3), manually play track lining, carry out railway roadbed with light track maintenance machinery and make firm by ramming;
(4), inspect for acceptance and open circuit.
6., go slowly after opening and line upkeep to Chang Su.
5, chassis base below bearing surface grouting and reinforcing.
After framework is in place, the chassis base below also has 10cm gap (dilatory framework needs) apart from bearing surface, around framework, seal with M10 cement mortar or sand pocket, utilizing the slip casting of high-pressure slip-casting method to fill reinforces, slurries are mixed accelerating admixture preparation, and the slideway two body side frames part of encorbelmenting reaches design strength at framework in back 120 minutes in place.Reserve grouting pipe, 3 meters of spacings, quincuncial arrangement when prefabricated.
6, remove.
(1), existing beam removes: cooperate with 2 150 tons of cranes and pursue Pin and down remove, abandon with 4 150 tons of Beam transportation vehicles and transport outside the venue.
(2), the temporary steel buttress is removed: cooperate by joint with 45 tons of jacks and down remove, until ground.
(3), existing 24, No. 25 bridge pier concretes are removed: usage mining machine band vibrating hammer is joined artificial use pneumatic pick segmentation and is removed.

Claims (2)

1. a railway existing line bridge successively incremeantal launching method framework method changes beam construction method, it is characterized in that: finish according to the following step: 1. in existing line one side, the split slideway is set respectively, at split slideway difference precast frame; 2. set up temporary rest pier in existing line bridge bottom, hold up the section of track with temporary rest pier; And carry out gapless track locking and the cross-arm rail is installed at two sections that change the beam section; 3. support existing line beam body with temporary rest pier, remove bearing at the bottom of the existing beam; 4. with steel strand precast frame is connected with existing beam; 5. the position that utilizes continuous jack traction steel strand that the framework that is cascaded and existing beam are dragged to designing requirement; 6. at precast frame floor below bearing surface grouting and reinforcing; 7. rail, benefit quarrel recovery circuit fall.
2. railway existing line bridge successively incremeantal launching method framework method according to claim 1 changes beam construction method, and it is characterized in that: above-mentioned split slideway is made up of the attached slideway of main skid and two settings in parallel; The slideway surface is provided with cystosepiment, and slide block is set on the cystosepiment; Slideway and counter-force seat are connected as a single entity.
CNB2007100603742A 2007-12-19 2007-12-19 Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process Active CN100464026C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007100603742A CN100464026C (en) 2007-12-19 2007-12-19 Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007100603742A CN100464026C (en) 2007-12-19 2007-12-19 Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process

Publications (2)

Publication Number Publication Date
CN101200881A true CN101200881A (en) 2008-06-18
CN100464026C CN100464026C (en) 2009-02-25

Family

ID=39516221

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007100603742A Active CN100464026C (en) 2007-12-19 2007-12-19 Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process

Country Status (1)

Country Link
CN (1) CN100464026C (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101660418A (en) * 2008-08-27 2010-03-03 上海市机械施工有限公司 Box culvert jack-in replacement rectangular pipe support method used for tunnel construction
CN101343861B (en) * 2008-08-22 2010-06-02 中铁六局集团有限公司 Construction method for replacing old frame bridge by new frame bridge in existing railway lines
CN101845780A (en) * 2010-05-17 2010-09-29 中铁六局集团有限公司 Construction method for reinforcing line of station wide-sleeper railway in blockade point by 5-5 fastening rails
CN101974883A (en) * 2010-10-14 2011-02-16 中铁九局集团有限公司 Bridge dragging slideway device
CN101985827A (en) * 2010-11-19 2011-03-16 中铁七局集团第一工程有限公司 Demolishing method for widened overpass of highway
CN102864706A (en) * 2012-10-11 2013-01-09 中铁六局集团天津铁路建设有限公司 Combined construction method for transforming underpass below ordinary-speed railway and building new high-speed railway
CN103410103A (en) * 2013-07-24 2013-11-27 中铁大桥局股份有限公司 Quick-beam change construction method for existing railway line of railroad
CN103726451A (en) * 2014-01-16 2014-04-16 中铁六局集团有限公司 Railway construction method of dismantling existing girder bridge and pushing frame structure in situ
CN104631345A (en) * 2014-12-22 2015-05-20 中国铁路总公司 Rapid replacing method of concrete bridge beam of dual-line electric railway
CN105274907A (en) * 2015-09-28 2016-01-27 中铁十八局集团第三工程有限公司 Monolithic track bed construction process for remodeling ballast track subgrade into ballastless track

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864726A (en) * 2010-06-11 2010-10-20 中铁大桥局集团有限公司 Reinforced pier body and pier body reinforcing method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1066229C (en) * 1995-12-04 2001-05-23 河北省石家庄公路桥梁建设总公司 Construction method of jacking and pushing bridge box and beam rear part
FR2750146B1 (en) * 1996-06-21 1998-12-18 Royer Jacques METHOD OF PLACING OR PUSHING A BRIDGE APRON
JP2004107972A (en) * 2002-09-18 2004-04-08 Mitsubishi Heavy Ind Ltd Launching method and launching machine for bridge

