WO2022025556A1 - 건설 기계 - Google Patents

건설 기계 Download PDF

Info

Publication number
WO2022025556A1
WO2022025556A1 PCT/KR2021/009626 KR2021009626W WO2022025556A1 WO 2022025556 A1 WO2022025556 A1 WO 2022025556A1 KR 2021009626 W KR2021009626 W KR 2021009626W WO 2022025556 A1 WO2022025556 A1 WO 2022025556A1
Authority
WO
WIPO (PCT)
Prior art keywords
boom
valve
pilot pressure
regenerative
electromagnetic proportional
Prior art date
Application number
PCT/KR2021/009626
Other languages
English (en)
French (fr)
Inventor
강병일
Original Assignee
두산인프라코어 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 두산인프라코어 주식회사 filed Critical 두산인프라코어 주식회사
Publication of WO2022025556A1 publication Critical patent/WO2022025556A1/ko

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2278Hydraulic circuits
    • E02F9/2285Pilot-operated systems
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2217Hydraulic or pneumatic drives with energy recovery arrangements, e.g. using accumulators, flywheels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/20Drives; Control devices
    • E02F9/22Hydraulic or pneumatic drives
    • E02F9/2264Arrangements or adaptations of elements for hydraulic drives
    • E02F9/2267Valves or distributors

Definitions

  • the present invention relates to a construction machine, and more particularly, to a construction machine capable of controlling the speed of a boom.
  • Construction machinery refers to all machines used in civil engineering works or building works.
  • construction machines have an engine and a hydraulic pump operated by the power of the engine, and drive or drive a work device with the power generated through the engine and the hydraulic pump.
  • an excavator which is a type of construction machine, is an excavator for civil engineering, construction, excavating work to dig the ground at a construction site, loading work to transport soil, crushing work to dismantle buildings, grading work to clear the ground, etc.
  • a construction machine it consists of a moving body that moves equipment, an upper revolving body that is mounted on the moving body and rotates 360 degrees, and a work device.
  • the excavator includes a traveling motor used for traveling, a swing motor used for swinging an upper swing body, and driving devices such as a boom cylinder, an arm cylinder, a bucket cylinder, and an optional cylinder used for a working device.
  • driving devices are driven by hydraulic oil discharged from a variable displacement hydraulic pump driven by an engine or an electric motor.
  • An embodiment of the present invention provides a construction machine that can control the speed of the boom as desired by the user.
  • a construction machine including a boom raises and lowers the boom and controls the flow rate of hydraulic oil discharged from the boom cylinder divided into the head side and the rod side, and the hydraulic oil discharged from the head side of the boom cylinder, and the received pilot
  • a boom valve whose opening area is adjusted as the spool is displaced according to pressure, an electromagnetic proportional pressure reducing valve for boom valve that generates the pilot pressure to be transmitted to the boom valve, and an operation device for generating an operation signal for operation of the boom; and calculating an opening area of the boom valve for passing the target through-flow rate and the target through-flow rate of the boom valve corresponding to the operation signal of the operating device, and to be transmitted to the boom valve to achieve the opening area and a control device for calculating a pilot pressure and transmitting a current command value to the electromagnetic proportional pressure reducing valve for the boom valve to generate the calculated pilot pressure.
  • the construction machine may further include a pilot pressure sensor for measuring the pilot pressure generated by the electromagnetic proportional pressure reducing valve for the boom valve. And the control device compares the calculated pilot pressure with the pilot pressure measured by the pilot pressure sensor, and controls the electromagnetic proportional pressure reducing valve for the boom valve so that the measured pilot pressure follows the calculated pilot pressure.
  • the construction machine includes a control valve for controlling supply of hydraulic oil to the boom cylinder, a first boom hydraulic line connecting the control valve and a head side of the boom cylinder, and a rod side of the control valve and the boom cylinder A second boom hydraulic line connecting the , and a recirculation line branched from the first boom hydraulic line and connected to the second boom hydraulic line may be further included. And the boom valve may be installed on the recirculation line.
  • the construction machine may further include a first pressure sensor installed on the first boom hydraulic line, and a second pressure sensor installed on the second boom hydraulic line.
  • the control device may calculate an opening area of the boom valve for passing the target flow rate in consideration of a difference between the pressure measured by the first pressure sensor and the pressure measured by the second pressure sensor.
  • the construction machine includes a main pump for supplying hydraulic oil to the control valve, a pilot pump for supplying hydraulic oil required for the electromagnetic proportional pressure reducing valve for the boom valve to generate the pilot pressure, and to the main pump and the pilot pump. It may further include an engine for providing rotational power.
  • the construction machine includes a regenerative motor generating regenerative energy by performing a regenerative operation with the hydraulic oil discharged from the boom cylinder, a regenerative line branched from the first boom hydraulic line and connected to the regenerative motor, and on the regenerative line
  • a regenerative valve installed to control the flow rate of hydraulic oil discharged to the head side of the boom cylinder, and the opening area is adjusted while the spool is displaced according to the received pilot pressure, and the regenerative valve electron for generating the pilot pressure to be transmitted to the regenerative valve It may further include a proportional pressure reducing valve.
  • the control device calculates a target passage flow rate of the regenerative valve and an opening area of the regenerative valve for passing the target passage flow rate corresponding to an operation signal of the operation device, and sends the regenerative valve to the regenerative valve to achieve the opening area.
  • the pilot pressure to be transmitted may be calculated, and a current command value may be transmitted to the electromagnetic proportional pressure reducing valve for the regenerative valve to generate the calculated pilot pressure.
  • the construction machine may further include an accumulator connected to the regeneration line for accumulating hydraulic oil, and an accumulator valve for controlling the inflow and outflow of hydraulic oil to the accumulator.
  • a construction machine including a boom raises and lowers the boom and controls the flow rate of hydraulic oil discharged from the boom cylinder divided into the head side and the rod side, and the hydraulic oil discharged from the head side of the boom cylinder and input
  • a boom valve whose opening area is adjusted while the spool is displaced according to the received pilot pressure, an electromagnetic proportional pressure reducing valve for a boom valve that generates the pilot pressure to be transmitted to the boom valve, and an operation for generating an operation signal for operation of the boom device, and controlling the electromagnetic proportional pressure reducing valve for the boom valve to follow the target speed of the boom corresponding to the operation signal of the operating device, and when an error occurs between the actual speed of the boom and the target speed of the boom, the boom and a control device for calculating the pilot pressure to be transmitted to the boom valve in order to follow the target speed of , and transmitting a command current value to the electromagnetic proportional pressure reducing valve for the boom valve to generate the calculated pilot pressure.
  • the construction machine can control the speed of the boom as desired by the user.
  • FIG. 1 is a side view of a construction machine according to an embodiment of the present invention.
  • FIG. 2 is a hydraulic circuit diagram illustrating a hydraulic system used in the construction machine of FIG. 1 .
  • FIG. 3 is a view showing a boom valve used in the hydraulic system of FIG. 1 .
  • FIG. 4 is a graph showing the correlation between the spool displacement and the opening area of the boom valve used in the hydraulic system of FIG. 1 .
  • 5 and 6 are graphs showing the correlation between the command current applied to the electromagnetic proportional pressure reducing valve and the pilot pressure generated by the electromagnetic proportional pressure reducing valve.
  • FIG. 7 is a flowchart illustrating a method for controlling a construction machine according to an embodiment of the present invention.
  • the embodiment of the present invention specifically represents an ideal embodiment of the present invention. As a result, various modifications of the diagram are expected. Accordingly, the embodiment is not limited to a specific shape of the illustrated area, and includes, for example, a shape modification by manufacturing.
  • FIGS. 1 to 6 a construction machine 101 according to an embodiment of the present invention will be described with reference to FIGS. 1 to 6 .
  • an excavator as the construction machine 101 will be described as an example.
  • the construction machine 101 is not limited to the excavator, and the present invention may be applied to any construction machine equipped with a working device 160 for generating potential energy, such as a boom 170 .
  • the construction machine 101 is installed on the lower traveling body 120 , the upper revolving body 130 mounted so as to be revolving on the lower traveling body 120 , and the upper revolving body 130 . It may include a cab 150 in which the user rides and various work devices 160 .
  • the lower traveling body 120 supports the upper revolving body 130 , and using power generated from the engine 100 (shown in FIG. 2 ) may be used to drive the construction machine 101 through the traveling device.
  • the lower traveling body 120 may be a caterpillar type traveling body including a caterpillar or a wheel type traveling body including traveling wheels.
  • the upper revolving body 130 may rotate on the lower traveling body 120 to set the working direction.
  • the upper revolving body 130 may include an upper frame 132 and a cab 150 and a work device 160 installed in the upper frame 132 .
  • the working device 160 may include a boom 170 , an arm 180 , and a bucket 190 .
  • a boom cylinder 200 for controlling the movement of the boom 170 may be installed between the boom 170 and the upper frame 132 .
  • an arm cylinder 182 for controlling the movement of the arm 180 is installed between the boom 170 and the arm 180 , and the movement of the bucket 190 is controlled between the arm 180 and the bucket 190 .
  • a bucket cylinder 192 for controlling may be installed.
  • the boom 170, the arm 180, and the bucket 190 may implement various movements, and the working device 160 ) can perform several tasks.
  • the boom cylinder 200 , the arm cylinder 182 , and the bucket cylinder 192 are operated by hydraulic oil supplied from the main pump 310 (shown in FIG. 2 ) to be described later.
  • the hydraulic system used in the construction machine 101 is a boom cylinder 200, a boom valve 410, an electromagnetic proportional pressure reducing valve 460 for the boom valve, an operation device 770 , and a control device 700 .
  • the hydraulic system used in the construction machine 101 includes a pilot pressure sensor 760 , a control valve 500 , a first boom hydraulic line 610 , and a second boom hydraulic line 620 .
  • recirculation line 650 first pressure sensor 710, second pressure sensor 720, main pump 310, pilot pump 370, engine 100, regenerative motor 380, regenerative line ( 670 ), a regenerative valve 420 , an electromagnetic proportional pressure reducing valve 470 for a regenerative valve, an accumulator 800 , and an accumulator valve 480 may be further included.
  • the engine 100 is connected to a main pump 310 to be described later to provide power.
  • the engine 100 generates power by burning fuel.
  • engine 100 may be a diesel engine or may be a liquefied natural gas (LNG) engine, a compressed natural gas (CNG) engine, an adsorption natural gas (ANG) engine, a liquefied petroleum gas (LPG) engine, or a gasoline engine.
  • LNG liquefied natural gas
  • CNG compressed natural gas
  • ANG adsorption natural gas
  • LPG liquefied petroleum gas
  • gasoline engine liquefied petroleum gas
  • an embodiment of the present invention is not limited to the above, and other power devices such as an electric motor may be used instead of the engine 100 .
