KR102183838B1 - Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation - Google Patents

Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation Download PDF

Info

Publication number
KR102183838B1
KR102183838B1 KR1020200066135A KR20200066135A KR102183838B1 KR 102183838 B1 KR102183838 B1 KR 102183838B1 KR 1020200066135 A KR1020200066135 A KR 1020200066135A KR 20200066135 A KR20200066135 A KR 20200066135A KR 102183838 B1 KR102183838 B1 KR 102183838B1
Authority
KR
South Korea
Prior art keywords
work
verification
task
project
workers
Prior art date
Application number
KR1020200066135A
Other languages
Korean (ko)
Inventor
박민우
김주영
Original Assignee
주식회사 크라우드웍스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 크라우드웍스 filed Critical 주식회사 크라우드웍스
Priority to KR1020200066135A priority Critical patent/KR102183838B1/en
Application granted granted Critical
Publication of KR102183838B1 publication Critical patent/KR102183838B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0283Price estimation or determination
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Development Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Business, Economics & Management (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • Educational Administration (AREA)
  • Operations Research (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a method for adjusting the unit cost of a project job using a job for verification of a crowdsourcing-based project for generating artificial intelligence learning data which adjusts the job unit cost of a project in accordance with the evaluated competence of workers. The method comprises: a step of assigning a plurality of jobs to a plurality of workers to request the workers to perform the jobs; a step of receiving a plurality of job results from the plurality of workers; a step of assigning the plurality of job results to a plurality of inspectors to request the inspectors to inspect the job results; a step of receiving inspection pass or rejection as a plurality of inspection results for the plurality of job results from the plurality of inspectors; a step of extracting inspection-passing job results satisfying a prescribed condition to generate a job pool for verification; a step of assigning jobs for verification included in the job pool for verification to the plurality of workers to request the workers to perform the jobs; a step of receiving job results for verification from the plurality of workers; a step of calculating average job performing time (hereafter, first job performing time) for each job for verification of the plurality of workers; a step of comparing the first job performing time and job performing time (hereafter, second job performing time) recorded for each job for verification before calculation of the first job performing time; and a step of adjusting project job unit costs for the plurality of workers by using results of the comparison.

Description

인공지능 학습 데이터 생성을 위한 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법{METHOD FOR ADJUSTING THE UNIT COST OF PROJECT WORK USING VERIFICATION WORK OF CROWDSOURCING BASED PROJECTS FOR ARTIFICIAL INTELLIGENCE TRAINING DATA GENERATION}{METHOD FOR ADJUSTING THE UNIT COST OF PROJECT WORK USING VERIFICATION WORK OF CROWDSOURCING BASED PROJECTS FOR ARTIFICIAL INTELLIGENCE TRAINING DATA GENERATION}

본 발명은 인공지능 학습 데이터 생성을 위한 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법에 관한 것이다.The present invention relates to a method for adjusting project work cost using a crowdsourcing-based project verification task for generating artificial intelligence learning data.

최근, 기업 활동의 일부 과정에 일반 대중을 참여시키는 크라우드소싱 기반으로 많은 양의 데이터를 수집 및 가공하는 기업들이 늘고 있다. 즉, 기업은 하나의 프로젝트를 오픈하여 일반 대중, 즉 작업자가 해당 프로젝트에 참여하게 함으로써, 작업자에 의해 완료된 작업 결과를 통해 필요한 정보를 수집하게 된다.Recently, more and more companies collect and process large amounts of data on a crowdsourcing basis that engages the general public in some process of corporate activities. In other words, by opening a project and allowing the general public, that is, workers to participate in the project, necessary information is collected through the work results completed by the workers.

이때, 기업은 보다 신뢰도가 높은 정보를 수집하기 위해, 작업자에 의해 완료된 작업 결과를 검수자에게 배정하여 검수 작업을 수행하도록 한다.At this time, in order to collect more reliable information, the company assigns the work result completed by the worker to the inspector to perform the inspection work.

구체적으로, 하나의 프로젝트가 오픈되면, 복수의 작업자 각각에게 복수의 작업이 배정된다. 각각의 작업자는 배정받은 복수의 작업을 수행하고, 작업 결과를 제공한다. 이후, 복수의 검수자 각각에게 작업 결과에 대한 복수의 검수 작업이 배정되고, 각각의 검수자는 배정받은 복수의 검수 작업을 수행하게 된다.Specifically, when one project is opened, a plurality of tasks are assigned to each of the plurality of workers. Each worker performs a plurality of tasks assigned to it, and provides the task results. Thereafter, a plurality of inspection tasks are assigned to each of the plurality of inspectors, and each inspector performs a plurality of inspection tasks assigned to them.

한편, 프로젝트가 진행될수록 작업자들은 프로젝트에 속한 작업에 대하여 더욱 능숙해진다. On the other hand, as the project progresses, workers become more proficient in the tasks belonging to the project.

하지만, 프로젝트 작업단가는 이러한 작업자들의 능숙도를 고려하지 않고 있으며, 프로젝트의 오픈시 단가와 프로젝트의 후반시 단가가 서로 동일하게 책정되어 있는 상태이다.However, the project work cost does not take into account the proficiency level of these workers, and the unit price at the time of opening the project and the unit price at the second half of the project are set equally.

즉, 프로젝트의 최초 작업단가는 능숙하지 않은 초기 작업자에 맞추어 설정되는 경우가 대부분이며, 이들을 기준으로 단위 시간당 기준 임금이 지급되도록 설정되는데, 이 경우 프로젝트 후반이 될수록 단위 시간당 기준 임금을 훨씬 초과하는 수익을 얻는 작업자들이 많아지게 된다.That is, in most cases, the initial unit cost of a project is set according to the initial worker who is not skilled, and based on these, the standard wage per unit time is set to be paid. In this case, the profit that far exceeds the standard wage per unit time in the latter half of the project. There will be many workers who get it.

이는 프로젝트 최초 작업단가가 잘못 책정됨에 따른 결과로서 의뢰자에게는 큰 부담이 되므로, 프로젝트가 진행될수록 작업자들이 능숙해지는 것으로 고려하여 프로젝트 작업단가를 변경할 필요성이 있다.This is a result of incorrectly setting the initial work cost of the project, and it is a great burden to the client. Therefore, it is necessary to change the project work cost considering that the workers become more proficient as the project progresses.

공개특허공보 제10-2014-0095956호, 2014.08.04.Unexamined Patent Publication No. 10-2014-0095956, 2014.08.04.

본 발명이 해결하고자 하는 과제는 프로젝트의 진행 중에 검증용 작업을 생성하여 작업자들에게 제공하고, 검증용 작업에 대한 작업 수행 시간을 체크하여, 평가된 작업자들의 능숙도에 따라 프로젝트의 작업단가를 조절하는 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법을 제공하는 것이다.The problem to be solved by the present invention is to create a verification task during the progress of the project and provide it to the workers, check the work execution time for the verification task, and adjust the work unit cost of the project according to the proficiency of the evaluated workers. It is to provide a method of controlling the cost of project work using the verification work of crowdsourcing-based projects.

다만, 본 발명이 해결하고자 하는 과제는 상기된 바와 같은 과제로 한정되지 않으며, 또다른 과제들이 존재할 수 있다.However, the problem to be solved by the present invention is not limited to the problem as described above, and other problems may exist.

상술한 과제를 해결하기 위한 본 발명의 일 면에 따른 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법은 크라우드소싱 기반 프로젝트(이하, "프로젝트")의 복수의 작업을 복수의 작업자에게 배정하여 작업 수행을 요청하는 단계; 상기 복수의 작업자로부터 복수의 작업 결과를 입력받는 단계; 상기 복수의 작업 결과를 복수의 검수자에게 배정하여 검수 수행을 요청하는 단계; 상기 복수의 검수자로부터 상기 복수의 작업 결과에 대한 복수의 검수 결과로 검수 통과 또는 반려를 입력받는 단계; 소정의 시간 구간 동안의 상기 복수의 작업 결과에 대한 복수의 검수 결과 중, 소정의 조건을 만족하는 검수 통과된 작업 결과를 추출하여 검증용 작업 풀을 생성하는 단계; 상기 검증용 작업 풀에 포함된 검증용 작업을 상기 복수의 작업자에게 배정하여 작업 수행을 요청하는 단계; 상기 복수의 작업자로부터 검증용 작업 결과를 입력받는 단계; 상기 복수의 작업자의 각 검증용 작업에 대한 평균 작업 수행 시간(이하, "제1 작업 수행 시간")을 산출하는 단계; 상기 제1 작업 수행 시간과, 상기 제1 작업 수행 시간의 산출 이전에 상기 각 검증용 작업에 대하여 기록된 작업 수행 시간(이하, "제2 작업 수행 시간)을 비교하는 단계; 및 상기 비교 결과를 이용하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계를 포함한다. 이때, 상기 제1 작업 수행 시간과 상기 제2 작업 수행 시간을 비교하는 단계는, 상기 복수의 작업자의 복수의 검증용 작업에 대한 제1 작업 수행 시간과 제2 작업 수행 시간의 각 편차를 산출하는 단계를 포함하고, 상기 비교 결과를 이용하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계는, 상기 산출된 각 편차의 평균 값에 기초하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계를 포함한다. In order to solve the above-described problems, a method for adjusting project work cost using a work for verifying a crowdsourcing-based project according to an aspect of the present invention is to perform a plurality of tasks of a crowdsourcing-based project (hereinafter, "project") to a plurality of workers. Assigning and requesting to perform a task; Receiving a plurality of job results from the plurality of workers; Assigning the plurality of work results to a plurality of inspectors and requesting to perform inspection; Receiving an inspection pass or rejection as a plurality of inspection results for the plurality of work results from the plurality of inspectors; Generating a work pool for verification by extracting a work result that has passed an inspection that satisfies a predetermined condition from among a plurality of inspection results for the plurality of work results during a predetermined time period; Allocating a verification task included in the verification task pool to the plurality of workers and requesting the task to be performed; Receiving verification results from the plurality of workers; Calculating an average task execution time (hereinafter, "first task execution time") for each verification task of the plurality of workers; Comparing the first task execution time with the task execution time (hereinafter, "second task execution time) recorded for each of the verification tasks before calculation of the first task execution time; And the comparison result And adjusting the project work unit cost for the plurality of workers by using the method, wherein the comparing of the first work execution time and the second work execution time includes a plurality of verification tasks of the plurality of workers. Comprising the step of calculating each deviation between the first task execution time and the second task execution time for, and adjusting the project work unit cost for the plurality of workers using the comparison result, the calculated deviation And adjusting the project work unit cost for the plurality of workers based on the average value of.

본 발명의 일부 실시예에서, 상기 소정의 조건은, 상기 검수자의 검수 소요 시간을 기준으로 하는 소정의 순위를 만족하는 조건일 수 있다.In some embodiments of the present invention, the predetermined condition may be a condition that satisfies a predetermined ranking based on the inspection time required by the inspector.

본 발명의 일부 실시예에서, 상기 검증용 작업 풀을 생성하는 단계는, 상기 검수 통과된 작업 결과를 검수한 검수자와 상이한 하나 이상의 타 검수자에게 재검수를 요청하는 단계; 및 상기 타 검수자에 의한 재검수 통과된 작업 결과를 상기 검증용 작업 풀에 추가시키는 단계를 포함할 수 있다.In some embodiments of the present invention, the step of generating the work pool for verification may include: requesting re-review from one or more other inspectors different from the inspector who inspected the inspection-passed work result; And adding the work result that has passed the re-check by the other inspector to the work pool for verification.