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101343861B (en) * 2008-08-22 2010-06-02 中铁六局集团有限公司 Construction method for replacing old frame bridge by new frame bridge in existing railway lines
CN101660418B (en) * 2008-08-27 2013-05-29 上海市机械施工有限公司 Box culvert jack-in replacement rectangular pipe support method used for tunnel construction
CN101660418A (en) * 2008-08-27 2010-03-03 上海市机械施工有限公司 Box culvert jack-in replacement rectangular pipe support method used for tunnel construction
CN101845780A (en) * 2010-05-17 2010-09-29 中铁六局集团有限公司 Construction method for reinforcing line of station wide-sleeper railway in blockade point by 5-5 fastening rails
CN101845780B (en) * 2010-05-17 2012-08-01 中铁六局集团有限公司 Construction method for reinforcing line of station wide-sleeper railway in blockade point by 5-5 fastening rails
CN101974883A (en) * 2010-10-14 2011-02-16 中铁九局集团有限公司 Bridge dragging slideway device
CN101974883B (en) * 2010-10-14 2012-02-01 中铁九局集团有限公司 Bridge dragging slideway device
CN101985827A (en) * 2010-11-19 2011-03-16 中铁七局集团第一工程有限公司 Demolishing method for widened overpass of highway
CN101985827B (en) * 2010-11-19 2012-09-26 中铁七局集团第一工程有限公司 Demolishing method for widened overpass of highway
CN102864706A (en) * 2012-10-11 2013-01-09 中铁六局集团天津铁路建设有限公司 Combined construction method for transforming underpass below ordinary-speed railway and building new high-speed railway
CN102864706B (en) * 2012-10-11 2014-09-10 中铁六局集团天津铁路建设有限公司 Combined construction method for transforming underpass below ordinary-speed railway and building new high-speed railway
CN103410103A (en) * 2013-07-24 2013-11-27 中铁大桥局股份有限公司 Quick-beam change construction method for existing railway line of railroad
CN103410103B (en) * 2013-07-24 2015-05-20 中铁大桥局集团有限公司 Quick-beam change construction method for existing railway line of railroad
CN103726451A (en) * 2014-01-16 2014-04-16 中铁六局集团有限公司 Railway construction method of dismantling existing girder bridge and pushing frame structure in situ
CN103726451B (en) * 2014-01-16 2015-10-07 中铁六局集团有限公司 A kind of existing railway tears the construction method of beam bridge original position jacking framed bridge open
CN104631345A (en) * 2014-12-22 2015-05-20 中国铁路总公司 Rapid replacing method of concrete bridge beam of dual-line electric railway
CN105274907A (en) * 2015-09-28 2016-01-27 中铁十八局集团第三工程有限公司 Monolithic track bed construction process for remodeling ballast track subgrade into ballastless track

Also Published As

Publication number Publication date
CN100464026C (en) 2009-02-25

Similar Documents

Publication Publication Date Title
CN100464026C (en) Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process
CN100572011C (en) Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method
CN102587296B (en) Self-balancing external prestressing strengthening method for bridge structure
WO2017125028A1 (en) Rail support beam low track and viaduct transition section structure for medium-low-speed magnetic suspension traffic project
CN103352400B (en) Prefabricated embedded tracks plate
CN106702910A (en) Main girder construction process for extradosed cable-stayed bridge with double towers and double cable planes
CN101550769B (en) Movable trestle
CN101691742B (en) Construction method for back cable-balancing single-side cantilever concreted beam bodies of slant-legged rigid frame bridges
CN111676819A (en) Jacking construction method for combined type temporary beam continuous reinforced line large-span frame structure bridge
CN102587282B (en) Large-section simply-supported box girder precasting and assembly process under conditions of strong wind and high altitude
CN113957793A (en) Construction method for prefabricating box girder support in complex urban environment
CN112411265A (en) Ballastless track structure suitable for large-span bridge and mounting method
CN105821764B (en) Non-fragment orbit rigidity adjuster
CN206219897U (en) Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
KR100454406B1 (en) Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent
CN106812065A (en) A kind of concrete freely-supported pre-stressed box girder construction process
CN106400615B (en) Medium-and low-speed maglev single line excavation location independence pier stud type support rail beam transition section structure
CN202298390U (en) Ballastless track rush repair device
CN106283957B (en) Medium-and low-speed maglev two-wire excavation location pile foundation joist framing type support rail beam transition section structure
CN201363154Y (en) Mobile trestle bridge
RU2352705C1 (en) Method for installation of permanent way
CN208167496U (en) Cable-stayed bridge π type concrete girder combined type cast-in-place support
CN206219912U (en) Medium-and low-speed maglev two-wire embankment location pile foundation joist framing type support rail beam transition section structure
CN211006761U (en) Mounting structure of circulating water pipe
CN206157481U (en) Compound framing type support rail roof beam transition section structure of moderate -low speed magnetic levitation double -line excavation location pile foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 300222 No. 18 South Dagu Road, Shuang Gang Town, Jinnan District, Tianjin

Patentee after: the Eighteenth Bureau of China's Railroad Group Co., Ltd.

Address before: 300222 Liu Lindong, Tianjin, Hexi District

Patentee before: the Eighteenth Bureau of China's Railroad Group Co., Ltd.

C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 300222 Tianjin Town, Jinnan District

Patentee after: the Eighteenth Bureau of China's Railroad Group Co., Ltd.

Address before: 300222 No. 18 South Dagu Road, Shuang Gang Town, Jinnan District, Tianjin

Patentee before: the Eighteenth Bureau of China's Railroad Group Co., Ltd.