US20020053486A1 - New process for mounting handrails in scaffolds - Google Patents

New process for mounting handrails in scaffolds Download PDF

Info

Publication number
US20020053486A1
US20020053486A1 US09/462,065 US46206500A US2002053486A1 US 20020053486 A1 US20020053486 A1 US 20020053486A1 US 46206500 A US46206500 A US 46206500A US 2002053486 A1 US2002053486 A1 US 2002053486A1
Authority
US
United States
Prior art keywords
railing
auxiliary element
bars
scaffolding
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US09/462,065
Inventor
Javier Galdos Urzelai
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ladas & Parry
Original Assignee
Ladas & Parry
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ladas & Parry filed Critical Ladas & Parry
Publication of US20020053486A1 publication Critical patent/US20020053486A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • E04G5/144Railings specific for the lateral, i.e. short side of a scaffold
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings
    • E04G5/147Railings specially adapted for mounting prior to the mounting of the platform

Definitions

  • the invention relates to a new assembly procedure for railings used in construction scaffolding, so that the first element which is assembled in each floor of the scaffolding is precisely the railing, thus providing this safety measure at all times during assembly of the scaffold.
  • the invention provides the advantage over known procedures of a greater ease in assembly of the safety railing, while it is made from a simple element which can be used in varying numbers and in combination with the bars of the scaffolding system.
  • the new assembly procedure for safety railings in scaffolding has been conceived to solve the aforementioned problems by greatly simplifying placing of the first or provisional safety railing from the lower level platform, so that it can be performed by a single worker.
  • the provisional safety railing is formed from the bars of the scaffolding itself and an element which is the core of the system, an auxiliary piece which from now on shall be known as a railing base, which is used to assemble the railing, hoist it to the upper level and anchor it to the frame of the scaffold structure, all of this before the remaining elements which make up the scaffold are assembled in this upper level.
  • This auxiliary element or railing base is provided with means for attaching the horizontal bars which are identical to those of the scaffold itself, as well as with means for attaching the assembled safety railing to the scaffold frame.
  • the auxiliary element or railing base is in the form of a very open angle, so that the first segment includes the means of anchoring to the frame, which segment, once having assembled the auxiliary element on the frame, is left divergent from the frame, and runs parallel to it after a point practically in its center.
  • the diverging segment includes the means for attaching the railing base to the frame, while the parallel segment includes the means for anchoring the bars.
  • the railing is assembled from the lower level platform provisionally, so that it is the first element assembled at the level immediately above.
  • first or provisional safety railing begins with its gradual assembly, for which the bars are joined to a first auxiliary element or railing base by conventional connection devices of the scaffold itself.
  • This auxiliary base with its bars anchored on one end is lifted and then connected to the corresponding frame of the scaffold, for which it is provided with a central hook and with an end plate which is inserted into corresponding receiving lugs provided in the frame.
  • the bars are connected at the opposite end to a further auxiliary element or railing base which in turn is connected to another set of bars, which would be part of the following segment of the safety railing
  • the second auxiliary element is raised and attached to the corresponding frame similarly to the first one, thus forming the first segment of the safety railing. This operation is repeated as many times as required by the length of railing needed for the scaffold.
  • the remaining elements which make up the scaffold are assembled at this level such as platforms, baseboards, horizontal bars, diagonal bars (if required), side bars, etc.
  • the bars which are part of the safety railing remain in this level as part of the definitive safety railing, that is, they remain as structural elements of the scaffold itself.
  • the recovered auxiliary elements or railing bases are used in assembling the provisional safety railing for the following level.
  • the conventional means referred to for connecting the auxiliary elements to the bars in assembling the railing consist of rods which are attached to the auxiliary elements.
  • FIG. 1 is a perspective view of the general structure of a scaffolding level during preparation for assembling the provisional railing of the higher level.
  • FIG. 2 is a representation similar to the previous one where the first auxiliary element or railing base is mounted on the corresponding frame.
  • FIG. 3 is a representation similar to the previous ones where the provisional assembly of a first segment of the provisional railing has been finished and assembly of a second segment has begun.
  • FIG. 4 shows similarly two assembled segments of the provisional safety railing.
  • FIG. 5 shows the incorporation of the remaining elements of this level, and how the railing bars are finally attached to the scaffold structure, forming the definitive safety railing.
  • FIG. 6 is an enlarged view of details of the means by which the auxiliary element or railing base is attached to the scaffolding frame.
  • FIG. 7 is a side view of the auxiliary element or railing base and the part of the frame on which it is mounted.
  • auxiliary element or railing base ( 1 ) is shown in detail in FIG. 7 showing that it consists of a bar, preferably a square tube, which is provided at the top with conventional attachment means ( 6 ) of bars ( 2 ). At the bottom are welded to it the elements for anchoring to frame ( 3 ). which consist of top hook ( 7 ) and lower plate ( 8 ) which can be inserted on corresponding lugs ( 9 ) and ( 10 ) of the aforementioned frame.
  • lugs ( 9 ) and ( 10 ) are U-bars which together with the bar of frame ( 3 ) to which they are connected form a vertical orifice.
  • Top hook ( 7 ) is also a U-bar which can be inserted in top lug ( 9 ), while lower plate ( 8 ) which is next to the bottom end of the auxiliary element or railing base ( 1 ) comes from a U-bar placed so that it lies along the side of the front bar of frame ( 3 ), whose plate is meant to be inserted in lower lug ( 10 ).
  • the first auxiliary element or railing base ( 1 ) is partially lifted and is attached to frame ( 3 ) with hook ( 7 ) and plate ( 8 ) which insert in respective lugs ( 9 ) and ( 10 ) of frame ( 3 ). Then the free ends of the bars are connected to a second auxiliary element or railing base ( 1 ′) which also receives an additional set of bars ( 2 ′).
  • the next step entails lifting the railing, lifting the second auxiliary element or railing base ( 1 ′) and attaching it in an identical manner as the first one to the corresponding frame so that the first segment of the railing will be ready and the second segment partially assembled, which will be formed once bars ( 2 ′) are joined by their free ends to a further auxiliary element ( 1 ′′) as shown in FIG. 5.
  • each auxiliary element or railing base ( 1 ) has an inclined lower segment as shown in FIG. 7, so that the rest of base ( 1 ) and railing bars ( 2 ) are located in front of frame ( 3 ) so that the upper lateral frame can be telescopically coupled

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Ladders (AREA)

Abstract

The invention is applicable as a safety measure in assembling scaffolds for construction work, specifically in assembly of the railings, so that these are made to be the first component installed on the upper level, this being performed from the level where the worker is already at, so that when said worker rises to complete the scaffold a provisional safety railing is already in place. The provisional railing is put together, raised and assembled by use of an auxiliary element or railing base to which the horizontal bars are connected, element which is anchored by suitable means to the structural frame of the scaffold

Description

  • The invention relates to a new assembly procedure for railings used in construction scaffolding, so that the first element which is assembled in each floor of the scaffolding is precisely the railing, thus providing this safety measure at all times during assembly of the scaffold. [0001]
  • The invention provides the advantage over known procedures of a greater ease in assembly of the safety railing, while it is made from a simple element which can be used in varying numbers and in combination with the bars of the scaffolding system. [0002]
  • BACKGROUND OF THE INVENTION
  • In construction work one of the first aspects to consider is the safety of the workers, as due to the conditions in which this work must be carried out it entails potentially dangerous tasks where serious accidents may occur. [0003]
  • In this sense, scaffolds are crucial working tools in construction work, where safety measures must be especially high, due to the heights which may be involved and because it is there that most work is in fact carried out. [0004]
  • For this reason, safety measures to prevent accidents are taken such as harnesses which secure the worker to the scaffolding structure and railings which prevent the worker from falling from the working platform. [0005]
  • However, while assembling the scaffolds there are times when protection is lower, as when the worker rises to the highest platform to complete the assembly of this level, in which the safety railing has not yet been assembled, and thus this worker will for some time work without this safety measure. [0006]
  • In order to solve this deficiency a mechanism is employed nowadays known as ‘French railing’ which can be attached to the railing and is an ideal solution, as this ‘French railing’ is assembled on the upper level before the remaining elements which make up the structure, that is, before workers begin to assemble this level of the scaffold. [0007]
  • However, said ‘French railing’ system, which provides optimum results from a functional point of view, presents problems which derive from its size, as because of it is an element of a large size which is integrated into the scaffold as part of its structure, it requires at least two workers for its assembly. [0008]
  • To the aforementioned problem must be added those which derive from transport of said elements and from their storage, both during the transportation from the warehouse to the construction site and at the construction site itself, as mentioned above due to its large size. [0009]
  • In fact, despite the ‘French railing’ being a good solution as regards safety, its use is not widespread as it is somewhat rejected due to its drawbacks deriving from the aforementioned problems. [0010]
  • DESCRIPTION OF THE INVENTION
  • The new assembly procedure for safety railings in scaffolding has been conceived to solve the aforementioned problems by greatly simplifying placing of the first or provisional safety railing from the lower level platform, so that it can be performed by a single worker. [0011]
  • Additionally, the provisional safety railing is formed from the bars of the scaffolding itself and an element which is the core of the system, an auxiliary piece which from now on shall be known as a railing base, which is used to assemble the railing, hoist it to the upper level and anchor it to the frame of the scaffold structure, all of this before the remaining elements which make up the scaffold are assembled in this upper level. [0012]
  • This auxiliary element or railing base is provided with means for attaching the horizontal bars which are identical to those of the scaffold itself, as well as with means for attaching the assembled safety railing to the scaffold frame. [0013]
  • The auxiliary element or railing base is in the form of a very open angle, so that the first segment includes the means of anchoring to the frame, which segment, once having assembled the auxiliary element on the frame, is left divergent from the frame, and runs parallel to it after a point practically in its center. The diverging segment includes the means for attaching the railing base to the frame, while the parallel segment includes the means for anchoring the bars. [0014]
  • The railing is assembled from the lower level platform provisionally, so that it is the first element assembled at the level immediately above. [0015]
  • Mounting of the first or provisional safety railing begins with its gradual assembly, for which the bars are joined to a first auxiliary element or railing base by conventional connection devices of the scaffold itself. This auxiliary base with its bars anchored on one end is lifted and then connected to the corresponding frame of the scaffold, for which it is provided with a central hook and with an end plate which is inserted into corresponding receiving lugs provided in the frame. Then the bars are connected at the opposite end to a further auxiliary element or railing base which in turn is connected to another set of bars, which would be part of the following segment of the safety railing The second auxiliary element is raised and attached to the corresponding frame similarly to the first one, thus forming the first segment of the safety railing. This operation is repeated as many times as required by the length of railing needed for the scaffold. [0016]
  • Once the safety railing is assembled the remaining elements which make up the scaffold are assembled at this level such as platforms, baseboards, horizontal bars, diagonal bars (if required), side bars, etc. The bars which are part of the safety railing remain in this level as part of the definitive safety railing, that is, they remain as structural elements of the scaffold itself. Naturally, the recovered auxiliary elements or railing bases are used in assembling the provisional safety railing for the following level. [0017]
  • The conventional means referred to for connecting the auxiliary elements to the bars in assembling the railing consist of rods which are attached to the auxiliary elements.[0018]
  • DESCRIPTION OF THE DRAWINGS
  • As a complement of the description being made and in order to aid a better comprehension of the characteristics of the invention, the present descriptive memory is accompanied by a set of drawings as an integral part of the same where, for purposes of illustration and in no way meant as a definition of the limits of the invention, the following is shown: [0019]
  • FIG. 1 is a perspective view of the general structure of a scaffolding level during preparation for assembling the provisional railing of the higher level. [0020]
  • FIG. 2 is a representation similar to the previous one where the first auxiliary element or railing base is mounted on the corresponding frame. [0021]
  • FIG. 3 is a representation similar to the previous ones where the provisional assembly of a first segment of the provisional railing has been finished and assembly of a second segment has begun. [0022]
  • FIG. 4 shows similarly two assembled segments of the provisional safety railing. [0023]
  • FIG. 5 shows the incorporation of the remaining elements of this level, and how the railing bars are finally attached to the scaffold structure, forming the definitive safety railing. [0024]
  • FIG. 6 is an enlarged view of details of the means by which the auxiliary element or railing base is attached to the scaffolding frame. [0025]
  • FIG. 7 is a side view of the auxiliary element or railing base and the part of the frame on which it is mounted.[0026]
  • PREFERRED EMBODIMENT OF THE INVENTION
  • The auxiliary element or railing base ([0027] 1) is shown in detail in FIG. 7 showing that it consists of a bar, preferably a square tube, which is provided at the top with conventional attachment means (6) of bars (2). At the bottom are welded to it the elements for anchoring to frame (3). which consist of top hook (7) and lower plate (8) which can be inserted on corresponding lugs (9) and (10) of the aforementioned frame.
  • In FIG. 6 one can see that lugs ([0028] 9) and (10) are U-bars which together with the bar of frame (3) to which they are connected form a vertical orifice. Top hook (7) is also a U-bar which can be inserted in top lug (9), while lower plate (8) which is next to the bottom end of the auxiliary element or railing base (1) comes from a U-bar placed so that it lies along the side of the front bar of frame (3), whose plate is meant to be inserted in lower lug (10).
  • With both attachments auxiliary element ([0029] 1) is held in the scaffold so that it cannot move in any direction but upwards
  • To form the provisional safety railing as shown in FIG. 1, the worker attaches bars ([0030] 2) by one of their ends to auxiliary element (1), leaving the other ends free. This is done with conventional means (6).
  • As seen in FIG. 2, the first auxiliary element or railing base ([0031] 1) is partially lifted and is attached to frame (3) with hook (7) and plate (8) which insert in respective lugs (9) and (10) of frame (3). Then the free ends of the bars are connected to a second auxiliary element or railing base (1′) which also receives an additional set of bars (2′).
  • The next step, shown in FIG. 3, entails lifting the railing, lifting the second auxiliary element or railing base ([0032] 1′) and attaching it in an identical manner as the first one to the corresponding frame so that the first segment of the railing will be ready and the second segment partially assembled, which will be formed once bars (2′) are joined by their free ends to a further auxiliary element (1″) as shown in FIG. 5.
  • This assembly process is repeated as many times as required to form the railing bar segments needed for the building facade covered by the scaffolding. [0033]
  • As shown in FIG. 5, once the provisional assembly of the provisional safety railing is finished, the remaining elements are added, such as frames ([0034] 3), lateral railings (4), baseboards (5), platforms (11), etc. At this stage of the assembly and in order to make coupling of frames (3) possible, each auxiliary element or railing base (1) has an inclined lower segment as shown in FIG. 7, so that the rest of base (1) and railing bars (2) are located in front of frame (3) so that the upper lateral frame can be telescopically coupled
  • Afterwards railing bars ([0035] 2) and (2′) are removed from their anchoring to basses (1) and attached to side frames (3) of the scaffolding, thus becoming part of the structure and forming the final safety railings

Claims (3)

1. New assembly procedure for scaffolding railings intending, as a safety measure, that the first element assembled at each scaffolding level is a railing, this assembly being performed from the lower level, characterised in that a provisional safety railing is formed with an auxiliary element or railing base (1) joined by conventional means (6) to bars (2), said auxiliary element (1) being used to raise and gradually secure each corresponding railing segment, assembled or pre-assembled, to the respective structural frames of the scaffolding, where auxiliary element (1) are attached to frames (3) by means of lugs (9) and (10) provided in the latter, and by auxiliary element (1) having an inverted U-bar hook which plays within lug (9) and a further U-bar near its end which laterally embraces auxiliary element (1) and is prolonged as a plate which fits in lug (10) of the frame.
2. New assembly procedure for scaffolding railings as in claim 1, characterised in that the worker partially puts together the provisional safety railing at the floor where it is being assembled, attaching matching ends of bars (2) of the railing to the conventional attachment means provided in auxiliary element (1), leaving the other ends free to later raise the unit manually, securing the auxiliary element to the scaffolding structure and repeating this process for a further one to which previously are attached the free ends and the ends of the group of bars which make up the next segment of the railing, and so on until the required length of railing is obtained, followed by assembly of the remaining elements which make up each level of the scaffold, so that once the installation is completed the bars of the provisional railing are removed from their attachments to the auxiliary element and definitively attached to the frames in order to create the fixed railing, while auxiliary element (1) are recovered to begin putting together, raising and assembling the provisional safety railing for the following floor above.
3. New assembly procedure for scaffolding railings as in previous claims, characterised in that auxiliary element or railing base (1) shows two segments which form an open angle between them, so that the lower segment, which after said auxiliary element is attached to the frame is divergent, includes the means of attachment to said frame, while the other segment, which after assembly is left parallel to the frame, includes the means for securing bars (2).
US09/462,065 1998-05-08 1998-05-08 New process for mounting handrails in scaffolds Abandoned US20020053486A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/ES1998/000130 WO1999058787A1 (en) 1998-05-08 1998-05-08 New process for mounting handrails in scaffolds

Publications (1)

Publication Number Publication Date
US20020053486A1 true US20020053486A1 (en) 2002-05-09

Family

ID=8302504

Family Applications (1)

Application Number Title Priority Date Filing Date
US09/462,065 Abandoned US20020053486A1 (en) 1998-05-08 1998-05-08 New process for mounting handrails in scaffolds

Country Status (4)

Country Link
US (1) US20020053486A1 (en)
EP (1) EP0995860A1 (en)
AU (1) AU7044798A (en)
WO (1) WO1999058787A1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040163889A1 (en) * 2001-03-27 2004-08-26 Harry Wallther Device for human protection in scaffolding
US20050061582A1 (en) * 2004-12-10 2005-03-24 Karanouh Rached Movable and repositionable safety guard rails for scaffolding
US20060000673A1 (en) * 2002-09-27 2006-01-05 Pluseight Safety Ab Device for personal safety on scaffolds
JP2015068146A (en) * 2013-10-01 2015-04-13 アルインコ株式会社 Safety device of preceding handrail
JP2015068145A (en) * 2013-10-01 2015-04-13 アルインコ株式会社 Safety device of preceding handrail
WO2021053358A1 (en) * 2019-09-20 2021-03-25 Turner Access Limited Temporary scaffolding rest
TWI824821B (en) * 2022-11-15 2023-12-01 吳宗和 Mounting rack and installation method for vertical warehouse shelf

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7079712B1 (en) 1999-05-25 2006-07-18 Silverbrook Research Pty Ltd Method and system for providing information in a document
DE20004389U1 (en) * 2000-03-13 2000-08-17 Rux Guenter Gmbh Set of components for a scaffold
GB2364733C (en) * 2000-05-12 2005-06-29 David Michael Kelk Improvements in and relating to builders' trestles
ES2203270B1 (en) * 2001-02-14 2005-02-16 Ingenieria De Encofrados Y Servicios, S.L. PERFECTION IN ANDAMIOS DE FACHADA.
CA2385380A1 (en) * 2001-05-31 2002-11-30 Tatsuo Ono Mounting method for a handrail in a frame scafolding
GB0126446D0 (en) * 2001-11-03 2002-01-02 R S Scaffolding N W Ltd Improvements in and relating to scaffolding
ES2337776T3 (en) * 2002-02-20 2010-04-29 Wilhelm Layher Verwaltungs-Gmbh DEVICE FOR ASSEMBLY OF A TEMPORARY BARREL LENGTH OF A SHELF.
DE10243356B4 (en) * 2002-07-22 2007-03-22 Peri Gmbh Dismountable scaffolding
ITMI20081670A1 (en) * 2008-09-22 2010-03-23 Montesanti Costruzioni Sas Di Giuse Ppe Montesanti STAND FOR THE TOTAL SAFETY OF THE PONTISTS
GB2476955B (en) * 2010-01-15 2012-01-04 David Michael Ward Temporary safety rail for scaffolding
BE1021482B1 (en) * 2013-09-05 2015-11-30 Afix Group N.V. METHOD FOR MOUNTING A SCAFFOLDING
WO2015033278A1 (en) * 2013-09-05 2015-03-12 Afix Group N.V. Method for mounting a scaffold

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2516141B1 (en) * 1981-11-10 1987-11-27 Philippe Robert METHOD OF ASSEMBLING A SCAFFOLDING AND ASSEMBLY DEVICE
FR2533610B1 (en) * 1982-09-23 1985-10-04 Somefran METHOD OF ASSEMBLING A SCAFFOLDING, BREATHING USED FOR THE IMPLEMENTATION OF THIS METHOD, AND SCAFFOLDING PROVIDED WITH SAID BRACKET
DE3311139A1 (en) * 1983-03-26 1984-09-27 Eberhard 7129 Güglingen Layher PROTECTIVE DEVICE FOR THE ASSEMBLY OF SCAFFOLDING FRAME
FR2732706B1 (en) * 1995-04-10 1997-05-09 Comabi Const Mat Batiment SCAFFOLDING GUARDRAILS
DE19655284B4 (en) * 1996-08-16 2008-01-24 Peri Gmbh Dismountable facade scaffolding

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040163889A1 (en) * 2001-03-27 2004-08-26 Harry Wallther Device for human protection in scaffolding
US7954598B2 (en) * 2001-03-27 2011-06-07 Pluseight Safety Ab Device for human protection in scaffolding
US20060000673A1 (en) * 2002-09-27 2006-01-05 Pluseight Safety Ab Device for personal safety on scaffolds
US20050061582A1 (en) * 2004-12-10 2005-03-24 Karanouh Rached Movable and repositionable safety guard rails for scaffolding
JP2015068146A (en) * 2013-10-01 2015-04-13 アルインコ株式会社 Safety device of preceding handrail
JP2015068145A (en) * 2013-10-01 2015-04-13 アルインコ株式会社 Safety device of preceding handrail
WO2021053358A1 (en) * 2019-09-20 2021-03-25 Turner Access Limited Temporary scaffolding rest
GB2589448B (en) * 2019-09-20 2024-02-28 Turner Access Ltd Temporary scaffolding rest
TWI824821B (en) * 2022-11-15 2023-12-01 吳宗和 Mounting rack and installation method for vertical warehouse shelf

Also Published As

Publication number Publication date
AU7044798A (en) 1999-11-29
EP0995860A1 (en) 2000-04-26
WO1999058787A8 (en) 2000-03-30
WO1999058787A1 (en) 1999-11-18

Similar Documents

Publication Publication Date Title
US20020053486A1 (en) New process for mounting handrails in scaffolds
US6554102B2 (en) Dismountable facade scaffold
RU2400609C2 (en) Complex system of accident prevention support in construction
US7748195B2 (en) Bracket and method for supporting a platform from concrete form tabs
US7975803B2 (en) Dismantlable scaffold and a railing adapter for it
US20110132685A1 (en) Scaffolding
US20120298449A1 (en) Scaffold and methods for installing or removing such a scaffold
US4253549A (en) Method and a system for the erection of high buildings
CN108699847B (en) Side panel, ceiling formwork system with at least one such side panel and method for erecting such a side panel
US20020185335A1 (en) Safety device
US6015028A (en) Pump jack hoisting apparatus including a safety railing for protecting workers from accidental falling
EP0606948B1 (en) Universal supporting construction
US20040200668A1 (en) Scaffolding system
US10731362B2 (en) Horizontal scaffold support component
AU2008100567A4 (en) A scaffolding stand for use in a formwork support system
EP1876315A1 (en) Integral safety system which can be used for construction
JPH0458866B2 (en)
GB2428729A (en) A scaffold stair unit
JPS6168971A (en) Assembling and disassembling of frame scaffold
US20220235562A1 (en) Scaffolding stair system
JP3638761B2 (en) H-framework scaffold
JPH047317Y2 (en)
KR940008464Y1 (en) Safety railing for scaffolding
AU2013100389A4 (en) Scaffolding system
JP3892240B2 (en) Working scaffold and assembly method thereof

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION