WO2022116482A1 - Tunnel heading method - Google Patents

Tunnel heading method Download PDF

Info

Publication number
WO2022116482A1
WO2022116482A1 PCT/CN2021/095744 CN2021095744W WO2022116482A1 WO 2022116482 A1 WO2022116482 A1 WO 2022116482A1 CN 2021095744 W CN2021095744 W CN 2021095744W WO 2022116482 A1 WO2022116482 A1 WO 2022116482A1
Authority
WO
WIPO (PCT)
Prior art keywords
temporary support
temporary
excavation
roadway
support
Prior art date
Application number
PCT/CN2021/095744
Other languages
French (fr)
Chinese (zh)
Inventor
王海军
王梁
王洪磊
刘少权
赵建
孟繁悦
朱伟
闫兴伟
任道远
张俊升
孟建新
杨晓辉
Original Assignee
煤炭科学研究总院
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 煤炭科学研究总院 filed Critical 煤炭科学研究总院
Publication of WO2022116482A1 publication Critical patent/WO2022116482A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D19/00Provisional protective covers for working space
    • E21D19/04Provisional protective covers for working space for use in drifting galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F1/00Ventilation of mines or tunnels; Distribution of ventilating currents
    • E21F1/006Ventilation at the working face of galleries or tunnels

