CN101196103A - Squeezing cement plugging technical skill for thick oil absorption well - Google Patents

Squeezing cement plugging technical skill for thick oil absorption well Download PDF

Info

Publication number
CN101196103A
CN101196103A CNA2008100100343A CN200810010034A CN101196103A CN 101196103 A CN101196103 A CN 101196103A CN A2008100100343 A CNA2008100100343 A CN A2008100100343A CN 200810010034 A CN200810010034 A CN 200810010034A CN 101196103 A CN101196103 A CN 101196103A
Authority
CN
China
Prior art keywords
cement
oil
sleeve pipe
well
pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008100100343A
Other languages
Chinese (zh)
Inventor
陶煜征
于广鹏
董晓彬
刘雪峰
李华清
姜贺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaohe Petroleum Exploration Bureau
Original Assignee
Liaohe Petroleum Exploration Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaohe Petroleum Exploration Bureau filed Critical Liaohe Petroleum Exploration Bureau
Priority to CNA2008100100343A priority Critical patent/CN101196103A/en
Publication of CN101196103A publication Critical patent/CN101196103A/en
Pending legal-status Critical Current

Links

Abstract

The invention relates to the thick oil absorption well squeeze cementing leakage sealing process technology. The process technology performs the adjustment and controlling according to the pressure difference of the well head oil and the sleeve during the process of the squeeze cementing displacement, in addition, the leakage stoppage, the re-washing of liquid cement and the moving of a pipe column are inexistent during the whole construction process, and the nonpressurized cement curing is adopted. The invention has novel conception, and the adjustment and controlling is easy to be executed, because the invention adopts the leakage stoppage free, the liquid cement re-washing free and the pipe column moving free and the nonpressurized cement curing squeezing cementing methods to construct, the re-washing of the liquid cement, the moving of the pipe column can not be used and the well can be directly shut off to perform cement curing when the cement mortar displacement is positioned, thereby, the time of the squeezing cementation can be shortened, the working risk and the ground pollution are reduced, the invention is favor of saving the cost and shortening the well repairing time, the technology is suitable for the thick oil well layer sealing and the leakage seal, and is particularly effective to the leakage sealing and the strengthening of the outer cement mantle of a sleeve pipe.

Description

A kind of squeezing cement plugging technical skill for thick oil absorption well
Technical field:
The present invention relates to a kind of technology that is used for the heavy oil wells workover treatment, belong to petroleum well workover operation technique class.
Background technology:
In viscous crude absorption well workover treatment process, must go ahead of the rest the leakage interval is clamp-oned grout off and scurried groove, just can carry out other operations then.At present, on-the-spot in the petroleum well workover operation viscous crude absorption well water squeezing mudding scurry technology commonly used two kinds of methods are arranged: the one, the leak stopping method is carried out squeeze method after using sealing agent that leakage channel is blocked.The 2nd, following cement retainer method will be scurried the above water squeezing mud of layer in the water squeezing mudding under the cement retainer.These water squeezing muddings are scurried process and all need be carried out leak stopping and backwash water drilling mud practice and have following point: 1 envelope is scurried and when reinforcing the outer cement sheath of sleeve pipe, cement paste is told outward, and it is relatively poor that envelope is scurried the effect of reinforcing; 2 closing wells are waited when coagulating, sleeve pipe external and internal pressure imbalance, and sleeve pipe is yielding; Carry out anti-flushing well during 3 squeeze methods, can pollute environment.
Summary of the invention:
The object of the present invention is to provide and a kind ofly can overcome existing viscous crude absorption well water squeezing mudding and scurry process existing problems and not enough squeezing cement plugging technical skill for thick oil absorption well.
Technical scheme of the present invention is as follows:
The characteristics that this kind envelope is scurried technology are in the squeeze method displacement process, regulate and control according to well head oil, sleeve pipe pressure reduction, and, not leak stopping of whole construction course, backwash water mud not, fixed tubular column, and adopt normal pressure to wait and coagulate.The implementation step of this technology is as follows: following bare string begins water squeezing mud to projected depth; Behind the boundary, pump truck begins to inject equilibrium liquid by sleeve pipe in well at the bottom of the cement paste arrival oil reservoir in the oil pipe, and oil pipe continues to inject cement paste and do not stop; The oil jacket annular space is closed in termination of pumping when the pump pressure of sleeve pipe reaches certain numerical value, continues positive cement injection in oil pipe; Just squeezing displacement fluid when pressure reaches design pressure, displacement fluid is closed the oil pipe gate after cement paste is ejected the following certain depth of tubing shoe; Instead squeeze displacement fluid from the oil jacket annular space cement paste is pushed up to the following 100m of tubing shoe or darker, close sleeve gate and wait with fixed attention.
In the squeeze method process, the head of liquid of sleeve pipe and oil pipe is observed U type pipe pressure equilibrium principle, and tubing shoe place pressure dependence formula is as follows:
P Cover is total=P Oil is total, that is P Cover+ P Cover 1+ P Cover 2=P Oil+ P Oil 1+ P Oil 2Or be P Cover+ γ The topGH 1+ γ CementGH 3=P Oil+ γ The topGH 2+ γ CementGH 4
In the formula: P Cover is total--the sleeve pipe gross pressure; P Oil is total-oil pipe gross pressure; P Cover--the cased well mouth pressure; P Oil--the oil pipe well head pressure; P Cover 1--sleeve pipe displacement fluid head of liquid; P Cover 2--the sleeve water mud column pressure; P Oil 1-oil pipe displacement fluid head of liquid; P Oil 2-sleeve water mud fluid column pressure; H 1--sleeve pipe displacement fluid liquid-column height; H 2-oil pipe displacement fluid liquid-column height; H 3--sleeve water mud height; H 4--oil pipe cement paste height; γ The top, γ CementBe respectively displacement fluid and cement slurry density; G-acceleration of gravity m/s 2
Whole water squeezing mudding is scurried activities can be divided into five stages, and each stage technique main points is as follows:
Phase I: leakage stage
Because oil well is missed, the fluid column in the well can not be full of pit shaft when water squeezing mud began, and liquid level is not at well head, it is empty that part is arranged in the pit shaft, the oil jacket annular pressure is a negative value, and when the infiltration rate on stratum during greater than the injection rate of oil, cover, the cement paste in the oil pipe can not return annular space from pipe shoe.
Second stage: pressure recovers the stage
When the infiltration rate on stratum during less than the injection rate of oil, sleeve pipe, some enters the stratum fluid in oil, the cover annular space, and another part enters the space that casing annulus does not fill up.(φ 177.8mm) casing annulus volume is greater than the internal volume of oil pipe generally speaking, and when discharge capacity oily, that cover injects fluid was identical, fluid was full of casing annulus after being full of oil pipe earlier again.Be that cement paste returns annular space from pipe shoe.
Phase III: band is pressed into the stage
When the fluid in oil, cover space when being full of, be full of cement paste in the oil pipe, well head plays pressure, is water γ as equilibrium liquid when the squeeze method The top=1g/cm 3, the density γ of cement paste Cement=1.81g/cm 3Can calculate according to the aforementioned pressure balanced relationship: P Cover=7.94H 1+ P Oil
According to following formula as seen, the well head sleeve pipe rises earlier and presses, and sleeve pipe rises when pressing and should continue to squeeze into displacement fluid from sleeve pipe, makes casing annulus not have cement paste, all is full of displacement fluid, when oil pipe and sleeve pipe maximal pressure difference are 7.94H, does not have cement paste in the sleeve pipe.When the degree of depth of squeeze method tubing string was 1km, the maximal pressure difference of oil pipe and sleeve pipe was 7.94Mpa.When all being displacement fluid in the sleeve pipe, close sleeve pipe, oil pipe continues squeeze method.The purpose that replaces at squeeze method process middle sleeve is that to make the anhydrous mud of oil jacket annular space be that the oil jacket annular space is full of displacement fluid.Can know H at any time according to formula and oil jacket pressure 1Numerical value be the height of sleeve pipe displacement fluid, just can judge sleeve ring return on having in vain not cement paste or on return what of cement paste.
Whether judge has cement paste that three kinds of methods are arranged in the sleeve pipe:
1 equation: judge according to formula Δ P=7.94H.In the formula, H is that the degree of depth of squeeze method tubing string is the pipe shoe degree of depth.
2 volumetric methods: calculate the volume of oil jacket annular space, the amount of equilibrium liquid is squeezed in metering, and when the balance liquid measure of squeezing into sleeve pipe during greater than the volume of oil jacket annular space, cement paste does not have in the sleeve pipe.
3 curve methods: when the squeeze method sizing process entered the phase III, cement paste entered target zone, and pressure is steady.The oil jacket annular space continues to squeeze into equilibrium liquid, and equilibrium liquid goes out behind the pipe shoe along being advanced into target zone under the sleeve pipe, and because of the viscosity of equilibrium liquid is low than the viscosity of cement paste, the pressure of clamp-oning the stratum is low, and pump pressure at this moment can reduce.
Quadravalence section: for the stage of squeezing
When the cement slurry volume of clamp-oning (or tubing pressure of water squeezing mud) stops to clamp-on cement paste when reaching designing requirement, begin to replace to squeeze, cement paste is ejected tubing shoe, close the oil pipe gate.
Five-stage: wait the stage of coagulating
Open sleeve gate, clamp-on displacement fluid from sleeve pipe cement paste is pushed up the precalculated position, closing well is waited and is coagulated.
The present invention is novel, regulation and control easy to implement, owing to adopt not leak stopping, backwash water mud, fixed tubular column and the squeeze method method construction with fixed attention of band pressure time, replace when putting in place and can wait and coagulate at cement paste without backwash water mud, the direct closing well of fixed tubular column, thereby can shorten the squeeze method time, reduce operating risk and ground pollution, help saving cost and shorten the well workover time, this technology is applicable to heavy oil wells seal, stifled scurrying, and it is particularly effective that the outer cement sheath of sleeve pipe is scurried, reinforced to envelope.
Description of drawings:
Accompanying drawing enters water squeezing mud layer tubing pressure change curve for equilibrium liquid in the work progress of the present invention.
The specific embodiment:
As shown in the figure, when the heavy oil wells envelope is scurried job execution, carry out according to aforementioned implementation step, and judge by three kinds of aforementioned methods whether equilibrium liquid arrives pipe shoe.Among the figure, being the oil well leakage stage by O to A, is that pressure recovers the stage by B to C, is that equilibrium liquid enters the water squeezing mud layer stage by C to E, and EF normally clamp-ons the stage for the following no equilibrium liquid of pipe shoe after stopping to buy equilibrium liquid.

Claims (1)

1. squeezing cement plugging technical skill for thick oil absorption well, it is characterized in that: this technology is in the squeeze method displacement process, regulates and control according to well head oil, sleeve pipe pressure reduction, and, not leak stopping of whole construction course, not backwash water mud fixed tubular column, and employing normal pressure is waited and is coagulated; In the squeeze method process, adopt three kinds of methods to judge whether cement paste is arranged in the sleeve pipe:
(1) equation: judge according to formula Δ P=7.94H;
(2) volumetric method: calculate the volume of oil jacket annular space, the amount of equilibrium liquid is squeezed in metering, and when the balance liquid measure of squeezing into sleeve pipe during greater than the volume of oil jacket annular space, cement paste does not have in the sleeve pipe;
(3) curve method: when the squeeze method sizing process entered the phase III, cement paste entered target zone, and pressure is steady; The oil jacket annular space continues to squeeze into equilibrium liquid, and equilibrium liquid goes out behind the pipe shoe along being advanced into target zone under the sleeve pipe, and because of the viscosity of equilibrium liquid is low than the viscosity of cement paste, the pressure of clamp-oning the stratum is low, and pump pressure at this moment can reduce.
CNA2008100100343A 2008-01-04 2008-01-04 Squeezing cement plugging technical skill for thick oil absorption well Pending CN101196103A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008100100343A CN101196103A (en) 2008-01-04 2008-01-04 Squeezing cement plugging technical skill for thick oil absorption well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008100100343A CN101196103A (en) 2008-01-04 2008-01-04 Squeezing cement plugging technical skill for thick oil absorption well

Publications (1)

Publication Number Publication Date
CN101196103A true CN101196103A (en) 2008-06-11

Family

ID=39546708

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008100100343A Pending CN101196103A (en) 2008-01-04 2008-01-04 Squeezing cement plugging technical skill for thick oil absorption well

Country Status (1)

Country Link
CN (1) CN101196103A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104879118A (en) * 2015-04-21 2015-09-02 长江大学 Oil well cement depth-returning fixation-accompanying monitoring method and system under conditions of underground single and double leaking layers
CN106948788A (en) * 2017-03-21 2017-07-14 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 A kind of method for implementing secondary well cementation in net horizontal section
CN114893146A (en) * 2021-12-24 2022-08-12 中煤地质集团有限公司 Method for unsealing and cementing of channeling drilling hole

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104879118A (en) * 2015-04-21 2015-09-02 长江大学 Oil well cement depth-returning fixation-accompanying monitoring method and system under conditions of underground single and double leaking layers
CN104879118B (en) * 2015-04-21 2018-04-24 长江大学 Cementing concrete returns deep with solid monitoring method and system under the conditions of the single, double drop ply in underground
CN106948788A (en) * 2017-03-21 2017-07-14 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 A kind of method for implementing secondary well cementation in net horizontal section
CN106948788B (en) * 2017-03-21 2020-03-17 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 Method for implementing secondary well cementation in horizontal well section
CN114893146A (en) * 2021-12-24 2022-08-12 中煤地质集团有限公司 Method for unsealing and cementing of channeling drilling hole

Similar Documents

Publication Publication Date Title
CN103343543B (en) Foundation pit dewatering well pressure-reduction-type plugging method
WO2017000622A1 (en) Storage-type precise quantitative injection system for injection of underground oil or gas well operating agent and injection method thereof
CN101864925B (en) Drilling-free sizing collar and process
CN102787602A (en) Curtain grouting technique
CN102877812A (en) Method of balancing pressure for well cementation
CN104153738A (en) Blocking controlling and leaking stopping tool assembly and leaking stopping method applied to drilling engineering
CN207161064U (en) A kind of long-acting layered water filler of binary channels with one heart
CN101196103A (en) Squeezing cement plugging technical skill for thick oil absorption well
CN102337859B (en) Coal field drill hole leak blocking system
CN102493403A (en) Rock-fill dam deformation control technology
CN203321428U (en) Controlling and plugging tool assembly applied to drilling engineering
CN109083631B (en) Utilize the device and method for repairing and mending in coiled tubing repairing cementing concrete crack
CN200989185Y (en) Expanding flushing packer
CN105587286B (en) Lost circulation prevention flushing packer
CN111852556A (en) Forward and reverse drainage method in downward through-layer drilling
CN103470221A (en) Underbalance tubing, no-killing gas lifting, shaft pumping and pump detecting combined method
CN201209423Y (en) Oilfield workover treatment cement squeeze device
CN204532233U (en) well cementing pipe column combination
CN104060959A (en) Conventional well-flushing valve, pumping well and well flushing method for pumping well
CN110905441A (en) Well cementation method of low-pressure easy-to-leak well and casing string
CN206769892U (en) Self-excitation pressure pulse is layered deblocking tool
CN2837505Y (en) Down-hole grouting tool
CN108979572A (en) Combined anti-pollution sand flushing device and method
RU2235852C1 (en) Method of cement bridge forming in well
CN204716213U (en) Pressure fluctuation meter drives self-balancing piston pump pumping equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20080611