CN100572011C - Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method - Google Patents

Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method Download PDF

Info

Publication number
CN100572011C
CN100572011C CNB2007100499024A CN200710049902A CN100572011C CN 100572011 C CN100572011 C CN 100572011C CN B2007100499024 A CNB2007100499024 A CN B2007100499024A CN 200710049902 A CN200710049902 A CN 200710049902A CN 100572011 C CN100572011 C CN 100572011C
Authority
CN
China
Prior art keywords
concrete
reinforcing bar
stretch
draw
internal mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2007100499024A
Other languages
Chinese (zh)
Other versions
CN101125441A (en
Inventor
韩伟
邹宏伟
王强
孙祖红
周文武
钟士全
申超
袁东
周玉兴
钟卫翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
Xinyun Emgineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway Erju Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CNB2007100499024A priority Critical patent/CN100572011C/en
Publication of CN101125441A publication Critical patent/CN101125441A/en
Application granted granted Critical
Publication of CN100572011C publication Critical patent/CN100572011C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of post-tensioned method prestressed concrete box beam whole opening prefabricated construction method, key step comprises: template, reinforcing bar and built-in fitting are installed, the placing of beam body concrete, the steam-cured or natural curing of beam body concrete, form removal, stretch-draw, postorder construction etc.; Wherein, reinforcing bar adopts pre-bundle, the integral hoisting technology concentrated, the stretch-draw step adopts pre-stretch-draw, initial tensioning and three tensioning process of whole stretch-draw, internal mold adopts the hydraulic internal mold system, the arrangement and method for construction that beam body concrete placing step adopts concrete centralized mixing, pipeline pumping to build, layering is passed continuously, builds one-shot forming by two ends to the centre is incremental.Construction method of the present invention is applicable to 32m/900t level large span, the whole opening prefabricated construction of large-tonnage prestressed concrete box girder in the special line for passenger trains.

