CH677386A5 - Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical - Google Patents

Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical Download PDF

Info

Publication number
CH677386A5
CH677386A5 CH152788A CH152788A CH677386A5 CH 677386 A5 CH677386 A5 CH 677386A5 CH 152788 A CH152788 A CH 152788A CH 152788 A CH152788 A CH 152788A CH 677386 A5 CH677386 A5 CH 677386A5
Authority
CH
Switzerland
Prior art keywords
centrifugal
concrete
reinforcing bars
speed
acceleration
Prior art date
Application number
CH152788A
Other languages
German (de)
Inventor
Georges Baettig
Original Assignee
Sacac Schleuderbetonwerk Ag
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sacac Schleuderbetonwerk Ag filed Critical Sacac Schleuderbetonwerk Ag
Priority to CH152788A priority Critical patent/CH677386A5/en
Publication of CH677386A5 publication Critical patent/CH677386A5/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/20Producing shaped prefabricated articles from the material by centrifugal or rotational casting
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/12Structures made of specified materials of concrete or other stone-like material, with or without internal or external reinforcements, e.g. with metal coverings, with permanent form elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/16Prestressed structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Materials Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The centrifugally-cast concrete support has a cross-section with periphery formed by curved and straight sections (5,3), or alternatively oval or elliptical. It can contain reinforcing bars, prestressed if desired, and at constant pitch, parallel to the outside surface, while the bars themselves can be of different cross-sections. ADVANTAGE - Increased load capacity in one direction.

Description

       

  
 



  Die vorliegende Erfindung betrifft eine Schleuderbetonstütze sowie ein Verfahren zum Herstellen einer solchen Schleuderbetonstütze. 



  Derartige Stützen aus Schleuderbeton sind schon im vorigen Jahrhundert bekanntgeworden. Sie wurden hauptsächlich in kreisrunden Querschnitten, in punktsymmetrischer Ausführung als reguläre Vielecke, beispielsweise quadratisch oder mit achteckigem Querschnitt, ausgeführt, wobei sich, bedingt durch den Schleuderprozess, im Kern eine kreisrunde \ffnung ergab. Derartige Schleuderbetonstützen wurden entweder zylindrisch oder konisch geformt, wie dies beispielsweise im Art. "Schleuderbeton" des SIA, Sonderdruck aus Heft 7/1981 von Erich Bacsa, Zürich, eingehend erläutert ist. 



  Die vorliegende Erfindung trägt dem Umstand Rechnung, dass die Belastung derartiger Schleuderbetonstützen in dem Sinne ungleichmässig ist, als beispielsweise in zwei zueinander rechtwinklig stehenden Meridianebenen derartiger Stützen die Beanspruchung ungleichmässig sein kann, was z.B. bei Verwendung solcher Betonstützen für Fernleitungen vorkommt. 



  Die vorliegende Erfindung bezweckt daher die Schaffung einer Schleuderbetonstütze, welche diesem Umstand Rechnung trägt und in einer Belastungsrichtung bei gleichen Spannungsverhältnissen grössere Belastungen erlaubt als in einer anderen Richtung. 



  In diesem Sinne zeichnet sich die Schleuderbetonstütze gemäss der vorliegenden Erfindung durch den kennzeichnenden Teil  des Anspruchs 1 aus. 



  Zu dieser Erfindung gehört ferner ein Verfahren zum Herstellen einer derartigen Schleuderbetonstütze, das sich durch den kennzeichnenden Teil des Verfahrensanspruches 4 auszeichnet. 



  Die Erfindung wird anschliessend beispielsweise anhand einer Zeichnung erläutert. 



  Es zeigen: 
 
   Fig. 1 bis 5 verschiedene Querschnitte von Schleuderbetonstützen, 
   Fig. 6 ein Zeit/Beschleunigungs-Schleuderdiagramm. 
 



  Fig. 1 zeigt einen Schleuderbetonstützen-Querschnitt 1 mit einer Aussenkontur 2, bestehend aus zwei parallelen Seitenebenen 3, die bei sich verjüngender Schleuderbetonstütze gegeneinander geneigt sein können, sowie durch zwei abgerundete Seitenflächen 5,  welche beispielsweise Zylindermantelflächen eines Zylinders mit der Drehachse 7 sein können. In der Mitte ergibt sich beim Schleudern ein im Querschnitt kreisförmiger Durchgang 6. Gleichmässig parallel zum Umfang oder in gewünschter anderer Konfiguration sind Armierungseisen 8, normalerweise runden Querschnittes, vorgesehen. Deren Abstand voneinander, d.h. die Teilung, ist, abgesehen von Spezialfällen, gleichmässig. Es sind ferner der Innenabstand, d.h. der Radius des mittigen Durchganges 6 von der Drehachse 7, der Innenabstand 9 sowie der Aussenminimalabstand 10 und der Aussenmaximalabstand 11 eingezeichnet. 



  Fig. 2 zeigt einen ovalen Stützenquerschnitt 15 mit zwei Seitenebenen 16 sowie halbkreisförmige Verbindungsseitenflächen 17. Im übrigen ist der Aufbau gleich wie derjenige gemäss Fig. 1. 



  In weiteren Fig. 3 bis 5 ist ein ellipsenförmiger Querschnitt, ein eiförmiger Querschnitt und ein mit geknickten Seitenebenen ausgeführter Querschnitt dargestellt. Auch hier können analoge Armierungseisen irgendwelchen Querschnittes vorgesehen werden. 



  Zum Herstellen derartiger Schleuderbetonstützen bedient man sich normalerweise einer Stahlform, welche zweiteilig und in der Längssymmetrieebene geteilt ist. Dadurch wird die Beschickungsfläche für das Einfüllen des Betons grösser und das Herausnehmen der fertigen Betonstütze einfacher, da keine Parallelflächen das Herausnehmen behindern. 



  Diese Formen werden in einer Betonschleudermaschine gelagert, wobei, da solche Maschinen auf dem Markt erhältlich sind und die vorliegende Erfindung deren Konstruktion nicht beinhaltet, diese nicht beschrieben wird. Heute sind diese Maschinen im allgemeinen auf dem sog. Rollenbankprinzip aufgebaut, ein Prinzip, welches auch bei Mischtrommeln bekannt ist. Der Antrieb erfolgt dann durch Antreiben der im Abstand von ungefähr 2 m angeordneten Lagerrollen, auf denen die dynamisch ausgewuchtete Form mit Drehzahlen in der Grössenordnung von 300 bis 660/min rotiert. 



  Nachdem die untere Halbschale der Form gefüllt ist, wobei entsprechende Armierungseisen, als sog. Körbe punktgeschweisst oder mit Drähten miteinander verbunden, eingelegt worden sind, und gegebenenfalls durch entsprechende Vorspannvorrichtungen vorgespannt werden, wird die obere Formhälfte aufgesetzt, die Form verschlossen und der Schleudervorgang kann, wie dies beispielsweise im Diagramm gemäss Fig. 6 dargestellt ist, ausgeführt werden. In diesem Beispiel wird in einer ersten Phase die Drehzahl vom Punkt 0 (Fig. 6) auf den Punkt I hochgefahren, um dann während einer Vorverteilzeit bis zum Zeitpunkt II diese Vorverteilbeschleunigung wirken zu lassen. Dann wird die Drehzahl erhöht, auf den Punkt III, und während der Verdichtungszeit bis zum Zeitpunkt IV das eigentliche Fertigschleudern unter Wirkung der Verdichtungsbeschleunigung durchgeführt.

  Hierauf wird die Drehzahl auf den Wert 0 gemäss Punkt V abgesenkt und die Form sowie die geschleuderte Betonstütze bekannterweise während einer gewissen Zeit zum Abbinden in der Form belassen 



  In der Folge werden beispielsweise einige Parametergrössen angegeben, welche einen qualitativ hochwertigen Schleuderbeton ergeben. Dabei ist vom Grundgedanken auszugehen, dass im zu schleudernden Betongemisch die grössten Bestandteile des Kieses dimensionsmässig nur ungefähr 2/3 des Abstandes benachbarter Mantelflächen der Bewehrungsstähle sein dürfen, ansonst die Gefahr des Hängenbleibens innerhalb des Bewehrungshages steigt und damit der Aussengürtel dieser Stützen zu wenig Grobanteile erhält. Der sog. Wasser/ Zementfaktor liegt vorzugsweise im Bereich zwischen 0,4 bis 0,42. Die Vorverteilzeit I bis II beträgt 6 bis 12 min, wobei die Drehzahl so zu wählen ist, dass die Beschleunigungen für die Abstände 9, 10 und 11 sich in den Grössen 0,4 bis 0,6 g, bzw. 0,8 bis 1,2 g, bzw. 1,4 bis 2,0 g bewegen.

  In diesen Grössenordnungen spielt die Erdbeschleunigung bei horizontalem Schleudern einen Einfluss, indem sie, je nach Lage des Betongemisches, sich zu den vorgegebenen Werten addiert oder von diesen subtrahiert, womit ein gewisses Einrütteln bzw. Einstampfen in dieser Phase erfolgt. 



   Nach dem Ansteigen auf die höhere Drehzahl erfolgt das Verdichten mit Beschleunigungswerten bezüglich der Abstände 9, 10 und 11 von 8 bis 10 g, bzw. 19 bis 22 g, bzw. 35 bis 40 g. Die Verdichtungszeit III bis IV dauert dabei normalerweise 4 bis 8 min. 



  Üblicherweise beträgt der im wesentlichen gleichmässige Abstand vom Hag der Armierungseisen 8 bis an die Aussenperipherie des Stützenquerschnittes 1 2,5 bis 5 cm. Dabei spielt die Berücksichtigung allfälliger Korrosionsgefahren, bedingt durch klimatische bzw. Umgebungsverhältnisse, eine wesentliche Rolle. 



  Es ist natürlich möglich, in einem Zug, allerdings bei entsprechend längerer Zeitdauer, vom Punkt 0 auf den Punkt III hochzufahren und dann die Zeitdauer III bis IV nötigenfalls entsprechend zu verlängern. 



  Es ist aber auch möglich, anstelle von zwei auch drei oder mehr Stufen vorzusehen. Auch können unterschiedliche Armierungshilfen, z.B. unterschiedliche Querschnitte, verwendet werden, beispielsweise Doppel-T-Balken, Rundeisen usw., wobei aber die Frage des freien Durchtrittes der grössten Betonbestandteile bei der Wahl und der Anordnung der Armierungen zu berücksichtigen sind. 



  Es ist hervorzuheben, dass die Herstellung derartiger, nicht reine Rotationsflächen darstellender Schleuderbetonstützen mit sehr hohen Bewehrungsgehalten, nämlich bis zu 17% des Betonquerschnittes, vorgesehen werden kann, was gegenüber den üblichen rotationssymmetrischen Querschnitten bzw. vieleckigen Querschnitten einen weiteren Vorteil darstellt. 



  In der Praxis betragen die Achsenverhältnisse der in den Fig. 1 bis 6 erläuterten Gebilde beispielsweise 27 x 48 cm, wobei die Querschnittsform im allgemeinen so zu wählen ist, dass die Betonfläche maximal 90% der Gesamtfläche entspricht. Dabei muss die minimale Wanddicke "w" eine genügende Überdeckung der Bewehrung gewährleisten, was insbesondere, wie erwähnt, durch die Korrosionsfestigkeit bedingt ist. 



  Bei nichtarmierten Stützen ergaben die folgenden Parameter optimale Eigenschaften:
 Beschleunigung in den Bereichen äusserer Maximalabstände = 4 g,
 Verdichtungszeit = 10 min, Faktor w/z = 0,38 oder auch
 Aussenmaximalabstandsbeschleunigung = 16 g,
 Verdichtungszeit = 1 min, Faktor w/z = 0,39. 



   Bei armierten Stützen ergaben sich ähnliche Verhältnisse. Die Versuche zeigten, dass die Parameter Armierung, Kornzusammensetzung, Betonzusätze, Abstand der Armierungseisen, unterschiedliches Anfahren, verschiedene Stufenzahlen im Sinne der Fig. 6 und deren Zeiten zu unterschiedlichen Resultaten führen. Die Versuche zeigten jedoch durchwegs den Vorteil von nicht kreisrunden oder regulären Vielecken in der Querschnittswahl der Stützen, insbesondere bei spezifischen Belastungen der Stützen in ihren Anwendungsbereichen. 



  Als Stützen sind im vorliegenden Falle sog. Profile und Träger ganz allgemein zu verstehen, welche durch Kräfte beansprucht werden, also insbesondere auch Biegeträger und dgl. 



  
 



  The present invention relates to a spun concrete support and a method for producing such a spun concrete support.



  Such props made of centrifugal concrete became known in the previous century. They were mainly made in circular cross-sections, in a point-symmetrical design as regular polygons, for example square or with an octagonal cross-section, whereby, due to the centrifugal process, a circular opening resulted in the core. Such centrifugal concrete props were either cylindrical or conical in shape, as explained in detail in the art. "Centrifugal concrete" of the SIA, special print from issue 7/1981 by Erich Bacsa, Zurich.



  The present invention takes into account the fact that the load on such centrifugal concrete columns is uneven in the sense that, for example, the stress can be uneven in two mutually perpendicular meridian planes of such columns, which e.g. occurs when using such concrete supports for long-distance lines.



  The present invention therefore aims to provide a centrifugal concrete support which takes this into account and allows greater loads in one loading direction with the same tension conditions than in another direction.



  In this sense, the centrifugal concrete prop according to the present invention is characterized by the characterizing part of claim 1.



  This invention also includes a method for producing such a centrifugal concrete prop, which is characterized by the characterizing part of method claim 4.



  The invention is subsequently explained, for example, using a drawing.



  Show it:
 
   1 to 5 different cross sections of spun concrete columns,
   6 is a time / acceleration spin diagram.
 



  Fig. 1 shows a spun-concrete prop cross-section 1 with an outer contour 2, consisting of two parallel side planes 3, which can be inclined towards each other with a tapered spun-concrete prop, and by two rounded side faces 5, which can be, for example, cylindrical outer surfaces of a cylinder with the axis of rotation 7. In the middle there is a passage 6 with a circular cross-section when spinning. Reinforcing irons 8, usually of round cross-section, are provided in a manner parallel to the circumference or in another desired configuration. Their distance from each other, i.e. apart from special cases, the division is uniform. It is also the inner distance, i.e. the radius of the central passage 6 from the axis of rotation 7, the inner distance 9 and the outer minimum distance 10 and the outer maximum distance 11 are shown.



  FIG. 2 shows an oval support cross section 15 with two side planes 16 and semicircular connecting side surfaces 17. Otherwise, the structure is the same as that according to FIG. 1.



  3 to 5 show an elliptical cross section, an egg-shaped cross section and a cross section designed with bent side planes. Analog reinforcement bars of any cross-section can also be provided here.



  A steel mold, which is divided into two parts and is divided in the longitudinal plane of symmetry, is normally used to produce centrifugal concrete supports of this type. This increases the loading area for the filling of the concrete and the removal of the finished concrete support easier, since no parallel surfaces hinder the removal.



  These molds are stored in a concrete centrifugal machine, and since such machines are available on the market and the present invention does not include their construction, they are not described. Today, these machines are generally based on the so-called roller bench principle, a principle that is also known for mixing drums. The drive then takes place by driving the bearing rollers, which are arranged at a distance of approximately 2 m, on which the dynamically balanced form rotates at speeds of the order of magnitude of 300 to 660 / min.



  After the lower half-shell of the mold has been filled, with appropriate reinforcing irons, as so-called baskets spot-welded or connected to each other with wires, and if necessary pre-stressed by appropriate pre-tensioning devices, the upper mold half is put on, the mold is closed and the spinning process can, as shown, for example, in the diagram according to FIG. 6. In this example, the speed is ramped up from point 0 (FIG. 6) to point I in a first phase, in order to then allow this pre-distribution acceleration to take effect during a pre-distribution time up to time II. Then the speed is increased to point III, and the actual final spin is carried out during the compression time up to time IV under the effect of the compression acceleration.

  The speed is then reduced to the value 0 in accordance with point V and, as is known, the mold and the flung concrete support are left in the mold for a certain time



  In the following, for example, some parameter sizes are given, which result in high-quality centrifugal concrete. The basic idea here is that the largest components of the gravel in the concrete mixture to be spun may only be about 2/3 of the distance between adjacent outer surfaces of the reinforcing steel, otherwise the risk of getting caught inside the reinforcement heap increases and the outer belt of these supports receives too little coarse material . The so-called water / cement factor is preferably in the range between 0.4 and 0.42. The pre-distribution time I to II is 6 to 12 min, the speed being selected so that the accelerations for the distances 9, 10 and 11 are in the sizes 0.4 to 0.6 g and 0.8 to 1, respectively , 2 g or 1.4 to 2.0 g.

  In these orders of magnitude, the acceleration due to gravity plays a role in horizontal spinning by adding to or subtracting from the specified values, depending on the position of the concrete mixture, which results in a certain shaking or pounding in this phase.



   After increasing to the higher speed, the compression takes place with acceleration values with respect to the distances 9, 10 and 11 of 8 to 10 g, or 19 to 22 g or 35 to 40 g. The compression time III to IV normally takes 4 to 8 minutes.



  Usually, the substantially uniform distance from the hail of the reinforcing bars 8 to the outer periphery of the column cross section 1 is 2.5 to 5 cm. The consideration of possible corrosion risks due to climatic or environmental conditions plays an important role.



  It is of course possible to go up from point 0 to point III in one train, but with a correspondingly longer time period, and then to extend the time period III to IV accordingly, if necessary.



  However, it is also possible to provide three or more stages instead of two. Different reinforcement aids, e.g. Different cross-sections are used, for example double T-beams, round bars etc., but the question of the free passage of the largest concrete components must be taken into account when choosing and arranging the reinforcements.



  It should be emphasized that the production of such centrifugal concrete columns, which do not represent pure rotational surfaces, with very high reinforcement contents, namely up to 17% of the concrete cross section, can be provided, which represents a further advantage over the usual rotationally symmetrical cross sections or polygonal cross sections.



  In practice, the axial ratios of the structures illustrated in FIGS. 1 to 6 are, for example, 27 × 48 cm, the cross-sectional shape generally being chosen so that the concrete surface corresponds to a maximum of 90% of the total surface. The minimum wall thickness "w" must ensure sufficient coverage of the reinforcement, which, as mentioned above, is due to the corrosion resistance.



  The following parameters gave optimal properties for non-reinforced columns:
 Acceleration in the areas of maximum external distances = 4 g,
 Compression time = 10 min, factor w / z = 0.38 or also
 External maximum acceleration of distance = 16 g,
 Compression time = 1 min, factor w / z = 0.39.



   The situation was similar for armored supports. The tests showed that the parameters reinforcement, grain composition, concrete additives, spacing of the reinforcement bars, different starting, different number of stages in the sense of FIG. 6 and their times lead to different results. However, the tests consistently showed the advantage of non-circular or regular polygons in the cross-sectional selection of the supports, especially with specific loads on the supports in their areas of application.



  In the present case, supports are to be understood in general terms as so-called profiles and beams which are stressed by forces, in particular also bending beams and the like.


    

Claims (9)

1. Schleuderbetonstütze, dadurch gekennzeichnet, dass sie Querschnitte aufweist, deren Umfang sich je aus Kreisbögen und Geradenstücken zusammensetzt oder oval oder ellipsenförmig ist.       1. centrifugal concrete column, characterized in that it has cross sections, the circumference of which is composed of arcs and straight lines or is oval or elliptical. 2. Schleuderbetonstütze nach Anspruch 1, dadurch gekennzeichnet, dass sie mit, gegebenenfalls vorgespannten, Armierungsstäben versehen ist, welche vorzugsweise mit konstanter Teilung, gleichlaufend zur Aussenkontur angeordnet sind. 2. Centrifugal concrete support according to claim 1, characterized in that it is provided with, optionally prestressed, reinforcing bars, which are preferably arranged with a constant pitch, running parallel to the outer contour. 3. Schleuderbetonstütze nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass die Armierungsstäbe unter sich ungleiche Querschnitte aufweisen. 3. centrifugal concrete support according to claim 1 or 2, characterized in that the reinforcing bars have unequal cross sections among themselves. 4. 4th Verfahren zum Herstellen einer Schleuderbetonstütze, nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass man die Betonmasse in eine Form einbringt und diese geschlossen in Drehung versetzt, dass man die Drehzahl stufenweise oder kontinuierlich auf einen Endwert steigert und diesen bis ans Ende der Schleuderzeit konstant hält, um die Drehzahl dann stufenweise oder kontinuierlich auf Null zu senken, und dass man dann nach einer Wartezeit die Stütze der Form entnimmt. Method for producing a centrifugal concrete support, according to one of claims 1 to 3, characterized in that the concrete mass is introduced into a mold and this is rotated closed, that the speed is increased gradually or continuously to a final value and this until the end of the centrifugal time holds constant in order to then gradually or continuously reduce the speed to zero and that after a waiting period the support is removed from the mold. 5. Verfahren nach Anspruch 4, dadurch gekennzeichnet, dass dass man die Enddrehzahl zum Schleudern in zwei Stufen erreicht. 5. The method according to claim 4, characterized in that one reaches the final speed for spinning in two stages. 6. Verfahren nach einem der Ansprüche 4 oder 5, dadurch gekennzeichnet, dass man die grössten Betonkörner ungefähr 2/3 so gross wie der kleinste Abstand zweier Armierungsstäbe im Stützenquerschnitt wählt. 6. The method according to any one of claims 4 or 5, characterized in that one selects the largest concrete grains approximately 2/3 as large as the smallest distance between two reinforcing bars in the column cross-section. 7. 7. Verfahren nach einem der Ansprüche 4 bis 6, dadurch gekennzeichnet, dass man in einer ersten Stufe durch Anwendung einer maximalen Zentrifugalbeschleunigung von 2 g, vorzugsweise von ungefähr 1 g, die Betonmasse einrüttelt, um sie anschliessend zu verdichten, z.B. mit einer Zentrifugalbeschleunigung von bis zu 40 g.  Method according to one of claims 4 to 6, characterized in that in a first stage, by applying a maximum centrifugal acceleration of 2 g, preferably about 1 g, the concrete mass is shaken in order to subsequently compact it, e.g. with a centrifugal acceleration of up to 40 g. 8. Verfahren nach Anspruch 7, dadurch gekennzeichnet, dass man höchstens während einer Vorverteilzeit von 15 min, vorzugsweise 6-12 min einrüttelt. 8. The method according to claim 7, characterized in that one shakes at most during a pre-distribution time of 15 min, preferably 6-12 min. 9. Verfahren nach einem der Ansprüche 4 bis 8, dadurch gekennzeichnet, dass man höchstens während 16 min, z.B. während 5 min, schleudert, mit einer zentrifugalen Aussenbeschleunigung von ungefähr 10 g. 1. Schleuderbetonstütze, dadurch gekennzeichnet, dass sie Querschnitte aufweist, deren Umfang sich je aus Kreisbögen und Geradenstücken zusammensetzt oder oval oder ellipsenförmig ist. 2. Schleuderbetonstütze nach Anspruch 1, dadurch gekennzeichnet, dass sie mit, gegebenenfalls vorgespannten, Armierungsstäben versehen ist, welche vorzugsweise mit konstanter Teilung, gleichlaufend zur Aussenkontur angeordnet sind. 3. Schleuderbetonstütze nach Anspruch 1 oder 2, dadurch gekennzeichnet, dass die Armierungsstäbe unter sich ungleiche Querschnitte aufweisen. 4. 9. The method according to any one of claims 4 to 8, characterized in that at most for 16 min, e.g. for 5 min, spins with a centrifugal external acceleration of approximately 10 g.       1. centrifugal concrete column, characterized in that it has cross sections, the circumference of which is composed of arcs and straight lines or is oval or elliptical. 2. Centrifugal concrete support according to claim 1, characterized in that it is provided with, optionally prestressed, reinforcing bars, which are preferably arranged with a constant pitch, running parallel to the outer contour. 3. centrifugal concrete support according to claim 1 or 2, characterized in that the reinforcing bars have unequal cross sections among themselves. 4th Verfahren zum Herstellen einer Schleuderbetonstütze, nach einem der Ansprüche 1 bis 3, dadurch gekennzeichnet, dass man die Betonmasse in eine Form einbringt und diese geschlossen in Drehung versetzt, dass man die Drehzahl stufenweise oder kontinuierlich auf einen Endwert steigert und diesen bis ans Ende der Schleuderzeit konstant hält, um die Drehzahl dann stufenweise oder kontinuierlich auf Null zu senken, und dass man dann nach einer Wartezeit die Stütze der Form entnimmt. 5. Verfahren nach Anspruch 4, dadurch gekennzeichnet, dass dass man die Enddrehzahl zum Schleudern in zwei Stufen erreicht. 6. Verfahren nach einem der Ansprüche 4 oder 5, dadurch gekennzeichnet, dass man die grössten Betonkörner ungefähr 2/3 so gross wie der kleinste Abstand zweier Armierungsstäbe im Stützenquerschnitt wählt. 7. Method for producing a centrifugal concrete support, according to one of claims 1 to 3, characterized in that the concrete mass is introduced into a mold and this is rotated closed, that the speed is increased gradually or continuously to a final value and this until the end of the centrifugal time holds constant in order to then gradually or continuously reduce the speed to zero and that after a waiting period the support is removed from the mold. 5. The method according to claim 4, characterized in that one reaches the final speed for spinning in two stages. 6. The method according to any one of claims 4 or 5, characterized in that one selects the largest concrete grains approximately 2/3 as large as the smallest distance between two reinforcing bars in the column cross-section. 7. Verfahren nach einem der Ansprüche 4 bis 6, dadurch gekennzeichnet, dass man in einer ersten Stufe durch Anwendung einer maximalen Zentrifugalbeschleunigung von 2 g, vorzugsweise von ungefähr 1 g, die Betonmasse einrüttelt, um sie anschliessend zu verdichten, z.B. mit einer Zentrifugalbeschleunigung von bis zu 40 g. 8. Verfahren nach Anspruch 7, dadurch gekennzeichnet, dass man höchstens während einer Vorverteilzeit von 15 min, vorzugsweise 6-12 min einrüttelt. 9. Verfahren nach einem der Ansprüche 4 bis 8, dadurch gekennzeichnet, dass man höchstens während 16 min, z.B. während 5 min, schleudert, mit einer zentrifugalen Aussenbeschleunigung von ungefähr 10 g.  Method according to one of claims 4 to 6, characterized in that in a first stage, by applying a maximum centrifugal acceleration of 2 g, preferably about 1 g, the concrete mass is shaken in order to subsequently compact it, e.g. with a centrifugal acceleration of up to 40 g. 8. The method according to claim 7, characterized in that one shakes at most during a pre-distribution time of 15 min, preferably 6-12 min. 9. The method according to any one of claims 4 to 8, characterized in that at most for 16 min, e.g. for 5 min, spins with a centrifugal external acceleration of approximately 10 g.  
CH152788A 1988-04-22 1988-04-22 Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical CH677386A5 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH152788A CH677386A5 (en) 1988-04-22 1988-04-22 Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH152788A CH677386A5 (en) 1988-04-22 1988-04-22 Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical

Publications (1)

Publication Number Publication Date
CH677386A5 true CH677386A5 (en) 1991-05-15

Family

ID=4212525

Family Applications (1)

Application Number Title Priority Date Filing Date
CH152788A CH677386A5 (en) 1988-04-22 1988-04-22 Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical

Country Status (1)

Country Link
CH (1) CH677386A5 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2785932A1 (en) * 1998-11-18 2000-05-19 Beton Moule Ind Overhead power, lighting or telecommunications pole made of concrete or a similar material has two vertical parts tapering upward from wide base to narrow top
ITUB20153350A1 (en) * 2015-09-02 2017-03-02 Schoenthaler Ohg Snc Support pole, and a procedure for making it, in particular a support pole for hops

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2785932A1 (en) * 1998-11-18 2000-05-19 Beton Moule Ind Overhead power, lighting or telecommunications pole made of concrete or a similar material has two vertical parts tapering upward from wide base to narrow top
ITUB20153350A1 (en) * 2015-09-02 2017-03-02 Schoenthaler Ohg Snc Support pole, and a procedure for making it, in particular a support pole for hops
EP3138391A1 (en) * 2015-09-02 2017-03-08 Schönthaler OHG- SNC Support masts, and method of producing same, in particular support masts for hop installations

Similar Documents

Publication Publication Date Title
EP2082131B1 (en) Mast for a wind turbine
DE1159818B (en) Process for the production of elastic wire ropes and wire ropes obtained by this process
DE1602660A1 (en) Method and machine for the production of rotational molded bodies by rolling
DE1584682C3 (en) Process for the manufacture of reinforced concrete pipes
CH677386A5 (en) Centrifugally cast concrete support - has periphery with curved and straight sections or oval or elliptical
DE2364230A1 (en) METHOD AND APPARATUS FOR PRODUCING CORE YARN IN AN OPEN-END SPINNING DEVICE
DE19613927C1 (en) Coating method for small items containing recesses
DE19851923B4 (en) Device for transporting yarn through a climatic chamber
DE2236230A1 (en) FORM FOR THE MANUFACTURE OF POLES, POSTS, PILLARS OR THE LIKE
AT390027B (en) Method for producing prestressed precast concrete parts
DE1510678A1 (en) Spinning tube
DE582258C (en) Method and device for producing a core strand consisting of non-circular individual wires
DE102017115141A1 (en) A method for producing a concrete formwork for a tower segment and method for producing a tower segment for a tower of a wind turbine
CH447031A (en) Device for cleaning a silo
DE3418735C2 (en)
DE2708202A1 (en) DEVICE FOR WINDING CORNER ARMORING COILS MADE OF METAL WIRE
DE1913179A1 (en) Process for the production of objects from strings of thread impregnated with a thermosetting synthetic resin
AT309756B (en) Wire or rod, in particular tension wire for prestressed concrete reinforcement, as well as method and device for its production
DE69807352T2 (en) METHOD FOR PRODUCING AN EXTENSIVE PRODUCT FROM REINFORCED CONCRETE FOR LONGITUDINAL LOADS
DE663432C (en) Load-bearing hollow reinforced concrete body, especially hollow reinforced concrete mast
DE2738110A1 (en) PERIODICALLY WORKING CENTRIFUGE FOR DISPENSING FILLING MATERIAL
DE1022144B (en) Process for the production of elongated and other prestressed concrete castings
AT323990B (en) DEVICE FOR APPLYING A REINFORCEMENT TO A CYLINDRICAL PLASTIC BODY
DE1948563C3 (en) Process for the production of a store for bulk material or liquids and store produced according to this process
CH347800A (en) Machine for simultaneous counter-rotating winding of two threads around an axis

Legal Events

Date Code Title Description
PL Patent ceased