본 발명의 일부 실시예에서, 상기 검증용 작업을 복수의 작업자에게 배정하여 작업 수행을 요청하는 단계는, 상기 프로젝트에 포함된 전체 작업 중 소정의 비율 이상의 작업에 대한 작업 결과가 제출된 시점 이후부터 상기 검증용 작업을 복수의 작업자에게 배정하여 작업 수행을 요청할 수 있다.In some embodiments of the present invention, the step of allocating the verification task to a plurality of workers and requesting the task to be performed may be performed from a point in time after the task result for tasks of a predetermined ratio or more among all tasks included in the project is submitted. The verification work may be assigned to a plurality of workers and requested to perform the work.

본 발명의 일부 실시예에서, 상기 복수의 작업자의 각 검증용 작업에 대한 제1 작업 수행 시간을 산출하는 단계는, 상기 복수의 작업자 중 작업 수행 건수가 n건(단, n은 1이상의 자연수) 미만인 작업자의 상기 검증용 작업에 대한 제1 작업 수행 시간은 배제시킬 수 있다.In some embodiments of the present invention, the step of calculating the first task execution time for each verification task of the plurality of workers includes n number of tasks performed among the plurality of workers (where n is a natural number of 1 or more) Less than the operator's first task execution time for the verification task can be excluded.

본 발명의 일부 실시예는, 상기 복수의 검수 결과를 기반으로 상기 검증용 작업 풀에 포함된 검증용 작업에 대한 반려율을 산출하는 단계 및 상기 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업에 대한 제1 작업 수행 시간을 배제시키는 단계를 더 포함할 수 있다.Some embodiments of the present invention include calculating a rejection rate for a verification job included in the verification job pool based on the plurality of inspection results, and a verification job in which the calculated rejection rate is greater than or equal to a preset rejection rate It may further include the step of excluding the first task execution time for.

본 발명의 일부 실시예에서, 상기 반려율이 기 설정된 반려율 이상인 검증용 작업에 대한 제1 작업 수행 시간을 배제시키는 단계는, 상기 제1 작업 수행 시간과 상기 제2 작업 수행 시간의 편차가 기 설정된 편차 이상인 경우, 상기 제1 작업 수행 시간을 배제시킬 수 있다.In some embodiments of the present invention, the step of excluding the first task execution time for the verification task in which the rejection rate is equal to or greater than a preset rejection rate may include a deviation between the first task execution time and the second task execution time. If the deviation is greater than or equal to the set deviation, the first task execution time may be excluded.

본 발명의 일부 실시예에서, 상기 비교 결과를 이용하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계는, 상기 제1 작업 수행 시간의 전체 평균 값이 상기 제2 작업 수행 시간의 전체 평균 값보다 더 짧은 시간을 갖는 경우, 상기 각 편차의 평균 값에 대응되는 비율만큼 상기 프로젝트의 작업단가를 감소시키는 단계; 및 상기 제1 작업 수행 시간의 전체 평균 값이 상기 제2 작업 수행 시간의 전체 평균 값보다 더 긴 시간을 갖는 경우, 상기 각 편차의 평균 값에 대응되는 비율만큼 상기 프로젝트의 작업단가를 증가시키는 단계를 포함할 수 있다.In some embodiments of the present invention, the step of adjusting the project work unit cost for the plurality of workers using the comparison result, the total average value of the first work execution time is the total average value of the second work execution time Reducing the work cost of the project by a ratio corresponding to the average value of each deviation when it has a shorter time; And when the total average value of the first work execution time has a longer time than the total average value of the second work execution time, increasing the work unit cost of the project by a ratio corresponding to the average value of each deviation. It may include.

본 발명의 일부 실시예는, 상기 복수의 작업자에 대한 프로젝트 작업단가가 조절된 이후, 상기 검증용 풀의 검증용 작업에 대하여 기록된 제2 작업 수행 시간을 상기 복수의 작업자의 각 검증용 작업에 대한 평균 작업 수행 시간인 제1 작업 수행 시간으로 갱신하는 단계를 더 포함할 수 있다.In some embodiments of the present invention, after the project work cost for the plurality of workers is adjusted, the second work execution time recorded for the verification work of the verification pool is applied to each verification work of the plurality of workers. It may further include updating to the first task execution time, which is the average task execution time for.

상술한 과제를 해결하기 위한 본 발명의 다른 면에 따른 컴퓨터 프로그램은, 하드웨어인 컴퓨터와 결합되어 상기 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법을 실행하며, 컴퓨터 판독가능 기록매체에 저장된다.A computer program according to another aspect of the present invention for solving the above-described problem is combined with a computer that is hardware to execute a method of adjusting the project work unit cost using the work for verification of the crowdsourcing-based project, and is stored in a computer-readable recording medium. Is saved.

본 발명의 기타 구체적인 사항들은 상세한 설명 및 도면들에 포함되어 있다.Other specific details of the present invention are included in the detailed description and drawings.

상술한 본 발명에 의하면, 프로젝트가 진행됨에 따라 작업자들의 능숙도가 변하여, 최초 산정된 프로젝트 작업단가가 현재 시점을 기준으로 부적절한 경우, 변경된 작업자들의 능숙도를 고려하여 프로젝트의 작업단가를 조절할 수 있다는 장점이 있다.According to the present invention, the proficiency level of workers changes as the project progresses, and if the initially calculated project work unit price is inappropriate from the current point in time, it is possible to adjust the work unit cost of the project in consideration of the proficiency level of the changed workers. have.

특히, 최초 산정된 프로젝트 작업단가에 대한 조절뿐만 아니라, 프로젝트 작업단가가 조절된 이후에도 현재 시점을 기준으로 이전 시점보다 작업자들의 능숙도가 향상되었는지 여부를 판단하고 이를 기반으로 프로젝트 작업단가를 조절할 수 있다.In particular, it is possible not only to adjust the initially calculated project unit cost, but also to determine whether the proficiency of workers has improved from the previous point based on the current point of time even after the project unit cost is adjusted, and adjust the project unit cost based on this.

본 발명의 효과들은 이상에서 언급된 효과로 제한되지 않으며, 언급되지 않은 또 다른 효과들은 아래의 기재로부터 통상의 기술자에게 명확하게 이해될 수 있을 것이다.The effects of the present invention are not limited to the effects mentioned above, and other effects not mentioned will be clearly understood by those skilled in the art from the following description.

도 1은 본 발명의 일 실시예에 따른 크라우드소싱 서비스의 개념도이다.
도 2는 본 발명의 일 실시예에 따른 크라우드소싱 기반의 프로젝트의 진행 프로세스를 설명하기 위한 흐름도이다.
도 3은 본 발명의 일 실시예에 따른 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법의 순서도이다.
도 4 및 도 5는 검증용 작업을 생성하는 내용을 설명하기 위한 도면이다.
검증용 작업은 프로젝트의 복수의 작업자에 의해 실제 수행된 실전용 작업을 기반으로 생성된다.
도 6은 검증용 작업에 대한 제1 및 제2 작업 수행 시간을 산출 및 비교하는 내용을 설명하기 위한 도면이다.
도 7은 제2 작업 수행 시간을 갱신하는 내용을 설명하기 위한 도면이다.
도 8은 본 발명의 일 실시예에 따른 프로젝트 작업단가 조절 장치를 설명하기 위한 도면이다.
1 is a conceptual diagram of a crowdsourcing service according to an embodiment of the present invention.
2 is a flowchart illustrating a crowdsourcing-based project progress process according to an embodiment of the present invention.
3 is a flowchart of a method for adjusting a project work cost using a work for verification of a crowdsourcing-based project according to an embodiment of the present invention.
4 and 5 are views for explaining contents of generating a verification task.
The verification work is created based on the actual work performed by the multiple workers of the project.
6 is a view for explaining the calculation and comparison of the first and second task execution times for the verification task.
7 is a diagram for explaining content of updating a second task execution time.
8 is a view for explaining a project work unit cost adjustment device according to an embodiment of the present invention.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되어 있는 실시예들을 참조하면 명확해질 것이다. 그러나, 본 발명은 이하에서 개시되는 실시예들에 제한되는 것이 아니라 서로 다른 다양한 형태로 구현될 수 있으며, 단지 본 실시예들은 본 발명의 개시가 완전하도록 하고, 본 발명이 속하는 기술 분야의 통상의 기술자에게 본 발명의 범주를 완전하게 알려주기 위해 제공되는 것이며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다. Advantages and features of the present invention, and a method of achieving them will become apparent with reference to the embodiments described below in detail together with the accompanying drawings. However, the present invention is not limited to the embodiments disclosed below, but may be implemented in a variety of different forms, only the present embodiments are intended to complete the disclosure of the present invention, It is provided to fully inform the technician of the scope of the present invention, and the present invention is only defined by the scope of the claims.

본 명세서에서 사용된 용어는 실시예들을 설명하기 위한 것이며 본 발명을 제한하고자 하는 것은 아니다. 본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 명세서에서 사용되는 "포함한다(comprises)" 및/또는 "포함하는(comprising)"은 언급된 구성요소 외에 하나 이상의 다른 구성요소의 존재 또는 추가를 배제하지 않는다. 명세서 전체에 걸쳐 동일한 도면 부호는 동일한 구성 요소를 지칭하며, "및/또는"은 언급된 구성요소들의 각각 및 하나 이상의 모든 조합을 포함한다. 비록 "제1", "제2" 등이 다양한 구성요소들을 서술하기 위해서 사용되나, 이들 구성요소들은 이들 용어에 의해 제한되지 않음은 물론이다. 이들 용어들은 단지 하나의 구성요소를 다른 구성요소와 구별하기 위하여 사용하는 것이다. 따라서, 이하에서 언급되는 제1 구성요소는 본 발명의 기술적 사상 내에서 제2 구성요소일 수도 있음은 물론이다.The terms used in the present specification are for describing exemplary embodiments and are not intended to limit the present invention. In this specification, the singular form also includes the plural form unless specifically stated in the phrase. As used in the specification, “comprises” and/or “comprising” do not exclude the presence or addition of one or more other elements other than the mentioned elements. Throughout the specification, the same reference numerals refer to the same elements, and “and/or” includes each and all combinations of one or more of the mentioned elements. Although "first", "second", and the like are used to describe various elements, it goes without saying that these elements are not limited by these terms. These terms are only used to distinguish one component from another component. Therefore, it goes without saying that the first component mentioned below may be the second component within the technical idea of the present invention.

다른 정의가 없다면, 본 명세서에서 사용되는 모든 용어(기술 및 과학적 용어를 포함)는 본 발명이 속하는 기술분야의 통상의 기술자에게 공통적으로 이해될 수 있는 의미로 사용될 수 있을 것이다. 또한, 일반적으로 사용되는 사전에 정의되어 있는 용어들은 명백하게 특별히 정의되어 있지 않는 한 이상적으로 또는 과도하게 해석되지 않는다.Unless otherwise defined, all terms (including technical and scientific terms) used in the present specification may be used as meanings that can be commonly understood by those of ordinary skill in the art to which the present invention belongs. In addition, terms defined in a commonly used dictionary are not interpreted ideally or excessively unless explicitly defined specifically.

이하, 첨부된 도면을 참조하여 본 발명의 실시예를 상세하게 설명한다. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명의 일 실시예에 따른 크라우드소싱 서비스의 개념도이다.1 is a conceptual diagram of a crowdsourcing service according to an embodiment of the present invention.

도 1을 참조하면, 크라우드소싱 서비스는 의뢰자(10), 서비스 제공 업체(20) 및 대중(30)으로 구성되어 수행된다.Referring to FIG. 1, a crowdsourcing service is performed by being composed of a client 10, a service provider 20, and a public 30.

