CN103955566B - A kind of transmission line of electricity three-dimensional design method and system based on Google Earth - Google Patents

A kind of transmission line of electricity three-dimensional design method and system based on Google Earth Download PDF

Info

Publication number
CN103955566B
CN103955566B CN201410142771.4A CN201410142771A CN103955566B CN 103955566 B CN103955566 B CN 103955566B CN 201410142771 A CN201410142771 A CN 201410142771A CN 103955566 B CN103955566 B CN 103955566B
Authority
CN
China
Prior art keywords
dimensional
transmission line
section
electricity
section point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410142771.4A
Other languages
Chinese (zh)
Other versions
CN103955566A (en
Inventor
孙永旺
黄有为
崔鸣昆
刘忠文
王伟
李立
田磊
雷占芬
柯淑琳
毛森茂
陈清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Co ltd
Shenzhen Power Supply Planning Design Institute Co ltd
Original Assignee
SHENZHEN POWER SUPPLY PLANNING DESIGN INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN POWER SUPPLY PLANNING DESIGN INSTITUTE Co Ltd filed Critical SHENZHEN POWER SUPPLY PLANNING DESIGN INSTITUTE Co Ltd
Priority to CN201410142771.4A priority Critical patent/CN103955566B/en
Publication of CN103955566A publication Critical patent/CN103955566A/en
Application granted granted Critical
Publication of CN103955566B publication Critical patent/CN103955566B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Geophysics And Detection Of Objects (AREA)

Abstract

The invention discloses a kind of transmission line of electricity three-dimensional design method and system based on Google Earth, method includes:Initialization is designed, so that it is determined that the parameter of transmission line of electricity to be designed;According to default Method of Data Organization and transmission line parameter to be designed, location and design is carried out on Google Earth, so as to obtain selected path profile and selected corner coordinate;According to selected corner coordinate, transmission line of electricity atural object vector quantization mark and section point data acquisition processing are carried out on Google Earth;Generate plane cross section;Shaft tower position walk-through is carried out according to the plane cross section of generation;The three-dimensional steel tower modeling module of generation parametrization, then the three-dimensional steel tower modeling module of loading parametrization carries out three-dimensional range and design optimization in Google Earth, so as to obtain tower position outcome table;Export path profile, plane cross section and tower the position outcome table of generation.The present invention have the advantages that data acquisition easily and fast with it is cheap, can be widely applied to electric power project engineering field.

