WO2023066327A1 - Construction method for underground building consisting of sinking wall foundation - Google Patents

Construction method for underground building consisting of sinking wall foundation Download PDF

Info

Publication number
WO2023066327A1
WO2023066327A1 PCT/CN2022/126352 CN2022126352W WO2023066327A1 WO 2023066327 A1 WO2023066327 A1 WO 2023066327A1 CN 2022126352 W CN2022126352 W CN 2022126352W WO 2023066327 A1 WO2023066327 A1 WO 2023066327A1
Authority
WO
WIPO (PCT)
Prior art keywords
wall
construction
pile
excavation
sinking
Prior art date
Application number
PCT/CN2022/126352
Other languages
French (fr)
Chinese (zh)
Inventor
王树生
Original Assignee
王树生
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王树生 filed Critical 王树生
Publication of WO2023066327A1 publication Critical patent/WO2023066327A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/26Placing by using several means simultaneously
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars

Definitions

  • the invention relates to the technical field of underground building construction, in particular to a construction method for an underground building composed of sinking wall foundations.
  • Existing large-scale underground buildings are often constructed by the open-cut method.
  • the open-cut method needs to excavate the foundation pit first for support and precipitation, and then pour or assemble the underground building in the foundation pit.
  • the process is complicated, the cost is expensive, and the construction period is long. There is a larger impact on the surrounding high-rise buildings.
  • the chain knife is easy to break and the driving power is greatly increased; it is easy to tilt when falling, and it is difficult to correct the deviation; The amount and sinking speed are out of control, and the cutter head is easy to wear.
  • the object of the present invention is to provide a construction method for an underground building composed of sinking wall foundations, so as to solve the problems mentioned in the above-mentioned background technology.
  • the building located underground comprises sinking wall foundation, slot pile, top plate, base plate, connecting body and construction device
  • sinking wall foundation is exactly the strip foundation under the wall of building, underground continuous wall
  • the exterior wall that is directly sunk in place without digging a foundation pit, and the adjacent exterior walls are connected by slot piles, and the adjacent slot piles and exterior walls are completed with slot piles first
  • the sunken wall construction of the outer wall is directly carried out on the ground.
  • the construction device includes a wall construction device and a pile sinking device.
  • the wall construction device includes a bottom excavation device and a hanging device on the top of the outer wall.
  • the hanging device hangs the outer wall, and the bottom digging device excavates the rock and soil at the bottom of the outer wall.
  • the section of the upper part of the slot pile includes an excavation groove. The width of the excavation groove is greater than or equal to the thickness of the two ends of the outer wall.
  • the pile sinking device includes a frame, a pile pressing device, a pile external drilling rig and an excavation pipe
  • the bottom of the slotted pile includes the positioning hole of the excavation pipe and the inclined cone at the bottom of the pile
  • the excavation pipe is located outside the slotted pile
  • the drill pipe of the drilling machine outside the pile is located in the unearthed pipe
  • the drilling tool at the bottom of the drill pipe protrudes out of the unearthed pipe.
  • the bottom excavation device includes a hydraulic excavation device
  • the hydraulic excavation device includes a scouring device and a pumping device
  • the scouring device includes a pipeline frame at the bottom of the outer wall, and the outer wall is suspended by the hanging device
  • the two ends of the outer wall include a transverse boss, and the bottom of the transverse boss includes a wall corner oblique cone surface.
  • the device is sent out, and the unearthed groove includes a C-shaped groove for fitting with the outer wall.
  • the maximum width of the C-shaped groove is greater than or equal to the thickness of the outer wall at the horizontal boss;
  • the wall construction device includes a formwork, and the outer wall is poured in the formwork.
  • the construction method of the external wall includes the construction method A of sinking while pouring, and the construction method B of sinking after all the pouring is completed.
  • the building is an underground tunnel
  • the construction area of the underground tunnel longitudinally includes a pile construction section, an outer wall construction section, a support construction section, an excavation section, a floor construction section and a roof construction section
  • the construction device includes Temporary support and building construction are carried out in flow operation according to the sequence of each construction section, and the main steps are as follows:
  • the construction method of described building is cover and dig method, and its main steps are as follows:
  • described building is basement, and basement comprises two-story basement, and second-floor basement comprises middle plate, and middle plate comprises middle plate beam, and the main construction steps of second-floor basement are as follows:
  • the building includes a mid-wall located between the exterior walls on both sides, the mid-wall includes a bottom mid-wall below the floor and an upper mid-wall above the bottom slab, and the mid-wall includes a full mid-wall and a column mid-wall
  • the two structures, the bottom middle wall and the upper middle wall in the full middle wall and the bottom middle wall in the column-in-wall adopt the same structure as the outer wall, and the upper middle wall in the column-in-wall includes columns arranged longitudinally inside the building,
  • the bottom excavation device includes a mid-wall excavation device, and the mid-wall excavation device excavates the bottom of the mid-wall
  • the rock and soil, columns and longitudinal mid-slab girders sink synchronously with the mid-wall in the grooves excavated by the mid-wall excavation device.
  • the hanging device includes a steel strand hydraulic lifting jack, and the steel strand hydraulic lifting jack adopts a core-through structure hydraulic lifter as the lifting tool, and the wedge-shaped anchorages at both ends of the hydraulic lifter have a one-way self- When the anchor is working, it will automatically lock the steel strand. When the anchor is not working, let go of the steel strand, and the steel strand can move up and down. The hydraulic lifting jacks of several steel strands are synchronously and slowly lifted. The wall is sunk in the suspended state.
  • the descending speed of the hanging device is controlled to meet different geological conditions.
  • the sinking wall foundation is a three-wall-in-one structure, which is particularly easy to adopt prefabricated buildings.
  • the permanent roof, floor slab or beam in the underground structure can be used as support, and the sinking wall foundation is replaced by a strip foundation under the wall
  • the traditional pile foundation can also play the role of a water-stop curtain. It is a rapid wall sinking construction method without foundation pits and supports.
  • the invention reduces the weight of the sinking construction of a single structural part through the split structure of the slot pile and the wall, and adds a hanging device.
  • the sinking speed is controllable and does not cause tilt.
  • Fig. 1 is a top view of an underground building 1, and is also a schematic structural view of an outer wall 2A, a slot pile 3, a roof 1-1 and a connecting body 1-3 forming the building 1;
  • Fig. 2 is the A-direction view of Fig. 1, and it is also a structural schematic diagram of the construction device 4 carrying out the subsidence construction of the outer wall 2A after the construction of the slot pile 3 is completed first, and it is also a structural schematic diagram of the bottom excavation device 5 using a chain knife to excavate the bottom rock and soil ;
  • Fig. 3 is a structural schematic diagram of the sinking construction of the slotted pile 3 by the pile sinking device 4B, and is also a structural schematic diagram of the part of the outer wall 2A that has been constructed between the two slotted piles 3;
  • Fig. 4 is the A-A view of Fig. 1, and also the drilling rig 4B-3 outside the pile passes through the drilling tool 4B-3-2 at the bottom of the drill pipe 4B-3-1 to excavate a large area of rock and soil at the bottom of the trench pile 3, and the rock and soil in other areas pass through Schematic diagram of the pile bottom inclined cone surface 3-3 pushing the rock and soil below to the drilling tool 4B-3-2;
  • Fig. 5 is the top view of slot pile 3;
  • Fig. 6 is a schematic structural view of the external wall 2A sinking construction through the hydraulic excavation device 5A;
  • Fig. 7 is a view of A-A of Fig. 6, which is also a schematic structural view of the flushing device 5A-1;
  • Fig. 8 is a schematic diagram of the structure of the external wall 2A, which is composed of a chain 5B-1 and a cutter 5B-2, and the wire saw 5B excavates the rock and soil at the bottom to carry out sinking construction;
  • Fig. 9 is a left view of Fig. 8, and it is also a structural schematic diagram of a wall angle tapered surface 2-1-1 provided at the bottom of the transverse boss 2-1;
  • Fig. 10 is a schematic diagram of the structure of the lateral boss 2-1 of the outer wall 2A embedded in the C-shaped groove 3-1C of the groove pile 3;
  • Fig. 11 is a schematic structural view of the outer wall 2A being poured in the template 4-2;
  • Fig. 12 shows that the construction area 6 includes pile construction section 6-1, exterior wall construction section 6-2, support construction section 6-3, excavation section 6-4, floor construction section 6-5 and roof construction section 6- Schematic diagram of the structure of 6;
  • Fig. 13 is the A-A view of Fig. 12;
  • Fig. 14 is that the construction method is the cover excavation method, after the construction of the outer wall 2A, the structural representation of the roof 1-1 is first constructed;
  • Fig. 15 is a structural schematic diagram of excavating the internal rock and soil after completing the construction of the top plate 1-1, and then completing the construction of the bottom plate 1-2;
  • FIG. 16 is a schematic structural view of a building 1 including a wall-in-column 9B between the outer walls 2A on both sides;
  • Fig. 17 is the A-A view of Fig. 16, and it is also a structural schematic diagram of the column middle wall 9B consisting of the bottom middle wall 9-1 below the bottom plate 1-2 and the upper middle wall 9-2 above;
  • Fig. 18 is a C-C view of Fig. 16, which is also a structural schematic diagram of longitudinally arranged longitudinal mid-plate beams 1-4-1X between adjacent columns 9-2-1;
  • Fig. 19 is a structural schematic diagram of the middle wall excavating device 59 excavating the rock and soil at the bottom of the middle wall 9;
  • Fig. 20 is a schematic structural view of the building 1 including the full central wall 9A;
  • Fig. 21 is the B-B view of Fig. 20;
  • 1 in the figure is the building; 11 is the underground tunnel; 12 is the basement; 12A is the second-floor basement; 2 is the sinking wall foundation; 1A is the strip foundation under the wall; 1B is the underground continuous wall; 1 is the top plate; 1-2 is the bottom plate; 1-3 is the connecting body; 1-4 is the middle plate; 1-4-1 is the middle plate beam; 1-4-1X is the longitudinal middle plate beam; 2A is the outer wall; 2X is the longitudinal outer wall; 2Y is the horizontal outer wall; 2-1 is the horizontal boss; 2-1-1 is the inclined cone surface of the wall corner; 3 is the slot pile; 3-1 is the excavation slot; 3-1C is the C-shaped slot ; 3-2 is a positioning hole; 3-3 is an inclined cone at the bottom of the pile; 4 is a construction device; 4-1 is a hanging device; 4-1A is a steel strand hydraulic lifting jack; 4A is a wall construction device; 4B is Pile sinking device; 4B-1 is the frame; 4B-2 is the pile pressing device; 4B
  • the building 1 located underground includes a sinking wall foundation 2, a slot pile 3, a top plate 1-1, a bottom plate 1-2, a connecting body 1-3 and a construction device 4, and the sinking wall foundation 2 is the strip foundation 1A under the wall of building 1, the underground continuous wall 1B and the structural exterior wall 1C.
  • the construction device 4 includes the wall construction device 4A and
  • the pile sinking device 4B and the wall construction device 4A include a bottom digging device 5 and a hanging device 4-1 positioned at the top of the outer wall 2A.
  • the hanging device 4-1 hangs the outer wall 2A, and the bottom digging device 5 excavates
  • the pile sinking device 4B includes a frame 4B-1, a pile pressing device 4B-2, a pile external drilling machine 4B-3 and an excavation pipe 4B-4, and the bottom of the slotted pile 3 includes a positioning hole 3- of the excavation pipe 4B-4. 2 and the inclined cone surface 3-3 at the bottom of the pile, the unearthed pipe 4B-4 is located in the unearthed groove 3-1 outside the grooved pile 3, and the drill pipe 4B-3-1 of the external drilling rig 4B-3 is located in the unearthed pipe 4B-4 , the drilling tool 4B-3-2 at the bottom of the drill pipe 4B-3-1 protrudes out of the excavation pipe 4B-4.
  • the pile pressing device 4B-2 presses the grooved pile 3 into the bottom, and the inclined cone surface 3 at the bottom of the pile -3 Squeeze the rock and soil below to the drilling tool 4B-3-2, and the external pile drilling rig 4B-3 sends the rock and soil at the bottom to the top through the excavation pipe 4B-4;
  • the pile pressing device 4B-2 includes an impact hammer and a vibratory hammer and static pressure devices.
  • the bottom excavation device 5 includes a hydraulic excavation device 5A, the hydraulic excavation device 5A includes a flushing device 5A-1 and a pumping device 5A-2, and the flushing device 5A-1 includes a pipeline frame 5A-1-1 at the bottom of the outer wall 2A. 1. Put the outer wall 2A in a suspended state through the hanging device 4-1, start the pumping device 5A-2, and the scouring device 5A-1 at the bottom of the outer wall 2A excavates the rock and soil, and the excavated rock and soil pass through the excavation tank 3- 1 is transported to the top to realize the sinking operation of the outer wall 2A.
  • the bottom excavation device 5 can also adopt the structure of a wire saw 5B, the wire saw 5B is composed of a chain 5B-1 and a cutter 5B-2, and the wire saw 5B at the bottom of the outer wall 2A To excavate rock and soil, the wire saw 5B from bottom to top will bring the excavated rock and soil to the top in the excavation groove 3-1.
  • the two ends of the outer wall 2A include a transverse boss 2-1, and the bottom of the transverse boss 2-1 includes a wall angle tapered surface 2-1-1.
  • the excavation groove 3-1 includes a C-shaped groove 3-1C for fitting with the outer wall 2A, and the maximum width of the C-shaped groove 3-1C is greater than or equal to the horizontal direction.
  • the building 1 is an underground tunnel 11, and the underground tunnel 11 longitudinally includes a pile construction section 6-1, an exterior wall construction section 6-2, a support construction section 6-3, and an excavation section.
  • the construction of the external wall 2A is completed; the hanging device 4-1 hangs the external wall 2A and descends slowly; the bottom digging device 5 excavates the rock and soil at the bottom of the external wall 2A; the excavated rock and soil Unearth through the excavation groove 3-1; the outer wall 2A sinks to the set position;
  • the construction method of described building 1 is cover and dig method, and its main steps are as follows:
  • the building 1 is a basement 12
  • the basement 12 includes a second-floor basement 12A
  • the second-floor basement 12A includes a middle plate 1-4
  • the middle plate 1-4 includes a middle plate beam 1 -4-1.
  • the main construction steps of the second-floor basement 12A are as follows:
  • the construction step 8 can also be completed after the construction step 9 is completed.
  • the tunnel 1 includes a middle wall 9 between the outer walls 2A on both sides, and the middle wall 9 includes a bottom middle wall 9-1 below the bottom plate 1-2 and an upper middle wall 9-2 above the bottom plate 1-2, and the middle wall 9 Including two structures of the full middle wall 9A and the column middle wall 9B, the bottom middle wall 9-1 and the upper middle wall 9-2 of the whole middle wall 9A and the bottom middle wall 9-1 of the column middle wall 9B adopt the same structure as the outer wall
  • the upper middle wall 9-2 in the middle wall 9B includes vertically arranged columns 9-2-1 in the tunnel 1, and longitudinally arranged longitudinal middle plates are included between adjacent columns 9-2-1
  • the beam 1-4-1X, the diameter of the column 9-2-1 and the thickness of the longitudinal middle plate beam 1-4-1X are all less than the thickness of the bottom middle wall 9-1;
  • the bottom excavation device 5 includes a middle wall excavation device 59, the middle wall Wall digging device 59 excavates the rock and soil at the bottom of middle wall 9, and column 9-2-1 and longitudinal middle plate beam
  • the hanging device 4-1 includes a steel strand hydraulic lifting jack 4-1A, and the steel strand hydraulic lifting jack 4-1A adopts a core-through structure hydraulic lifter as a lifting tool, and the wedge-shaped anchors at both ends of the hydraulic lifter have One-way self-locking function, when the anchorage is working tight, it will automatically lock the steel strand, when the anchorage is not loose, release the steel strand, the steel strand can move up and down, several steel strand hydraulic lift jacks 4- 1A is lifted and lowered slowly synchronously, and the outer wall 2A sinks in a suspended state. Due to its own huge dead weight, it is difficult to produce deflection.
  • the external wall 2A satisfies different geological conditions by controlling the descending speed of the hanging device 4-1 during sunken wall construction.
  • connection should be interpreted in a broad sense, for example, it can be fixed connection or detachable connection, or The integrated connection may also be a mechanical connection, or an indirect connection through an intermediary, and the specific meaning of the terms in the present invention may be understood according to specific circumstances.

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to the technical field of underground building construction. Disclosed is a construction method for an underground building consisting of a sinking wall foundation. The underground building comprises the sinking wall foundation, slotted piles, a top plate, a bottom plate, a connecting body, and a construction device; the sinking wall foundation is an external wall which is formed by combining an under-wall strip-shaped foundation, an underground diaphragm wall, and a structural external wall of the building and directly sinks in place without digging a foundation pit after construction is completed on the ground; adjacent external walls are connected by means of the slotted piles; for adjacent slotted piles and external walls, after construction of the slotted piles is completed firstly, the external walls are then directly subjected to wall sinking construction on the ground. The construction device comprises a wall construction device and a pile sinking device; a hanging device hangs the external wall; a bottom excavating device excavates rock soil at the bottom of the external wall, and the excavated rock soil is unearthed by means of an unearthed slot; the external wall sinks to a set position; the rock soil in the unearthed slot is cleaned, the connecting body is poured, and then follow-up construction is conducted till all construction of the building is completed.

Description

用于由沉墙基础组成的地下建筑的施工法Construction method for underground constructions consisting of sunken wall foundations 技术领域technical field
本发明涉及地下建筑施工技术领域,具体是用于由沉墙基础组成的地下建筑的施工法。The invention relates to the technical field of underground building construction, in particular to a construction method for an underground building composed of sinking wall foundations.
背景技术Background technique
现有大型地下建筑物用明挖法施工较多,明挖法需要先开挖基坑做支护和降水,然后在基坑内浇筑或者装配地下建筑,工艺复杂,成本昂贵,施工周期长,而且对周边的高层建筑有较大的。Existing large-scale underground buildings are often constructed by the open-cut method. The open-cut method needs to excavate the foundation pit first for support and precipitation, and then pour or assemble the underground building in the foundation pit. The process is complicated, the cost is expensive, and the construction period is long. There is a larger impact on the surrounding high-rise buildings.
现有地下建筑整体下沉,靠自重下沉,自身的重量全部压在底部链刀上,链刀易断且驱动功率大大增加;下降易产生倾斜,很难纠偏;不能控制下降速度即进刀量,下沉速度完成处于失控状态,刀头容易磨损。The existing underground buildings sink as a whole, relying on their own weight to sink, and their own weight is all pressed on the chain knife at the bottom. The chain knife is easy to break and the driving power is greatly increased; it is easy to tilt when falling, and it is difficult to correct the deviation; The amount and sinking speed are out of control, and the cutter head is easy to wear.
发明内容Contents of the invention
针对现有技术中存在的问题,本发明的目的在于提供用于由沉墙基础组成的地下建筑的施工法,来解决上述背景技术中提到的问题。Aiming at the problems existing in the prior art, the object of the present invention is to provide a construction method for an underground building composed of sinking wall foundations, so as to solve the problems mentioned in the above-mentioned background technology.
为实现上述目的,本发明提供如下技术方案:位于地下的建筑包括沉墙基础、槽桩、顶板、底板、连接体和施工装置,沉墙基础就是建筑的墙下条形基础、地下连续墙和结构外墙三墙合一的在地面完成施工后,不挖基坑直接下沉到位的外墙,相邻的外墙通过槽桩连接,相邻的槽桩和外墙是先完成槽桩的施工后,再在地面上直接进行外墙的沉墙施工,施工装置包括墙施工装置和沉桩装置,墙施工装置包括底部挖掘装置和位于外墙顶部的吊挂装置,沉墙施工时,吊挂装置吊挂外墙,底部挖掘装置挖掘外墙底部的岩土,槽桩上部的截面包括出土槽,出土槽的宽度大于或等于外墙两端的厚度,外墙的两端嵌入出土槽中,已挖掘的岩土通过出土槽进行出土,外墙下沉至设定的位置,清理出土槽中的岩土,浇筑连接体,再进行后续施工,直至完成建筑的全部施工。In order to achieve the above object, the present invention provides the following technical solutions: the building located underground comprises sinking wall foundation, slot pile, top plate, base plate, connecting body and construction device, and sinking wall foundation is exactly the strip foundation under the wall of building, underground continuous wall and After the construction of the three-in-one structural exterior wall is completed on the ground, the exterior wall that is directly sunk in place without digging a foundation pit, and the adjacent exterior walls are connected by slot piles, and the adjacent slot piles and exterior walls are completed with slot piles first After the construction, the sunken wall construction of the outer wall is directly carried out on the ground. The construction device includes a wall construction device and a pile sinking device. The wall construction device includes a bottom excavation device and a hanging device on the top of the outer wall. The hanging device hangs the outer wall, and the bottom digging device excavates the rock and soil at the bottom of the outer wall. The section of the upper part of the slot pile includes an excavation groove. The width of the excavation groove is greater than or equal to the thickness of the two ends of the outer wall. The excavated rock and soil are excavated through the excavation tank, the outer wall is sunk to the set position, the rock and soil in the excavation tank are cleaned, the connecting body is poured, and the follow-up construction is carried out until the entire construction of the building is completed.
作为本发明优选的,所述的沉桩装置包括机架、压桩装置、桩外钻机和出土管,槽桩的底部包括出土管的定位孔和桩底斜锥面,出土管位于槽桩外的出土槽内,桩外钻机的钻杆位于出土管内,位于钻杆底部的钻具伸出出土管,沉桩时,压桩装置将槽桩压入下方,桩底斜锥面将下方的岩土挤向钻具,桩外钻机通过出土管将底部的岩土送至上方。As preferred in the present invention, the pile sinking device includes a frame, a pile pressing device, a pile external drilling rig and an excavation pipe, the bottom of the slotted pile includes the positioning hole of the excavation pipe and the inclined cone at the bottom of the pile, and the excavation pipe is located outside the slotted pile In the unearthed groove, the drill pipe of the drilling machine outside the pile is located in the unearthed pipe, and the drilling tool at the bottom of the drill pipe protrudes out of the unearthed pipe. The soil squeezes to the drilling tool, and the external drilling rig sends the rock and soil at the bottom to the top through the excavation pipe.
作为本发明优选的,所述的底部挖掘装置包括水力挖掘装置,水力挖掘装置包括冲刷装置和泵送装置,冲刷装置包括位于外墙底部的管路架,通过吊挂装置将外墙处于 悬挂状态下,启动泵送装置,外墙底部的冲刷装置挖掘岩土,已挖掘的岩土通过出土槽输送至上方,实现外墙的下沉作业。As preferred in the present invention, the bottom excavation device includes a hydraulic excavation device, the hydraulic excavation device includes a scouring device and a pumping device, the scouring device includes a pipeline frame at the bottom of the outer wall, and the outer wall is suspended by the hanging device Next, start the pumping device, the scouring device at the bottom of the outer wall excavates the rock and soil, and the excavated rock and soil are transported to the upper part through the excavation tank to realize the sinking operation of the outer wall.
作为本发明优选的,所述的外墙的两端包括横向凸台,横向凸台的底部包括墙角斜锥面,沉墙时,墙角斜锥面将下方的岩土挤向中间,被底部挖掘装置送出,出土槽包括用于与外墙嵌合的C型槽,C型槽的最大宽度大于或等于横向凸台处外墙的厚度;墙施工装置包括模板,外墙是在模板内浇筑而成的,外墙的施工法包括采用边浇筑边下沉的施工A法、和采用完成全部浇筑后再下沉的施工B法。As preferred in the present invention, the two ends of the outer wall include a transverse boss, and the bottom of the transverse boss includes a wall corner oblique cone surface. The device is sent out, and the unearthed groove includes a C-shaped groove for fitting with the outer wall. The maximum width of the C-shaped groove is greater than or equal to the thickness of the outer wall at the horizontal boss; the wall construction device includes a formwork, and the outer wall is poured in the formwork. The construction method of the external wall includes the construction method A of sinking while pouring, and the construction method B of sinking after all the pouring is completed.
作为本发明优选的,所述的建筑是地下隧道,地下隧道的施工区域在纵向包括桩施工段、外墙施工段、支护施工段、挖掘段、底板施工段和顶板施工段,施工装置包括临时支护,建筑的施工是按各施工段顺序进行流水作业的,其主要步骤如下:As preferred in the present invention, the building is an underground tunnel, and the construction area of the underground tunnel longitudinally includes a pile construction section, an outer wall construction section, a support construction section, an excavation section, a floor construction section and a roof construction section, and the construction device includes Temporary support and building construction are carried out in flow operation according to the sequence of each construction section, and the main steps are as follows:
1)在桩施工段完成槽桩的施工;1) Complete the construction of the grooved pile in the pile construction section;
2)在外墙施工段:完成外墙的施工;吊挂装置吊挂外墙,缓慢下降;底部挖掘装置挖掘外墙底部的岩土;已挖掘的岩土通过出土槽进行出土;外墙下沉至设定的位置;2) In the construction section of the exterior wall: the construction of the exterior wall is completed; the hanging device hangs the exterior wall and descends slowly; the bottom excavation device excavates the rock and soil at the bottom of the exterior wall; the excavated rock and soil are excavated through the excavation groove; the exterior wall sinks to the set position;