Definitions

  • the present application relates to the technical field of mining, and in particular, to a roadway excavation method.
  • the mechanized excavation of mine roadways generally adopts the excavation and support excavation method.
  • the roadway working face requires a large number of workers to work together at the same time. These workers are all in an extremely harsh working environment, which seriously threatens the health of workers. Occurrence of various occupational diseases, such as pneumoconiosis, deafness, skin diseases, rheumatism, nervous system diseases, etc. The number of deaths due to occupational diseases has far exceeded the number of accident deaths every year.
  • the present application aims to solve one of the technical problems in the related art at least to a certain extent.
  • the present application proposes a roadway excavation method to protect the health of workers, reduce the risk of workers suffering from occupational diseases, and reduce the number of deaths due to occupational diseases.
  • an embodiment of the first aspect of the present application provides a roadway excavation method, including: controlling the excavation unit to perform the excavation operation, and controlling the temporary support device to perform the temporary support operation; when the temporary support distance reaches a preset distance When the distance threshold is reached, the tunneling unit is controlled to stop the tunneling operation; after the shutdown working face of the tunneling unit is ventilated and dust-reduced and safety is determined, the roadway is supported for a long time.
  • the temporary support device is controlled to perform the temporary support operation, and when the temporary support distance reaches a preset distance threshold, the excavation unit is controlled to stop the excavation operation, After the tunneling unit is shut down for ventilation and dust reduction and safety is determined, the roadway is supported for a long time. Being in an extremely harsh working environment reduces the risk of occupational diseases for workers and reduces the number of deaths due to occupational diseases.
  • tunnel excavation method may also have the following additional technical features:
  • the roadway excavation method further includes: after the long-term support operation is completed, returning to the control excavation unit to perform the excavation operation, and controlling the temporary support device to perform the temporary support operation step.
  • the tunnel excavation method further includes: controlling the ore material transport system to transport the ore material excavated by the tunneling unit to a transfer device; and controlling the transfer device to transport the ore material out of the tunnel.
  • the temporary support device is arranged on the body of the tunneling unit or the body of the temporary support machine.
  • the temporary support device includes a temporary scaffold installation arm and a temporary support scaffold; the controlling the temporary support device to perform the temporary support operation includes: controlling the temporary scaffold installation arm One of the temporary support scaffolds is installed every set distance.
  • the installation of one of the temporary support scaffolds includes: unfolding the temporary support scaffold in a retracted state; and installing the temporary support scaffold in the unfolded state.
  • the roadway excavation method further includes: after the permanent support operation of the corresponding area of the temporary support scaffold is completed, loading the temporary support scaffold onto the body of the tunneling unit Or on the body of the temporary support machine.
  • the long-term support operation for the roadway includes: using a manual method to perform the long-term support operation for the roadway; or, controlling the long-term support equipment to perform the long-term support operation for the roadway.
  • the ore material transportation system includes: a crushing transfer device and a retractable continuous transfer device; the control ore material transportation system transports the ore material excavated by the tunneling unit to the transfer equipment, including: The crushing and transferring device is controlled to crush the ore material excavated by the tunneling unit; the continuous transferring device is controlled to transport the crushed ore material to the transferring equipment.
  • the roadway excavation method further includes: when the excavation unit performs the excavation operation, setting a temporary partition wall behind the temporary support area.
  • FIG. 1 is a schematic diagram of a working scene of a roadway excavation system according to an embodiment of the application
  • FIG. 2 is a schematic flowchart of a roadway excavation method according to an embodiment of the application.
  • Fig. 3 is the scene schematic diagram of the temporary support operation performed by the temporary support device
  • FIG. 4 is a schematic flowchart of a roadway excavation method according to another embodiment of the present application.
  • the mechanized excavation of mine roadways generally adopts the excavation and support excavation method.
  • the roadway working face requires a large number of workers to work together at the same time. These workers are all in an extremely harsh working environment, which seriously threatens the health of workers. Occurrence of various occupational diseases, such as pneumoconiosis, deafness, skin diseases, rheumatism, nervous system diseases, etc., the number of deaths due to occupational diseases every year has far exceeded the number of accident deaths.
  • FIG. 1 is a schematic diagram of a working scene of a roadway excavation system according to an embodiment of the present application.
  • the excavation roadway is segmented and divided into the excavation section (ie the cutting area), the temporary support section (ie the temporary support area), and the permanent support section (ie the permanent support area).
  • the roadway may be a coal mine roadway or the like, which is not limited in this application.
  • the excavation section is the excavation work area of the excavation unit 1 such as roadheader, bolter, continuous shearer and other excavation equipment;
  • the temporary support section is the temporary support area for the temporary support device 2 to implement rapid unmanned temporary support;
  • long-term support The section is the area that requires long-term support treatment by staff, such as bolting, anchoring cables, tightening protective nets, etc. Work on a time-sharing basis on the basis of the above subsections.
  • FIG. 2 is a schematic flowchart of a roadway excavation method according to an embodiment of the present application. As shown in FIG. 2 , the tunnel excavation method of the embodiment of the present application may specifically include the following steps:
  • the tunneling unit when the tunneling unit performs the tunneling operation, only the temporary support device is controlled to perform the unmanned temporary support operation.
  • the tunneling unit is controlled to stop the tunneling operation.
  • the working face of the tunneling unit is stopped to ventilate and reduce dust and determine safety, the workers enter the working face and carry out long-term support operations on the roadway.
  • the excavation avoids the staff from being in an extremely bad working environment, reduces the risk of occupational diseases for the staff, and reduces the number of deaths due to occupational diseases.
  • the "permanent support operation on the roadway” in step S203 may specifically include: using a manual method to perform the long-term support operation on the roadway; or, controlling the long-term support equipment to perform the long-term support operation on the roadway.
  • the support form may be various existing support forms such as bolt anchor cable support, concrete forming support, etc., which are not limited in the embodiments of the present application.
  • the temporary support device is controlled to perform the temporary support operation, and when the temporary support distance reaches a preset distance threshold, the excavation unit is controlled to stop the excavation operation, After the shutdown face of the tunneling unit is ventilated and dusted and the safety is determined, long-term support operations are carried out on the roadway. Being in an extremely harsh working environment reduces the risk of occupational diseases for workers and reduces the number of deaths due to occupational diseases.
  • the efficiency of support work can be greatly improved, the problem of unmatched progress of excavation and support work in roadway excavation can be completely solved, and the efficiency of roadway excavation can be greatly improved.
  • the tunnel can be supported along with the tunnel, effectively shortening the distance between the empty roof (the distance without support in the tunneling section), and reducing the occurrence of roadway disasters such as roof fall and gangway to the greatest extent. to reduce security risks.
  • the tunnel excavation method of the embodiment of the present application may further include: after the long-term support operation is completed, returning to control the excavation unit to perform the excavation operation, and controlling the temporary support device to perform the temporary support operation.
  • the staff withdraws from the working face, and then continues the above S201 to control the excavation unit to carry out the excavation operation, and control the temporary support device to carry out the temporary support operation steps.
  • the excavation operation and the support operation can be separated from space and time, realizing the time-sharing and segmented roadway excavation, avoiding the staff from being in an extremely harsh working environment, reducing the risk of occupational diseases for the staff, and reducing the risk of occupational diseases. And the death toll.
  • the tunnel excavation method of the embodiment of the present application may further include: when the excavation unit performs the excavation operation, setting a temporary partition wall behind the temporary support area.
  • a temporary partition wall can be set up behind the temporary support area of the roadway, so as to isolate the dust, noise and toxic and harmful gases when the tunneling unit is working, so as to facilitate the staff. Carry out other related work operations behind the wall.
  • the tunnel excavation method of the embodiment of the present application may further include: controlling the ore material transportation system to transport the ore material excavated by the tunneling unit to the transfer equipment; and controlling the transfer equipment to transport the ore material to the outside of the tunnel.
  • the tunneling unit 1 is connected to a retractable mineral material transportation system 3 , and when the tunneling unit 1 performs the tunneling operation, the mineral material transporting system 3 is controlled to continuously uninterrupted the mineral material excavated by the tunneling unit 1 It is transported from the excavation section to the rear transfer equipment, and the transfer equipment is controlled to transport the ore material to the outside of the roadway.
  • the mineral material transportation system 3 may specifically include: a crushing transfer device 31 and a retractable continuous transfer device 32 .
  • the above-mentioned step "controlling the mineral material transport system to transport the mineral material excavated by the tunneling unit to the transfer equipment" may specifically include: controlling the crushing and transferring device 31 to crush the mineral material excavated by the tunneling unit 1; controlling the continuous transfer device 32 to The crushed ore material is transported to the transfer equipment.
  • the temporary support device 2 and the excavation unit 1 may be integrally provided, that is, the temporary support device 2 may be provided on the body of the excavation unit 1 .
  • the temporary support device 2 and the tunneling unit 1 may also be provided separately, that is, the temporary support device 2 may also be provided on the body of the temporary support machine behind the tunneling unit 1 .
  • the temporary support device 2 may specifically include a temporary scaffold installation arm 21 and a temporary support scaffold 22 .
  • the "controlling the temporary support device to perform the temporary support operation" in the above step S201 may specifically include: controlling the temporary scaffold installation arm 21 to install a temporary support scaffold 22 every set distance.
  • the temporary support scaffold 22 can be retracted and unfolded, and the above-mentioned steps of "installing a temporary support scaffold 22" may specifically include: unfolding the temporary support scaffold 22 in the retracted state; installing the temporary support scaffold 22 in the unfolded state Shelving 22.
  • the roadway excavation method of the embodiment of the present application may further include: after the permanent support operation of the corresponding area of the temporary support scaffold 22 is completed, loading the temporary support scaffold 22 onto the body of the tunneling unit 1 or temporarily support it. on the body of the machine.
  • the front part of the excavation unit 1 is fixedly provided with a temporary scaffold installation arm 21 and a temporary scaffold transport frame 4 .
  • the temporary scaffolding transport frame 4 is responsible for carrying and transporting the temporary supporting scaffolding 22 in a retracted state.
  • the temporary scaffold installation arm 21 is controlled to install a temporary support scaffold 22 every set distance, for example, 1 meter.
  • the temporary scaffold installation arm 21 first unfolds the temporary support scaffold 22 in the retracted state through its mechanical arm and hydraulic or pneumatic device, and then installs the temporary support scaffold 22 in the unfolded state at the corresponding position.
  • a temporary support is formed for the roadway to prevent the occurrence of accidents such as roof fall and gangway. While the workers perform long-term support operations on the roadway, the temporary support scaffolding 22 in the unfolded state can also be stowed, and the temporary supporting scaffolding 22 in the retracted state can be loaded to the excavation through the temporary scaffolding transport frame 4 On the body of unit 1, make preparations for the next excavation and unmanned temporary support operation.
  • FIG. 4 is a schematic flowchart of a roadway excavation method according to another embodiment of the present application. As shown in FIG. 4 , the roadway excavation method of this embodiment may specifically include the following steps:
  • the temporary support scaffold is loaded onto the body of the tunneling unit or the body of the temporary support machine through the temporary scaffold shipping frame.
  • step S405 after the long-term support operation is completed, withdraw from the working face, and continue to step S401.
  • first and second are only used for descriptive purposes, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as “first” or “second” may expressly or implicitly include one or more of that feature.
  • plurality means two or more, unless otherwise expressly and specifically defined.
  • the terms “installed”, “connected”, “connected”, “fixed” and other terms should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection , or integrated; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of the two elements or the interaction relationship between the two elements.
  • installed may be a fixed connection or a detachable connection , or integrated; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of the two elements or the interaction relationship between the two elements.
  • a first feature "on” or “under” a second feature may be in direct contact with the first and second features, or the first and second features indirectly through an intermediary touch.
  • the first feature being “above”, “over” and “above” the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is level higher than the second feature.
  • the first feature being “below”, “below” and “below” the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.

Abstract

A tunnel heading method, the method comprising: controlling a heading unit (1) to perform heading operation, and controlling a temporary supporting device (2) to perform temporary supporting operation; when the temporary supporting distance reaches a preset distance threshold, controlling the heading unit (1) to stop the heading operation; and performing long-term supporting operation on the tunnel after ventilation and dust settling at the working face where the heading unit (1) stops and safety confirmation. In the present method, the heading operation and the supporting operation are separated in space and time, such that tunnel heading can be carried out by time and sections, thereby preventing workers from working in extreme severe environments, lowering the risk of relevant employees suffering from occupational diseases, and reducing the deaths due to occupational diseases.

Description

巷道掘进方法Roadway excavation method
相关申请的交叉引用CROSS-REFERENCE TO RELATED APPLICATIONS
本申请要求煤炭科学研究总院于2020年12月04日提交的、发明名称为“巷道掘进方法”的、中国专利申请号为“202011407904.8”的优先权。This application claims the priority of the Chinese patent application number "202011407904.8" filed by the General Research Institute of Coal Science on December 04, 2020, with the invention titled "Roadway Excavation Method".
技术领域technical field
本申请涉及开采技术领域,尤其涉及一种巷道掘进方法。The present application relates to the technical field of mining, and in particular, to a roadway excavation method.
背景技术Background technique
相关技术中,矿井巷道机械化掘进一般都采用随掘随支护的掘进方法,巷道工作面需要大量工作人员同时协同工作,这些工作人员都处于极端恶劣的工作环境中,严重威胁工作人员健康,导致各类职业病的发生,如尘肺病,耳聋,皮肤病,风湿病,神经系统疾病等。每年因职业病而死亡人数已远超事故死亡人数。In related technologies, the mechanized excavation of mine roadways generally adopts the excavation and support excavation method. The roadway working face requires a large number of workers to work together at the same time. These workers are all in an extremely harsh working environment, which seriously threatens the health of workers. Occurrence of various occupational diseases, such as pneumoconiosis, deafness, skin diseases, rheumatism, nervous system diseases, etc. The number of deaths due to occupational diseases has far exceeded the number of accident deaths every year.
申请内容Application content
本申请旨在至少在一定程度上解决相关技术中的技术问题之一。The present application aims to solve one of the technical problems in the related art at least to a certain extent.
为此,本申请提出一种巷道掘进方法,以保障工作人员健康,降低工作人员罹患职业病的风险,降低因职业病而死亡人数。Therefore, the present application proposes a roadway excavation method to protect the health of workers, reduce the risk of workers suffering from occupational diseases, and reduce the number of deaths due to occupational diseases.
为了实现上述目的,本申请第一方面实施例提供了一种巷道掘进方法,包括:控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业;当临时支护距离达到预设的距离阈值时,控制所述掘进机组停止掘进作业;在所述掘进机组的停机工作面通风降尘并确定安全后,对巷道进行长久支护作业。In order to achieve the above purpose, an embodiment of the first aspect of the present application provides a roadway excavation method, including: controlling the excavation unit to perform the excavation operation, and controlling the temporary support device to perform the temporary support operation; when the temporary support distance reaches a preset distance When the distance threshold is reached, the tunneling unit is controlled to stop the tunneling operation; after the shutdown working face of the tunneling unit is ventilated and dust-reduced and safety is determined, the roadway is supported for a long time.
本申请实施例提供的巷道掘进方法,在控制掘进机组进行掘进作业时,控制临时支护装置进行临时支护作业,当临时支护距离达到预设的距离阈值时,控制掘进机组停止掘进作业,在掘进机组的停机工作面通风降尘并确定安全后, 对巷道进行长久支护作业,通过将掘进作业和支护作业从空间和时间上分开,实现了分时分段巷道掘进,避免了工作人员处于极端恶劣的工作环境中,降低了工作人员罹患职业病的风险,降低了因职业病而死亡人数。In the roadway excavation method provided by the embodiment of the present application, when the excavation unit is controlled to perform the excavation operation, the temporary support device is controlled to perform the temporary support operation, and when the temporary support distance reaches a preset distance threshold, the excavation unit is controlled to stop the excavation operation, After the tunneling unit is shut down for ventilation and dust reduction and safety is determined, the roadway is supported for a long time. Being in an extremely harsh working environment reduces the risk of occupational diseases for workers and reduces the number of deaths due to occupational diseases.
另外,根据本申请上述实施例的巷道掘进方法还可以具有如下附加的技术特征:In addition, the tunnel excavation method according to the above embodiments of the present application may also have the following additional technical features:
根据本申请的一个实施例,所述巷道掘进方法还包括:长久支护作业完成后,返回所述控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业步骤。According to an embodiment of the present application, the roadway excavation method further includes: after the long-term support operation is completed, returning to the control excavation unit to perform the excavation operation, and controlling the temporary support device to perform the temporary support operation step.
根据本申请的一个实施例,所述巷道掘进方法还包括:控制矿料运输系统将所述掘进机组采掘的矿料运输至转运设备;控制所述转运设备将矿料运输至巷道外。According to an embodiment of the present application, the tunnel excavation method further includes: controlling the ore material transport system to transport the ore material excavated by the tunneling unit to a transfer device; and controlling the transfer device to transport the ore material out of the tunnel.
根据本申请的一个实施例,所述临时支护装置设置在所述掘进机组的车身上或者临时支护机的车身上。According to an embodiment of the present application, the temporary support device is arranged on the body of the tunneling unit or the body of the temporary support machine.
根据本申请的一个实施例,所述临时支护装置包括临时棚架安装臂和临时支护棚架;所述控制临时支护装置进行临时支护作业,包括:控制所述临时棚架安装臂每隔设定距离安装一个所述临时支护棚架。According to an embodiment of the present application, the temporary support device includes a temporary scaffold installation arm and a temporary support scaffold; the controlling the temporary support device to perform the temporary support operation includes: controlling the temporary scaffold installation arm One of the temporary support scaffolds is installed every set distance.
根据本申请的一个实施例,所述安装一个所述临时支护棚架,包括:将处于收缩状态的所述临时支护棚架展开;安装处于展开状态的所述临时支护棚架。According to an embodiment of the present application, the installation of one of the temporary support scaffolds includes: unfolding the temporary support scaffold in a retracted state; and installing the temporary support scaffold in the unfolded state.
根据本申请的一个实施例,所述巷道掘进方法还包括:所述临时支护棚架对应区域的长久支护作业完成后,将所述临时支护棚架装载至所述掘进机组的车身上或者所述临时支护机的车身上。According to an embodiment of the present application, the roadway excavation method further includes: after the permanent support operation of the corresponding area of the temporary support scaffold is completed, loading the temporary support scaffold onto the body of the tunneling unit Or on the body of the temporary support machine.
根据本申请的一个实施例,所述对巷道进行长久支护作业,包括:采用人工的方式对巷道进行长久支护作业;或者,控制长久支护设备对巷道进行长久支护作业。According to an embodiment of the present application, the long-term support operation for the roadway includes: using a manual method to perform the long-term support operation for the roadway; or, controlling the long-term support equipment to perform the long-term support operation for the roadway.
根据本申请的一个实施例,所述矿料运输系统包括:破碎转运装置和可伸缩的连续转运装置;所述控制矿料运输系统将所述掘进机组采掘的矿料运输至 转运设备,包括:控制所述破碎转运装置对所述掘进机组采掘的矿料进行破碎处理;控制所述连续转运装置将破碎处理后的矿料运输至所述转运设备。According to an embodiment of the present application, the ore material transportation system includes: a crushing transfer device and a retractable continuous transfer device; the control ore material transportation system transports the ore material excavated by the tunneling unit to the transfer equipment, including: The crushing and transferring device is controlled to crush the ore material excavated by the tunneling unit; the continuous transferring device is controlled to transport the crushed ore material to the transferring equipment.
根据本申请的一个实施例,所述巷道掘进方法还包括:在掘进机组进行掘进作业时,在临时支护区域后设置临时隔离墙。According to an embodiment of the present application, the roadway excavation method further includes: when the excavation unit performs the excavation operation, setting a temporary partition wall behind the temporary support area.
本申请附加的方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本申请的实践了解到。Additional aspects and advantages of the present application will be set forth, in part, in the following description, and in part will be apparent from the following description, or learned by practice of the present application.
附图说明Description of drawings
本申请上述的和/或附加的方面和优点从下面结合附图对实施例的描述中将变得明显和容易理解,其中:The above and/or additional aspects and advantages of the present application will become apparent and readily understood from the following description of embodiments taken in conjunction with the accompanying drawings, wherein:
图1为本申请一个实施例的巷道掘进系统的工作场景示意图;1 is a schematic diagram of a working scene of a roadway excavation system according to an embodiment of the application;
图2为本申请一个实施例的巷道掘进方法的流程示意图;2 is a schematic flowchart of a roadway excavation method according to an embodiment of the application;
图3为临时支护装置进行临时支护作业的场景示意图;Fig. 3 is the scene schematic diagram of the temporary support operation performed by the temporary support device;
图4为本申请另一个实施例的巷道掘进方法的流程示意图;4 is a schematic flowchart of a roadway excavation method according to another embodiment of the present application;
附图标号:Reference number:
1-掘进机组,2-临时支护装置,21-临时棚架安装臂,22-临时支护棚架,3-矿料运输系统,31-破碎转运装置,32-连续转运装置,4-临时棚架装运架。1- Tunneling unit, 2- Temporary support device, 21- Temporary scaffold installation arm, 22- Temporary support scaffold, 3- Mineral material transport system, 31- Crushing transfer device, 32- Continuous transfer device, 4- Temporary Shelving shipping rack.
具体实施方式Detailed ways
为了更好的理解上述技术方案,下面将参照附图更详细地描述本申请的示例性实施例。虽然附图中显示了本申请的示例性实施例,然而应当理解,可以以各种形式实现本申请而不应被这里阐述的实施例所限制。相反,提供这些实施例是为了能够更透彻地理解本申请,并且能够将本申请的范围完整的传达给本领域的技术人员。In order to better understand the above technical solutions, the exemplary embodiments of the present application will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present application are shown in the drawings, it should be understood that the present application may be embodied in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided so that the application will be more thoroughly understood, and will fully convey the scope of the application to those skilled in the art.
根据国家卫健委统计,截止2018年底,全国累计报告职业病例超过97万,居世界首位,其中大部分都集中在矿井从业劳动者中。矿井中,尤其是矿井掘 进工作面环境恶劣,粉尘、热害、噪声和有毒有害气体组成“四害”,严重威胁劳动者健康,导致各类职业病的发生,例如尘肺病,耳聋,皮肤病,风湿病,神经系统疾病等,每年因职业病而死亡人数已远超事故死亡人数。According to statistics from the National Health and Medical Commission, by the end of 2018, the cumulative number of occupational cases reported nationwide exceeded 970,000, ranking first in the world, most of which were concentrated among mine workers. In mines, especially the excavation working face of mines has a harsh environment. Dust, heat damage, noise and toxic and harmful gases form the "four hazards", which seriously threaten the health of workers and lead to the occurrence of various occupational diseases, such as pneumoconiosis, deafness, skin diseases, Rheumatism, nervous system diseases, etc., the number of deaths due to occupational diseases has far exceeded the number of accident deaths every year.
相关技术中,矿井巷道机械化掘进一般都采用随掘随支护的掘进方法,巷道工作面需要大量工作人员同时协同工作,这些工作人员都处于极端恶劣的工作环境中,严重威胁工作人员健康,导致各类职业病的发生,例如尘肺病,耳聋,皮肤病,风湿病,神经系统疾病等,每年因职业病而死亡人数已远超事故死亡人数。In related technologies, the mechanized excavation of mine roadways generally adopts the excavation and support excavation method. The roadway working face requires a large number of workers to work together at the same time. These workers are all in an extremely harsh working environment, which seriously threatens the health of workers. Occurrence of various occupational diseases, such as pneumoconiosis, deafness, skin diseases, rheumatism, nervous system diseases, etc., the number of deaths due to occupational diseases every year has far exceeded the number of accident deaths.
为了降低矿井掘进面工作人员罹患职业病的风险,本申请实施例提出了一种分段分时的巷道掘进方法。图1为本申请一个实施例的巷道掘进系统的工作场景示意图。如图1,将掘进巷道进行分段,分为掘进段(即截割区域)、临时支护段(即临时支护区域)、长久支护段(即长久支护区域)。巷道可以是煤矿巷道等,本申请对此不做过多限定。其中掘进段为掘进机组1如掘进机、掘锚机、连续采煤机等掘进设备的掘进工作区域;临时支护段为临时支护装置2实施快速无人化临时支护区域;长久支护段为需要工作人员进行长久支护处理的区域,如打锚杆、锚索、紧固防护网等。在上述分段的基础上进行分时作业。In order to reduce the risk of occupational diseases for workers at the mine tunneling face, the embodiment of the present application proposes a subsection and time-sharing tunneling method. FIG. 1 is a schematic diagram of a working scene of a roadway excavation system according to an embodiment of the present application. As shown in Figure 1, the excavation roadway is segmented and divided into the excavation section (ie the cutting area), the temporary support section (ie the temporary support area), and the permanent support section (ie the permanent support area). The roadway may be a coal mine roadway or the like, which is not limited in this application. The excavation section is the excavation work area of the excavation unit 1 such as roadheader, bolter, continuous shearer and other excavation equipment; the temporary support section is the temporary support area for the temporary support device 2 to implement rapid unmanned temporary support; long-term support The section is the area that requires long-term support treatment by staff, such as bolting, anchoring cables, tightening protective nets, etc. Work on a time-sharing basis on the basis of the above subsections.
下面参考附图描述本申请实施例的巷道掘进方法。图2是本申请一个实施例的巷道掘进方法的流程示意图。如图2所示,本申请实施例的巷道掘进方法,具体可包括以下步骤:The tunnel excavation method of the embodiments of the present application will be described below with reference to the accompanying drawings. FIG. 2 is a schematic flowchart of a roadway excavation method according to an embodiment of the present application. As shown in FIG. 2 , the tunnel excavation method of the embodiment of the present application may specifically include the following steps:
S201,控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业。S201 , controlling the tunneling unit to perform the tunneling operation, and controlling the temporary support device to perform the temporary support operation.
S202,当临时支护距离达到预设的距离阈值时,控制掘进机组停止掘进作业。S202, when the temporary support distance reaches a preset distance threshold, control the excavation unit to stop the excavation operation.
S203,在掘进机组的停机工作面通风降尘并确定安全后,对巷道进行长久支护作业。S203, after the shutdown face of the excavation unit is ventilated and dust-reduced and safety is determined, long-term support operation is performed on the roadway.
具体的,在掘进机组进行掘进作业时,只控制临时支护装置进行无人化临 时支护作业。当临时支护距离达到预设的距离阈值时,控制掘进机组停止掘进作业。在掘进机组的停机工作面通风降尘并确定安全后,工作人员进入工作面,对巷道进行长久支护作业,通过将掘进作业和支护作业从空间和时间上分开,实现了分时分段巷道掘进,避免了工作人员处于极端恶劣的工作环境中,降低了工作人员罹患职业病的风险,降低了因职业病而死亡人数。Specifically, when the tunneling unit performs the tunneling operation, only the temporary support device is controlled to perform the unmanned temporary support operation. When the temporary support distance reaches the preset distance threshold, the tunneling unit is controlled to stop the tunneling operation. After the working face of the tunneling unit is stopped to ventilate and reduce dust and determine safety, the workers enter the working face and carry out long-term support operations on the roadway. The excavation avoids the staff from being in an extremely bad working environment, reduces the risk of occupational diseases for the staff, and reduces the number of deaths due to occupational diseases.
其中,步骤S203中的“对巷道进行长久支护作业”具体可包括:采用人工的方式对巷道进行长久支护作业;或者,控制长久支护设备对巷道进行长久支护作业。支护形式可以是锚杆锚索支护、混凝土成形支护等现有的各种支护形式,本申请实施例对此不进行限制。Wherein, the "permanent support operation on the roadway" in step S203 may specifically include: using a manual method to perform the long-term support operation on the roadway; or, controlling the long-term support equipment to perform the long-term support operation on the roadway. The support form may be various existing support forms such as bolt anchor cable support, concrete forming support, etc., which are not limited in the embodiments of the present application.
本申请实施例提供的巷道掘进方法,在控制掘进机组进行掘进作业时,控制临时支护装置进行临时支护作业,当临时支护距离达到预设的距离阈值时,控制掘进机组停止掘进作业,在掘进机组的停机工作面通风降尘并确定安全后,对巷道进行长久支护作业,通过将掘进作业和支护作业从空间和时间上分开,实现了分时分段巷道掘进,避免了工作人员处于极端恶劣的工作环境中,降低了工作人员罹患职业病的风险,降低了因职业病而死亡人数。通过掘进分段分时、无人化临时支护,可以将支护工作效率极大提高,彻底解决巷道掘进中采掘、支护工作进度不匹配问题,极大的提高巷道掘进效率。通过掘进分段分时、无人化临时支护,可以随掘随支,有效缩短空顶距离(掘进段无支护距离),最大程度上降低冒顶、片帮等巷道灾害的发生,极大的降低安全隐患。In the roadway excavation method provided by the embodiment of the present application, when the excavation unit is controlled to perform the excavation operation, the temporary support device is controlled to perform the temporary support operation, and when the temporary support distance reaches a preset distance threshold, the excavation unit is controlled to stop the excavation operation, After the shutdown face of the tunneling unit is ventilated and dusted and the safety is determined, long-term support operations are carried out on the roadway. Being in an extremely harsh working environment reduces the risk of occupational diseases for workers and reduces the number of deaths due to occupational diseases. Through the time-sharing and unmanned temporary support of excavation, the efficiency of support work can be greatly improved, the problem of unmatched progress of excavation and support work in roadway excavation can be completely solved, and the efficiency of roadway excavation can be greatly improved. Through the time-sharing and unmanned temporary support of tunneling, the tunnel can be supported along with the tunnel, effectively shortening the distance between the empty roof (the distance without support in the tunneling section), and reducing the occurrence of roadway disasters such as roof fall and gangway to the greatest extent. to reduce security risks.
进一步的,本申请实施例的巷道掘进方法,还可以包括:长久支护作业完成后,返回控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业步骤。Further, the tunnel excavation method of the embodiment of the present application may further include: after the long-term support operation is completed, returning to control the excavation unit to perform the excavation operation, and controlling the temporary support device to perform the temporary support operation.
具体的,工作人员完成对巷道的长久支护作业后,撤出工作面,再继续上述S201控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业步骤。如此周而复始,就可以将掘进作业和支护作业从空间和时间上分开,实现了分时分段巷道掘进,避免工作人员处于极端恶劣的工作环境中,降低工作 人员罹患职业病的风险,降低因职业病而死亡人数。Specifically, after completing the long-term support operation for the roadway, the staff withdraws from the working face, and then continues the above S201 to control the excavation unit to carry out the excavation operation, and control the temporary support device to carry out the temporary support operation steps. In this way, the excavation operation and the support operation can be separated from space and time, realizing the time-sharing and segmented roadway excavation, avoiding the staff from being in an extremely harsh working environment, reducing the risk of occupational diseases for the staff, and reducing the risk of occupational diseases. And the death toll.
此处需要说明的是,在工作人员对巷道进行长久支护作业的同时,还可以为下次掘进与无人化临时支护作业做好准备工作,然后撤出工作面。It should be noted here that while the staff performs long-term support operations on the roadway, they can also make preparations for the next excavation and unmanned temporary support operations, and then withdraw from the working face.
进一步的,本申请实施例的巷道掘进方法,还可以包括:在掘进机组进行掘进作业时,在临时支护区域后设置临时隔离墙。Further, the tunnel excavation method of the embodiment of the present application may further include: when the excavation unit performs the excavation operation, setting a temporary partition wall behind the temporary support area.
具体的,可以根据巷道环境、除尘、运输等设备的布置情况,在巷道临时支护区域后设置临时隔离墙,以便在掘进机组工作时将粉尘、噪声和有毒有害气体进行隔离,从而方便工作人员在隔离墙后进行其他相关工作作业。Specifically, according to the layout of the roadway environment, dust removal, transportation and other equipment, a temporary partition wall can be set up behind the temporary support area of the roadway, so as to isolate the dust, noise and toxic and harmful gases when the tunneling unit is working, so as to facilitate the staff. Carry out other related work operations behind the wall.
进一步的,本申请实施例的巷道掘进方法,还可以包括:控制矿料运输系统将掘进机组采掘的矿料运输至转运设备;控制转运设备将矿料运输至巷道外。Further, the tunnel excavation method of the embodiment of the present application may further include: controlling the ore material transportation system to transport the ore material excavated by the tunneling unit to the transfer equipment; and controlling the transfer equipment to transport the ore material to the outside of the tunnel.
具体的,如图1所示,掘进机组1后连接可伸缩的矿料运输系统3,在掘进机组1进行掘进作业时,控制矿料运输系统3连续不间断的将掘进机组1采掘的矿料由掘进段运输至后部的转运设备,控制转运设备将矿料运输至巷道外。Specifically, as shown in FIG. 1 , the tunneling unit 1 is connected to a retractable mineral material transportation system 3 , and when the tunneling unit 1 performs the tunneling operation, the mineral material transporting system 3 is controlled to continuously uninterrupted the mineral material excavated by the tunneling unit 1 It is transported from the excavation section to the rear transfer equipment, and the transfer equipment is controlled to transport the ore material to the outside of the roadway.
进一步的,如图1所示,矿料运输系统3具体可包括:破碎转运装置31和可伸缩的连续转运装置32。对应的,上述步骤“控制矿料运输系统将掘进机组采掘的矿料运输至转运设备”具体可包括:控制破碎转运装置31对掘进机组1采掘的矿料进行破碎处理;控制连续转运装置32将破碎处理后的矿料运输至转运设备。Further, as shown in FIG. 1 , the mineral material transportation system 3 may specifically include: a crushing transfer device 31 and a retractable continuous transfer device 32 . Correspondingly, the above-mentioned step "controlling the mineral material transport system to transport the mineral material excavated by the tunneling unit to the transfer equipment" may specifically include: controlling the crushing and transferring device 31 to crush the mineral material excavated by the tunneling unit 1; controlling the continuous transfer device 32 to The crushed ore material is transported to the transfer equipment.
进一步的,如图1所示,临时支护装置2与掘进机组1可以一体化设置,即临时支护装置2可以设置在掘进机组1的车身上。本领域技术人员可以理解,临时支护装置2与掘进机组1也可以分开设置,即临时支护装置2也可以设置在掘进机组1后的临时支护机的车身上。Further, as shown in FIG. 1 , the temporary support device 2 and the excavation unit 1 may be integrally provided, that is, the temporary support device 2 may be provided on the body of the excavation unit 1 . Those skilled in the art can understand that the temporary support device 2 and the tunneling unit 1 may also be provided separately, that is, the temporary support device 2 may also be provided on the body of the temporary support machine behind the tunneling unit 1 .
其中,如图1、图3所示,临时支护装置2具体可包括临时棚架安装臂21和临时支护棚架22。对应的,上述步骤S201中的“控制临时支护装置进行临时支护作业”具体可包括:控制临时棚架安装臂21每隔设定距离安装一个临时支护棚架22。其中,临时支护棚架22可收缩可展开,上述步骤“安装一个临 时支护棚架22”具体可包括:将处于收缩状态的临时支护棚架22展开;安装处于展开状态的临时支护棚架22。Wherein, as shown in FIGS. 1 and 3 , the temporary support device 2 may specifically include a temporary scaffold installation arm 21 and a temporary support scaffold 22 . Correspondingly, the "controlling the temporary support device to perform the temporary support operation" in the above step S201 may specifically include: controlling the temporary scaffold installation arm 21 to install a temporary support scaffold 22 every set distance. Wherein, the temporary support scaffold 22 can be retracted and unfolded, and the above-mentioned steps of "installing a temporary support scaffold 22" may specifically include: unfolding the temporary support scaffold 22 in the retracted state; installing the temporary support scaffold 22 in the unfolded state Shelving 22.
进一步的,本申请实施例的巷道掘进方法,还可以包括:临时支护棚架22对应区域的长久支护作业完成后,将临时支护棚架22装载至掘进机组1的车身上或者临时支护机的车身上。Further, the roadway excavation method of the embodiment of the present application may further include: after the permanent support operation of the corresponding area of the temporary support scaffold 22 is completed, loading the temporary support scaffold 22 onto the body of the tunneling unit 1 or temporarily support it. on the body of the machine.
具体的,如图1、图3所示,掘进机组1的前部固定设置有临时棚架安装臂21和临时棚架装运架4。临时棚架装运架4负责承载与运输处于收缩状态的临时支护棚架22。随着掘进机组1在巷道内掘进,控制临时棚架安装臂21每隔设定距离例如1米安装一个临时支护棚架22。安装时,临时棚架安装臂21通过其机械臂与液压或者气动装置先将处于收缩状态的临时支护棚架22展开,然后再将处于展开状态的临时支护棚架22安装在对应位置,从而对巷道形成临时支撑,防止冒顶、片帮等事故发生。在工作人员对巷道进行长久支护作业的同时,还可以将处于展开状态的临时支护棚架22收起,通过临时棚架装运架4将处于收缩状态的临时支护棚架22装载至掘进机组1的车身上,为下次掘进与无人化临时支护作业做好准备工作。Specifically, as shown in FIG. 1 and FIG. 3 , the front part of the excavation unit 1 is fixedly provided with a temporary scaffold installation arm 21 and a temporary scaffold transport frame 4 . The temporary scaffolding transport frame 4 is responsible for carrying and transporting the temporary supporting scaffolding 22 in a retracted state. As the tunneling unit 1 is excavating in the roadway, the temporary scaffold installation arm 21 is controlled to install a temporary support scaffold 22 every set distance, for example, 1 meter. During installation, the temporary scaffold installation arm 21 first unfolds the temporary support scaffold 22 in the retracted state through its mechanical arm and hydraulic or pneumatic device, and then installs the temporary support scaffold 22 in the unfolded state at the corresponding position. In this way, a temporary support is formed for the roadway to prevent the occurrence of accidents such as roof fall and gangway. While the workers perform long-term support operations on the roadway, the temporary support scaffolding 22 in the unfolded state can also be stowed, and the temporary supporting scaffolding 22 in the retracted state can be loaded to the excavation through the temporary scaffolding transport frame 4 On the body of unit 1, make preparations for the next excavation and unmanned temporary support operation.
下面以设置40个临时支护棚架22为例,详细描述本申请实施例的巷道掘进方法。The tunnel excavation method of the embodiment of the present application will be described in detail below by taking the setting of 40 temporary support scaffolds 22 as an example.
图4是本申请另一个实施例的巷道掘进方法的流程示意图,如图4,本实施例的巷道掘进方法具体可包括以下步骤:FIG. 4 is a schematic flowchart of a roadway excavation method according to another embodiment of the present application. As shown in FIG. 4 , the roadway excavation method of this embodiment may specifically include the following steps:
S401,控制掘进机组进行掘进作业,随着掘进机组的掘进,每隔1米安装1个临时支护棚架。S401, control the excavation unit to perform excavation operation, and install a temporary support scaffold every 1 meter along with the excavation of the excavation unit.
S402,当40个临时支护棚架全部安装完毕时,掘进距离和临时支护距离为40米,控制掘进机组停止掘进作业。S402, when all the 40 temporary support scaffolds are installed, the excavation distance and the temporary support distance are 40 meters, and the excavation unit is controlled to stop the excavation operation.
S403,在掘进机组的停机工作面通风降尘并确定安全后,工作人员进入工作面,对巷道进行长久支护作业。S403, after the shutdown working face of the excavation unit is ventilated and dust-removed and safety is determined, the staff enters the working face to carry out long-term support operations for the roadway.
S404,临时支护棚架对应区域的长久支护作业完成后,通过临时棚架装运 架将临时支护棚架装载至掘进机组的车身上或者临时支护机的车身上。S404, after the long-term support operation in the corresponding area of the temporary support scaffold is completed, the temporary support scaffold is loaded onto the body of the tunneling unit or the body of the temporary support machine through the temporary scaffold shipping frame.
S405,长久支护作业完成后,撤出工作面,继续步骤S401。S405, after the long-term support operation is completed, withdraw from the working face, and continue to step S401.
在本申请的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”、“顺时针”、“逆时针”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。In the description of this application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", " Rear, Left, Right, Vertical, Horizontal, Top, Bottom, Inner, Outer, Clockwise, Counterclockwise, Axial, The orientations or positional relationships indicated by "radial direction", "circumferential direction", etc. are based on the orientations or positional relationships shown in the accompanying drawings, which are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying the indicated devices or elements. It must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as a limitation of the present application.
此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本申请的描述中,“多个”的含义是两个或两个以上,除非另有明确具体的限定。In addition, the terms "first" and "second" are only used for descriptive purposes, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first" or "second" may expressly or implicitly include one or more of that feature. In the description of the present application, "plurality" means two or more, unless otherwise expressly and specifically defined.
在本申请中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。In this application, unless otherwise expressly specified and limited, the terms "installed", "connected", "connected", "fixed" and other terms should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection , or integrated; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, and it can be the internal connection of the two elements or the interaction relationship between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific situations.
在本申请中,除非另有明确的规定和限定,第一特征在第二特征“上”或“下”可以是第一和第二特征直接接触,或第一和第二特征通过中间媒介间接接触。而且,第一特征在第二特征“之上”、“上方”和“上面”可是第一特征在第二特征正上方或斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”可以是第一特征在第二特征正下方或斜下方,或仅仅表示第一特征水平高度小于第二特征。In this application, unless otherwise expressly stated and defined, a first feature "on" or "under" a second feature may be in direct contact with the first and second features, or the first and second features indirectly through an intermediary touch. Also, the first feature being "above", "over" and "above" the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is level higher than the second feature. The first feature being "below", "below" and "below" the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature has a lower level than the second feature.
在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、 结构、材料或者特点包含于本申请的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不必须针对的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任一个或多个实施例或示例中以合适的方式结合。此外,在不相互矛盾的情况下,本领域的技术人员可以将本说明书中描述的不同实施例或示例以及不同实施例或示例的特征进行结合和组合。In the description of this specification, description with reference to the terms "one embodiment," "some embodiments," "example," "specific example," or "some examples", etc., mean specific features described in connection with the embodiment or example , structure, material or feature is included in at least one embodiment or example of the present application. In this specification, schematic representations of the above terms are not necessarily directed to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, those skilled in the art may combine and combine the different embodiments or examples described in this specification, as well as the features of the different embodiments or examples, without conflicting each other.
尽管上面已经示出和描述了本申请的实施例,可以理解的是,上述实施例是示例性的,不能理解为对本申请的限制,本领域的普通技术人员在本申请的范围内可以对上述实施例进行变化、修改、替换和变型。Although the embodiments of the present application have been shown and described above, it should be understood that the above embodiments are exemplary and should not be construed as limitations to the present application. Embodiments are subject to variations, modifications, substitutions and variations.

Claims (10)

  1. 一种巷道掘进方法,其特征在于,包括:A roadway excavation method, characterized in that, comprising:
    控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业;Control the excavation unit to carry out the excavation operation, and control the temporary support device to carry out the temporary support operation;
    当临时支护距离达到预设的距离阈值时,控制所述掘进机组停止掘进作业;When the temporary support distance reaches a preset distance threshold, controlling the tunneling unit to stop the tunneling operation;
    在所述掘进机组的停机工作面通风降尘并确定安全后,对巷道进行长久支护作业。After the shutdown working face of the excavation unit is ventilated and dust-removed and safety is determined, long-term support work is carried out on the roadway.
  2. 根据权利要求1所述的巷道掘进方法,其特征在于,还包括:The tunnel excavation method according to claim 1, characterized in that, further comprising:
    长久支护作业完成后,返回所述控制掘进机组进行掘进作业,并控制临时支护装置进行临时支护作业步骤。After the long-term support operation is completed, the control excavation unit is returned to carry out the excavation operation, and the temporary support device is controlled to carry out the temporary support operation steps.
  3. 根据权利要求1所述的巷道掘进方法,其特征在于,还包括:The tunnel excavation method according to claim 1, characterized in that, further comprising:
    控制矿料运输系统将所述掘进机组采掘的矿料运输至转运设备;Controlling the ore material transportation system to transport the ore material excavated by the tunneling unit to the transfer equipment;
    控制所述转运设备将矿料运输至巷道外。The transfer equipment is controlled to transport the ore material out of the tunnel.
  4. 根据权利要求1所述的巷道掘进方法,其特征在于,所述临时支护装置设置在所述掘进机组的车身上或者临时支护机的车身上。The roadway excavation method according to claim 1, wherein the temporary support device is arranged on the body of the tunneling unit or the body of the temporary support machine.
  5. 根据权利要求1所述的巷道掘进方法,其特征在于,所述临时支护装置包括临时棚架安装臂和临时支护棚架;所述控制临时支护装置进行临时支护作业,包括:The tunnel excavation method according to claim 1, wherein the temporary support device comprises a temporary scaffold installation arm and a temporary support scaffold; and the control of the temporary support device to perform the temporary support operation includes:
    控制所述临时棚架安装臂每隔设定距离安装一个所述临时支护棚架。The temporary scaffold installation arm is controlled to install one of the temporary support scaffolds every set distance.
  6. 根据权利要求5所述的巷道掘进方法,其特征在于,所述安装一个所述临时支护棚架,包括:The tunnel excavation method according to claim 5, wherein the installing one of the temporary support scaffolds comprises:
    将处于收缩状态的所述临时支护棚架展开;unfolding the temporary support scaffold in a retracted state;
    安装处于展开状态的所述临时支护棚架。Install the temporary support scaffolding in the deployed state.
  7. 根据权利要求5所述的巷道掘进方法,其特征在于,还包括:The tunnel excavation method according to claim 5, characterized in that, further comprising:
    所述临时支护棚架对应区域的长久支护作业完成后,将所述临时支护棚架装载至所述掘进机组的车身上或者所述临时支护机的车身上。After the permanent support operation of the corresponding area of the temporary support scaffold is completed, the temporary support scaffold is loaded onto the body of the tunneling unit or the body of the temporary support machine.
  8. 根据权利要求1所述的巷道掘进方法,其特征在于,所述对巷道进行长久支护作业,包括:The roadway excavation method according to claim 1, wherein the long-term support operation for the roadway comprises:
    采用人工的方式对巷道进行长久支护作业;或者,Long-term support of the roadway by manual means; or,
    控制长久支护设备对巷道进行长久支护作业。Control the long-term support equipment to carry out long-term support operations on the roadway.
  9. 根据权利要求3所述的巷道掘进方法,其特征在于,所述矿料运输系统包括:破碎转运装置和可伸缩的连续转运装置;所述控制矿料运输系统将所述掘进机组采掘的矿料运输至转运设备,包括:The roadway excavation method according to claim 3, characterized in that, the ore material transport system comprises: a crushing transfer device and a retractable continuous transfer device; Shipping to transfer equipment, including:
    控制所述破碎转运装置对所述掘进机组采掘的矿料进行破碎处理;Controlling the crushing and transferring device to crush the ore excavated by the tunneling unit;
    控制所述连续转运装置将破碎处理后的矿料运输至所述转运设备。The continuous transfer device is controlled to transport the crushed ore material to the transfer equipment.
  10. 根据权利要求1所述的巷道掘进方法,其特征在于,还包括:The tunnel excavation method according to claim 1, further comprising:
    在掘进机组进行掘进作业时,在临时支护区域后设置临时隔离墙。When the tunneling unit performs the tunneling operation, a temporary partition wall is set behind the temporary support area.
PCT/CN2021/095744 2020-12-04 2021-05-25 Tunnel heading method WO2022116482A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202011407904.8 2020-12-04
CN202011407904.8A CN112593961A (en) 2020-12-04 2020-12-04 Roadway driving method

Publications (1)

Publication Number Publication Date
WO2022116482A1 true WO2022116482A1 (en) 2022-06-09

Family

ID=75188330

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/095744 WO2022116482A1 (en) 2020-12-04 2021-05-25 Tunnel heading method

Country Status (2)

Country Link
CN (1) CN112593961A (en)
WO (1) WO2022116482A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112593961A (en) * 2020-12-04 2021-04-02 煤炭科学研究总院 Roadway driving method
CN114017051B (en) * 2021-10-11 2023-10-20 煤炭科学研究总院有限公司 Bracket mounting vehicle
CN113622971B (en) * 2021-10-11 2021-12-24 煤炭科学研究总院 Quick supporting device for roadway
CN114017078B (en) * 2021-10-13 2023-02-28 煤炭科学研究总院有限公司 Control method and device for unmanned full-automatic self-adaptive installation of roadway support

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3813126A (en) * 1972-10-02 1974-05-28 Bendix Corp Continuously operable underground mining vehicle
CN102678151A (en) * 2012-04-17 2012-09-19 太原理工大学 Fully-mechanized excavating self-moving type temporary support system and technological method thereof
CN103382844A (en) * 2013-07-15 2013-11-06 郑东风 Temporary support and permanent support parallel operation excavating technology and equipment for tracked hydraulic combined support
CN105971628A (en) * 2016-03-31 2016-09-28 中国矿业大学(北京) Temporary supporting method for tunneled roadway
CN109184691A (en) * 2018-08-07 2019-01-11 中国矿业大学(北京) Full-mechanized roadway piercing technique based on the anchor combined unit of robotization pick branch
CN109915163A (en) * 2019-03-28 2019-06-21 廊坊景隆重工机械有限公司 Speedy drivage system and speedy drivage method
CN110410118A (en) * 2019-07-29 2019-11-05 沈阳天安科技股份有限公司 A kind of novel piercing technique
CN112593961A (en) * 2020-12-04 2021-04-02 煤炭科学研究总院 Roadway driving method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2189645Y (en) * 1993-12-02 1995-02-15 中国矿业大学 Special hydraulic supporting rack for temporary supporting of digging head
CN102787854A (en) * 2012-08-13 2012-11-21 内蒙古鲁新能源开发有限责任公司 Forepoling method used in tunneling of weak cemented soft rock roadway
CN111140245B (en) * 2020-01-14 2021-08-24 天地科技股份有限公司 Intelligent tunnel digging and supporting machine and method for rapidly forming tunnel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3813126A (en) * 1972-10-02 1974-05-28 Bendix Corp Continuously operable underground mining vehicle
CN102678151A (en) * 2012-04-17 2012-09-19 太原理工大学 Fully-mechanized excavating self-moving type temporary support system and technological method thereof
CN103382844A (en) * 2013-07-15 2013-11-06 郑东风 Temporary support and permanent support parallel operation excavating technology and equipment for tracked hydraulic combined support
CN105971628A (en) * 2016-03-31 2016-09-28 中国矿业大学(北京) Temporary supporting method for tunneled roadway
CN109184691A (en) * 2018-08-07 2019-01-11 中国矿业大学(北京) Full-mechanized roadway piercing technique based on the anchor combined unit of robotization pick branch
CN109915163A (en) * 2019-03-28 2019-06-21 廊坊景隆重工机械有限公司 Speedy drivage system and speedy drivage method
CN110410118A (en) * 2019-07-29 2019-11-05 沈阳天安科技股份有限公司 A kind of novel piercing technique
CN112593961A (en) * 2020-12-04 2021-04-02 煤炭科学研究总院 Roadway driving method

Also Published As

Publication number Publication date
CN112593961A (en) 2021-04-02

Similar Documents

Publication Publication Date Title
WO2022116482A1 (en) Tunnel heading method
CN104564050B (en) Equipment for heading and anchoring parallel operation construction
CN102562066B (en) Method for mechanically mining coal by using steep seam pseudo inclination bracing type retractable flexible shield support
EA037982B1 (en) Method for pillarless mining with self-preserving development without roadway development at mining area
US10662771B2 (en) Drill and blast method and apparatus for the same
CN103643979A (en) Hydraulic support used for roadway temporary support and erecting and use method of hydraulic support
KR20100003061A (en) Tunneling method and apparatus for blasting of enlargement and construction of concrete lining carried out simultaneously during excavation of pilot tunnel by tbm
CN107060795A (en) A kind of underground mine TBM assembly construction methods
AU2014292699A1 (en) Temporary supporting and permanent supporting parallel operation excavating technology for crawler-type hydraulic combination bracket and equipment using same
BRPI1015022B1 (en) method to develop an underground mine
US7331735B2 (en) Apparatus, system, and method for supporting a gate entry for underground full extraction mining
CN104373147B (en) Folding extension type roadway hydraulic bracket
Girmscheid et al. Tunnel boring machines
RU2470157C1 (en) Layer development method of thick steeply inclined coal formation
CN104712356A (en) Hydraulic self-moving circulating supporting tunnel combined support and construction method
CN105736027A (en) Support group for gob-side entry retaining
CN112727467A (en) Chamber construction method for repairing shield cutter head cutter
RU2361087C1 (en) Section of support of mini face of thick steeply inclined coal bed
CA2998001A1 (en) Rapid development mobile canopy for underground mining
CA1181438A (en) Method of and apparatus for hydraulic mining
CN112627827A (en) Control device for excavating and deslagging of vertical shaft at upper part of existing tunnel
WO1999067506A1 (en) Tunnel boring machinery
US1785096A (en) Tunnel
CN218542280U (en) Temporary supporting device for tunnel arch frame
CN215213500U (en) Control device for excavating and deslagging of vertical shaft at upper part of existing tunnel

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21899525

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21899525

Country of ref document: EP

Kind code of ref document: A1