BE485889A - - Google Patents

Info

Publication number
BE485889A
BE485889A BE485889DA BE485889A BE 485889 A BE485889 A BE 485889A BE 485889D A BE485889D A BE 485889DA BE 485889 A BE485889 A BE 485889A
Authority
BE
Belgium
Prior art keywords
elements
prefabricated
terized
charac
floor
Prior art date
Application number
Other languages
French (fr)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Publication of BE485889A publication Critical patent/BE485889A/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/26Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated with filling members between the beams
    • E04B5/261Monolithic filling members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/26Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated with filling members between the beams
    • E04B5/261Monolithic filling members
    • E04B5/265Monolithic filling members with one or more hollow cores
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/26Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated with filling members between the beams
    • E04B5/268End filling members to be placed between the floor and the wall, e.g. thermal breaks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Building Environments (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
  • Reinforcement Elements For Buildings (AREA)

Description

       

   <Desc/Clms Page number 1> 
    



  PLANCHER PERFECTIONNE   
La présente invention est relative à un   plancher   perfectionné qui peut être classé dans la catégorie des   pion   chers à ossature mixte fer-béton. 



   L'invention   a pour   objet essentiel un plancher construit, en   partie, à   l'aide   d'éléments préfabriqués   en métal et en béton armé et, en partie, à l'aide d'éléments en béton armé réalisés sur le chantier, ledit plancher pré-      sentant tous les   avantages des     systèmes   métalliques pour les éléments   préfabriqués et   des systèmes an béton   armé   à préfabrication   partielle   pour les éléments réalisés sur pla- ce. 



   Le plancher selon l'invention est caractérisé en ce qu'il   est   constitué par des éléments métalliques préfa- 

 <Desc/Clms Page number 2> 

 briques en forme de caisson et par   des éléments   de   remplis-   sage   préfabriqués en   béton armé   destinés à être     supportes   
 EMI2.1 
 directement par lesdits éléments cctalliques, ceux-ci ser-   vent     coffrage     pour la     fabrication sur     plaça   de poutres an béton armé et étant.

   -noyés dans une   classe   de béton   coulé   sur   place,   pour assurer le blocage des   divers     éléments   cons- 
 EMI2.2 
 titutifs du plancher et le 7,cnolithis-e duo c31t1Í-ci. 



     Selon,   une   forme   de réalisation   préférée   de l'in-   vention, les     éléments   métalliques   préfabriqués     en for e   de caisson   Bout   constituas chacun par deux profils en fols   pliée sensiblement   en forme de S   et assemblés     par     soudure,

     les   éléments   de   remplissais     préfabriqués     en     béton   armé é- tant constitués soit par des   outsins à   section en   T dont   la   soleils   est rabattus sur   les     entremîtes   et dont l'âme est   percée   de trous, soit par des hourdis comportant des   alvéoles   présentant, de préférence, une section   triangu-     laire.   



   D'autres caractéristiques et avantages de l'in-   vention     ressortiront   de la description qui va suivre cn regard des dessins   annexés,     donnés     uniquement   à   titra d'e-'   xemple et   dans'     lesquels :   
 EMI2.3 
 La fig. 1 est une vue sen perspective d'un '-.;:àdnt vt,Ili7t?^ préfabriqué en forme de caisson servant à ls   réuli   sation sur   place   d'une poutre ordinsirs an   béton   armé. 



  La fig. 2 est une   vue     en   perspective   d'un élément     métallique     préfabriqué en forme de   caisson   servent   à la réali sation sur place d'une poutre de chevêtre en   bétor   armé. 



  La fig. 3 est une vue en coupe transversale d'un   devient   me   tallique préfabriqué.   



  La fig. 4 est uns   vue   en   perspective   d'un élément de   rempli   

 <Desc/Clms Page number 3> 

 sage préfabriqué en béton armé, réalisé sous la forme d'un   voutain.   



  La fig. 5 est une vue en coupe transversale suivant V-V de la fig. 4. 



  La fig. 6 est une vue en perspective d'un élément de remplis sage préfabriqué en béton armé, réalisé sous la forme d'un hourdis. 



  La fig. 7 est une vue en   perspective     illustrant   la réalisa- tion sur place   de poutres   eh béton   arcié,   à   l'aide   d'éléments analogues à celui de la fie. 1. 



  La fig. 8 est une vue de détail en coupe transversale illus- trant la disposition des éléments métalliques au cours de leur remplissage avec du béton pour la fa   brication   des poutres. 



  La fig. 9 est une vue en coupe transversale illustrant une poutre en béton terminés, en position d'utilisa- tion. 



  La fig. 10 est une vue an perspective illustrant le   montas   des -éléments de remplissage sur les poutres. 



  La fie. 11   est   une vue en coupe transversale d'un plancher terminé. 



  La fig. 12 est une vue en perspective d'une portion de plan- cher non terminée comportant une poutre de   chevê-     tre.   



  La fig. 13 est une   vue en   coupe   suivant   XIII-XIII de la fig. 



   12, illustrant un plancher avec poutres   de   chavê-   tre terminé.   



     Ainsi.qu'on   l'a indiqué   précédemment,     le plancher   selon l'invention est constitué par des   éléments   métalliques préfabriqués, par des éléments an béton armé préfabriqués et par des   éléments   en béton   orné     réalisés   sur le chantier. 



     L'élément     métallique     préfabriqué   illustré sur la 

 <Desc/Clms Page number 4> 

 
 EMI4.1 
 iG. qui on- ;,;-i s a t i- o Eur lcce j n:2 -,Do fis. oui est destiné à la réalisation sur pièce d'une pou tre en béton armé, est   constitué     essentiellement   par deux profils   Identiques -1,   et 2, en   tôle     plies     sensiblement   on fox re do S,   assembles   par soudure de   manière   à   former   un cais- son.

   Cet élément métallique est   complété,     d'uns   part,   par-   une armature   en   far   rond   soudée sur   des   barrettes d'écer- 
 EMI4.2 
 tnmnt 4 entretoisant les deux profila 1 et ¯2 at. d'autre part, par une armaturs Ce liaison 2. soudée sur- la face au- pîrisure da l!! l ,'..',11 "nt Comme représenta, i ''yT9lW Câttq. v en fsi- rond e t2rrin, a chacune de ses extrémités, par uni partie 6¯ recourbée en forras de crochet. 



  L'élément illustré par la fis. 2, qui est destiné à la fabrication sur place d'une poutre do chevêtre, ne se   distingue   du   précédent   que per   le     fit     eue     ces   deux extré- 
 EMI4.3 
 :'¯^i't:u sont coupées en biais, connus indiqua en 1 pour pcr- a-3tt.rs à cet ciblent de venir s'aceroersr perpendiculaire- ment, à l'aide du crochet 5¯ de son '-';'1;-:'+""c, ) en fer rond, sur l'Cléffi0nt de la fis. 1. 



     En   ce qui   concerne     les   éléments de   remplissage     préfabriqués   en   bétel?   armé,   il±     peuvent     être     relises   soit 
 EMI4.4 
 ûouk for-o Ce Toutains I.,.-.t""l 4 et 5), soit sous fore de hourdis (.", 6-} . 



  Lorsou'il est réalisé sous la for ne d'un Tout 3 in l'élément de : .¯;;1  présente une section en T dent la 'SG8118 8 est rabattue sur les extrémités de manière à cons- tituer dos. surfaces .' - )t1 . L; et dont l'a#o 10 e&t percée de trous 11. 



   Lorsqu'il est réalisé   sous   la   forme     d'un     hourdis   
 EMI4.5 
 12 (fie 6) l'élément de L-erplissase est traversé por ùcù al v3o'les 13 présentant, de préférence, une section -I11c311Ct:",,-,"[.1.CO!O> l   Los     éléments     préfabriqués     qui   viennent   d'être   dé- 

 <Desc/Clms Page number 5> 

 crits, penvant être   réalises   en toute   longueur     convenable     correspondent,   en ce qui   concerne   les   éléments     métalliques,   à   1'écarteront   entre les ours d'appui du plancher et,

   en ce qui concerne les   éléments     préfabriqués  on   béton,   le dis- tance entre poutres audit   plancher.   



   La construction d'un   plancher   au   mouron   des   élément   des fies 1 à 6 s'effectue   en   trois   phases   se succédant dans l'ordre suivant :   réalisation     sur   place des poutres   en   béton armé   à   l'aide des éléments   métalliques     préfabriqués   en   foras   de caisson, sise en place des poutres en béton armé et   des   
 EMI5.1 
 éL.3r!K!l t: (le remplissage en béton Dn:'2.Ó, Goi?1C0 t.L? béton ermé   destiné     au. blocage   des   éléments   constitutifs du plancher. 



     Pour la     fabrication     sur     place     des -poutres   en béton 
 EMI5.2 
 arr.ié, on .îl',.d 1 O ' placer les élénients !:C..tlc9¯11 .(¯Î770.,.., 14 (figs 8 st 9) en f'Ol'Í'l,:4C' caisson les uns à coté des autres. en 7 ........ -- ---......:. v-'J-.- .J...J 4.¯-k.J ç.... J>J'':' a,.,2t-2ez. 



  Ceci fait leurs   extrémités    adjacentes     sont     obturées    à     l'aide   
 EMI5.3 
 d'une planche amovible 12 maintenue en place'à l'aide, de (;8,- 1GB 16 engagées entre la planche JL± et .l' extrémité (18 18 par fie .6, en forme de crochet de chaque arnature 3. Les élér.Tjt. métalliques 14 ainsi montés sont   ensuite     remplis     avec du   bé- ton 17 jusqu'à leur tranche supérieure ainsi qu'il   résulte   de la fig. 9. 



   Suivant que l'on disposa ou non   d'appareils   de   la-   vege   les poutres en   béton armé sont   réalistes   au sol ou di- 
 EMI5.4 
 rect eiisnt sur les ours arrascs au niveau du plancher, es der nier cas étant celui représenté à la i 1 . 7' Lorsque les pou très sont réalisées su col, les éléments 2{allioua 14 sont placés   côte   à côte, leurs extrémités seules   reposant   sur des appuis (briques ou   madriers).   



   Une fois   fabriquées les   poutres 18 (fig. 10)   en bé   
 EMI5.5 
 ton arme sont disposées a leur emplacement C11'i'?ltlT' t s- près réglage du   niveau   par les   procédés     .usuels,   les   éléments   

 <Desc/Clms Page number 6> 

 
 EMI6.1 
 de reaplissase préfabriqués en béton 4?'Li- (des voutains 1,9,   par     exemple)   sont, à leur   tour,     montés   en   position   convens- ble.

   Cette mise en   place     dos     poutres   en béton   armé   18 et   des   $voutains 19 constitue la   deuxième     phase   du   procédé   de cons-   truction   du   plancher.   Il est à   remarquer   que les poutres en béton   armé   18 sont mises en place   dans   la position   qu'elles   occupent à la fig. 9, de façon que leur   armature   de liaison   5. soit     dirigée   vers le haut.

   après la mise en   place     des     éléments   il   n'y   a plus 
 EMI6.2 
 qu'à couler entre deu- rangeas 4:.'j-.3'.''c''.l'?tv>'3' -de voutains 19, ur.   masse   de béton 20 (fig.   Il)     qui     assure,   d'une part, le bloca ge entre eux des   poutres   18 et   des   voutains 19 et, d'autre part,   le     monolithisme     du     plancher.   



   En ce qui   concerne   les   appuis     du plancher,   ils peu vent être   réalises     sur   Gros durs,   sur     refende   ou sur   filets,     exactement   comme   pour   un   plancher-     ordinaire,     les     armatures   3 das   poutres   18   venant     s'ancrer     dans   les   chaînages,     et des   er   matures supplémentaires   étant   disposées,     lorsque     cels   est   né-   cessaire,

   dans les   semelles   de   compression   pour les   moments     négatifs.   



   Dans le cas où il   faut   utiliser des poutres de che   vêtrs,   cellen-ci,   désignées     par   21 aux   figures   12 et 13,sont accrochées à   l'aide   du crochet 6 de leur armature 3 sur   les   poutres   d'enchevêtrure   réalisées sous la   foras   de   poutre?   or dinaires 18, 1a   coffrage     extérieur     étant     obtenu à     l'aide   de cloisons an béton 22, et   le     coffrage   intérieur de la   trémie   par un   encadrement   en planches 23 établi sur le   chantier.   



   Le   plancher   est- terminé   par   la   mise   en place d'un   revêtement   24 (fig. 13), reposant   directement   sur les vou- tains 19 et sur la   masse   en béton 20 assurant le blocage des éléments constitutifs du plancher, et   par   la pose de pannsei- de plafond 25   pouvant   être revêtus   d'un     enduit     26.   

 <Desc/Clms Page number 7> 

 



     Comme     représente à   la fig. 13 qui illustre un plan cher avec plafond suspendu, les   panneaux de     plafond   25 sont   fixés   sur les âmes   des   voutains 19 à l'side   d'attaches   27, ces   panneau;/   étant   également     fixes   sur le chevêtre à   l'aida     d'attaches   28. 



   Avec les éléments préfabriqués et avec   ceux   réali- ses directement sur place, il est possible de   construire   tous les types de planchers connus et,   notamment :   a) Des planchers de type économique constitués uni   quêtent   par des poutres en béton armé et des solivattes en bois, disposées 'entre ces poutres à   1' écartement     désirable,   le   revêtement   desdits   planchers   étant réalisé par un parquet cloué directement sur les   30 limettes   et le plafond pouvant être formé par un   enduit   en plâtre sur lattes, sur bacula ou sur treillage.

   b) Dos planchers avec voutsins admettant tous les   revêtements   et tous   les   plafonds, qu'ils soient   tradition-   nels ou préfabriqués,   les     plafonds   étant accrochés sur des lambourdes en sapin fixées aux   voutains.   c} Des planchers avec voutains et avec plafonds suspendus (fig.

     13).   d) Des planchers   dans     lesquels   les   voutains   sont   remplacés   par   des   hourdis, ce type   de     planchers   sdrettant tous les   revêtements   de sol, et   permettant   la   réalisation   de   plafonds   par un simpla   enduit   en   plâtra     applique     directement   sur   la face   inférieure des hourdis. 



   Le   plancher   décrit permet non   seulement     l'usinage,   le transport, le   stockage   et la mise en place des   éléments     préfabriqués,   sans aucune sujétion de   fragilité   et aux moin- dres frais, mais   encore :

     a) La construction d'un plancher monolithique for- mant poutre au vent. 

 <Desc/Clms Page number 8> 

 b) Une bonne   solidariaation.     transversale   parmettan l'établissement de cloisons en un endroit quelconque. c) Des   chaînages   et   liaisons     parfaits   avec les murs porteurs. d) Une construction facile et parfaitement moncli- thique des assemblages, trémies et chevêtres. e) La possibilité de réaliser des surcharges import tances sans modifications de le trace. 



   Il va   de   soi que le plancher n'a été décrit et re- présenté   qu'à   titre   purement     explicatif,   nullement limitatif et que   diverses     modifications   de détail   pourraient     être ap-   portées aux formes de réalisation indiquées sans   qu'on     sor-   te pour cela du domaine de l'invention.   C'est   ainsi que, par   exemple,   les poutres en béton   armé   pourraient être entière- ment fabriquées en usine. 



    REVENDICATIONS   
1) Plancher   perfectionne   caractérisé en ce qu'il est constitué par des   éléments     métalliques   préfabriqués en forme de caisson et par des éléments de   remplissage     préfa-     briquas   en béton armé   destinés  à être   supportés  dirsetament   par   lesdits éléments   métalliques,   ceux-ci servant de   coffra-   ge pour la fabrication sur place de poutres sn béton   arme   et   étant   noyés   dans   une   Rasée   de béton coulé sur   place,

       pour   assurer le blocage des divers éléments constitutifs du plan- cher et le monolithisme de celui-ci.



   <Desc / Clms Page number 1>
    



  PERFECTED FLOOR
The present invention relates to an improved floor which can be classified in the category of expensive pegs with a mixed iron-concrete frame.



   The essential object of the invention is a floor constructed, in part, using prefabricated metal and reinforced concrete elements and, in part, using reinforced concrete elements produced on the site, said floor presenting all the advantages of metal systems for prefabricated elements and of partially prefabricated reinforced concrete systems for on-site elements.



   The floor according to the invention is characterized in that it is constituted by prefabricated metal elements.

 <Desc / Clms Page number 2>

 box-shaped bricks and by prefabricated reinforced concrete infill elements intended to be supported
 EMI2.1
 directly by said cctallic elements, these serve as formwork for the on-site fabrication of reinforced concrete beams and being.

   - drowned in a class of concrete poured in place, to ensure the blocking of the various components -
 EMI2.2
 titutives of the floor and the 7, cnolithis-e duo c31t1Í-ci.



     According to a preferred embodiment of the invention, the prefabricated metal elements in the form of a box end each constituted by two flat profiles folded substantially in the form of an S and assembled by welding,

     the prefabricated reinforced concrete filling elements consisting either of T-section outsins whose suns are folded over the entremites and whose core is pierced with holes, or by slabs comprising cells preferably presenting a triangular section.



   Other characteristics and advantages of the invention will emerge from the description which will follow with reference to the appended drawings, given solely by way of example and in which:
 EMI2.3
 Fig. 1 is a perspective view of a '-.;: Àdnt vt, Ili7t? ^ Prefabricated box-shaped used for ls réuli zation on site of a beam ordinsirs a reinforced concrete.



  Fig. 2 is a perspective view of a prefabricated metal element in the form of a box used for the on-site production of a reinforced concrete header beam.



  Fig. 3 is a cross-sectional view of a prefabricated metal frame.



  Fig. 4 is a perspective view of an element of filled

 <Desc / Clms Page number 3>

 sage prefabricated in reinforced concrete, made in the form of a vault.



  Fig. 5 is a cross-sectional view along V-V of FIG. 4.



  Fig. 6 is a perspective view of a prefabricated reinforced concrete filling element made in the form of a slab.



  Fig. 7 is a perspective view illustrating the on-site production of arched concrete beams, using elements similar to that of the beam. 1.



  Fig. 8 is a detail view in cross section illustrating the arrangement of the metal elements during their filling with concrete for the manufacture of the beams.



  Fig. 9 is a cross-sectional view illustrating a finished concrete beam in position for use.



  Fig. 10 is a perspective view illustrating the assembly of the filling elements on the beams.



  The fie. 11 is a cross-sectional view of a finished floor.



  Fig. 12 is a perspective view of an unfinished floor portion including a head beam.



  Fig. 13 is a sectional view along XIII-XIII of FIG.



   12, illustrating a floor with finished capsize beams.



     Thus, as previously indicated, the floor according to the invention is constituted by prefabricated metal elements, by prefabricated reinforced concrete elements and by ornate concrete elements produced on site.



     The prefabricated metal element shown on

 <Desc / Clms Page number 4>

 
 EMI4.1
 iG. qui on-;,; - i s a t i- o Eur lcce j n: 2 -, Do fis. yes is intended for the production on part of a reinforced concrete beam, consists essentially of two Identical profiles -1, and 2, in sheet metal folded substantially on fox re do S, assembled by welding so as to form a box his.

   This metal element is completed, on the one hand, by a round frame welded to bar bars.
 EMI4.2
 tnmnt 4 bracing the two profila 1 and ¯2 at. on the other hand, by a reinforcement This connection 2. welded on the face at the pîrisure da l !! l, '..', 11 "nt As represented, i '' yT9lW Câttq. v in fsi- round e t2rrin, at each of its ends, by a part 6¯ curved in forras of hook.



  The element illustrated by the fis. 2, which is intended for the on-site manufacture of a header beam, differs from the previous one only because of the fit in these two extremes.
 EMI4.3
 : '¯ ^ i't: u are cut at an angle, known to indicate at 1 for pcr- a-3tt.rs to this target to come aceroersr perpendicularly, using the hook 5¯ of its' - ';' 1; -: '+ "" c,) in round iron, on the key of the fis. 1.



     What about prefabricated betel fillers? armed, it ± can be read back either
 EMI4.4
 ûouk for-o Ce Toutains I., .-. t "" l 4 and 5), or under slabs (. ", 6-}.



  When the element of: .¯ ;; 1 is made in the form of an All 3 has a T-section, the SG8118 8 is folded over at the ends so as to constitute a back. surfaces. ' -) t1. L; and whose a # o 10 has holes drilled 11.



   When it is made in the form of a slab
 EMI4.5
 12 (fie 6) the element of L-erplissase is crossed by ùcù al v3o'les 13 having, preferably, a section -I11c311Ct: ",, -" [. 1.CO! O> l Los prefabricated elements which have just been de-

 <Desc / Clms Page number 5>

 crits, which can be made in any suitable length correspond, as regards the metallic elements, to the distance between the bearing supports of the floor and,

   as regards the precast or concrete elements, the distance between beams to said floor.



   The construction of a chickweed floor of the elements of fies 1 to 6 is carried out in three successive phases in the following order: on-site production of reinforced concrete beams using prefabricated metal elements in box foras, located in place of reinforced concrete beams and
 EMI5.1
 éL.3r! K! l t: (the concrete infill Dn: '2.Ó, Goi? 1C0 t. The sealed concrete intended for the blocking of the constituent elements of the floor.



     For on-site fabrication of concrete beams
 EMI5.2
 arr.ié, we .îl ',. d 1 Where to place the elements!: C..tlc9¯11. (¯Î770., .., 14 (figs 8 st 9) in f'Ol'Í'l, : 4C 'box next to each other. In 7 ........ - ---......:. V-'J -.- .J ... J 4.¯ -kJ ç .... J> J '': 'a,., 2t-2ez.



  This makes their adjacent ends are plugged using
 EMI5.3
 a removable board 12 held in place with the aid of (; 8, - 1GB 16 engaged between the board JL ± and. the end (18 18 by fie .6, in the form of a hook of each armature 3 The metal elements 14 thus mounted are then filled with concrete 17 up to their upper edge as shown in Fig. 9.



   Depending on whether or not washing devices are available, the reinforced concrete beams are realistic on the ground or di-
 EMI5.4
 rect eiisnt on the arrascs bears at floor level, the last case being that shown in i 1. 7 'When the very lice are made on the neck, the elements 2 {allioua 14 are placed side by side, their ends alone resting on supports (bricks or planks).



   Once the beams 18 (fig. 10) have been manufactured in bé
 EMI5.5
 your weapon are arranged at their location C11'i '? ltlT' t s- near level adjustment by the usual methods, the elements

 <Desc / Clms Page number 6>

 
 EMI6.1
 Prefabricated concrete reaplissase 4 'Li- (eg, vaults 1.9) are, in turn, mounted in a suitable position.

   This placement of the reinforced concrete beams 18 and the vaults 19 constitutes the second phase of the floor construction process. It should be noted that the reinforced concrete beams 18 are placed in the position they occupy in FIG. 9, so that their connecting frame 5. is directed upwards.

   after the installation of the elements there is no more
 EMI6.2
 that to flow between deu- rangeas 4:. 'j-.3'. '' c ''. l '? tv>' 3 '-de voutains 19, ur. mass of concrete 20 (Fig. II) which ensures, on the one hand, the blocka ge between them beams 18 and vaults 19 and, on the other hand, the monolithism of the floor.



   Regarding the floor supports, they can be carried out on coarse hard, on slit or on nets, exactly as for an ordinary floor, the reinforcements 3 das beams 18 coming to be anchored in the chains, and mature er additional being arranged, when necessary,

   in the compression soles for negative moments.



   In the case where it is necessary to use cheek beams, these, designated by 21 in figures 12 and 13, are hung using the hook 6 of their reinforcement 3 on the entanglement beams made under the foras of beam? Or dinaires 18, 1a outer formwork being obtained using concrete partitions 22, and the inner formwork of the hopper by a plank frame 23 established on the site.



   The floor is finished by the installation of a covering 24 (fig. 13), resting directly on the shutters 19 and on the concrete mass 20 ensuring the blocking of the constituent elements of the floor, and by the installation of ceiling panel 25 which can be coated with plaster 26.

 <Desc / Clms Page number 7>

 



     As shown in fig. 13 which illustrates an expensive plan with suspended ceiling, the ceiling panels 25 are fixed on the cores of the vaults 19 at the side of fasteners 27, these panels; / being also fixed on the header with the help of fasteners 28 .



   With the prefabricated elements and with those produced directly on site, it is possible to build all known types of floors and, in particular: a) Low-cost floors made up uniquely by reinforced concrete beams and wooden joists , arranged between these beams at 1 desirable spacing, the covering of said floors being achieved by a parquet nailed directly to the files 30 and the ceiling can be formed by a plaster coating on slats, on bacula or on trellis.

   b) Back floors with vaults admitting all coverings and all ceilings, whether traditional or prefabricated, the ceilings being hung on fir joists fixed to the vaults. c} Floors with vaults and with suspended ceilings (fig.

     13). d) Floors in which the vaults are replaced by slabs, this type of floor covering all floor coverings, and allowing ceilings to be made using a simple plaster coating applied directly to the underside of the slabs.



   The floor described not only allows the machining, transport, storage and installation of prefabricated elements, without any subjugation of fragility and at the lowest cost, but also:

     a) The construction of a monolithic floor forming a wind beam.

 <Desc / Clms Page number 8>

 b) Good solidarity. transverse parmettan the establishment of partitions in any place. c) Perfect chaining and links with load-bearing walls. d) Easy and perfectly monolithic construction of the assemblies, hoppers and headers. e) The possibility of carrying out significant overloads without modification of the trace.



   It goes without saying that the floor has been described and shown for purely explanatory purposes, in no way limiting, and that various modifications of detail could be made to the embodiments indicated without leaving out for this. within the scope of the invention. Thus, for example, reinforced concrete beams could be entirely manufactured in the factory.



    CLAIMS
1) Perfect floor characterized in that it is constituted by prefabricated metal elements in the form of a box and by prefabricated reinforced concrete filling elements intended to be supported dirsetament by said metal elements, the latter serving as a box. ge for the on-site manufacture of reinforced concrete beams and being embedded in a shaved concrete poured in place,

       to ensure the blocking of the various constituent elements of the floor and the monolithism of the latter.


    

Claims (1)

2) Plancher suivant la revendication 1 caractéri- sé en ce que les éléments métalliques préfabriqués en forme de caisson sont constitués chacun par deux profils en tôle pliée sensiblement en forre de S et assemblés par soudure. <Desc/Clms Page number 9> 2) Floor according to claim 1 charac- terized in that the prefabricated metal elements in the form of a box each consist of two sheet metal profiles folded substantially in the form of an S and assembled by welding. <Desc / Clms Page number 9> 3 ) Plancher suivant les revendications 1 et 2 sa- ractérisé on ce que chaque élément métallique préfabriqué est pourvu d'une armature longitudinale en fer rond mainte- mue par des barrettes d'écartement et présentant des extré- mités en forcie de crochet. 3) Floor according to claims 1 and 2 charac- terized that each prefabricated metal element is provided with a longitudinal round iron frame maintained by spacer bars and having hook-shaped ends. 4) Plancher suivant la revendication 1 caractéri- sé en ce qu'une armature de liaison est rapportée par soudu- re sur la face supérieure de chaque élément métallique pré- fabriqué. 4) Floor according to claim 1 charac- terized in that a connecting reinforcement is attached by welding to the upper face of each prefabricated metal element. 5) Plancher suivant le revendication 1 caractéri- sé en ce que les extrémités des éléments métalliques préfa- briqués sont coupées en biais lorsque lesdits éléments sont destinés à des poutres de chevêtre. 5) Floor according to claim 1 charac- terized in that the ends of the prefabricated metal elements are cut at an angle when said elements are intended for header beams. 6 ) Plancher suivant la revendication 1 caractéri- sé en ce que les éléments de remplissais préfabriqués en bé- ton armé sont constitués par des voutaine à section en T dont le semelle est rabattue sur les extrémités et dont l'â- me est percée de trous. 6) Floor according to claim 1 charac- terized in that the prefabricated reinforced concrete filling elements are constituted by vault with a T-section whose sole is folded over the ends and whose core is pierced with holes. 7 ) Plancher suivant la revendication 1 caractéri- sé en ce que les éléments (le remplissage préfabriqués en bé- ton armé sont constitués par des hourdis comportant des al- véoloE présentant, de préférence, une section triangulaire. 7) Floor according to claim 1 charac- terized in that the elements (the prefabricated reinforced concrete filling are constituted by slabs comprising alveolus preferably having a triangular section.
BE485889D 1948-10-14 1948-11-19 BE485889A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
FR976721T 1948-10-14

Publications (1)

Publication Number Publication Date
BE485889A true BE485889A (en) 1948-12-15

Family

ID=9519040

Family Applications (1)

Application Number Title Priority Date Filing Date
BE485889D BE485889A (en) 1948-10-14 1948-11-19

Country Status (2)

Country Link
BE (1) BE485889A (en)
FR (1) FR976721A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2526467B1 (en) * 1982-05-05 1987-06-19 Standarm VARIABLE LENGTH CHEVETER

Also Published As

Publication number Publication date
FR976721A (en) 1951-03-21

Similar Documents

Publication Publication Date Title
EP1941104B1 (en) New type of building, method and means for erecting it
EP0011555A1 (en) Method of manufacturing prefabricated concrete beams
FR2620153A1 (en) CONSTRUCTION PANEL, ESPECIALLY CLADDING PANEL, WITH INTEGRATED THERMAL INSULATION
WO2014053905A2 (en) Structured beam and modular construction element made using said beam
EP2423402B1 (en) Highly insulated prefabricated element
FR3005669A1 (en) PANEL OF CONSTRUCTION BOIS-BETON
BE485889A (en)
FR3026121A1 (en) BUILDING WITH IMPROVED THERMAL INSULATION, METHOD FOR CONSTRUCTING THE SAME BUILDING AND STAPLES DESIGNED FOR CARRYING OUT SAID METHOD
FR2950910A1 (en) Panel for construction in e.g. factory, has end faces comprising groove of housing of assembling element, where groove is parallel to plane of framework, and walls provided with shoulder that constitutes positioning unit of adjacent panel
EP0210116A1 (en) Prefabricated-construction system, element and mould for carrying it out
CH637721A5 (en) Thermally insulating load-bearing wall
FR2880370A1 (en) Antiseismic, anticyclonic and heat insulating wall mounting method for building, involves placing trellis, channel bar and lattice stanchion in space between two rows of panels and filling concrete in space until to height of rows
WO2022034271A1 (en) Building with wooden framework and concrete floor
EP0784128B1 (en) Process for the manufacturing of a half timbered panel, panel obtained by the process and construction comprising at least one such panel
FR2918395A1 (en) Building e.g. individual house, constructing method, involves constructing internal and external finishings of surfaces of bearing walls on internal and external visible surfaces of panels integrated with concrete core
FR3022271A1 (en) MIXED CONSTRUCTION WOOD AND CONCRETE
EP0147456A1 (en) Prefabricated formwork elements intended to the building of walls, method and device related thereto.
FR2581405A1 (en) Construction to be used as a dwelling, built from precast reinforced concrete panels
FR3033811A1 (en) PREFABRICATED CONSTRUCTION ELEMENT AND METHOD FOR MANUFACTURING SUCH A PREFABRICATED CONSTRUCTION ELEMENT
FR2467923A2 (en) Tied industrialised building frame - is formed by slab edge grooves and ducts with column reinforcement in slab at duct
CH439648A (en) Prefabricated construction frame for the construction of buildings
CH298799A (en) A method of constructing a building and a building obtained by this method.
FR3105276A1 (en) Ladder-of-link
FR2530705A1 (en) Structural elements especially for the prefabrication of floors.
EP0229041A1 (en) Panels for constructions by assembling on the spot, and method for manufacturing said panels