3)在支护施工段完成临时支护的施工;3) Complete the construction of temporary support in the support construction section;
4)在挖掘段完成外墙内全部岩土的挖掘;4) Complete the excavation of all rock and soil inside the outer wall in the excavation section;
5)在底板施工段完成底板的施工;5) Complete the construction of the base plate in the base plate construction section;
6)在顶板施工段完成顶板的施工;6) Complete the construction of the roof in the roof construction section;
7)拆除临时支护,即完成地下隧道的全部施工。7) Remove the temporary support, that is, complete the entire construction of the underground tunnel.
作为本发明优选的,所述的建筑的施工法为盖挖法,其主要步骤如下:Preferably as the present invention, the construction method of described building is cover and dig method, and its main steps are as follows:
1)完成槽桩的施工;1) Complete the construction of the slot pile;
2)完成外墙的施工;2) Complete the construction of the exterior wall;
3)完成顶板的施工;3) Complete the construction of the roof;
4)在外墙内挖掘岩土;4) Excavating rock and soil inside the outer wall;
5)完成底板的施工。5) Complete the construction of the bottom plate.
作为本发明优选的,所述的建筑是地下室,地下室包括二层地下室,二层地下室包括中板,中板包括中板梁,二层地下室的主要施工步骤如下:Preferably as the present invention, described building is basement, and basement comprises two-story basement, and second-floor basement comprises middle plate, and middle plate comprises middle plate beam, and the main construction steps of second-floor basement are as follows:
1)完成槽桩的施工;1) Complete the construction of the slot pile;
2)完成外墙的施工;2) Complete the construction of the exterior wall;
3)完成外墙上方临时支护的施工;3) Complete the construction of temporary support above the outer wall;
4)挖掘负一层下部外墙内设定深度的岩土;4) Excavate the rock and soil at a set depth in the lower outer wall of the negative floor;
5)完成中板梁的施工;5) Complete the construction of the plate girder;
6)挖掘负二层内全部岩土;6) Excavate all the rock and soil in the negative second floor;
7)浇筑底板;7) Pouring the bottom plate;
8)完成顶板的施工;8) Complete the construction of the roof;
9)完成中板的施工,拆除临时支护,即完成全部施工。9) Complete the construction of the middle plate and remove the temporary support, that is to say, complete all the construction.
作为本发明优选的,所述的建筑包括位于两侧外墙之间的中墙,中墙包括分别位于底板下方的底中墙和上方的上中墙,中墙包括全中墙和柱中墙两种结构,全中墙中的底中墙和上中墙以及柱中墙中的底中墙采用与外墙相同的结构,柱中墙中的上中墙包括位于建筑内纵向排列的柱,相邻的柱之间包括纵向布置的纵中板梁,柱的直径和纵中板梁的厚度均小于底中墙的厚度;底部挖掘装置包括中墙挖掘装置,中墙挖掘装置挖掘中墙底部的岩土,柱和纵中板梁在中墙挖掘装置挖掘出的槽中与中墙一起同步下沉。As preferred in the present invention, the building includes a mid-wall located between the exterior walls on both sides, the mid-wall includes a bottom mid-wall below the floor and an upper mid-wall above the bottom slab, and the mid-wall includes a full mid-wall and a column mid-wall The two structures, the bottom middle wall and the upper middle wall in the full middle wall and the bottom middle wall in the column-in-wall adopt the same structure as the outer wall, and the upper middle wall in the column-in-wall includes columns arranged longitudinally inside the building, There are longitudinal mid-slab beams arranged longitudinally between adjacent columns, the diameter of the columns and the thickness of the longitudinal mid-slab beams are smaller than the thickness of the bottom mid-wall; the bottom excavation device includes a mid-wall excavation device, and the mid-wall excavation device excavates the bottom of the mid-wall The rock and soil, columns and longitudinal mid-slab girders sink synchronously with the mid-wall in the grooves excavated by the mid-wall excavation device.
作为本发明优选的,所述的吊挂装置包括钢绞线液压升降千斤顶,钢绞线液压升降千斤顶采用穿芯式结构液压提升器作为升降机具,液压升降器两端的楔形锚具具有单向自锁作用,当锚具工作时,会自动锁紧钢绞线,锚具不工作时,放开钢绞线,钢绞线可上下活动,若干钢绞线液压升降千斤顶是同步缓慢升降的,外墙是在悬挂状态下下沉的。As preferred in the present invention, the hanging device includes a steel strand hydraulic lifting jack, and the steel strand hydraulic lifting jack adopts a core-through structure hydraulic lifter as the lifting tool, and the wedge-shaped anchorages at both ends of the hydraulic lifter have a one-way self- When the anchor is working, it will automatically lock the steel strand. When the anchor is not working, let go of the steel strand, and the steel strand can move up and down. The hydraulic lifting jacks of several steel strands are synchronously and slowly lifted. The wall is sunk in the suspended state.
作为本发明优选的,所述的外墙在进行沉墙施工时,是通过控制吊挂装置的下降速度来满足不同的地质条件。As preferred in the present invention, when the external wall is sunk, the descending speed of the hanging device is controlled to meet different geological conditions.
综上所述,沉墙基础是三墙合一结构,特别容易采用装配式建筑,可以将地下结构中永久性的顶板、楼层板或者梁作为支护,沉墙基础用墙下条形基础替代传统的桩基,还可以起到止水帷幕的作用,是一种无基坑、无支护的快速沉墙施工法。To sum up, the sinking wall foundation is a three-wall-in-one structure, which is particularly easy to adopt prefabricated buildings. The permanent roof, floor slab or beam in the underground structure can be used as support, and the sinking wall foundation is replaced by a strip foundation under the wall The traditional pile foundation can also play the role of a water-stop curtain. It is a rapid wall sinking construction method without foundation pits and supports.
相对于建筑整体下沉,自身重量大,本发明通过槽桩和墙分体结构,降低单件结构件下沉施工的重量,而且增加了吊挂装置,下沉速度可控,而且不会产生倾斜。Compared with the overall sinking of the building, its own weight is large. The invention reduces the weight of the sinking construction of a single structural part through the split structure of the slot pile and the wall, and adds a hanging device. The sinking speed is controllable and does not cause tilt.
附图说明Description of drawings
图1是地下的建筑1的俯视图,也是组成建筑1的外墙2A、槽桩3、顶板1-1和连接体1-3的结构示意图;Fig. 1 is a top view of an underground building 1, and is also a schematic structural view of an outer wall 2A, a slot pile 3, a roof 1-1 and a connecting body 1-3 forming the building 1;
图2是图1的A向视图,也是在先完成槽桩3的施工后,施工装置4对外墙2A进行下沉施工的结构示意图,也是底部挖掘装置5采用链刀挖掘底部岩土的结构示意图;Fig. 2 is the A-direction view of Fig. 1, and it is also a structural schematic diagram of the construction device 4 carrying out the subsidence construction of the outer wall 2A after the construction of the slot pile 3 is completed first, and it is also a structural schematic diagram of the bottom excavation device 5 using a chain knife to excavate the bottom rock and soil ;
图3是沉桩装置4B对槽桩3进行下沉施工的结构示意图,也是在两个槽桩3之间已经施工部分外墙2A的结构示意图;Fig. 3 is a structural schematic diagram of the sinking construction of the slotted pile 3 by the pile sinking device 4B, and is also a structural schematic diagram of the part of the outer wall 2A that has been constructed between the two slotted piles 3;
图4是图1的A-A视图,也是桩外钻机4B-3通过钻杆4B-3-1底部的钻具4B-3-2挖掘 槽桩3底部大面积的岩土,其他区域的岩土通过桩底斜锥面3-3将下方的岩土挤向钻具4B-3-2的结构示意图;Fig. 4 is the A-A view of Fig. 1, and also the drilling rig 4B-3 outside the pile passes through the drilling tool 4B-3-2 at the bottom of the drill pipe 4B-3-1 to excavate a large area of rock and soil at the bottom of the trench pile 3, and the rock and soil in other areas pass through Schematic diagram of the pile bottom inclined cone surface 3-3 pushing the rock and soil below to the drilling tool 4B-3-2;
图5是槽桩3的俯视图;Fig. 5 is the top view of slot pile 3;
图6是通过水力挖掘装置5A使外墙2A下沉施工的结构示意图;Fig. 6 is a schematic structural view of the external wall 2A sinking construction through the hydraulic excavation device 5A;
图7是图6的A-A视图,也是冲刷装置5A-1的结构示意图;Fig. 7 is a view of A-A of Fig. 6, which is also a schematic structural view of the flushing device 5A-1;
图8是外墙2A由链条5B-1和刀具5B-2组成的绳锯5B挖掘底部的岩土而进行下沉施工的结构示意图;Fig. 8 is a schematic diagram of the structure of the external wall 2A, which is composed of a chain 5B-1 and a cutter 5B-2, and the wire saw 5B excavates the rock and soil at the bottom to carry out sinking construction;
图9是图8的左视图,也是横向凸台2-1的底部设有墙角斜锥面2-1-1的结构示意图;Fig. 9 is a left view of Fig. 8, and it is also a structural schematic diagram of a wall angle tapered surface 2-1-1 provided at the bottom of the transverse boss 2-1;
图10是外墙2A的横向凸台2-1嵌入槽桩3的C型槽3-1C中的结构示意图;Fig. 10 is a schematic diagram of the structure of the lateral boss 2-1 of the outer wall 2A embedded in the C-shaped groove 3-1C of the groove pile 3;
图11是外墙2A是在模板4-2内浇筑而成的结构示意图;Fig. 11 is a schematic structural view of the outer wall 2A being poured in the template 4-2;
图12是施工区域6在纵向包括桩施工段6-1、外墙施工段6-2、支护施工段6-3、挖掘段6-4、底板施工段6-5和顶板施工段6-6的结构示意图;Fig. 12 shows that the construction area 6 includes pile construction section 6-1, exterior wall construction section 6-2, support construction section 6-3, excavation section 6-4, floor construction section 6-5 and roof construction section 6- Schematic diagram of the structure of 6;
图13是图12的A-A视图;Fig. 13 is the A-A view of Fig. 12;
图14是施工法为盖挖法,在施工外墙2A后,先施工顶板1-1的结构示意图;Fig. 14 is that the construction method is the cover excavation method, after the construction of the outer wall 2A, the structural representation of the roof 1-1 is first constructed;