Description

A kind of transmission line of electricity three-dimensional design method and system based on Google Earth
Technical field
The present invention relates to electric power project engineering field, especially a kind of transmission line of electricity three dimensional design side based on Google Earth Method and system.
Background technology
Explanation of nouns:
Ruby language:A kind of object-oriented, injunctive, functional expression, dynamic general programming language, in 1990s Mid-term is designed and developed by Japanese's Yukihiro Matsumoto.
Google SketchUp softwares:Google's sketch great master's software, is a free 3D designs that Google provides Software.
Electric power route selection will consider nature, geographical conditions and economy, social factor, it is therefore desirable to the higher ground of actuality Based on shape figure, acquisition cycle length, the cost of topographic map data are high.
When conventional transmission lines road is designed, designer needs to carry out addressing, route selection and project opinion on the basis of topographic map Card.But influenceed by various factors, the Fundamental Geographic Information Data of some remote mountain areas updates slower, still continues to use seventy or eighty The topographic map in age, the need for not caught up with economy and social development.In addition, the acquisition of data also needs to territory, planning etc. The examination & approval of all departments, flow is cumbersome, and the cycle is long.
In order to solve the above problems, domestic and international associated companies devise power engineering Three-dimensional Design Software, are built using three-dimensional Mould technology is simulated to circuit panorama, makes designer from the feasibility for macroscopically holding design, to design expropriation of land Remove less, scissors crossing it is few, the scheme of reduced investment and short time limit.But, the program needs a large amount of acquisition costs high and obtains week The dem data and DOM data supportings of phase length, data acquisition not enough facilitate, and speed is relatively slow and cost is higher.
Google Maps(Google map)And Google Earth(Google Earth)Free data are not only provided, and Allow user to find point of interest wherein and make to mark, mark, other global users are shared with by internet, so that Reach that the whole world of GIS information datas is shared.Google Earth possess in the satellite image of global range, big and medium-sized cities region also There is the high-resolution image in continuous renewal.In rural areas, the resolution ratio of Google Earth images is about in 10~30m, energy Reflect water system fully aware ofly and substantially tell village, particularly tell sheet of factory and exploitation with being apparent from Area.And the high definition image resolution of big and medium-sized cities reaches 0.4m, the general graticule that can be seen that on highway, the atural object letter reflected Breath compares 1:2000 topographic maps are apparent., more can be anti-than traditional topographic map and these satellite images are all to shoot recent years Reflect region present situation.Current Google companies have been opened for carrying out Google map, the API of Google earth secondary development Storehouse, on this basis, user can download the information such as google earth elevation and image, then by computer programming Corresponding electronic topographic map is made by carrying out professional software, is prospective design service.
But, also there is not a kind of data acquisition easily and fast and lower-cost in the industry at present, based on the defeated of Google Earth Electric line three-dimensional design method and system.
The content of the invention
In order to solve the above-mentioned technical problem, the purpose of the present invention is:There is provided a kind of data acquisition easily and fast and cost compared with Low, the transmission line of electricity three-dimensional design method based on Google Earth.
It is another object of the present invention to:A kind of data acquisition is provided easily and fast and lower-cost, based on Google Earth Transmission line of electricity three-dimensional design system.
The technical solution adopted for the present invention to solve the technical problems is:A kind of transmission line of electricity based on Google Earth is three-dimensional Design method, including:
A, initialization is designed, so that it is determined that the parameter of transmission line of electricity to be designed;
B, the transmission line parameter to be designed according to default Method of Data Organization and determination, are selected on Google Earth Line is designed, so as to obtain selected path profile and selected corner coordinate;
The selected corner coordinate of C, basis, carries out transmission line of electricity atural object vector quantization mark on Google Earth and section is counted Handled according to acquisition, so as to obtain the panel data and section point data of plane cross section;
D, the panel data according to plane cross section and section point data, generate plane cross section;
E, according to the plane cross section of generation carry out shaft tower position walk-through;
F, using Ruby language application programming interface to google SketchUp softwares carry out secondary development, from And generate the three-dimensional steel tower modeling module of parametrization;Then according to the result of shaft tower position walk-through, parametrization is loaded in Google Earth Three-dimensional steel tower modeling module carries out three-dimensional range and design optimization, so as to obtain tower position outcome table;
G, the path profile of output generation, plane cross section and tower position outcome table.
Further, the step B, it includes:
B1, according to default Method of Data Organization, the transmission line of electricity data of collection are converted to and inputted after KML file data Into Google Earth;
B2, the parameter with reference to Google Earth, Google Maps and transmission line of electricity to be designed carry out path and selected, so as to be selected Fixed path profile and selected corner coordinate.
Further, the step C, it includes:
C1, on Google Earth to the atural object in the setpoint distance of transmission line of electricity both sides and transmission line of electricity across in area Important atural object carries out vector quantization mark, so as to obtain the panel data of plane cross section;
The selected corner coordinate of C2, basis, carries out section point P on Google Earth(X, Y, Z)Three-dimensional abscissa and three Tie up ordinate to calculate, the section point P(X, Y, Z)Three-dimensional abscissa P.X and three-dimensional vertical P.Y calculation formula of sitting be:
,
Wherein, J1 and J2 is two adjacent corners, and J1.X is corner J1 to section point P(X, Y, Z)Lateral separation, J1.Y is corner J1 to section point P(X, Y, Z)Fore-and-aft distance, S be default section point sampling spacing,For corner J1 To corner J2 grid azimuth;
C3, section point P obtained using elevation interpolation method(X, Y, Z)Elevation, so as to obtain the section point P of plane cross section (X, Y, Z)Three-dimensional Z coordinate P.Z.
Further, the step C3, it includes:
C31, the coordinate for obtaining adjacent two corner in selected path profile;
C32, according to default fixed range, interpolation goes out section point between adjacent two corner;
C33, the geodetic coordinates for obtaining interpolation section point, are then converted into screen by the geodetic coordinates of interpolation section point and sit Mark;
C34, the screen coordinate according to interpolation section point, call elevation to obtain the elevation that function obtains interpolation section point, from And obtain the section point P of plane cross section(X, Y, Z)Three-dimensional Z coordinate P.Z.
Further, the step F, it includes:
F1, using Ruby language application programming interface to google SketchUp softwares carry out secondary development, from And generate the three-dimensional steel tower modeling module of parametrization;
F2, steel tower threedimensional model built using the three-dimensional steel tower modeling module of parametrization;
F3, the data that the steel tower three-dimensional modeling data of structure is converted into dae forms;
F4, with reference to structure steel tower threedimensional model and shaft tower position walk-through result, generate for three dimensional navigation KML text Part;
F5, in the KML file of generation the path of transmission line of electricity is optimized, so as to obtain tower position outcome table.
Further, the parameter of the transmission line of electricity to be designed includes line voltage distribution grade, sideline distance and elevation point sampling Spacing.
Further, the default Method of Data Organization include point-like Method of Data Organization, wire Method of Data Organization and Planar Method of Data Organization.