의뢰자(10)는 크라우드소싱 기반의 프로젝트(이하, 프로젝트)를 의뢰하는 기업이나 개인을 의미한다.The sponsor 10 refers to a company or individual who requests a crowdsourcing-based project (hereinafter, referred to as a project).

의뢰자(10)는 인공지능 학습데이터의 생성을 위한 소스 데이터의 수집 또는 데이터 어노테이션 등을 목적으로 프로젝트를 의뢰한다. 프로젝트를 통해서 생성된 데이터는 지도 학습, 비지도 학습, 강화 학습 등의 임의의 기계 학습의 학습데이터로 활용될 수 있다. 소스 데이터의 수집은 녹음된 음성 수집, 사진 수집 등 가공되지 않은 데이터를 수집하는 것을 의미한다. 데이터 어노테이션은 텍스트, 사진, 비디오 등의 소스 데이터에 관련 주석 데이터를 입력하는 것을 의미한다. 예들 들어, 데이터 어노테이션은 주어진 지문에서 개체를 찾는 것, 유사한 문장을 찾는 것 등이 있을 수 있으나 이에 제한되지 않는다. 한편, 전술한 프로젝트의 종류는 일 실시예에 불과하며, 의뢰자의 설계에 따라 다양한 프로젝트가 본 발명에서 취급될 수 있다.The requester 10 requests a project for the purpose of collecting source data or annotating data for generating artificial intelligence learning data. The data generated through the project can be used as learning data for arbitrary machine learning such as supervised learning, unsupervised learning, and reinforcement learning. Collection of source data refers to collecting raw data such as recorded voice collection and photo collection. Data annotation refers to inputting relevant annotation data into source data such as text, photos, and videos. For example, the data annotation may include finding an entity in a given fingerprint or finding a similar sentence, but is not limited thereto. Meanwhile, the types of the above-described projects are only one embodiment, and various projects may be handled in the present invention according to the design of the client.

서비스 제공 업체(20)는 크라우드소싱 서비스를 제공하는 기업을 의미한다.The service provider 20 refers to a company that provides crowdsourcing services.

서비스 제공 업체(20)는 의뢰자(10)로부터 제품 또는 서비스에 대한 프로젝트를 의뢰 받으면, 해당 프로젝트에 대한 작업을 일반 대중(30)에게 배정하여 대중(30)으로부터 작업 결과를 제공받는다. 이후, 작업 결과를 기반으로 추출된 최종 산출물을 의뢰자(10)에게 제공한다.When the service provider 20 receives a request for a project for a product or service from the client 10, the service provider 20 allocates a task for the project to the general public 30 and receives the work result from the public 30. Thereafter, the final product extracted based on the work result is provided to the client 10.

이때, 서비스 제공 업체(20)는 크라우드소싱 플랫폼(이하, 플랫폼)을 통해 의뢰자(10) 및 대중(30)에게 크라우드소싱 서비스를 제공한다. 즉, 서비스 제공 업체(20)는 의뢰자(10)로부터 프로젝트를 의뢰 받으면, 플랫폼에 프로젝트를 오픈한다. 이후, 대중(30)으로부터 오픈된 프로젝트에 대한 작업 결과를 제공받으면, 해당 프로젝트를 플랫폼 상에서 종료하고, 최종 산출물을 추출하여 의뢰자(10)에게 제공할 수 있다.At this time, the service provider 20 provides a crowdsourcing service to the client 10 and the public 30 through a crowdsourcing platform (hereinafter, the platform). That is, when the service provider 20 receives a request for a project from the client 10, the service provider 20 opens the project on the platform. Thereafter, when the work result for the open project is received from the public 30, the project is terminated on the platform, and the final product may be extracted and provided to the client 10.

대중(30)은 플랫폼에 오픈된 프로젝트에 참여하는 일반 대중을 의미한다. 여기서, 대중(30)은 서비스 제공 업체(20)가 제공하는 애플리케이션 또는 웹사이트 등을 통해 플랫폼에 오픈된 프로젝트에 참여할 수 있다. The public 30 refers to the general public participating in the project open on the platform. Here, the public 30 may participate in a project opened on the platform through an application or website provided by the service provider 20.

대중(30)은 작업자(32) 및 검수자(34)로 구성된다.The public 30 is composed of a worker 32 and an inspector 34.

작업자(32)는 플랫폼에 오픈된 복수의 프로젝트 중 특정 프로젝트에 참여를 결정한다. 이후, 작업자(32)는 소스 데이터의 수집 또는 데이터 어노테이션 등의 작업을 수행하고, 이를 플랫폼에 전송한다.The worker 32 decides to participate in a specific project among a plurality of projects open on the platform. Thereafter, the operator 32 performs an operation such as collection of source data or data annotation, and transmits it to the platform.

검수자(34)는 플랫폼에 오픈된 복수의 프로젝트 중 특정 프로젝트에 참여를 결정한다. 이후, 검수자(34)는 작업자(32)가 수행한 작업 결과에 대한 검수를 수행한다. 검수자(34)는 검수 수행 결과로서, 검수 통과 처리 또는 반려 처리를 할 수 있고, 반려 처리시 반려 사유를 입력할 수 있다. 검수 통과의 경우 재작업과 이로 인한 재검수가 필요하지 않으므로, 검수 통과는 검수 완료와 동일한 의미를 가진다.The inspector 34 decides to participate in a specific project among a plurality of projects open on the platform. Thereafter, the inspector 34 inspects the result of the work performed by the operator 32. As a result of performing the inspection, the inspector 34 may perform inspection pass processing or rejection processing, and input a rejection reason during rejection processing. In the case of passing the inspection, it is not necessary to rework and re-examination due to this, so passing inspection has the same meaning as completion of inspection.

도 2는 본 발명의 일 실시예에 따른 크라우드소싱 기반의 프로젝트의 진행 프로세스를 설명하기 위한 흐름도이다. 2 is a flowchart illustrating a crowdsourcing-based project progress process according to an embodiment of the present invention.

먼저, 의뢰자(10)는 서비스 제공 업체(20)로 하나 이상의 프로젝트를 의뢰한다(S11).First, the requester 10 requests one or more projects to the service provider 20 (S11).

이후, 서비스 제공 업체(20)는 의뢰된 프로젝트를 플랫폼 상에 오픈한다(S12). 이때, 서비스 제공 업체(20)는 프로젝트 오픈 전에, 해당 프로젝트의 난이도 등을 고려하여 등급을 결정할 수 있다. 즉, 난이도에 따라 어떤 등급 이상의 대중(30)에게 해당 프로젝트를 노출시킬지를 결정할 수 있다. 이에 따라, 프로젝트의 작업 결과의 신뢰도를 높일 수 있게 된다. Thereafter, the service provider 20 opens the requested project on the platform (S12). At this time, the service provider 20 may determine the grade in consideration of the difficulty of the project before opening the project. That is, depending on the difficulty level, it is possible to determine which level or higher public 30 to expose the project. Accordingly, it is possible to increase the reliability of the work result of the project.

이후, 서비스 제공 업체(20)는 프로젝트의 등급에 따라 해당 등급 이상의 작업자(32)에게 작업을 할당하여 작업 요청한다(S13).Thereafter, the service provider 20 requests the work by assigning the work to the workers 32 of the corresponding level or higher according to the level of the project (S13).

이후, 작업자(32)는 할당된 작업을 수행하게 된다(S14). 이때, 작업자(32)는 어떤 이유에 의해 작업 자체가 불가능한 작업에 대해서는 작업을 수행하지 않고 작업 불가 사유를 입력할 수 있다. Thereafter, the worker 32 performs the assigned task (S14). In this case, the worker 32 may input the reason for the inability to work without performing the work for a work in which the work itself is impossible for some reason.

이후, 서비스 제공 업체(20)는 작업자(32)로부터 작업 결과를 제공받고(S15), 해당 작업 결과에 대한 검수 작업을 검수자(34)에게 할당하여 검수 요청한다(S16).Thereafter, the service provider 20 receives the work result from the worker 32 (S15), and assigns the work result to the inspector 34 to request the inspection (S16).

마찬가지로 본 발명의 일 실시예는 프로젝트의 난이도에 따라 설정된 등급 또는 검수자(34)의 자격 요건에 따라 수행 중인 전체 프로젝트 중 적합한 프로젝트만 검수자(34)에게 노출되게끔 할 수 있다.Similarly, according to an embodiment of the present invention, only a suitable project may be exposed to the inspector 34 out of the total projects being performed according to the level set according to the difficulty of the project or the qualification requirements of the inspector 34.

이후, 검수자(34)는 할당된 검수를 수행하게 된다(S17). 이때, 검수자(34)는 작업이 적합하게 수행된 것으로 판단하면 검수 완료를 결정하고, 검수 작업이 잘못된 것으로 판단하면 반려 처리한다. 반려 처리 시, 검수자(34)는 어떤 이유로 작업이 잘못된 것으로 판단했는지에 대한 반려 사유를 입력한다.Thereafter, the inspector 34 performs the assigned inspection (S17). At this time, the inspector 34 determines that the inspection is completed when it is determined that the work has been properly performed, and if it is determined that the inspection operation is wrong, the inspector 34 rejects it. During rejection processing, the inspector 34 inputs the rejection reason for what reason the job was judged to be wrong.

이후, 서비스 제공 업체(20)는 검수자(34)로부터 검수 결과를 제공받는다(S18). Thereafter, the service provider 20 receives the inspection result from the inspector 34 (S18).

검수 결과가 검수 완료인 경우, 서비스 제공 업체(20)는 해당 작업 결과를 유효한 데이터로 사용하여, 이를 기반으로 하여 프로젝트 종료 시 최종 산출물을 추출하게 된다.When the inspection result is the inspection completion, the service provider 20 uses the work result as valid data, and based on this, extracts the final product at the end of the project.

검수 결과가 반려 처리인 경우, 서비스 제공 업체(20)는 내부적으로 검수를 다시 수행하거나, 작업자(32)에게 다시 작업을 배정하여 재작업을 수행하게 할 수도 있다. 재작업시 검수자의 재검수가 필요하다.When the inspection result is rejection processing, the service provider 20 may internally perform the inspection again, or assign the work to the worker 32 again to perform the rework. When reworking, re-examination by an inspector is required.

이후, 서비스 제공 업체(20)는 프로젝트 기간이 종료되거나 충분한 유효 데이터를 확보하게 되면 해당 프로젝트를 종료하고(S19), 확보된 유효 데이터를 기반으로 최종 결과물을 산출하여 의뢰자(10)에게 제공한다(S20).Thereafter, when the project period ends or sufficient valid data is secured, the service provider 20 terminates the project (S19), calculates a final result based on the secured valid data, and provides it to the client 10 ( S20).

이때, 프로젝트 종료 전, 서비스 제공 업체(20)는 작업자(32) 및 검수자(34)의 수행 결과를 평가하고, 평가에 따라 작업 비용 및 검수 비용을 산출하여 작업자(32) 및 검수자(34)에게 지급한다.At this time, before the end of the project, the service provider 20 evaluates the performance results of the worker 32 and the inspector 34, calculates the work cost and the inspection cost according to the evaluation, to the worker 32 and the inspector 34. give.

도 1 및 도 2에서는 단순히 의뢰자(10), 서비스 제공 업체(20), 작업자(32), 검수자(34)로 표현하였으나, 이들은 각 참여자에 의해서 운용되는 스마트폰, 태블릿, PDA, 랩톱, 데스크톱, 서버 등과 같은 컴퓨터 장치 또는 전기 통신 장치를 의미한다.In FIGS. 1 and 2, it is simply expressed as a requester 10, a service provider 20, an operator 32, and an inspector 34, but these are smartphones, tablets, PDAs, laptops, desktops, operated by each participant. It means a computer device such as a server or a telecommunication device.