图15是完成顶板1-1施工后,挖掘内部岩土,然后再完成底板1-2施工的结构示意图;Fig. 15 is a structural schematic diagram of excavating the internal rock and soil after completing the construction of the top plate 1-1, and then completing the construction of the bottom plate 1-2;
图16是包括位于两侧外墙2A之间的柱中墙9B的建筑1的结构示意图;FIG. 16 is a schematic structural view of a building 1 including a wall-in-column 9B between the outer walls 2A on both sides;
图17是图16的A-A视图,也是柱中墙9B由位于底板1-2下方的底中墙9-1和上方的上中墙9-2的结构示意图;Fig. 17 is the A-A view of Fig. 16, and it is also a structural schematic diagram of the column middle wall 9B consisting of the bottom middle wall 9-1 below the bottom plate 1-2 and the upper middle wall 9-2 above;
图18是图16的C-C视图,也是相邻的柱9-2-1之间包括纵向布置的纵中板梁1-4-1X的结构示意图;Fig. 18 is a C-C view of Fig. 16, which is also a structural schematic diagram of longitudinally arranged longitudinal mid-plate beams 1-4-1X between adjacent columns 9-2-1;
图19是中墙挖掘装置59挖掘中墙9底部岩土的结构示意图;Fig. 19 is a structural schematic diagram of the middle wall excavating device 59 excavating the rock and soil at the bottom of the middle wall 9;
图20是建筑1包括全中墙9A的结构示意图;Fig. 20 is a schematic structural view of the building 1 including the full central wall 9A;
图21是图20的B-B视图;Fig. 21 is the B-B view of Fig. 20;
图中的1是建筑;11是地下隧道;12是地下室;12A是二层地下室;2是沉墙基础;1A是墙下条形基础;1B是地下连续墙;1C是结构外墙;1-1是顶板;1-2是底板;1-3是连接体;1-4是中板;1-4-1是中板梁;1-4-1X是纵中板梁;2A是外墙;2X是纵向外墙;2Y是横向外墙;2-1是横向凸台;2-1-1是墙角斜锥面;3是槽桩;3-1是出土槽;3-1C是C型槽;3-2是定位孔;3-3是桩底斜锥面;4是施工装置;4-1是吊挂装置;4-1A是钢绞线液压升降千斤顶;4A是墙施工装置;4B是沉桩装置;4B-1是机架;4B-2是压桩装置;4B-3是桩外钻机;4B-4是出土管;4-2是模板;4-3是临时支护;5是底部挖掘装置;5A 是水力挖掘装置;5A-1是冲刷装置;5A-1-1是管路架;5A-2是泵送装置;5B是绳锯;5B-1是链条;5B-2是刀具;59是中墙挖掘装置;6是施工区域;6-1是桩施工段;6-2是外墙施工段;6-3是支护施工段;6-4是挖掘段;6-5是底板施工段;6-6是顶板施工段;9是中墙;9-1是底中墙;9-2是上中墙;9A是全中墙;9B是柱中墙;9-2-1是柱。1 in the figure is the building; 11 is the underground tunnel; 12 is the basement; 12A is the second-floor basement; 2 is the sinking wall foundation; 1A is the strip foundation under the wall; 1B is the underground continuous wall; 1 is the top plate; 1-2 is the bottom plate; 1-3 is the connecting body; 1-4 is the middle plate; 1-4-1 is the middle plate beam; 1-4-1X is the longitudinal middle plate beam; 2A is the outer wall; 2X is the longitudinal outer wall; 2Y is the horizontal outer wall; 2-1 is the horizontal boss; 2-1-1 is the inclined cone surface of the wall corner; 3 is the slot pile; 3-1 is the excavation slot; 3-1C is the C-shaped slot ; 3-2 is a positioning hole; 3-3 is an inclined cone at the bottom of the pile; 4 is a construction device; 4-1 is a hanging device; 4-1A is a steel strand hydraulic lifting jack; 4A is a wall construction device; 4B is Pile sinking device; 4B-1 is the frame; 4B-2 is the pile pressing device; 4B-3 is the drilling rig outside the pile; 4B-4 is the excavation pipe; 4-2 is the template; 4-3 is the temporary support; 5 is Bottom excavation device; 5A is hydraulic excavation device; 5A-1 is flushing device; 5A-1-1 is pipeline frame; 5A-2 is pumping device; 5B is wire saw; Cutter; 59 is the middle wall excavation device; 6 is the construction area; 6-1 is the pile construction section; 6-2 is the outer wall construction section; 6-3 is the support construction section; 6-4 is the excavation section; 6-5 6-6 is the roof construction section; 9 is the middle wall; 9-1 is the bottom middle wall; 9-2 is the upper middle wall; 9A is the whole middle wall; 9B is the column middle wall; 9-2- 1 is the column.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例,基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on The embodiments of the present invention and all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
请参阅图1~21本发明实施例中,位于地下的建筑1包括沉墙基础2、槽桩3、顶板1-1、底板1-2、连接体1-3和施工装置4,沉墙基础2就是建筑1的墙下条形基础1A、地下连续墙1B和结构外墙1C三墙合一的在地面完成施工后,不挖基坑直接下沉到位的外墙2A,相邻的外墙2A通过槽桩3连接,相邻的槽桩3和外墙2A是先完成槽桩3的施工后,再在地面上直接进行外墙2A的沉墙施工,施工装置4包括墙施工装置4A和沉桩装置4B,墙施工装置4A包括底部挖掘装置5和位于外墙2A顶部的吊挂装置4-1,沉墙施工时,吊挂装置4-1吊挂外墙2A,底部挖掘装置5挖掘外墙2A底部的岩土,槽桩3上部的截面包括出土槽3-1,出土槽3-1的宽度大于或等于外墙2A两端的厚度,外墙2A的两端嵌入出土槽3-1中,已挖掘的岩土通过出土槽3-1进行出土,外墙2A下沉至设定的位置,清理出土槽3-1中的岩土,浇筑连接体1-3,再进行后续施工,直至完成建筑1的全部施工。Please refer to FIGS. 1-21. In the embodiment of the present invention, the building 1 located underground includes a sinking wall foundation 2, a slot pile 3, a top plate 1-1, a bottom plate 1-2, a connecting body 1-3 and a construction device 4, and the sinking wall foundation 2 is the strip foundation 1A under the wall of building 1, the underground continuous wall 1B and the structural exterior wall 1C. 2A is connected by slotted piles 3, and the adjacent slotted piles 3 and the outer wall 2A are first completed after the construction of the slotted piles 3, and then the sinking wall construction of the outer wall 2A is directly carried out on the ground, and the construction device 4 includes the wall construction device 4A and The pile sinking device 4B and the wall construction device 4A include a bottom digging device 5 and a hanging device 4-1 positioned at the top of the outer wall 2A. During wall sinking construction, the hanging device 4-1 hangs the outer wall 2A, and the bottom digging device 5 excavates The rock and soil at the bottom of the outer wall 2A, the cross-section of the upper part of the groove pile 3 includes the excavation groove 3-1, the width of the excavation groove 3-1 is greater than or equal to the thickness of the two ends of the outer wall 2A, and the two ends of the outer wall 2A are embedded in the excavation groove 3-1 Among them, the excavated rock and soil are excavated through the excavation tank 3-1, the outer wall 2A is sunk to the set position, the rock and soil in the excavation tank 3-1 are cleaned, the connecting body 1-3 is poured, and then the follow-up construction is carried out. Until the entire construction of Building 1 is completed.
所述的沉桩装置4B包括机架4B-1、压桩装置4B-2、桩外钻机4B-3和出土管4B-4,槽桩3的底部包括出土管4B-4的定位孔3-2和桩底斜锥面3-3,出土管4B-4位于槽桩3外的出土槽3-1内,桩外钻机4B-3的钻杆4B-3-1位于出土管4B-4内,位于钻杆4B-3-1底部的钻具4B-3-2伸出出土管4B-4,沉桩时,压桩装置4B-2将槽桩3压入下方,桩底斜锥面3-3将下方的岩土挤向钻具4B-3-2,桩外钻机4B-3通过出土管4B-4将底部的岩土送至上方;压桩装置4B-2包括冲击锤、振动锤和静压装置。The pile sinking device 4B includes a frame 4B-1, a pile pressing device 4B-2, a pile external drilling machine 4B-3 and an excavation pipe 4B-4, and the bottom of the slotted pile 3 includes a positioning hole 3- of the excavation pipe 4B-4. 2 and the inclined cone surface 3-3 at the bottom of the pile, the unearthed pipe 4B-4 is located in the unearthed groove 3-1 outside the grooved pile 3, and the drill pipe 4B-3-1 of the external drilling rig 4B-3 is located in the unearthed pipe 4B-4 , the drilling tool 4B-3-2 at the bottom of the drill pipe 4B-3-1 protrudes out of the excavation pipe 4B-4. When sinking the pile, the pile pressing device 4B-2 presses the grooved pile 3 into the bottom, and the inclined cone surface 3 at the bottom of the pile -3 Squeeze the rock and soil below to the drilling tool 4B-3-2, and the external pile drilling rig 4B-3 sends the rock and soil at the bottom to the top through the excavation pipe 4B-4; the pile pressing device 4B-2 includes an impact hammer and a vibratory hammer and static pressure devices.
所述的底部挖掘装置5包括水力挖掘装置5A,水力挖掘装置5A包括冲刷装置5A-1和泵送装置5A-2,冲刷装置5A-1包括位于外墙2A底部的管路架5A-1-1,通过吊挂装置4-1将外墙2A处于悬挂状态下,启动泵送装置5A-2,外墙2A底部的冲刷装置5A-1挖掘岩土,已挖掘的岩土通过出土槽3-1输送至上方,实现外墙2A的下沉作业。The bottom excavation device 5 includes a hydraulic excavation device 5A, the hydraulic excavation device 5A includes a flushing device 5A-1 and a pumping device 5A-2, and the flushing device 5A-1 includes a pipeline frame 5A-1-1 at the bottom of the outer wall 2A. 1. Put the outer wall 2A in a suspended state through the hanging device 4-1, start the pumping device 5A-2, and the scouring device 5A-1 at the bottom of the outer wall 2A excavates the rock and soil, and the excavated rock and soil pass through the excavation tank 3- 1 is transported to the top to realize the sinking operation of the outer wall 2A.
需要说明的是:如图8和图9所示,底部挖掘装置5也可以采用绳锯5B结构, 绳锯5B由链条5B-1和刀具5B-2组成,位于外墙2A底部的绳锯5B挖掘岩土,在出土槽3-1内由下而上的绳锯5B将已挖掘的岩土带至上方。It should be noted that: as shown in Figure 8 and Figure 9, the bottom excavation device 5 can also adopt the structure of a wire saw 5B, the wire saw 5B is composed of a chain 5B-1 and a cutter 5B-2, and the wire saw 5B at the bottom of the outer wall 2A To excavate rock and soil, the wire saw 5B from bottom to top will bring the excavated rock and soil to the top in the excavation groove 3-1.
