- WO2023170828A1 WO2023170828A1 PCT/JP2022/010328 JP2022010328W WO2023170828A1 WO 2023170828 A1 WO2023170828 A1 WO 2023170828A1 JP 2022010328 W JP2022010328 W JP 2022010328W WO 2023170828 A1 WO2023170828 A1 WO 2023170828A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- air conditioning
- power supply
- unit
- demand adjustment
- period
- Prior art date
Links
- 238000004378 air conditioning Methods 0.000 title claims abstract description 238
- 238000001514 detection method Methods 0.000 claims abstract description 24
- 238000005338 heat storage Methods 0.000 claims description 121
- 238000004364 calculation method Methods 0.000 claims description 56
- 230000005855 radiation Effects 0.000 claims description 26
- 238000002360 preparation method Methods 0.000 claims description 20
- 238000000034 method Methods 0.000 claims description 13
- 230000006870 function Effects 0.000 claims description 12
- 238000001816 cooling Methods 0.000 claims description 9
- 238000010438 heat treatment Methods 0.000 claims description 9
- 239000003507 refrigerant Substances 0.000 description 19
- 238000010586 diagram Methods 0.000 description 10
- 230000005611 electricity Effects 0.000 description 7
- 230000000737 periodic effect Effects 0.000 description 6
- 238000005057 refrigeration Methods 0.000 description 6
- 238000004891 communication Methods 0.000 description 5
- 230000001771 impaired effect Effects 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 239000002131 composite material Substances 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24F—AIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
- F24F2110/00—Control inputs relating to air properties
- F24F2110/50—Air quality properties
- F24F2110/80—Electric charge
Definitions
- the present disclosure relates to a building frame heat storage type air conditioning system.
- a structural heat storage type air conditioning system that suppresses an increase in power consumption due to excessive heat storage by calculating the required amount of heat storage from the previous day's heat storage amount (for example, Patent Document 1).
- Such a building-frame heat storage type air conditioning system has a problem in that heat can only be stored up to the set temperature when the target air conditioning section is used, and the amount of heat storage is small.
- the amount of heat storage is small.
- heat is stored in the target air-conditioning compartment until the temperature reaches a temperature that significantly deviates from the set temperature, the comfort of the users of the target air-conditioning compartment will be impaired.
- the present disclosure has been made in view of the above circumstances, and aims to provide a frame heat storage type air conditioning system that can increase heat storage without impairing the comfort of the target air conditioning section.
- An air conditioning system includes an air conditioner indoor unit provided in an air conditioning compartment, an occupancy detection unit that detects occupancy information indicating the presence or absence of a person in the air conditioning compartment, and detection by the occupancy detection unit. If the room occupancy information indicates that there is no person in the air conditioning compartment, the operating conditions of the air conditioner indoor unit may be changed from the time when the air conditioner indoor unit was operated under the operating conditions set for the air conditioner indoor unit.
- the air conditioner is also equipped with a control unit that changes the air conditioning capacity to increase.
- the control unit of the air conditioning system changes the operating conditions of the air conditioner indoor unit to increase the capacity when the room occupancy detection unit indicates the absence of the air conditioning compartment. Therefore, the air conditioning system can use the air conditioning section where no user is present as a heat storage tank, and can store heat in the air conditioning section without impairing the comfort of the target air conditioning section.
- FIG. 1 is a schematic diagram showing a building equipped with an air conditioning system according to Embodiment 1.
- FIG. 3 is a flowchart for explaining the operation of the air conditioner indoor unit according to the first embodiment.
- FIG. 7 is a diagram showing an air conditioner indoor unit in an air conditioning system according to a second embodiment.
- FIG. 3 is a functional block diagram showing the functions of a control unit in the air conditioning system according to Embodiment 2.
- FIG. 7 is a flowchart of operation control of the air conditioning system according to Embodiment 2.
- FIG. FIG. 3 is a functional block diagram showing the functions of a control unit in an air conditioning system according to a third embodiment.
- 7 is a flowchart of operation control of the air conditioning system according to Embodiment 3.
- FIG. 7 is a schematic diagram showing a building equipped with an air conditioning system according to Embodiment 4.
- FIG. 1 is a schematic diagram showing a building B equipped with an air conditioning system 20 according to the first embodiment.
- the air conditioning system 20 includes an air conditioner indoor unit 1, a room occupancy detection section 2, a control section 3, and an air conditioning section usage information storage section 15.
- the air conditioning system 20 of this embodiment is a frame heat storage type air conditioning system 20 that uses any one or more of the air conditioning sections 14 as a heat storage tank.
- the room occupancy detection unit 2 is provided in at least one of the air conditioning compartments 14 in which the air conditioner indoor unit 1 is installed.
- FIG. 1 shows a case where the room occupancy detection unit 2 is provided in each of the air conditioning compartments 14 where a person is shown and the air conditioning compartment 14 where a person is not shown.
- the occupancy detector 2 detects occupancy information indicating the presence or absence of a person in the air-conditioned section 14 .
- the room presence detection unit 2 is an infrared sensor, detection information of a card reader, a thermal image sensor, an illuminance sensor, a device in the air conditioning section 14, or the like.
- the room occupancy detection section 2 inputs the detected room occupancy information to the control section 3.
- the control unit 3 is communicably connected to the air conditioner indoor unit 1 to be controlled via a communication line such as the Internet.
- the control section 3 controls the air conditioner indoor unit 1.
- the control unit 3 sets the operating conditions of the air conditioner indoor unit 1 to the air conditioner indoor unit 1.
- the air conditioning capacity is changed to be greater than when operating under the set operating conditions.
- the control section 3 controls the settings of the air conditioning section 14 of the air conditioner indoor unit 1 during cooling. The temperature is kept low, and the set temperature of the air conditioner indoor unit 1 is made high during heating.
- the processing circuit of the control unit 3 is dedicated hardware
- the processing circuit is, for example, a single circuit, a composite circuit, an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array), or a combination of these. things is applicable.
- Each of the functional units realized by the processing circuit may be realized by separate hardware, or each functional unit may be realized by one piece of hardware.
- the processing circuit of the control unit 3 is a CPU
- each function executed by the processing circuit is realized by software, firmware, or a combination of software and firmware.
- Software and firmware are written as programs and stored in the storage unit 109.
- the CPU implements each function of the processing circuit by reading and executing programs stored in the storage unit. Note that some of the functions of the processing circuit may be realized by dedicated hardware, and some of them may be realized by software or firmware.
- the air conditioning compartment usage information storage unit 15 accumulates information on future usage plans for the air conditioning compartments 14.
- the air conditioning compartment usage information storage unit 15 is communicably connected to the control unit 3 via a communication line such as the Internet.
- a conference room reservation system or the like may be used as the air conditioning section usage information storage section 15.
- FIG. 2 is a flowchart for explaining the operation of the air conditioner indoor unit 1 according to the first embodiment.
- the room occupancy detection unit 2 detects room occupancy information indicating the presence or absence of a person in the air conditioning section 14 (step S1).
- the control unit 3 determines whether the occupancy information detected by the occupancy detection unit 2 indicates the absence of a person in the air conditioning section 14 (step S2).
- the control unit 3 can identify air-conditioning compartments 14 that are not scheduled to be used based on information about future usage plans of the air-conditioning compartments 14 stored in the air-conditioning compartment usage information storage unit 15. The control unit 3 may determine the occupancy information only for the identified air conditioning section 14 that is not scheduled to be used.
- step S3 if the control unit 3 determines that the occupancy information detected by the occupancy detection unit 2 does not indicate the absence of a person in the air conditioning section 14 (NO in step S3), the control unit 3 detects the presence of a person in the room.
- the air conditioner indoor unit 1 is controlled to continue the air conditioning operation of the air conditioning section 14 in which the section 2 is provided (step S4).
- step S3 if the control unit 3 determines that the room occupancy information detected by the room occupancy detection unit 2 indicates the absence of a person in the air conditioning section 14 (YES in step S3), the air conditioner indoor unit 1 is activated during cooling.
- the set temperature of the air conditioning section 14 is set low, and the set temperature of the air conditioner indoor unit 1 is set high during heating (step S5).
- the heat stored in the air conditioning compartments 14 that are not occupied is transferred to the air from the walls between the air conditioning compartments 14 to the air and radiated when the air conditioning is operated when a person is present. used for.
- control unit 3 may start the air conditioning operation when the air conditioner indoor unit 1 is not operating in the air conditioning section 14 that has been confirmed to be absent. Further, the control unit 3 may increase the air volume of the fan of the air conditioner indoor unit 1 in the air conditioning section 14 that has been confirmed to be absent.
- step S3 the control unit 3 repeatedly obtains occupancy information from the occupancy detection unit 2 during an absence determination period of about 30 minutes to 1 hour, for example, and determines that all the occupancy information during this absence determination period indicates the absence of a person. It may be determined that the person is absent if the person is absent. Thereby, the control unit 3 can prevent erroneous identification of the presence or absence of a person.
- the control unit 3 may preferentially use as a heat storage tank an air conditioning section 14 that is selected based on past usage information and is used less frequently.
- the air conditioning compartment usage information storage unit 15 accumulates information on past usage history of the air conditioning compartments 14, and the control unit 3 determines the usage frequency of each air conditioning compartment 14 based on the accumulated usage history. judge. Then, when it is determined that a person is absent from the plurality of air conditioning sections 14 based on the occupancy information from the room occupancy detection section 2, the control section 3 controls the number of air conditioning sections according to the required amount of heat storage. 14, the air conditioner indoor unit 1 of the air conditioning section 14 that is used less frequently is operated preferentially. By preferentially using the air conditioning section 14 that is used less frequently as a heat storage tank, the comfort of the users of building B is less likely to be impaired.
- the control unit 3 determines when the air conditioning compartment 14 is scheduled to be used during a period in which power consumption is desired to be reduced, based on information about the future usage schedule of the air conditioning compartment 14 stored in the air conditioning compartment usage information storage unit 15. , the air conditioner indoor unit 1 may be operated before the period during which it is desired to reduce power consumption. Heat is stored in the air conditioning compartment 14 before the period during which it is desired to reduce power consumption. Thereby, it is possible to reduce the power consumption of the air conditioner indoor unit 1 during the period in which the amount of power consumption is desired to be reduced.