  • the engine 100 may be connected to a pilot pump 370 to be described later in addition to the main pump 310 to provide power to the pilot pump 370 .
  • the engine 100 may be connected to a regenerative motor 380 to be described later in addition to the main pump 310 to receive energy from the regenerative motor 380 .
  • the main pump 310 operates with the power generated by the engine 100 and discharges hydraulic oil.
  • the hydraulic oil discharged from the main pump 310 may be supplied to various working devices 160 including a boom cylinder 200 to be described later.
  • the main pump 310 may be a variable capacity pump in which the discharged flow rate varies according to the angle of the swash plate.
  • the boom cylinder 200 elevates the boom 170 and is divided into a head side 210 and a rod side 220 .
  • the control valve 500 controls the supply of hydraulic oil discharged by the main pump 310 to the boom cylinder 200 . That is, the hydraulic oil discharged from the main pump 310 is supplied to the head side 210 of the boom cylinder 200 or supplied to the rod side 220 of the boom cylinder 200 according to the switching operation of the control valve 500 , or Supply may be cut off.
  • the first boom hydraulic line 610 connects the control valve 500 and the head side 210 of the boom cylinder 200 .
  • the second boom hydraulic line 620 connects the control valve 500 and the rod side 220 of the boom cylinder 200 .
  • the hydraulic oil discharged from the main pump 310 and passed through the control valve 500 moves to the head side 210 of the boom cylinder 200 along the first boom hydraulic line 610 or the second boom hydraulic line ( It can move to the rod side 220 of the boom cylinder 200 along 620 .
  • the recirculation line 630 is branched from the first boom hydraulic line 610 and is connected to the second boom hydraulic line 620 . A portion of the hydraulic oil discharged to the head side 210 of the boom cylinder 200 by the recirculation line 630 may be supplied to the rod side 220 of the boom cylinder 200 .
  • some of the hydraulic oil discharged from the head side 210 of the boom cylinder 200 during the lowering operation of the boom 170 moves along the recirculation line 630 and passes through the second boom hydraulic line 620 to the boom cylinder ( 200) into the rod side 220 .
  • the hydraulic oil discharged from the head side 210 of the boom cylinder 200 flows into the rod side 220 of the boom cylinder 200 to increase the pressure of the boom cylinder 200 and increase the energy Utilization efficiency can be improved.
  • the boom valve 410 is installed on the recirculation line 630 .
  • the boom valve 410 may control the flow rate of the hydraulic oil discharged from the head side 210 of the boom cylinder 200 .
  • the boom valve 410 may control the flow rate of hydraulic oil discharged from the head side 210 of the boom cylinder 200 and introduced into the rod side 220 of the boom cylinder 200 .
  • the boom valve 410 controls the speed of the boom 170 , in particular, the descending speed of the boom 170 .
  • the boom valve 410 when the boom valve 410 is opened, the high pressure of the head side 210 is transferred to the rod side 220 to increase the pressure on the rod side 220 , and the head side due to the increased pressure on the rod side 220 . (210) The pressure rises again. Due to this, the pressure of the head side 210 of the boom cylinder 200 is increased during the lowering operation of the boom 170, and the regenerative motor 380 through the regenerative valve 420 to be described later for the increased head side 210 pressure. Energy efficiency may be increased by driving or storing in the accumulator 800 .
  • the boom valve 410 includes a sleeve 415 and a spool 411 for adjusting the opening area through which the hydraulic oil will pass while moving within the sleeve 415 , and the spool 411 . It may include a spring 418 to restore the position of the. That is, the position of the spool 411 of the boom valve 410 is changed according to the received pilot pressure P S1 , and the opening area is adjusted according to the displacement of the spool 411 . In this case, the displacement of the spool 411 may be calculated through Equation 4 to be described later.
  • An electric proportional pressure reducing valve (EPPR valve) 460 for the boom valve generates a pilot pressure P S1 to be delivered to the boom valve 410 . That is, the pilot pressure P S1 generated by the electromagnetic proportional pressure reducing valve 460 for the boom valve presses one end of the spool 411 of the boom valve 410 to displace the spool 411 .
  • the pilot pump 370 supplies the hydraulic oil required for the electromagnetic proportional pressure reducing valve 460 for the boom valve to generate the pilot pressure P S1 .
  • the electromagnetic proportional pressure reducing valve 460 for the boom valve processes it to generate the secondary pilot pressure, and thus the generated secondary The pilot pressure presses one end of the spool 411 of the boom valve 410 .
  • the operation device 770 generates an operation signal for operation of the boom 170 .
  • a control device to be described later ( 700 ) receives an operation signal from the operation device ( 770 ) and transmits a current command value corresponding to the operation signal to the electromagnetic proportional pressure reducing valve ( 460 ) for a boom valve. Then, the electromagnetic proportional pressure reducing valve 460 for the boom valve generates a pilot pressure P S1 according to the received current command value.
  • manipulation device 770 may include a joystick, a manipulation lever, and a pedal installed in the cab 150 so that the user can operate the various working devices 160 and the driving device.
  • the first pressure sensor 710 is installed on the first boom hydraulic line 610 . That is, the pressure measured by the first pressure sensor 710 becomes the head side 210 pressure of the boom cylinder 200 .
  • the second pressure sensor 720 is installed on the second boom hydraulic line 620 . That is, the pressure measured by the second pressure sensor 720 becomes the pressure on the rod side 220 of the boom cylinder 200 .