所述的外墙2A的两端包括横向凸台2-1,横向凸台2-1的底部包括墙角斜锥面2-1-1,沉墙时,墙角斜锥面2-1-1将下方的岩土挤向中间,被底部挖掘装置5送出,出土槽3-1包括用于与外墙2A嵌合的C型槽3-1C,C型槽3-1C的最大宽度大于或等于横向凸台2-1处外墙2A的厚度;墙施工装置4A包括模板4-2,外墙2A是在模板4-2内浇筑而成的,外墙2A的施工法包括采用边浇筑边下沉的施工A法、和采用完成全部浇筑后再下沉的施工B法。The two ends of the outer wall 2A include a transverse boss 2-1, and the bottom of the transverse boss 2-1 includes a wall angle tapered surface 2-1-1. When sinking the wall, the wall corner tapered surface 2-1-1 will The rock and soil below are squeezed to the middle and sent out by the bottom excavation device 5. The excavation groove 3-1 includes a C-shaped groove 3-1C for fitting with the outer wall 2A, and the maximum width of the C-shaped groove 3-1C is greater than or equal to the horizontal direction. The thickness of the outer wall 2A at the boss 2-1; the wall construction device 4A includes a formwork 4-2, the outer wall 2A is poured in the formwork 4-2, and the construction method of the outer wall 2A includes sinking while pouring The construction method A, and the construction method B after all the pouring is completed.
如图12~图13所示,所述的建筑1是地下隧道11,地下隧道11的在纵向包括桩施工段6-1、外墙施工段6-2、支护施工段6-3、挖掘段6-4、底板施工段6-5和顶板施工段6-6,施工装置4包括临时支护4-3,建筑1的施工是按各施工段顺序进行流水作业的,其主要步骤如下:As shown in Figures 12 to 13, the building 1 is an underground tunnel 11, and the underground tunnel 11 longitudinally includes a pile construction section 6-1, an exterior wall construction section 6-2, a support construction section 6-3, and an excavation section. Section 6-4, bottom plate construction section 6-5 and roof construction section 6-6, construction device 4 includes temporary support 4-3, construction of building 1 is carried out in flow operation according to the order of each construction section, and its main steps are as follows:
1)在桩施工段6-1完成槽桩3的施工;1) Complete the construction of the grooved pile 3 in the pile construction section 6-1;
2)在外墙施工段6-2:完成外墙2A的施工;吊挂装置4-1吊挂外墙2A,缓慢下降;底部挖掘装置5挖掘外墙2A底部的岩土;已挖掘的岩土通过出土槽3-1进行出土;外墙2A下沉至设定的位置;2) In the external wall construction section 6-2: the construction of the external wall 2A is completed; the hanging device 4-1 hangs the external wall 2A and descends slowly; the bottom digging device 5 excavates the rock and soil at the bottom of the external wall 2A; the excavated rock and soil Unearth through the excavation groove 3-1; the outer wall 2A sinks to the set position;
3)在支护施工段6-3完成临时支护4-3的施工;3) Complete the construction of the temporary support 4-3 in the support construction section 6-3;
4)在挖掘段6-4完成外墙2A内全部岩土的挖掘;4) Complete the excavation of all the rock and soil in the outer wall 2A in the excavation section 6-4;
5)在底板施工段6-5完成底板1-2的施工;5) Complete the construction of the base plate 1-2 in the base plate construction section 6-5;
6)在顶板施工段6-6完成顶板1-1的施工;6) Complete the construction of roof 1-1 in roof construction section 6-6;
7)拆除临时支护4-3,即完成地下隧道11的全部施工。7) Remove the temporary support 4-3, that is, complete the entire construction of the underground tunnel 11.
如图14和图15所示,所述的建筑1的施工法为盖挖法,其主要步骤如下:As shown in Figure 14 and Figure 15, the construction method of described building 1 is cover and dig method, and its main steps are as follows:
1)完成槽桩3的施工;1) finish the construction of groove pile 3;
2)完成外墙2A的施工;2) Complete the construction of exterior wall 2A;
3)完成顶板1-1的施工;3) Complete the construction of roof 1-1;
4)在外墙2A内挖掘岩土;4) Excavating rock and soil within the outer wall 2A;
5)完成底板1-2的施工;5) Complete the construction of base plate 1-2;
如图16~图19所示,其特征是所述的建筑1是地下室12,地下室12包括二层地下室12A,二层地下室12A包括中板1-4,中板1-4包括中板梁1-4-1,二层地下室12A的主要施工步骤如下:As shown in Figures 16 to 19, the feature is that the building 1 is a basement 12, the basement 12 includes a second-floor basement 12A, the second-floor basement 12A includes a middle plate 1-4, and the middle plate 1-4 includes a middle plate beam 1 -4-1. The main construction steps of the second-floor basement 12A are as follows:
1)完成槽桩3的施工;1) finish the construction of groove pile 3;
2)完成外墙2A的施工;2) Complete the construction of exterior wall 2A;
3)完成外墙2A上方临时支护4-3的施工;3) Complete the construction of the temporary support 4-3 above the outer wall 2A;
4)挖掘负一层下部外墙2A内设定深度的岩土;4) Excavate the rock and soil at a set depth in the lower outer wall 2A of the negative first floor;
5)完成中板梁1-4-1的施工;5) Complete the construction of the plate beam 1-4-1;
6)挖掘负二层内全部岩土;6) Excavate all the rock and soil in the negative second floor;
7)浇筑底板1-1;7) Pouring the bottom plate 1-1;
8)完成顶板1-1的施工;8) Complete the construction of roof 1-1;
9)完成中板1-4的施工,拆除临时支护4-3,即完成全部施工。9) Complete the construction of the middle plate 1-4, and dismantle the temporary support 4-3, that is, complete the entire construction.
需要说明的是:也可以完成施工步骤9后,再完成施工步骤8。It should be noted that: the construction step 8 can also be completed after the construction step 9 is completed.
所述的隧道1包括位于两侧外墙2A之间的中墙9,中墙9包括分别位于底板1-2下方的底中墙9-1和上方的上中墙9-2,中墙9包括全中墙9A和柱中墙9B两种结构,全中墙9A中的底中墙9-1和上中墙9-2以及柱中墙9B中的底中墙9-1采用与外墙2A相同的结构,柱中墙9B中的上中墙9-2包括位于隧道1内纵向排列的柱9-2-1,相邻的柱9-2-1之间包括纵向布置的纵中板梁1-4-1X,柱9-2-1的直径和纵中板梁1-4-1X的厚度均小于底中墙9-1的厚度;底部挖掘装置5包括中墙挖掘装置59,中墙挖掘装置59挖掘中墙9底部的岩土,柱9-2-1和纵中板梁1-4-1X在中墙挖掘装置59挖掘出的槽中与中墙9一起同步下沉。The tunnel 1 includes a middle wall 9 between the outer walls 2A on both sides, and the middle wall 9 includes a bottom middle wall 9-1 below the bottom plate 1-2 and an upper middle wall 9-2 above the bottom plate 1-2, and the middle wall 9 Including two structures of the full middle wall 9A and the column middle wall 9B, the bottom middle wall 9-1 and the upper middle wall 9-2 of the whole middle wall 9A and the bottom middle wall 9-1 of the column middle wall 9B adopt the same structure as the outer wall The same structure as 2A, the upper middle wall 9-2 in the middle wall 9B includes vertically arranged columns 9-2-1 in the tunnel 1, and longitudinally arranged longitudinal middle plates are included between adjacent columns 9-2-1 The beam 1-4-1X, the diameter of the column 9-2-1 and the thickness of the longitudinal middle plate beam 1-4-1X are all less than the thickness of the bottom middle wall 9-1; the bottom excavation device 5 includes a middle wall excavation device 59, the middle wall Wall digging device 59 excavates the rock and soil at the bottom of middle wall 9, and column 9-2-1 and longitudinal middle plate beam 1-4-1X sink synchronously with middle wall 9 in the groove that middle wall digging device 59 excavates.
所述的吊挂装置4-1包括钢绞线液压升降千斤顶4-1A,钢绞线液压升降千斤顶4-1A采用穿芯式结构液压提升器作为升降机具,液压升降器两端的楔形锚具具有单向自锁作用,当锚具工作紧时,会自动锁紧钢绞线,锚具不工作松时,放开钢绞线,钢绞线可上下活动,若干钢绞线液压升降千斤顶4-1A是同步缓慢升降的,外墙2A是在悬挂状态下下沉的。由于其自身的巨大自重,难以产生偏移。The hanging device 4-1 includes a steel strand hydraulic lifting jack 4-1A, and the steel strand hydraulic lifting jack 4-1A adopts a core-through structure hydraulic lifter as a lifting tool, and the wedge-shaped anchors at both ends of the hydraulic lifter have One-way self-locking function, when the anchorage is working tight, it will automatically lock the steel strand, when the anchorage is not loose, release the steel strand, the steel strand can move up and down, several steel strand hydraulic lift jacks 4- 1A is lifted and lowered slowly synchronously, and the outer wall 2A sinks in a suspended state. Due to its own huge dead weight, it is difficult to produce deflection.
需要说明的是:由于其自身的巨大自重,难以产生偏移所以无需纠偏。What needs to be explained is: due to its own huge weight, it is difficult to produce deviation, so there is no need for deviation correction.
所述的外墙2A在进行沉墙施工时,是通过控制吊挂装置4-1的下降速度来满足不同的地质条件。The external wall 2A satisfies different geological conditions by controlling the descending speed of the hanging device 4-1 during sunken wall construction.
在本发明的描述中,需要说明的是,术语“中心”、“上”、“下”、“左”、“右”、“竖直”、“水平”、“前”、“后”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制, 本发明中,还需要说明的是,术语“安装”、“连接”应做广义理解,例如,可以固定连接,也可以是可拆卸连接,或一体成型连接,也可以是机械连接,也可以是通过中间媒介间接连接,可以通过具体情况理解术语在本发明中的具体含义。In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "front", "rear" etc. The indicated orientation or positional relationship is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, or in a specific orientation. structure and operation, so it should not be construed as a limitation to the present invention. In the present invention, it should also be noted that the terms "installation" and "connection" should be interpreted in a broad sense, for example, it can be fixed connection or detachable connection, or The integrated connection may also be a mechanical connection, or an indirect connection through an intermediary, and the specific meaning of the terms in the present invention may be understood according to specific circumstances.
此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。In addition, it should be understood that although this specification is described according to implementation modes, not each implementation mode only contains an independent technical solution, and this description in the specification is only for clarity, and those skilled in the art should take the specification as a whole , the technical solutions in the various embodiments can also be properly combined to form other implementations that can be understood by those skilled in the art.

Claims (10)

  1. 用于由沉墙基础组成的地下建筑的施工法,其特征是位于地下的建筑(1)包括沉墙基础(2)、槽桩(3)、顶板(1-1)、底板(1-2)、连接体(1-3)和施工装置(4),沉墙基础(2)就是建筑(1)的墙下条形基础(1A)、地下连续墙(1B)和结构外墙(1C)三墙合一的在地面完成施工后,不挖基坑直接下沉到位的外墙(2A),相邻的外墙(2A)通过槽桩(3)连接,相邻的槽桩(3)和外墙(2A)是先完成槽桩(3)的施工后,再在地面上直接进行外墙(2A)的沉墙施工,施工装置(4)包括墙施工装置(4A)和沉桩装置(4B),墙施工装置(4A)包括底部挖掘装置(5)和位于外墙(2A)顶部的吊挂装置(4-1),沉墙施工时,吊挂装置(4-1)吊挂外墙(2A),底部挖掘装置(5)挖掘外墙(2A)底部的岩土,槽桩(3)上部的截面包括出土槽(3-1),出土槽(3-1)的宽度大于或等于外墙(2A)两端的厚度,外墙(2A)的两端嵌入出土槽(3-1)中,已挖掘的岩土通过出土槽(3-1)进行出土,外墙(2A)下沉至设定的位置,清理出土槽(3-1)中的岩土,浇筑连接体(1-3),再进行后续施工,直至完成建筑(1)的全部施工。A construction method for an underground building consisting of sunken wall foundations, characterized in that the underground building (1) includes sunken wall foundations (2), slot piles (3), roof (1-1), floor (1-2 ), connectors (1-3) and construction devices (4), the sinking wall foundation (2) is the under-wall strip foundation (1A), underground diaphragm wall (1B) and structural exterior wall (1C) of the building (1) After the three-wall-in-one construction is completed on the ground, the outer wall (2A) that is directly sunk in place without digging a foundation pit, the adjacent outer walls (2A) are connected by slotted piles (3), and the adjacent slotted piles (3) and the exterior wall (2A) is to first complete the construction of the slot pile (3), and then directly carry out the wall sinking construction of the exterior wall (2A) on the ground, and the construction device (4) includes the wall construction device (4A) and the pile sinking device (4B), the wall construction device (4A) includes a bottom excavation device (5) and a hanging device (4-1) at the top of the outer wall (2A). During sinking wall construction, the hanging device (4-1) hangs Excavation wall (2A), bottom excavation device (5) excavates rock and soil at the bottom of exterior wall (2A), and the section of slot pile (3) top comprises unearthed groove (3-1), and the width of unearthed groove (3-1) is greater than Or equal to the thickness of the two ends of the outer wall (2A), the two ends of the outer wall (2A) are embedded in the excavation groove (3-1), and the excavated rock and soil are excavated through the excavation groove (3-1), and the outer wall (2A) Sinking to the set position, clearing the rock and soil in the excavation tank (3-1), pouring the connecting body (1-3), and then carrying out subsequent construction until the entire construction of the building (1) is completed.
  2. 根据权利要求1所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的沉桩装置(4B)包括机架(4B-1)、压桩装置(4B-2)、桩外钻机(4B-3)和出土管(4B-4),槽桩(3)的底部包括出土管(4B-4)的定位孔(3-2)和桩底斜锥面(3-3),出土管(4B-4)位于槽桩(3)外的出土槽(3-1)内,桩外钻机(4B-3)的钻杆(4B-3-1)位于出土管(4B-4)内,位于钻杆(4B-3-1)底部的钻具(4B-3-2)伸出出土管(4B-4),沉桩时,压桩装置(4B-2)将槽桩(3)压入下方,桩底斜锥面(3-3)将下方的岩土挤向钻具(4B-3-2),桩外钻机(4B-3)通过出土管(4B-4)将底部的岩土送至上方。According to claim 1, the construction method for an underground building composed of sunken wall foundations is characterized in that said pile sinking device (4B) comprises a frame (4B-1), a pile pressing device (4B-2) , pile external drilling rig (4B-3) and unearthed pipe (4B-4), the bottom of slotted pile (3) comprises the location hole (3-2) of unearthed pipe (4B-4) and pile bottom inclined cone surface (3- 3), the unearthed pipe (4B-4) is located in the unearthed groove (3-1) outside the grooved pile (3), and the drill pipe (4B-3-1) of the pile external drilling machine (4B-3) is located in the unearthed pipe (4B -4), the drilling tool (4B-3-2) at the bottom of the drill pipe (4B-3-1) protrudes out of the excavation pipe (4B-4), and during pile sinking, the pile pressing device (4B-2) pushes the groove The pile (3) is pressed into the bottom, the inclined cone surface (3-3) at the bottom of the pile squeezes the rock and soil below to the drilling tool (4B-3-2), and the drilling machine outside the pile (4B-3) passes through the excavation pipe (4B-4 ) to send the rock and soil at the bottom to the top.
  3. 根据权利要求2所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的底部挖掘装置(5)包括水力挖掘装置(5A),水力挖掘装置(5A)包括冲刷装置(5A-1)和泵送装置(5A-2),冲刷装置(5A-1)包括位于外墙(2A)底部的管路架(5A-1-1),通过吊挂装置(4-1)将外墙(2A)处于悬挂状态下,启动泵送装置(5A-2),外墙(2A)底部的冲刷装置(5A-1)挖掘岩土,已挖掘的岩土通过出土槽(3-1)输送至上方,实现外墙(2A)的下沉作业。According to claim 2, the construction method for underground construction composed of sinking wall foundation is characterized in that said bottom excavation device (5) comprises a hydraulic excavation device (5A), and the hydraulic excavation device (5A) comprises a flushing device (5A-1) and pumping device (5A-2), the flushing device (5A-1) includes the pipeline frame (5A-1-1) at the bottom of the outer wall (2A), and the hanging device (4-1 ) put the outer wall (2A) in a suspended state, start the pumping device (5A-2), the scour device (5A-1) at the bottom of the outer wall (2A) excavates the rock and soil, and the excavated rock and soil pass through the excavation tank (3 -1) Conveying to the upper side to realize the sinking operation of the outer wall (2A).
  4. 根据权利要求3所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的外墙(2A)的两端包括横向凸台(2-1),横向凸台(2-1)的底部包括墙角斜锥面(2-1-1),沉墙时,墙角斜锥面(2-1-1)将下方的岩土挤向中间,被底部挖掘装置(5)送出,出土槽(3-1)包括用于与外墙(2A)嵌合的C型槽(3-1C),C型槽(3-1C)的最大宽度大于或等于横向凸台(2-1)处外墙(2A)的厚度;墙施工装置(4A)包括模板(4-2),外 墙(2A)是在模板(4-2)内浇筑而成的,外墙(2A)的施工法包括采用边浇筑边下沉的施工A法、和采用完成全部浇筑后再下沉的施工B法。The construction method for an underground building composed of sunk wall foundations according to claim 3, characterized in that the two ends of the outer wall (2A) comprise a transverse boss (2-1), and the transverse boss (2 The bottom of -1) includes the inclined cone surface (2-1-1) of the wall corner. When the wall sinks, the inclined cone surface (2-1-1) of the wall corner squeezes the rock and soil below to the middle, and is sent out by the bottom excavating device (5) , the excavation groove (3-1) includes a C-shaped groove (3-1C) for fitting with the outer wall (2A), and the maximum width of the C-shaped groove (3-1C) is greater than or equal to the transverse boss (2-1 ) at the thickness of the exterior wall (2A); the wall construction device (4A) includes the formwork (4-2), the exterior wall (2A) is poured in the formwork (4-2), and the construction of the exterior wall (2A) The methods include the construction method A of subsidence while pouring, and the construction method B of subsidence after all pouring is completed.
  5. 根据权利要求4所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的建筑(1)是地下隧道(11),地下隧道(11)的施工区域(6)在纵向包括桩施工段(6-1)、外墙施工段(6-2)、支护施工段(6-3)、挖掘段(6-4)、底板施工段(6-5)和顶板施工段(6-6),施工装置(4)包括临时支护(4-3),建筑(1)的施工是按各施工段顺序进行流水作业的,其主要步骤如下:The construction method for an underground building composed of sinking wall foundations according to claim 4, characterized in that said building (1) is an underground tunnel (11), and the construction area (6) of the underground tunnel (11) is in Longitudinal includes pile construction section (6-1), exterior wall construction section (6-2), support construction section (6-3), excavation section (6-4), floor construction section (6-5) and roof construction Section (6-6), construction device (4) comprises temporary support (4-3), and the construction of building (1) is to carry out flow operation according to the order of each construction section, and its main steps are as follows:
    1)在桩施工段(6-1)完成槽桩(3)的施工;1) Complete the construction of the grooved pile (3) at the pile construction section (6-1);
    2)在外墙施工段(6-2):完成外墙(2A)的施工;吊挂装置(4-1)吊挂外墙(2A),缓慢下降;底部挖掘装置(5)挖掘外墙(2A)底部的岩土;已挖掘的岩土通过出土槽(3-1)进行出土;外墙(2A)下沉至设定的位置;2) In the exterior wall construction section (6-2): complete the construction of the exterior wall (2A); the hanging device (4-1) hangs the exterior wall (2A) and lowers slowly; the bottom digging device (5) excavates the exterior wall ( 2A) the rock and soil at the bottom; the excavated rock and soil are excavated through the excavation groove (3-1); the outer wall (2A) sinks to the set position;
    3)在支护施工段(6-3)完成临时支护(4-3)的施工;3) Complete the construction of the temporary support (4-3) in the support construction section (6-3);
    4)在挖掘段(6-4)完成外墙(2A)内全部岩土的挖掘;4) Complete the excavation of all rock and soil in the outer wall (2A) in the excavation section (6-4);
    5)在底板施工段(6-5)完成底板(1-2)的施工;5) Complete the construction of the base plate (1-2) in the base plate construction section (6-5);
    6)在顶板施工段(6-6)完成顶板(1-1)的施工;6) Complete the construction of the roof (1-1) in the roof construction section (6-6);
    7)拆除临时支护(4-3),即完成地下隧道(11)的全部施工。7) Remove the temporary support (4-3), that is, complete all the construction of the underground tunnel (11).
  6. 根据权利要求5所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的建筑(1)的施工法为盖挖法,其主要步骤如下:According to claim 5, the construction method for the underground building composed of sinking wall foundation is characterized in that the construction method of the building (1) is the cover-excavation method, and its main steps are as follows:
    1)完成槽桩(3)的施工;1) finish the construction of groove pile (3);
    2)完成外墙(2A)的施工;2) Complete the construction of the exterior wall (2A);
    3)完成顶板(1-1)的施工;3) Complete the construction of the roof (1-1);
    4)在外墙(2A)内挖掘岩土;4) Excavating rock and soil inside the outer wall (2A);
    5)完成底板(1-2)的施工。5) Complete the construction of the bottom plate (1-2).
  7. 根据权利要求4所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的建筑(1)是地下室(12),地下室(12)包括二层地下室(12A),二层地下室(12A)包括中板(1-4),中板(1-4)包括中板梁(1-4-1),二层地下室(12A)的主要施工步骤如下:The construction method for an underground building composed of sinking wall foundations according to claim 4, characterized in that said building (1) is a basement (12), and the basement (12) includes a two-story basement (12A), two The first floor basement (12A) includes the middle plate (1-4), the middle plate (1-4) includes the middle plate beam (1-4-1), and the main construction steps of the second floor basement (12A) are as follows:
    1)完成槽桩(3)的施工;1) finish the construction of groove pile (3);
    2)完成外墙(2A)的施工;2) Complete the construction of the exterior wall (2A);
    3)完成外墙(2A)上方临时支护(4-3)的施工;3) Complete the construction of the temporary support (4-3) above the outer wall (2A);
    4)挖掘负一层下部外墙(2A)内设定深度的岩土;4) Excavate the rock and soil of the set depth in the lower outer wall (2A) of the negative floor;
    5)完成中板梁(1-4-1)的施工;5) Complete the construction of the plate beam (1-4-1);
    6)挖掘负二层内全部岩土;6) Excavate all the rock and soil in the negative second floor;
    7)浇筑底板(1-1);7) Pouring the bottom plate (1-1);
    8)完成顶板(1-1)的施工;8) Complete the construction of the roof (1-1);
    9)完成中板(1-4)的施工,拆除临时支护(4-3),即完成全部施工。9) Complete the construction of the middle plate (1-4), remove the temporary support (4-3), and then complete all the construction.
  8. 根据权利要求6或7所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的建筑(1)包括位于两侧外墙(2A)之间的中墙(9),中墙(9)包括分别位于底板(1-2)下方的底中墙(9-1)和上方的上中墙(9-2),中墙(9)包括全中墙(9A)和柱中墙(9B)两种结构,全中墙(9A)中的底中墙(9-1)和上中墙(9-2)以及柱中墙(9B)中的底中墙(9-1)采用与外墙(2A)相同的结构,柱中墙(9B)中的上中墙(9-2)包括位于建筑(1)内纵向排列的柱(9-2-1),相邻的柱(9-2-1)之间包括纵向布置的纵中板梁(1-4-1X),柱(9-2-1)的直径和纵中板梁(1-4-1X)的厚度均小于底中墙(9-1)的厚度;底部挖掘装置(5)包括中墙挖掘装置(59),中墙挖掘装置(59)挖掘中墙(9)底部的岩土,柱(9-2-1)和纵中板梁(1-4-1X)在中墙挖掘装置(59)挖掘出的槽中与中墙(9)一起同步下沉。According to claim 6 or 7, the construction method for the underground building composed of sinking wall foundation is characterized in that the building (1) includes a middle wall (9) between the outer walls (2A) on both sides , the middle wall (9) includes a bottom middle wall (9-1) below the base plate (1-2) and an upper middle wall (9-2) above, and the middle wall (9) includes a full middle wall (9A) and There are two structures of the column-in-wall (9B), the bottom-middle wall (9-1) and the upper-middle wall (9-2) in the full-middle wall (9A) and the bottom-middle wall (9-2) in the column-middle wall (9B). 1) Using the same structure as the outer wall (2A), the upper middle wall (9-2) in the middle wall (9B) includes columns (9-2-1) arranged longitudinally in the building (1), adjacent The columns (9-2-1) include longitudinally arranged longitudinal mid-plate beams (1-4-1X), the diameter of the columns (9-2-1) and the longitudinal mid-plate beams (1-4-1X) Thickness is all less than the thickness of bottom middle wall (9-1); Bottom excavation device (5) comprises middle wall excavation device (59), and middle wall excavation device (59) excavates rock and soil at the bottom of middle wall (9), and column (9) -2-1) and the longitudinal mid-plate beam (1-4-1X) sink synchronously with the mid-wall (9) in the groove excavated by the mid-wall digging device (59).
  9. 根据权利要求8所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的吊挂装置(4-1)包括钢绞线液压升降千斤顶(4-1A),钢绞线液压升降千斤顶(4-1A)采用穿芯式结构液压提升器作为升降机具,液压升降器两端的楔形锚具具有单向自锁作用,当锚具工作时,会自动锁紧钢绞线,锚具不工作时,放开钢绞线,钢绞线可上下活动,若干钢绞线液压升降千斤顶(4-1A)是同步缓慢升降的,外墙(2A)是在悬挂状态下下沉的。The construction method for underground buildings composed of sinking wall foundations according to claim 8, characterized in that said hanging device (4-1) comprises a steel strand hydraulic lifting jack (4-1A), a steel strand The line hydraulic lifting jack (4-1A) adopts the core-through structure hydraulic lifter as the lifting tool. The wedge-shaped anchorages at both ends of the hydraulic lifter have a one-way self-locking effect. When the anchorage is working, it will automatically lock the steel strand. When the anchorage is not working, release the steel strand, and the steel strand can move up and down. Several steel strand hydraulic lifting jacks (4-1A) are lifted and lowered synchronously and slowly, and the outer wall (2A) sinks in the suspended state .
  10. 根据权利要求9所述的用于由沉墙基础组成的地下建筑的施工法,其特征是所述的外墙(2A)在进行沉墙施工时,是通过控制吊挂装置(4-1)的下降速度来满足不同的地质条件。The construction method for an underground building composed of sunk wall foundations according to claim 9, characterized in that the outer wall (2A) is constructed by controlling the hanging device (4-1) when carrying out sunk wall construction. The descending speed can be adjusted to meet different geological conditions.
PCT/CN2022/126352 2021-10-21 2022-10-20 Construction method for underground building consisting of sinking wall foundation WO2023066327A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202111226335.1 2021-10-21
CN202111226335.1A CN114164861A (en) 2021-10-21 2021-10-21 Construction method for underground building composed of wall-sinking foundation

Publications (1)

Publication Number Publication Date
WO2023066327A1 true WO2023066327A1 (en) 2023-04-27

Family

ID=80477143

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2022/126352 WO2023066327A1 (en) 2021-10-21 2022-10-20 Construction method for underground building consisting of sinking wall foundation

Country Status (2)

Country Link
CN (1) CN114164861A (en)
WO (1) WO2023066327A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114164929A (en) * 2021-10-21 2022-03-11 王树生 Wall foundation and construction device thereof
CN114164861A (en) * 2021-10-21 2022-03-11 王树生 Construction method for underground building composed of wall-sinking foundation

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3783626A (en) * 1971-02-08 1974-01-08 Redpath Dorman Long Ltd Structure, and method and apparatus for founding a structure
CN1120104A (en) * 1994-09-16 1996-04-10 阎林森 Film water wall sinking method
WO2012167170A2 (en) * 2011-06-03 2012-12-06 Kruse Darin R Lubricated soil mixing systems and methods
CN106759106A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of constructing device and its construction method for revetment
CN106759460A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of constructing device and its construction method for bank basis
CN106812156A (en) * 2017-03-29 2017-06-09 王燏斌 A kind of assembled hypogee and its construction method
CN207714369U (en) * 2017-03-29 2018-08-10 王燏斌 A kind of assembled hypogee
CN114164861A (en) * 2021-10-21 2022-03-11 王树生 Construction method for underground building composed of wall-sinking foundation

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3783626A (en) * 1971-02-08 1974-01-08 Redpath Dorman Long Ltd Structure, and method and apparatus for founding a structure
CN1120104A (en) * 1994-09-16 1996-04-10 阎林森 Film water wall sinking method
WO2012167170A2 (en) * 2011-06-03 2012-12-06 Kruse Darin R Lubricated soil mixing systems and methods
CN106759106A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of constructing device and its construction method for revetment
CN106759460A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of constructing device and its construction method for bank basis
CN106812156A (en) * 2017-03-29 2017-06-09 王燏斌 A kind of assembled hypogee and its construction method
CN207714369U (en) * 2017-03-29 2018-08-10 王燏斌 A kind of assembled hypogee
CN114164861A (en) * 2021-10-21 2022-03-11 王树生 Construction method for underground building composed of wall-sinking foundation

Also Published As

Publication number Publication date
CN114164861A (en) 2022-03-11

Similar Documents

Publication Publication Date Title
WO2023066327A1 (en) Construction method for underground building consisting of sinking wall foundation
CN104947681B (en) Super large super deep basement ground pit construction method
WO2018133740A1 (en) Underground building and construction method for same
CN112554198B (en) Construction method of deep foundation pit protection structure adjacent to high-rise building
WO2023066325A1 (en) Sunken frame foundation and ground prefabricating equipment and sinking device thereof
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
WO2018133746A1 (en) Underground building formed of piles and walls, and method for constructing same
CN107326898B (en) I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof
WO2023066326A1 (en) Sunken wall foundation, and construction devices and method therefor
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN216640561U (en) Novel combined type enclosure structure
CN111218939A (en) Construction method of foundation pit supporting wall
CN215108944U (en) Arch subway station is opened up and is built structure of plugging into
CN108915735A (en) Slopes wall construction method for supporting and slopes wall support system
CN109653193B (en) Reverse construction method for underground continuous wall
CN108843339B (en) The auxiliary slip casting platform and construction method of large-scale solution cavity are passed through when existing tunnel digs
CN209958372U (en) Railway newly-added second-line platform back way foundation pile pipe curtain supporting structure
CN113565533A (en) Arch subway station building connection structure and construction method
CN113482028A (en) Construction method for breaking pile blocking of open caisson
CN111636440A (en) Structure for supporting and waterproof curtain to penetrate through old bottom plate obstacle and construction method thereof
CN110144824A (en) Beret slice single side formwork method
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
CN216765985U (en) Sinking construction device for cast-in-place underground building

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 22882932

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE