CN101158195B - 弦支穹顶多次预应力施工方法 - Google Patents
弦支穹顶多次预应力施工方法 Download PDFInfo
- Publication number
- CN101158195B CN101158195B CN2007101774692A CN200710177469A CN101158195B CN 101158195 B CN101158195 B CN 101158195B CN 2007101774692 A CN2007101774692 A CN 2007101774692A CN 200710177469 A CN200710177469 A CN 200710177469A CN 101158195 B CN101158195 B CN 101158195B
- Authority
- CN
- China
- Prior art keywords
- rope
- radial bars
- dome
- last
- strut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明公开了一种建筑领域应用的弦支穹顶结构多次预应力施工方法。其施工方法为:第一步安装上层的中心压力环、上径向杆、边缘构件;第二步安装下层的下径向索、下环向索和撑杆;第三步,通过张拉下环向索或者下径向索或者调整撑杆的长度,在结构中施加预应力;第四步,安装上环向杆;第五步,对结构施加外荷载。本发明形成的弦支穹顶结构比传统的方法形成的结构受力简洁,降低了构件的压力峰值,甚至使部分构件由压力杆转变成拉力杆,避免了构件的失稳,同时提高了整个结构的整体稳定性,增大了极限承载力。另外,使上层网壳杆件的内力大小分布更均匀,有利于构件统一,方便设计和施工,同时可以减小施加的预应力值,降低施工难度。
Description
技术领域
本发明涉及建筑领域应用的一种弦支穹顶结构的施工方法,具体为弦支穹顶多次预应力施工方法。
背景技术
近年来随着预应力钢结构的发展,涌现出了一大批新型结构体系,如弦支穹顶结构。弦支穹顶是将索穹顶和单层网壳结合在一起而形成的新结构,即将索穹顶的上部柔性索采用单层网壳代替而来,其增大了屋面刚度,降低施工难度。目前传统的施工方法是先安装上层网壳,在上层网壳全部安装完成后,再按照一定的顺序张拉环向索,但采用传统方法形成的弦支穹顶存在以下不足:
(1)弦支穹顶结构上层单层网壳中绝大部分杆件受压,不利于受压构件的平面外稳定和上层单层网壳的平面外局部稳定性,及整个结构的整体稳定。
(2)弦支穹顶上层单层网壳内力由下层钢索和外荷载作用被动产生,不能自我调整内力,使得上层单层网壳环向杆件大部分被动受压,不能自我调整以减小压力;使得上层单层网壳径向杆件大部分被动受压,而且压力大小不等,分布不均匀,给构件选型造成不便,造成了材料的浪费。
发明内容
为了解决上述问题,本发明的目的在于提供一种弦支穹顶结构的多次预应力施工方法,这种施工方法将弦支穹顶的施工成型和索力的施加穿插进行,结果弦支穹顶上层网壳中环向杆件的压力大大减小,有些压力甚至转变为拉力,弦支穹顶上层网壳中径向杆件的内力峰值得到了降低,内力大小分布更加均匀。而且在张拉成型过程中施加的初始索力也得到了相应减少。这种多次预应力弦支穹顶施工方法在保留了原有弦支穹顶结构的受力优点外,又具有自身独特的优点,稳定性和承载力得到提高,大大节约了材料。
为了达到上述目的,本发明采取了如下技术方案。本方法将弦支穹顶的预应力施加与上层网壳的安装间隔进行,具体施工步骤如下;
第一步:安装上层的中心压力环、上径向杆、边缘构件;
第二步:安装下层的下径向索、下环向索和撑杆;
第三步:通过张拉下环向索或者下径向索或者调整撑杆的长度,在结构中施加预应力;
第四步:安装上环向杆;
第五步:对结构施加外荷载。
所述的第一步中的具体安装步骤为:首先安装边缘构件和中心压力环,在边缘构件和中心压力环之间安装上径向杆,上径向杆之间首尾依次连接,最外圈的上径向杆的一端与其相邻的上径向杆连接,另一端与边缘构件连接;最内圈的上径向杆一端与其相邻的上径向杆连接,另一端与中心压力环连接。
所述的第二步中的具体安装步骤为:首先将撑杆的上端与上层网壳的相应节点连接,然后将下径向索的上端与上层网壳的相应节点连接,将下径向索的下端与撑杆的下端连接,最后安装环向索,环向索与撑杆的下端和下径向索的下端铰接在一起。
在安装上径向杆时,可以按照由边缘构件向压力环的顺序安装或者按照由中心压力环向边缘构件的顺序安装或者按照同时从边缘构件和中心压力环向中间的顺序进行安装。
所述的由上层中心压力环、上径向杆、上环向杆、边缘构件组成的网壳外轮廓为椭圆形或为圆形或为多边形。