- the air conditioning system 20 of the first embodiment based on the occupancy information obtained by the occupancy detector 2, the operating conditions of the air conditioner indoor unit 1 of the air conditioning compartment 14 whose absence has been confirmed are determined based on the occupancy information obtained by the occupancy detection unit 2.
- the air conditioning capacity is changed to be greater than when operating under the operating conditions set for the air conditioner indoor unit 1. Therefore, according to the air conditioning system 20 of the first embodiment, cold heat or heat can be stored in the air conditioning section 14 where no one is present. Therefore, the air conditioning section 14 can be used as a heat storage tank without impairing comfort. Further, the cold heat or heat stored in the air conditioning section 14 as a heat storage tank is used for subsequent air conditioning operation of the air conditioning system 20.
- the set temperature of the air conditioner indoor unit 1 corresponding to the air conditioning section 14 where no one is present is lowered than the set temperature during cooling when a person is present.
- the set temperature of the air conditioner indoor unit 1 corresponding to the air conditioning section 14 where no one is present is raised higher than the set temperature during heating when a person is present. Thereby, the amount of heat storage in the air conditioning section 14 where no one is present can be increased.
- Embodiment 2 the operation from when the air conditioning system 20 receives the power supply and demand adjustment command until the end of the power supply and demand adjustment period will be described.
- the "power supply and demand adjustment period” indicates a period during which the power consumption of the air conditioning system 20 is actually adjusted based on the power supply and demand adjustment command.
- power consumption adjustment during the "power supply and demand adjustment period” includes posiwatt type adjustment that increases power consumption and negative watt type adjustment that reduces power consumption.
- the air conditioning system 20 performs heat storage operation during the "power supply and demand adjustment period”.
- a “power supply and demand adjustment preparation period” is provided before the "power supply and demand adjustment period”.
- the “power supply and demand adjustment preparation period” indicates a period during which heat storage operation is performed before the power supply and demand adjustment period.
- the operation of changing the settings according to the presence or absence of a person in the first embodiment is the operation of the heat storage operation of the air conditioning system 20 during the above-mentioned “power supply and demand adjustment period” and “power supply and demand adjustment preparation period”.
- FIG. 3 is a diagram showing the air conditioner indoor unit 1 in the air conditioning system 20 according to the second embodiment. As shown in FIG. 2, the air conditioner indoor unit 1 provided in the air conditioning section 14 has a temperature sensor 30.
- the temperature sensor 30 is connected to the control unit 3, measures the room temperature of the air conditioning section 14, and outputs the measured room temperature to the control unit 3.
- FIG. 4 is a functional block diagram showing the functions of the control unit 3 in the air conditioning system 20 according to the second embodiment.
- control unit 3 includes an electric power supply and demand adjustment command receiving unit 5, a heat load history information storage unit 6, a heat load prediction unit 4, an allowable heat storage amount calculation unit 9, an operation plan creation unit 18, a period operation efficiency It includes a calculation section 17, a power consumption calculation section 19, and a power supply and demand adjustment allowance calculation section 16.
- the power supply and demand adjustment command receiving unit 5 receives power supply and demand adjustment commands from the outside via a communication line such as the Internet.
- the power supply and demand adjustment command receiving unit 5 acquires the power supply and demand adjustment period, the amount of power adjustment, the power adjustment consideration, etc. based on the received power supply and demand adjustment command.
- the power supply and demand adjustment command receiving unit 5 may acquire the power supply and demand adjustment period, power adjustment amount, power adjustment consideration, etc. from another server or the like based on the power supply and demand adjustment command.
- Electricity supply and demand adjustment directives are issued by aggregators, electric power companies, etc.
- the electric power supply and demand adjustment command is, for example, an electric power supply and demand adjustment command with contents such as "reduce electric power consumption to 100 kW or less from 16:00 to 19:00 tomorrow."
- the power supply and demand adjustment command includes information such as the supply and demand adjustment period, the amount of power adjustment, and the consideration for power adjustment, but some or all of this information may be predetermined in a separate contract or the like. If all information on the power supply and demand adjustment command is predetermined in a contract or the like, the power supply and demand adjustment command receiving section 5 reads out information stored in advance in a memory (not shown) of the control section 3.
- the heat load history information storage section 6 stores past operation data of the air conditioner indoor unit 1.
- the operation data includes the heat load of the air conditioning section 14, the room temperature of the air conditioning section 14, the power consumption of the air conditioner indoor unit 1, the air volume setting, the refrigerant temperature, the refrigerant pressure, or the compressor frequency.
- the heat load of the air conditioning compartment 14 represents the amount of heat for cooling or heating provided to the air conditioning compartment 14 by the air conditioner indoor unit 1.
- the air volume setting of the air conditioner indoor unit 1 represents the air volume of a fan provided in the air conditioner indoor unit 1 that sends cooled or heated air to the air conditioning section 14.
- the refrigerant temperature refers to the temperature of the refrigerant in any one or more of the compressor, condenser, or evaporator when the air conditioning system 20 uses a refrigeration cycle as a heat source.
- the refrigerant pressure refers to the refrigerant pressure at one or more of the discharge side of the compressor or the downstream side of the expansion valve when the air conditioning system 20 uses a refrigeration cycle as a heat source.
- the compressor frequency refers to the driving frequency of the compressor that circulates refrigerant when the air conditioning system 20 uses a refrigeration cycle as a heat source.
- a case where the air conditioning system 20 uses a refrigeration cycle as a heat source will be described as an example.
- the heat load prediction unit 4 predicts the heat load during the power supply and demand adjustment period. For example, the heat load prediction unit 4 predicts the heat load of the air conditioning section 14 during the power supply and demand adjustment period based on past operation data of the air conditioning system 20 stored in the heat load history information storage unit 6. The heat load prediction unit 4 predicts the heat load of the plurality of air conditioning sections 14 for each air conditioning section 14.
- the heat load can be determined from the temperature difference between the room temperature of the air conditioning compartment 14 that the air conditioner indoor unit 1 sucks in and the air that it discharges, and the air volume of the fan.
- it can also be determined from the difference between the inlet pressure and the outlet pressure of the refrigerant of the air conditioner indoor unit 1, and the difference between the inlet temperature and the outlet temperature.
- the heat load prediction unit 4 stores a database that links accumulated heat load data from past operations with outside temperature, solar radiation, room occupancy information, room temperature information, humidity information, ventilation heat amount, etc. ing.
- the heat load prediction unit 4 compares information such as weather forecasts (outside temperature, solar radiation) for the desired time period, usage information of the air conditioning section 14, temperature changes in the room temperature, etc. with a stored database, thereby calculating the amount of heat load. Predict. This improves the accuracy of heat load prediction.
- the heat load prediction unit 4 can improve the prediction accuracy of the heat load by using the thermal image of the air conditioning section 14 obtained by the infrared sensor and the sensor information obtained by the humidity sensor.
- the prediction accuracy can be improved by updating the accumulated data stored in the thermal load history information storage section 6 with the newly obtained thermal load data and performing AI learning.
- the heat load prediction unit 4 updates the past operation data stored in the heat load history information storage unit 6 using the future heat load predicted and obtained by the heat load prediction unit 4, and performs AI learning. , it is possible to improve the prediction accuracy of heat load.
- AI learning is used to rank which information has the greatest impact on the prediction, and based on the results, the weighting of the information used for prediction is determined. adjust.
- the allowable heat storage amount calculation unit 9 calculates the allowable heat storage amount that can be stored in the air conditioning section 14 during the power supply and demand adjustment preparation period.
- the allowable heat storage amount calculation unit 9 predicts the amount of heat that can be stored from past temperature data of each air conditioning section 14.
- the allowable heat storage amount calculation unit 9 calculates, for example, the heat load when the heat storage operation was performed during the power supply and demand adjustment preparation period from past operation data, and the heat load when the air conditioning system 20 stopped operation or reduced the heat load during the power supply and demand adjustment period. In this case, it can be determined from how long a predetermined temperature range can be maintained in each air conditioning section 14.
- the allowable heat storage amount calculation unit 9 can improve the calculation accuracy of the allowable heat storage amount by referring to the outside temperature, weather information, and information on the number of users of the target air conditioning section 14, as well as predicting the heat load. .
- the allowable heat storage amount calculation unit 9 measures the amount of heat storage in the air conditioning section 14 based on the amount of change in room temperature with respect to the heat load applied to the air conditioning section 14.
- the allowable heat storage amount calculation unit 9 improves the accuracy of estimating the amount of heat storage by accumulating data regarding the amount of change in room temperature for a given heat load from past operation data accumulated in the heat load history information storage unit 6. be able to.
- the allowable heat storage amount calculation unit 9 calculates the amount of heat storage when the room temperature changes to the target temperature, based on the data of the amount of change in room temperature with respect to the heat load applied to the air conditioning section 14 in the past, which is accumulated in the heat load history information storage unit 6. Allowances can be calculated. Further, the allowable heat storage amount calculation unit 9 can improve the accuracy of the allowable heat storage amount calculated from past operating data, the outside temperature, the amount of solar radiation, occupancy information, humidity information, and ventilation heat amount at that time.
- the operation plan creation unit 18 calculates the heat load of the air conditioning compartment 14 during the power supply and demand adjustment period predicted by the heat load prediction unit 4 and the heat storage in the air conditioning compartment 14 during the power supply and demand adjustment preparation period calculated by the heat storage allowance calculation unit 9. Create an operation plan for air conditioning operation and heat storage operation based on the allowable amount of heat storage.
- the period operation efficiency calculation unit 17 calculates the period operation efficiency of the air conditioning operation during the power supply and demand adjustment period and the heat storage operation during the power supply and demand adjustment preparation period when the operation plan created by the operation plan creation unit 18 is executed.
- the period operation efficiency calculation unit 17 determines the period operation efficiency based on the outside temperature, indoor temperature, indoor unit air volume, indoor set temperature, etc. included in the operation data stored in the heat load history information storage unit 6.
- Other influencing parameters may include weather forecast data, solar radiation to the outdoor unit, indoor heat load (exhaust heat from people and machinery), etc. This makes it possible to accurately calculate the operating efficiency during the operating period.
- the power consumption calculating unit 19 calculates the amount of power consumed in the power supply and demand adjustment period from the periodic operation efficiency in the power supply and demand adjustment period calculated by the periodic operation efficiency calculation unit 17. Further, the power consumption calculation unit 19 calculates the amount of power consumed in the power supply and demand adjustment preparation period from the periodic operation efficiency in the power supply and demand adjustment preparation period calculated by the period operation efficiency calculation unit 17. The power consumption calculation unit 19 updates the amount of power consumption calculated during the power supply and demand adjustment preparation period and the power supply and demand adjustment period.
- the power supply and demand adjustment allowance calculation unit 16 calculates the power supply and demand adjustment allowance that can be used to adjust the power supply and demand, from the power consumption calculated by the power consumption calculation unit 19. Specifically, the power supply and demand adjustment allowable amount calculation unit 16 calculates the amount of power consumed based on the difference between the power consumption calculated by the power consumption calculation unit 19 and the period power consumption (predicted value) when operating using the conventional control method. Calculate the power supply and demand adjustment allowance.
- the conventional control method refers to an operation control method when power supply and demand adjustment is not performed.
- the power supply and demand adjustment allowable amount calculation unit 16 uses temperature information detected by a temperature sensor 30 provided in the air conditioner indoor unit 1 and past air conditioner information stored in the heat load history information storage unit 6.
- the power supply and demand adjustment allowable amount can be calculated from the operation data of the indoor unit 1. Furthermore, the power supply and demand adjustment allowable amount calculation unit 16 accurately adjusts the power supply and demand by calculating the power supply and demand adjustment allowable amount from the information obtained from the room occupancy detection unit 2 and the information obtained from the air conditioning compartment usage information storage unit 15. Allowances can be calculated. Therefore, it is possible to prevent a decrease in operating efficiency due to excessive heat storage and a large deviation in power consumption from the supply and demand adjustment command value.
- the power supply and demand adjustment allowance calculated by the power supply and demand adjustment allowance calculation unit 16 is transmitted to the outside via a communication line such as the Internet.
- FIG. 5 is a flowchart of operation control of the air conditioning system 20 according to the second embodiment.
- the operation from when the air conditioning system 20 receives the power adjustment command until the end of the supply and demand adjustment period will be described with reference to FIG. 5.
- the power supply and demand adjustment command receiving unit 5 receives a power supply and demand adjustment command from the outside via a communication line such as the Internet (step S11).
- the power supply and demand adjustment command receiving unit 5 acquires the power supply and demand adjustment period, the amount of power adjustment, the power adjustment consideration, etc. based on the received power supply and demand adjustment command.
- the heat load prediction unit 4 predicts the heat load of the air conditioning section 14 during the power supply and demand adjustment period based on the past operation data of the air conditioning system 20 stored in the heat load history information storage unit 6 (Ste S12).
- the allowable heat storage amount calculation unit 9 calculates the allowable heat storage amount that can be stored in the air conditioning section 14 during the power supply and demand adjustment preparation period (step S13).
- the operation plan creation section 18 calculates the heat load of the air conditioning section 14 during the power supply and demand adjustment period predicted by the heat load prediction section 4 and the heat load of the air conditioning section 14 during the power supply and demand adjustment preparation period calculated by the heat storage allowance calculation section 9.
- An operation plan for air conditioning operation and heat storage operation is created based on the allowable amount of heat storage that can be stored in 14 (step S14).
- the period operation efficiency calculation unit 17 calculates the period operation efficiency of the air conditioning operation during the electricity supply and demand adjustment period and the heat storage operation during the electricity supply and demand adjustment preparation period when the operation plan created by the operation plan creation unit 18 is executed. (Step S15).
- the power consumption calculation unit 19 calculates the amount of power consumption from the period operation efficiency calculated by the period operation efficiency calculation unit 17 (step S16).
- the power supply and demand adjustment allowance calculation unit 16 calculates the power supply and demand adjustment allowance in the power supply and demand adjustment period from the power consumption calculated by the power consumption calculation unit 19 (step S17).
- the air conditioning system 20 starts power supply and demand adjustment air conditioning and heat storage operation (step S18).
- control unit 3 regularly updates the predicted value of the heat load, the weather forecast data, the air conditioning section usage information, and the calculated power consumption (predicted value) (step S19).
- control unit 3 determines whether the updated power consumption amount is smaller than the initial predicted power amount (threshold value) (step S20).
- step S22 determines whether the power supply and demand adjustment period has expired. If the power supply and demand adjustment period has expired (YES in step S22), the process ends. If the power supply and demand adjustment period has not expired (NO in step S22), the operation continues and the process returns to step S19.
- step S20 if the updated power consumption is greater than or equal to the initial predicted power consumption (NO in step S20), the control unit 3 performs power-saving operation such as setting an upper limit on the compressor frequency and performing a peak cut. is performed (step S21), and the process returns to step S19. That is, after starting the power saving operation, the control unit 3 repeatedly updates the calculated power consumption amount and compares it with the initially predicted power amount.
- the obtained data is referred to as learning data when creating the next power supply and demand adjustment air conditioning and heat storage operation plan (step S14).
- the air conditioning system 20 it is possible to execute an operation plan corresponding to an external power supply and demand adjustment command.
- the amount of power consumption calculated by the power consumption calculation unit 19 during the power supply and demand adjustment preparation period and the power supply and demand adjustment period is updated. If the calculated power consumption is equal to or greater than the threshold, power-saving operation is started.
- the air conditioning system 20 if the power supply and demand adjustment request is of the posiwatt type that increases power consumption, the heat storage operation is performed in addition to the air conditioning operation during the power supply and demand adjustment period, and the power consumption is increased. The amount of electricity can be increased. The heat stored during the power supply and demand adjustment period is used in the air conditioning section 14 after the power supply and demand adjustment period ends.
- the request for electricity supply and demand adjustment is a negawatt type that reduces power consumption
- heat storage operation will be performed in addition to air conditioning operation during the supply and demand adjustment preparation period, and the stored heat will be used to operate air conditioning during the electricity supply and demand adjustment period. By doing so, power consumption can be reduced.
- the air conditioning capacity is adjusted based on information on the presence of people in the air conditioning section 14.
- the air conditioning system 20 consumes less power. Electric power consumption can be reduced.
- Embodiment 2 in light of the monetary compensation obtained by responding to the power supply and demand adjustment command (for example, incentives such as discounts on electricity rates), It is also possible to control the operation of the air conditioning system 20 therein.
- Each functional unit of the control unit 3 operates during the power supply and demand adjustment period and so as to allow a decrease in efficiency with respect to conventional control of the air conditioning system 20 within a range that does not impair the compensation (threshold value) obtained by responding to the power supply and demand adjustment command. It is possible to determine operating conditions during the preparation period for power supply and demand adjustment.
- an optimal control algorithm can be selected according to economic efficiency, demand response ability, and purpose.
- Embodiment 3 the period operation efficiency of the air conditioning system 20 is improved by determining the heat storage priority order.
- FIG. 6 is a functional block diagram showing the functions of the control unit 3 in the air conditioning system 20 according to the third embodiment. Note that the same parts as those in FIG. 4 are denoted by the same reference numerals, and here, the newly shown heat radiation amount prediction section 21 and heat storage priority setting section 8 will be explained.
- the heat radiation amount prediction unit 21 calculates and predicts the amount of heat radiation to the outside of each air conditioning section 14.
- the heat radiation amount prediction unit 21 calculates the heat radiation amount when the minimum amount of heat storage is stored in each air conditioning section that is a heat storage target.
- the amount of heat radiation is calculated from the temperature change in the room temperature of the air conditioning section 14 that is the target.
- the temperature change is measured using data from the temperature sensor 30 provided in the air conditioner indoor unit 1 or the temperature sensor 30 separately provided in the air conditioning compartment 14.
- temperature data with weather prediction data such as outside temperature and amount of solar radiation, or usage information of the air conditioning section 14, the accuracy of predicting the amount of heat radiation can be improved.
- the heat storage priority setting unit 8 is based on the heat release amount of each air conditioning section 14 predicted by the heat release amount prediction section 21 and the period operation efficiency in heat storage operation of the air conditioning section 14 calculated by the period operation efficiency calculation section 17. , determines the heat storage priority of each air conditioning section 14.
- the heat storage priority setting unit 8 also calculates the operating efficiency of each air conditioning section 14 in heat storage operation calculated by the period operation efficiency calculation section 17 and the heat radiation amount prediction result of each air conditioning section 14 predicted by the heat radiation amount prediction section 21.
- the priority order of heat storage and the amount of heat storage in each air conditioning section 14 are calculated from the following.
- the heat storage priority order can be set in advance in addition to the operating efficiency.
- FIG. 7 is a flowchart of operation control of the air conditioning system 20 according to the third embodiment.
- a heat storage target is extracted from the room occupancy information obtained by the room occupancy detection unit 2, the future usage information of the air conditioning compartment 14 obtained by the air conditioning compartment usage information storage unit 15, etc. (step S30).
- the heat storage target is the air conditioning section 14 having the air conditioner indoor unit 1.
- a threshold value of periodic operation efficiency during heat storage operation is determined, which is an index for determining the ratio of the total heat storage amount of the determined heat storage target section to the heat storage amount stored in each heat storage target (step S31).
- the operating efficiency threshold is the lower limit of operating efficiency that is set to determine the allowable amount of heat storage in heat storage operation. The allowable heat storage amount is determined in the subsequent flow within a range that does not fall below this lower limit.
- the heat radiation amount prediction unit 21 calculates the heat radiation amount when the minimum amount of heat storage is stored in each air conditioning section 14 (step S32).
- the operating efficiency of each air conditioning section 14 during heat storage is calculated from the calculated heat radiation amount and past operating data stored in the heat load history information storage section 6 (step S33).
- the operating efficiency can be determined from the calculated heat radiation amount of each air conditioning section 14 and the heat load required in each air conditioning section 14 during heat storage.
- the initial value of the heat storage amount given as a condition is provisionally given from past performance data.
- heat storage priorities are determined in descending order of the calculated operating efficiency of each air conditioning section 14 (step S34).
- the ratio of heat storage amount in each air conditioning section 14 is changed so that the period operation efficiency is maximized (step S35).
- the period operation efficiency is the operation efficiency of all target sections of the air conditioning system 20 during the calculation target period.
- the period operation efficiency is the operation efficiency during heat storage operation.
- step S36 if the calculated period operation efficiency is equal to or greater than the threshold value (NO in step S36), there is still heat storage capacity, so the total heat storage amount is increased (step S37), and the process returns to step S32 to increase the heat release amount again. Do calculations. If the period operation efficiency is smaller than the threshold (YES in step S36), the determination of heat storage priority is ended.
- the control unit 3 performs processing according to the set heat storage priority order. Specifically, the heat load prediction unit 4 of the control unit 3, the heat storage allowance calculation unit 9, the operation plan creation unit 18, the period operation efficiency calculation unit 17, the power consumption calculation unit 19, the power supply and demand adjustment allowance calculation unit 16, and The heat radiation amount prediction unit 21 performs heat storage operation in the air conditioning section 14 according to the set heat storage priority order. During the heat storage operation, when the room occupancy information or the usage information of the air conditioning section 14 is updated, the heat storage priority order is updated.
- the operating efficiency during heat storage operation can be improved and power consumption can be reduced.
- the priority order of the heat storage operation of each air conditioning section 14 is determined using the operating efficiency according to the heat radiation amount of each air conditioning section 14. For example, an air conditioning section 14 that does not face the outdoors has a high priority for heat storage operation because it radiates a small amount of heat to the outdoors, and an air conditioning section 14 that faces the outdoors and radiates a large amount of heat to the outdoors has a high priority for heat storage operation. lower priority. Therefore, heat radiation loss from the air conditioning section 14 can be reduced, and the period operation efficiency of the air conditioning system 20 can be improved.
- the air-conditioning compartment 14 to be subjected to heat storage is the wall, ceiling, and floor of the air-conditioning compartment 14 equipped with the air conditioner indoor unit 1, a heat storage tank provided separately from these, or the wall of the air-conditioning compartment 14, etc. It is possible to use the structures of surrounding buildings.
- the heat storage priority may be set in advance. By setting heat storage priorities in advance, it is possible to quickly respond to supply and demand adjustment commands from the outside.
- the threshold value of the period operation efficiency is set to the period operation efficiency during non-thermal storage operation, the amount of power consumption can be reduced compared to during non-thermal storage operation.
- air conditioning operation with high cost performance can be performed by determining the threshold value of periodic operation efficiency from the monetary consideration obtained by responding to power supply and demand adjustment.
- FIG. 8 is a schematic diagram showing a building equipped with an air conditioning system 20 according to the fourth embodiment.
- the air conditioning system 20 of Embodiment 4 uses a refrigeration cycle as a heat source.
- the air conditioning system 20 includes at least one multi-air conditioner in which a plurality of air conditioner indoor units 1 are connected to one air conditioner outdoor unit 10 via a refrigerant relay device 22. ing.
- the air conditioner outdoor unit 10, the refrigerant relay machine 22, and the air conditioner indoor unit 1 are connected to each other by piping, and the refrigerant circulates through these piping.
- the air conditioner outdoor unit 10 is provided with a heat exchanger that exchanges heat between refrigerant and air.
- the refrigerant relay device 22 is provided with a flow path switching device that switches the flow path of the refrigerant toward each of the plurality of air conditioner indoor units 1. By switching the flow path switching device by the control unit 3, the heat exchanger provided in the air conditioner indoor unit 1 functions as a refrigerant condenser or evaporator.
- the control unit 3 controls the air heat exchanger of the air conditioner indoor unit 1 in the air conditioning section 14 where no one is present. is used as a condenser or evaporator.
- the air conditioner indoor unit 1 in the air conditioning compartment 14 where a person is present is referred to as the first indoor unit
- the air conditioner indoor unit 1 where no person is present is referred to as the second indoor unit
- the first indoor unit When performing cooling operation, the flow path switching device of the refrigerant relay device 22 is controlled so that the air heat exchanger provided in the second indoor unit functions as a condenser.
- the flow path switching device of the refrigerant relay device 22 is controlled so that the air heat exchanger provided in the second indoor unit functions as an evaporator.
- the air conditioning system 20 of Embodiment 4 can also be used in Embodiments 1, 2, and 3.
- the stored heat amount can be transferred faster than when the stored heat amount is transferred by heat conduction through the wall surface of the room. If the heat load during the power supply and demand adjustment period becomes larger than initially expected, air at a temperature lower than the outside temperature can be used as a heat source, making it possible to reduce power consumption during the power supply and demand adjustment period.
- Embodiments 1 to 3 are applied to air conditioning systems that use an electric heater or a gas furnace as a heat source in addition to air conditioning systems that use a refrigeration cycle as a heat source.
- Air conditioner indoor unit 2. Room occupancy detection section, 3. Control section, 4. Heat load prediction section, 5. Electric power supply and demand adjustment command receiving section, 6. Heat load history information storage section, 7. Required heat storage amount calculation section, 8. Heat storage priority order. Setting section, 9 Allowable heat storage amount calculation section, 10 Air conditioner outdoor unit, 11 Refrigerant distributor, 12 Room usage reservation information storage section, 13 Heat storage tank, 14 Air conditioning section, 15 Air conditioning section usage information storage section, 16 Power supply and demand adjustment Allowable amount calculation section, 17. Periodic operation efficiency calculation section, 18. Operation plan creation section, 19. Power consumption calculation section, 20. Air conditioning system, 21. Heat radiation amount prediction section, 22. Refrigerant relay machine, 30. Temperature sensor, B. Building.
Landscapes
- Air Conditioning Control Device (AREA)
Abstract
空気調和システムは、空調区画に備わる空気調和機室内ユニットと、空調区画において人の存在又は不在を示す在室情報を検出する在室検出部と、在室検出部により検出した在室情報が空調区画における人の不在を示している場合に、空気調和機室内ユニットの運転条件を、空気調和機室内ユニットに対して設定された運転条件で運転したときよりも空調能力が大きくなるように変更する制御部とを具備する。
Description
本開示は、躯体蓄熱型の空気調和システムに関する。
前日の蓄熱量から必要な蓄熱量を算出することで、必要以上に蓄熱することによる消費電力の増加を抑制する躯体蓄熱型の空気調和システムが知られている(例えば特許文献1)。
このような躯体蓄熱型の空気調和システムでは、対象となる空調区画を使用する際の設定温度になるまでしか蓄熱することができず、蓄熱量が小さいという問題がある。一方、蓄熱量を大きくするために、対象となる空調区画を設定温度から大きく逸脱する温度になるまで蓄熱すると、対象となる空調区画の利用者の快適性が損なわれる。
本開示は、上記実情に鑑みてなされたものであり、対象となる空調区画の快適性を損なうことなく蓄熱を増加することができる躯体蓄熱型の空気調和システムを提供することを目的とする。
本開示に係る空気調和システムは、空調区画に備わる空気調和機室内ユニットと、前記空調区画において人の存在又は不在を示す在室情報を検出する在室検出部と、前記在室検出部により検出した前記在室情報が前記空調区画における人の不在を示している場合に、前記空気調和機室内ユニットの運転条件を、前記空気調和機室内ユニットに対して設定された運転条件で運転したときよりも空調能力が大きくなるように変更する制御部とを具備する。
本開示によれば、空気調和システムの制御部が、在室検出部が空調区画の不在を示している場合に、空気調和機室内ユニットの運転条件を能力が大きくなるように変更する。従って、空気調和システムは、利用者が不在の空調区間を蓄熱槽として利用でき、対象となる空調区画の快適性を損なうことなく空調区画に蓄熱できる。
以下、図面を参照して、実施形態に係る空気調和システムについて説明する。なお、図面において、同一の構成要素には同一符号を付して説明し、重複説明は必要な場合にのみ行う。本開示は、以下の各実施形態で説明する構成のうち、組合せ可能な構成のあらゆる組合せを含み得る。
実施形態1.
図1は、実施形態1に係る空気調和システム20を備えた建物Bを示す概略図である。図1に示すように、空気調和システム20は、空気調和機室内ユニット1、在室検出部2、制御部3及び空調区画利用情報蓄積部15を有する。
図1は、実施形態1に係る空気調和システム20を備えた建物Bを示す概略図である。図1に示すように、空気調和システム20は、空気調和機室内ユニット1、在室検出部2、制御部3及び空調区画利用情報蓄積部15を有する。
建物B内には、空調区画14は複数存在する。空気調和機室内ユニット1は空調区画14毎に設けられる。空気調和機室内ユニット1は、空調区画14内に冷却された空気を供給する冷房運転と、加熱された空気を供給する暖房運転とのいずれかを実行する。建物B内の1フロアを1つの空調区画14としてもよいし、1部屋を1つの空調区画14としてもよいし、1部屋内の一部の領域を1つの空調区画14としてもよい。本実施形態の空気調和システム20は、いずれか1つ以上の空調区画14を蓄熱槽として利用する躯体蓄熱型の空気調和システム20である。
在室検出部2は、空気調和機室内ユニット1が設置されている空調区画14の少なくとも一つに設けられる。図1においては、人が示されている空調区画14と、人が示されていない空調区画14のそれぞれに在室検出部2が設けられている場合を示している。在室検出部2は、空調区画14において人の存在又は不在を示す在室情報を検出する。在室検出部2は、赤外線センサ、カードリーダーの検出情報、熱画像センサ、照度センサ又は空調区画14における機器等である。在室検出部2は,検出した在室情報を制御部3に入力する。
制御部3は、インターネットなどの通信回線を介して、制御対象となる空気調和機室内ユニット1と通信可能に接続されている。制御部3は、空気調和機室内ユニット1を制御する。制御部3は、在室検出部2により検出した在室情報が空調区画14における人の不在を示している場合に、空気調和機室内ユニット1の運転条件を、当該空気調和機室内ユニット1に対して設定された運転条件で運転したときよりも空調能力が大きくなるように変更する。具体的には、制御部3は、在室検出部2により検出した在室情報が空調区画14における人の不在を示している場合に、冷房時には空気調和機室内ユニット1の空調区画14の設定温度を低く、暖房時には空気調和機室内ユニット1の設定温度を高くする。
制御部3の処理回路が専用のハードウェアである場合、処理回路は、例えば、単一回路、複合回路、ASIC(Application Specific Integrated Circuit)、FPGA(Field Programmable Gate Array)、又はこれらを組み合わせたものが該当する。処理回路が実現する各機能部のそれぞれを、個別のハードウェアで実現してもよいし、各機能部が一つのハードウェアで実現されてもよい。制御部3の処理回路がCPUの場合、処理回路が実行する各機能は、ソフトウェア、ファームウェア、又はソフトウェアとファームウェアとの組み合わせにより実現される。ソフトウェア及びファームウェアはプログラムとして記述され、記憶部109に格納される。CPUは、記憶部に格納されたプログラムを読み出して実行することにより、処理回路の各機能を実現する。なお、処理回路の機能の一部を専用のハードウェアで実現し、一部をソフトウェア又はファームウェアで実現するようにしてもよい。
空調区画利用情報蓄積部15は、将来の空調区画14の利用予定の情報を蓄積する。空調区画利用情報蓄積部15は、インターネットなどの通信回線を介して、制御部3と通信可能に接続されている。空調区画利用情報蓄積部15には、会議室の予約システムなどを用いても良い。
動作.
次に、実施形態1に係る空気調和システム20における空気調和機室内ユニット1の動作について説明する。図2は、実施形態1に係る空気調和機室内ユニット1の動作を説明するためのフローチャートである。
次に、実施形態1に係る空気調和システム20における空気調和機室内ユニット1の動作について説明する。図2は、実施形態1に係る空気調和機室内ユニット1の動作を説明するためのフローチャートである。
図2に示すように、在室検出部2が空調区画14における人の存在又は不在を示す在室情報を検出する(ステップS1)。次に、制御部3は、在室検出部2により検出した在室情報が空調区画14における人の不在を示しているか否かを判断する(ステップS2)。
制御部3は、空調区画利用情報蓄積部15に蓄積された将来の空調区画14の利用予定の情報に基づいて、利用する予定のない空調区画14を識別することができる。制御部3は、識別された利用する予定のない空調区画14のみの在室情報を判断しても良い。
ステップS3において、制御部3が在室検出部2により検出した在室情報が空調区画14における人の不在を示していないと判断した場合(ステップS3のNO)、制御部3は、在室検出部2が設けられた空調区画14の空気調和運転を継続するように、空気調和機室内ユニット1を制御する(ステップS4)。
ステップS3において、制御部3が在室検出部2により検出した在室情報が空調区画14における人の不在を示している判断した場合(ステップS3のYES)、冷房時には空気調和機室内ユニット1の空調区画14の設定温度を低く、暖房時には空気調和機室内ユニット1の設定温度を高くする(ステップS5)。
不在の空調区画14に蓄えられた熱は、その後の人が在室する際の空調運転時などに、空調区画14間の壁から空気への伝熱及び輻射などにより、空調区画14の空気調和に利用される。
なお、空気調和機室内ユニット1の運転条件を、当該空気調和機室内ユニット1に対して設定された運転条件で運転したときよりも空調能力が大きくなるように変更する他の例としては、次のようなものが挙げられる。具体的に、制御部3は、不在であることを確認できた空調区画14において、空気調和機室内ユニット1が運転していなかった場合に、空気調和運転を開始しても良い。また、制御部3は、不在であることを確認できた空調区画14の空気調和機室内ユニット1のファンの風量を増加しても良い。
制御部3は、ステップS3において、例えば30分~1時間程度の不在判定期間に在室検出部2から在室情報を繰り返し取得し、この不在判定期間の在室情報がすべて人の不在を示している場合に、人が不在であると判断してもよい。これにより、制御部3は、人の存在及び不在の誤識別を防ぐことができる。
制御部3は、過去の利用情報に基づいて選択された利用頻度が少ない空調区画14を、優先的に蓄熱槽として使用するようにしてもよい。具体的に、空調区画利用情報蓄積部15は、過去の空調区画14の利用履歴の情報を蓄積し、制御部3は、蓄積された利用履歴に基づいて、それぞれの空調区画14の利用頻度を判定する。そして、制御部3は、在室検出部2からの在室情報に基づいて複数の空調区画14において人が不在であると判断された場合には、必要な蓄熱量に応じた数の空調区画14の数に応じて、利用頻度の低い空調区画14の空気調和機室内ユニット1を優先的に動作させる。利用頻度の低い空調区画14を優先的に蓄熱槽として利用することで、建物Bの利用者の快適性を損ないにくい。
制御部3は、空調区画利用情報蓄積部15に蓄積された将来の空調区画14の利用予定の情報に基づいて、消費電力量を削減したい期間に空調区画14の利用が予定されている場合に、消費電力量を削減したい期間の前に空気調和機室内ユニット1を稼働しても良い。消費電力量を削減したい期間の前に、空調区画14に蓄熱するのである。これにより、消消費電力量を削減したい期間の空気調和機室内ユニット1の消費電力を削減することができる。
実施形態1の空気調和システム20によれば、在室検出部2により得られた在室情報から、不在であることを確認できた空調区画14の空気調和機室内ユニット1の運転条件を、当該空気調和機室内ユニット1に対して設定された運転条件で運転したときよりも空調能力が大きくなるように変更する。従って、実施形態1の空気調和システム20によれば、人が不在の空調区画14に冷熱、又は温熱を蓄えることができる。そのため、快適性を損なうことなく空調区画14を蓄熱槽として利用することができる。また、蓄熱槽としての空調区画14に蓄えた冷熱又は温熱は、その後の空気調和システム20の空調運転に利用される。
また、冷房時には、人が不在の空調区画14に対応した空気調和機室内ユニット1の設定温度を、人が在室するときの冷房時の設定温度よりも下げる。また、暖房時には、人が不在の空調区画14に対応した空気調和機室内ユニット1の設定温度を、人が在室するときの暖房時の設定温度よりも上げる。これにより、人が不在の空調区画14における蓄熱量を増加することができる。
実施形態2.
実施形態2では、空気調和システム20が電力需給調整指令を受信してから電力需給調整期間が終了するまでの動作を説明する。「電力需給調整期間」は、電力需給調整指令に基づいて実際に空気調和システム20の消費電力を調整する期間を示す。ここで、「電力需給調整期間」における消費電力の調整には、消費電力を増加させるポジワット型の調整と、消費電力を低減させるネガワット型の調整とがある。「電力需給調整期間」において消費電力を増加させる場合には、「電力需給調整期間」に空気調和システム20が蓄熱運転を行う。また、「電力需給調整期間」において消費電力を低減させる場合には、「電力需給調整期間」の前に「電力需給調整準備期間」が設けられる。「電力需給調整準備期間」は、電力需給調整期間の前に蓄熱運転を行う期間を示す。
実施形態2では、空気調和システム20が電力需給調整指令を受信してから電力需給調整期間が終了するまでの動作を説明する。「電力需給調整期間」は、電力需給調整指令に基づいて実際に空気調和システム20の消費電力を調整する期間を示す。ここで、「電力需給調整期間」における消費電力の調整には、消費電力を増加させるポジワット型の調整と、消費電力を低減させるネガワット型の調整とがある。「電力需給調整期間」において消費電力を増加させる場合には、「電力需給調整期間」に空気調和システム20が蓄熱運転を行う。また、「電力需給調整期間」において消費電力を低減させる場合には、「電力需給調整期間」の前に「電力需給調整準備期間」が設けられる。「電力需給調整準備期間」は、電力需給調整期間の前に蓄熱運転を行う期間を示す。
なお、実施形態1における人の在、不在に合わせて設定を変更する動作は、上記の「電力需給調整期間」及び「電力需給調整準備期間」における空気調和システム20の蓄熱運転の動作である。
実施形態2に係る空気調和システム20の構成は、図1に示した空気調和システム20と同様であり、図1と同一の部分には同一符号を付して説明する。図3は、実施形態2に係る空気調和システム20における空気調和機室内ユニット1を示す図である。図2に示すように、空調区画14に設けられる空気調和機室内ユニット1は、温度センサ30を有する。
温度センサ30は、制御部3と接続されており、空調区画14の室温を測定し、測定された室温を制御部3に出力する。
図4は、実施形態2に係る空気調和システム20における制御部3の機能を示す機能ブロック図である。
図4に示すように、制御部3は、電力需給調整指令受信部5、熱負荷履歴情報蓄積部6、熱負荷予測部4、蓄熱許容量計算部9、運転計画作成部18、期間運転効率計算部17、消費電力計算部19及び電力需給調整許容量計算部16を具備する。
電力需給調整指令受信部5は、外部からの電力需給調整指令をインターネットなどの通信回線を介して受信する。電力需給調整指令受信部5は、受信した電力需給調整指令に基づいて、電力需給調整期間、電力調整量及び電力調整対価等を取得する。なお、電力需給調整指令受信部5は、電力需給調整指令に基づいて、電力需給調整期間、電力調整量及び電力調整対価等を他のサーバ等から取得しても良い。
電力需給調整指令は、アグリゲータ、電力会社等から発令される。電力需給調整指令は、例えば、「明日の16時から19時まで電力使用量を100kW以下にする」等の内容の電力需給調整指令である。電力需給調整指令には、需給調整期間、電力調整量、及び電力調整対価等の情報が含まれるが、これらの情報の一部又は全部が、別途契約などで予め定められていても良い。電力需給調整指令のすべての情報が契約などで予め定められている場合には、電力需給調整指令受信部5は、制御部3の図示しないメモリに予め記憶された情報を読み出す。
熱負荷履歴情報蓄積部6は、過去の空気調和機室内ユニット1の運転データを蓄積する。ここで、運転データには、空調区画14の熱負荷、空調区画14の室温、若しくは空気調和機室内ユニット1の消費電力、風量設定、冷媒温度、冷媒圧力又は圧縮機周波数等がある。
空調区画14の熱負荷とは、空気調和機室内ユニット1によって空調区画14に供された冷房又は暖房の熱量を表している。空気調和機室内ユニット1の風量設定とは、空気調和機室内ユニット1に設けられ冷却又は加熱された空気を空調区画14に送出するファンの風量を表している。冷媒温度は、空気調和システム20が冷凍サイクルを熱源として用いる場合の、圧縮機、凝縮器又は蒸発器のいずれか1つ以上における冷媒の温度をいう。冷媒圧力は、空気調和システム20が冷凍サイクルを熱源として用いる場合の、圧縮機の吐出側又は膨張弁の下流側のいずれか1つ以上における冷媒の圧力をいう。圧縮機周波数は、空気調和システム20が冷凍サイクルを熱源として用いる場合に冷媒を循環させる圧縮機の、駆動周波数をいう。以下、本実施形態では、空気調和システム20が冷凍サイクルを熱源として用いる場合を例に説明する。
熱負荷予測部4は、電力需給調整期間の熱負荷を予測する。例えば、熱負荷予測部4は、熱負荷履歴情報蓄積部6に蓄積されている過去の空気調和システム20の運転データに基づいて、電力需給調整期間における空調区画14の熱負荷を予測する。熱負荷予測部4は、複数の空調区画14の熱負荷を空調区画14毎に予測する。
次に、熱負荷の測定方法について説明する。例えば、空気調和機室内ユニット1が吸い込む空調区画14の室温と、吐き出す空気の温度差、及びファンの風量から熱負荷を求めることができる。又は、空気調和機室内ユニット1の冷媒の入口圧力と出口圧力との差、及び入口温度と出口温度との差から求めることもできる。
次に、熱負荷の予測方法について説明する。熱負荷予測部4は、過去の運転での熱負荷の蓄積データと、そのときの外気温、日射量、在室情報、室温情報、湿度情報及び換気熱量等とを紐づけたデータベースを記憶している。熱負荷予測部4は、予測したい時間帯の気象予測(外気温、日射量)、空調区画14の利用情報、室温の温度推移等の情報を、記憶したデータベースと照合することで、熱負荷量を予測する。これにより、熱負荷の予測の精度が向上する。
また、熱負荷予測部4は、赤外線センサによる空調区画14の熱画像及び湿度センサによるセンサ情報を利用することで、熱負荷の予測精度を向上できる。
ここで、新たに得られる熱負荷のデータにより、熱負荷履歴情報蓄積部6に蓄積されている蓄積データを更新し、AI学習を行うことによって予測精度を向上できる。
熱負荷予測部4は、熱負荷予測部4によって予測して得られた将来の熱負荷により、熱負荷履歴情報蓄積部6に蓄積された過去の運転データを更新し、AI学習を行うことにより、熱負荷の予測精度を向上することができる。
例えば、予測した熱負荷と、測定した熱負荷とから、どの情報が予測に最も影響が大きいかをAI学習により順位付けを行い、その結果をもとに予測の際に用いる情報の重みづけを調整する。
蓄熱許容量計算部9は、電力需給調整準備期間において空調区画14に蓄熱できる蓄熱許容量を計算する。蓄熱許容量計算部9は、各空調区画14の過去の温度データなどから蓄熱できる量を予測する。蓄熱許容量計算部9は、例えば、過去の運転データから電力需給調整準備期間に蓄熱運転をした際の熱負荷と、電力需給調整期間に空気調和システム20が運転を停止又は熱負荷を低減した際に、どれだけの間、各空調区画14で所定の温度範囲を維持できたかから求めることができる。
蓄熱許容量計算部9は、熱負荷の予測と同様に、外気温、気象情報、対象となる空調区画14の利用人数の情報も参照することで蓄熱許容量の計算精度を向上することができる。
次に蓄熱量の測定方法について説明する。蓄熱許容量計算部9は、空調区画14に与えた熱負荷に対する室温の変化量から空調区画14の蓄熱量を測定する。蓄熱許容量計算部9は、熱負荷履歴情報蓄積部6に蓄積された過去の運転データから、与えた熱負荷に対する室温の変化量に関するデータを蓄積することにより、蓄熱量の推定精度を向上することができる。
次に、蓄熱許容量計算部9による蓄熱許容量の計算方法について説明する。蓄熱許容量計算部9は、熱負荷履歴情報蓄積部6に蓄積された過去の空調区画14に与えた熱負荷に対する室温の変化量のデータを元に、目的温度まで室温が変化した際の蓄熱許容量を計算することができる。また、蓄熱許容量計算部9は、過去の運転データと、そのときの外気温、日射量、在室情報、湿度情報及び換気熱量から計算する蓄熱許容量の精度を向上することができる。
運転計画作成部18は、熱負荷予測部4によって予測された電力需給調整期間における空調区画14の熱負荷と、蓄熱許容量計算部9によって計算された電力需給調整準備期間において空調区画14に蓄熱できる蓄熱許容量とに基づいて、空調運転及び蓄熱運転の運転計画を作成する。
期間運転効率計算部17は、運転計画作成部18により作成された運転計画を実行した際の電力需給調整期間における空調運転及び電力需給調整準備期間における蓄熱運転の期間運転効率を計算する。
期間運転効率計算部17は、熱負荷履歴情報蓄積部6に蓄積されている運転データに含まれる外気温と室内温度、室内機風量及び室内設定温度等に基づいて、期間運転効率を定める。その他影響を与えるパラメータとして、気象予測データ、室外機への日射量、室内の熱負荷(人、機械類からの排熱)等を含めても良い。これにより、運転期間の運転効率を正確に計算することができる。
消費電力計算部19は、期間運転効率計算部17により計算された電力需給調整期間における期間運転効率から、電力需給調整期間における消費電力量を計算する。また、消費電力計算部19は、期間運転効率計算部17により計算された電力需給調整準備期間における期間運転効率から、電力需給調整準備期間における消費電力量を計算する。消費電力計算部19は、電力需給調整準備期間及び電力需給調整期間中に計算された消費電力量を更新する。
電力需給調整許容量計算部16は、消費電力計算部19によって計算された消費電力量から、電力需給調整できる電力需給調整許容量を計算する。具体的には、電力需給調整許容量計算部16は、消費電力計算部19によって計算された消費電力量と、従来の制御方法で運転した場合の期間消費電力量(予測値)との差から電力需給調整許容量を計算する。ここで従来の制御方法は、電力需給調整を実施しない場合の運転制御方法を指す。また、電力需給調整許容量計算部16は、空気調和機室内ユニット1に備わっている温度センサ30により検出される温度情報と、熱負荷履歴情報蓄積部6に蓄積されている過去の空気調和機室内ユニット1の運転データとから電力需給調整許容量を計算することができる。さらに、電力需給調整許容量計算部16は、在室検出部2から得られる情報、空調区画利用情報蓄積部15により得られる情報から電力需給調整許容量を計算することによって、正確に電力需給調整許容量を計算することができる。従って、必要以上に蓄熱することによる運転効率の低下及び需給調整指令値から消費電力量が大きく外れることを防ぐことができる。
電力需給調整許容量計算部16により計算された電力需給調整許容量は、インターネットなどの通信回線を介して外部に送信される。
図5は、実施形態2に係る空気調和システム20の運転制御のフローチャートである。以下、空気調和システム20が電力調整指令を受信してから需給調整期間が終了するまでの動作について、図5を参照して説明する。
電力需給調整指令受信部5が、外部からの電力需給調整指令をインターネットなどの通信回線を介して受信する(ステップS11)。電力需給調整指令受信部5は、受信した電力需給調整指令に基づいて、電力需給調整期間、電力調整量及び電力調整対価等を取得する。
次に、熱負荷予測部4が、熱負荷履歴情報蓄積部6に蓄積されている過去の空気調和システム20の運転データに基づいて、電力需給調整期間における空調区画14の熱負荷を予測する(ステップS12)。次に、蓄熱許容量計算部9が、電力需給調整準備期間において空調区画14に蓄熱できる蓄熱許容量を計算する(ステップS13)。
次に、運転計画作成部18が、熱負荷予測部4によって予測された電力需給調整期間における空調区画14の熱負荷と、蓄熱許容量計算部9によって計算された電力需給調整準備期間において空調区画14に蓄熱できる蓄熱許容量とに基づいて、空調運転及び蓄熱運転の運転計画を作成する(ステップS14)。
次に、期間運転効率計算部17が、運転計画作成部18により作成された運転計画を実行した際の電力需給調整期間における空調運転及び電力需給調整準備期間における蓄熱運転の期間運転効率を計算する(ステップS15)。
次に、消費電力計算部19が、期間運転効率計算部17により計算された期間運転効率から消費電力量を計算する(ステップS16)。電力需給調整許容量計算部16が、消費電力計算部19によって計算された消費電力量から、電力需給調整期間における電力需給調整許容量を計算する(ステップS17)。
次に、空気調和システム20が電力需給調整空調及び蓄熱運転を開始する(ステップS18)。
制御部3は、運転開始後も定期的に熱負荷の予測値、気象予測データ及び空調区画利用情報、計算された消費電力量(予測値)を更新する(ステップS19)。
次に、制御部3は、更新された消費電力量が当初の予測電力量(閾値)よりも小さいか否かを判断する(ステップS20)。
制御部3は、更新された消費電力量が当初の予測電力量よりも小さい場合(ステップS20のYES)、電力需給調整期間が満了しているかを判断する(ステップS22)。電力需給調整期間が満了している場合(ステップS22のYES)、処理を終了する。電力需給調整期間が満了していない場合(ステップS22のNO)、運転を継続し、ステップS19の処理に戻る。
一方、ステップS20において、更新された消費電力量が当初の予測電力量以上である場合(ステップS20のNO)、制御部3は、圧縮機周波数に上限を設けてピークカットする等の省電力運転を行い(ステップS21)、ステップS19に戻る。すなわち、制御部3は、省電力運転を開始後、定期的に計算された消費電力量を更新し、当初の予測電力量と比較する操作を繰り返し行う。
電力需給調整期間が終了した後、得られたデータは学習データとして次回の電力需給調整空調及び蓄熱運転計画の作成時(ステップS14)に参照される。
従って、実施形態2に係る空気調和システム20によれば、外部からの電力需給調整指令に対応した運転計画の実行を行うことができる。
また、電力需給調整準備期間及び電力需給調整期間中に消費電力計算部19によって計算された消費電力量を更新する。計算された消費電力量が閾値以上だった場合には、省電力運転を開始する。
これにより、実施形態2に係る空気調和システム20によれば、電力需給調整要請が消費電力を増加するポジワット型の内容であれば、電力需給調整期間に空調運転に加えて蓄熱運転を行い、消費電力量を増加することができる。電力需給調整期間に蓄えられた熱は、電力需給調整期間が終了した後に空調区画14にて使用される。また、電力需給調整要請が消費電力を削減するネガワット型の内容であれば、需給調整準備期間に、空調運転の他に蓄熱運転を行い、電力需給調整期間にその蓄えた熱を用いて空調運転を行うことによって、消費電力量を削減することができる。この蓄熱運転においては、実施形態1で説明したように、空調区画14における人の在室情報に基づいて、空調能力が調整される。
また、電力需給調整期間中又は電力需給調整準備期間中に更新された消費電力量が当初の予測電力量(閾値)よりも大きい場合には、省電力運転を行なうので、空気調和システム20の消費電力量を削減することができる。
さらに、実施形態2によれば、電力需給調整指令に応じることによって得られる金銭的な対価(例えば、電気料金から値引き等のインセンティブ)に照らし合わせて、電力需給調整期間中及び電力需給調整準備期間中の空気調和システム20の運転を制御することもできる。電力需給調整指令に応じることによって得られる対価(閾値)を損なわない範囲で、空気調和システム20の従来制御に対する効率低下を許容するように、制御部3の各機能部が電力需給調整期間中及び電力需給調整準備期間中の運転条件を決定できる。実施形態2によれば、経済性、デマンドレスポンス力及び目的に応じて最適な制御アルゴリズムを選択できる。
実施形態3.
実施形態3では、蓄熱優先順位の判定を行うことにより、空気調和システム20の期間運転効率を向上するものである。
実施形態3では、蓄熱優先順位の判定を行うことにより、空気調和システム20の期間運転効率を向上するものである。
図6は、実施形態3に係る空気調和システム20における制御部3の機能を示す機能ブロック図である。なお、図4と同一部分には、同一符号を付し、ここでは新たに示した放熱量予測部21及び蓄熱優先順位設定部8について説明する。
放熱量予測部21は、各空調区画14の外部への放熱量を計算して予測する。放熱量予測部21は、蓄熱対象である各空調区画に最小蓄熱量を蓄熱した際の放熱量を計算する。放熱量は、対象となる空調区画14の室温の温度変化から計算する。
ここで、温度変化は、空気調和機室内ユニット1に備え付けられた温度センサ30、又は別途空調区画14内に設けられた温度センサ30のデータを利用して測定される。
また、外気温、日射量などの気象予測データ、又は空調区画14の利用情報などと温度データとを組み合わせることで、放熱量の予測精度を向上できる。
蓄熱優先順位設定部8は、放熱量予測部21により予測された各空調区画14の放熱量と、期間運転効率計算部17により計算された空調区画14の蓄熱運転における期間運転効率とに基づいて、各空調区画14の蓄熱優先順位を決定する。また、蓄熱優先順位設定部8は、期間運転効率計算部17により計算された各空調区画14の蓄熱運転における運転効率と、放熱量予測部21より予測された各空調区画14の放熱量予測結果から蓄熱する優先順位及び各空調区画14の蓄熱量を計算する。蓄熱優先順位は、運転効率だけではなく、予め設定しておくこともできる。
以下、蓄熱優先順位設定の手順について説明する。図7は、実施形態3に係る空気調和システム20の運転制御のフローチャートである。
まず、在室検出部2により得られる在室情報、空調区画利用情報蓄積部15により得られる将来の空調区画14の利用情報などから、蓄熱対象を抽出する(ステップS30)。ここで、蓄熱対象は空気調和機室内ユニット1を有する空調区画14である。
次に、決定した蓄熱対象区画の総蓄熱量と、各蓄熱対象に蓄熱する蓄熱量の比率を決定するための指標となる蓄熱運転時の期間運転効率の閾値を決定する(ステップS31)。ここで、運転効率の閾値は、蓄熱運転における許容蓄熱量を決めるために設定する運転効率の下限値である。この下限値を下まわらない範囲で、以降のフローで蓄熱許容量を求める。
次に、放熱量予測部21により、各空調区画14に最小蓄熱量を蓄熱した際の放熱量を計算する(ステップS32)。
次に、計算された放熱量と熱負荷履歴情報蓄積部6に蓄積されている過去の運転データとから蓄熱時の各空調区画14の運転効率を計算する(ステップS33)。運転効率は、計算した各空調区画14の放熱量と、各空調区画14において必要となる蓄熱時の熱負荷から求めることができる。条件として与える蓄熱量の初期値は、過去の実績データなどから仮に与える。
次に、計算された各空調区画14の運転効率が高い順に蓄熱優先順位を決定する(ステップS34)。
次に、期間運転効率が最大になるように、各空調区画14の蓄熱量の比率を変更する(ステップS35)。ここで、期間運転効率は、空気調和システム20の全対象区画の計算対象期間の運転効率である。
次に、求められた期間運転効率が閾値よりも小さいかを判断する(ステップS36)。ここで、期間運転効率は、蓄熱運転時の運転効率である。
次に、計算された期間運転効率が閾値以上であれば(ステップS36のNO)、まだ蓄熱する能力があるため、総蓄熱量を増加し(ステップS37)、ステップS32に戻り、再度放熱量の計算行う。期間運転効率が閾値よりも小さければ(ステップS36のYES)、蓄熱優先順位の決定を終了する。
制御部3は、設定された蓄熱優先順位に従って処理を行なう。具体的には、制御部3の熱負荷予測部4、蓄熱許容量計算部9、運転計画作成部18、期間運転効率計算部17、消費電力計算部19、電力需給調整許容量計算部16及び放熱量予測部21は、設定された蓄熱優先順位に従って空調区画14における蓄熱運転を行なう。蓄熱運転中に、在室情報又は空調区画14の利用情報が更新された際には、蓄熱優先順位を更新する。
実施形態3に係る空気調和システム20によれば、蓄熱運転時の運転効率を向上し、消費電力を削減することができる。また、各空調区画14の放熱量に応じた運転効率を用いて、各空調区画14の蓄熱運転の優先順位が決定される。例えば屋外に面していない空調区画14は、屋外への放熱量が少ないことから蓄熱運転の優先順位が高くなり、屋外に面していて屋外への放熱量が多い空調区画14の蓄熱運転の優先順位が低くなる。このため、空調区画14からの放熱ロスを削減することができ、空気調和システム20の期間運転効率を向上することができる。
ここで、蓄熱対象とする空調区画14は、空気調和機室内ユニット1が備えられた空調区画14の壁、天井及び床、これらとは別に設けられた蓄熱槽、又は空調区画14の壁等の周囲にある建物躯体などを利用することができる。
ここで、蓄熱優先順位は、あらかじめ設定されていてもよい。蓄熱優先順位をあらかじめ設定しておくことによって外部からの需給調整指令に迅速に対応することができる。
ここで、期間運転効率の閾値を、非蓄熱運転時の期間運転効率とすることで、消費電力量を非蓄熱運転時よりも削減することができる。
ここで、期間運転効率の閾値を、電力需給調整に応じることによって得られる金銭的な対価から求めることで、コストパフォーマンスの高い空調運転を行うことができる。
実施形態4.
図8は、実施形態4に係る空気調和システム20を備えた建物を示す概略図である。実施形態4の空気調和システム20は、冷凍サイクルを熱源として用いる。
図8は、実施形態4に係る空気調和システム20を備えた建物を示す概略図である。実施形態4の空気調和システム20は、冷凍サイクルを熱源として用いる。
実施形態4に係る空気調和システム20は、1つの空気調和機室外ユニット10に、冷媒中継機22を介して複数の空気調和機室内ユニット1が接続されているマルチ空気調和機を少なくとも一つ備えている。空気調和機室外ユニット10、冷媒中継機22及び空気調和機室内ユニット1は互いに配管接続されており、この配管を冷媒が循環する。空気調和機室外ユニット10には、冷媒と空気との間で熱交換する熱交換器が設けられている。冷媒中継機22には、複数の空気調和機室内ユニット1のそれぞれへ向かう冷媒の流路を切り換える流路切替装置が設けられている。流路切替装置が制御部3によって切り換えられることによって、空気調和機室内ユニット1に設けられた熱交換器が、冷媒の凝縮器又は蒸発器として機能する。
制御部3は、空調区画14を用いた躯体蓄熱による蓄熱量が、要求される熱負荷よりも大きい場合には、人が不在である空調区画14の空気調和機室内ユニット1の空気熱交換器を、凝縮器又は蒸発器として使用する。具体的に、人が存在する空調区画14の空気調和機室内ユニット1を第1室内ユニットと称し、人が不在の空気調和機室内ユニット1を第2室内ユニットと称すると、第1室内ユニットで冷房運転をするときには、第2室内ユニットに備わる空気熱交換器を凝縮器として機能させるよう、冷媒中継機22の流路切替装置を制御する。第1室内ユニットで暖房運転をするときには、第2室内ユニットに備わる空気熱交換器を蒸発器として機能させるよう、冷媒中継機22の流路切替装置を制御する。
実施形態4の空気調和システム20は、実施形態1、実施形態2及び実施形態3にも起用することはできる。
従って、実施形態4に係る空気調和システム20によれば、蓄えた熱量を部屋の壁面を介した熱伝導で伝熱するよりも早く熱量を移動することができる。電力需給調整期間の熱負荷が当初の想定よりも大きくなった場合に、外気温よりも低い温度の空気を熱源にすることができるため、電力需給調整期間の消費電力を削減することができる。
実施形態は、例として提示したものであり、請求の範囲を限定することは意図していない。実施形態は、その他の様々な形態で実施されることが可能であり、実施形態の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。これら実施形態及びその変形は、実施形態の範囲及び要旨に含まれる。また、実施形態1~3は、冷凍サイクルを熱源として用いる空気調和システムのほか、電気ヒータ又はガスファーネスを熱源として用いる空気調和システムにも適用される。
1 空気調和機室内ユニット、2 在室検出部、3 制御部、4 熱負荷予測部、5 電力需給調整指令受信部、6 熱負荷履歴情報蓄積部、7 必要蓄熱量計算部、8 蓄熱優先順位設定部、9 蓄熱許容量計算部、10 空気調和機室外ユニット、11 冷媒分配器、12 部屋利用予約情報蓄積部、13 蓄熱タンク、14 空調区画、15 空調区画利用情報蓄積部、16 電力需給調整許容量計算部、17 期間運転効率計算部、18 運転計画作成部、19 消費電力計算部、20 空気調和システム、21 放熱量予測部、22 冷媒中継機、30 温度センサ、B 建物。
Claims (8)
- 空調区画に備わる空気調和機室内ユニットと、
前記空調区画において人の存在又は不在を示す在室情報を検出する在室検出部と、
前記在室検出部により検出した前記在室情報が前記空調区画における人の不在を示している場合に、前記空気調和機室内ユニットの運転条件を、前記空気調和機室内ユニットに対して設定された運転条件で運転したときよりも空調能力が大きくなるように変更する制御部と
を具備する空気調和システム。 - 前記在室情報が前記空調区画における人の不在を示している場合に、前記制御部は、冷房時には前記空調区画における前記空気調和機室内ユニットの設定温度を低く、暖房時には前記空調区画における前記空気調和機室内ユニットの前記設定温度を高くする
請求項1記載の空気調和システム。 - 前記空気調和機室内ユニットの運転データを蓄積する熱負荷履歴情報蓄積部を具備し、
前記制御部は、
前記熱負荷履歴情報蓄積部に蓄積された前記空調区画の前記運転データと、電力需給調整指令とに基づいて実際に消費電力を調整する期間である電力需給調整期間における前記空調区画の熱負荷を予測する熱負荷予測部と、
前記電力需給調整期間の前に蓄熱運転を行う期間である電力需給調整準備期間において前記空調区画に蓄熱できる蓄熱許容量を計算する蓄熱許容量計算部と、
前記熱負荷予測部によって予測された前記電力需給調整期間における前記空調区画の熱負荷と、前記蓄熱許容量計算部によって計算された前記電力需給調整準備期間において前記空調区画に蓄熱できる蓄熱許容量とに基づいて、空調運転及び蓄熱運転の運転計画を作成する運転計画作成部と
を具備する請求項1又は2に記載の空気調和システム。 - 前記運転計画作成部により作成された前記運転計画を実行した際の前記電力需給調整期間における前記空調運転及び前記電力需給調整準備期間における前記蓄熱運転の期間運転効率を計算する期間運転効率計算部と、
前記期間運転効率計算部により計算された前記期間運転効率から前記電力需給調整期間における消費電力量を計算する消費電力計算部と
を具備する請求項3記載の空気調和システム。 - 前記電力需給調整指令を受信する電力需給調整指令受信部を具備し、
前記熱負荷予測部は、前記電力需給調整指令受信部にて受信した前記電力需給調整指令から前記電力需給調整期間を取得する
請求項3又は4に記載の空気調和システム。 - 前記消費電力計算部によって計算された消費電力量から、前記電力需給調整期間に電力需給調整できる電力量である電力需給調整許容量を計算する電力需給調整許容量計算部
を具備する請求項4に記載の空気調和システム。 - 前記空調区画は複数であり、
前記空調区画の外部への放熱量を計算する放熱量予測部と、
前記放熱量予測部により計算された前記空調区画の放熱量と、前記期間運転効率計算部により計算された前記空調区画の前記蓄熱運転における前記期間運転効率とに基づいて、前記複数の空調区画の蓄熱優先順位を決定する蓄熱優先順位設定部とを具備し、
前記制御部は、前記蓄熱優先順位設定部により決定された優先順位に基づいて前記複数の空調区画対する空調運転を行う
請求項4又は6に記載の空気調和システム。 - 前記空気調和機室内ユニットは、熱交換器を備えた第1室内ユニットと、熱交換器を備えた第2室内ユニットとを有し、
前記第1室内ユニットと前記第2室内ユニットとの一方が冷房運転を実行するときには、他方の前記熱交換器を凝縮器として機能させ、前記第1室内ユニットと前記第2室内ユニットとの一方が暖房運転を実行するときには、他方の前記熱交換器を蒸発器として機能させる
請求項1~7のいずれか1項に記載の空気調和システム。
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2024505731A JPWO2023170828A1 (ja) | 2022-03-09 | 2022-03-09 | |
PCT/JP2022/010328 WO2023170828A1 (ja) | 2022-03-09 | 2022-03-09 | 空気調和システム |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/JP2022/010328 WO2023170828A1 (ja) | 2022-03-09 | 2022-03-09 | 空気調和システム |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2023170828A1 true WO2023170828A1 (ja) | 2023-09-14 |
Family
ID=87936332
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2022/010328 WO2023170828A1 (ja) | 2022-03-09 | 2022-03-09 | 空気調和システム |
Country Status (2)
Country | Link |
---|---|
JP (1) | JPWO2023170828A1 (ja) |
WO (1) | WO2023170828A1 (ja) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05306848A (ja) * | 1992-04-30 | 1993-11-19 | Matsushita Seiko Co Ltd | 熱回収型マルチエアコン |
JP2012233620A (ja) * | 2011-04-28 | 2012-11-29 | Mitsubishi Electric Corp | 空調装置、空調方法及びプログラム |
JP2016142491A (ja) * | 2015-02-04 | 2016-08-08 | 株式会社日立製作所 | 熱源システムの運転管理装置、熱源システムの運転管理方法およびコンピュータプログラム |
JP2018148790A (ja) * | 2018-04-17 | 2018-09-20 | 三菱電機株式会社 | コントローラ、スケジュール作成方法、及びプログラム |
US20200132324A1 (en) * | 2018-10-29 | 2020-04-30 | Johnson Controls Technology Company | Systems and methods for thermal storage in a zoning system |
-
2022
- 2022-03-09 JP JP2024505731A patent/JPWO2023170828A1/ja active Pending
- 2022-03-09 WO PCT/JP2022/010328 patent/WO2023170828A1/ja unknown
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05306848A (ja) * | 1992-04-30 | 1993-11-19 | Matsushita Seiko Co Ltd | 熱回収型マルチエアコン |
JP2012233620A (ja) * | 2011-04-28 | 2012-11-29 | Mitsubishi Electric Corp | 空調装置、空調方法及びプログラム |
JP2016142491A (ja) * | 2015-02-04 | 2016-08-08 | 株式会社日立製作所 | 熱源システムの運転管理装置、熱源システムの運転管理方法およびコンピュータプログラム |
JP2018148790A (ja) * | 2018-04-17 | 2018-09-20 | 三菱電機株式会社 | コントローラ、スケジュール作成方法、及びプログラム |
US20200132324A1 (en) * | 2018-10-29 | 2020-04-30 | Johnson Controls Technology Company | Systems and methods for thermal storage in a zoning system |
Also Published As
Publication number | Publication date |
---|---|
JPWO2023170828A1 (ja) | 2023-09-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8655492B2 (en) | Air-conditioning apparatus control device and refrigerating apparatus control device | |
CN104110799B (zh) | 空调器电子膨胀阀的综合控制方法及电路 | |
US10088211B2 (en) | Air-conditioning apparatus | |
JP7170740B2 (ja) | 情報処理装置およびこれを備えた空調システム | |
JP4957342B2 (ja) | 空気調和システム及び空調管理装置 | |
US20060207269A1 (en) | Multi-air conditioner peak power control system and control method thereof | |
CN111237995B (zh) | 一种空调冷机的控制方法 | |
WO2015173868A1 (ja) | 空調装置 | |
CN102265097A (zh) | 负载处理均衡设定装置 | |
JP5404556B2 (ja) | 空気調和機の制御装置および冷凍装置の制御装置 | |
GB2516577A (en) | Air conditioning device | |
WO2021033231A1 (ja) | 情報処理装置 | |
JP4811077B2 (ja) | 空調システム | |
CN113366266A (zh) | 空调管理装置、空调管理系统、空调管理方法以及程序 | |
JP2003065588A (ja) | 空気調和装置 | |
EP3221944A1 (en) | A method for operating at least one distributed energy resource comprising a refrigeration system | |
CN115654665B (zh) | 空调及其控制方法、存储介质 | |
US10830474B2 (en) | Systems and methods of predicting energy usage | |
JP6053201B2 (ja) | 冷凍装置 | |
KR101078010B1 (ko) | 복합 열원 공조 시스템 장치 및 이의 제어 방법 | |
WO2023170828A1 (ja) | 空気調和システム | |
EP4184072B1 (en) | System for determining operation condition of precooling operation/preheating operation of air conditioner | |
JP5677198B2 (ja) | 空冷ヒートポンプチラー | |
JP2012007887A (ja) | 空気調和システム及び空調管理装置 | |
JP7199529B2 (ja) | 制御装置、空気環境調整システム、空気環境調整方法、プログラム、及び記録媒体 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 22930811 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2024505731 Country of ref document: JP Kind code of ref document: A |