  • the pressure difference between the front and rear ends of the boom valve 410 may be calculated using the first pressure sensor 710 and the second pressure sensor 720 . That is, one port of the boom valve 410 is connected to the head side 210 of the boom cylinder 200, and the other port of the boom valve 410 is connected to the rod side 220 of the boom cylinder 200,
  • the pressure difference ⁇ P applied to both ends of the boom valve 410 may be calculated as in Equation 1 below.
  • Ph is the pressure measured by the first pressure sensor 710 as the pressure on the head side 210 of the boom cylinder 200
  • Pr is the pressure on the rod side 220 of the boom cylinder 200 by the second pressure sensor ( 720) is the measured pressure.
  • the pilot pressure sensor 760 measures the pilot pressure generated by the electromagnetic proportional pressure reducing valve 460 for the boom valve and delivered to the boom valve 410 .
  • the control device 700 may calculate a target passage flow rate of the boom valve 410 corresponding to the operation signal of the operation device 770 and an opening area of the boom valve 410 for allowing the target flow rate to pass therethrough.
  • control device 700 determines the target speed of the boom 170 corresponding to the manipulation signal of the operating device 770 , and passes the target through which the hydraulic oil must pass through the boom valve 410 in order to achieve the target speed. Calculate the flow.
  • the target flow rate can be calculated through Equation 2 below.
  • V bm is the target speed of the boom 170
  • Q rod is the flow rate of the rod side 220 of the boom cylinder 200
  • a rod is the area of the rod side 220 of the boom cylinder 200
  • Q v1 is the target flow through which the boom valve 410 should pass.
  • the target flow rate to be discharged from the head side 210 of the boom cylinder 200 and to be introduced into the rod side 220 of the boom cylinder 200 through the boom valve 410 is determined through Equation 2 described above. can be calculated
  • control device 700 calculates the opening area of the boom valve 410 for passing the target flow rate as described above.
  • the opening area of the boom valve 410 may be calculated through Equation 3 below.
  • a v1 is the opening area of the boom valve and ⁇ is the density.
  • Cd is a constant preset as an outflow coefficient.
  • the pressure difference between the pressure measured by the first pressure sensor 710 and the pressure measured by the second pressure sensor 720 may be considered in calculating the opening area of the boom valve 410 for passing the target flow rate.
  • the control device 700 determines the displacement of the spool 411 from the spool displacement-area diagram defined according to the designed spool shape of the boom valve 410 . As shown in FIG. 4 , in one embodiment of the present invention, as the displacement of the spool 411 increases, the opening area through which the flow rate passes increases.
  • the displacement of the spool 411 is determined by the pilot pressure P S1 acting on one side of the spool 411 , which is the cross-sectional area of the spool 411 and the spring 418 supporting the spool 411 . follow the relationship
  • the displacement of the spool 411 may be calculated through Equation 4 below.
  • x is the displacement of the spool 411
  • k is the spring coefficient
  • F 0 is the initial spring preload force
  • P S1 is the pilot pressure acting on the receiving surface of the spool 411
  • As is the spool under pressure is the area of (411).
  • the control device 700 controls the calculated pilot pressure transmits the current command value to the electromagnetic proportional pressure reducing valve 460 for the boom valve to generate
  • the pilot pressure P S1 acting on the spool 411 is controlled by the electromagnetic proportional pressure reducing valve 460 for the boom valve, and as the current applied to the electromagnetic proportional pressure reducing valve 460 for the boom valve increases, the pilot pressure ( P S1 ) ideally shows an increasing characteristic as shown in FIG. 5 . At this time, if the current acting on the electromagnetic proportional pressure reducing valve 460 for the boom valve and the pilot pressure P S1 generated thereby exactly match as shown in FIG. 5 , the target speed can be achieved.
  • the current value corresponding to the pressure P1 at a specific point in time may be A1 or A2.
  • the current corresponding to P1 pressure in Fig. 6 is predefined as A1
  • P2 pressure is formed in the actual valve, which means that the target boom speed cannot be reached .
  • the adverse effect of greatly slowing the reaction of the boom appears.
  • the control device 700 compares the calculated pilot pressure with the pilot pressure measured by the pilot pressure sensor 760, and if the calculated pilot pressure and the measured pilot pressure are different from each other, the boom valve By controlling the electromagnetic proportional pressure reducing valve 460 for the boom valve so that the measured pilot pressure follows the calculated pilot pressure by correcting the current command value transmitted to the electromagnetic proportional pressure reducing valve 460 for hysteresis (hysteresis) generated in FIG. ) and response delay can be improved, and controllability of the boom 170 can be improved.
  • control device 700 calculates the target speed of the boom 170 corresponding to the operation signal of the operating device 770 and uses the boom valve so that the actual speed of the boom 170 follows the target speed of the boom 170 .
  • An electromagnetic proportional pressure reducing valve 460 may be controlled.
  • control device 700 controls the electromagnetic proportional pressure reducing valve 460 for the boom valve to follow the target speed of the boom 170 corresponding to the operation signal of the operation device 770 , and thus the actual speed of the boom 170 .
  • a current command value to generate the calculated pilot pressure may be delivered to the electromagnetic proportional pressure reducing valve 460 for the boom valve.
  • control device 700 may control various components of the construction machine 101 , such as the engine 100 , the main pump 310 , the regenerative motor 380 , and the control valve 500 .
  • control device 700 may include one or more of an engine control unit (ECU) and a vehicle control unit (VCU).
