CN100556790C - Lift facility - Google Patents

Lift facility Download PDF

Info

Publication number
CN100556790C
CN100556790C CNB200710100898XA CN200710100898A CN100556790C CN 100556790 C CN100556790 C CN 100556790C CN B200710100898X A CNB200710100898X A CN B200710100898XA CN 200710100898 A CN200710100898 A CN 200710100898A CN 100556790 C CN100556790 C CN 100556790C
Authority
CN
China
Prior art keywords
deflection sheave
sheave
deflection
winch
lift facility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB200710100898XA
Other languages
Chinese (zh)
Other versions
CN101062744A (en
Inventor
富田正道
萩谷知文
藤野笃哉
荒堀升
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Publication of CN101062744A publication Critical patent/CN101062744A/en
Application granted granted Critical
Publication of CN100556790C publication Critical patent/CN100556790C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Cage And Drive Apparatuses For Elevators (AREA)

Abstract

A kind of lift facility of machine House-less is provided, and the size of the left and right directions of its driver train is little, and the friction force between hoist cable and the driving rope sheave is big.In this lift facility, lift car (1) that is suspended in midair by hoist cable (5) in hoist trunk (6) and counterbalanced weight (2) drive by the rope sheave (4) of winch (3), winch wherein is set below hoist trunk, about below this winch, first deflection sheave (7) and second deflection sheave (8) are set respectively, and make both be in highly different positions, the left end of first deflection sheave is positioned at the left side of rope sheave right-hand member, and the right-hand member of second deflection sheave is positioned at the right side of rope sheave left end, the hoist cable that stretches out from the right-hand member of rope sheave prolongs by extending up behind first deflection sheave, arrive lift car through the 3rd deflection sheave (9), the hoist cable that stretches out from the left end of rope sheave through four deflection sheave (10) arrives counterbalanced weight by extending behind second deflection sheave up.

Description

Lift facility
Technical field
The present invention relates to a kind of lift facility, this lift facility has winch in hoist trunk, and its lift car and counterbalanced weight move along the guide rail in the hoist trunk.
Background technology
As conventional art, disclosed winch and be arranged in the hoist trunk, deflection sheave is arranged near the lift facility the winch.
For example, open the patent of invention spy of Japan of following patent documentation 1 and to disclose a kind of lift facility in the 2004-26424 communique, in this lift facility, two deflection sheavies are arranged side by side below winch, the hoist cable that down extends respectively from the both sides of winch rope sheave is wound on described two deflection sheavies, extends respectively afterwards and is wound on the deflection sheave on top.
In addition, for example disclose in No. 2004/050528 patent gazette and disclose a kind of lift facility in the world of following patent documentation 2, in this lift facility, two deflection sheavies are arranged side by side above winch, the hoist cable that up extends respectively from the both sides of the driving rope sheave of winch is wound on described two deflection sheavies, by making the relation and the variable in distance of the diameter between these deflection sheavies and the driving rope sheave, regulate the winding angle that drives the hoist cable on the rope sheave.
The patent of invention spy of patent documentation 1-Japan opens 2004-26424 communique (Fig. 1, Fig. 2 and Fig. 4 etc.)
International No. 2004/050528 patent gazette (Fig. 4 and Fig. 5 etc.) that disclose of patent documentation 2-
, in above-mentioned patent documentation 1 and patent documentation 2 disclosed lift facilities, winch is arranged on the top of hoist trunk, for the maintenance activity personnel in elevator hole, carry out the winch maintenance activity aspect, above-mentioned patent documentation is not made any consideration.And in above-mentioned patent documentation 1 and patent documentation 2 disclosed lift facilities, two deflection sheavies are arranged on the identical height, so be not easy to dwindle the size of the left and right directions of the whole driver train that comprises these deflection sheavies.And, if the axle base of deflection sheave is provided with too smallly, existing problems aspect the comfort feature of maintenance activity and safety then, therefore, in above-mentioned patent documentation 1 and patent documentation 2 disclosed lift facilities, be not easy at hoist cable and drive between the rope sheave big winding angle is set, its result is difficult to obtain to drive required enough friction force such as lift car.
Summary of the invention
The object of the present invention is to provide a kind of lift facility of machine House-less, the size of the left and right directions of its driver train is little, and the friction force between hoist cable and the driving rope sheave is big.
To achieve these goals, in lift facility of the present invention, lift car that is suspended in midair by hoist cable in hoist trunk and counterbalanced weight drive by the rope sheave of winch, wherein, below described hoist trunk central authorities, winch is set, first deflection sheave and second deflection sheave are set below this winch, the axle of described first deflection sheave is positioned at the right side of the axle of described second deflection sheave, and be in different height and positions with the axle of described second deflection sheave, the left end of described first deflection sheave is positioned at the left side of described rope sheave right-hand member, and the right-hand member of described second deflection sheave is positioned at the right side of described rope sheave left end, after extending through described first deflection sheave, extends by the described hoist cable that stretches out towards the below from the right-hand member of described rope sheave towards the top, extend the described lift car of arrival via the 3rd deflection sheave, extend towards the top after the described hoist cable that stretches out towards the below from the left end of described rope sheave extends through described second deflection sheave, extend via the 4th deflection sheave and arrive described counterbalanced weight.
According to the present invention, a kind of lift facility can be provided at an easy rate, in this lift facility, use is arranged on first deflection sheave and second deflection sheave of winch below, can at an easy rate the winding angle of hoist cable on rope sheave be set for greater than 180 degree, so can improve friction force between hoist cable and the rope sheave.And, according to the present invention, can also provide a kind of lift facility, it can dwindle the size of the left and right directions of the driver train that comprises these deflection sheavies by first deflection sheave and the second deflection sheave setting are gone up at various height.
Description of drawings
Fig. 1 is the scheme drawing of method for winding of the hoist cable of the lift facility in expression the present invention first form of implementation;
Fig. 2 is the top plan view of the hoist trunk of the lift facility in the present invention's first form of implementation;
Fig. 3 is the scheme drawing of method for winding of the hoist cable of the lift facility in expression the present invention second form of implementation;
Fig. 4 is the scheme drawing of method for winding of the hoist cable of the lift facility in expression the present invention the 3rd form of implementation.
Nomenclature
1 lift car
2 counterbalanceds weight
3 winchs
4 rope sheaves
5 hoist cables
6 hoist trunks
7 first deflection sheavies
8,8a, 8b second deflection sheave
9 the 3rd deflection sheavies
10 the 4th deflection sheavies
11 hoist trunk walls
12,13 hoist cable fixed parts
Sliding wheel on 14
The suspension pulley of 15 counterbalanceds weight
16a, 16b car guide rail
17a, 17b counterbalanced weight guide rail
18 pedestals
The specific embodiment
Below, with reference to accompanying drawing form of implementation of the present invention is described.
Fig. 1 is the figure of hoist cable 5 method for winding of the lift facility in local expression the present invention first form of implementation, and Fig. 2 is the top plan view of the hoist trunk 6 in the lift facility of this form of implementation.The lift facility of this form of implementation is constituted as, and lift car 1 is along car guide rail 16a, 16b lifting, and counterbalanced weight 2 is along counterbalanced weight guide rail 17a, 17b lifting.And lift car 1 is suspended in midair by hoist cable 5 with counterbalanced weight 2, and is driven by the rope sheave 4 of winch 3.
On the position of the below that winch 3 is arranged on hoist trunk 6 central authorities near the elevator hole, it is in the space in the moving area of lift car 1 and the gap between the hoist trunk wall 11.First deflection sheave 7 and second deflection sheave 8 are set below this winch 3, the axle of first deflection sheave 7 is positioned at the right side of the axle of second deflection sheave 8, and be in different height and positions with the axle of second deflection sheave, the left end of first deflection sheave 7 is positioned at the left side of rope sheave 4 right-hand members, and the right-hand member of second deflection sheave 8 is positioned at the right side of rope sheave 4 left ends.And the left end of first deflection sheave 7 is positioned at the left side of second deflection sheave, 8 right-hand members.At this, right side of the present invention is meant as shown in Figure 1, during from the top view of winch 3, is the position that benchmark is positioned at the right side with rope sheave 4.
And, the hoist cable 5 that stretches out towards the below from the right-hand member of rope sheave 4 extends through first deflection sheave, 7 backs and extends towards the top, via fixing and be arranged on two the 3rd deflection sheavies 9 at hoist trunk 6 tops and extend through two of being arranged on lift car 1 bottom and go up slidings wheel 14, and arrive the hoist cable fixed part 12 at hoist trunk 6 tops.On the other hand, the hoist cable 5 that stretches out towards the below from the left end of rope sheave 4 extends through second deflection sheave, 8 backs and extends towards the top, via fixing and be arranged on two the 4th deflection sheavies 10 at hoist trunk 6 tops after, extend through the suspension pulley 15 that is installed in counterbalanced weight 2 tops, arrive afterwards on the hoist cable fixed part 13 at hoist trunk 6 tops.And as shown in Figure 2, the vertical projection of the 3rd deflection sheave 9 is configured to vertical substantially with the vertical projection of the vertical projection of the 4th deflection sheave 10 and rope sheave 4.
And first deflection sheave 7 is arranged on the different position of height with second deflection sheave 8 on the pedestal 18 of one, and the axle of two pulleys is different on upper-lower position.Described first deflection sheave 7 and described second deflection sheave 8 are configured to, and the bolt hole of the axle of two pulleys and the fixed part of bearing has a plurality of on above-below direction, thus, can regulate (not shown) to the position of two pulleys.
And described winch 3 is a kind of slim winchs.At this, so-called slim winch is meant to have the winch of the radial dimension of outling of truss greater than these characteristics of axial width size.
According to this form of implementation, because first deflection sheave 7 is arranged on the different position of height with second deflection sheave 8, so, be arranged side by side in the situation of equal height with second deflection sheave 8 with first deflection sheave 7 and compare, can make the S. A. of the S. A. of first deflection sheave 7 and second deflection sheave 8 approaching mutually in the horizontal direction at an easy rate.Specifically, when the equal diameters of the diameter of rope sheave 4 and first deflection sheave 7 and second deflection sheave 8, if these deflection sheavies are arranged side by side on identical height, then the horizontal throw d between the axle of each deflection sheave will be greater than the diameter D of rope sheave 4, but also can be as this form of implementation, horizontal throw d is arranged to diameter D less than rope sheave 4.Therefore, can dwindle the side-to-side dimensions of the whole driver train of forming by winch 3 and two deflection sheavies thereunder.
And, even first deflection sheave 7 and second deflection sheave 8 are approaching in the horizontal direction, but because the axle base of these pulleys itself can keep bigger value, so can guarantee the comfort feature and the safety of maintenance activity.Its result can set the winding angle of the hoist cable on the rope sheave 45 greater than 180 degree easily, and then improves the friction force between rope sheave 4 and the hoist cable 5, so can increase driving efficiency.Therefore, have and under certain loading condiction, to constitute the effect of more small-sized driver train.And,, have the effect that can constitute more small-sized hoist trunk as its result.
And,,,, have and can improve the effect that acts on the friction force on the rope sheave 4 so compare with the structure that deflection sheave is not arranged on winch 3 belows because the deadweight of hoist cable 5 acts on the rope sheave 4 according to this form of implementation.
And then according to this form of implementation, the situation that is arranged on hoist trunk 6 tops with winch 3 is identical, owing to downward load is arranged from 4 effects of 5 pairs of rope sheaves of hoist cable, so,, then have the effect that can directly use this winch 3 if there is the winch 3 that is designed to be arranged on hoist trunk 6 tops.
And then, according to this form of implementation, because the slim winch of described winch 3 employings in the moving area that is arranged on lift car 1 and the space in the gap between the hoist trunk wall 11, thus also have whole hoist trunk can be provided with the effect of miniaturization more.
Followingly second form of implementation of the present invention is described with reference to Fig. 3.The integral structure of lift facility and first form of implementation are roughly the same.Be that with the difference of first form of implementation second deflection sheave 8 is that pulley 8a and 8b constitute by a plurality of pulleys, pulley 8a and 8b are contiguous side by side to be provided with, and the height of the axle of these pulleys is roughly the same.
According to this form of implementation, identical with described form of implementation, have when improving driving efficiency, dwindle the effect of the lateral dimension on the direction of hoist trunk wall 11 of driver train.Especially, because first deflection sheave 7 is different with the high and low position of second deflection sheave 8, and two second deflection sheave 8a, 8b are arranged side by side in the horizontal direction, the winding angle of hoist cable 5 on rope sheave 4 can be maintained bigger angle so have, and this new effect of rising starting point position that simultaneously can free adjustment hoist cable 5.
At last, with reference to Fig. 4 the 3rd form of implementation of the present invention is described.The integral structure of lift facility and second form of implementation are roughly the same.Be that with the difference of second form of implementation among the second deflection sheave 8a, the 8b, the axle of another deflection sheave of axial ratio 8a of the deflection sheave 8b of close hoist trunk wall 11 is high, thereby is arranged side by side on the different position of height.
According to this form of implementation, identical with described each form of implementation, having can be when improving driving efficiency, dwindles the effect of the lateral dimension on the direction of hoist trunk wall 11 of driver train.
Especially, two second deflection sheave 8a, 8b are set on the different position of height, so, compare with second form of implementation, have and can shorten this new effect of hoist cable 5 total lengths.

Claims (9)

1. lift facility is driven by the lift car of hoist cable suspention and the counterbalanced weight rope sheave by winch in hoist trunk, and this lift facility is characterised in that,
Below described hoist trunk central authorities, winch is set, first deflection sheave and second deflection sheave are set below this winch, the axle of described first deflection sheave is positioned at the right side of the axle of described second deflection sheave, and be in different height and positions with the axle of described second deflection sheave, the left end of described first deflection sheave is positioned at the left side of described rope sheave right-hand member, and the right-hand member of described second deflection sheave is positioned at the right side of described rope sheave left end, after extending through described first deflection sheave, extends by the described hoist cable that stretches out towards the below from the right-hand member of described rope sheave towards the top, extend the described lift car of arrival via the 3rd deflection sheave, extend towards the top after the described hoist cable that stretches out towards the below from the left end of described rope sheave extends through described second deflection sheave, extend via the 4th deflection sheave and arrive described counterbalanced weight.
2. lift facility as claimed in claim 1 is characterized in that,
Described winch is positioned at the space in the gap of the moving area of described lift car and hoist trunk between the walls.
3. lift facility as claimed in claim 1 or 2 is characterized in that,
Described winch is slim winch.
4. lift facility as claimed in claim 1 or 2 is characterized in that,
The left end of described first deflection sheave is positioned at the left side of the described second deflection sheave right-hand member.
5. lift facility as claimed in claim 1 or 2 is characterized in that,
Described first deflection sheave and/or described second deflection sheave are configured to the position of above-below direction and can regulate.
6. lift facility as claimed in claim 1 or 2 is characterized in that,
Described winch, described first deflection sheave and described second deflection sheave are arranged on the pedestal of one.
7. lift facility as claimed in claim 1 or 2 is characterized in that,
Have a plurality of described first deflection sheavies and/or described second deflection sheave.
8. lift facility as claimed in claim 7 is characterized in that,
The axle of the described a plurality of pulleys in described first deflection sheave or second deflection sheave is positioned at essentially identical height and position.
9. lift facility as claimed in claim 7 is characterized in that,
The axle of the pulley of close described hoist trunk wall is positioned at than on the high position of the axle of other pulleys in described a plurality of pulleys in described first deflection sheave or second deflection sheave.
CNB200710100898XA 2006-04-25 2007-04-24 Lift facility Expired - Fee Related CN100556790C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2006120030 2006-04-25
JP2006120030A JP4802844B2 (en) 2006-04-25 2006-04-25 Elevator equipment