由于这种多次预应力弦支穹顶的上环向杆件是在预应力施加之后,屋面材料等外荷载安装之前安装的,使得初始预应力不会在环向杆件中产生压力,减小了环向杆件的压力峰值;在施加预应力前不安装上环向杆件,使得弦支穹顶传力更加简洁,使上径向杆件的内力大小分布更均匀,有利于构件统一,方便设计和施工;另外,所需施加的预应力大小可以适当降低,降低了施工难度和成本。这种施工方法得到的多次预应力弦支穹顶结构,在承受外荷载时,上部单层网壳中部分环向杆件由受压转变成受拉,使得受压杆件的平面外稳定和上层单层网壳的平面外局部稳定性及整个结构的整体稳定都得到相应提高。由于原承受压力较大的上环向杆件中内力峰值得到了降低,使得整个结构的极限承载能力得到了提高,降低了材料消耗。总之与传统方法形成的弦支穹顶相比,本施工方法形成的多次预应力弦支穹顶总成本得到降低。
附图说明
图1上层为联方形网格的预应力弦支穹顶立体轴侧图
图2为图1所示的圆形预应力弦支穹顶上层构件布置图
图3为图1所示的椭圆形预应力弦支穹顶上层构件布置图
图4为图1所示的圆形预应力弦支穹顶下层支撑体系轴侧图
图5为图1所示的椭圆形预应力弦支穹顶下层支撑体系轴侧图
图6为图1所示的预应力弦支穹顶结构剖面图
图7为图1所示的圆形预应力弦支穹顶施加预应力前上层构件布置图
图8为图1所示的椭圆形预应力弦支穹顶施加预应力前上层构件布置图
图中:1、压力环,2、上径向杆,3、上环向杆,4、撑杆,5、下径向索,6、下环向索,7、边缘构件。
具体实施方式
下面结合图1~9详细说明本实施例。
实施例1
如图1、图2、图4、图6、图7所示,本实施例的施工成型过程为:第一步安装上层的中心压力环1、上径向杆2、边缘构件7,形成的上层网壳结构如图7所示。具体安装方法为:可以首先安装边缘构件7,然后按照由外向内的顺序,安装上径向杆2,最外圈的上径向杆2一端与边缘构件7连接,另一端与其它上径向杆2首尾相连,最内圈的上径向杆2一端与其它上径向杆2首尾相连,另一端与中心压力环1连接。也可以按照相反的顺序安装这些构件,或者按照同时由内外开始向中间进行的施工顺序。
第二步安装下层的下径向索5、下环向索6和撑杆4,即图4、图6所示的支撑体系。首先撑杆4的上端与上层网壳的相应节点连接,下端与下径向索5和下环向索6的交点连接。然后安装下径向索5,其上端与网壳的相应节点连接,下端与下环向索6和撑杆4交汇在一起。最后安装就位下环向索6,其可以与下环向索6和撑杆4的交点铰连接。
第三步张拉图4、图6所示的支撑体系中的下环向索6或者下径向索5或者调整撑杆4的长度,在结构中施加预应力。
第四步,安装上环向杆3,上环向杆3与其所在圆周位置的上径向杆2之间的相应节点连接,使上层网壳形成如图2所示的完整网壳,最终整个结构形成如图1所示的完整的多次预应力弦支穹顶结构。
第五步,对结构施加外荷载,最终完成整个结构的施工。
本实施例中的上环向杆3与上径向杆2可以铰接也可以固定连接,下环向索6与撑杆4之间为铰接,其他的连接均可以为固定连接或者铰接。
实施例2
如图3、图5、图6、图8所示,本实施例与实施例1的施工方法相同,不同之处仅在于其上层中心压力环1、上径向杆2、上环向杆3和边缘构件7组成的如图3所示的网格外形轮廓形状为椭圆形;撑杆4、下径向索5、下环向索6形成的支撑体系如图5所示为选为椭圆形。
实施例3
本实施例与实施例1的结构相同,不同之处仅在于其上层中心压力环1、上径向杆2、上环向杆3和边缘构件7组成的网格外形轮廓形状为多边形。
这种施工方法形成的多次预应力弦支穹顶结构即保留了传统弦支穹顶结构的优点,又具有自身独特的优点:减小了上层环向杆件的压力甚至使其转变成拉力,降低了其材料消耗提高了构件稳定性和网壳局部稳定性及整个结构的整体稳定性;使上层径向杆件的内力分布更加均有,有利于构件形式的统一,方便了设计和施工。由于施加预应力时上层环向杆件没有安装,使得施加的预应力值可以适当降低,降低了施工张拉成本和难度。
Claims (3)
1.弦支穹顶多次预应力施工方法,其特征在于:将弦支穹顶的预应力施加与上层网壳的安装间隔进行,具体施工步骤如下;
第一步:安装上层的中心压力环(1)、上径向杆(2)、边缘构件(7),上径向杆(2)端部固定接在一起;具体安装步骤为:首先安装边缘构件(7)和中心压力环(1),在边缘构件(7)和中心压力环(1)之间安装上径向杆(2),上径向杆(2)之间首尾依次连接,最外圈的上径向杆(2)的一端与其相邻的上径向杆(2)连接,另一端与边缘构件(7)连接;最内圈的上径向杆(2)一端与其相邻的上径向杆(2)连接,另一端与中心压力环连接;