The present invention solves another technical scheme for being used of its technical problem:A kind of transmission line of electricity based on Google Earth Three-dimensional design system, including:
Initialization module, for being designed initialization, so that it is determined that the parameter of transmission line of electricity to be designed;
Location and design module, for according to default Method of Data Organization and determine transmission line parameter to be designed, Location and design is carried out on Google Earth, so as to obtain selected path profile and selected corner coordinate;
Vector quantization is marked with section point data acquisition module, and the corner coordinate selected for basis is enterprising in Google Earth Row transmission line of electricity atural object vector quantization is marked and section point data acquisition processing, so as to obtain the panel data and section of plane cross section Point data;
Plane cross section generation module, for the panel data according to plane cross section and section point data, generates plane cross section;
Shaft tower position walk-through module, for carrying out shaft tower position walk-through according to the plane cross section of generation;
Three-dimensional range and design optimization module, for the application programming interface using Ruby language to google SketchUp softwares carry out secondary development, so as to generate the three-dimensional steel tower modeling module of parametrization;Then according to shaft tower position walk-through As a result, the three-dimensional steel tower modeling module of loading parametrization carries out three-dimensional range and design optimization in Google Earth, so as to obtain tower Position outcome table;;
Output module, path profile, plane cross section and tower the position outcome table for exporting generation;
The output end of the initialization module passes sequentially through location and design module, vector quantization mark and obtained with section point data Module, plane cross section generation module, shaft tower position walk-through module, three-dimensional range and design optimization module and then defeated with output module Enter end connection.
Further, the location and design module, it includes:
Date Conversion Unit, for according to default Method of Data Organization, the transmission line of electricity data of collection to be converted into KML It is input to after file data in Google Earth;
Unit is selected in path, and the parameter for combining Google Earth, Google Maps and transmission line of electricity to be designed carries out path It is selected, so as to obtain selected path profile and selected corner coordinate;
The output end of the input of the Date Conversion Unit and initialization module is connected, the Date Conversion Unit it is defeated Go out to hold passage path to select unit and then be connected with vector quantization mark with the input of section point data acquisition module.
Further, the vector quantization mark and section point data acquisition module, it includes:
Vector quantization indexing unit, on Google Maps to the atural object in the setpoint distance of transmission line of electricity both sides and transmission of electricity Important atural object in line crossing area carries out vector quantization mark, so as to obtain the panel data of plane cross section;
Coordinate calculating unit, the corner coordinate selected for basis, carry out section point P on Google Earth in length and breadth(X, Y, Z)Three-dimensional abscissa and three-dimensional ordinate calculate, the section point P(X, Y, Z)Three-dimensional abscissa P.X and three-dimensional vertical sit P.Y Calculation formula is:
,
Wherein, J1 and J2 is two adjacent corners, and J1.X is corner J1 to section point P(X, Y, Z)Lateral separation, J1.Y is corner J1 to section point P(X, Y, Z)Fore-and-aft distance, S be default section point sampling spacing,For corner J1 To corner J2 grid azimuth;
Section point height acquiring unit, for obtaining section point P using elevation interpolation method(X, Y, Z)Elevation so that To the section point P of plane cross section(X, Y, Z)Three-dimensional Z coordinate P.Z;
The output end that the input of the vector quantization indexing unit selectes unit with path is connected, the quantization indexing unit Output end pass sequentially through coordinate calculating unit in length and breadth and section point height acquiring unit so that with plane cross section generation module Input is connected.
The beneficial effects of the method for the present invention is:Transmission line of electricity three dimensional design is carried out based on Google Earth, taken full advantage of The geography information such as detailed topographical map, aviation image figure that Google Earth and Google Maps are provided free and social and economic information are to set Meter service, realizes transmission line of electricity route selection, major surface features vector quantization, the drawing of flat section, shaft tower Parametric three-dimensional modeling, design effect The Transmission Line Design overall processes such as fruit three-dimensional range, three-dimensional artificial, path optimization's design and result of design output, are reduced to passing Unite topographic map data dependence, have the advantages that data acquisition easily and fast with it is cheap.
The beneficial effect of system of the present invention is:Transmission line of electricity three dimensional design is carried out based on Google Earth, taken full advantage of The geography information such as detailed topographical map, aviation image figure that Google Earth and Google Maps are provided free and social and economic information are to set Meter service, realizes transmission line of electricity route selection, major surface features vector quantization, the drawing of flat section, shaft tower Parametric three-dimensional modeling, design effect The Transmission Line Design overall processes such as fruit three-dimensional range, path optimization's design and result of design output, reduce to dem data and The dependence of DOM data, have the advantages that data acquisition easily and fast with it is cheap.
Brief description of the drawings
The invention will be further described with reference to the accompanying drawings and examples.
Fig. 1 is a kind of step flow chart of the transmission line of electricity three-dimensional design method based on Google Earth of the present invention;
Fig. 2 is step B of the present invention flow chart;
Fig. 3 is step C of the present invention flow chart;
Fig. 4 is step C3 of the present invention flow chart;
Fig. 5 is step F of the present invention flow chart;
Fig. 6 is a kind of functional block diagram of the transmission line of electricity three-dimensional design system based on Google Earth of the present invention;
Fig. 7 is the structured flowchart of location and design module of the present invention;
Fig. 8 is the structured flowchart of vector quantization of the present invention mark and section point data acquisition module;
Fig. 9 is the specific mistake that the embodiment of the present invention one carries out transmission line of electricity three dimensional design using Google Earth and Google Maps Journey schematic diagram;
Figure 10 is that the section point coordinates of the embodiment of the present invention one obtains schematic diagram
Figure 11 is the implementation process schematic diagram that the embodiment of the present invention two obtains elevation.
Embodiment
Reference picture 1, a kind of transmission line of electricity three-dimensional design method based on Google Earth, including:
A, initialization is designed, so that it is determined that the parameter of transmission line of electricity to be designed;
B, the transmission line parameter to be designed according to default Method of Data Organization and determination, are selected on Google Earth Line is designed, so as to obtain selected path profile and selected corner coordinate;
The selected corner coordinate of C, basis, carries out transmission line of electricity atural object vector quantization mark on Google Earth and section is counted Handled according to acquisition, so as to obtain the panel data and section point data of plane cross section;
D, the panel data according to plane cross section and section point data, generate plane cross section;
E, according to the plane cross section of generation carry out shaft tower position walk-through;
F, using Ruby language application programming interface to google SketchUp softwares carry out secondary development, from And generate the three-dimensional steel tower modeling module of parametrization;Then according to the result of shaft tower position walk-through, parametrization is loaded in Google Earth Three-dimensional steel tower modeling module carries out three-dimensional range and design optimization, so as to obtain tower position outcome table;
G, the path profile of output generation, plane cross section and tower position outcome table.
Wherein, corner coordinate, for representing the position that transmission line of electricity trend changes.
The three-dimensional steel tower modeling module of parametrization, for automatically generating required three-dimensional iron according to the circuit design parameter of input Tower model.
Reference picture 2, is further used as preferred embodiment, the step B, and it includes:
B1, according to default Method of Data Organization, the transmission line of electricity data of collection are converted to and inputted after KML file data Into Google Earth;
B2, the parameter with reference to Google Earth, Google Maps and transmission line of electricity to be designed carry out path and selected, so as to be selected Fixed path profile and selected corner coordinate.
Wherein, KML is Keyhole markup languages(Keyhole Markup Language)Abbreviation, initially by The exploitation of Keyhole companies is a kind of based on XML grammers and form, for describing and preserving geography information(Such as point, line, figure Picture, polygon and model etc.)Coding criterion, can be recognized and be shown by Google Maps and Google Earth.
Reference picture 3, is further used as preferred embodiment, the step C, and it includes:
C1, on Google Maps to the atural object in the setpoint distance of transmission line of electricity both sides and transmission line of electricity across in area Important atural object carries out vector quantization mark, so as to obtain the panel data of plane cross section;
The selected corner coordinate of C2, basis, carries out section point P on Google Earth(X, Y, Z)Three-dimensional abscissa and three Tie up ordinate to calculate, the section point P(X, Y, Z)Three-dimensional abscissa P.X and three-dimensional vertical P.Y calculation formula of sitting be:
,
Wherein, J1 and J2 is two adjacent corners, and J1.X is corner J1 to section point P(X, Y, Z)Lateral separation, J1.Y is corner J1 to section point P(X, Y, Z)Fore-and-aft distance, S be default section point sampling spacing,For corner J1 To corner J2 grid azimuth;
C3, section point P obtained using elevation interpolation method(X, Y, Z)Elevation, so as to obtain the section point P of plane cross section (X, Y, Z)Three-dimensional Z coordinate P.Z.
Wherein, transmission line of electricity includes highway, railway, water system, park, settlement place, industry across the important atural object in area Area, mining area etc..
Reference picture 4, is further used as preferred embodiment, the step C3, and it includes:
C31, the coordinate for obtaining adjacent two corner in selected path profile;
C32, according to default fixed range, interpolation goes out section point between adjacent two corner;
C33, obtain interpolation section point geodetic coordinates, then the geodetic coordinates of interpolation section point be converted into screen coordinate;
C34, the screen coordinate according to interpolation section point, call elevation to obtain the elevation that function obtains interpolation section point, from And obtain the section point P of plane cross section(X, Y, Z)Three-dimensional Z coordinate P.Z.
Reference picture 5, is further used as preferred embodiment, the step F, and it includes:
F1, using Ruby language application programming interface to google SketchUp softwares carry out secondary development, from And generate the three-dimensional steel tower modeling module of parametrization;
F2, steel tower threedimensional model built using the three-dimensional steel tower modeling module of parametrization;
F3, the data that the steel tower three-dimensional modeling data of structure is converted into dae forms;
F4, with reference to structure steel tower threedimensional model and shaft tower position walk-through result, generate for three dimensional navigation KML text Part;
F5, in the KML file of generation the path of transmission line of electricity is optimized, so as to obtain tower position outcome table.
It is further used as preferred embodiment, the parameter of the transmission line of electricity to be designed includes line voltage distribution grade, side Linear distance and elevational point sampling interval.
Be further used as preferred embodiment, the default Method of Data Organization include point-like Method of Data Organization, Wire Method of Data Organization and planar Method of Data Organization.
Reference picture 6, a kind of transmission line of electricity three-dimensional design system based on Google Earth, including:
Initialization module, for being designed initialization, so that it is determined that the parameter of transmission line of electricity to be designed;
Location and design module, for according to default Method of Data Organization and determine transmission line parameter to be designed, Location and design is carried out on Google Earth, so as to obtain selected path profile and selected corner coordinate;
Vector quantization is marked with section point data acquisition module, and the corner coordinate selected for basis is enterprising in Google Earth Row transmission line of electricity atural object vector quantization is marked and section point data acquisition processing, so as to obtain the panel data and section of plane cross section Point data;
Plane cross section generation module, for the panel data according to plane cross section and section point data, generates plane cross section;
Shaft tower position walk-through module, for carrying out shaft tower position walk-through according to the plane cross section of generation;
Three-dimensional range and design optimization module, for the application programming interface using Ruby language to google SketchUp softwares carry out secondary development, so as to generate the three-dimensional steel tower modeling module of parametrization;Then according to shaft tower position walk-through As a result, the three-dimensional steel tower modeling module of loading parametrization carries out three-dimensional range and design optimization in Google Earth, so as to obtain tower Position outcome table;
Output module, path profile, plane cross section and tower the position outcome table for exporting generation;
The output end of the initialization module passes sequentially through location and design module, vector quantization mark and obtained with section point data Module, plane cross section generation module, shaft tower position walk-through module, three-dimensional range and design optimization module and then defeated with output module Enter end connection.
Reference picture 7, is further used as preferred embodiment, the location and design module, and it includes:
Date Conversion Unit, for according to default Method of Data Organization, the transmission line of electricity data of collection to be converted into KML It is input to after file data in Google Earth;
Unit is selected in path, and the parameter for combining Google Earth, Google Maps and transmission line of electricity to be designed carries out path It is selected, so as to obtain selected path profile and selected corner coordinate;
The output end of the input of the Date Conversion Unit and initialization module is connected, the Date Conversion Unit it is defeated Go out to hold passage path to select unit and then be connected with vector quantization mark with the input of section point data acquisition module.
Reference picture 8, is further used as preferred embodiment, the vector quantization mark and section point data acquisition module, It includes:
Vector quantization indexing unit, on Google Maps to the atural object in the setpoint distance of transmission line of electricity both sides and transmission of electricity Important atural object in line crossing area carries out vector quantization mark, so as to obtain the panel data of plane cross section;
Coordinate calculating unit, the corner coordinate selected for basis, carry out section point P on Google Earth in length and breadth(X, Y, Z)Three-dimensional abscissa and three-dimensional ordinate calculate, the section point P(X, Y, Z)Three-dimensional abscissa P.X and three-dimensional vertical sit P.Y Calculation formula is:
,
Wherein, J1 and J2 is two adjacent corners, and J1.X is corner J1 to section point P(X, Y, Z)Lateral separation, J1.Y is corner J1 to section point P(X, Y, Z)Fore-and-aft distance, S be default section point sampling spacing,For corner J1 To corner J2 grid azimuth;
Section point height acquiring unit, for obtaining section point P using elevation interpolation method(X, Y, Z)Elevation so that To the section point P of plane cross section(X, Y, Z)Three-dimensional Z coordinate P.Z;
The output end that the input of the vector quantization indexing unit selectes unit with path is connected, the quantization indexing unit Output end pass sequentially through coordinate calculating unit in length and breadth and section point height acquiring unit so that with plane cross section generation module Input is connected.
The present invention is described in further detail with reference to specific embodiment.
Embodiment one
Reference picture 9, the present invention carries out the detailed process bag of transmission line of electricity three dimensional design using Google Earth and Google Maps Include:
