CH148039A CH148039DA CH148039A CH 148039 A CH148039 A CH 148039A CH 148039D A CH148039D A CH 148039DA CH 148039 A CH148039 A CH 148039A
Authority
CH
Switzerland
Prior art keywords
reinforced concrete
rods
reinforcement
rigid
skeleton
Prior art date
Application number
Other languages
German (de)
Inventor
Bruno Dr Bauer
Original Assignee
Bruno Dr Bauer
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bruno Dr Bauer filed Critical Bruno Dr Bauer
Publication of CH148039A publication Critical patent/CH148039A/en

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Description

  

  Verfahren zur Herstellung von     Eisenbetonkonstruktionen    und nach demselben  hergestellte     Eisenbetonkonstruktion.       Der reine     Stahlskelettbau,    wie er heute  für     Grossgeschossbauten    (Hochhäuser, Wol  kenkratzer) in der Regel verwendet wird,  hat den Nachteil, dass die feuersichere Aus  mauerung und Verkleidung, bestehe sie aus  Beton oder Ziegel, zur     Mittragung    nicht  herangezogen wird und für das Stahlskelett  deshalb nur eine unerwünschte Mehrbelastung  bedeutet.  



  Demgegenüber stellen     Bauwerkskonstruk-          tionen    aus Eisenbeton einen Verbundkörper  dar, der die beiden Baustoffe, Beton und  Eisen, anteilmässig zur     Lasttragung    aus  nützt.  



  Bei Hochhausbauten mit der bei Her  stellung von Eisenbeton bisher üblichen Ar  beitsweise lässt sich der wirtschaftliche Vor  teil des Eisenbetonbaues nur zu einem ge  ringen Teil ausnützen. Da die Festigkeit der       Eisenbetonkonstruktion    erst nach dem Er  härten des Betons in Erscheinung tritt und  anderseits die normale Eisenarmierung nur    eine sehr geringe     Standfestigkeit    besitzt, ist  es notwendig, den Bau stufenweise     hoehzu-          treiben,    wobei für jede Stufe ein starres,  standfestes     Schalungsgerüst    hergestellt wer  den muss, in das die Armierung unter nach  folgender     Einbetonierung    eingelegt wird.

    Herstellung der Armierung und Einbetonie  rung wechseln ständig ab. Der für die Her  stellung der schweren, starren Verschalung  verlorene Aufwand und der stetige Wechsel  von Herstellung der Armierung und Beto  nierung sind für die Verwendung der     Eisen-          betonbauweise    für     Hochhausbauten    ein gro  sses Hindernis.  



  Durch die vorliegende Erfindung, welch  ein Verfahren zur Herstellung von Eisen  betonkonstruktionen zum Gegenstande hat,  wird es nun ermöglicht, die Vorteile der rei  nen Stahlskelett- und der     Eisenbetonbau-          weise    zu vereinigen und die beiden Bau  weisen anhaftenden Nachteile zu vermeiden,  und zwar dadurch, dass man     biegungssteife         Metallstäbe     biegungssteif    miteinander ver  bindet, mit einer     Umschnürung    versieht und  zu einem die ganze Armierung für den Bau  bildenden standfesten Skelett, vor der Aus  betonierung, verbindet, wobei man die zur  Herstellung des Skelettes dienenden Teile in  ihren Dimensionen so wählt und so mitein  ander verbindet,

   dass das sich ergebende  Skelett     imstande        isst,    die während der Aus  betonierung auftretenden Spannungen aufzu  nehmen und das zur Ausbetonierung erfor  derliche Gerüst zu tragen.  



  Die nach diesem Verfahren hergestellte       Eisenbetonkonstruktion    besitzt ein Metall  skelett, das     biegungssteife-Metallstäbe    auf-,  weist, die unmittelbar mit ihren Stirnseiten       aneinanderstossend,        biegungssteif    miteinander  verbunden und mit einer     Umschnürung    ver  sehen sind.  



  Für die     Armierung    kommen     zweckmässi-          gerweise    Stangen oder Stäbe aus Materialien  von verhältnismässig geringer     Quetschbarkeit,     wie Gusseisen oder     Transmissionswellenstahl,     zur Verwendung, und deren Verbindung kann       unmittelbar    durch Schweissen oder vermittelst  Näpfen, Rillen, Nuten, geilen, Schlössern       bezw.    verschiebbaren Muffen     etc.    erfolgen.  



  Die     Zeichnung    dient     zur    Erläuterung des  Verfahrens nach der Erfindung und zeigt  beispielsweise einige Ausführungsformen der  Armierung.  



       Fig.    1 veranschaulicht einen schemati  schen     Längsschnitt    durch die     vertikale          Längsarmierung    für eine Betonsäule, welche  drei Stockwerke     durchragt;          Fig.    2, 3, 4, 5 und 6 veranschaulichen  Querschnitte durch verschiedene Ausfüh  rungsformen der     Armierung    für eine Beton  säule;       Fig.    7 zeigt einen schematischen Längs  schnitt durch die     Armierung    zweier aufein  anderfolgender Druckglieder für eine Beton  brücke;

         Fig.    8 veranschaulicht einen Querschnitt  durch die     Armierung    benachbarter Druck  glieder einer Betonbrücke.    Die     Fig.    9 bis 15 zeigen Ausführungs  formen der Verbindung zwischen den verti  kalen     Armierungen    und den horizontalen  Armierungen für eine Hochbank.  



  Bei der Ausführungsform gemäss     Fig.    1  sind die     biegungssteifen    Stangen oder Stäbe 1  mit ihren Stirnseiten unmittelbar aneinander  stossend derart aufeinandergelegt, dass die       Armierung    das ganze Bauwerk durch alle  Stockwerke     durchragt.    Die Verbindung der  einzelnen aufeinandergelegten Stäbe 1 er  folgt entweder, wie bei 3 angedeutet ist,  durch     Schweissen    oder aber durch Muffen 4.  2 sind die Stäbe 1 verbindende Distanzhalter.  5 ist eine     Umschnürung    aus Walzdraht;  6 ist eine     Umschnürung    aus einem Flach  eisen, welches hochkantig in     Richtung    der  Längsachse der Armierung gewickelt ist.

    7 ist eine     Umschnürung,    bestehend aus einem  die     biegungssteifen    Längsstäbe 1 umschnü  renden, zylindrischen, gelochten Rohr, das  zugleich den Putzträger bildet. Dieses per  forierte Rohr ist entweder nahtlos oder durch  Verschweissen der Länge nach gebildet. Es  kann direkt über dem     Stabgerippe    verfestigt  werden oder in einem besonderen Arbeits  gang hergestellt und hierauf erst über die  Längsstäbe aufgeschoben werden.

   Die Längs  stäbe 1 können gemäss     Fig.    2 und 3 recht  eckigen Querschnitt besitzen und radial hoch  kantig angeordnet sein, und zwar können im  Säulenquerschnitt zum Beispiel gemäss     Fig.    2  vier, oder gemäss     Fig.    3 mehr als vier Stäbe  angeordnet sein. Die Stäbe können auch  hohl sein.  



  Die Stäbe zusammen mit den Distanz  haltern und der     Umschnürung    bilden eine  standfeste     Armierung,    welche so dimensio  niert ist,     da.ss    das     sich,ergebende    Skelett im  stande ist, die während der Ausbetonierung  auftretenden Spannungen aufzunehmen und  das zur Ausbetonierung erforderliche Gerüst  zu tragen.  



  Bei der Ausführungsform gemäss     Fig.    4  sind acht Rundstäbe verwendet.     Fig.    5 zeigt  die Verwendung von vier Rundstäben, wel  che mit sie verbindenden Distanzhaltern 2      gehalten werden. Nach     Fig.    6 sind die vier  Rundstäbe mit den Distanzhaltern aus einem       Gussstück    gebildet.  



  Die     Fig.    7 und 8 zeigen als Beispiele  das     Armierungsskelett    zweier Eisenbeton  brücken. Diese     Skelette    bestehen im wesent  lichen aus denselben Elementen (Längsstäbe  mit Distanzhaltern und     Umschnürung)        wie     das bereits beschriebene Beispiel, wobei die  mit ihren' Stirnseiten aneinander stossenden  Längsstäbe der Druckglieder durch Schwei  ssen oder dergleichen miteinander vereinigt  sind. In den     Fig.    7 und 8 sind die ein  zelnen Elemente mit denselben Bezugsbuch  staben bezeichnet wie in den früheren Fi  guren.  



  Gemäss der     Fig.    8 sind die Armierungen  durch Streben 8 miteinander verbunden,  könnten aber auch auf andere Art mitein  ander verbunden sein.  



  Bei der Ausführungsform, welche     Fig.    9  in Seitenansicht und     Fig.    10 in Draufsicht  zeigt, sind an den     biegungssteifen    vertikalen  Stäben oder Längsarmierungen 1, welche aus  unmittelbar mit ihren Stirnseiten     aneinan-          derstossenden    und     biegungssteif    miteinander  verbundenen Stäben gebildet sind, die     bie-          gungssteifen    horizontalen Armierungen 9  dadurch starr verbunden, dass an den     Längs-          armierungen    bügelartig ausgebildete Träger  10 für diese horizontalen Armierungen an  geordnet sind.

   Die Träger 10 sind an Stan  gen 11 befestigt, welche vermittelst Hülsen  12, die mit den Trägern 10 aus einem Stück  bestehen, an den Längsarmierungen 1 auf  geschoben werden. Die Hülsen 12 können  aber auch fest mit den Stangen 11 ver  bundene Hülsen sein. Diese Stangen 11 über  laschen zweckmässig die Stossstellen der  Längsarmierungen, so dass sie unter Um  ständen die     biegungssteife    Verbindung der  einzelnen Elemente dieser Längsarmierungen  darstellen können. Die horizontalen     Armie-          rungen    9 sind mit den bügelartigen Trägern  10 zweckmässig durch Verschrauben, Ver  nieten, Verschweissen oder dergleichen ver  bunden. Die vertikalen     Längsarmierungen       sind in der vorher beschriebenen Art um  schnürt.

   Bei der dargestellten Ausführungs  form besteht die     Umschnürung    aus einer  Drahtspirale 5.  



  Bei der Ausführungsform, welche     Fig.    11  in Seitenansicht und     Fig.    12 in     Draufsieht     zeigt, sind in die bügelartigen Träger 10       Horizontalarmierungen    13 eingelegt. welche  im Querschnitt U-förmig ausgebildet sind  und zweckmässig aus Stahlblech mit     raspel-          artig    ausgestossenen Öffnungen gebildet wer  den. Diese Horizontalarmierungen dienen       gleichzeitig    als Schalung für die Decken  balken. Die     Umschnürung    der vertikalen  Längsarmierungen 1 erfolgt nach der dar  gestellten Ausführungsform durch ein per  foriertes Rohr 7.  



  Bei der in     Fig.    13 schaubildlich dar  gestellten Ausführungsform sind die Stäbe 1  wieder die     biegungsfeste        Längsarmierung;     die     Umschnürung    ist nicht gezeigt. Die  Stangen 11, welche vermittelst Hülsen 12  über die Längsarmierungen geschoben wer  den, tragen Ösen 14, in welche die im Quer  schnitt U-förmigen horizontalen     Armierun-          gen    13     vermittelst    Haken 15 eingehängt  werden.

   Bei der Ausführungsform. welche       Fig.    1.4 in Seitenansicht und     Fig.    15 in  Draufsicht zeigt, bestehen die vertikalen       Längsarmierungen    1 und die horizontalen  Armierungen 16 aus hohlen Stäben, welche  an den Stossstellen miteinander verschweisst  sind. In das dadurch gebildete starre Stahl  skelett werden die     trogartig    ausgebildeten  Horizontalarmierungen 13 eingehängt. Die       Umschnürung    der vertikalen     Längsarmierun-          gen    erfolgt gemäss dieser Ausführungsform  durch ein spiralig gewundenes Band 6.  



  Die     Verwendung    der im Querschnitt     0-          förmigen    Horizontalarmierungen aus     raspel-          artig    durchstossendem Stahlblech erfordert  gewisse Vorkehrungen, um den eingegossenen  Beton fest mit diesen, gleichzeitig als Scha  lung dienenden Horizontalarmierungen zu  verbinden. Es werden deshalb vor dem Ein  giessen des Betons die Blechwände     finit    Beton  milch bestrichen, und zwar kann das Be-      streichen entweder aussen oder innen oder an  beiden Seiten erfolgen. Es ist auch möglich,  die Blechwände vorher zu verputzen, bezie  hungsweise unter     Verwendung    einer Beton  kanone zu überziehen.

   Durch diese Vor  behandlung werden die     raspelartig    aus  gestossenen Öffnungen verschlossen und haf  tet der nachträglich eingegossene Beton voll  kommen fest an der Schalung.



  Process for the production of reinforced concrete structures and reinforced concrete structures produced according to the same. The pure steel frame construction, as it is usually used today for large-storey buildings (high-rise buildings, skyscrapers), has the disadvantage that the fireproof lining and cladding, whether it is made of concrete or brick, is not used for supporting and therefore for the steel frame only means an undesirable additional burden.



  In contrast, building structures made of reinforced concrete represent a composite body that uses the two building materials, concrete and iron, proportionally to carry the load.



  In the case of high-rise buildings with the previously usual method of manufacturing reinforced concrete, the economic advantages of reinforced concrete construction can only be exploited to a limited extent. Since the strength of the reinforced concrete structure only becomes apparent after the concrete has hardened and, on the other hand, the normal iron reinforcement has only a very low level of stability, it is necessary to raise the building step by step, with a rigid, stable formwork frame being produced for each step must, in which the reinforcement is placed under after the following concreting.

    The production of reinforcement and embedding alternate constantly. The effort lost for the production of the heavy, rigid formwork and the constant alternation between the production of reinforcement and concreting are a major obstacle for the use of reinforced concrete construction for high-rise buildings.



  The present invention, which has a method for the production of reinforced concrete structures as its object, now makes it possible to combine the advantages of the pure steel frame and reinforced concrete construction and to avoid the disadvantages inherent in both construction. that bending-resistant metal rods are connected to one another in a bending-resistant manner, provided with a cord and connected to a stable skeleton, which forms the entire reinforcement for the building, before concreting, whereby the dimensions of the parts used to produce the skeleton are selected and so with one another connects others,

   that the resulting skeleton is able to absorb the stresses occurring during concreting and to carry the scaffolding necessary for concreting.



  The reinforced concrete structure produced by this method has a metal skeleton, the rigid metal rods, has, which are directly abutting with their end faces, rigidly connected to each other and see ver with a constriction.



  For the reinforcement, bars or rods made of materials of relatively low squeezability, such as cast iron or transmission shaft steel, are expediently used, and their connection can be directly by welding or by means of cups, grooves, grooves, horns, locks, or sliding sleeves etc. take place.



  The drawing serves to explain the method according to the invention and shows, for example, some embodiments of the reinforcement.



       Fig. 1 illustrates a schematic longitudinal section through the vertical longitudinal reinforcement for a concrete column which extends through three floors; Fig. 2, 3, 4, 5 and 6 illustrate cross sections through various Ausfüh approximate forms of reinforcement for a concrete column; Fig. 7 shows a schematic longitudinal section through the reinforcement of two successive pressure members for a concrete bridge;

         Fig. 8 illustrates a cross section through the reinforcement of adjacent pressure members of a concrete bridge. 9 to 15 show execution forms of the connection between the vertical reinforcements and the horizontal reinforcements for a high bench.



  In the embodiment according to FIG. 1, the rigid rods or bars 1 are placed with their end faces directly abutting one another in such a way that the reinforcement protrudes through the entire structure through all floors. The connection of the individual stacked rods 1 he follows either, as indicated at 3, by welding or by sleeves 4. 2 are the rods 1 connecting spacers. 5 is a strapping made of wire rod; 6 is a constriction made of a flat iron, which is wound on edge in the direction of the longitudinal axis of the reinforcement.

    7 is a constriction, consisting of a bend-resistant longitudinal rods 1 umschnü generating, cylindrical, perforated tube, which also forms the plaster base. This perforated pipe is either seamless or formed by welding along its length. It can be solidified directly over the bar framework or produced in a special work gear and then only pushed over the longitudinal bars.

   The longitudinal rods 1 can have a rectangular cross-section according to FIGS. 2 and 3 and be arranged radially edged, namely four rods can be arranged in the column cross-section, for example according to FIG. 2, or more than four rods according to FIG. 3. The bars can also be hollow.



  The bars together with the spacers and the constriction form a stable reinforcement, which is dimensioned in such a way that the resulting skeleton is able to absorb the stresses occurring during concreting and to support the scaffolding required for concreting.



  In the embodiment according to FIG. 4, eight round bars are used. Fig. 5 shows the use of four round rods wel che with spacers 2 connecting them are held. According to FIG. 6, the four round bars with the spacers are formed from a cast piece.



  7 and 8 show the reinforcement skeleton of two reinforced concrete bridges as examples. These skeletons consist essentially of the same elements (longitudinal rods with spacers and constriction) as the example already described, the longitudinal rods of the pressure members abutting with their 'end faces being united by welding or the like. In Figs. 7 and 8, the individual elements with the same reference letters are designated as in the earlier Fi gures.



  According to FIG. 8, the reinforcements are connected to one another by struts 8, but could also be connected to one another in other ways.



  In the embodiment shown in FIG. 9 in a side view and FIG. 10 in a top view, the flexurally stiff horizontal bars or longitudinal reinforcements 1, which are formed from sticks that abut one another directly at their end faces and are joined to one another in a stiffly stiff manner, are rigidly flexurally stiff Reinforcements 9 rigidly connected in that bracket-like supports 10 for these horizontal reinforcements are arranged on the longitudinal reinforcements.

   The carriers 10 are attached to Stan gene 11, which means sleeves 12, which are made of one piece with the carriers 10, are pushed onto the longitudinal reinforcements 1. The sleeves 12 can also be firmly connected to the rods 11 sleeves. These rods 11 over tabs expediently the joints of the longitudinal reinforcements, so that they can represent the rigid connection of the individual elements of these longitudinal reinforcements under order. The horizontal reinforcements 9 are expediently connected to the bow-like supports 10 by screwing, riveting, welding or the like. The vertical longitudinal reinforcements are tied around in the manner described above.

   In the embodiment shown, the constriction consists of a wire spiral 5.



  In the embodiment, which FIG. 11 shows in side view and FIG. 12 in top view, horizontal reinforcements 13 are inserted into the bracket-like carriers 10. which are U-shaped in cross-section and are expediently formed from sheet steel with rasp-like openings. These horizontal reinforcements also serve as formwork for the ceiling beams. The constriction of the vertical longitudinal reinforcements 1 takes place according to the embodiment provided by a perforated pipe 7.



  In the embodiment shown diagrammatically in FIG. 13, the rods 1 are again the bending-resistant longitudinal reinforcement; the wrapping is not shown. The rods 11, which by means of sleeves 12 are pushed over the longitudinal reinforcements, carry eyelets 14 into which the horizontal reinforcements 13, which are U-shaped in cross section, are hooked by means of hooks 15.

   In the embodiment. which Fig. 1.4 shows in side view and Fig. 15 in plan view, the vertical longitudinal reinforcements 1 and the horizontal reinforcements 16 consist of hollow rods which are welded to one another at the joints. The trough-like horizontal reinforcements 13 are suspended in the rigid steel skeleton thus formed. According to this embodiment, the vertical longitudinal reinforcements are tied around by a spiral-wound band 6.



  The use of the horizontal reinforcement, which has a 0-shaped cross-section and is made of rasp-like piercing sheet steel, requires certain precautions in order to connect the poured concrete firmly to this horizontal reinforcement, which also serves as formwork. For this reason, before the concrete is poured in, the sheet metal walls are coated with finite concrete milk, and the coating can be either outside or inside or on both sides. It is also possible to plaster the sheet metal walls beforehand, or to cover them using a concrete cannon.

   This pre-treatment closes the rasp-like openings and the subsequently poured concrete adheres firmly to the formwork.

 

Claims (1)

PATENTAN SPRÜCIHE I. Verfahren zur Herstellung von Eisen betonkonstruktionen, dadurch gekenn zeichnet, dass man biegungssteife Me tallstäbe biegungssteif miteinander ver bindet, mit einer Umschnürung versieht und zu einem die ganze Armierung für den Bau bildenden standfesten Skelett, vor der Ausbetonierung, verbindet, wobei man die zur Herstellung des Skelettes dienenden Teile in ihren Dimensionen so wählt und so miteinander verbindet. dass das sich ergebende Skelett imstande ist, die während der Ausbetonierung auf tretenden Spannungen aufzunehmen und das zur Ausbetonierung erforderliche Ge rüst zu tragen. PATENTAN SPRAY I. A process for the production of reinforced concrete structures, characterized in that rigid metal rods are connected to one another in a rigid manner, provided with a constriction and to form a stable skeleton, which forms the entire reinforcement for the building, before the concreting, whereby one the parts that are used to make the skeleton are chosen in terms of their dimensions and so connect with one another. that the resulting skeleton is able to absorb the stresses occurring during the concreting and to support the scaffolding required for concreting. II. Eisenbetonkonstruktion, hergestellt nach dem Verfahren nach Patentanspruch I, dadurch gekennzeichnet, dass sie ein Me tallskelett besitzt, welches aus biegungs- steifen Metallstäben besteht, die unmit telbar mit ihren Stirnseiten aneinander stossend biegungssteif miteinander verbun den und mit einer Umschnürung ver sehen sind und eine das ganze Bauwerk durchragende standfeste Armierung bil den. II. Reinforced concrete construction, produced according to the method according to claim I, characterized in that it has a metal skeleton which consists of rigid metal rods which are directly connected to one another with their end faces in a flexurally rigid manner and are provided with a constriction and stable reinforcement protruding through the entire structure. UNTERANSPRÜCHE: 1. Eisenbetonkonstruktion nach Patent anspruch II, dadurch gekennzeichnet, dass die Umschnürung der Metallstäbe des Metallskelettes aus einem Flacheisen besteht, welches hochkantig in Richtung der Längsaze der Armierung gewickelt ist. SUBClaims: 1. Reinforced concrete construction according to patent claim II, characterized in that the constriction of the metal rods of the metal skeleton consists of a flat iron which is wound upright in the direction of the longitudinal point of the reinforcement. \?. Eisenbetonkonstruktion nach Patent anspruch II, dadurch gekennzeichnet, dass die Umschnürung der Metallstäbe des Metallskelettes aus einem die bie- gungssteifen Stäbe umschliessenden, zt#lin- drischen, gelochten Rohr, das gleich zeitig einen Putzträger bildet, besteht. \ ?. Reinforced concrete construction according to patent claim II, characterized in that the constriction of the metal rods of the metal skeleton consists of a partially linear, perforated tube which encloses the rigid rods and which at the same time forms a plaster base. 3. Eisenbetonkonstruktion nach Patent anspruch II, für einen Hochbau, dadurch gekennzeichnet, dass die im Patent anspruch II genannten biegungssteifen Stäbe zur Vertikalarmierung des Bau werkes gehören und mit biegungssteifen horizontalen Armierungen zu einem einheitlichen Armierungsskelett verbun den sind. 3. Reinforced concrete construction according to patent claim II, for a building construction, characterized in that the rigid rods mentioned in patent claim II belong to the vertical reinforcement of the building and are verbun with rigid horizontal reinforcements to form a uniform reinforcement skeleton. .1. Eisenbetonkonstruktion nach Patentan- spruch II und Unteranspruch 3, dadurch gekennzeichnet, dass die biegungssteiferi Stäbe der Vertikalarmierung Mittel zum Anschluss der horizontalen Armierungen aufweisen. .1. Reinforced concrete construction according to claim II and dependent claim 3, characterized in that the rigid bars of the vertical reinforcement have means for connecting the horizontal reinforcements. 5. Eisenbetonkonstruktion nach Patent anspruch II und Unteransprüchen 3 und .I, dadurch gekennzeichnet, dass die Mittel zum Anschluss der horizontalen Armierung aus mit Hülsen versehenen Stäben bestehen, die mit den Hülsen die Stossstellen der Stäbe der Vertikal- armierung überlaschend über diese Stäbe geschoben sind und bügelartige Ansätze zur Aufnahme der horizontalen Armie rung aufweisen. 5. Reinforced concrete construction according to patent claim II and dependent claims 3 and .I, characterized in that the means for connecting the horizontal reinforcement consist of rods provided with sleeves, which are pushed over these rods overlapping the joints of the rods of the vertical reinforcement with the sleeves and have bracket-like approaches for receiving the horizontal reinforcement.
CH148039D 1928-12-24 1929-12-16 Process for the production of reinforced concrete structures and reinforced concrete structures produced according to the same. CH148039A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AT148039X 1928-12-24
AT200729X 1929-07-20

Publications (1)

Publication Number Publication Date
CH148039A true CH148039A (en) 1931-07-15

Family

ID=25606916

Family Applications (1)

Application Number Title Priority Date Filing Date
CH148039D CH148039A (en) 1928-12-24 1929-12-16 Process for the production of reinforced concrete structures and reinforced concrete structures produced according to the same.

Country Status (1)

Country Link
CH (1) CH148039A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2348943A1 (en) * 1972-09-29 1974-04-11 Fresa Ets RELATED ELEMENTS FOR ERECTING BUILDINGS

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2348943A1 (en) * 1972-09-29 1974-04-11 Fresa Ets RELATED ELEMENTS FOR ERECTING BUILDINGS

Similar Documents

Publication Publication Date Title
DE19832921A1 (en) Tower construction esp. for wind power plant with metal outer and inner shells and concrete shell arranged between these also connecting carrying elements for forming carrying
DE2350129A1 (en) DEVICE FOR ERECTING PREFERABLY ENCLOSED CONCRETE BUILDINGS
DE1914298A1 (en) Connection of relatively inclined reinforced concrete beam parts
AT123206B (en) Multi-storey buildings.
DE598730C (en) Construction process using components produced in the workshop
CH148039A (en) Process for the production of reinforced concrete structures and reinforced concrete structures produced according to the same.
DE2022965A1 (en) Reinforced concrete structure
DE631553C (en) Process for the production of beamless reinforced concrete cups
DE2158489C3 (en) Process for the production of a multi-purpose pavilion in prefabricated construction as well as a steel column with an anchoring leg for carrying out the process
DE557473C (en) Method of manufacturing reinforced concrete chimneys with rigid iron inserts
DE3621611A1 (en) Arched bridge and method for the construction thereof
DE404002C (en) Construction method for arches made of reinforced concrete
DE448746C (en) Reinforced concrete arches for bridges and similar structures with reinforcement serving as a supporting structure
DE820068C (en) Process for the production of monolithic masonry between removable formwork and formwork supports for this purpose
DE2460742A1 (en) FORMWORK FOR THE PRODUCTION OF CONE AND CONE-SHAPED BUILDING PARTS
DE1128114B (en) Process for erecting buildings with the help of assembly supports
DE2652783C3 (en) Wooden skeleton for a multi-storey building
AT105225B (en) Process for the production of reinforced concrete arches with an inner reinforcement consisting of iron pipes filled with concrete.
DE16921C (en) Methods of making hollow columns, shafts, girders, pillars and similar structural parts more resistant
CH156964A (en) Steel skeleton for multi-storey buildings.
DE638584C (en) A wall consisting of two wall shells reinforced by a wire mesh or reinforcement layers of any kind, as well as a method and device for producing the same
AT121835B (en) Reinforcement for multi-storey buildings made of reinforced concrete.
DE677797C (en) Steel frame building made of pipes and filler panels
DE900384C (en) Ceiling beams for the production of solid ceilings
DE919135C (en) Process for the production of ceilings from cylindrical or prismatic shells and reinforced in-situ concrete ribs