  • ECU engine control unit
  • VCU vehicle control unit
  • the regenerative motor 380 generates regenerative energy by performing a regenerative operation with the hydraulic oil discharged from the boom cylinder 200 .
  • the regenerative motor 380 is connected to a regenerative line 640 to be described later and operates with the pressure of the hydraulic oil supplied through the regenerative line 640 .
  • the regenerative motor 380 may drive the main pump 310 by assisting the engine 100 . That is, the fuel efficiency of the engine 100 can be reduced as much as the regenerative motor 380 drives the main pump 310 .
  • the regenerative motor 380 may also be of a variable capacity type, and the swash plate angle may be adjusted according to a signal from the control device 700 .
  • the engine 100 , the main pump 310 , the pilot pump 370 , and the regenerative motor 380 may be directly connected.
  • the regenerative line 640 is branched from the first boom hydraulic line 610 and is connected to the regenerative motor 380 .
  • the regeneration line 640 is branched from the first boom hydraulic line 610 to move the hydraulic oil discharged from the head side 210 of the boom cylinder 200 during the lowering operation of the boom 170 . That is, the hydraulic oil discharged from the boom cylinder 200 and moved along the regenerative line 640 operates the regenerative motor 380 .
  • the regenerative valve 420 is installed on the regenerative line 640 to control the flow rate of hydraulic oil discharged to the head side 210 of the boom cylinder 200, and the opening area is adjusted while the spool is displaced according to the received pilot pressure.
  • the electromagnetic proportional pressure reducing valve 470 for the regenerative valve generates a pilot pressure to be transmitted to the regenerative valve 420 .
  • the regenerative valve 420 and the electromagnetic proportional pressure reducing valve 470 for the regenerative valve operate according to the same operating principle as the above-described boom valve 410 and the electromagnetic proportional pressure reducing valve 460 for the boom valve. can do.
  • control device 700 calculates the target passage flow rate of the regenerative valve 420 corresponding to the operation signal of the operation device 770 and the opening area of the regenerative valve 420 for passing the target flow rate, and , it is possible to calculate the pilot pressure to be transmitted to the regenerative valve 420 to achieve the opening area, and transmit the current command value to the electromagnetic proportional pressure reducing valve 470 for the regenerative valve to generate the calculated pilot pressure.
  • the accumulator 800 is connected to the regeneration line 640 to accumulate hydraulic oil. That is, the accumulator 800 may store the hydraulic oil discharged from the boom cylinder 200 when the boom 170 is lowered, and supply the stored hydraulic oil to the regenerative motor 380 to regenerate energy.
  • the accumulator valve 480 controls the inflow and outflow of hydraulic oil into the accumulator 800 .
  • the accumulator valve 480 may operate according to a current command value of the control device 700 .
  • the construction machine 101 can control the speed of the boom 170 as desired by the user.
  • the control device 700 receives the operation signal and determines the target speed of the bom 170 according to the operation signal. do. That is, it determines the target speed of the boom 170 required by the user.
  • control device 700 calculates a target passage flow rate of the boom valve 410 for achieving the target speed, and calculates an opening area of the boom valve 410 required to pass the calculated target flow rate.
  • the control device 700 determines the displacement of the spool 411 corresponding to the opening area.
  • the pilot pressure required to displace the spool 411 is calculated.
  • control device 700 transmits the calculated current command value for generating the pilot pressure to the electromagnetic proportional pressure reducing valve 460 for the boom valve, and the electromagnetic proportional pressure reducing valve 460 for the boom valve responds to the received current command value. to generate pilot pressure.
  • the pilot pressure actually generated by the electromagnetic proportional pressure reducing valve 460 for the boom valve is measured, and the pilot pressure calculated by the control device 700 is compared with the pilot pressure actually generated by the electromagnetic proportional pressure reducing valve 460 .
  • control device 700 corrects the current command value so that the measured pilot pressure follows the calculated pilot pressure.
  • the spool 411 of the boom valve 410 is displaced according to the pilot pressure, and as the spool 411 of the boom valve 410 is displaced, the pressure of the boom cylinder 200 is changed.
  • the control method of the construction machine 101 it is possible to control the speed of the boom 170 as desired by the user. That is, it is possible to suppress the occurrence of hysteresis and response delay in the control process and improve the controllability of the boom 170 .
  • upper frame 150 cab
  • pilot pump 380 regenerative motor
  • first boom hydraulic line 620 second boom hydraulic line
  • control device 710 first pressure sensor
  • An embodiment of the present invention may provide a construction machine capable of controlling the speed of the boom as desired by the user.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Operation Control Of Excavators (AREA)

Abstract

본 발명의 실시예에 따른 붐을 포함하는 건설 기계는 상기 붐을 승강시키며 헤드측과 로드측으로 구분된 붐 실린더와, 상기 붐 실린더의 헤드측에서 배출되는 작동유의 유량을 제어하며, 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 붐 밸브와, 상기 붐 밸브에 전달할 상기 파일럿 압력을 생성하는 붐 밸브용 전자 비례 감압 밸브와, 상기 붐의 조작을 위한 조작 신호를 발생시키는 조작 장치, 그리고 상기 조작 장치의 조작 신호에 대응하는 상기 붐 밸브의 목표 통과 유량과 상기 목표 통과 유량을 통과시키기 위한 상기 붐 밸브의 개구 면적을 계산하고 상기 개구 면적을 달성하기 위해 상기 붐 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 붐 밸브용 전자 비례 감압 밸브에 전달하는 제어 장치를 포함한다.

Description

건설 기계
본 발명은 건설 기계에 관한 것으로, 더욱 상세하게는 붐의 속도를 제어할 수 있는 건설 기계에 관한 것이다.
건설 기계는 크게 토목 공사나 건축 공사에 사용되는 모든 기계를 말한다. 일반적으로 건설 기계는 엔진과 엔진의 동력으로 동작하는 유압 펌프를 가지며, 엔진과 유압 펌프를 통해 발생한 동력으로 주행을 하거나 작업 장치를 구동한다.
예를 들어, 건설 기계의 한 종류인 굴삭기는 토목, 건축, 건설 현장에서 땅을 파는 굴삭 작업, 토사를 운반하는 적재 작업, 건물을 해체하는 파쇄 작업, 지면을 정리하는 정지 작업 등의 작업을 행하는 건설 기계로서 장비의 이동 역할을 하는 주행체와, 주행체에 탑재되어 360도 회전하는 상부 선회체, 그리고 작업 장치로 구성되어 있다.
또한, 굴삭기는 주행에 이용되는 주행 모터와, 상부 선회체 스윙(swing)에 사용되는 선회 모터, 그리고 작업 장치에 이용되는 붐 실린더, 암 실린더, 버킷 실린더, 및 옵션 실린더 등의 구동 장치들을 포함한다. 그리고 이러한 구동 장치들은 엔진 또는 전기 모터에 의해 구동되는 가변 용량형 유압 펌프로부터 토출되는 작동유에 의해 구동된다.
그런데, 붐, 암, 및 각종 어태치먼트는 상대적으로 매우 무거운 중량을 갖고 있으므로, 사용자가 조이스틱을 조작해 붐을 하강시킬 때 사용자의 의도와 다른 속도로 붐이 하강되기 쉽다.
전류 지령값이 변경된 후 변경된 전류 지령값에 따라 붐의 속도가 변경되기까지는 여러 신호 전달 체계를 거치게 되고 그 과정에서 응답 지연과 히스테리시스(hysteresis) 현상이 발생된다. 이에, 붐의 속도가 보정되기까지 지연 및 왜곡이 발생되므로 붐의 속도를 사용자의 의도대로 제어하기 어려운 문제점이 있다.
본 발명의 실시예는 붐의 속도를 사용자의 의도대로 제어할 수 있는 건설 기계를 제공한다.
본 발명의 실시예에 따르면, 붐을 포함하는 건설 기계는 상기 붐을 승강시키며 헤드측과 로드측으로 구분된 붐 실린더와, 상기 붐 실린더의 헤드측에서 배출되는 작동유의 유량을 제어하며, 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 붐 밸브와, 상기 붐 밸브에 전달할 상기 파일럿 압력을 생성하는 붐 밸브용 전자 비례 감압 밸브와, 상기 붐의 조작을 위한 조작 신호를 발생시키는 조작 장치, 그리고 상기 조작 장치의 조작 신호에 대응하는 상기 붐 밸브의 목표 통과 유량과 상기 목표 통과 유량을 통과시키기 위한 상기 붐 밸브의 개구 면적을 계산하고 상기 개구 면적을 달성하기 위해 상기 붐 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 붐 밸브용 전자 비례 감압 밸브에 전달하는 제어 장치를 포함한다.
상기한 건설 기계는 상기 붐 밸브용 전자 비례 감압 밸브가 생성한 파일럿 압력을 측정하는 파일럿 압력 센서를 더 포함할 수 있다. 그리고 상기 제어 장치는 산출된 상기 파일럿 압력과 상기 파일럿 압력 센서가 측정한 상기 파일럿 압력을 비교하고, 측정된 상기 파일럿 압력이 산출된 상기 파일럿 압력을 추종하도록 상기 붐 밸브용 전자 비례 감압 밸브를 제어할 수 있다.
상기한 건설 기계는 상기 붐 실린더에 대한 작동유의 공급을 제어하는 제어 밸브와, 상기 제어 밸브와 상기 붐 실린더의 헤드측을 연결하는 제1 붐 유압 라인과, 상기 제어 밸브와 상기 붐 실린더의 로드측을 연결하는 제2 붐 유압 라인, 그리고 상기 제1 붐 유압 라인에서 분기되어 상기 제2 붐 유압 라인과 연결된 재순환 라인을 더 포함할 수 있다. 그리고 상기 붐 밸브는 상기 재순환 라인 상에 설치될 수 있다.
상기한 건설 기계는 상기 제1 붐 유압 라인 상에 설치된 제1 압력 센서와, 상기 제2 붐 유압 라인 상에 설치된 제2 압력 센서를 더 포함할 수 있다. 그리고 상기 제어 장치는 상기 제1 압력 센서가 측정한 압력과 상기 제2 압력 센서가 측정한 압력 차이를 고려하여 상기 목표 통과 유량을 통과시키기 위한 상기 붐 밸브의 개구 면적을 계산할 수 있다.
상기한 건설 기계는 상기 제어 밸브로 작동유를 공급하는 메인 펌프와, 상기 붐 밸브용 전자 비례 감압 밸브가 상기 파일럿 압력을 생성하기 위해 필요한 작동유를 공급하는 파일럿 펌프, 그리고 상기 메인 펌프 및 상기 파일럿 펌프에 회전 동력을 제공하는 엔진을 더 포함할 수 있다.
상기한 건설 기계는 상기 붐 실린더에서 배출된 작동유로 회생 동작을 수행하여 재생 에너지를 생성하는 회생 모터와, 상기 제1 붐 유압 라인에서 분기되어 상기 회생 모터와 연결된 회생 라인과, 상기 회생 라인 상에 설치되어 상기 붐 실린더의 헤드측으로 배출되는 작동유의 유량을 제어하며 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 회생 밸브, 그리고 상기 회생 밸브에 전달할 상기 파일럿 압력을 생성하는 회생 밸브용 전자 비례 감압 밸브를 더 포함할 수 있다.
상기 제어 장치는 상기 조작 장치의 조작 신호에 대응하는 상기 회생 밸브의 목표 통과 유량과 상기 목표 통과 유량을 통과시키기 위한 상기 회생 밸브의 개구 면적을 계산하고, 상기 개구 면적을 달성하기 위해 상기 회생 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고, 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 회생 밸브용 전자 비례 감압 밸브에 전달할 수 있다.
상기한 건설 기계는 상기 회생 라인과 연결되어 작동유를 축적하는 어큐뮬레이터와, 상기 어큐뮬레이터로의 작동유 유출입을 제어하는 어큐뮬레이터 밸브를 더 포함할 수 있다.
상기 조작 장치의 조작 신호에 대응하는 상기 붐의 목표 속도를 계산하고 상기 붐의 실제 속도가 상기 붐의 목표 속도를 추종하도록 상기 붐 밸브용 전자 비례 감압 밸브를 제어할 수 있다.
또한, 본 발명의 다른 실시예에 따르면, 붐을 포함하는 건설 기계는 상기 붐을 승강시키며 헤드측과 로드측으로 구분된 붐 실린더와, 상기 붐 실린더의 헤드측에서 배출되는 작동유의 유량을 제어하며 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 붐 밸브와, 상기 붐 밸브에 전달할 상기 파일럿 압력을 생성하는 붐 밸브용 전자 비례 감압 밸브와, 상기 붐의 조작을 위한 조작 신호를 발생시키는 조작 장치, 그리고 상기 조작 장치의 조작 신호에 대응하는 상기 붐의 목표 속도를 추종하도록 상기 붐 밸브용 전자 비례 감압 밸브를 제어하고 상기 붐의 실제 속도와 상기 붐의 목표 속도 간에 오차가 발생하는 경우 상기 붐의 목표 속도를 추종하기 위해 상기 붐 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 붐 밸브용 전자 비례 감압 밸브에 전달하는 제어 장치를 포함한다.
본 발명의 실시예에 따르면, 건설 기계는 붐의 속도를 사용자의 의도대로 제어할 수 있다.
도 1은 본 발명의 일 실시예에 따른 건설 기계의 측면도이다.
도 2는 도 1의 건설 기계에 사용된 유압 시스템을 나타낸 유압 회로도이다.
도 3은 도 1의 유압 시스템에 사용된 붐 밸브를 나타낸 도면이다.
도 4는 도 1의 유압 시스템에 사용된 붐 밸브의 스풀 변위와 개구 면적의 상관관계를 나타낸 그래프이다.
도 5 및 도 6은 전자 비례 감압 밸브에 인가된 전류 지령값과 전자 비례 감압 밸브가 생성한 파일럿 압력의 상관관계를 나타낸 그래프이다.
도 7은 본 발명의 일 실시예에 따른 건설 기계의 제어 방법을 나타낸 순서도이다.
이하, 첨부한 도면을 참고로 하여 본 발명의 실시예에 대하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 상세히 설명한다. 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다.
도면들은 개략적이고 축척에 맞게 도시되지 않았다는 것을 일러둔다. 도면에 있는 부분들의 상대적인 치수 및 비율은 도면에서의 명확성 및 편의를 위해 그 크기에 있어 과장되거나 축소되어 도시되었으며 임의의 치수는 단지 예시적인 것이지 한정적인 것은 아니다. 그리고 둘 이상의 도면에 나타나는 동일한 구조물, 요소 또는 부품에는 동일한 참조 부호가 유사한 특징을 나타내기 위해 사용된다.
본 발명의 실시예는 본 발명의 이상적인 실시예를 구체적으로 나타낸다. 그 결과, 도해의 다양한 변형이 예상된다. 따라서 실시예는 도시한 영역의 특정 형태에 국한되지 않으며, 예를 들면 제조에 의한 형태의 변형도 포함한다.
이하, 도 1 내지 도 6을 참조하여 본 발명의 일 실시예에 따른 건설 기계(101)를 설명한다.
본 명세서에서는, 건설 기계(101)로 굴삭기를 예로 들어 설명한다. 하지만, 건설 기계(101)가 굴삭기에 한정되는 것은 아니며, 본 발명은 붐(170)과 같이 위치 에너지를 발생시키는 작업 장치(160)가 장착된 모든 건설 기계에 적용될 수 있다.
도 1에 도시한 바와 같이, 건설기계(101)는 하부 주행체(120), 하부 주행체(120) 상에 선회 가능하도록 탑재되는 상부 선회체(130), 및 상부 선회체(130)에 설치되어 사용자가 탑승하는 운전실(150)과 각종 작업 장치(160)를 포함할 수 있다.
하부 주행체(120)는 상부 선회체(130)를 지지하고, 엔진(100)(도 2에 도시)에서 발생한 동력을 이용하여 주행 장치를 통해 건설 기계(101)를 주행시킬 수 있다. 하부 주행체(120)는 무한궤도를 포함하는 무한궤도식 타입의 주행체이거나 주행 휠들을 포함하는 휠 타입의 주행체일 수 있다.