Description

Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method
Technical field
The present invention relates to the construction method of the prestressed reinforced concrete construction of science of bridge building, belong to beam bridge prefabricating technique field.
Background technology
Prestressed reinforced concrete construction is to be developed by ordinary reinforced concrete structure, it is the abbreviation of prestressed reinforced concrete, it to alleviate dead load, improve shock resistance, give full play to material intensity, reduce construction costs, improve the structural elements stress performance and enlarge aspects such as the armored concrete scope of application, all demonstrate good effect.Be widely used in and comprised industry and aspects such as civil buildings, bridge, sleeper, pressure pipeline, electric pole, stake, liquid storage and gas storage pond jar.
The case beam of the domestic Qinhuangdao Shenyang Special Passenger Line of having built up is two kinds of 20m and 24m, and maximum weight reaches 570 tons.The beam prefabricated construction method of case comprises form work engineering, reinforced bar engineering, concrete works, prestress engineering etc.Because case beam span and beam are heavy less, its technology difficulty is less, and internal mold adopts frame for movement more, and concrete does not have to adopt the high-performance durability concrete that satisfies 100 years structural designs yet.Aspect prestress engineering, the case beam does not adopt the pre-tensioning process of band mould, and the situation underbeam body bigger at internal-external temperature difference is prone to infant cracking, and these defectives do not satisfy the needs of China's Passenger dedicated railway Bridge engineering.
The 32m/900t level post-tensioned method prestressed concrete box beam that closes peaceful railway employing is single case cross section structure, beam length 32.6m, and span 31.5m, deck-siding 13.0m, the high 3m of beam-ends, span centre deck-molding 2.8m, weight reaches 830 tons; Have volume big, from characteristics such as great, that width is big, its prefabricated construction is first domestic, the specification requirement height, and the engineering difficulty is big, can therefore not need proposition one cover to be applicable to the new technical scheme of the beam prefabricated construction of this highway section case for using for reference and have mature technique at home and abroad.
Summary of the invention
The purpose of this invention is to provide a kind of new post-tensioned method prestressed concrete box beam whole opening prefabricated construction method, this construction method is applicable to 32m/900t level large span, the whole opening prefabricated construction of large-tonnage prestressed concrete box girder in the special line for passenger trains.
The technical solution adopted for the present invention to solve the technical problems is:
Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method, its technological process as shown in Figure 1, key step comprises:
(1) template, reinforcing bar and built-in fitting etc. are installed:
This step mainly comprises sequentially: trimming bed die, adjustment side form, erection support plate and anti-fall beam slab, installation withdrawing sebific duct, lifting main body reinforcing bar, mounting rail body built-in fitting, lifting internal mold, installation end mould, lifting surfacing steel bar, the installation of bridge floor built-in fitting etc.;
(2) beam body concrete (beam body concrete) placing, beam body concrete steam-cured (or natural curing);
(3) form removal:
This step mainly comprises sequentially: withdrawing sebific duct, dismounting end mould, dismounting internal mold, loose side form etc.;
(4) stretch-draw:
This step mainly comprises sequentially: steel strand, the pre-stretch-draw of case beam, case beam initial tensioning, move beam to the whole stretch-draw of beam strorage area, concrete curing, case beam etc.;
(5) postorder construction:
This step mainly comprises sequentially: cut silk, pipeline pneumatic mortar, bridge sealing off and covering anchorage, maintenance, the appearance of case beam inspection, box beam erection, making watertight composition, construction protective layer, maintenance etc.;
Wherein:
Described main body reinforcing bar and bridge floor reinforcing bar all adopt concentrates pre-bundle, integral hoisting technology, i.e. the processing of case beam steel (comprising main body reinforcing bar and bridge floor reinforcing bar) is all finished in the reinforcing bar workshop, carries out colligation then on loose tool; Install for making things convenient for internal mold, divide two stages to carry out the colligation of case beam steel: the phase I, the main muscle that earlier beam body master muscle (comprise web and base plate reinforcing bar, contain a seat board, anti-fall beam slab, drilling sebific duct) coexisted is pricked in advance and is implemented pre-the bundle on the frame, and the bridge floor reinforcing bar is then pricked in advance on the frame at special bridge floor and pricked in advance; Second stage, treat main muscle and internal mold hoisted in position after, adopt straddle truck that bridge floor reinforcing bar and beam body master muscle assembly unit colligation is in place.
At the bottom of the above-mentioned case beam, web reinforcement carries out colligation and can adopt following method on loose tool: the vertical and horizontal bar space is according to Design Requirement Drawing, on the limb of angle steel vertical plane, cut the groove of 50 * 30mm, reinforcing bar just in time is stuck in the groove, to guarantee the laid reinforcement binding quality; For guaranteeing that the vertical and horizontal reinforcing bar position correctly reaches the allowable error of the satisfied regulation of protective layer thickness of both sides web reinforcement; can weld one 75 * 6mm angle steel respectively on the base, two outsides of loose tool tool; make a retaining with its vertical limb; when colligation; the crotch of horizontal bar and web stirrup are adjacent to this limb back of the body, neat with the tram that guarantees reinforcing bar and outside reinforcing bar.
Above-mentioned box girder bridge face reinforcing bar carries out colligation on loose tool can adopt following method: the main body of loose tool is welded with 50 * 30mm square steel; Because the cross sectional shape of bridge floor reinforcing bar has determined the bridge floor reinforcing bar to be not suitable for operating in the plane, therefore, cross sectional shape according to the bridge floor reinforcing bar, the supporting leg that can add weldering 500mm to 800mm varying length in the bottom of colligation loose tool, make the operation plane just in time about 900mm, both met design requirement, again handled easily; At two lateral surfaces of loose tool, by the height of wing plate (being floorings) reinforcing bar, the contour short square steel of weldering that keeps at a certain distance away, the end face of short square steel promptly is the reinforcing bar height; Pressing the short square steel that the weldering of wing plate reinforcing bar design grade does not highly wait at the loose tool two ends, weld one elongated (isometric with bridge floor) reinforcing bar at the top of short square steel, promptly is the height of bridge floor top layer reinforcing bar; The control of bridge floor bar spacing can be adopted following method: reinforcing bar makes " U " shape card with Φ 5mm high tensile steel wire on loose tool, be welded in the relevant position of loose tool then by the requirement of drawing design pitch, when colligation reinforcing bar just in time is stuck in " U " shape card.
For contraction crack appears in prevention beam body concrete, described stretch-draw step adopts three tensioning process, that is: pre-stretch-draw, initial tensioning and whole stretch-draw; Pre-tensioning process wherein is meant: for the control cabinet beam produces Temperature Cracks in early days, and " the early stage pre-stretch-draw of prestressing force band mould " technology of under low-intensity, carrying out partial prestressing stretch-draw of taking, that is: to the pre-stretch-draw steel bundle that designs on the design drawing and initial tensioning bundle etc., when concrete strength with play mould and reach 50% and 50% of design load respectively and carry out part steel Shu Zhangla when above, tension stress is controlled by design load 55%; When concrete strength with play the 80% initial tensioning partial prestressing bundle that mould reaches design load respectively, tension stress is by design load 70% control, after finishing the case beam is carried to and deposits the beam pedestal; Treat concrete strength and play to carry out other prestressing tendon stretch-draw when mould all reaches design load, and pre-stretch-draw and initial tensioning Shu Jinhang benefit are moved to the design proof stress.
Box girder inner formwork in the above-mentioned post-tensioned method prestressed concrete box beam whole opening prefabricated construction method, adopt following hydraulic internal mold system:
This system comprises standard paragraphs (beam body interlude), variable cross-section section (beam body web thickening section) and aperture section, and template is consistent with case overall size in the case beam; Standard paragraphs and variable cross-section section are formed by template system, frame system and frame (containing support) and hydraulic system, and the aperture section is made up of template system and frame system and frame (containing support); Wherein, template is a bulk punching block composed structure, divides counterdie, Bian Mo and three parts of backform; Variable cross-section section and aperture section are the bulk combined steel, can be formed by 14# worker's steel, 14# channel-section steel, 6~12mm steel plate assembly welding; Frame system and frame comprises vehicle frame truss, traveling support and travelling wheel, can by shaped steel [20, [14, ∠ 14 * 10 and 10,16mm steel plate assembly welding form;
It at first is internal mold merogenesis assembly unit on platform for lining in advance that internal mold is installed, and is coupled to an integral body by joint then, in place with two straddle truck integral hoistings; Internal mold integral body is hung in the pedestal upper base web reinforcement skeleton, the screw rod strut on the chassis is supported in (this preformed hole is made case beam base plate spilled water hole) in the preformed hole, internal mold is stablized be installed on the bed die;
Hydraulic internal mold adopts the segmentation method for dismounting when removing, its key step is as follows: (1), take off all struts, start lower mold oil cylinder, pack up the both sides counterdie; (2), start the dual-side mould oil cylinder, pack up the limit mould; (3), start vertical oil cylinder, fall backform; (4), screw out the spiral push rod, formwork integral drops on the track, pulls out the case beam.
Case beam external mold (side form) in the above-mentioned post-tensioned method prestressed concrete box beam whole opening prefabricated construction method, adopt following external mold (side form) system:
This system is made up of bed die, outer side form and end mould, is bulk punching block composed structure; Built-in fitting welding on bed die and the beam making bench is fixing, and outer side form adopts primary and secondary iron wedge to be connected with the wedging of bed die crossbeam, and the end mould is connected with bolt with the end, side form;
The bed die system is made up of crossbeam, longitudinal stiffener and panel; For strengthening segment structure, can adopt thickness is vertical rib of panel, 14# double flute steel and 20# double flute steel combination beam crossbeam about 20mm to bed die near the bearing two ends; The middle part be general segment structure, and can adopt thickness is that panel, 14# channel-section steel about 10mm indulged rib and 16# double flute steel combination beam; Outer side form can be that panel, longitudinal stiffener (10#, 12# worker's steel) and keel truss (16# worker's steel and channel-section steel combination) about 8mm formed by thickness; It is panel, 16# worker's steel rib and 20# channel-section steel frame in length and breadth about 10mm that the end mould can adopt thickness; Because the connecting reinforcement that the case beam stretches out in middle pier side is more, for being convenient in demoulding, this side mould can adopt little block structure, and the Side Template of the pier side of keeping to the side adopts bulk punching block composed structure.
Beam body concrete in the above-mentioned post-tensioned method prestressed concrete box beam whole opening prefabricated construction method (beam body concrete) placing step, because case beam concrete design quantity is big, particularly the 32m beam reaches 318m 3, be the shortening concreting time, the arrangement and method for construction that system beam field by using concrete centralized mixing, pipeline pumping are built, that is:
Adopt the independently stirring of three covers, casting system configuration, every cover system adopts the automatic mixing plant+concrete pump of concrete+boom+equipment that vibrates, and the mode that layering is passed is continuously built to the incremental construction method in centre by two ends, one-shot forming is built thickness<30cm for every layer; Three covers stir, casting system starts by cover, and wherein two covers are responsible for the one end concreting of case beam, another set of responsible other end concreting; Oblique segmentation is adopted in concreting, the continuous placing of the mode of horizontal slice, the placing order is according to marking among Fig. 2 1., 2., 3., 4. sequencing, cloth carries out synchronously symmetrically and evenly from case beam two coxostermums earlier, build web and base plate junction concrete earlier, build web concrete again, when the both sides web concrete is poured into top board face binding site, use the concreting hole blanking teeming underplate concrete of reserving from the internal mold end face instead, and in time shakeout, supply, vibrate, control absolute altitude well, reach designing requirement, build top board (floorings) concrete at last.
Should note in the beam body concrete placing step: when building the both sides web concrete, adopt synchronous symmetry to build web concrete, prevent both sides concrete height great disparity, cause internal mold skew or other adverse consequences; Bridge deck concrete is also built from two ends to middle contiguous segmentation, about 2 meters every section, receives slurry in order to the surface and touches face; The beam body concrete is built and can be adopted the moulding of vibrating of plug-in type vibrating head, and is aided with that side is shaken and the end shakes, to guarantee concrete compaction; Build in the process and to note strengthening vibrating of case beam-ends head, chamfering and reinforcing bar dense part, emphasis strengthen corner, web and base plate the interface place vibrate and the base plate absolute altitude is controlled; Bridge deck concrete adopts the plate vibration trowelling machine in time to catch up with pressure, floating after being poured into designed elevation, and it is floating in case crackle makes bridge floor reach smooth to carry out receiving slurry the second time to bridge floor before concrete initial set, and draining is unobstructed.
On the other hand, for satisfying the needs that the case beam adapts to 100 years durability, the inventor is by carrying out a large amount of service checks to raw material, thousands of assembly composition and division in a proportion tests, and the on-the-spot temporary project of combination has been carried out engineer testing repeatedly, develop the employing conventional raw materials, common process, adding coal ash, ore deposit quarrel powder as additive and efficient additive, the durable concrete of preparing through ratio optimization of case beam C50 high-performance with high-durability and works fine, as the used concrete preferred version of post-tensioned method prestressed concrete box beam whole opening prefabricated construction method central sill body of the present invention (also can adopt present beam bridge prefabricated in concrete commonly used), its composition and optimum weight part proportioning are:
262 parts of cement, 140 parts in slag, 68 parts in flyash, 742 parts in sand,
1068 parts in stone, 3.9 parts of additives, 141 parts in water.
Additive wherein is a high efficiency water reducing agent, as: go up the LEX-9H liquid water reducer that Haicheng City sincere building materials Co., Ltd produces, or the TH-2A powder water reducer of railway construction research institute of institute of iron section production etc.
Compared with prior art, the invention has the beneficial effects as follows:
Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method of the present invention is at the technological difficulties in large span, the whole opening prefabricated work progress of large-tonnage prestressed concrete box girder such as 32m/900t level in the special line for passenger trains, adopt the corresponding techniques means to solve, thereby obtain satisfied technique effect, the prestressed concrete box girder that makes adhered to specification:
(1) in the post-tensioned method prestressed concrete box beam whole opening prefabricated construction method of the present invention, main body reinforcing bar and bridge floor reinforcing bar all adopt pre-bundle, the integral hoisting technology concentrated, this technology reinforcing bar pricks in advance that quality is good, and it is accurate that reinforcing bar is pricked the position in advance, and spacing and cover to reinforcement adhere to specification; The framework of steel reinforcement distortion when lifting of end web reinforcement and bridge floor reinforcing bar is little, lifting and easy for installation, efficient height;
(2) post-tensioned method prestressed concrete box beam whole opening prefabricated construction method of the present invention has adopted the hydraulic internal mold construction technology, and this technology has advantages such as strong operability, safe in utilization, efficient, good reliability; Make the interior case of the case beam that makes bright and clean, overall size is good, meets design requirement;
(3) tensioning process of post-tensioned method prestressed concrete box beam whole opening prefabricated construction method of the present invention has adopted the pre-stretching construction technology of band mould, can avoid the beam body infant cracking to occur, can satisfy bridge structure life requirement in 100 years;
(4) in the post-tensioned method prestressed concrete box beam whole opening prefabricated construction method of the present invention, the arrangement and method for construction that beam body concrete placing step has adopted concrete centralized mixing, pipeline pumping to build, adopt the independently stirring of three covers, casting system configuration, adopt the continuous placing of mode of oblique segmentation, horizontal slice, by two ends to the incremental construction in centre, one-shot forming, can shorten the concreting time, and early age strength of concrete is low, avoid the beam body infant cracking to occur, can satisfy bridge structure life requirement in 100 years.
Description of drawings
Fig. 1 is the post-tensioned method prestressed concrete box beam whole opening prefabricated construction flow chart of the present invention;
Fig. 2 is the beam body concrete placing sequential schematic in the post-tensioned method prestressed concrete box beam whole opening prefabricated construction method technical process of the present invention.
The specific embodiment
The present invention is described in further detail below in conjunction with the specific embodiment.
But this should be interpreted as that the scope of the above-mentioned theme of the present invention only limits to following embodiment.
Embodiment
The technological process of present embodiment post-tensioned method prestressed concrete box beam whole opening prefabricated construction method as shown in Figure 1, its key step comprises:
(1) template, reinforcing bar and built-in fitting etc. are installed:
This step mainly comprises sequentially: trimming bed die, adjustment side form, erection support plate and anti-fall beam slab, installation withdrawing sebific duct, lifting main body reinforcing bar, mounting rail body built-in fitting, lifting internal mold, installation end mould, lifting surfacing steel bar, the installation of bridge floor built-in fitting etc.
In this step:
Main body reinforcing bar and bridge floor reinforcing bar all adopt concentrates pre-bundle, integral hoisting technology, i.e. the processing of case beam steel (comprising main body reinforcing bar and bridge floor reinforcing bar) is all finished in the reinforcing bar workshop, carries out colligation then on loose tool; Install for making things convenient for internal mold, divide two stages to carry out the colligation of case beam steel: the phase I, the main muscle that earlier beam body master muscle (comprise web and base plate reinforcing bar, contain a seat board, anti-fall beam slab, drilling sebific duct) coexisted is pricked in advance and is implemented pre-the bundle on the frame, and the bridge floor reinforcing bar is then pricked in advance on the frame at special bridge floor and pricked in advance; Second stage, treat main muscle and internal mold hoisted in position after, adopt straddle truck that bridge floor reinforcing bar and beam body master muscle assembly unit colligation is in place;
At the bottom of the case beam, web reinforcement adopts following method when carrying out colligation on loose tool: the vertical and horizontal bar space is cut the groove of 50 * 30mm according to Design Requirement Drawing on the limb of angle steel vertical plane, reinforcing bar just in time is stuck in the groove, to guarantee the laid reinforcement binding quality; For guaranteeing that the vertical and horizontal reinforcing bar position correctly reaches the allowable error of the satisfied regulation of protective layer thickness of both sides web reinforcement, one 75 * 6mm angle steel is welded on base, two outsides at the loose tool tool respectively, make a retaining with its vertical limb, when colligation, the crotch of horizontal bar and web stirrup are adjacent to this limb back of the body, neat with the tram that guarantees reinforcing bar and outside reinforcing bar;
The box girder bridge face reinforcing bar adopts following method when carrying out colligation on loose tool: the main body of loose tool is welded with 50 * 30mm square steel; Because the cross sectional shape of bridge floor reinforcing bar has determined the bridge floor reinforcing bar to be not suitable for operating in the plane, therefore, cross sectional shape according to the bridge floor reinforcing bar, the supporting leg that adds weldering 500mm to 800mm varying length in the bottom of colligation loose tool, make the operation plane just in time about 900mm, both met design requirement, again handled easily; At two lateral surfaces of loose tool, by the height of wing plate (being floorings) reinforcing bar, the contour short square steel of weldering that keeps at a certain distance away, the end face of short square steel promptly is the reinforcing bar height; Pressing the short square steel that the weldering of wing plate reinforcing bar design grade does not highly wait at the loose tool two ends, weld one elongated (isometric with bridge floor) reinforcing bar at the top of short square steel, promptly is the height of bridge floor top layer reinforcing bar; Bridge floor bar spacing control employing method is: reinforcing bar makes " U " shape card with Φ 5mm high tensile steel wire on loose tool, be welded in the relevant position of loose tool then by the requirement of drawing design pitch, when colligation reinforcing bar just in time is stuck in " U " shape card.
Box girder inner formwork adopts following hydraulic internal mold system:
This system comprises standard paragraphs (beam body interlude), variable cross-section section (beam body web thickening section) and aperture section, and template is consistent with case overall size in the case beam; Standard paragraphs and variable cross-section section are formed by template system, frame system and frame (containing support) and hydraulic system, and the aperture section is made up of template system and frame system and frame (containing support); Wherein, template is a bulk punching block composed structure, divides counterdie, Bian Mo and three parts of backform; Variable cross-section section and aperture section are the bulk combined steel, are formed by 14# worker's steel, 14# channel-section steel, 6~12mm steel plate assembly welding; Frame system and frame comprises vehicle frame truss, traveling support and travelling wheel, by shaped steel [20, [14, ∠ 14 * 10 and 10,16mm steel plate assembly welding form;
It at first is internal mold merogenesis assembly unit on platform for lining in advance that internal mold is installed, and is coupled to an integral body by joint then, in place with two straddle truck integral hoistings; Internal mold integral body is hung in the pedestal upper base web reinforcement skeleton, the screw rod strut on the chassis is supported in (this preformed hole is made case beam base plate spilled water hole) in the preformed hole, internal mold is stablized be installed on the bed die;
Hydraulic internal mold adopts the segmentation method for dismounting when removing, its key step is as follows: (1), take off all struts, start lower mold oil cylinder, pack up the both sides counterdie; (2), start the dual-side mould oil cylinder, pack up the limit mould; (3), start vertical oil cylinder, fall backform; (4), screw out the spiral push rod, formwork integral drops on the track, pulls out the case beam.
Case beam external mold (side form) adopts following external mold (side form) system:
This system is made up of bed die, outer side form and end mould, is bulk punching block composed structure; Built-in fitting welding on bed die and the beam making bench is fixing, and outer side form adopts primary and secondary iron wedge to be connected with the wedging of bed die crossbeam, and the end mould is connected with bolt with the end, side form;
The bed die system is made up of crossbeam, longitudinal stiffener and panel; For strengthening segment structure, employing thickness is vertical rib of panel, 14# double flute steel and the 20# double flute steel combination beam crossbeam about 20mm to bed die near the bearing two ends; The middle part is general segment structure, and employing thickness is vertical rib of panel, 14# channel-section steel and the 16# double flute steel combination beam about 10mm; Outer side form is that panel, longitudinal stiffener (10#, 12# worker's steel) and keel truss (16# worker's steel and channel-section steel combination) about 8mm formed by thickness; It is panel, 16# worker's steel rib and 20# channel-section steel frame in length and breadth about 10mm that the end mould adopts thickness; Because the connecting reinforcement that the case beam stretches out in middle pier side is more, for being convenient in demoulding, this side mould adopts little block structure, and the Side Template of the pier side of keeping to the side adopts bulk punching block composed structure.
(2) beam body concrete (beam body concrete) placing, beam body concrete are steam-cured.
Because case beam concrete design quantity is big, particularly the 32m beam reaches 318m 3, be the shortening concreting time, the arrangement and method for construction that system beam field by using concrete centralized mixing, pipeline pumping are built, that is:
Adopt the independently stirring of three covers, casting system configuration, every cover system adopts the automatic mixing plant+concrete pump of concrete+boom+equipment that vibrates, and the mode that layering is passed is continuously built to the incremental construction method in centre by two ends, one-shot forming is built thickness<30cm for every layer; Three covers stir, casting system starts by cover, and wherein two covers are responsible for the one end concreting of case beam, another set of responsible other end concreting; The continuous placing of the mode of oblique segmentation, horizontal slice is adopted in concreting, placing order according to mark among Fig. 2 1., 2., 3., 4. sequencing, cloth carries out synchronously symmetrically and evenly from case beam two coxostermums earlier, build web and base plate junction concrete earlier, build web concrete again, when the both sides web concrete is poured into top board face binding site, use the concreting hole blanking teeming underplate concrete of reserving from the internal mold end face instead, and in time shakeout, supply, vibrate, control absolute altitude well, reach designing requirement, build concrete roof at last;
In the beam body concrete placing process, when building the both sides web concrete, adopt synchronous symmetry to build web concrete, prevent both sides concrete height great disparity, cause internal mold skew or other adverse consequences; Bridge deck concrete is also built from two ends to middle contiguous segmentation, about 2 meters every section, receives slurry in order to the surface and touches face; The beam body concrete is built and is adopted the moulding of vibrating of plug-in type vibrating head, and is aided with that side is shaken and the end shakes, to guarantee concrete compaction; Build in the process and to strengthen vibrating of case beam-ends head, chamfering and reinforcing bar dense part, emphasis strengthen corner, web and base plate the interface place vibrate and the base plate absolute altitude is controlled; Bridge deck concrete adopts the plate vibration trowelling machine in time to catch up with pressure, floating after being poured into designed elevation, and it is floating in case crackle makes bridge floor reach smooth to carry out receiving slurry the second time to bridge floor before concrete initial set, and draining is unobstructed.
On the other hand, for satisfying the needs that the case beam adapts to 100 years durability, adopt the durable concrete of case beam C50 high-performance of following composition and weight portion proportioning to carry out the placing of beam body:
262 parts of cement, 140 parts in slag, 68 parts in flyash, 742 parts in sand,
1068 parts in stone, 3.9 parts of additives, 141 parts in water.
Additive wherein is the LEX-9H liquid water reducer that last Haicheng City sincere building materials Co., Ltd produces.
(3) form removal:
This step mainly comprises sequentially: withdrawing sebific duct, dismounting end mould, dismounting internal mold, loose side form etc.
(4) stretch-draw:
This step mainly comprises sequentially: steel strand, the pre-stretch-draw of case beam, case beam initial tensioning, move beam to the whole stretch-draw of beam strorage area, concrete curing, case beam etc.
For contraction crack appears in prevention beam body concrete, this stretch-draw step adopts three tensioning process, that is: pre-stretch-draw, initial tensioning and whole stretch-draw; Pre-tensioning process wherein is meant " the early stage pre-stretch-draw of the prestressing force band mould " technology of carrying out partial prestressing stretch-draw under low-intensity, that is: when concrete strength with play mould and reach 50% and 50% of design load respectively and carry out part steel Shu Zhangla when above, tension stress is controlled by design load 55%; When concrete strength with play the 80% initial tensioning partial prestressing bundle that mould reaches design load respectively, tension stress is by design load 70% control, after finishing the case beam is carried to and deposits the beam pedestal; Treat concrete strength and play to carry out other prestressing tendon stretch-draw when mould all reaches design load, and pre-stretch-draw and initial tensioning Shu Jinhang benefit are moved to the design proof stress.
(5) postorder construction:
This step mainly comprises sequentially: cut silk, pipeline pneumatic mortar, bridge sealing off and covering anchorage, maintenance, the appearance of case beam inspection, box beam erection, making watertight composition, construction protective layer, maintenance etc.

