CN101178310B - Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology - Google Patents

Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology Download PDF

Info

Publication number
CN101178310B
CN101178310B CN2007101853872A CN200710185387A CN101178310B CN 101178310 B CN101178310 B CN 101178310B CN 2007101853872 A CN2007101853872 A CN 2007101853872A CN 200710185387 A CN200710185387 A CN 200710185387A CN 101178310 B CN101178310 B CN 101178310B
Authority
CN
China
Prior art keywords
gps
software
data
plane cross
carry out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2007101853872A
Other languages
Chinese (zh)
Other versions
CN101178310A (en
Inventor
张焕杰
魏利民
田朝刚
任立华
张根山
冯千通
黄真辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.
Original Assignee
Hebei Electric Power Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Electric Power Design and Research Institute filed Critical Hebei Electric Power Design and Research Institute
Priority to CN2007101853872A priority Critical patent/CN101178310B/en
Publication of CN101178310A publication Critical patent/CN101178310A/en
Application granted granted Critical
Publication of CN101178310B publication Critical patent/CN101178310B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Position Fixing By Use Of Radio Waves (AREA)

Abstract

The invention relates to a method on carrying through the integration of office and field operations of transmission line investigating design by the technology of full numeralization photography and measuring. The invention is improved based on the prior art. The main improvement of the invention is that the plane section data generated by Supresoft is used for carrying through filed operation measuring and annotation, and then the plane section data is input in a Daoheng Software platform by data batch process software interface. The invention has the advantages of low cost, high working efficiency, reducing work intensity, few personnel investment, reliable quality, convenient popularity and application as well as remarkable economic and social benefits.

Description

Utilize totally digitilized photogrammetric technology to carry out transmission line of electricity survey and design inside and outside trade integration method
Technical field
The present invention relates to a kind ofly utilize totally digitilized photogrammetric technology to carry out transmission line of electricity survey and design inside and outside trade integration method, belong to transmission line of electricity survey and design method and technology field.
Background technology
Along with the development of computer technology, aerial survey technology, late nineteen nineties in last century makes in the photogrammetric measurement and has already developed into the totally digitilized photogrammetric stages of all realizing on computers from simulation, resolution phase.Photogrammetric office work work is finished on computers in batches automatically, has significantly reduced the quality of boat sheet and the technical requirement of operator; Automatic triangulation has significantly reduced the quantity of field operation photo control point; The development of GPS technology and application increase substantially the surveying work efficient of field operation photo control point; In addition, homemade totally digitilized Digital Photogrammetric System (promptly suitable general software) is compared with external totally digitilized Digital Photogrammetric System, has friendly interface, the significant advantage that expense reduces significantly.In sum, totally digitilized photogrammetric technology is applied rapidly in China.
The total digitalization Digital Photogrammetric System can be exported stereoscopic model, orthophotoquad (DOM), digital elevation model (DEM), digital line layout figure (DLG), digital raster figure (DRG), utilizes its corresponding software module can generate digital topography map.
Exploration department in electric system is applied to the aerial survey technology in the surveying work of ultra-high-tension power transmission line engineering very early.Development along with the GPS technology, the exploitation of homemade full digital photogrammetric system (suitable general software), making with totally digitilized Digital Photogrammetric System, GPS technology is that the totally digitilized photogrammetric technology of core is applied in ultra-high-tension power transmission line engineering survey design and become possibility.The full digital photogrammetric technology has become a comparatively technology in forward position of Electric Power Survey design system, how to make totally digitilized photogrammetric technology better service become the focus of research in the high-tension line survey and design.Suitable general software company has developed the software module of utilizing stereoscopic model to optimize the transmission line of electricity path cooperatively with electric system about 2003, and Preliminary Exploitation from the software module of stereoscopic model extraction transmission line of electricity plane cross section.Because the research that suitable general software company uses the transmission line of electricity survey and design is limited with input, it is perfect not to the utmost to optimize the path module function, extracting circuit plane cross section vertical accuracy that circuit plane cross section module obtains can not engineering demands, and does not have batch processing software data interface with general transmission route survey design integration software-Dao Heng software (SLCAD).Online one point data interface not only needs the technician many, inefficiency, and also failure rate is higher, causes to optimize use GPS measurement plane cross section behind the path, and the prosperous software in intake duct, to reach the accuracy requirement of engineering.
At present, electric system exploration department survey and design method step commonly used is: (1) boat flies; (2) GPS aerial survey external control; (3) utilize the interior operation of navigating of suitable general software; (4) indoor stereo model route selection and practicable on the spot; (5) according to optimized path, survey crew uses GPS field acquisition plane cross section data; (6), and generate the circuit plane cross section with the prosperous software of above-mentioned plane cross section data input channel; (7) walkthrough tower position on the prosperous software platform in road; And the open-air setting-out tower of use GPS position; With the setting-out tower position prosperous software of input channel as a result, utilize prosperous transmission line of electricity CAD software to generate flat section location map again, further launch design effort for the designer.
That the shortcoming of above-mentioned survey and design method is that cost height, inefficiency, personnel drop into is many, labour intensity big, quality can not get guaranteeing.
Summary of the invention
The technical solution adopted for the present invention to solve the technical problems:
The present invention improves on the basis of existing technology and forms, its main improvement is circuit plane cross section data of utilizing suitable general software to generate, carry out again that field operation is measured and transfer paint after, use batch data process software interface with in the prosperous software platform of plane cross section data input channel.
Concrete grammar step of the present invention is as follows:
Concrete grammar step of the present invention includes: (1) boat flies: aeroplane photography is carried out in the path according to primary design; (2) GPS aerial survey external control: the three-dimensional coordinate that uses GPS field survey photo control point; And navigate to transfer to other localities and paint; (3) utilize the interior operation of navigating of suitable general software: according to aviation scanning information, the GPS external control result of above-mentioned (1), (2) step gained, transfer the data of painting, at suitable general software is to carry out automatic triangulation on the full digital photogrammetric system workbench, sets up the digital ground stereoscopic model and generates digital orthoimage topomap and DTM; (4) indoor stereo model route selection and practicable on the spot: utilize digital orthoimage topomap, DTM and stereoscopic model to carry out indoor route selection and optimization path; Field operation uses the RTK mode of operation of GPS that the path setting-out of indoor optimization is arrived on the spot, and adjusts on the spot with GPS, and final corner coordinate is noted with GPS; It is characterized in that it also includes following five steps:
(5) gather the plane cross section data:
Utilize suitable general virtuozo EPMapper software, carry out the stereoscopic model mapping, simultaneously generation pass plane cross section data file according to final route;
(6) field operation is measured and is transferred and paint:
Use the RTK mode of operation of GPS, measure the straight line stake, elevation is checked point, and the repetition measurement corner pile, measure grave, well, the line of electric force class data that to differentiate from the stereoscopic model simultaneously; Use the GPS software kit that data communication is gone into computing machine, and generate data file;
(7) use batch data Processing Interface software to carry out data-switching:
Using batch data Processing Interface software at first to read in field operation measures and transfers the gps data of painting and fit the plane cross section data that general software plane cross section extraction module extracts from stereoscopic model, proofread and correct aerial survey plane cross section data according to gps data then, make the elevation unanimity; The plane cross section data file of prosperous software format is satisfied in output at last, and suffix is TL;
(8) in the prosperous software platform in road, measure design:
The plane cross section data interchange file of batch data Processing Interface software output is called in prosperous software platform, provide the designer in identical platform walkthrough tower position through editor, utilize the position stake of the open-air setting-out tower of GPS, and, further carry out design effort for the designer with the prosperous software platform of final tower bit data input channel that GPS gathers;
(9) set up circuit GIS:
With 1: 5 ten thousand scanning topomap, 1: 1 ten thousand orthophotoquad, tower position coordinate results digital material incoming line GIS platform; Be convenient to carry out figure and belong to inquiry and genus figure inquiry, output thematic map.
Beneficial effect of the present invention is as follows:
(1) cost is low:
The total digitalization Digital Photogrammetric System adopts homemade suitable general software, and cost only is 1/4 of an external homogeneous system (for example extra large Bearing score system); Utilize batch data Processing Interface software than the synchronous plane cross section data acquisition hardware of single-point, cost-saved 20,000 yuan/cover; Optimize the path contraction path, reduce and remove, change tower saving steel etc., can significantly save investment; Personnel's less investment can reduce human cost; Work efficiency improves, and can save the survey and design cost.
(2) high efficiency:
Adopt homemade totally digitilized Digital Photogrammetric System, compare with traditional aerial survey, boat tablet quality, technician's level are required significantly to reduce, the photogrammetric office work work efficiency improves 5 times; Adopt GPS to carry out the aerial survey external control, and compare external locus of control with traditional aerial survey and reduce 60%, work efficiency significantly improves; Adopt batch data Processing Interface software, increase work efficiency 3-5 doubly than the synchronous online plane cross section collecting method of single-point that suitable general software provides, directly adopt GPS field acquisition plane cross section data increase work efficiency 2 times (need not fit in the general software industry gather the plane cross section data) behind the path by stereoscopic model than optimizing; In general, this method is than adopting traditional worker's survey method to increase work efficiency more than 3 times, than adopting traditional airborne survey method to increase work efficiency more than 4 times.
(3) reduce labour intensity:
On the one hand, adopt homemade totally digitilized Digital Photogrammetric System, because work efficiency improves and technical requirement reduces, photogrammetric office work technician's labour intensity significantly reduces; On the other hand, aerial survey external control workload reduces, and adopts the GPS work efficiency to improve, and field operation labour intensity reduces; In addition, because batch data Processing Interface software has solved the precision and the lower problem of efficient of aerial survey plane cross section data, most of plane cross section The data airborne survey method obtains, and has reduced the labour intensity of field work; The method that the plane cross section data that batch data Processing Interface software and suitable general software provide enter the SLCAD platform, because its work efficiency improves 3-5 doubly, labour intensity also can significantly reduce.
(4) personnel's less investment:
The photogrammetric office work work efficiency improves, and can reduce personnel's input; Aerial survey external control workload reduces and adopts GPS, can reduce technician 2-3 people; Batch data Processing Interface software input is used, and can be reduced to 1 people to 2 technician of suitable general software and SLCAD on-line job, and work efficiency improves the input that also can reduce human resources.
(5) reliable in quality:
Owing to adopt the integral application method of multinomial new and high technology, human intervention has been dropped to minimum, error rate significantly reduces; Adopt GPS to carry out the field data collection, error does not accumulate; Use and check by engineering, accumulated tight Quality Control Procedure and the method for a cover.For example GPS field work requirement has avoided base station to start the wrong mistake that causes.
(6) easy to utilize:
The total digitalization Digital Photogrammetric System adopts homemade suitable general software, and it is convenient not only to link up, and expense is lower, and boat tablet quality and technician are required to reduce, and is easy to utilize; Adopt batch data Processing Interface software, simple to operate, high efficiency, and also swap data is the * .TL form of original Electric Power Design Institute system widespread use, is convenient to understand and editor; Solved the problem that aerial survey data vertical accuracy is proofreaied and correct and entered the SLCAD platform in batches by batch data Processing Interface software, and the deficiency that the gps data warehouse-in efficiency that has remedied SLCAD software is low and aerial survey data vertical accuracy calibration function is weak, and SLCAD reaches 95% in the market share of power survey and design institute system.
(7) economic benefit and obvious social benefit:
Optimize the direct investment that path contraction path, minimizing housing demolition etc. reduce engineering, work efficiency improves, and reduces the input of manpower and materials, and it is that power grid GIS is laid the data basis that the 4D digital product is provided, and it is conspicuous obtaining remarkable economic efficiency.The applicant has utilized this technology to finish 500kV circuit 2500km, adopt homemade totally digitilized Digital Photogrammetric System to optimize path 4%, every kilometer investment is by 1,800,000 yuan of calculating, save 18,000 ten thousand yuan of investments, add to reduce and remove and change tower saving steel, conservative estimation is about 8,000,000 yuan; The work efficiency raising reduces survey and design manpower and materials input, saves 4 by every kilometer and organizes work day, and each organizes 1000 yuan of calculating on work day, saves 1,000 ten thousand yuan of funds altogether; Utilize 4D and other digital product,, gather 2000 yuan of calculating of expense, can save 5,000,000 yuan by every kilometer later stage for circuit GIS provides basic digital information.Total is economized on the use of funds 1.95 hundred million yuan, remarkable in economical benefits.
Shorten path and reduce leap, removal and trees felling by path optimization, environment has been played the maximization protection, reduced taking of ploughing; By reducing inside and outside industry working time and intensity, alleviated technician's labour intensity greatly; By abundant digital basis information is provided,, make more real, the science of GISization management of electrical network in the future, obvious social benefit for the GIS data that provides the foundation.
Description of drawings
Fig. 1 is a theory diagram of the present invention.
Fig. 2 is batch data Processing Interface software workflow figure.
Fig. 3 is suitable general software, batch data Processing Interface software, the prosperous software in road, the integrated workflow diagram of GPS.
Embodiment
Utilize method of the present invention to carry out survey and design work at mountain route (sweat sea-Guyuan-circuit Hebei, safety city section) and Plain circuit (dan north, 500KV Shijiazhuang-stone east circuit) respectively, the concrete grammar step is to operate according to the technical scheme in the foregoing invention content part.
Need to prove the problem that is converted to prosperous ORG form about gps measurement data here:
Develop the corresponding software (being batch data Processing Interface software) that the mass data that satisfies suitable general software output is converted to demand data form (* .TL and * .CSV) fast.
(1) selection of development language:
Because this software does not need too many interface, only need the input raw filename, produce specified file and get final product, therefore not selecting visible language, is development language and select the C language, and the internal memory that the C language system accounts for is little, transplantability is good, carry out the efficient height, and computing function is comparatively powerful.
(2) selection of suitable general software output data form:
The data file of selecting text formatting is as source data file, the content that this document comprised is the abundantest, has promptly comprised the terrestrial coordinate (terrestrial coordinate X, terrestrial coordinate Y, terrestrial coordinate Z) that circuit coordinate (atural object coding, tired distance, offset distance, elevation) has also comprised circuit atural object.
(3) selection of the prosperous software input in road data layout:
* the file of .TL and * .CSV data layout.* .TL is the data layout that survey crew is familiar with the most, is convenient to read and editor; * .CSV is the most frequently used data layout that GPS gathers.Therefore, select to import data layout as the prosperous software in road with the file of these two kinds of data layouts.
Adopt batch data Processing Interface software data processing, only need output TXT data file from aerial survey software, carry out data batch processing interface software, import file name just can generate the data file of * .TL and two kinds of forms of * .CSV, it is simple to operate that circuit plane cross section in the feasible suitable general software converts prosperous software route plan to, do not need industry personnel in two, do not need to increase in addition computer equipment, improve the work efficiency of the data processing of industry in the aerial survey line project is measured simultaneously, reduced error rate.

Claims (1)

1. utilize totally digitilized photogrammetric technology to carry out transmission line of electricity survey and design inside and outside trade integration method, its concrete grammar step includes: (1) boat flies: aeroplane photography is carried out in the path according to primary design; (2) GPS aerial survey external control: the three-dimensional coordinate that uses GPS field survey photo control point; And navigate to transfer to other localities and paint; (3) utilize the interior operation of navigating of suitable general software: according to aviation scanning information, the GPS external control result of above-mentioned (1), (2) step gained, transfer the data of painting, at suitable general software is to carry out automatic triangulation on the full digital photogrammetric system workbench, sets up the digital ground stereoscopic model and generates digital orthoimage topomap and DTM; (4) indoor stereo model route selection and practicable on the spot: utilize digital orthoimage topomap, DTM and stereoscopic model to carry out indoor route selection and optimization path; Field operation uses the RTK mode of operation of GPS that the path setting-out of indoor optimization is arrived on the spot, and adjusts on the spot with GPS, and final corner coordinate is noted with GPS; It is characterized in that it also includes following five steps:
(5) gather the plane cross section data:
Utilize suitable general virtuozo EPMapper software, carry out the stereoscopic model mapping, simultaneously generation pass plane cross section data file according to final route;
(6) field operation is measured and is transferred and paint:
Use the RTK mode of operation of GPS, measure the straight line stake, elevation is checked point, and the repetition measurement corner pile, measure grave, well, the line of electric force class data that to differentiate from the stereoscopic model simultaneously; Use the GPS software kit that data communication is gone into computing machine, and generate data file;
(7) use batch data Processing Interface software to carry out data-switching:
Using batch data Processing Interface software at first to read in field operation measures and transfers the gps data of painting and fit the plane cross section data that general software plane cross section extraction module extracts from stereoscopic model, proofread and correct aerial survey plane cross section data according to gps data then, make the elevation unanimity; The plane cross section data file of prosperous software format is satisfied in output at last, and suffix is TL;
(8) in the prosperous software platform in road, measure design:
The plane cross section data interchange file of batch data Processing Interface software output is called in prosperous software platform, provide the designer in identical platform walkthrough tower position through editor, utilize the position stake of the open-air setting-out tower of GPS, and, further carry out design effort for the designer with the prosperous software platform of final tower bit data input channel that GPS gathers;
(9) set up circuit GIS:
With 1: 5 ten thousand scanning topomap, 1: 1 ten thousand orthophotoquad, tower position coordinate results digital material incoming line GIS platform; Be convenient to carry out figure and belong to inquiry and genus figure inquiry, output thematic map.
CN2007101853872A 2007-12-12 2007-12-12 Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology Active CN101178310B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007101853872A CN101178310B (en) 2007-12-12 2007-12-12 Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007101853872A CN101178310B (en) 2007-12-12 2007-12-12 Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology

Publications (2)

Publication Number Publication Date
CN101178310A CN101178310A (en) 2008-05-14
CN101178310B true CN101178310B (en) 2010-08-11

Family

ID=39404653

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007101853872A Active CN101178310B (en) 2007-12-12 2007-12-12 Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology

Country Status (1)

Country Link
CN (1) CN101178310B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101929858B (en) * 2009-12-14 2012-09-05 煤航(香港)有限公司 Precise surveying and mapping method of 0.25m contour interval of flat ground with large scale of 1:500 to 1:200
CN101763658B (en) * 2009-12-14 2012-07-25 煤航(香港)有限公司 Manufacturing method for full-factor real-tridimensional large scale numerical map
CN101742435B (en) * 2009-12-17 2012-07-25 西北师范大学 Digital mapping method
CN102235858A (en) * 2011-03-24 2011-11-09 广东省电力设计研究院 Coded real-time kinematic global positioning system (RTK-GPS) plane section measuring method and system
CN102645663A (en) * 2012-04-25 2012-08-22 云南电力试验研究院(集团)有限公司电力研究院 Rapid transmission line tower coordinate positioning method based on coordinate transformation
CN102750413B (en) * 2012-06-19 2014-11-05 江苏省电力设计院 Data processing and mapping method of topographic surveying of electric transmission line tower positions
CN102760189A (en) * 2012-06-19 2012-10-31 江苏省电力设计院 Automatic outputting method of electric transmission line house distribution map
CN102968522B (en) * 2012-10-31 2015-04-15 中国石油化工股份有限公司 Integrated information application method for survey and design of oil and gas transmission pipeline
CN104006805A (en) * 2013-02-27 2014-08-27 河南省电力勘测设计院 Electric power engineering field reconnaissance method based on mobile GIS
CN103388344A (en) * 2013-07-23 2013-11-13 吴江市同心电子科技有限公司 GSM-based (Global System of Mobile Communication-based) pile foundation construction survey and setting-out system
CN104462706A (en) * 2014-12-19 2015-03-25 浪潮集团有限公司 Method for automatically building specific-width plate edge copper in ALLEGRO software
CN104899371B (en) * 2015-06-03 2018-03-23 国核电力规划设计研究院 Survey of Transmission Line method and device
CN109238242A (en) * 2017-07-10 2019-01-18 北京正能空间信息技术有限公司 Transmission line of electricity path optimization route selection based on three-dimensional large scene
CN109655044B (en) * 2018-12-29 2021-03-16 中国能源建设集团浙江省电力设计院有限公司 Quality control method for surveying, positioning and measuring finished products of power transmission lines
CN110986888A (en) * 2019-12-17 2020-04-10 中煤航测遥感集团有限公司 Aerial photography integrated method
CN111473771A (en) * 2020-04-17 2020-07-31 河南省焦作地质勘察设计有限公司 Method for measuring mine topographic map by RTK (real-time kinematic) linear lofting measurement
CN112558100B (en) * 2021-02-25 2021-04-27 山东广域科技有限责任公司 Three-dimensional visual intelligent monitoring device for high-voltage transmission line

Also Published As

Publication number Publication date
CN101178310A (en) 2008-05-14

Similar Documents

Publication Publication Date Title
CN101178310B (en) Method for surveying and designing powerline and inside and outside trade integration using full digitisation photogrammetric technology
CN110222357B (en) BIM modeling method for planning and constructing sponge city
CN106846478B (en) Water and electricity hydraulic engineering geology three-dimensional outdoor scene editing, recording and map filling system
CN103884321B (en) A kind of remote sensing image becomes figure technique
CN106779417A (en) The collection of engineering investigation information digitalization, management and integrated application method
CN101988961B (en) Geographic location data collecting system
CN102222140B (en) Design drawing information extraction method of complex bridge structural analysis and modeling
CN103955566B (en) A kind of transmission line of electricity three-dimensional design method and system based on Google Earth
CN103093008A (en) System and method for power transmission and transformation project three-dimensional-aided preliminary design
CN102708587A (en) Method and system for acquiring three-dimensional building information rapidly
CN110704928A (en) Method for converting BIM model into GIS model
CN104657563A (en) Intelligent design platform and intelligent design method of photovoltaic power station
CN102750359A (en) Space information extraction and format conversion method based on electric transmission line three-dimensional model
CN110929363A (en) Communication line investigation design method and system
CN105005580A (en) Method and device for displaying reservoir terrain
CN110688756B (en) Collection and drawing integrated completion drawing manufacturing method
CN108595079A (en) A kind of project of transmitting and converting electricity surveying method shared based on multiple terminals cloud platform
CN103245331A (en) Large-scale aerial survey indoor and outdoor integrated system and control method
CN102880749B (en) 2D-3D (two-dimensional-three-dimensional) union layout method of communication satellite
Zhao et al. The research and development of 3D urban geographic information system with Unity3D
CN103996991B (en) Selection method and system for transmission line of electricity
CN114167450A (en) Beidou foundation enhancement system with high-precision positioning function
CN107741925B (en) Automatic conversion method and device for underground pipeline survey data
Chang et al. Design and realization of a 3D and user-oriented auxiliary system for electric power engineering field survey
Kong et al. Application of unmanned aerial vehicle remote sensing technology in completion survey of land increase and decrease connection projects in mountainous area

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 050031 No. 6 Jianhua Street, Shijiazhuang City, Hebei Province

Patentee after: China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.

Address before: 050031 No. 6 Jianhua Street, Shijiazhuang City, Hebei Province

Patentee before: Hebei Province Power Surveying Design & Research Institute

CP01 Change in the name or title of a patent holder