AU2021101421A4 - Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel - Google Patents

Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel Download PDF

Info

Publication number
AU2021101421A4
AU2021101421A4 AU2021101421A AU2021101421A AU2021101421A4 AU 2021101421 A4 AU2021101421 A4 AU 2021101421A4 AU 2021101421 A AU2021101421 A AU 2021101421A AU 2021101421 A AU2021101421 A AU 2021101421A AU 2021101421 A4 AU2021101421 A4 AU 2021101421A4
Authority
AU
Australia
Prior art keywords
grouting
tunnel
collapse
double
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2021101421A
Inventor
Anjian HUANG
Laosan LI
Xiangping Zhang
Xin Zhang
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC, China Railway 18th Bureau Group Co Ltd filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to AU2021101421A priority Critical patent/AU2021101421A4/en
Application granted granted Critical
Publication of AU2021101421A4 publication Critical patent/AU2021101421A4/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

Disclosed is a method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel. The construction method is performed s according to the following steps: performing accurate measurement at the mountain top, and determining vertical and horizontal ranges of targeted grouting; determining drilling locations according to a designed layout plan, and excavating a drilling platform; drilling a row of holes on both sides of the tunnel, and making a curtain by adopting cement-water glass two-shot grouting, so as to create good conditions for filling collapse body reinforcing grout; after o grouting at the mountain top for about 2 days, starting to construct a pipe shed and grout in the tunnel after a loose collapse body is solidified basically. The grouting effect of the loose collapse body is ensured after the curtain is formed by performing two-shot grouting at a designed position of the surface of the earth. After grouting at the mountain top for about 2 days, the loose collapse body is solidified basically. The drilling speed and the grouting effect of s the pipe shed in the tunnel are improved. The excavation and support per cycle are accelerated obviously, and are improved from original 4 m per month to above 10 m. The collapse treatment progress is accelerated, and technical and economic effects are achieved. il N I N N I I N N t N g I Ij I *rufi holNeiN i I N * N 4 Tunnel arch FIG.1I 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Grouting hole 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 FIG. 2

Description

il
N I N N I I N N t Ng I Ij I
*rufi holNeiN i I N *N 4
Tunnel arch
FIG.1I
0 0 0 0 0 0 00
0 0 0 0 0 0
0 0 0 0 0 0 0 0 Grouting hole 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
FIG. 2
METHOD FOR PERFORMING STEPPED REMOTE TARGETED FILLING, SOLIDIFYING, AND GROUTING ON HILLSIDE OF DOUBLE-TRACK COLLAPSE TUNNEL
TECHNICAL FIELD The present disclosure relates to a grouting method capable of effectively improving the treatment progress of large scale collapse of a double-track tunnel, and in particular, to a construction technology for performing remote targeted filling, solidifying, and grouting on the surface of the earth.
BACKGROUND Six collapses occurred in Nashi Tunnel 2 in 17 days in total, and three collapses occurred at the top of the tunnel. The total amount of subsidence was about 300 m3 , many cracks were found, and the widest crack was 5 cm. Arch grouting is performed in the tunnel by matching a s 060 medium pipe shed with a large extrapolation angle and a 089 large pipe shed. Each large pipe shed is 15 m long, each 060 medium pipe shed is 6 m long, each ring is 2.5 m, the
extrapolation angle is 40 °, and the circumferential spacing is 0.4 m. Because of rock stratum
dislocation and large gaps in a collapse area, it is very difficult to drill, and almost every pipe shed is stuck before reaching the designed length. The grouting of each cycle requires more than 20 o days. The excavation and the initial support of each month is only 4 m, so the progress is very slow, and the construction cost is high.
SUMMARY The objective of the present disclosure is to provide a method capable of effectively accelerating excavation and initial support of a collapse tunnel to overcome the disadvantages in collapse treatment in a tunnel. The construction process of the method is simple, practical, economic, and efficient. The technical solution of the present disclosure is: a method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel. The construction method is performed according to the following steps: (1) performing accurate measurement at the mountain top, and determining vertical and horizontal ranges of targeted grouting; (2) determining drilling locations according to a designed layout plan, and excavating a drilling platform;
(3) drilling a row of holes on both sides of the tunnel, and making a curtain by adopting cement-water glass two-shot grouting, so as to create good conditions for filling collapse body reinforcing grout; (4) after grouting at the mountain top for about 2 days, starting to construct a pipe shed and grout in the tunnel after a loose collapse body is solidified basically. The drilling range and depth must be determined according to the measured data, and holes must be drilled vertically to ensure the grouting range. The mixing proportion of double-liquid grout must be set through tests, which ensures that the curtain can be formed effectively. o The present disclosure has the following advantages and beneficial effects: (1) the grouting effect of the loose collapse body is ensured after the curtain is formed by performing two-shot grouting at a designed position of the surface of the earth; (2) after grouting at the mountain top for about 2 days, the loose collapse body is solidified basically; the drilling speed and the grouting effect of the pipe shed in the tunnel are effectively improved; the excavation and support per cycle are accelerated obviously, and are improved from original 4 m per month to above 10 m; (3) the collapse treatment progress is accelerated, and good technical and economic effects are achieved.
)o BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a longitudinal layout of grouting holes in the surface of the earth at tunnel collapse. FIG. 2 is a horizontal layout of the grouting holes in the surface of the earth at the tunnel collapse.
DETAILED DESCRIPTION As shown in FIGs. 1 to 2, a method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel. The specific implementation process is as follows: (1) accurately measuring excavation sidelines of a tunnel collapse section at the mountain top, and determining a grouting range; (2) excavating a drilling platform at the mountain top according to a designed grouting hole layout, referring to FIG. 1; (3) drilling a row of holes on both sides of the tunnel, and forming a curtain by adopting cement-water glass two-shot grouting; (4) grouting and reinforcing the loose collapse body, and when a loose collapse body is basically solidified, excavating after constructing a pipe shed in the tunnel and grouting.
A method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel is performed according to the following steps: (1) performing accurate measurement at the mountain top, and determining vertical and horizontal ranges of targeted grouting; (2) determining drilling locations according to a designed layout s plan, and excavating a drilling platform; (3) drilling a row of holes on both sides of the tunnel, and making a curtain by adopting cement-water glass two-shot grouting, so as to create good conditions for filling collapse body reinforcing grout; (4) after grouting at the mountain top for about 2 days, starting to construct a pipe shed and grout in the tunnel after a loose collapse body is solidified basically. o The measurement at the mountain top is required to be accurate, and excavation sidelines of a collapse section at the mountain top must be paid off accurately to determine a grouting range. The mixing proportion of double-liquid grout used for constructing the curtain is the key; the grout can neither solidify too fast nor flow too far after flowing out of a grouting pipe, so that a curtain can be effectively formed. s The drilling range and depth for targeted grouting on the surface of the earth must be determined according to the measured data, and the holes must be drilled vertically to ensure the grouting range and effect.

Claims (4)

Claims WHAT IS CLAIMED IS:
1. A method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel, wherein the construction method is performed s according to the following steps: (1) performing accurate measurement at the mountain top, and determining vertical and horizontal ranges of targeted grouting; (2) determining drilling locations according to a designed layout plan, and excavating a drilling platform; (3) drilling a row of holes on both sides of the tunnel, and making a curtain by adopting cement-water glass two-shot grouting, so as to create good conditions for filling collapse body reinforcing grout; (4) o after grouting at the mountain top for about 2 days, starting to construct a pipe shed and grout in the tunnel after a loose collapse body is solidified.
2. The method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel according to claim 1, wherein the measurement at the mountain top is required to be accurate, and excavation sidelines of a tunnel collapse section s must be paid off accurately to determine a grouting targeted range.
3. The method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel according to claim 1, wherein the mixing proportion of double-liquid grout used for constructing the curtain is the key; the grout can neither solidify too fast nor flow too far after flowing out of a grouting pipe, so that a curtain can be effectively o formed.
4. The method for performing stepped remote targeted filling, solidifying, and grouting on a hillside of a double-track collapse tunnel according to claim 1, wherein the drilling range and depth for targeted grouting on the surface of the earth must be determined according to measured data, and the holes must be drilled vertically, so as to ensure the grouting range and effect.
AU2021101421A 2021-03-19 2021-03-19 Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel Ceased AU2021101421A4 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2021101421A AU2021101421A4 (en) 2021-03-19 2021-03-19 Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AU2021101421A AU2021101421A4 (en) 2021-03-19 2021-03-19 Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel

Publications (1)

Publication Number Publication Date
AU2021101421A4 true AU2021101421A4 (en) 2021-05-27

Family

ID=76094283

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2021101421A Ceased AU2021101421A4 (en) 2021-03-19 2021-03-19 Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel

Country Status (1)

Country Link
AU (1) AU2021101421A4 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114251107A (en) * 2021-12-16 2022-03-29 中国电建集团成都勘测设计研究院有限公司 Tunnel collapse treatment method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114251107A (en) * 2021-12-16 2022-03-29 中国电建集团成都勘测设计研究院有限公司 Tunnel collapse treatment method
CN114251107B (en) * 2021-12-16 2023-04-28 中国电建集团成都勘测设计研究院有限公司 Tunnel collapse processing method

Similar Documents

Publication Publication Date Title
Ni et al. Quality control of double fluid jet grouting below groundwater table: case history
CN104929146B (en) A kind of multilayer karst growth zone pile foundation engineering method
Xue et al. Deformation rule and mechanical characteristic analysis of subsea tunnel crossing weathered trough
CN113565525A (en) Construction protection system and construction method for newly-built shield tunnel super-close ultra-shallow buried upper-span existing tunnel
Arroyo et al. Design of jet-grouting for tunnel waterproofing
AU2021101421A4 (en) Method for performing stepped remote targeted filling, solidifying, and grouting on hillside of double-track collapse tunnel
CN112814737A (en) Collapse column advanced treatment method and system based on laminated multi-branch horizontal well
CN114991770A (en) Island working surface grouting scour prevention stoping method based on multistage divergent type directional well
CN110145309B (en) Shallow coal seam grouting filling green coal mining method and settlement observation device thereof
Hwang et al. Utilizing direct-push crosshole seismic testing to verify the effectiveness of shallow ground improvements: A case study involving low-mobility grout columns in Christchurch, New Zealand
CN109209448B (en) Tunnel earth surface grouting water-blocking construction method
CN108589724A (en) Steel pipe and pvc pipe composite bushing sandy ground matter pore-forming anti-float anchor rod construction
Bilotta et al. Ground movements induced by tunnel boring in Naples
Morey et al. Quality control of jet grouting on the Cairo metro
CN110528522B (en) Accurate tracking grouting construction method
CN109188540B (en) Method for exploring range of frozen layer for many years in large-porosity giant loose rock mass
SHI et al. Physical experimental study on excavation disturbance of TBM in deep composite strata
CN105673020A (en) Construction method for remote and targeted filling, consolidating and grouting at two-line collapse tunnel mountaintop
CN111335903A (en) Construction method for penetrating dense building group downwards in stratum of joint zone
Chuaqui et al. A case study: Two-fluid jet grouting for tunneling application-soil stabilization and permeability reduction
CN101696633B (en) Construction method and equipment for cutting deep-buried structure with small-caliber drill tool
Charlton et al. Comprehensive Foundation Rehabilitation at Bear Creek Dam
CN116464410B (en) Drilling coring construction method for unconsolidated formation
CN116556963A (en) Boulder detection processing and construction method for shield downward penetrating old house area
CN208718681U (en) Rich water gravel layer shield duct piece grouting behind shaft or drift lining geologic radar detection test platform

Legal Events

Date Code Title Description
FGI Letters patent sealed or granted (innovation patent)
MK22 Patent ceased section 143a(d), or expired - non payment of renewal fee or expiry