CH683197A5 - Basket for concrete pile mfr. - has permeable stocking around rigid basket members to prevent dispersion of sand and cement into surrounding ground and water - Google Patents
Basket for concrete pile mfr. - has permeable stocking around rigid basket members to prevent dispersion of sand and cement into surrounding ground and water Download PDFInfo
- Publication number
- CH683197A5 CH683197A5 CH402790A CH402790A CH683197A5 CH 683197 A5 CH683197 A5 CH 683197A5 CH 402790 A CH402790 A CH 402790A CH 402790 A CH402790 A CH 402790A CH 683197 A5 CH683197 A5 CH 683197A5
- Authority
- CH
- Switzerland
- Prior art keywords
- stocking
- elongated support
- water
- basket according
- support basket
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
1 1
CH 683 197 A5 CH 683 197 A5
2 2nd
Beschreibung description
Die Erfindung betrifft einen länglichen Stützkorb, zur Herstellung eines Betonpfahles. Die Erfindung betrifft weiterhin ein Verfahren zur Herstellung dieses Stützkorbes. The invention relates to an elongated support basket for the production of a concrete pile. The invention further relates to a method for producing this support basket.
Will man an einer Baustelle einen Betonpfahl mit Ortsbeton in einer Vertiefung des Erdreiches herstellen, so kann das auf verschiedene Weise erfolgen. Es kann eine Bohrung abgeteuft werden (mit einem Drehbohrer oder Greifer); es kann aber auch ein Hohlpfahl als Verdrängungspfahl gesetzt werden (Verdrängen des Erdreiches). In beiden Fällen wird dann die im Erdreich hergestellte Vertiefung mit Ortsbeton gefüllt. Ist der herzustellende Betonpfahl ein tragendes Element, so wird er armiert, und hierfür wird ein länglicher Armierungskorb in die im Erdreich hergestellte Vertiefung eingesetzt. If you want to produce a concrete pile with in-situ concrete in a deepening of the ground at a construction site, you can do this in different ways. A hole can be sunk (with a rotary drill or gripper); however, a hollow pile can also be placed as a displacement pile (displacing the soil). In both cases, the recess made in the ground is then filled with in-situ concrete. If the concrete pile to be manufactured is a load-bearing element, it is reinforced and an elongated reinforcement basket is inserted into the recess made in the ground.
In die im Erdreich hergestellte Vertiefung wird dann ein Schüttrohr eingebracht und dünnflüssiger Fliessbeton über dieses Schüttrohr in die Vertiefung gegeben, und vom Boden der Vertiefung aus wird nach oben betoniert. Hierbei wird das Schüttrohr und das Bohrrohr (beim Herstellen der Vertiefung mittels Drehbohrer oder Greifer) bzw. der Hohlpfahl (beim Herstellen der Vertiefung durch Verdrängen) sukzessive nach oben gezogen. Beim Herstellen des Betonpfahles auf diese vorerwähnte Weise lässt es sich nicht vermeiden, dass Zement und Füllmaterial (Sand) ins umgebende Gewässer (fliessend oder stehend) ausgeschwemmt werden. Dieses sollte aus Gründen der Umweltverschmutzung vermieden werden, und zusätzlich würde bei dieser Verhinderung der Ausschwemmung auch wirtschaftlicher mit dem Zement umgegangen. Die der Erfindung zugrundeliegende Aufgabe besteht daher darin, dieses erwähnte Ausschwemmen des Zementes und des Füllmaterials zu vermeiden. Hierzu wird der eingangs erwähnte Armierungskorb besonders ausgebildet, wobei der Armierungskorb aber auch so gestaltet sein kann, dass er keine Armierungsfunktion im herzustellenden Betonpfahl übernehmen muss und deshalb mit dem übergeordneten Begriff «Stützkorb» bezeichnet wird. A pouring pipe is then introduced into the recess made in the ground and thin, flowing concrete is poured into the recess via this pouring pipe, and concreting is carried out from the bottom of the recess. Here, the pouring pipe and the drill pipe (when making the recess using a rotary drill or gripper) or the hollow pile (when producing the recess by displacing) are successively pulled upwards. When manufacturing the concrete pile in this way, it cannot be avoided that cement and filler material (sand) are washed out into the surrounding water (flowing or standing). This should be avoided for reasons of environmental pollution and, in addition, this prevention of flooding would also make the cement more economical to use. The object underlying the invention is therefore to avoid the above-mentioned flushing out of the cement and the filler material. For this purpose, the reinforcement cage mentioned at the outset is specially designed, but the reinforcement cage can also be designed in such a way that it does not have to perform a reinforcement function in the concrete pile to be produced and is therefore referred to by the superordinate term “support cage”.
Die erfindungsgemässe Ausbildung des länglichen Stützkorbs, der also auch als Armierungskorb dienen kann, ergibt sich aus dem kennzeichnenden Teil des Patentanspruchs 1. The inventive design of the elongated support cage, which can therefore also serve as a reinforcement cage, results from the characterizing part of patent claim 1.
Es wird also davon ausgegangen, dass der sogenannte Stützkorb aus starren Bauteilen aufgebaut ist, da er ja sonst keine Funktion als Stütze oder gar als Armierung ausüben kann. It is therefore assumed that the so-called support cage is made up of rigid components, since otherwise it cannot have any function as a support or even as a reinforcement.
In der Zeichnung ist ein Ausführungsbeispiel des Erfindungsgegenstandes dargestellt, wobei der erfindungsgemässe Stützkorb als Armierungskorb ausgebildet ist, und wobei der herzustellende Betonpfahl mittels eines Bohrrohres (mit Drehbohrer oder Greifer) und nicht durch Verdrängen mittels eines Hohlpfahles gebildet werden soll. Es zeigen: In the drawing, an embodiment of the subject of the invention is shown, wherein the support cage according to the invention is designed as a reinforcement cage, and wherein the concrete pile to be produced is to be formed by means of a drill pipe (with a rotary drill or gripper) and not by displacement by means of a hollow pile. Show it:
Fig. 1 einen Vertikalschnitt durch den unteren Teil einer im Erdreich hergestellten Bohrung, mit eingesetztem, als Armierungskorb ausgebildetem Stützkorb, und Fig. 1 shows a vertical section through the lower part of a hole made in the ground, with an inserted, designed as a reinforcing cage support basket, and
Fig. 2 einen Querschnitt nach der Linie II-II in Fig. 1. FIG. 2 shows a cross section along the line II-II in FIG. 1.
Der erfindungsgemässe längliche Stützkorb weist starre Bauteile 1-5 auf, die radial und unten axial von einem flexiblen Strumpf 6 umgeben sind. Die starren Bauteile 1-4 stellen hierbei Armierungseisen dar, und die starren Bauteile 5 dienen als Distanzhalter für den Strumpf 6 und sind als zueinander parallel verlaufende Kunststoffrohre ausgebildet. Durch diese als Distanzhalter dienenden Kunststoffrohre 5 wird der Beinteil 7 des Strumpfes 6 im radialen Abstand zu den Armierungseisen 2 und 3 gehalten, damit dann in später erläuterter Weise beim Betonieren diese Armierungseisen 2,3 und natürlich auch die Armierungseisen 1 im Beton eingebettet liegen. Der Strumpf 6 hat neben seinem Beinteil 7 noch eine Fussstirnfläche 8. Die als Distanzhalter für den Strumpf 6 dienenden Kunststoffrohre 5 können an den Armierungseisen 3 angebunden sein, wobei die aus Baustahl bestehenden Armierungseisen 1-4 miteinander verschweisst sein können. Aus den Fig. 1 und 2 ist ersichtlich, dass sich der Strumpf 6 mit seinem Beinteil 7 radial ausserhalb der Kunststoffrohre 5 befindet. The elongated support cage according to the invention has rigid components 1-5, which are surrounded radially and axially below by a flexible stocking 6. The rigid components 1-4 represent reinforcing irons, and the rigid components 5 serve as spacers for the stocking 6 and are designed as plastic tubes running parallel to one another. By means of these plastic tubes 5 serving as spacers, the leg part 7 of the stocking 6 is held at a radial distance from the reinforcing bars 2 and 3, so that these reinforcing bars 2, 3 and, of course, also the reinforcing bars 1 are embedded in the concrete when concreting later. In addition to its leg part 7, the stocking 6 also has a foot end face 8. The plastic tubes 5 serving as spacers for the stocking 6 can be connected to the reinforcing bars 3, wherein the reinforcing bars 1-4 made of structural steel can be welded to one another. 1 and 2 that the stocking 6 with its leg part 7 is located radially outside the plastic tubes 5.
Der Strumpf 6 besteht aus einem Kunststoffgewebe oder ist im wesentlichen aus einem Kunststoffgewebe aufgebaut, könnte also auch noch Anteile aus anderen Materialien enthalten. In der Praxis hat sich ein Kunststoffgewebe hierfür bewährt, das aus Polyethylen und Polypropylen besteht. Es ist vorteilhaft, wenn ein «Drosselstrumpf» verwendet wird, so dass dieser Strumpf wasserdurchlässig sein soll, so dass also Wasser gedrosselt hindurchtreten kann. In der Praxis wurde ein Kunststoffgewebe für den Strumpf verwendet, das eine Wasserdurchlässigkeit im Bereich von 30-50 Liter/m2 • s aufweist. Der Strumpf 6 kann als nahtloser zylindrischer Schlauch vorliegen, an dem eine die Fussstirnfläche 8 bildende Rondelle angenäht werden kann. Der so gebildete Strumpf kann dann vom unteren Ende der starren Bauteile 1-5 her über diese nach oben gezogen werden, wie es aus Fig. 1 ersichtlich ist. Bei einer anderen Ausführungsform könnte der Beinteil 7 des Strumpfes 6 aber auch aus einem bahnförmigen Material gebildet werden, das an zwei einander gegenüberliegenden Enden zum Bilden eines Schlauches miteinander verbunden ist, worauf dann an diesen Schlauch wiederum die die Fussstirnfläche 8 bildende Rondelle befestigt wird. The stocking 6 consists of a plastic fabric or is essentially made up of a plastic fabric, and could therefore also contain portions of other materials. In practice, a plastic fabric made of polyethylene and polypropylene has proven itself. It is advantageous if a "throttling stocking" is used so that this stocking should be permeable to water, so that water can pass through in a throttled manner. In practice, a plastic fabric was used for the stocking, which has a water permeability in the range of 30-50 liters / m2 • s. The stocking 6 can be in the form of a seamless cylindrical tube to which a rondelle forming the foot end face 8 can be sewn on. The stocking thus formed can then be pulled upwards from the lower end of the rigid components 1-5, as can be seen from FIG. 1. In another embodiment, the leg part 7 of the stocking 6 could also be formed from a web-shaped material which is connected to one another at two opposite ends to form a tube, whereupon the roundel forming the foot end face 8 is then attached to this tube.
Der Umfang des Beinteils 7 vom Strumpf 6 ist um einiges grösser als der Umfang der starren Stützkorbteile 1-5, wobei diese Bedeutung später noch erläutert wird. The circumference of the leg part 7 from the stocking 6 is somewhat larger than the circumference of the rigid support basket parts 1-5, this meaning being explained later.
Im folgenden soll die Herstellung eines Betonpfahles erläutert werden, wobei das Abteufen der Bohrung mittels eines nicht dargestellten Greifers innerhalb eines Bohrrohres 9 erfolgt. Während der Abteufung der Bohrung ist das herzustellende Bohrloch 10 ständig geflutet. Durch das Abteufen mittels Greifer entsteht ein radiales Übermass 11, das also radial ausserhalb des etwa parallel zum Greifer abgetieften Bohrrohres 9 liegt. Ausserhalb des Bohrloches 10 ist der Armierungskorb fertiggestellt wor5 The manufacture of a concrete pile will be explained below, the drilling of the borehole being carried out by means of a gripper (not shown) within a drill pipe 9. During the drilling of the borehole, the borehole 10 to be produced is continuously flooded. The sinking by means of a gripper creates a radial oversize 11, which is therefore radially outside of the drill pipe 9, which is lowered approximately parallel to the gripper. The reinforcement cage has been completed outside the borehole 10
10 10th
15 15
20 20th
25 25th
30 30th
35 35
40 40
45 45
50 50
55 55
60 60
65 65
2 2nd
3 3rd
CH 683 197 A5 CH 683 197 A5
4 4th
den, der aus den starren Bauteilen 1-5 und dem darübergezogenen flexiblen Strumpf 6 besteht. Nunmehr wird dieser Armierungskorb in das geflutete Bohrloch 10 abgesenkt, wobei die erwähnte Wasserdurchlässigkeit des Strumpfes 6 zweckmässig ist. In der Praxis kann sich dieses Absenken des Armierungskorbes z.B. über eine Dauer von 10 Minuten erstrecken, wobei während dieser Zeit ein Austausch des im Bohrloch 10 befindlichen Wassers von aussen durch den Strumpf nach innen erfolgt. Wäre der Strumpf wasserundurchlässig, so müsste während des Einsetzens des Armierungskorbes das Wasser aus dem Bohrloch gepumpt und wieder ins Innere des Stumpfes hineingepumpt werden. Während dieses Einsetzens des Armierungskorbes in das Bohrloch 10 befindet sich das Bohrrohr 9 noch im Bohrloch. Ist der Armierungskorb ganz im Bohrloch 10 innerhalb des Bohrrohres 9 eingesetzt worden, wird ein nicht dargestelltes Schüttrohr durch den Armierungskorb hindurch eingeführt, das sich ebenfalls mit Wasser füllt. Mittels eines im Schüttrohr geführten Kolbens wird dann das Wasser aus dem Schüttrohr ausgetrieben, wobei diesem Kolben der dünnflüssige Fliessbeton nachfolgt und vom Boden des Bohrloches 10 aus nach oben betoniert wird, wobei das erwähnte Schüttrohr und das Bohrrohr 9 sukzessive nach oben gezogen werden. Beim Nachobenziehen des Bohrrohres 9 schmiegt sich der flexible Strumpf 6 an das Erdreich 12 an, wie in Fig. 1 unterhalb des Bohrrohres 9 ersichtlich ist. Aus diesem Grund hat der Beinteil 7 des Strumpfes einen grösseren Umfang als das Bohrrohr 9. Beim Betonieren kann nunmehr weder Zement noch Füllmaterial (Sand) ausgeschwemmt werden, da der Zement und das Füllmaterial vom wasserdurchlässigen Strumpf zurückgehalten werden. Allmählich wird das Gewebe des Strumpfes durch den zurückgehaltenen Zement und das zurückgehaltene Füllmaterial ganz verstopft und wird daher auch wasserundurchlässig. Wenn somit der Betonpfahl hergestellt worden ist, ist auch der Strumpf nahezu wasserundurchlässig geworden, so dass auch später der fertige Betonpfahl vom fliessenden oder stehenden Gewässer nahezu unbeeinflusst bleibt. Ist der Strumpf von Anfang an wasserundurchlässig, bleibt der fertige Betonpfahl vom fliessenden oder stehenden Gewässer unbeeinflusst. that which consists of the rigid components 1-5 and the flexible stocking 6 pulled over them. This reinforcing cage is now lowered into the flooded borehole 10, the water permeability of the stocking 6 mentioned being expedient. In practice, this lowering of the reinforcement cage can e.g. extend over a period of 10 minutes, during which time the water in the borehole 10 is exchanged from the outside through the stocking to the inside. If the stocking were impermeable to water, the water would have to be pumped out of the borehole during the insertion of the reinforcement cage and pumped back into the interior of the stump. During this insertion of the reinforcement cage into the borehole 10, the drill pipe 9 is still in the borehole. If the reinforcement cage has been inserted completely into the borehole 10 within the drill pipe 9, a pouring pipe, not shown, is inserted through the reinforcement cage and also fills with water. The water is then expelled from the pouring tube by means of a piston guided in the pouring tube, this fluid being followed by the low-viscosity flow concrete and concreted upwards from the bottom of the borehole 10, the aforementioned pouring tube and the drilling tube 9 being successively pulled upwards. When the drill pipe 9 is pulled upwards, the flexible stocking 6 nestles against the soil 12, as can be seen in FIG. 1 below the drill pipe 9. For this reason, the leg part 7 of the stocking has a larger circumference than the drill pipe 9. When concreting, neither cement nor filler material (sand) can now be washed out, since the cement and filler material are retained by the water-permeable stocking. Gradually, the tissue of the stocking becomes completely blocked by the retained cement and the retained filling material and therefore also becomes impermeable to water. When the concrete pile has thus been produced, the stocking has also become almost impermeable to water, so that the finished concrete pile remains virtually unaffected by the flowing or standing water later on. If the stocking is impermeable to water right from the start, the finished concrete pile remains unaffected by the flowing or standing water.
Da der Strumpf durch die Distanzhalter 5 im radialen Abstand ausserhalb der Armierungseisen 2 und 3 gehalten wird, sind diese beim Herstellen des Betonpfahles vom Beton umgeben worden und liegen eingebettet innerhalb des Betonpfahles. Since the stocking is held at a radial distance outside of the reinforcing bars 2 and 3 by the spacers 5, these have been surrounded by the concrete during the manufacture of the concrete pile and are embedded within the concrete pile.
Soll ein Betonpfahl ohne Armierung hergestellt werden, werden die Armierungseisen 1-4 nicht benötigt, so dass lediglich ein Stützkorb zum Stützen des Drosselstrumpfes 6 benötigt wird. Ein solcher Stützkorb muss also selbsttragend sein, und hat wiederum starre Bauteile, z.B. die Kunststoffrohre 5, die durch nicht dargestellte Mittel auf der aus Fig. 2 ersichtlichen Kreisbahn gehalten werden, um eine Stütze für den übergestülpten flexiblen Strumpf 6 zu bilden. If a concrete pile is to be produced without reinforcement, the reinforcing irons 1-4 are not required, so that only a support basket is required to support the throttle stocking 6. Such a support cage must therefore be self-supporting and in turn has rigid components, e.g. the plastic tubes 5, which are held by means not shown on the circular path shown in FIG. 2 to form a support for the flexible stocking 6 put on.
Claims (14)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CH402790A CH683197A5 (en) | 1990-12-19 | 1990-12-19 | Basket for concrete pile mfr. - has permeable stocking around rigid basket members to prevent dispersion of sand and cement into surrounding ground and water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CH402790A CH683197A5 (en) | 1990-12-19 | 1990-12-19 | Basket for concrete pile mfr. - has permeable stocking around rigid basket members to prevent dispersion of sand and cement into surrounding ground and water |
Publications (1)
Publication Number | Publication Date |
---|---|
CH683197A5 true CH683197A5 (en) | 1994-01-31 |
Family
ID=4268448
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CH402790A CH683197A5 (en) | 1990-12-19 | 1990-12-19 | Basket for concrete pile mfr. - has permeable stocking around rigid basket members to prevent dispersion of sand and cement into surrounding ground and water |
Country Status (1)
Country | Link |
---|---|
CH (1) | CH683197A5 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0796948A1 (en) * | 1994-12-05 | 1997-09-24 | Shogen Okawa | Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method |
US20150275455A1 (en) * | 2012-11-08 | 2015-10-01 | Asahi Engineering Co., Ltd. | Construction method for foundation pile |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1550295A (en) * | 1967-10-27 | 1968-12-20 |
-
1990
- 1990-12-19 CH CH402790A patent/CH683197A5/en not_active IP Right Cessation
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR1550295A (en) * | 1967-10-27 | 1968-12-20 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0796948A1 (en) * | 1994-12-05 | 1997-09-24 | Shogen Okawa | Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method |
EP0796948A4 (en) * | 1994-12-05 | 1999-05-06 | Shogen Okawa | Pile head treating tool for cast-in-place pile, pile head treating method, and cast-in-place piling method |
US20150275455A1 (en) * | 2012-11-08 | 2015-10-01 | Asahi Engineering Co., Ltd. | Construction method for foundation pile |
US10767333B2 (en) * | 2012-11-08 | 2020-09-08 | Asahi Engineering Co., Ltd. | Construction method for foundation pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE3416568A1 (en) | MEMBRANE BLOCK AGAINST UNDERGROUND FLUID FLOWS AND SECTION THEREFOR | |
CH600077A5 (en) | Seal for gaps in concrete structures | |
EP0788572B1 (en) | Building underpinning process | |
DE3726191C2 (en) | ||
CH683197A5 (en) | Basket for concrete pile mfr. - has permeable stocking around rigid basket members to prevent dispersion of sand and cement into surrounding ground and water | |
DE102012023185A1 (en) | Method for producing a pile | |
EP0109397B1 (en) | Hollow foundation element and manufacturing method thereof | |
DE2838363A1 (en) | LIQUID AND PERMEABLE WALL AND METHOD OF MANUFACTURING THE SAME | |
DE2711899A1 (en) | DEVICE FOR SOIL INJECTION IN HIGH PRESSURE SOIL AND PILE FOUNDATIONS | |
DE3410830C2 (en) | ||
WO2021139978A1 (en) | Method for creating a foundation element in the ground and foundation element | |
DE3543059C2 (en) | ||
DE3521434A1 (en) | Injection method and apparatus for soil stabilisation | |
DE10025966A1 (en) | Ground reinforcement by sleeved body insertion encloses insert body in bottom-closed sleeve before or during ground insertion ready for backfilling sleeve at target depth downhole. | |
DE102005019168A1 (en) | Use of a drill injection anchor for producing ground drainage by introducing a pumpable filter material through the drill crown into the hole to fill the hole | |
DE102021116487B3 (en) | Geotextile covered liquid soil columns | |
DE3106662C2 (en) | ||
DE19528330C2 (en) | Construction of an excavation pit with subsequent groundwater flow | |
DE3727752C2 (en) | ||
DE102009033834B3 (en) | Device for lifting base plate corresponding to foundation element, comprises empty annular space, which is formed around lifting element, where annular space is limited by exterior seal made of plastic or rubber | |
DE947540C (en) | Process for the production and lowering of any shaped caissons | |
DE3035060C2 (en) | Process for producing a temporarily watertight construction pit enclosure and device for carrying out the process | |
EP0346941B1 (en) | Method for producing construction elements in the soil, such as piles, anchors or the like, and apparatus for applying this method | |
DE3132435A1 (en) | Pipe, in particular fountain pipe, made of plastic and process for the production thereof | |
DE102009039570B4 (en) | Reinforcement for a foundation element and method for creating the foundation element and foundation element |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PL | Patent ceased |