Claims (6)

1. post-tensioned method prestressed concrete box beam whole opening prefabricated construction method, key step comprises:
(1) template, reinforcing bar and built-in fitting are installed:
This step mainly comprises sequentially: trimming bed die, adjustment side form, erection support plate and anti-fall beam slab, installation withdrawing sebific duct, lifting main body reinforcing bar, mounting rail body built-in fitting, lifting internal mold, installation end mould, lifting surfacing steel bar, bridge floor built-in fitting are installed;
(2) beam body concrete placing, the steam-cured or natural curing of beam body concrete;
(3) form removal:
This step mainly comprises sequentially: withdrawing sebific duct, dismounting end mould, dismounting internal mold, loose side form;
(4) stretch-draw:
This step mainly comprises sequentially: steel strand, the pre-stretch-draw of case beam, case beam initial tensioning, move beam to the whole stretch-draw of beam strorage area, concrete curing, case beam;
(5) postorder construction:
This step mainly comprises sequentially: cut silk, pipeline pneumatic mortar, bridge sealing off and covering anchorage, maintenance, the appearance of case beam inspection, box beam erection, making watertight composition, construction protective layer, maintenance;
Wherein:
Described main body reinforcing bar and bridge floor reinforcing bar all adopt concentrates pre-bundle, integral hoisting technology, i.e. the processing of case beam steel is all finished in the reinforcing bar workshop, carries out colligation then on loose tool; For making things convenient for internal mold to install, divide two stages to carry out the colligation of case beam steel: the phase I, the main muscle that earlier beam body master muscle one coexisted is pricked in advance and is implemented pre-the bundle on the frame, and the bridge floor reinforcing bar is then pricked in advance on the frame at special bridge floor and pricked in advance; Second stage, treat main muscle and internal mold hoisted in position after, adopt straddle truck that bridge floor reinforcing bar and beam body master muscle assembly unit colligation is in place;
Described stretch-draw step adopts three tensioning process, that is: pre-stretch-draw, initial tensioning and whole stretch-draw; Pre-tensioning process wherein is meant " the early stage pre-stretch-draw of the prestressing force band mould " technology of carrying out partial prestressing stretch-draw under low-intensity, that is: according to the design on the design drawing, when concrete strength with play mould and reach 50% and 50% of design load respectively and carry out part steel Shu Zhangla when above, tension stress is controlled by design load 55%; When concrete strength with play the 80% initial tensioning partial prestressing bundle that mould reaches design load respectively, tension stress is by design load 70% control, after finishing the case beam is carried to and deposits the beam pedestal; Treat concrete strength and play to carry out other prestressing tendon stretch-draw when mould all reaches design load, and pre-stretch-draw and initial tensioning Shu Jinhang benefit are moved to the design proof stress;
Described internal mold, adopt following hydraulic internal mold system: this system comprises standard paragraphs, variable cross-section section and aperture section, template is consistent with case overall size in the case beam; Standard paragraphs and variable cross-section section are formed by template system, frame system and frame and hydraulic system, and the aperture section is made up of template system and frame system and frame; Wherein, template is a bulk punching block composed structure, divides counterdie, Bian Mo and three parts of backform; Frame system and frame comprises vehicle frame truss, traveling support and travelling wheel;
Described beam body concrete placing step, the arrangement and method for construction of building in system beam field by using concrete centralized mixing, pipeline pumping, that is: adopt the independently stirring of three covers, casting system to dispose, every cover system adopts concrete, and automatic mixing plant+concrete pump+boom+equipment vibrates, the mode that layering is passed continuously, build one-shot forming by two ends to the incremental construction method in centre; Three covers stir, casting system starts by cover, and wherein two covers are responsible for the one end concreting of case beam, another set of responsible other end concreting; The continuous placing of the mode of oblique segmentation, horizontal slice is adopted in concreting, cloth carries out synchronously symmetrically and evenly from case beam two coxostermums earlier, build web and base plate junction concrete earlier, build web concrete again, when the both sides web concrete is poured into top board face binding site, use the concreting hole blanking teeming underplate concrete of reserving from the internal mold end face instead, build concrete roof at last.
2. post-tensioned method prestressed concrete box beam whole opening prefabricated construction method according to claim 1 is characterized in that:
Described reinforcing bar is concentrated in pre-bundle, the integral hoisting technology, at the bottom of the case beam, web reinforcement adopts following method when carrying out colligation on loose tool: the vertical and horizontal bar space is according to Design Requirement Drawing, on the limb of angle steel vertical plane, cut the groove of 50 * 30mm, just in time be stuck in reinforcing bar in the groove; One 75 * 6mm angle steel is welded on base, two outsides at the loose tool tool respectively, makes a retaining with its vertical limb, when colligation, the crotch and the web stirrup of horizontal bar is adjacent to this limb back of the body.
3. post-tensioned method prestressed concrete box beam whole opening prefabricated construction method according to claim 1 is characterized in that:
Described reinforcing bar is concentrated in pre-bundle, the integral hoisting technology, and the bridge floor reinforcing bar adopts following method when carrying out colligation on loose tool: the main body of loose tool is welded with 50 * 30mm square steel; According to the cross sectional shape of bridge floor reinforcing bar, add the supporting leg of weldering 500mm to 800mm varying length in the bottom of colligation loose tool, make the operation plane just in time about 900mm; At two lateral surfaces of loose tool, press the height of wing plate reinforcing bar, the contour short square steel of weldering that keeps at a certain distance away, the end face of short square steel promptly is the reinforcing bar height; Pressing the short square steel that the weldering of wing plate reinforcing bar design grade does not highly wait at the loose tool two ends, weld an elongated reinforcing bar at the top of short square steel, promptly is the height of bridge floor top layer reinforcing bar; Following method is adopted in the control of bridge floor bar spacing: reinforcing bar makes " U " shape card with Φ 5mm high tensile steel wire on loose tool, be welded in the relevant position of loose tool then by the requirement of drawing design pitch, when colligation reinforcing bar just in time is stuck in " U " shape card.
4. post-tensioned method prestressed concrete box beam whole opening prefabricated construction method according to claim 1 is characterized in that:
The installation method of described internal mold is: at first with internal mold merogenesis assembly unit on platform for lining in advance, be coupled to an integral body by joint then, and in place with two straddle truck integral hoistings; Internal mold integral body is hung in the pedestal upper base web reinforcement skeleton, the screw rod strut on the chassis is supported in the preformed hole, internal mold is stablized be installed on the bed die.
5. post-tensioned method prestressed concrete box beam whole opening prefabricated construction method according to claim 1 is characterized in that: described internal mold adopts the segmentation method for dismounting when removing, its key step is as follows:
(1), take off all struts, start lower mold oil cylinder, pack up the both sides counterdie;
(2), start the dual-side mould oil cylinder, pack up the limit mould;
(3), start vertical oil cylinder, fall backform;
(4), screw out the spiral push rod, formwork integral drops on the track, pulls out the case beam.
6. post-tensioned method prestressed concrete box beam whole opening prefabricated construction method according to claim 1 is characterized in that:
In the described beam body concrete placing step: when building the both sides web concrete, adopt synchronous symmetry to build web concrete; Bridge deck concrete is also built from two ends to middle contiguous segmentation; Adopt the moulding of vibrating of plug-in type vibrating head when the beam body concrete is built, and be aided with that side is shaken and the end shakes, to guarantee concrete compaction; Strengthen vibrating of case beam-ends head, chamfering and reinforcing bar dense part, emphasis strengthen corner, web and base plate the interface place vibrate and the base plate absolute altitude is controlled; Bridge deck concrete adopts the plate vibration trowelling machine in time to catch up with pressure, floating after being poured into designed elevation, and it is floating before concrete initial set bridge floor to be carried out receiving slurry the second time.
CNB2007100499024A 2007-08-31 2007-08-31 Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method Active CN100572011C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007100499024A CN100572011C (en) 2007-08-31 2007-08-31 Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007100499024A CN100572011C (en) 2007-08-31 2007-08-31 Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method