第二步:安装下层的下径向索(5)、下环向索(6)和撑杆(4),三者铰接在一起;具体安装步骤为:首先将撑杆(4)的上端与上层网壳的相应节点连接,然后将下径向索(5)的上端与上层网壳的相应节点连接,将下径向索(5)的下端与撑杆(4)的下端连接,最后安装环向索(6),环向索(6)与撑杆(4)的下端和下径向索(5)的下端铰接在一起;
第三步:通过张拉下环向索(6)或者下径向索(5)或者调整撑杆(4)的长度,在结构中施加预应力;
第四步:安装上环向杆(3),上环向杆与上径向杆固定连接;
第五步:对结构施加外荷载。
2.根据权利要求1所述的弦支穹顶多次预应力施工方法,其特征在于:在安装上径向杆(2)时,可以按照由边缘构件(7)向压力环(1)的顺序安装或者按照由中心压力环(1)向边缘构件(7)的顺序安装或者按照同时从边缘构件(7)和中心压力环(1)向中间的顺序进行安装。
3.根据权利要求1所述的弦支穹顶多次预应力施工方法,其特征在于:所述的由上层中心压力环(1)、上径向杆(2)、上环向杆(3)、边缘构件(7)组成的网壳外轮廓为椭圆形、圆形或者多边形。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007101774692A CN101158195B (zh) | 2007-11-16 | 2007-11-16 | 弦支穹顶多次预应力施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2007101774692A CN101158195B (zh) | 2007-11-16 | 2007-11-16 | 弦支穹顶多次预应力施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101158195A CN101158195A (zh) | 2008-04-09 |
CN101158195B true CN101158195B (zh) | 2010-07-07 |
Family
ID=39306416
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2007101774692A Expired - Fee Related CN101158195B (zh) | 2007-11-16 | 2007-11-16 | 弦支穹顶多次预应力施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101158195B (zh) |
Families Citing this family (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101649661B (zh) * | 2009-09-03 | 2011-05-11 | 浙江大学 | 逐层双环葵花型索穹顶结构与施工成形方法 |
CN101956440B (zh) * | 2010-09-27 | 2012-07-04 | 薛贵宝 | 双层索-杆屋盖体系 |
CN102720295B (zh) * | 2012-04-04 | 2013-07-31 | 中国航空规划建设发展有限公司 | 一种基于索穹顶张拉和承载全过程分析的预应力确定方法 |
CN103953115B (zh) * | 2014-05-22 | 2016-06-15 | 中国建筑西南设计研究院有限公司 | 大开口葵花型索承网格结构 |
CN104234200B (zh) * | 2014-09-24 | 2016-08-24 | 东南大学 | 一种弦支穹顶索杆系逐环提升安装方法 |
CN106049920A (zh) * | 2016-06-27 | 2016-10-26 | 哈尔滨工业大学空间钢结构幕墙有限公司 | 车辐式张拉结构冷却塔 |
CN106088707A (zh) * | 2016-06-27 | 2016-11-09 | 哈尔滨工业大学空间钢结构幕墙有限公司 | 斜交网格车辐式张拉结构冷却塔 |
CN107268792A (zh) * | 2017-07-10 | 2017-10-20 | 中国建筑西南设计研究院有限公司 | 一种带环向支撑的刚性屋面索穹顶结构 |
CN109763568B (zh) * | 2019-01-17 | 2020-12-04 | 中建七局安装工程有限公司 | 一种弦支穹顶网格结构施工方法 |
CN110258802B (zh) * | 2019-05-31 | 2020-08-11 | 东南大学 | 一种基于飞燕式桁架拱的超大跨径轮辐式弦支穹顶结构 |
