AT18949B - Foundation pillars for making foundations. - Google Patents

Foundation pillars for making foundations.

Info

Publication number
AT18949B
AT18949B AT18949DA AT18949B AT 18949 B AT18949 B AT 18949B AT 18949D A AT18949D A AT 18949DA AT 18949 B AT18949 B AT 18949B
Authority
AT
Austria
Prior art keywords
box
filled
foundation pillars
foundations
parts
Prior art date
Application number
Other languages
German (de)
Original Assignee
Raymond Concrete Pile Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Raymond Concrete Pile Co filed Critical Raymond Concrete Pile Co
Application granted granted Critical
Publication of AT18949B publication Critical patent/AT18949B/en

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Description

  

   <Desc/Clms Page number 1> 
 
 EMI1.1 
 
 EMI1.2 
 

 <Desc/Clms Page number 2> 

   Befinden sich die Teile in der in Fig. 1 gezeichneten Stellung, so wird die Er unter dem innersten Kastenteil durch das aus dem Rohr  kommende Druckmittel ver-   drängt und bewirkt auf diese Weise das Senken des Kopfes und des Rohres ebenso wie auch das Senken des innersten Kastenteiles   C',   welcher auf dem Pfahlschuh aufruht. Wenn der Teil C so weit gesunken ist, dass sein oberes Ende in gleicher Höhe mit dem unteren Ende des nächstfolgenden Teiles D liegt, so ist er mit letzterem in Verbindung getreten, wie dies aus Fig. 2 hervorgeht, und wird nun der Teil E in die Öffnung des Bodens nachgezogen, sobald die   Sonkarbeit   fortgesetzt wird.

   Bevor die Erde unter dem Kastenteil entfernt wird, kann der erste Kastenteil C mit einem passenden Füllmittel, wie z. B. Beton oder dgl., ausgefüllt werden oder aber das Füllmittel kann auch gleichzeitig während der Versenkung des Pfahlschuhes B und des Teiles C eingeschüttet worden. Ebenso kann das Füllmittel auch dann eingebracht worden, nachdem der Teil 0 versenkt ist. In diesem Stadium der Gründung hat der Senkkörper die aus Fig. 2 ersichtliche Gestalt, bei welcher das obere Ende des Teiles C mit dem nächsten Teile D in Eingriff ist und des letzteren beim weiteren Senken   des'rreibkoptes mit   in den Boden zieht. Der zweite Teil D wird dann je nach Bedarf, wie oben erklärt, ausgefüllt und zu entsprechender Zeit wird sein oberes Ende mit dem unteren Ende des dritten Teiles E in sperrenden Eingriff kommen und denselben mit in den Boden ziehen.

   Der dritte Teil wird dann ebenfalls ausgefüllt, worauf der Senkkörper in diesem Stadium fertig ist, wie dies aus Fig. 3 hervorgeht
Der vierte Teil F des Kastens, welcher im vorliegenden Beispiel der letzte ist, ist mit dem Teil E in Eingriff und der Baugrund wird fertiggestellt, sobald der letzte Teil in der obenbeschriebenen Weise gesenkt und ausgefüllt ist. Um die Gründung noch tiefer fortzusetzen, wird der Kasten durch Zufügung noch mehrerer Teile verlängert und das   Fülliiiittel   in der beschriebenen Weise eingebracht, bis die gewünschte Länge erzielt ist. 



   In dem gezeichneten Beispiel haben die Teile kreisförmigen Querschnitt ; jedoch ist es   selbstverständlich, dass   sie auch jede beliebige Gestalt und von beliebiger Grösse sem 
 EMI2.1 
 



   Es ist   vorteilhaft,   das   Ausfüllen   mit dem Sinken des Kastenteiles fortschreiten zu lassen, so dass das Gewicht des Füllmittels auf das Senken des Treibkopfes und der einzelnen Teile einwirkt. Indessen können auch insbesondere bei tiefen Versenkungen die Kastenteile in der oben beschriebenen Weise versenkt und dann erst ausgefüllt werden. 



  Wenn das Ausfüllen während der Versenkung des Kastens geschieht, kann ein   verhältn-   mässig dünner Kasten verwendet werden, ohne dass man ein Zusammendrücken desselben befürchten muss. Die Kastenteile können auch vor dem Versenken auf die ganze   Länp   des Senkkörpers ausgezogen werden, welche vor dem Versenken oder während   desselben   ausgefülltwerdenkann.



   <Desc / Clms Page number 1>
 
 EMI1.1
 
 EMI1.2
 

 <Desc / Clms Page number 2>

   If the parts are in the position shown in FIG. 1, the he under the innermost box part is displaced by the pressure medium coming from the pipe and in this way causes the lowering of the head and the pipe as well as the lowering of the innermost box part C ', which rests on the pole shoe. When part C has sunk so far that its upper end is at the same level as the lower end of the next following part D, it has come into contact with the latter, as can be seen from FIG. 2, and is now part E in the opening of the floor is drawn as soon as the work continues.

   Before the earth is removed from under the box part, the first box part C can be filled with a suitable filler, such as. B. concrete or the like., Be filled or the filler can also be poured in simultaneously during the sinking of the pile shoe B and the part C. Likewise, the filler can also be introduced after the part 0 has been countersunk. At this stage of the foundation, the sinker has the shape shown in FIG. 2, in which the upper end of part C engages with the next part D and pulls the latter into the ground as the des'rreibkoptes is further lowered. The second part D is then filled in as required, as explained above, and at the appropriate time its upper end will come into locking engagement with the lower end of the third part E and pull the same into the ground.

   The third part is then also filled in, whereupon the sinker is finished at this stage, as can be seen from FIG
The fourth part F of the box, which in the present example is the last, is in engagement with part E and the building ground is completed as soon as the last part is lowered and filled in as described above. In order to continue the foundation even deeper, the box is lengthened by adding more parts and the filling agent is introduced in the manner described until the desired length is achieved.



   In the example shown, the parts have a circular cross-section; however, it goes without saying that they can also be of any shape and size
 EMI2.1
 



   It is advantageous to let the filling proceed with the sinking of the box part, so that the weight of the filler acts on the lowering of the driving head and the individual parts. In the meantime, even in the case of deep countersinks, the box parts can be countersunk in the manner described above and only then filled.



  If the filling is done while the box is being lowered, a relatively thin box can be used without having to worry about it being compressed. The box parts can also be pulled out to the entire length of the sinker before sinking, which can be filled before sinking or during the same.

 

Claims (1)

PATENT-ANSPRUCH : Grundpfeiler zur herstellung von Gründungen, gekennzeichnet durch einen nach oben EMI2.2 konischer Gestalt bestehenden Hohlkörper, dessen einzelne aufeinander folgende Teile einanderbeimVersenkenselbsttätignachziehen. PATENT CLAIM: Basic pillars for the production of foundations, marked by an upwards EMI2.2 conical shape existing hollow body, the individual successive parts of which pull each other automatically when countersinking.
AT18949D 1903-03-07 1903-03-07 Foundation pillars for making foundations. AT18949B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
AT18949T 1903-03-07

Publications (1)

Publication Number Publication Date
AT18949B true AT18949B (en) 1905-01-25

Family

ID=3523316

Family Applications (1)

Application Number Title Priority Date Filing Date
AT18949D AT18949B (en) 1903-03-07 1903-03-07 Foundation pillars for making foundations.

Country Status (1)

Country Link
AT (1) AT18949B (en)

Similar Documents

Publication Publication Date Title
AT18949B (en) Foundation pillars for making foundations.
DE1129895B (en) Method and device for the production of a foundation pile with concrete casing
DE730986C (en) Device for the production of concrete place posts with a thickened base
DE717532C (en) Process for sinking and pulling back foundation bodies under the effect of shaking, as well as equipment for carrying out the process
DE902959C (en) Device and method for the production of foundation piles
AT69455B (en) Method of making well bores and pile holes.
AT130301B (en) Method of making piles in poor terrain.
DE575261C (en) Device for filling in soil shafts
DE2817252A1 (en) Sand drainage device for dewatering ground strata - has corrugated perforated drainage tubes with lateral long thin wings (NL 24.10.78)
DE816680C (en) Ramming shoe for hollow piles
AT117702B (en) Method and device for the execution of foundations using basic hardening columns.
AT50956B (en) Ram core for internal ramming.
DE859878C (en) Method and device for the production of foundation piles from in-situ concrete
DE521653C (en) Process for the production of cores for hollow blocks to be cast
AT140889B (en) Device for making a concrete pilot.
AT206823B (en) Method of manufacturing sleeve piles
DE730767C (en) Method for making a concrete pile
DE625897C (en) Multi-part drive core for driving in sheet metal sleeves for location posts
DE1928471A1 (en) Process and device for compacting and draining soil
AT296130B (en) Method and device for the production of concrete poles
DE588638C (en) Device for making holes for in-situ concrete piles
AT330095B (en) DEVICE FOR MANUFACTURING AN IN-SITE CONCRETE POST
AT23844B (en) Process for the production of load-bearing concrete piles.
AT24263B (en) Core for driving in and countersinking sinkers for concrete foundations.
AT102024B (en) Device for the execution of pile foundations.