(1)Initialization:New construction, custom design criteria;
New construction project, determines the power transmission lines to be designed such as line voltage distribution grade, sideline distance, elevational point sampling interval Road parameter.
(2)Location and design is carried out on Google Earth, so that output corner coordinate;
Open software Google Earth software, by the planning high pressure corridor collected from departments such as territory, planning, communications,
Existing transmission line of electricity trend, gas pipeline, oil pipeline, radio guard, Microwave emission platform, main industrial and mining area Planning and present situation data input Deng influence Path selection is into Google Earth.
Google Earth data interchange format is mainly KML file, and the present invention is for the ease of with Google Earth progress data friendship Change, develop the KML data-interface softwares with Google Earth, data is carried out tissue in the way of point, line, surface, so that will be from It is KML file that unified arrange of the data come is collected by the departments such as government territory, planning, water utilities, communication, is then input to Google Earth In.
Then, with reference to Google Maps and Google Earth, Path selection is carried out.Path selection avoids reservoir, ore deposit as far as possible at once Area, park, the facility of residential block, and selected distance is short, intersection is used as preferred plan across scheme few with environmental disruption less.
After path is selected, selected corner coordinate is output to KML file.
(3)Importantly thing is marked on Google Earth, and carries out vector quantization output;
Due to numerous aspects such as Transmission Line Design work nature, geography, soil, economy, humanity, society, safety, technologies The influence of factor, therefore route selection work can not possibly accomplish perfection.In many cases, line alignment is had to across existing The atural objects such as highway, railway, river, reservoir, building.Accordingly, it would be desirable to carry out vector quantization to the above-mentioned atural object in line crossing area Mark, it is also desirable to circuit the right and left setpoint distance(Voltage class is different, required distance is different)Interior various buildings, structure Build the information such as thing and carry out vector quantization annotation.
After vector quantization, KML file is formed, the planar section of generation plane cross section is used as.
(4)Section point data is obtained from Google Earth;
After corner coordinate is determined, you can carry out the acquisition of section point data, section point data is the three-dimensional seat of section point Mark, as shown in Figure 10.It is that can obtain section by the three-dimensional abscissa of the section point of the present invention and three-dimensional ordinate calculation formula Point P1(X, Y, Z)Three-dimensional abscissa P1.X and three-dimensional ordinate P1.Y.And section point P1(X, Y, Z)Three-dimensional Z coordinate P1.Y That is the elevation of P1 points, then need to obtain by the elevation interpolation method of the present invention.
(5)With reference to panel data and profile data, plane cross section is generated;
Profile data in plane cross section of the present invention uses the org forms of Transmission Line Design industry universal.
(6)Shaft tower position walk-through is carried out according to plane cross section;
(7)Shaft tower Parametric three-dimensional modeling is carried out according to first ranking results;
(8)Carry out three-dimensional range and optimization design.
The present invention uses RubyAPI language secondary development google SketchUp, forms Parametric three-dimensional modeling module, Steel tower threedimensional model is set up, and changes into dae forms, these threedimensional models thus can be directly called in GE.Model is set up Afterwards, according to(6)The ranking results of step, can generate the KML file for three dimensional navigation.
Generate after the KML file for three dimensional navigation, can in a computer display field true to nature landform, landforms and its Its social and economic information, and the three-dimensional inquiry, amount in conjunction with design software are calculated, analytic function, it is possible to carrying out indoor tune paints, The optimization to engineered paths scheme can be realized on virtual three-dimensional visualization platform, section, optimization shaft tower rule are automatically extracted Draw, utilize shaft tower ranking achievement estimation body quantity, statistics housing demolition amount, forest zone area, scissors crossing quantity etc. Work, makes path move towards more reasonable, cost of investment is more economical.
Embodiment two
The default three kinds of Method of Data Organization of the present invention are introduced the present embodiment.The default three kinds of data groups of the present invention The mode of knitting includes:
A. punctual geo-objects such as Microwave emission platform, its Method of Data Organization is:
<Placemark>
<name>Call the roll</name>
<visibility>0</visibility>
<LookAt>
<longitude>Longitude</longitude>
<latitude>Latitude</latitude>
<altitude>Elevation</altitude>
<tilt>0</tilt>
<range>Angular field of view</range>
<gx:altitudeMode>relativeToSeaFloor</gx:altitudeMode>
</LookAt>
<styleUrl>The label symbol of # points</styleUrl>
<Point>
<coordinates>Longitude, latitude, elevation</coordinates>
</Point>
</Placemark>
<Placemark>
B. the linear ground object such as power circuit, pipeline, its data are organized as:
<Placemark>
<name>Line title</name>
<description>0</description>
<styleUrl># line patterns</styleUrl>
<LineString>
<coordinates>
Longitude, latitude, elevation, longitude, latitude, elevation ...(The node coordinate string of line)</coordinates>
</LineString>
</Placemark>
C. the area features such as high pressure corridor, Planning and Development area are planned, its Method of Data Organization is:
<Placemark>
<name>Unnamed polygon</name>
<styleUrl>#msn_ylw-pushpin</styleUrl>
<Polygon>
<tessellate>1</tessellate>
<outerBoundaryIs>
<LinearRing>
<coordinates>
Longitude, latitude, elevation, longitude, latitude, elevation ...(Polygon vertex coordinate string)
</coordinates>
</LinearRing>
</outerBoundaryIs>
</Polygon>
</Placemark>。
Embodiment three
The elevation elevation that section point is obtained by elevation interpolation method is introduced the present embodiment.
The elevation of section point needs the DEM provided by Google Earth to obtain, and based on the GE DEM for being extracting tool. The elevation acquisition process mainly use IApplicationGE, ICameraInfoGE, IPointOnTerraGE, This four class libraries of IVewExtentsGE.
And IApplicationGE GetPointOnTerrainFromScreenCoords functions can then realize elevation Direct acquisition.Its grammer is:IPointOnTerrainGE GetPointOnTerrainFromScreenCoords (double screen_x,double screen_y), the input parameter screen_x and screen_y of the function are Double types, and the two parameter values are between -1 and 1, represent coordinate value of the view central point in screen coordinate system.
And known variables during present invention progress elevation interpolation are the geodetic coordinates of section point, it is therefore desirable to first sit the earth Mark, which is mapped to screen coordinate, could obtain the elevation of the point.Its basic ideas is:The adjacent two corners coordinate of acquisition approach, is then pressed Fixed range intercepts interpolated point, and obtains the geodetic coordinates of interpolated point, and interpolated point geodetic coordinates then is converted into screen coordinate System, the height value of the point is obtained finally according to screen coordinate.
The basic procedure that whole section point coordinates of the invention is obtained is as shown in figure 11.
Compared with prior art, the present invention carries out transmission line of electricity three dimensional design based on Google Earth, takes full advantage of Google The geography information such as detailed topographical map, aviation image figure that the earth and Google Maps are provided free and social and economic information take for design Business, realizes transmission line of electricity route selection, major surface features vector quantization, the drawing of flat section, design effect three-dimensional range, path optimization's design With result of design output etc. Transmission Line Design overall process, reduce the dependence to dem data and DOM data, obtained with data Take easily and fast with cheap advantage.
Above is the preferable implementation to the present invention is illustrated, but the invention is not limited to the implementation Example, those skilled in the art can also make a variety of equivalent variations or replace on the premise of without prejudice to spirit of the invention Change, these equivalent deformations or replacement are all contained in the application claim limited range.

Claims (10)

1. a kind of transmission line of electricity three-dimensional design method based on Google Earth, it is characterised in that:Including:
A, initialization is designed, so that it is determined that the parameter of transmission line of electricity to be designed;
B, the transmission line parameter to be designed according to default Method of Data Organization and determination, progress route selection is set on Google Earth Meter, so as to obtain selected path profile and selected corner coordinate;
The selected corner coordinate of C, basis, carries out transmission line of electricity atural object vector quantization mark on Google Earth and section point data is obtained Processing is taken, so as to obtain the panel data and section point data of plane cross section;
D, the panel data according to plane cross section and section point data, generate plane cross section;
E, according to the plane cross section of generation carry out shaft tower position walk-through;
F, secondary development carried out to google SketchUp softwares using the application programming interface of Ruby language, so that raw Into the three-dimensional steel tower modeling module of parametrization;Then according to the result of shaft tower position walk-through, loading parametrization is three-dimensional in Google Earth Steel tower modeling module carries out three-dimensional range and design optimization, so as to obtain tower position outcome table;
G, the path profile of output generation, plane cross section and tower position outcome table.
2. a kind of transmission line of electricity three-dimensional design method based on Google Earth according to claim 1, it is characterised in that:Institute Step B is stated, it includes:
B1, according to default Method of Data Organization, be input to paddy after the transmission line of electricity data of collection are converted into KML file data Sing in the earth;
B2, the parameter with reference to Google Earth, Google Maps and transmission line of electricity to be designed carry out path and selected, so as to obtain selected Path profile and selected corner coordinate.
3. a kind of transmission line of electricity three-dimensional design method based on Google Earth according to claim 2, it is characterised in that:Institute Step C is stated, it includes:
C1, on Google Earth to the atural object in the setpoint distance of transmission line of electricity both sides and transmission line of electricity across important in area Atural object carries out vector quantization mark, so as to obtain the panel data of plane cross section;
The selected corner coordinate of C2, basis, the three-dimensional abscissa and three-dimensional that section point P (X, Y, Z) is carried out on Google Earth is vertical Coordinate is calculated, and the three-dimensional abscissa P.X of the section point P (X, Y, Z) and three-dimensional vertical P.Y calculation formula of sitting are:
<mrow> <mfenced open = "{" close = ""> <mtable> <mtr> <mtd> <mrow> <mi>P</mi> <mo>.</mo> <mi>X</mi> <mo>=</mo> <mi>J</mi> <mn>1.</mn> <mi>X</mi> <mo>+</mo> <mi>S</mi> <mo>&amp;times;</mo> <msub> <mi>Sin&amp;alpha;</mi> <mrow> <mi>J</mi> <mn>1</mn> <mi>J</mi> <mn>2</mn> </mrow> </msub> </mrow> </mtd> </mtr> <mtr> <mtd> <mrow> <mi>P</mi> <mo>.</mo> <mi>Y</mi> <mo>=</mo> <mi>J</mi> <mn>1.</mn> <mi>Y</mi> <mo>+</mo> <mi>S</mi> <mo>&amp;times;</mo> <msub> <mi>Cos&amp;alpha;</mi> <mrow> <mi>J</mi> <mn>1</mn> <mi>J</mi> <mn>2</mn> </mrow> </msub> </mrow> </mtd> </mtr> </mtable> </mfenced> <mo>,</mo> </mrow>
Wherein, J1 and J2 is two adjacent corners, and J1.X is corner J1 to section point P (X, Y, Z) lateral separation, and J1.Y is Corner J1 to section point P (X, Y, Z) fore-and-aft distance, S is default section point sampling spacing, αJ1J2For corner J1 to corner J2 Grid azimuth;
C3, using elevation interpolation method obtain section point P (X, Y, Z) elevation so that obtain plane cross section section point P (X, Y, Z three-dimensional Z coordinate P.Z).
4. a kind of transmission line of electricity three-dimensional design method based on Google Earth according to claim 3, it is characterised in that:Institute Step C3 is stated, it includes:
C31, the coordinate for obtaining adjacent two corner in selected path profile;
C32, according to default fixed range, interpolation goes out section point between adjacent two corner;
C33, the geodetic coordinates for obtaining interpolation section point, are then converted into screen coordinate by the geodetic coordinates of interpolation section point;
C34, the screen coordinate according to interpolation section point, call elevation to obtain the elevation that function obtains interpolation section point, so that To the section point P (X, Y, Z) of plane cross section three-dimensional Z coordinate P.Z.
5. a kind of transmission line of electricity three-dimensional design method based on Google Earth according to claim 4, it is characterised in that:Institute Step F is stated, it includes:
F1, secondary development carried out to google SketchUp softwares using the application programming interface of Ruby language, so that raw Into the three-dimensional steel tower modeling module of parametrization;
F2, steel tower threedimensional model built using the three-dimensional steel tower modeling module of parametrization;
F3, the data that the steel tower three-dimensional modeling data of structure is converted into dae forms;
F4, with reference to structure steel tower threedimensional model and shaft tower position walk-through result, generate the KML file for three dimensional navigation;
F5, in the KML file of generation the path of transmission line of electricity is optimized, so as to obtain tower position outcome table.
6. a kind of transmission line of electricity three-dimensional design method based on Google Earth according to claim any one of 1-5, it is special Levy and be:The parameter of the transmission line of electricity to be designed includes line voltage distribution grade, sideline distance and elevational point sampling interval.
7. a kind of transmission line of electricity three-dimensional design method based on Google Earth according to claim any one of 1-5, it is special Levy and be:The default Method of Data Organization includes point-like Method of Data Organization, wire Method of Data Organization and planar data Organizational form.
8. a kind of transmission line of electricity three-dimensional design system based on Google Earth, it is characterised in that:Including:
Initialization module, for being designed initialization, so that it is determined that the parameter of transmission line of electricity to be designed;
Location and design module, for according to default Method of Data Organization and the transmission line parameter to be designed determined, in Google Location and design is carried out on the earth, so as to obtain selected path profile and selected corner coordinate;
Vector quantization is marked to be carried out defeated with section point data acquisition module, the corner coordinate selected for basis on Google Earth Electric line atural object vector quantization is marked and section point data acquisition processing, so as to obtain the panel data and section points of plane cross section According to;
Plane cross section generation module, for the panel data according to plane cross section and section point data, generates plane cross section;
Shaft tower position walk-through module, for carrying out shaft tower position walk-through according to the plane cross section of generation;
Three-dimensional range and design optimization module, for the application programming interface using Ruby language to google SketchUp softwares carry out secondary development, so as to generate the three-dimensional steel tower modeling module of parametrization;Then according to shaft tower position walk-through As a result, the three-dimensional steel tower modeling module of loading parametrization carries out three-dimensional range and design optimization in Google Earth, so as to obtain tower Position outcome table;
Output module, path profile, plane cross section and tower the position outcome table for exporting generation;
The output end of the initialization module passes sequentially through location and design module, vector quantization mark and obtains mould with section point data Block, plane cross section generation module, shaft tower position walk-through module, three-dimensional range and design optimization module so with the input of output module End connection.
9. a kind of transmission line of electricity three-dimensional design system based on Google Earth according to claim 8, it is characterised in that:Institute Location and design module is stated, it includes:
Date Conversion Unit, for according to default Method of Data Organization, the transmission line of electricity data of collection to be converted into KML file It is input to after data in Google Earth;
Unit is selected in path, and the parameter progress path for combining Google Earth, Google Maps and transmission line of electricity to be designed is selected, So as to obtain selected path profile and selected corner coordinate;
The input of the Date Conversion Unit and the output end of initialization module are connected, the output end of the Date Conversion Unit Passage path is selected unit and then is connected with vector quantization mark with the input of section point data acquisition module.
10. a kind of transmission line of electricity three-dimensional design system based on Google Earth according to claim 9, it is characterised in that: The vector quantization mark and section point data acquisition module, it includes:
Vector quantization indexing unit, on Google Maps to the atural object and transmission line of electricity in the setpoint distance of transmission line of electricity both sides Vector quantization mark is carried out across the important atural object in area, so as to obtain the panel data of plane cross section;
Coordinate calculating unit, the corner coordinate selected for basis, carry out section point P's (X, Y, Z) on Google Earth in length and breadth Three-dimensional abscissa and three-dimensional ordinate are calculated, and the three-dimensional abscissa P.X of the section point P (X, Y, Z) and the three-dimensional vertical P.Y that sits are calculated Formula is:
<mrow> <mfenced open = "{" close = ""> <mtable> <mtr> <mtd> <mrow> <mi>P</mi> <mo>.</mo> <mi>X</mi> <mo>=</mo> <mi>J</mi> <mn>1.</mn> <mi>X</mi> <mo>+</mo> <mi>S</mi> <mo>&amp;times;</mo> <msub> <mi>Sin&amp;alpha;</mi> <mrow> <mi>J</mi> <mn>1</mn> <mi>J</mi> <mn>2</mn> </mrow> </msub> </mrow> </mtd> </mtr> <mtr> <mtd> <mrow> <mi>P</mi> <mo>.</mo> <mi>Y</mi> <mo>=</mo> <mi>J</mi> <mn>1.</mn> <mi>Y</mi> <mo>+</mo> <mi>S</mi> <mo>&amp;times;</mo> <msub> <mi>Cos&amp;alpha;</mi> <mrow> <mi>J</mi> <mn>1</mn> <mi>J</mi> <mn>2</mn> </mrow> </msub> </mrow> </mtd> </mtr> </mtable> </mfenced> <mo>,</mo> </mrow>
Wherein, J1 and J2 is two adjacent corners, and J1.X is corner J1 to section point P (X, Y, Z) lateral separation, and J1.Y is Corner J1 to section point P (X, Y, Z) fore-and-aft distance, S is default section point sampling spacing, αJ1J2For corner J1 to corner J2 Grid azimuth;
Section point height acquiring unit, the elevation for obtaining section point P (X, Y, Z) using elevation interpolation method, so as to be put down The section point P (X, Y, Z) of sectional drawing three-dimensional Z coordinate P.Z;
The output end that the input of the vector quantization indexing unit selectes unit with path is connected, the vector quantization indexing unit Output end passes sequentially through coordinate calculating unit in length and breadth and section point height acquiring unit and then defeated with plane cross section generation module Enter end connection.
CN201410142771.4A 2014-04-10 2014-04-10 A kind of transmission line of electricity three-dimensional design method and system based on Google Earth Active CN103955566B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410142771.4A CN103955566B (en) 2014-04-10 2014-04-10 A kind of transmission line of electricity three-dimensional design method and system based on Google Earth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410142771.4A CN103955566B (en) 2014-04-10 2014-04-10 A kind of transmission line of electricity three-dimensional design method and system based on Google Earth

Publications (2)

Publication Number Publication Date
CN103955566A CN103955566A (en) 2014-07-30
CN103955566B true CN103955566B (en) 2017-10-24

Family

ID=51332841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410142771.4A Active CN103955566B (en) 2014-04-10 2014-04-10 A kind of transmission line of electricity three-dimensional design method and system based on Google Earth

Country Status (1)

Country Link
CN (1) CN103955566B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104504747B (en) * 2014-11-19 2016-05-25 中国南方电网有限责任公司电网技术研究中心 The three-dimensional shaft tower modeling method of a kind of Full Parameterized
CN104794314A (en) * 2015-05-18 2015-07-22 国家电网公司 Three-dimensional simulation model of power transmission line and construction method of three-dimensional simulation model
CN105512399A (en) * 2015-12-09 2016-04-20 国家电网公司 Three-dimensional simulation system for power transmission lines
CN106156883A (en) * 2016-06-21 2016-11-23 长江勘测规划设计研究有限责任公司 A kind of work transmission line early stage tower-pole planning method
CN106503301B (en) * 2016-09-28 2019-08-02 山东东电电气工程技术有限公司 A kind of three-dimensional panorama digitlization electric power line pole tower ranking method
CN107092354B (en) * 2017-04-01 2020-09-29 宁强 Sketchup model virtual reality transformation technology method
CN107729703B (en) * 2017-11-27 2020-08-28 中船第九设计研究院工程有限公司 Sketch Up workshop process design method based on Ruby language
CN109064500B (en) * 2018-06-15 2022-02-08 上海卫星工程研究所 Mapping method for sight line and remote sensing image of static meteorological satellite imager
CN110232739A (en) * 2019-06-21 2019-09-13 国核电力规划设计研究院重庆有限公司 A kind of method that CAD topographic map data is converted to power circuit section
CN112163056A (en) * 2020-09-09 2021-01-01 四川长园工程勘察设计有限公司 Ground object insertion method based on path diagram
CN112182812B (en) * 2020-09-09 2022-11-25 成都深瑞同华软件技术有限公司 Distribution line design method
CN112700030A (en) * 2020-12-02 2021-04-23 国网冀北电力有限公司经济技术研究院 Method for applying cloud computing technology to engineering design
CN112528444A (en) * 2020-12-04 2021-03-19 国网浙江省电力有限公司嘉兴供电公司 Three-dimensional design method and system for power transmission line
CN115640639B (en) * 2022-12-22 2023-03-28 中国建筑第五工程局有限公司 Urban updating scheme simulation and cost estimation method based on digital urban design

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110006805A (en) * 2009-07-15 2011-01-21 주식회사 제이캐스트 Method for designing wireless networks using the google-earth
CN103295085A (en) * 2012-03-02 2013-09-11 姜海西 Highway engineering three-dimensional office system building method based on Google earth

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102590701B (en) * 2012-02-07 2014-04-30 云南电力试验研究院(集团)有限公司电力研究院 Coordinate calibration method for power transmission line towers
CN102945570B (en) * 2012-11-23 2014-03-05 华东师范大学 Method for constructing full-space three-dimensional digital earth model

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110006805A (en) * 2009-07-15 2011-01-21 주식회사 제이캐스트 Method for designing wireless networks using the google-earth
CN103295085A (en) * 2012-03-02 2013-09-11 姜海西 Highway engineering three-dimensional office system building method based on Google earth

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Google Earth二次开发方法及其在公路勘察设计中的应用研究;梁诚等;《交通科技》;20100731;第107-110页 *
Google Earth在输电线路工程中的应用研究;赵成铭;《测绘通报》;20120530(第5期);第71-72页 *

Also Published As

Publication number Publication date
CN103955566A (en) 2014-07-30

Similar Documents

Publication Publication Date Title
CN103955566B (en) A kind of transmission line of electricity three-dimensional design method and system based on Google Earth
CN104766366B (en) A kind of method for building up of three-dimension virtual reality demonstration
CN105320811A (en) Method for establishing topological connected model of urban underground electricity pipe network
CN105701295A (en) Method for rapid integrated presentation of BIM model and three-dimensional geographical information system
CN103093008A (en) System and method for power transmission and transformation project three-dimensional-aided preliminary design
Kaňuk et al. Generating time series of virtual 3-D city models using a retrospective approach
Li et al. Webvrgis based city bigdata 3d visualization and analysis
CN105975591B (en) A kind of production of urban global energy consumption numerical map and display methods and system
Luo et al. Analysis of urban ventilation potential using rule-based modeling
CN106570789A (en) Method for recognizing ecologically sensitive region in power grid planning based on GIS (Geographic Information System)
CN108038138A (en) A kind of method for the WGS84 coordinate systems that Google Maps is transformed into from CAD plane coordinate systems
CN102289581A (en) Method for simulating city expansion based on space function division
CN110175370A (en) A kind of REGION OF WATER INJECTION OILFIELD recognition methods of city charge for remittance
CN109658510A (en) The method, apparatus and server of substation site selection
CN102693328A (en) Application of ARCVIEW GIS (geographic information system) 3.2 technology in mountainous land building design
Khayyal et al. Creation and spatial analysis of 3D city modeling based on GIS data
CN105354882A (en) Method for constructing big data architecture based three-dimensional panoramic display platform for large-spatial-range electricity transmission
CN107169080A (en) A kind of geospatial analysis system being combined based on GIS and spatial database
CN101763659B (en) Method for automatically generating large-scale digitization altitude data model based on image set
JP3940834B2 (en) Analysis work support CAE device using numerical map information data
Stanislawski et al. A raster alternative for partitioning line densities to support automated cartographic generalization
Kaňuk et al. Using virtual 3-D city models in temporal analysis of urban transformations
Yang Energy resilient urban planning
Ryu et al. A development direction of a new archi-urban integration model for utilizing spatial information
Abdel-Bary Ebrahim et al. Planning road networks in new cities using GIS: The case of New Sohag, Egypt

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Sun Yongwang

Inventor after: Mao Senmao

Inventor after: Chen Qing

Inventor after: Huang Youwei

Inventor after: Cui Mingkun

Inventor after: Liu Zhongwen

Inventor after: Wang Wei

Inventor after: Li Li

Inventor after: Tian Lei

Inventor after: Lei Zhanfen

Inventor after: Ke Shulin

Inventor before: Sun Yongwang

Inventor before: Li Li

Inventor before: Chen Qing

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190325

Address after: 518000 First to Sixth Floors of Fuxing Building No. 7 Yuehai Road, Nanshan District, Shenzhen City, Guangdong Province

Co-patentee after: Shenzhen Power Supply Co.,Ltd.

Patentee after: SHENZHEN POWER SUPPLY PLANNING DESIGN INSTITUTE Co.,Ltd.

Address before: 518000 First to Sixth Floors of Fuxing Building No. 7 Yuehai Road, Nanshan District, Shenzhen City, Guangdong Province

Patentee before: SHENZHEN POWER SUPPLY PLANNING DESIGN INSTITUTE Co.,Ltd.