이하에서는 도 3 내지 도 7을 참조하여 본 발명의 일 실시예에 따른 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법을 설명하도록 한다.Hereinafter, a method of adjusting a project work unit cost using a work for verifying a crowdsourcing-based project according to an embodiment of the present invention will be described with reference to FIGS. 3 to 7.

도 3은 본 발명의 일 실시예에 따른 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법의 순서도이다. 3 is a flowchart of a method for adjusting a project work cost using a work for verification of a crowdsourcing-based project according to an embodiment of the present invention.

한편, 도 3에 도시된 단계들은 서비스 제공 업체(20)에 의해 운영되는 플랫폼 서버(이하, 서버)에 의해 수행되는 것으로 이해될 수 있지만, 이에 제한되는 것은 아니다.Meanwhile, the steps shown in FIG. 3 may be understood as being performed by a platform server (hereinafter, referred to as a server) operated by the service provider 20, but are not limited thereto.

또한, 복수의 작업자(32) 또는 복수의 검수자(34)는 소정의 단말 장치를 이용하여 작업을 수행한다. 작업자(32) 또는 검수자(34)의 단말 장치는 스마트폰, 태블릿, PDA, 랩톱, 데스크톱 등과 같은 컴퓨터 장치 또는 전기 통신 장치일 수 있으나, 이에 제한되는 것은 아니다.In addition, a plurality of workers 32 or a plurality of inspectors 34 perform work using a predetermined terminal device. The terminal device of the operator 32 or the inspector 34 may be a computer device or a telecommunication device such as a smartphone, tablet, PDA, laptop, desktop, etc., but is not limited thereto.

먼저, 도 3을 참조하면 서버는 크라우드소싱 기반의 프로젝트(이하, 프로젝트라 한다)의 복수의 작업을 복수의 작업자(32)에게 배정하여 작업 수행을 요청하고(S105), 복수의 작업자(32)로부터 복수의 작업 결과를 입력받는다(S110).First, referring to FIG. 3, the server assigns a plurality of tasks of a crowdsourcing-based project (hereinafter referred to as a project) to a plurality of workers 32 and requests the task to be performed (S105), and a plurality of workers 32 A plurality of work results are inputted from (S110).

여기에서, 하나의 프로젝트에는 복수의 작업이 포함될 수 있으며, 복수의 작업은 종류에 따라 복수의 태스크로 그룹화될 수 있고, 또는 각각의 작업이 서로 다른 종류의 작업일 수도 있으며, 동일한 작업일 수도 있지만, 이에 제한되는 것은 아니다.Here, one project may contain multiple jobs, and the plurality of jobs may be grouped into a plurality of tasks according to their type, or each job may be a different type of job or the same job. , But is not limited thereto.

다음으로, 서버는 복수의 작업 결과를 복수의 검수자(34)에게 배정하여 검수 수행을 요청하고(S115), 복수의 검수자(34)로부터 복수의 작업 결과에 대한 복수의 검수 결과를 입력받는다(S120). 이때, 검수자(34)는 복수의 검수 결과로 검수 통과 또는 반려를 입력할 수 있다.Next, the server assigns the plurality of work results to the plurality of inspectors 34 to request the inspection performance (S115), and receives a plurality of inspection results for the plurality of job results from the plurality of inspectors 34 (S120). ). At this time, the inspector 34 may input the inspection pass or rejection as a plurality of inspection results.

다음으로, 서버는 복수의 작업 결과에 대한 복수의 검수 결과 중, 소정의 조건을 만족하는 검수 통과된 작업 결과를 추출하여 검증용 작업 풀을 생성한다(S125). Next, the server extracts a job result that has passed the inspection that satisfies a predetermined condition from among the plurality of inspection results for the plurality of job results, and generates a job pool for verification (S125).

참고로, 본 발명의 설명에서 작업자(32)를 검증하기 위한 용도의 작업을 '검증용 작업'이라 하고, 이에 대한 작업 결과를 '검증용 작업 결과'라 하도록 한다. 이와 구별되도록, 작업자(32)가 실제로 작업을 수행하며 프로젝트 결과물로 이용되어야 하는 작업을 '실전용 작업'이라 하고, 이에 대한 작업 결과를 '실전용 작업 결과'라 하도록 한다.For reference, in the description of the present invention, a task for verifying the operator 32 is referred to as a'verification operation', and the result of the operation is referred to as a'verification operation result'. To be distinguished from this, a task that the worker 32 actually performs the task and should be used as a project result is referred to as a'practical-only work', and the work result is referred to as a'practical-only work result'.

일 실시예로, 서버는 소정의 구간 동안의 복수의 작업 결과에 대한 복수의 검수 결과 중, 소정의 조건을 만족하는 검수 통과된 작업 결과를 추출하여 검증용 작업 풀에 포함시킬 수 있다.In an embodiment, the server may extract, from among a plurality of inspection results for a plurality of job results during a predetermined period, a job result that has passed the inspection that satisfies a predetermined condition and includes it in the verification job pool.

이는, 제1 시간 구간 동안(t0)에서 작업을 수행한 제1 작업자의 작업 결과를 이용해서 제2 시간 구간(t1)에서 작업을 수행할 복수의 작업자(32)를 검증하고, 마찬가지로 제2 시간 구간(t1)에서 작업을 수행한 제2 작업자의 작업 결과를 이용해서 제3 시간 구간(t2)에서 작업을 수행할 복수의 작업자(32)를 검증하는 구조이다.This is to verify the plurality of workers 32 who will perform the work in the second time period (t1) by using the work result of the first worker who performed the work in the first time period (t0), and similarly, the second time This is a structure in which a plurality of workers 32 who will perform the work in the third time period t2 are verified using the work result of the second worker who performed the work in the section t1.

이하, 도 4 및 도 5를 참조하여 검증용 작업에 대하여 구체적으로 설명하도록 한다.Hereinafter, the verification operation will be described in detail with reference to FIGS. 4 and 5.

도 4 및 도 5는 검증용 작업을 생성하는 내용을 설명하기 위한 도면이다.4 and 5 are views for explaining contents of generating a verification task.

검증용 작업은 프로젝트의 복수의 작업자(32)에 의해 실제 수행된 실전용 작업을 기반으로 생성된다. The verification work is generated based on the practical work actually performed by the plurality of workers 32 of the project.

먼저 도 4를 참조하면, 복수의 작업자(32)에 의해 수행된 실전용 작업에 대한 작업 결과(P1)가 입력되면, 실전용 작업 결과(P1)는 검수자(34)에게 배정되고, 검수자(34)는 실전용 작업 결과(P1)에 대하여 검수를 수행한다. First, referring to FIG. 4, when a work result (P1) for a practical work performed by a plurality of workers 32 is input, the practical work result (P1) is assigned to the inspector 34, and the inspector 34 ) Performs an inspection on the actual work result (P1).

그 다음 실전용 작업 결과(P1)에 대한 검수자(34)의 검수가 완료되면, 서버는 복수의 검수 결과 중 검수 통과된 작업 결과(P2)를 추출한다. 본 발명의 일 실시예에서 검증용 작업은 검수 통과, 즉 최초 검수 통과나 재검수 통과된 작업을 기반으로 생성되므로, 검증용 작업은 정답이 검수 통과나 반려로 정해지며, 이러한 정답의 입력 여부를 통해 작업자(32)를 검증하게 된다.Then, when the inspection by the inspector 34 on the practical work result P1 is completed, the server extracts the inspection result P2 from among the plurality of inspection results. In an embodiment of the present invention, since the verification task is generated based on the verification pass, that is, the initial verification pass or re-review pass, the verification task is determined as the correct answer as the verification pass or rejection, and whether or not the correct answer is entered Through this, the operator 32 is verified.

그 다음, 서버는 검수 통과된 작업 결과(P2) 중 소정의 조건을 만족하는 검수 통과된 작업 결과(P3)를 추출하여 검증용 작업 풀로 생성한다. 이때, 소정의 조건의 일 실시예로는 검수자(34)의 검수 소요 시간을 기준으로 하는 소정의 순위를 만족하는 것일 수 있다.Then, the server extracts the inspection-passed job result P3 that satisfies a predetermined condition among the inspection-passed job results P2 and generates a verification job pool. In this case, as an embodiment of the predetermined condition, a predetermined ranking based on the inspection time required by the inspector 34 may be satisfied.

즉, 서버는 검수 통과된 실전용 작업 결과(P2)들에 대하여, 검수에 소요된 시간이 긴 순서대로 정렬하고, 이 중에서 소정의 순위에 해당하는 실전용 작업 결과(P3)만을 추출한다.That is, the server sorts the actual work results P2 that have passed the inspection in the order in which the time required for the inspection is long, and extracts only the practical work results P3 corresponding to a predetermined priority among them.

여기에서 검수에 소요된 시간이 길다는 것은 다른 검수자(34)에 비하여 성실하게 검수를 수행할 가능성이 높으며 이는 검수 결과에 오류가 있을 확률이 적다는 것을 의미하므로, 검수에 소요된 시간이 긴 실전용 작업 결과(P3)를 추출하여 검증용 작업 풀에 포함시킴이 바람직하다.Here, the long time spent for inspection means that the inspection is more likely to be faithfully performed compared to other inspectors 34, and this means that the probability of errors in the inspection results is low. It is desirable to extract the exclusive work result (P3) and include it in the work pool for verification.

이때, 소정의 순위는 서버나 관리자, 또는 의뢰자(10)에 의해 미리 설정되어 있을 수 있으며, 소정의 순위는 개수 단위뿐 아니라 시간 단위로도 추출할 수 있다.In this case, the predetermined ranking may be set in advance by the server, the administrator, or the requester 10, and the predetermined ranking may be extracted not only in units of number but also in units of time.

이와 같이 소정의 조건을 만족하는 검수 통과된 작업 결과(P3)는 곧바로 검증용 작업 풀에 포함될 수 있다.As described above, the inspection result P3 that satisfies the predetermined condition may be immediately included in the verification job pool.

하지만, 실전용 작업 결과를 검수한 검수자(34) 역시 오류를 범할 가능성이 있으므로, 작업자(32)에게 보다 검증된 작업을 제공하기 위해 다른 검수자(34)로 하여금 검수 통과된 작업 결과에 대한 재검수를 수행하도록 한 후, 재검수 통과된 실전용 작업 결과를 검증용 작업 풀에 포함시킬 수 있다.However, since there is a possibility that the inspector 34 who has inspected the actual work result may also make an error, another inspector 34 re-examines the inspected work result in order to provide a more verified work to the operator 32. After performing the re-examination, it is possible to include the results of the practical work that has passed the re-examination in the work pool for verification.

즉, 서버는 복수의 작업 결과(P1)에 대하여 검수 통과된 작업 결과(P2) 중, 소정의 조건을 만족하는 검수 통과된 작업 결과(P3)를 추출하면, 해당 작업 결과(P3)를 검수한 검수자(34)와 상이한 하나 이상의 검수자(34)에게 재검수를 요청하고(P4), 재검수를 한 검수자 의해 검수 통과된 작업 결과(P5)를 검증용 작업(P6)으로 생성할 수 있다.That is, if the server extracts the work result (P3) that has passed the inspection and satisfies a predetermined condition among the work results (P2) that have passed the inspection for the plurality of work results (P1), the work result (P3) is inspected. It is possible to request a re-examination from one or more inspectors 34 different from the inspector 34 (P4), and a work result (P5) that has passed the inspection by the inspector who has re-examined may be generated as a verification operation (P6).

도 5를 참조하면, 소정의 순위를 만족하는 실전용 작업 결과가 추출되면, 실전용 작업 결과는 각각 다른 검수자(34)의 추가적인 검수 작업을 거치게 된다.Referring to FIG. 5, when a result of the practical use that satisfies a predetermined priority is extracted, the result of the practical use is subjected to an additional inspection process by different inspectors 34, respectively.

예를 들어, 도 4에서 제1 검수자에 의해 '실전용 작업 결과 1~4(P2)'가 검수 통과된 경우, 이 중에서 소정의 순위에 따라 3개의 '실전용 작업 결과 1~3(P3)'이 추출되고, 3개의 실전용 작업 결과(P3)는 제1 검수자와 상이한 제2 및 제3 검수자에 의해 재검수가 수행된다(P4). 이때, 도 5의 예시에서는 2명의 검수자에 의해 재검수가 수행되는 것으로 도시되어 있으나, 반드시 이에 한정되는 것은 아니다.For example, in FIG. 4, when the first inspector passes the inspection, three'practical work results 1 to 3 (P3) according to a predetermined ranking. 'Is extracted, and the three practical work results (P3) are re-inspected by the second and third inspectors different from the first inspector (P4). In this case, in the example of FIG. 5, it is shown that the re-examination is performed by two inspectors, but is not limited thereto.

제2 및 제3 검수자에 의해 재검수된 결과, 제2 검수자에 의해 '실전용 작업 결과 1, 2'가 검수 통과되었고, 제3 검수자에 의해 '실전용 작업 결과 1'만 검수 통과된 경우, 검수자(34)들 모두에 의해 검수 통과된 '실전용 작업 결과 1(P5)'만이 검증용 작업(P6)으로 검증용 작업 풀에 포함될 수 있다.As a result of re-inspection by the 2nd and 3rd inspectors, if the 2nd inspector passed the inspection and only the'practical work result 1'passed by the third inspector, Only the'practical work result 1 (P5)' that has been inspected by all the inspectors 34 may be included in the verification work pool as the verification work (P6).

이와 같은 검증용 작업 풀이 생성되고 난 이후에는, 실전용 작업 결과의 검수 결과에 대하여 실시간으로 또는 소정의 주기마다 조건 만족 여부를 체크하여 검증용 작업 풀을 업데이트할 수 있다.After the verification work pool is generated, the verification work pool may be updated by checking whether the condition is satisfied in real time or at predetermined intervals with respect to the verification result of the actual work result.

한편, 실전용 작업에 대한 작업 수행이 진행되지 않거나, 소정의 조건을 만족하는 실전용 작업이 없는 상태, 또는 검증용 작업 풀에 포함된 검증용 작업을 모두 작업자(32)에게 배정하여 더 이상 검증용 작업을 배정할 수 없는 상태가 있을 수 있다. 이 경우, 본 발명의 일 실시예는 의뢰자(10)에 의해 미리 준비된 검증용 작업을 검증용 풀에 추가할 수 있으며, 추가되는 시기는 프로젝트의 특정 시기에 한정되지 않는다.On the other hand, the task is not performed for the actual task, there is no actual task that satisfies a predetermined condition, or all the verification tasks included in the verification task pool are assigned to the worker 32 for further verification. There may be conditions in which the dragon task cannot be assigned. In this case, an embodiment of the present invention may add a verification task prepared in advance by the client 10 to the verification pool, and the time to be added is not limited to a specific period of the project.

다시 도 3을 참조하면, 검증용 작업 풀이 생성됨에 따라 서버는 검증용 작업 풀에 포함된 검증용 작업을 복수의 작업자(32)에게 배정하여 작업 수행을 요청하고(S130), 복수의 작업자(32)로부터 검증용 작업 결과를 입력받는다(S135).Referring back to FIG. 3, as the verification task pool is created, the server assigns verification tasks included in the verification task pool to a plurality of workers 32 to request the task performance (S130), and a plurality of workers 32 ) Receives the verification result from (S135).

이때, 검증용 작업은 프로젝트에 포함된 전체 작업 중 소정의 비율 이상의 작업에 대한 작업 결과가 제출된 시점 이후부터 복수의 작업자(32)에게 배정될 수 있다.In this case, the verification work may be assigned to the plurality of workers 32 from a point in time after a work result for a task having a predetermined ratio or more of all tasks included in the project is submitted.

즉, 프로젝트 초반의 경우에는 능숙한 작업자(32)가 나타나는 경우가 드물기 때문에, 검증용 작업을 미리 배정하는 것은 리소스 낭비일 수 있으므로, 프로젝트의 중후반에 해당하는 작업 결과가 제출된 시점 이후부터 검증용 작업의 배정이 이루어짐이 바람직하다.In other words, since proficient workers (32) rarely appear at the beginning of the project, pre-allocation of the verification work may be a waste of resources, so the verification work from the time when the work results corresponding to the mid-to-late part of the project are submitted. It is desirable that the allocation of

하지만, 검증용 작업의 배정 시기는 반드시 이에 한정되는 것은 아니며, 작업자 풀의 능숙도를 주기적으로 체크하기 위하여 프로젝트의 초반부터 배정될 수도 있음은 물론이다.However, the timing of assignment of verification tasks is not necessarily limited thereto, and of course, they may be assigned from the beginning of the project to periodically check the proficiency level of the worker pool.

서버는 복수의 작업자(32)로부터 검증용 작업 결과를 입력받음에 따라, 도 6에 도시된 바와 같이 검증용 작업을 수행한 작업자(32)들의 평균 작업 수행 시간과, 검증용 작업에 대하여 기록된 작업 수행 시간을 산출 및 비교함으로써, 복수의 작업자(32)에 대한 프로젝트 작업단가를 조절할 수 있다.As the server receives the verification work results from the plurality of workers 32, the average work execution time of the workers 32 who have performed the verification work as shown in FIG. 6, and the verification work are recorded. By calculating and comparing the work execution time, it is possible to adjust the project work unit cost for the plurality of workers 32.

도 6은 검증용 작업에 대한 제1 및 제2 작업 수행 시간을 산출 및 비교하는 내용을 설명하기 위한 도면이다.6 is a view for explaining the calculation and comparison of the first and second task execution times for the verification task.

서버는 복수의 작업자(32)의 각 검증용 작업에 대한 평균 작업 수행 시간(이하, "제1 작업 수행 시간"이라 한다)을 산출한다(S140). The server calculates an average work execution time (hereinafter, referred to as "first work execution time") for each verification task of the plurality of workers 32 (S140).

이때, 평균 작업 수행 시간은 각 작업자(32)에게 배정된 검증용 작업 수행을 시작한 시각과, 작업 수행을 완료하여 작업 결과를 입력한 시각에 기초하여 산출된 작업 수행 시간을 평균화한 것이다.In this case, the average work execution time is an average of the work execution time calculated based on the start time of performing the verification work assigned to each worker 32 and the time when the work execution is completed and the work result is input.

일 실시예로, 복수의 작업자(32) 중 작업 수행 건수가 n건(단, n은 1 이상의 자연수) 미만인 작업자(32)의 검증용 작업에 대한 제1 작업 수행 시간은 배제시킬 수 있다.In one embodiment, the first task execution time for the verification task of the worker 32 whose number of tasks is less than n (where n is a natural number of 1 or more) among the plurality of workers 32 may be excluded.

일 예로, 작업 수행 건수가 n건 미만인 작업자(32)는 작업 수행에 익숙하지 못한 신규 작업자일 수 있으며, 너무 많은 신규 작업자의 데이터가 함께 고려될 경우, 현재 능숙해진 작업자 풀을 평가하는데 문제가 될 수 있으므로 배제시킬 수 있다.For example, a worker 32 with fewer than n tasks performed may be a new worker unfamiliar with performing the task, and if too many new workers' data is considered together, it will be a problem in evaluating the current skilled worker pool. It can be ruled out.

다음으로, 서버는 제1 작업 수행 시간과, 제1 작업 수행 시간의 산출 이전에 각 검증용 작업에 대하여 기록된 작업 수행 시간(이하, "제2 작업 수행 시간"이라 한다)을 비교하고(S145), 비교 결과를 이용하여 복수의 작업자(32)에 대한 프로젝트 작업단가를 조절한다(S150).Next, the server compares the first task execution time with the task execution time (hereinafter referred to as "second task execution time") recorded for each verification task before the calculation of the first task execution time (S145 ), by using the comparison result to adjust the project work unit cost for the plurality of workers 32 (S150).

여기에서, 제2 작업 수행 시간은 제1 작업 수행 시간이 산출되기 이전에 검증용 작업에 대하여 기록된 시간으로, 검증용 작업에 대응하는 실전용 작업을 수행한 작업자(32)의 작업 수행 시간일 수 있다.Here, the second task execution time is a time recorded for the verification task before the first task execution time is calculated, and the task execution time day of the worker 32 who performed the practical task corresponding to the verification task I can.

또한, 제2 작업 수행 시간이 제1 작업 수행 시간으로 갱신되는 경우, 복수의 작업자(32)들의 검증용 작업 결과를 수행한 평균 작업 수행 시간으로 제2 작업 수행 시간이 될 수도 있다. In addition, when the second task execution time is updated to the first task execution time, the second task execution time may be an average task execution time obtained by performing the verification task results of the plurality of workers 32.

서버는 복수의 작업자(32)의 복수의 검증용 작업에 대한 제1 작업 수행 시간과 제2 작업 수행 시간의 각 편차를 산출하여 제1 및 제2 작업 수행 시간을 비교한다. 그리고 산출된 각 편차의 평균 값에 기초하여 복수의 작업자(32)에 대한 프로젝트 작업단가를 조절한다.The server calculates deviations between the first task execution time and the second task execution time for a plurality of verification tasks of the plurality of workers 32 and compares the first and second task execution times. And, based on the calculated average value of each deviation, the project cost for the plurality of workers 32 is adjusted.

일 실시예로, 서버는 복수의 검증용 작업에 대한 제1 작업 수행 시간의 전체 평균 값과, 복수의 검증용 작업에 대한 제2 작업 수행 시간의 전체 평균값을 산출할 수 있다.In an embodiment, the server may calculate an overall average value of the execution time of the first task for the plurality of verification tasks and the overall average value of the execution time of the second task for the plurality of verification tasks.

그리고 제1 작업 수행 시간의 전체 평균 값이 제2 작업 수행 시간의 전체 평균 값보다 더 짧은 시간을 갖는 경우, 각 편차의 평균 값에 대응되는 비율만큼 프로젝트의 작업단가를 감소시킬 수 있다.In addition, when the total average value of the first work execution time has a shorter time than the total average value of the second work execution time, the work unit cost of the project may be reduced by a ratio corresponding to the average value of each deviation.

예를 들어, 도 6에서 검증용 작업 ID 1001 내지 1003에 대한 제1 작업 수행 시간의 전체 평균 값은 88/3초((30s+40s+18s)/3)이고, 제2 작업 수행 시간의 전체 평균 값은 125/3초((40s+60s+25s)/3)이며, 제1 작업 수행 시간의 전체 평균 값이 제2 작업 수행 시간의 전체 평균 값보다 더 짧은 시간을 갖는다. 이 경우, 서버는 각 편차(-10, -20, -7)의 평균 값(-37/3=-12.3)에 대응되는 비율인 12.3%만큼 프로젝트의 작업단가를 감소시킬 수 있다.For example, in FIG. 6, the total average value of the first task execution time for the verification task IDs 1001 to 1003 is 88/3 seconds ((30s+40s+18s)/3), and the total of the second task execution time The average value is 125/3 seconds ((40s+60s+25s)/3), and the overall average value of the first task execution time has a shorter time than the overall average value of the second task execution time. In this case, the server can reduce the work cost of the project by 12.3%, a ratio corresponding to the average value (-37/3=-12.3) of each deviation (-10, -20, -7).

이와 달리, 제1 작업 수행 시간의 전체 평균 값이 제2 작업 수행 시간의 전체 평균 값보다 더 긴 시간을 갖는 경우, 각 편차의 평균 값에 대응되는 비율만큼 프로젝트의 작업단가를 증가시킬 수 있다.In contrast, when the total average value of the first work execution time has a longer time than the total average value of the second work execution time, the work unit cost of the project may be increased by a ratio corresponding to the average value of each deviation.

그밖에, 본 발명에서 제1 및 제2 작업 수행 시간의 각 편차의 평균 값에 기반하여 프로젝트의 작업단가를 조절하는 실시예는 다양할 수 있으며, 편차의 평균 값에 비율을 적용하는 것 외에 편차의 평균 값을 등급별로 구분(-11~-20=-10%, -21~30=-20% 등) 및 적용하여 프로젝트 작업단가를 조절할 수도 있다.In addition, in the present invention, there may be various embodiments of adjusting the work unit cost of a project based on the average value of each deviation of the first and second work execution times, and in addition to applying a ratio to the average value of the deviation, You can also adjust the project unit cost by classifying and applying the average value by grade (-11~-20=-10%, -21~30=-20%, etc.).

한편, 검증용 작업의 난이도가 너무 높을 경우, 작업 수행 결과뿐만 아니라 작업 수행 시간에 있어서도 작업자(32)별 편차가 너무 클 수 있다. 이러한 결과를 이용할 경우 프로젝트 작업단가 조절시 작업자(32)들의 능숙도 추세와는 다른 결과를 반영하게 되는 것인바, 이를 방지하기 위해 본 발명의 일 실시예는 프로젝트 작업단가를 조절함에 있어 난이도가 너무 높은 검증용 작업에 대한 데이터를 배제시킬 수 있다.On the other hand, when the difficulty of the verification task is too high, the deviation for each worker 32 may be too large in the task execution time as well as the task execution result. When these results are used, a result different from the proficiency trend of the workers 32 is reflected when adjusting the project work cost. To prevent this, an embodiment of the present invention has too high difficulty in adjusting the project work cost. Data on verification work can be excluded.

즉, 서버는 복수의 검수 결과를 기반으로 검증용 작업 풀에 포함된 검증용 작업에 대한 반려율을 산출한 후, 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업의 경우 난이도가 높은 검증용 작업으로 판단하여 제1 작업 수행 시간을 배제시킬 수 있다.In other words, the server calculates the rejection rate for the verification job included in the verification job pool based on the results of multiple inspections, and then, in the case of the verification job where the calculated rejection rate is higher than the preset rejection rate, it is for verification with high difficulty. By judging as a task, the time to perform the first task can be excluded.

예를 들어, 하나의 검증용 작업에 대한 반려율은 하나의 실전용 작업이 복수의 작업자(32)에게 배정되는 다중할당 방식인 경우, 작업자 A는 최초 검수 통과, 작업자 B는 1회 반려 후 검수 통과, 작업자 C는 2회 반려 후 검수 통과되었다면, 반려율은 (총 3회 반려/3명)=100%로 산출될 수 있다. 또는, 최초 검수 결과만 고려할 경우 (총 2회 반려/3명)=66.7%로 산출될 수 있다. For example, if the rejection rate for one verification task is a multi-allocation method in which one practical task is assigned to a plurality of workers 32, worker A passes the initial inspection, and worker B is returned once and then inspected. If passed, worker C is rejected twice and passed inspection, the rejection rate can be calculated as (total of 3 rejections/3 people) = 100%. Alternatively, if only the results of the initial inspection are considered (total 2 times/three persons) = 66.7% can be calculated.

이때, 서버는 제1 작업 수행 시간과 제2 작업 수행 시간의 편차가 기 설정된 편차 이상인 경우에, 제1 작업 수행 시간을 배제시킬 수 있다.In this case, when the deviation between the first task execution time and the second task execution time is greater than or equal to a preset deviation, the server may exclude the first task execution time.

즉, 검증용 작업에 대한 반려율이 높은 경우라 하더라도, 기존에 실전용 작업을 수행한 작업자(32)의 작업 수행 시간과, 금번 검증용 작업을 수행한 작업자(32)들의 평균 작업 수행 시간의 편차가 거의 없는 경우, 전체 작업자(32)들간의 능숙도 편차가 거의 없는 것으로 볼 수 있다. 반면, 그 반대인 경우에는 현재 검증용 작업을 수행한 작업자(32)들 간에도 큰 편차가 존재할 가능성이 높으므로, 이러한 경우 제1 작업 수행 시간을 배제시킬 수 있다.That is, even if the rejection rate for the verification work is high, the work execution time of the worker 32 who has previously performed the actual work and the average work execution time of the workers 32 who have performed the current verification work When there is little deviation, it can be seen that there is little deviation in proficiency among all the workers 32. On the other hand, in the opposite case, since there is a high possibility that a large deviation exists among the workers 32 who have currently performed the verification work, in this case, the first work execution time can be excluded.

프로젝트의 작업단가가 조절된 이후, 서버는 현재 기준으로 작업자(32)들의 경향성을 파악하기 위하여, 이전 사용된 데이터를 지표에서 제외시킬 수 있다.After the work unit cost of the project is adjusted, the server may exclude previously used data from the index in order to grasp the trends of the workers 32 based on the current standard.

도 7은 제2 작업 수행 시간을 갱신하는 내용을 설명하기 위한 도면이다.7 is a diagram for explaining content of updating a second task execution time.

서버는 복수의 작업자(32)에 대한 프로젝트 작업단가가 조절된 이후, 검증용 풀의 검증용 작업에 대하여 기록된 제2 작업 수행 시간을 복수의 작업자(32)의 각 검증용 작업에 대한 평균 작업 수행 시간인 제1 작업 수행 시간으로 갱신할 수 있다.After the project unit cost for the plurality of workers 32 is adjusted, the server calculates the second work execution time recorded for the verification work of the verification pool as an average work for each verification work of the plurality of workers 32 It can be updated to the execution time of the first task.

프로젝트 작업단가가 처음 조절된 경우에는, 검증용 작업에 대응하는 실전용 작업을 수행한 작업자(32)의 제2 작업 수행 시간이 제외되고, 제2 작업 수행 시간은 해당 검증용 작업을 수행한 복수의 작업자(32)들의 제1 작업 수행 시간으로 갱신된다.When the project unit cost is adjusted for the first time, the second task execution time of the worker 32 who performed the practical task corresponding to the verification task is excluded, and the second task execution time is a plurality of the verification tasks. It is updated with the first task execution time of the workers 32.

이후 프로젝트 작업단가가 다시 조절되면, 복수의 작업자(32)들의 평균 작업 수행 시간으로 기록된 제2 작업 수행 시간은 제외되고, 또 다른 복수의 작업자(32)들의 평균 작업 수행 시간인 제1 작업 수행 시간이 제2 작업 수행 시간으로 갱신된다.After the project unit cost is adjusted again, the second task execution time recorded as the average task execution time of the plurality of workers 32 is excluded, and the first task execution time, which is the average task execution time of another plurality of workers 32 The time is updated to the second task execution time.

예를 들어, 작업자 100명이 있는 상태에서, ID 1001 등의 검증용 작업이 랜덤한 순서로 50명에게 배정되어, 해당 데이터를 기반으로 프로젝트 작업단가가 1,000원에서 1,500원으로 상승한 경우, 50명에 대한 평균 작업 수행 시간으로 제2 작업 수행 시간이 갱신되게 된다. For example, if there are 100 workers, and verification tasks such as ID 1001 are assigned to 50 people in a random order, and the project unit cost increases from 1,000 won to 1,500 won based on the data, 50 The second task execution time is updated as the average task execution time.

프로젝트가 더 진행된 이후, ID 1001 등의 검증용 작업이 랜덤한 순서로 남은 50명의 작업자들에게 배정되었고, 프로젝트 후반에 해당하여 작업자(32)들이 더욱 능숙해짐에 따라 프로젝트 작업단가가 1,500원에서 2,000원으로 상승한 경우, 이전 50명에 대한 평균 작업 수행 시간은 배제되고, 현재의 50명에 대한 평균 작업 수행 시간으로 제2 작업 수행 시간이 갱신되게 된다.After the project was further progressed, verification tasks such as ID 1001 were assigned to the remaining 50 workers in a random order, and as the workers 32 became more proficient in the latter part of the project, the project unit cost was from 1,500 won to 2,000. In the case of rising to a circle, the average work execution time for the previous 50 people is excluded, and the second work execution time is updated with the average work execution time for the current 50 people.

이와 같은 갱신 과정을 통해, 현재 작업자(32)들이 기존에 비하여 더욱 능숙해졌는지 여부를 보다 정확히 판단할 수 있다.Through such an update process, it is possible to more accurately determine whether the current workers 32 are more proficient than the existing ones.

한편, 상술한 설명에서, 단계 S11 내지 S150은 본 발명의 구현예에 따라서, 추가적인 단계들로 더 분할되거나, 더 적은 단계들로 조합될 수 있다. 또한, 일부 단계는 필요에 따라 생략될 수도 있고, 단계 간의 순서가 변경될 수도 있다. 아울러, 기타 생략된 내용이라 하더라도 후술하는 도 8의 내용은 도 1 내지 도 7의 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법에도 적용될 수 있다.Meanwhile, in the above description, steps S11 to S150 may be further divided into additional steps or may be combined into fewer steps according to an embodiment of the present invention. In addition, some steps may be omitted as necessary, and the order between steps may be changed. In addition, even if other contents are omitted, the contents of FIG. 8 to be described later can also be applied to the method of adjusting the project work unit cost using the work for verification of the crowdsourcing-based project of FIGS. 1 to 7.

이하에서는 본 발명의 일 실시예에 따른 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 장치(200, 이하 프로젝트 작업단가 조절 장치라 한다)에 대하여 설명하도록 한다.Hereinafter, a description will be given of a project work cost control device 200 (hereinafter referred to as a project work cost control device) using a work for verifying a crowdsourcing-based project according to an embodiment of the present invention.

도 8은 본 발명의 일 실시예에 따른 프로젝트 작업단가 조절 장치(200)를 설명하기 위한 도면이다.8 is a view for explaining a project work unit cost adjustment device 200 according to an embodiment of the present invention.

도 8을 참조하면, 따른 프로젝트 작업단가 조절 장치(200)는 통신모듈(210), 메모리(220) 및 프로세서(230)를 포함한다.Referring to FIG. 8, the apparatus 200 for adjusting the unit cost of a project according to the present invention includes a communication module 210, a memory 220, and a processor 230.

통신모듈(210)은 하나의 프로젝트에 대한 크라우드소싱 기반의 작업을 복수의 작업자(32)에게 송신하여 작업 수행을 요청하고, 복수의 작업자(32)로부터 작업 결과를 수신한다. 또한, 복수의 작업자(32)로부터 수신된 작업 결과를 복수의 검수자(34)에게 송신하여 검수를 요청하고, 복수의 검수자(34)로부터 검수 결과를 수신한다. 또한, 통신모듈(210)은 검증용 작업을 복수의 작업자(32)에게 배정하여 작업 수행을 요청하고, 복수의 작업자(32)로부터 검증용 작업에 대한 작업 결과를 입력받는다.The communication module 210 transmits a crowdsourcing-based work for one project to a plurality of workers 32 to request a task to be performed, and receives a work result from the plurality of workers 32. Further, the work results received from the plurality of workers 32 are transmitted to the plurality of inspectors 34 to request inspection, and the inspection results are received from the plurality of inspectors 34. In addition, the communication module 210 allocates a verification task to a plurality of workers 32 to request the task to be performed, and receives a task result for the verification task from the plurality of workers 32.

메모리(220)에는 검증용 작업 결과에 대한 작업 수행 시간에 기초하여 복수의 작업자(32)의 프로젝트 작업단가를 조절하기 위한 프로그램이 저장된다.The memory 220 stores a program for adjusting the project work cost of the plurality of workers 32 based on the work execution time for the verification work result.

프로세서(230)는 메모리(220)에 저장된 프로그램을 실행시킴에 따라, 검증용 작업 풀을 생성한 후 검증용 작업을 복수의 작업자(32)에게 배정하고, 검증용 작업 결과에 대한 평균 작업 수행 시간 및 검증용 작업에 기록된 작업 수행 시간을 비교하여 작업자(32)들의 프로젝트의 작업단가를 조절한다.As the processor 230 executes the program stored in the memory 220, after generating the verification task pool, assigns the verification task to the plurality of workers 32, and the average task execution time for the verification task result And, by comparing the work execution time recorded in the verification work, the work unit cost of the project of the workers 32 is adjusted.

이상에서 전술한 본 발명의 일 실시예에 따른 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법은, 하드웨어인 컴퓨터와 결합되어 실행되기 위해 프로그램(또는 어플리케이션)으로 구현되어 매체에 저장될 수 있다.The method for controlling project work cost using the work for verifying a crowdsourcing-based project according to an embodiment of the present invention described above is implemented as a program (or application) to be executed in combination with a computer that is hardware and stored in a medium. I can.

상기 전술한 프로그램은, 상기 컴퓨터가 프로그램을 읽어 들여 프로그램으로 구현된 상기 방법들을 실행시키기 위하여, 상기 컴퓨터의 프로세서(CPU)가 상기 컴퓨터의 장치 인터페이스를 통해 읽힐 수 있는 C, C++, JAVA, Ruby, 기계어 등의 컴퓨터 언어로 코드화된 코드(Code)를 포함할 수 있다. 이러한 코드는 상기 방법들을 실행하는 필요한 기능들을 정의한 함수 등과 관련된 기능적인 코드(Functional Code)를 포함할 수 있고, 상기 기능들을 상기 컴퓨터의 프로세서가 소정의 절차대로 실행시키는데 필요한 실행 절차 관련 제어 코드를 포함할 수 있다. 또한, 이러한 코드는 상기 기능들을 상기 컴퓨터의 프로세서가 실행시키는데 필요한 추가 정보나 미디어가 상기 컴퓨터의 내부 또는 외부 메모리의 어느 위치(주소 번지)에서 참조되어야 하는지에 대한 메모리 참조관련 코드를 더 포함할 수 있다. 또한, 상기 컴퓨터의 프로세서가 상기 기능들을 실행시키기 위하여 원격(Remote)에 있는 어떠한 다른 컴퓨터나 서버 등과 통신이 필요한 경우, 코드는 상기 컴퓨터의 통신 모듈을 이용하여 원격에 있는 어떠한 다른 컴퓨터나 서버 등과 어떻게 통신해야 하는지, 통신 시 어떠한 정보나 미디어를 송수신해야 하는지 등에 대한 통신 관련 코드를 더 포함할 수 있다.The above-described program includes C, C++, JAVA, Ruby, which can be read by a processor (CPU) of the computer through the device interface of the computer, in order for the computer to read the program and execute the methods implemented as a program. It may include a code (Code) coded in a computer language such as machine language. Such code may include a functional code related to a function defining necessary functions for executing the methods, and a control code related to an execution procedure necessary for the processor of the computer to execute the functions according to a predetermined procedure. can do. In addition, such code may further include additional information required for the processor of the computer to execute the functions or code related to a memory reference to which location (address address) of the internal or external memory of the computer should be referenced. have. In addition, when the processor of the computer needs to communicate with any other computer or server in the remote in order to execute the functions, the code uses the communication module of the computer to determine how It may further include a communication-related code for whether to communicate, what kind of information or media should be transmitted and received during communication.

상기 저장되는 매체는, 레지스터, 캐쉬, 메모리 등과 같이 짧은 순간 동안 데이터를 저장하는 매체가 아니라 반영구적으로 데이터를 저장하며, 기기에 의해 판독(reading)이 가능한 매체를 의미한다. 구체적으로는, 상기 저장되는 매체의 예로는 ROM, RAM, CD-ROM, 자기 테이프, 플로피디스크, 광 데이터 저장장치 등이 있지만, 이에 제한되지 않는다. 즉, 상기 프로그램은 상기 컴퓨터가 접속할 수 있는 다양한 서버 상의 다양한 기록매체 또는 사용자의 상기 컴퓨터상의 다양한 기록매체에 저장될 수 있다. 또한, 상기 매체는 네트워크로 연결된 컴퓨터 시스템에 분산되어, 분산방식으로 컴퓨터가 읽을 수 있는 코드가 저장될 수 있다.The stored medium is not a medium that stores data for a short moment, such as a register, cache, memory, etc., but a medium that stores data semi-permanently and can be read by a device. Specifically, examples of the storage medium include, but are not limited to, ROM, RAM, CD-ROM, magnetic tape, floppy disk, optical data storage device, and the like. That is, the program may be stored in various recording media on various servers to which the computer can access, or on various recording media on the user's computer. In addition, the medium may be distributed over a computer system connected through a network, and computer-readable codes may be stored in a distributed manner.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The above description of the present invention is for illustrative purposes only, and those of ordinary skill in the art to which the present invention pertains will be able to understand that other specific forms can be easily modified without changing the technical spirit or essential features of the present invention will be. Therefore, it should be understood that the embodiments described above are illustrative in all respects and not limiting. For example, each component described as a single type may be implemented in a distributed manner, and similarly, components described as being distributed may also be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is indicated by the claims to be described later rather than the detailed description, and all changes or modified forms derived from the meaning and scope of the claims and their equivalent concepts should be interpreted as being included in the scope of the present invention. do.

10 : 의뢰자
20 : 서비스 제공 업체
30 : 대중
32 : 작업자
34 : 검수자
200 : 프로젝트 작업단가 조절 장치
210 : 통신모듈
220 : 메모리
230 : 프로세서
10: Client
20: service provider
30: public
32: worker
34: inspector
200: Project work unit cost control device
210: communication module
220: memory
230: processor

Claims (10)

컴퓨터에 의해 수행되는 방법으로서,
크라우드소싱 기반 프로젝트(이하, "프로젝트")의 복수의 실전용 작업을 복수의 작업자에게 배정하여 작업 수행을 요청하는 단계;
상기 복수의 작업자로부터 복수의 실전용 작업 결과를 입력받는 단계;
상기 복수의 실전용 작업 결과를 복수의 검수자에게 배정하여 검수 수행을 요청하는 단계;
상기 복수의 검수자로부터 상기 복수의 실전용 작업 결과에 대한 복수의 검수 결과로 검수 통과 또는 반려를 입력받는 단계;
제1 시간 구간 동안의 상기 복수의 실전용 작업 결과에 대한 복수의 검수 결과에 기초하여, 소정의 조건을 만족하는 실전용 작업 결과에 대응하는 실전용 작업을 이용하여 복수의 검증용 작업을 생성하는 단계;
상기 제1 시간 구간 이후의 제2 시간 구간 동안 상기 복수의 검증용 작업을 상기 복수의 실전용 작업을 배정받아 작업을 수행하는 복수의 작업자에게 배정하여 작업 수행을 요청하는 단계;
상기 복수의 작업자로부터 상기 복수의 검증용 작업에 대한 작업 결과를 입력받는 단계;
각 검증용 작업과 관련하여 상기 복수의 작업자의 평균 작업 수행 시간(이하, "제1 작업 수행 시간")을 산출하는 단계;
각 검증용 작업에 대한 상기 제1 작업 수행 시간과, 상기 각 검증용 작업에 대응하는 각 실전용 작업에 대하여 기록된 작업 수행 시간(이하, "제2 작업 수행 시간)을 비교하는 단계; 및
상기 비교 결과를 이용하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계를 포함하되,
각 검증용 작업에 대한 상기 제1 작업 수행 시간과, 상기 각 검증용 작업에 대응하는 각 실전용 작업에 대하여 기록된 작업 수행 시간(이하, "제2 작업 수행 시간)을 비교하는 단계는,
상기 복수의 검증용 작업 각각에 대해서 제1 작업 수행 시간과 제2 작업 수행 시간의 편차를 산출하는 단계를 포함하고,
상기 비교 결과를 이용하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계는,
상기 복수의 검증용 작업 각각에 대해서 산출된 편차의 평균 값에 기초하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계를 포함하는,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
As a method performed by a computer,
Assigning a plurality of practical tasks of a crowdsourcing-based project (hereinafter, "project") to a plurality of workers and requesting to perform the task;
Receiving a plurality of practical work results from the plurality of workers;
Allocating the plurality of practical work results to a plurality of inspectors and requesting to perform inspection;
Receiving an inspection pass or rejection as a plurality of inspection results for the plurality of practical work results from the plurality of inspectors;
Based on a plurality of inspection results of the plurality of practical work results during a first time period, a plurality of verification jobs is generated using a practical job corresponding to a practical job result that satisfies a predetermined condition. step;
Requesting to perform a task by assigning the plurality of verification tasks to a plurality of workers who perform tasks by receiving the plurality of practical tasks during a second time section after the first time section;
Receiving work results for the plurality of verification tasks from the plurality of workers;
Calculating an average work execution time (hereinafter, "first work execution time") of the plurality of workers in relation to each verification task;
Comparing the first task execution time for each verification task and the task execution time recorded for each practical task corresponding to each verification task (hereinafter, "second task execution time); And
Including the step of adjusting the project work unit cost for the plurality of workers by using the comparison result,
Comparing the first task execution time for each verification task and the task execution time recorded for each practical task corresponding to each verification task (hereinafter, "second task execution time),
Comprising the step of calculating a deviation between the first task execution time and the second task execution time for each of the plurality of verification tasks,
Adjusting the project work unit cost for the plurality of workers using the comparison result,
Including the step of adjusting the project work unit cost for the plurality of workers based on the average value of the deviation calculated for each of the plurality of verification tasks,
A method of adjusting the cost of project work using the verification work of crowdsourced projects.
제1항에 있어서,
상기 소정의 조건은,
상기 검수자의 검수 수행 시간을 기준으로 하는 소정의 순위를 만족하는 조건인 것인,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 1,
The predetermined conditions are:
It is a condition that satisfies a predetermined ranking based on the inspection execution time of the inspector,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제2항에 있어서,
제1 시간 구간 동안의 상기 복수의 실전용 작업 결과에 대한 복수의 검수 결과에 기초하여, 소정의 조건을 만족하는 실전용 작업 결과에 대응하는 실전용 작업을 이용하여 복수의 검증용 작업을 생성하는 단계는,
상기 소정의 조건을 만족하는 실전용 작업 결과를 검수한 검수자와 상이한 하나 이상의 타 검수자에게 재검수를 요청하는 단계; 및
상기 소정의 조건을 만족하고, 상기 타 검수자에 의해서 재검수 통과된 실전용 작업 결과에 대응하는 실전용 작업을 이용하여 상기 복수의 검증용 작업을 생성하는 단계를 포함하는,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 2,
Based on a plurality of inspection results of the plurality of practical work results during a first time period, a plurality of verification jobs is generated using a practical job corresponding to a practical job result that satisfies a predetermined condition. The steps are,
Requesting re-examination from at least one other inspector different from the inspector who inspects the results of the practical use that satisfy the predetermined condition; And
Comprising the step of generating the plurality of verification tasks using a practical job corresponding to a result of a practical job that satisfies the predetermined condition and has been re-examined by the other inspector,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제1항에 있어서,
상기 제1 시간 구간 이후의 제2 시간 구간 동안 상기 복수의 검증용 작업을 상기 복수의 실전용 작업을 배정받아 작업을 수행하는 복수의 작업자에게 배정하여 작업 수행을 요청하는 단계는,
상기 프로젝트에 포함된 전체 작업 중 소정의 비율 이상의 실전용 작업에 대한 실전용 작업 결과가 제출된 시점 이후부터 상기 검증용 작업을 복수의 작업자에게 배정하여 작업 수행을 요청하는,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 1,
The step of requesting to perform a task by assigning the plurality of verification tasks to a plurality of workers who are assigned the plurality of practical tasks and perform tasks during a second time interval after the first time interval,
Allocating the verification work to a plurality of workers from the time when the results of the practical work for the practical work of more than a predetermined percentage of the total work included in the project are submitted to request the execution of the work,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제1항에 있어서,
상기 각 검증용 작업과 관련하여 상기 복수의 작업자의 평균 작업 수행 시간(이하, "제1 작업 수행 시간")을 산출하는 단계는,
상기 복수의 작업자 중 실전용 작업 수행 건수가 n건(단, n은 1이상의 자연수) 미만인 작업자의 작업 수행 시간은 배제시키고 산출하는 것인,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 1,
The step of calculating the average work execution time (hereinafter, "first work execution time") of the plurality of workers in relation to each of the verification tasks,
The number of practical tasks among the plurality of workers is calculated by excluding and calculating the task execution time of workers with less than n (however, n is a natural number of 1 or more).
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제1항에 있어서,
상기 복수의 검증용 작업 각각에 대해서 제1 작업 수행 시간과 제2 작업 수행 시간의 편차를 산출하는 단계는,
상기 복수의 검수 결과를 기반으로 상기 복수의 검증용 작업에 대한 반려율을 산출하고,
상기 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업에 대한 제1 작업 수행 시간을 배제시키고 산출하는 것인,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 1,
The step of calculating a deviation between the first task execution time and the second task execution time for each of the plurality of verification tasks,
Calculating rejection rates for the plurality of verification tasks based on the plurality of inspection results,
The calculated rejection rate is to exclude and calculate the first task execution time for the verification task that is more than a preset rejection rate,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제6항에 있어서,
상기 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업에 대한 제1 작업 수행 시간을 배제시키고 산출하는 것은,
상기 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업에 대한 상기 제1 작업 수행 시간과 상기 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업에 대응하는 실전용 작업에 대한 상기 제2 작업 수행 시간의 편차가 기 설정된 편차 이상인 경우, 상기 산출된 반려율이 기 설정된 반려율 이상인 검증용 작업에 대한 상기 제1 작업 수행 시간을 배제시키고 산출하는 것인,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 6,
Excluding and calculating the first task execution time for the verification task in which the calculated rejection rate is greater than or equal to a preset rejection rate,
Performing the first task execution time for the verification task in which the calculated rejection rate is greater than or equal to a preset rejection rate and the second task for practical tasks corresponding to the verification task in which the calculated rejection rate is greater than or equal to a preset rejection rate When the deviation of the time is greater than or equal to a preset deviation, the calculated rejection rate excludes and calculates the first task execution time for the verification task whose rejection rate is greater than or equal to the preset rejection rate,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제1항에 있어서,
상기 비교 결과를 이용하여 상기 복수의 작업자에 대한 프로젝트 작업단가를 조절하는 단계는,
상기 각 검증용 작업에 대한 제1 작업 수행 시간의 전체 평균 값이 상기 각 검증용 작업에 대응하는 각 실전용 작업에 대한 제2 작업 수행 시간의 전체 평균 값보다 더 짧은 시간을 갖는 경우, 상기 산출된 편차의 평균 값에 대응되는 비율만큼 상기 복수의 작업자에 대한 상기 프로젝트의 작업단가를 감소시키는 단계; 및
상기 각 검증용 작업에 대한 제1 작업 수행 시간의 전체 평균 값이 상기 각 검증용 작업에 대응하는 각 실전용 작업에 대한 제2 작업 수행 시간의 전체 평균 값보다 더 긴 시간을 갖는 경우, 상기 산출된 편차의 평균 값에 대응되는 비율만큼 상기 복수의 작업자에 대한 상기 프로젝트의 작업단가를 증가시키는 단계를 포함하는,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 1,
Adjusting the project work unit cost for the plurality of workers using the comparison result,
When the overall average value of the first task execution time for each verification task has a shorter time than the overall average value of the second task execution time for each practical task corresponding to each verification task, the calculation Reducing the work unit cost of the project for the plurality of workers by a ratio corresponding to the average value of the deviation; And
When the total average value of the first task execution time for each verification task is longer than the overall average value of the second task execution time for each practical task corresponding to each verification task, the calculation Comprising the step of increasing the work unit cost of the project for the plurality of workers by a ratio corresponding to the average value of the deviation,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
제1항에 있어서,
상기 복수의 작업자에 대한 프로젝트 작업단가가 조절된 이후, 상기 각 검증용 작업에 대응하는 각 실전용 작업에 대한 제2 작업 수행 시간을 상기 각 검증용 작업과 관련하여 상기 복수의 작업자의 평균 작업 수행 시간인 제1 작업 수행 시간으로 갱신하는 단계를 더 포함하는,
크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법.
The method of claim 1,
After the project work cost for the plurality of workers is adjusted, the second work execution time for each practical work corresponding to each verification work is calculated in relation to each verification work, and the average work performed by the plurality of workers Further comprising the step of updating the first task execution time, which is a time,
A method of controlling the cost of project work using the verification work of crowdsourced projects.
컴퓨터와 결합되어, 제1항 내지 제9항 중 어느 하나의 항의 크라우드소싱 기반 프로젝트의 검증용 작업을 이용한 프로젝트 작업단가 조절 방법을 실행시키기 위하여 컴퓨터 판독가능 기록매체에 저장된 컴퓨터 프로그램.A computer program combined with a computer and stored in a computer-readable recording medium to execute the method of adjusting the project work unit cost using the work for verifying the crowdsourcing-based project according to any one of claims 1 to 9.
KR1020200066135A 2020-06-02 2020-06-02 Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation KR102183838B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200066135A KR102183838B1 (en) 2020-06-02 2020-06-02 Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200066135A KR102183838B1 (en) 2020-06-02 2020-06-02 Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation

Publications (1)

Publication Number Publication Date
KR102183838B1 true KR102183838B1 (en) 2020-11-30

Family

ID=73641826

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200066135A KR102183838B1 (en) 2020-06-02 2020-06-02 Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation

Country Status (1)

Country Link
KR (1) KR102183838B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007011697A (en) * 2005-06-30 2007-01-18 Toshiba Corp Estimating work support system, estimating work support device and estimating work support method
JP2011013763A (en) * 2009-06-30 2011-01-20 Hitachi Ltd Duration calculator and duration calculation method
KR20140095956A (en) 2013-01-25 2014-08-04 한국전자통신연구원 Method and system for generating image-knowledge contents based on crowdsourcing
KR20170123073A (en) * 2016-04-28 2017-11-07 (주)한국기업경영연구원 Consunlting service method using on-line
KR101941418B1 (en) * 2018-08-10 2019-04-12 김희선 Crowding testing platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007011697A (en) * 2005-06-30 2007-01-18 Toshiba Corp Estimating work support system, estimating work support device and estimating work support method
JP2011013763A (en) * 2009-06-30 2011-01-20 Hitachi Ltd Duration calculator and duration calculation method
KR20140095956A (en) 2013-01-25 2014-08-04 한국전자통신연구원 Method and system for generating image-knowledge contents based on crowdsourcing
KR20170123073A (en) * 2016-04-28 2017-11-07 (주)한국기업경영연구원 Consunlting service method using on-line
KR101941418B1 (en) * 2018-08-10 2019-04-12 김희선 Crowding testing platform

Similar Documents

Publication Publication Date Title
KR102164844B1 (en) Method for evaluating workers using the unit of work difficulty of crowdsourcing based projects for artificial intelligence training data generation
KR102232859B1 (en) Method for automatically generating a worker pool based on the functional elements and difficulty of crowdsourcing based projects for artificial intelligence training data generation
KR102232866B1 (en) Method for distributing functional element unit work of crowdsourcing based project for artificial intelligence training data generation
KR102155790B1 (en) Method and apparatus for measuring competence of worker using average return rate
KR102195630B1 (en) Method for providing rewarded training for training participants in a crowdsourcing based projects for artificial intelligence training data generation
KR102155877B1 (en) Method for providing information of projects matching qualifications of crowdsourcing platform for artificial intelligence training data generation
KR102232874B1 (en) Method for evaluating new inspector using verification work result of crowdsourcing based project for artificial intelligence training data generation
KR102169334B1 (en) Method for adjusting inspection standards of inspectors by comparing inspection results of crowdsourcing based projects for artificial intelligence training data generation
KR102205811B1 (en) Method for setting minimum work time using work time of each functional elements of crowdsourcing based project for artificial intelligence training data generation
KR102164769B1 (en) Method for measuring competence using the number of inspection pass of crowdsourcing based project for artificial intelligence training data generation
KR102183836B1 (en) Method for automatically calculating estimates based on estimated work time of crowdsourcing based projects for artificial intelligence training data generation
KR102155748B1 (en) Method for automatic apdating inspection unit price using work time versus inspection time of crowdsourcing based project for artificial intelligence training data generation
KR102155839B1 (en) Method and apparatus for monitoring worker based on the reason for not wokring
KR102183812B1 (en) Method for paying inspection fee based on hourly wage for each inspector using the verification work results of crowdsourcing based projects for artificial intelligence training data generation
KR102183837B1 (en) Method for paying work fee based on hourly wage for each workers using verification work of crowdsourcing based projects for artificial intelligence training data generation
KR102183838B1 (en) Method for adjusting the unit cost of project work using verification work of crowdsourcing based projects for artificial intelligence training data generation
KR102164852B1 (en) Method for restricting participation of project considering urgent degree of crowdsourcing based project for artificial intelligence training data generation
KR102164837B1 (en) Method for cost-effectively managing inspection quality of crowdsourcing based projects for artificial intelligence training data generation
KR102155886B1 (en) Method for applying maximum number of work limits per worker based on inspection result of crowdsourcing based projects for artificial intelligence training data generation
KR102195606B1 (en) Method for improving reliability by selective self check of worker of crowdsourcing based project for artificial intelligence training data generation
KR102244705B1 (en) Method for controlling worker inflow into project by reversal adjustment of work unit price between crowdsourcing based similar projects for training data generation
KR102195632B1 (en) Method for calculating maximum wor result quantity by selecting available worker of crowdsourcing based project for artificial intelligence training data generation
KR102156586B1 (en) Method for sequentially assigning work and inspection of crowdsourcing based project for artificial intelligence training data generation
KR102169321B1 (en) Method for adjusting the cost of project inspection using the verification work results of crowdsourcing based projects for artificial intelligence training data generation
KR102155747B1 (en) Method for setting minimum re-work and re-inspection time based on the number of objects returned of crowdsourcing based project for artificial intelligence training data generation

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant