BE1015162A5 - Rail system coated. - Google Patents

Rail system coated. Download PDF

Info

Publication number
BE1015162A5
BE1015162A5 BE2002/0621A BE200200621A BE1015162A5 BE 1015162 A5 BE1015162 A5 BE 1015162A5 BE 2002/0621 A BE2002/0621 A BE 2002/0621A BE 200200621 A BE200200621 A BE 200200621A BE 1015162 A5 BE1015162 A5 BE 1015162A5
Authority
BE
Belgium
Prior art keywords
rail
coating
rail system
fixed
saddles
Prior art date
Application number
BE2002/0621A
Other languages
French (fr)
Original Assignee
Vanhonacker Patrick Rotthier D
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Vanhonacker Patrick Rotthier D filed Critical Vanhonacker Patrick Rotthier D
Priority to BE2002/0621A priority Critical patent/BE1015162A5/en
Priority to AT03077981T priority patent/ATE327381T1/en
Priority to EP03077981A priority patent/EP1416089B1/en
Priority to ES03077981T priority patent/ES2263910T3/en
Priority to DE60305412T priority patent/DE60305412T2/en
Application granted granted Critical
Publication of BE1015162A5 publication Critical patent/BE1015162A5/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B19/00Protection of permanent way against development of dust or against the effect of wind, sun, frost, or corrosion; Means to reduce development of noise
    • E01B19/003Means for reducing the development or propagation of noise
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B21/00Track superstructure adapted for tramways in paved streets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Railway Tracks (AREA)
  • Platform Screen Doors And Railroad Systems (AREA)
  • Linear Motors (AREA)
  • Chain Conveyers (AREA)

Abstract

The railway track has a rail (11) fixed to the sleepers at regular intervals and an enclosure to cover the rail on both sides. The enclosure (18) has two flexible support profiles (14) fixed to the foot of the rail and extending between the sleepers. Alternatively, the rail sections can have concrete casings to allow use of prefabricated sections.

Description

       

   <Desc/Clms Page number 1> 
 



   Système de rail enrobé Description La présente invention concerne un rail enveloppé dans un enrobage pour l'installation de voies ferrées dans une voirie. 



  Dans l'installation de voies ferrées, le problème se situe principalement à trois niveaux : a) Au niveau de la mise en place des rails ; b) Au niveau de la maintenance de la voie en cours d'exploitation ; c) Au niveau de l'amortissement des vibrations et des bruits lors de la circulation des voitures sur les rails. 



  Il est connu, dans certaines applications, d'installer dans la voirie des rails enrobés dans un matériau très compact dans le but de conférer au rail une meilleure résistance mécanique aux dilatations et aux efforts engendrés par la circulation des voitures sur les rails. Cette disposition a pour inconvénient principal que, une fois le rail installé, le remplacement d'un tronçon de rail nécessite de casser d'abord l'enrobage pour avoir accès aux dispositifs de fixation du tronçon de rail à remplacer et, après remplacement de celui-ci, de couler un nouvel enrobage. Tout ceci demande un temps d'exécution relativement long pendant lequel le trafic doit être interrompu. D'autre part, l'utilisation d'un matériau d'enrobage très compact ne présente pas les caractéristiques statiques et dynamiques requises pour assurer une isolation antivibratoire efficace. 



  L'invention a pour but de pallier les inconvénients susmentionnés. A cet effet, elle propose un système de rail pour voie ferrée fixé à intervalles réguliers sur des selles et une gaine d'enrobage enrobant longitudinalement le rail sur ses deux côtés, dans lequel l'enrobage repose sur des profilés souples fixés au patin du rail et s'étendant entre les selles sur lesquelles est fixé le rail. 



  La mise en place d'un rail peut ainsi se faire en un temps très court. Et par la suite, au cours de l'exploitation de la voie ferrée, lorsque l'on doit avoir accès aux 

 <Desc/Clms Page number 2> 

 dispositifs de fixation, par exemple pour le remplacement d'un tronçon de rail, il suffit de forer dans le mortier à l'emplacement des boulons de fixation du rail pour libérer le tronçon de rail, le retirer avec sa gaine d'enrobage et mettre en place et fixer un nouveau tronçon de rail en un temps très court, sans devoir interrompre le trafic de manière importante. 



  Dans un mode de réalisation avantageux, un tronçon de rail, les selles sur lesquelles le tronçon de rail est fixé et la gaine d'enrobage forment un ensemble logé dans un caisson prêt à être mis en place sur un site. La mise en place peut alors se faire en un temps très court par simple coulage du mortier d'enrobage 21 et la mise en circulation du trafic sur les rails peut être lancée sans attendre le durcissement du mortier d'enrobage. 



  De plus, l'utilisation d'un matériau d'enrobage de densité relativement réduite et le choix des raideurs des semelles sous le rail favorisent la réalisation d'un niveau d'amortissement optimal des vibrations et bruits en cours d'exploitation de la voie ferrée. 



  L'invention est décrite plus en détails dans ce qui suit à l'aide des dessins dans lesquels :
La figure 1 est une vue en coupe transversale d'un système de rail suivant l'invention, avant coulage de la gaine d'enrobage;
La figure 2 est une coupe suivant la ligne 2-2 de la figure 1;
La figure 3 est une coupe suivant la ligne 3-3 de la figure 2 ;
La figure 4 est une coupe suivant la ligne 4-4 de la figure 3 ;
La figure 5 est une vue en coupe transversale du système de rail suivant l'invention, après coulage de la gaine d'enrobage et bétonnage dans un premier mode de réalisation ;
Les figures 6 et 7 illustrent une variante de réalisation du système de rail représenté à la figure 1;
La figure 8 est une vue en coupe transversale d'un système de rail suivant l'invention intégré dans un module de voie ferrée préfabriqué ;

  
La figure 9 est une vue en plan du module de voie ferrée représenté à la figure 8. 



  Dans les dessins, une même référence désigne un élément identique ou un élément similaire ou équivalent. 

 <Desc/Clms Page number 3> 

 Les figures 1 à 3 montrent un système de rail comprenant un rail 11 fixé à intervalles réguliers sur des selles 12 en acier avec interposition d'une semelle 13 en matière élastique. Le rail est fixé sur les selles au moyen de brides 15 et de boulons 17 avec rondelles. La selle 12 est munie de chaque côté d'une rainure longitudinale 16 destinée à recevoir une cornière 18 lors de la mise en place du rail, les deux cornières 18 formant les parois longitudinales d'une gouttière 19 longeant le rail 11 sur ses deux côtés. L'extrémité supérieure des cornières 18 vient se situer à environ 3 mm du bord supérieur du rail 11.

   Entre les selles 12 s'étendent des profilés 14 souples, en polyéthylène par exemple, qui sont fixés au patin du rail 11et ont une largeur égale à l'écartement entre les cornières 18 (Fig. 4). 



  Un enrobage 21 est coulé dans la gouttière 19 qui s'étend le long des deux côtés du rail 11. L'enrobage est constitué d'un mortier de caoutchouc fluide élastique, exempt de retrait et ayant une compressibilité stable. Le mortier est par exemple constitué d'un mélange de résine époxy et de polyuréthane et un durcisseur d'amine cycloaliphatique insensible à l'eau. Le poids spécifique est de 0,7 kg/dm3 environ. La résistance à la traction est supérieure à environ 1 N/mm2. Le mortier mis en place est tassé jusqu'à un niveau de-28 mm par rapport au bord supérieur du rail 11. La localisation des dispositifs de fixation est repérée au moyen d'une marque permanente laissée dans le mortier.

   La surface supérieure du mortier est terminée avec un joint élastique 23 constitué du même composé que la masse du mortier mais ayant une densité plus élevée que celle-ci, par exemple une densité de 0,9 kg/dm3. Ce joint a pour but d'éviter l'infiltration des eaux de pluies dans la gouttière. La résistance à l'arrachement sur béton et acier est supérieure à environ 2,5 N/mm2. Entre la masse de la gaine et le joint est disposée une plaquette de séparation en matière plastique. 



  Après alignement des rails 11 et coulage de l'enrobage 21, la voirie 24 peut être bétonnée en une ou plusieurs phases. Les cornières 18 peuvent alors être retirées (Fig. 5). 



  Dans un autre mode de réalisation, les cornières 18 sont montées en sens inverse, avec leur aile 22 orientée vers l'extérieur de la gouttière 19 (Fig. 6). Après réalisation de la 

 <Desc/Clms Page number 4> 

 gaine d'enrobage et bétonnage de la voirie, ces cornières sont maintenues en place afin de renforcer les coins des dalles de béton de la voirie 24 (Fig. 7). 



  La surface des cornières devant venir en contact avec le mortier d'enrobage est de préférence recouverte d'un film destiné à faciliter l'enlèvement du mortier si nécessaire, par exemple lors du remplacement du rail. 



  Lorsque l'on doit avoir accès au dispositif de fixation, par exemple pour le remplacement d'un tronçon de rail, il suffit de forer dans le mortier à l'emplacement des boulons de fixation du rail pour libérer le tronçon de rail, le retirer avec son enrobage et mettre en place et fixer un nouveau tronçon de rail en un temps très court, sans devoir interrompre le trafic de manière importante. 



  Des essais effectués sur un tronçon de rail de 6 m de long avec fixation tous les 0,9 m ont montré que la flexion statique d'un système de rail suivant l'invention est de 1 mm environ sous une charge à l'essieu de 11 tonnes. La première fréquence propre du système roue/rail est de 40 Hz environ pour un système de support classique et de 30 Hz environ pour un système antivibratoire performant. Le réglage de la fréquence propre se fait par un choix adéquat des semelles élastiques placées sous le rail. Ce résultat se compare avantageusement à la fréquence propre du système roue/rail d'une voie sur ballast, qui est d'environ 60 Hz. 



  Les raideurs statiques et dynamiques des semelles antivibratoires sous le rail peuvent avantageusement être choisies de manière que les appuis successifs le long des rails constituent alternativement un appui relativement rigide et un appui relativement souple. 



  Dans un mode de réalisation avantageux, l'ensemble d'un tronçon de rail 11 et des selles 12 qui le supportent est lui-même enrobé dans un caisson 20 en béton coulé en¯usine. 



  Les Fig. 8 et 9 représentent, respectivement en coupe transversale et vu en plan, un caisson 20 dans lequel sont enrobés deux ensembles 10 comprenant chacun un tronçon de rail 11fixé sur selles 12 et enrobé dans son enrobage 21 comme décrit plus haut. Un tel caisson, qui a par exemple des dimensions de 3 x 9 m, constitue ainsi un module de voie ferrée préfabriqué qui facilite l'installation d'une voie ferrée sur un site. La mise en 

 <Desc/Clms Page number 5> 

 place peut alors être faite en un temps très court par simple alignement des tronçons de rails de caissons contigus et jointure de ces caissons entre eux, et la mise en circulation du trafic sur les rails peut se faire sans avoir à attendre le durcissement du béton de voirie. 



  Il est bien entendu que les formes d'exécution illustrées sur les dessins et décrites dans ce qui précèdent sont donnés à titre d'exemples d'exécution du système de rail suivant l'invention et que l'invention n'est nullement limitée à ces exemples d'exécution.



   <Desc / Clms Page number 1>
 



   Coated rail system Description The present invention relates to a rail wrapped in a coating for the installation of railways in a road network.



  In the installation of railways, the problem lies mainly on three levels: a) At the level of the installation of the rails; b) At the level of track maintenance during operation; c) At the level of damping of vibrations and noises during the movement of cars on the rails.



  It is known, in certain applications, to install rails encased in a very compact material in the road network in order to give the rail better mechanical resistance to expansion and to the forces generated by the movement of cars on the rails. The main drawback of this arrangement is that, once the rail has been installed, replacing a section of rail necessitates first breaking the coating in order to have access to the devices for fixing the section of rail to be replaced and, after replacing that here, pour a new coating. All this requires a relatively long execution time during which the traffic must be interrupted. On the other hand, the use of a very compact coating material does not have the static and dynamic characteristics required to ensure effective antivibration isolation.



  The invention aims to overcome the aforementioned drawbacks. To this end, it offers a rail system for railways fixed at regular intervals on saddles and a coating sheath longitudinally coating the rail on its two sides, in which the coating rests on flexible profiles fixed to the shoe of the rail. and extending between the saddles on which the rail is fixed.



  The installation of a rail can thus be done in a very short time. And thereafter, during the operation of the railway, when one must have access to

 <Desc / Clms Page number 2>

 fixing devices, for example for the replacement of a rail section, it suffices to drill in the mortar at the location of the rail fixing bolts to release the rail section, remove it with its covering sheath and put in place and fix a new section of rail in a very short time, without having to interrupt traffic significantly.



  In an advantageous embodiment, a rail section, the saddles on which the rail section is fixed and the coating sheath form an assembly housed in a box ready to be put in place on a site. The establishment can then be done in a very short time by simply pouring the coating mortar 21 and the circulation of traffic on the rails can be started without waiting for the hardening of the coating mortar.



  In addition, the use of a coating material of relatively reduced density and the choice of the stiffnesses of the soles under the rail favor the achievement of an optimal level of damping of vibrations and noises during operation of the track. railway.



  The invention is described in more detail below with the aid of the drawings in which:
Figure 1 is a cross-sectional view of a rail system according to the invention, before casting of the coating sheath;
Figure 2 is a section along line 2-2 of Figure 1;
Figure 3 is a section along line 3-3 of Figure 2;
Figure 4 is a section along line 4-4 of Figure 3;
Figure 5 is a cross-sectional view of the rail system according to the invention, after pouring of the coating sheath and concreting in a first embodiment;
Figures 6 and 7 illustrate an alternative embodiment of the rail system shown in Figure 1;
Figure 8 is a cross-sectional view of a rail system according to the invention integrated in a prefabricated rail module;

  
FIG. 9 is a plan view of the railroad module shown in FIG. 8.



  In the drawings, the same reference designates an identical element or a similar or equivalent element.

 <Desc / Clms Page number 3>

 Figures 1 to 3 show a rail system comprising a rail 11 fixed at regular intervals on steel saddles 12 with interposition of a sole 13 of elastic material. The rail is fixed to the saddles by means of flanges 15 and bolts 17 with washers. The saddle 12 is provided on each side with a longitudinal groove 16 intended to receive an angle iron 18 during the positioning of the rail, the two angles 18 forming the longitudinal walls of a gutter 19 running along the rail 11 on its two sides . The upper end of the angles 18 is located approximately 3 mm from the upper edge of the rail 11.

   Between the saddles 12 extend flexible sections 14, made of polyethylene for example, which are fixed to the shoe of the rail 11 and have a width equal to the spacing between the angles 18 (Fig. 4).



  A coating 21 is poured into the gutter 19 which extends along the two sides of the rail 11. The coating consists of an elastic fluid rubber mortar, free of shrinkage and having stable compressibility. The mortar is for example made up of a mixture of epoxy resin and polyurethane and a cycloaliphatic amine hardener insensitive to water. The specific weight is approximately 0.7 kg / dm3. The tensile strength is greater than about 1 N / mm2. The mortar in place is packed down to a level of -28 mm from the upper edge of the rail 11. The location of the fixing devices is identified by means of a permanent mark left in the mortar.

   The upper surface of the mortar is finished with an elastic joint 23 made of the same compound as the mass of the mortar but having a higher density than the latter, for example a density of 0.9 kg / dm3. The purpose of this joint is to prevent the infiltration of rainwater into the gutter. The pull-out resistance on concrete and steel is greater than approximately 2.5 N / mm2. Between the sheath mass and the seal is placed a plastic separation plate.



  After aligning the rails 11 and pouring the coating 21, the roadway 24 can be concreted in one or more phases. The angles 18 can then be removed (Fig. 5).



  In another embodiment, the angles 18 are mounted in the opposite direction, with their wing 22 oriented towards the outside of the gutter 19 (FIG. 6). After completion of the

 <Desc / Clms Page number 4>

 coating sheathing and concreting of the road, these angles are held in place in order to reinforce the corners of the concrete slabs of the road 24 (Fig. 7).



  The surface of the angles to come into contact with the coating mortar is preferably covered with a film intended to facilitate the removal of the mortar if necessary, for example when replacing the rail.



  When it is necessary to have access to the fixing device, for example for the replacement of a rail section, it suffices to drill in the mortar at the location of the rail fixing bolts to release the rail section, remove it with its coating and set up and fix a new section of rail in a very short time, without having to interrupt traffic significantly.



  Tests carried out on a 6 m long section of rail with fixing every 0.9 m have shown that the static bending of a rail system according to the invention is approximately 1 mm under an axle load of 11 tonnes. The first natural frequency of the wheel / rail system is approximately 40 Hz for a conventional support system and approximately 30 Hz for a high-performance anti-vibration system. The adjustment of the natural frequency is made by an adequate choice of the elastic soles placed under the rail. This result compares advantageously to the natural frequency of the wheel / rail system of a track on ballast, which is around 60 Hz.



  The static and dynamic stiffnesses of the antivibration pads under the rail can advantageously be chosen so that the successive supports along the rails alternately constitute a relatively rigid support and a relatively flexible support.



  In an advantageous embodiment, the whole of a section of rail 11 and saddles 12 which support it is itself coated in a box 20 made of concrete poured in the factory.



  Figs. 8 and 9 represent, respectively in cross section and seen in plan, a box 20 in which two assemblies 10 are coated each comprising a section of rail 11 fixed on saddles 12 and coated in its coating 21 as described above. Such a box, which for example has dimensions of 3 x 9 m, thus constitutes a prefabricated railroad module which facilitates the installation of a railroad on a site. Setting

 <Desc / Clms Page number 5>

 space can then be made in a very short time by simply aligning the sections of rails of contiguous boxes and joining these boxes together, and the circulation of traffic on the rails can be done without having to wait for the hardening of the concrete of road.



  It is understood that the embodiments illustrated in the drawings and described in the foregoing are given as examples of execution of the rail system according to the invention and that the invention is in no way limited to these examples of execution.


    

Claims (7)

Revendications 1. Système de rail pour voie ferrée comprenant un rail (11), plusieurs selles (12) sur lesquelles le rail (11) se trouve fixé à intervalles réguliers, et un enrobage (21) enrobant longitudinalement le rail sur ses deux côtés, caractérisé en que l'enrobage (21) repose sur des profilés souples (14) fixés au patin du rail (11) et s'étendant entre les selles (12) sur lesquelles est fixé le rail. Claims 1. Rail system for a railway track comprising a rail (11), several saddles (12) on which the rail (11) is fixed at regular intervals, and a covering (21) longitudinally coating the rail on its two sides, characterized in that the coating (21) rests on flexible profiles (14) fixed to the shoe of the rail (11) and extending between the saddles (12) on which the rail is fixed. 2. Système de rail suivant la revendication 1, caractérisé en ce que l'enrobage (21) précité est délimité latéralement par des cornières (18) fixées aux selles (12). 2. Rail system according to claim 1, characterized in that the coating (21) above is delimited laterally by angles (18) fixed to the saddles (12). 3. Système de rail suivant l'une quelconque des revendications précédentes, caractérisé en ce que l'enrobage (21) est constitué d'un mortier de caoutchouc fluide élastique, exempt de retrait et ayant une compressibilité stable. 3. Rail system according to any one of the preceding claims, characterized in that the coating (21) consists of an elastic fluid rubber mortar, free of shrinkage and having stable compressibility. 4. Système de rail suivant l'une quelconque des revendications précédentes, caractérisé en ce que la partie supérieure de l'enrobage (21) est constituée d'un joint (23) imperméable, ayant une densité supérieure à celle de la partie restante de l'enrobage. 4. Rail system according to any one of the preceding claims, characterized in that the upper part of the coating (21) consists of a seal (23) impermeable, having a density greater than that of the remaining part of coating. 5. Système de rail suivant l'une quelconque des revendications précédentes, caractérisé en ce que le rail (11) est fixé sur les selles (12) avec interposition d'une semelle antivibratoire (13). 5. Rail system according to any one of the preceding claims, characterized in that the rail (11) is fixed to the saddles (12) with the interposition of an anti-vibration sole (13). 6. Système de rail suivant l'une quelconque des revendications précédentes, caractérisé en ce qu'il est lui-même enrobé dans un caisson (20) en béton pour former un module préfabriqué. 6. Rail system according to any one of the preceding claims, characterized in that it is itself embedded in a concrete box (20) to form a prefabricated module. 7. Système de rail suivant la revendication 6, caractérisé en ce que ledit caisson (20) enrobe deux systèmes de rail (10) parallèles. 7. Rail system according to claim 6, characterized in that said box (20) coats two rail systems (10) parallel.
BE2002/0621A 2002-10-31 2002-10-31 Rail system coated. BE1015162A5 (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
BE2002/0621A BE1015162A5 (en) 2002-10-31 2002-10-31 Rail system coated.
AT03077981T ATE327381T1 (en) 2002-10-31 2003-09-22 COVERED RAIL SYSTEM
EP03077981A EP1416089B1 (en) 2002-10-31 2003-09-22 Embedded rail system
ES03077981T ES2263910T3 (en) 2002-10-31 2003-09-22 RAIL COATED SYSTEM.
DE60305412T DE60305412T2 (en) 2002-10-31 2003-09-22 Sheathed rail system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
BE2002/0621A BE1015162A5 (en) 2002-10-31 2002-10-31 Rail system coated.

Publications (1)

Publication Number Publication Date
BE1015162A5 true BE1015162A5 (en) 2004-10-05

Family

ID=32075047

Family Applications (1)

Application Number Title Priority Date Filing Date
BE2002/0621A BE1015162A5 (en) 2002-10-31 2002-10-31 Rail system coated.

Country Status (5)

Country Link
EP (1) EP1416089B1 (en)
AT (1) ATE327381T1 (en)
BE (1) BE1015162A5 (en)
DE (1) DE60305412T2 (en)
ES (1) ES2263910T3 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102018121333A1 (en) * 2018-08-31 2020-03-05 Joachim Süss Track construction and running rail

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB943623A (en) * 1960-05-12 1963-12-04 Shell Res Ltd Improvements in or relating to polyurethanes
DE1809955B1 (en) * 1968-11-20 1970-03-19 Stelcon Ag METHOD OF FASTENING RAILS IN THE RAIL CHANNELS OF TRACK PLATES
DE3626490A1 (en) * 1986-08-11 1988-04-07 Lothar Eisner Device for the casting-in of rails
DE19627468A1 (en) * 1995-07-06 1997-01-16 Polyplan Gmbh Polyurethan Masc Grooved rail for tram track embedded in street - is enclosed by polyurethane reaction mixture introduced into formwork
EP0937817A1 (en) * 1998-02-19 1999-08-25 DVG Deutsche Verpackungsmittel-GmbH Filling element for rails, especially tramway rails
EP0952252A1 (en) * 1998-04-14 1999-10-27 POLYPLAN GmbH Polyurethan-Maschinen Shuttering for embedding a rail
FR2791369A1 (en) * 1999-03-27 2000-09-29 Regie Autonome Transports FILLING PROFILES FOR FLOOR RAIL TRACK

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9309446U1 (en) * 1992-07-17 1993-09-02 Ortwein, Hermann, 50735 Köln Rail for rail vehicles
DE19801583A1 (en) * 1998-01-19 1999-07-29 Schreck Mieves Gmbh Composite rail for railway track
DE59909614D1 (en) * 1998-10-16 2004-07-01 Phoenix Ag ELECTRICALLY INSULATING RAIL ARRANGEMENT

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB943623A (en) * 1960-05-12 1963-12-04 Shell Res Ltd Improvements in or relating to polyurethanes
DE1809955B1 (en) * 1968-11-20 1970-03-19 Stelcon Ag METHOD OF FASTENING RAILS IN THE RAIL CHANNELS OF TRACK PLATES
DE3626490A1 (en) * 1986-08-11 1988-04-07 Lothar Eisner Device for the casting-in of rails
DE19627468A1 (en) * 1995-07-06 1997-01-16 Polyplan Gmbh Polyurethan Masc Grooved rail for tram track embedded in street - is enclosed by polyurethane reaction mixture introduced into formwork
EP0937817A1 (en) * 1998-02-19 1999-08-25 DVG Deutsche Verpackungsmittel-GmbH Filling element for rails, especially tramway rails
EP0952252A1 (en) * 1998-04-14 1999-10-27 POLYPLAN GmbH Polyurethan-Maschinen Shuttering for embedding a rail
FR2791369A1 (en) * 1999-03-27 2000-09-29 Regie Autonome Transports FILLING PROFILES FOR FLOOR RAIL TRACK

Also Published As

Publication number Publication date
DE60305412T2 (en) 2007-05-03
EP1416089B1 (en) 2006-05-24
DE60305412D1 (en) 2006-06-29
EP1416089A1 (en) 2004-05-06
ES2263910T3 (en) 2006-12-16
ATE327381T1 (en) 2006-06-15

Similar Documents

Publication Publication Date Title
US5653553A (en) Drainage channel and associated method
US5647689A (en) Drainage channel grates for athletic playing surfaces and associated methods
US7556208B1 (en) Pre-assembled plate consisting of armoured concrete
EP2354300A1 (en) Embedded rail system
SE500547C2 (en) dilatation joint
EP0939164B1 (en) Construction method for a railway track
JP2007138467A (en) Load bearing type expansion device of elevated road and its construction method
CZ296446B6 (en) Railway or tramway rail fastening system and method of laying such railway or tramway rail
CA2687027A1 (en) Prefabricated module for a railway and method for manufacturing this module
JP5441187B2 (en) Bridge joint structure
JP2007046365A (en) Joint portion structure of bridge
JP4448066B2 (en) Flexible waterproof joint and its construction method
KR20170082318A (en) Elastic recovering type expansion joint and the construction method therefor
BE1015162A5 (en) Rail system coated.
JP5185978B2 (en) Bridge joint structure
KR100659978B1 (en) Crevice join fabric of construction
FR2901814A1 (en) Railway track assembly for railway level crossing, has protection bars on both sides of continuous welded rails, and fixation system fixing rails on support element, where system transmits internal longitudinal efforts of rails to element
KR100954597B1 (en) Expansion joint and manufacturing method and construciting method
JP2531574B2 (en) Projection support method for slab track
JP2007092305A (en) Waterproof flexible coupling for culvert
BE1009576A6 (en) Rail laying system
JP5998181B2 (en) Bridge deck connection method for road bridges
EP1457599B1 (en) Method for constructing a railroad level-crossing
JP3269038B2 (en) Structure of closing means for road bridge buried joint
JP2908295B2 (en) Elastic bearing for sleepers

Legal Events

Date Code Title Description
RE Patent lapsed