CN112064893A (zh) * | 2020-09-21 | 2020-12-11 | 北京城建六建设集团有限公司 | 轮辐式索桁架结构环向和径向索系连接装置及其使用方法 |
CN112878493B (zh) * | 2021-01-08 | 2022-07-26 | 中国航空规划设计研究总院有限公司 | 带斗屏子结构的球面穹顶 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001081865A (ja) * | 1999-09-13 | 2001-03-27 | Tomoe Corp | 屋根構造物およびその構築工法 |
CN1851184A (zh) * | 2006-05-12 | 2006-10-25 | 北京工业大学 | 预应力钢结构撑杆可调节节点连接装置 |
CN101029522A (zh) * | 2007-03-30 | 2007-09-05 | 北京工业大学 | 索杆弦支穹顶 |
-
2007
- 2007-11-16 CN CN2007101774692A patent/CN101158195B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001081865A (ja) * | 1999-09-13 | 2001-03-27 | Tomoe Corp | 屋根構造物およびその構築工法 |
CN1851184A (zh) * | 2006-05-12 | 2006-10-25 | 北京工业大学 | 预应力钢结构撑杆可调节节点连接装置 |
CN101029522A (zh) * | 2007-03-30 | 2007-09-05 | 北京工业大学 | 索杆弦支穹顶 |
Also Published As
Publication number | Publication date |
---|---|
CN101158195A (zh) | 2008-04-09 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101158195B (zh) | 弦支穹顶多次预应力施工方法 | |
CN100532750C (zh) | 索杆弦支穹顶 | |
CN110258802B (zh) | 一种基于飞燕式桁架拱的超大跨径轮辐式弦支穹顶结构 | |
CN112482577B (zh) | 一种大跨空间弦支轮辐式桁架结构体系及施工方法 | |
CN103061412B (zh) | 一种劲性支撑穹顶结构的施工方法 | |
CN107268791B (zh) | 一种刚性屋面组合型张力穹顶结构 | |
CN113719139B (zh) | 一种体育场馆不规则空间网架吊装施工方法 | |
CN105804247B (zh) | 一种脊杆环撑索穹顶结构 | |
CN112982669A (zh) | 一种偏心环状大悬挑预应力钢结构体系及其施工方法 | |
CN102704607B (zh) | 一种索穹顶结构与悬挑结构形成的组合结构及其组合方法 | |
CN100570094C (zh) | 局部双层张弦球面网壳 | |
CN111101632A (zh) | 大开口内环钢桁架索穹顶结构 | |
CN105926850A (zh) | 一种环形交叉索桁架结构 | |
CN103967125A (zh) | 大开口车辐式索承网格结构 | |
CN105952049A (zh) | 一种双撑杆索穹顶结构 | |
CN201901944U (zh) | 一种环形刚性索穹顶结构 | |
CN206928431U (zh) | 一种带环向支撑的刚性屋面索穹顶结构 | |
CN201172905Y (zh) | 张弦环状挑棚结构 | |
CN102330470B (zh) | 一种单层预应力框架结构 | |
CN201172903Y (zh) | 局部双层张弦球面网壳 | |
CN112922340B (zh) | 基于张拉力自调式节点的全张拉交叉索结构的施工成形方法 | |
CN103953115A (zh) | 大开口葵花型索承网格结构 | |
CN201024561Y (zh) | 索杆弦支穹顶 | |
CN113047440A (zh) | 一种带抗风索的双层辐射式张弦梁结构及其施工方法 | |
CN111119338A (zh) | 一种葵花型多撑杆索穹顶及其安装方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100707 Termination date: 20121116 |