Publications (2)

Publication Number Publication Date
CN101062744A CN101062744A (en) 2007-10-31
CN100556790C true CN100556790C (en) 2009-11-04

Family

ID=38761830

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200710100898XA Expired - Fee Related CN100556790C (en) 2006-04-25 2007-04-24 Lift facility

Country Status (3)

Country Link
JP (1) JP4802844B2 (en)
CN (1) CN100556790C (en)
HK (1) HK1110571A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5303266B2 (en) * 2008-12-26 2013-10-02 株式会社日立製作所 Elevator hoisting machine
WO2015025396A1 (en) * 2013-08-22 2015-02-26 三菱電機株式会社 Elevator device
CN109704178A (en) * 2018-12-13 2019-05-03 中国矿业大学 A kind of single container friction winding system between adjacent hoistway

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6061262U (en) * 1983-10-03 1985-04-27 三菱電機株式会社 elevator equipment
JP2000095461A (en) * 1998-09-24 2000-04-04 Hitachi Ltd Traction elevator
JP4135262B2 (en) * 1999-07-15 2008-08-20 三菱電機株式会社 Self-propelled elevator equipment
JP4849712B2 (en) * 2000-11-08 2012-01-11 東芝エレベータ株式会社 elevator
JP4825368B2 (en) * 2001-07-10 2011-11-30 東芝エレベータ株式会社 Elevator equipment
JP2004026424A (en) * 2002-06-26 2004-01-29 Toshiba Elevator Co Ltd Elevator facility
EP1724229A4 (en) * 2004-03-01 2011-07-20 Mitsubishi Electric Corp Elevator apparatus
JP2006001698A (en) * 2004-06-17 2006-01-05 Meidensha Corp Elevator apparatus

Also Published As

Publication number Publication date
JP4802844B2 (en) 2011-10-26
CN101062744A (en) 2007-10-31
HK1110571A1 (en) 2008-07-18
JP2007290815A (en) 2007-11-08

Similar Documents

Publication Publication Date Title
KR101884988B1 (en) rope-less elevator
TWI295272B (en) Elevator installation
JP5095401B2 (en) Elevator installation method and elevator
US8448323B2 (en) Method for modernizing an elevator
US20200354195A1 (en) Elevator system roping arrangement
JP5889412B2 (en) Elevator suspension structure and guide shoe structure
KR101335800B1 (en) Elevator device
CN100556790C (en) Lift facility
KR100870389B1 (en) Elevator device
CN101356110B (en) Elevator apparatus
KR20180129843A (en) Suspension and lift motor systems for multiple elevator caps and balancers moving independently of one another in various sections of a hoistway
EP1828044B1 (en) Elevator roping arrangement
CN1789103B (en) Elevator device
WO2018225140A1 (en) Elevator
CN1833981B (en) Elevator system
EP1641698B1 (en) A method for modernising an elevator
JPWO2005080250A1 (en) Machine room-less elevator
KR20080055705A (en) Lift system
CN106061884A (en) Low-construction trolley for wire rope hoist
CN101177223A (en) Elevator equipment
JP4750104B2 (en) Elevator equipment
CN100534887C (en) Lift installation
EP3553013A2 (en) Lifting system
CN101381050A (en) Elevator
CN101152942A (en) Elevator equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
REG Reference to a national code

Ref country code: HK

Ref legal event code: DE

Ref document number: 1110571

Country of ref document: HK

C14 Grant of patent or utility model
GR01 Patent grant
REG Reference to a national code

Ref country code: HK

Ref legal event code: GR

Ref document number: 1110571

Country of ref document: HK

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091104