Publications (2)

Publication Number Publication Date
CN101125441A CN101125441A (en) 2008-02-20
CN100572011C true CN100572011C (en) 2009-12-23

Family

ID=39093613

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007100499024A Active CN100572011C (en) 2007-08-31 2007-08-31 Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method

Country Status (1)

Country Link
CN (1) CN100572011C (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109747037A (en) * 2019-01-26 2019-05-14 中铁三局集团广东建设工程有限公司 A kind of elder generation's post-tensioned prestressing combines the U-shaped beam prefabricated construction technology of large span of construction

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101596744B (en) * 2009-07-06 2011-05-11 中冶建工有限公司 Method for binding and mounting continuous stirrups of post-tensioned prestressed reinforced concrete box girder
CN102011366B (en) * 2009-12-29 2011-11-16 中交第一航务工程局有限公司 Construction method for mud jacking of post-tensioning pre-stressed concrete box girder pipe
CN101758557B (en) * 2009-12-30 2012-07-18 中铁二十三局集团有限公司 Producing method of track slabs
CN102294741B (en) * 2011-07-14 2013-11-06 中铁二局股份有限公司 Construction method for prefabricating hollow slab beams using hinged draw type steel internal mould
CN102528927B (en) * 2012-01-30 2014-03-26 中铁四局集团第五工程有限公司 Production line precast beam construction method
CN102909786B (en) * 2012-11-22 2014-10-29 中国水利水电第十四工程局有限公司 Construction technology for prefabricating concrete crane beam
CN106042173B (en) * 2016-06-02 2018-08-31 中铁十六局集团铁运工程有限公司 Bridge production system
CN106758820A (en) * 2016-11-15 2017-05-31 中铁二局集团有限公司 A kind of continuous Cast-in-situ Beam prestressing tendon stretch-draw construction method of minor radius
CN106836604B (en) * 2017-02-07 2022-08-12 叶长青 Method for manufacturing large-span inclined roof
CN107471428B (en) * 2017-08-22 2019-10-25 中铁十七局集团第三工程有限公司 Manufacturing method in a kind of non-standard box beam field
CN108381746B (en) * 2017-12-19 2020-06-19 中铁隧道集团四处有限公司 Construction method of sliding type pedestal prefabricated box girder
CN108638324A (en) * 2018-05-28 2018-10-12 中交路桥北方工程有限公司 A kind of construction method of prefabricated case beam
CN108943378A (en) * 2018-06-07 2018-12-07 广州市市政工程设计研究总院有限公司 A kind of method for prefabricating of UHPC small box girder end tabula
CN108943374A (en) * 2018-06-07 2018-12-07 广州市市政工程设计研究总院有限公司 A kind of method for prefabricating of pre-buried steel board-like UHPC small box girder end tabula
CN108755448B (en) * 2018-08-16 2023-06-23 中铁四局集团有限公司 Tool and method for positioning, installing and dismantling large-span continuous rigid frame suspension irrigation end template
CN109203225A (en) * 2018-09-30 2019-01-15 恒城建设科技有限公司 Prefabricated components mechanical forming process
CN109235732B (en) * 2018-10-29 2020-02-14 中电建十一局工程有限公司 Construction method for prefabricated hollow beam slab
CN109483726B (en) * 2018-12-13 2023-10-13 宁波交通工程建设集团有限公司 Hydraulic formwork for binding reinforcement framework of prefabricated box girder and construction method
CN111844384B (en) * 2020-07-29 2021-11-09 中国建筑第八工程局有限公司 Method for manufacturing special-shaped column template
CN112323817A (en) * 2020-11-24 2021-02-05 中铁第四勘察设计院集团有限公司 Pre-tensioning precast concrete supporting member, inner supporting system and construction method
CN113430942A (en) * 2021-06-25 2021-09-24 中铁十九局集团第五工程有限公司 Construction method for pouring box girder concrete
CN113910443B (en) * 2021-10-15 2023-04-14 中铁建工集团广东有限公司 Small box girder inner die and construction method for pouring small box girder
CN115026944A (en) * 2022-06-27 2022-09-09 中交(南京)建设有限公司 Method for pre-stressed construction of highway municipal prestressed concrete precast box girder
CN115042298A (en) * 2022-07-18 2022-09-13 中铁二局集团有限公司 Manufacturing method of subway vehicle section assembled reinforced concrete beam
CN115094752A (en) * 2022-07-25 2022-09-23 成都天府轨谷科技有限公司 Linear box-shaped bridge curve rail groove structure and manufacturing method thereof
CN117428923B (en) * 2023-12-21 2024-02-20 蚌埠市蚌铁轨枕有限责任公司 Prestressed tensioning device for reinforced concrete sleeper

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2295788Y (en) * 1997-05-09 1998-10-28 交通部第二公路勘察设计院 Prestressed post-tension concrete box beam
JP2003138520A (en) * 2001-10-31 2003-05-14 Joban Kosan Kk Bridge girder structure
JP3720837B1 (en) * 2004-10-14 2005-11-30 株式会社ピーエス三菱 Extrusion erection method
CN1952261A (en) * 2006-11-16 2007-04-25 东南大学 Split type prestressed concrete combined box beam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2295788Y (en) * 1997-05-09 1998-10-28 交通部第二公路勘察设计院 Prestressed post-tension concrete box beam
JP2003138520A (en) * 2001-10-31 2003-05-14 Joban Kosan Kk Bridge girder structure
JP3720837B1 (en) * 2004-10-14 2005-11-30 株式会社ピーエス三菱 Extrusion erection method
CN1952261A (en) * 2006-11-16 2007-04-25 东南大学 Split type prestressed concrete combined box beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109747037A (en) * 2019-01-26 2019-05-14 中铁三局集团广东建设工程有限公司 A kind of elder generation's post-tensioned prestressing combines the U-shaped beam prefabricated construction technology of large span of construction

Also Published As

Publication number Publication date
CN101125441A (en) 2008-02-20

Similar Documents

Publication Publication Date Title
CN100572011C (en) Post-tensioned method prestressed concrete box beam whole opening prefabricated construction method
CN100587165C (en) Cast-in-situ beam-making construction method of assembled support
CN100464026C (en) Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN102817325B (en) Construction method of simply supported-continuous switching system of negative moment beam prestressed precast box beam
CN105625188A (en) Construction method for 48m sectional beam of passenger railway based on BIM technology
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN111764216A (en) Construction method and application of fabricated concrete road plate
CN103615053A (en) Construction method for post-cast belt of cast-in-place reinforced concrete structure
CN202596743U (en) Formwork trolley for underground tunnel pull-rod-free side wall construction
CN104532754B (en) A kind of prestressed concrete box girder end-blocking template construction method
CN101125440A (en) Pretensioned beam whole opening prefabricated construction method
CN110219667B (en) Tunnel inverted arch and inverted arch filling layer substituted steel-concrete combined structure and construction process
CN109281249A (en) A kind of UHPC-NC overlapping trestle deck structrue and its construction method
CN103321111A (en) Tramcar track continuous-laying construction method
CN102587282B (en) Large-section simply-supported box girder precasting and assembly process under conditions of strong wind and high altitude
CN105804395A (en) Staircase one-step continuous casting forming construction method based on integral shaped formwork
CN100513696C (en) Pier body cap cracking body outside stress reinforcing method
CN110184928A (en) A kind of pier stud construction method that the public rail using falsework is built together overhead
CN105821764B (en) Non-fragment orbit rigidity adjuster
CN102797223A (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
WO2024041054A1 (en) Prefabricated track structure for built-in pump house section in rail transportation and construction method
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN202148694U (en) Prefabricated T-shaped beam steel bar colligation positioning device
CN217629396U (en) UHPC-RC superposed wet joint structure and bridge thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160104

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: 610041 high building, No. nine Hing Road, Chengdu hi tech Development Zone, Sichuan, 6

Patentee before: China Railway Erju Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180822

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: China Railway Erju Corporation Ching Engineering Co., Ltd.

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: China Railway Erju Corporation Ching Engineering Co., Ltd.

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee before: China Railway Erju Corporation Ching Engineering Co., Ltd.

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.