상부 선회체(130)는 하부 주행체(120) 상에서 회전하여 작업 방향을 설정할 수 있다. 상부 선회체(130)는 상부 프레임(132)과 상부 프레임(132)에 설치되는 운전실(150)과 작업 장치(160)를 포함할 수 있다.
작업 장치(160)는 붐(170), 암(180) 및 버켓(190)을 포함할 수 있다. 붐(170)과 상부 프레임(132) 사이에는 붐(170)의 움직임을 제어하기 위한 붐 실린더(200)가 설치될 수 있다. 또한, 붐(170)과 암(180) 사이에는 암(180)의 움직임을 제어하기 위한 암 실린더(182)가 설치되고, 암(180)과 버켓(190) 사이에는 버켓(190)의 움직임을 제어하기 위한 버켓 실린더(192)가 설치될 수 있다.
붐 실린더(200), 암 실린더(182) 및 버켓 실린더(192)가 신장 또는 수축함에 따라 붐(170), 암(180), 및 버켓(190)은 다양한 움직임을 구현할 수 있고, 작업 장치(160)는 여러 작업들을 수행할 수 있다. 이때, 붐 실린더(200), 암 실린더(182) 및 버켓 실린더(192)는 후술할 메인 펌프(310)(도 2에 도시)로부터 공급되는 작동유에 의해 동작된다.
도 2에 도시한 바와 같이, 본 발명의 일 실시예에 따른 건설 기계(101)에 사용되는 유압 시스템은 붐 실린더(200), 붐 밸브(410), 붐 밸브용 전자 비례 감압 밸브(460), 조작 장치(770), 및 제어 장치(700)를 포함한다.
또한, 본 발명의 일 실시예에 따른 건설 기계(101)에 사용되는 유압 시스템은 파일럿 압력 센서(760), 제어 밸브(500), 제1 붐 유압 라인(610), 제2 붐 유압 라인(620), 재순환 라인(650), 제1 압력 센서(710), 제2 압력 센서(720), 메인 펌프(310), 파일럿 펌프(370), 엔진(100), 회생 모터(380), 회생 라인(670), 회생 밸브(420), 회생 밸브용 전자 비례 감압 밸브(470), 어큐뮬레이터(800), 및 어큐뮬레이터 밸브(480)를 더 포함할 수 있다.
엔진(100)은 후술할 메인 펌프(310)와 연결되어 동력을 제공한다. 엔진(100)은 연료를 연소시켜 동력을 발생시킨다. 예를 들어, 엔진(100)은 디젤 엔진이거나 액화 천연 가스(LNG) 엔진, 압축 천연 가스(CNG) 엔진, 흡착 천연 가스(ANG) 엔진, 액화 석유 가스(LPG) 엔진, 또는 가솔린 엔진일 수 있다. 하지만, 본 발명의 일 실시예가 전술한 바에 한정되는 것은 아니며, 엔진(100) 대신 전기 모터 등 다른 동력 장치가 사용될 수도 있다.
또한, 엔진(100)은 메인 펌프(310) 이외에 후술할 파일럿 펌프(370)와 연결되어 파일럿 펌프(370)에도 동력을 제공할 수도 있다.
또한, 엔진(100)은 메인 펌프(310) 이외에 후술할 회생 모터(380)와 연결되어 회생 모터(380)로부터 에너지를 공급받을 수도 있다.
메인 펌프(310)는 엔진(100)이 발생시킨 동력으로 동작하며 작동유를 토출한다. 메인 펌프(310)에서 토출된 작동유는 후술할 붐 실린더(200)를 포함한 각종 작업 장치(160)에 공급될 수 있다. 또한, 메인 펌프(310)는 사판의 각도에 따라 토출되는 유량이 가변하는 가변 용량형 펌프일 수 있다.
이하, 본 명세서에서는, 전술한 여러 작업 장치(160) 중에서 붐 실린더(200)를 예로 들어 설명한다. 붐 실린더(200)는 붐(170)을 승강시키며, 헤드측(210)과 로드측(220)으로 구분된다.
제어 밸브(500)는 붐 실린더(200)에 대한 메인 펌프(310)가 토출한 작동유의 공급을 제어한다. 즉, 메인 펌프(310)에서 토출된 작동유는 제어 밸브(500)의 절환 동작에 따라 붐 실린더(200)의 헤드측(210)으로 공급하거나 붐 실린더(200)의 로드측(220)으로 공급되거나 공급이 차단될 수 있다.
제1 붐 유압 라인(610)은 제어 밸브(500)와 붐 실린더(200)의 헤드측(210)을 연결한다.
제2 붐 유압 라인(620)은 제어 밸브(500)와 붐 실린더(200)의 로드측(220)을 연결한다.
즉, 메인 펌프(310)에서 토출되어 제어 밸브(500)를 통과한 작동유는 제1 붐 유압 라인(610)을 따라 붐 실린더(200)의 헤드측(210)으로 이동하거나 제2 붐 유압 라인(620)을 따라 붐 실린더(200)의 로드측(220)으로 이동할 수 있다.
재순환 라인(630)은 제1 붐 유압 라인(610)에서 분기되어 제2 붐 유압 라인(620)과 연결된다. 재순환 라인(630)에 의해 붐 실린더(200)의 헤드측(210)으로 배출된 작동유의 일부는 붐 실린더(200)의 로드측(220)으로 공급될 수 있다.
이에, 붐(170)의 하강 동작 시 붐 실린더(200)의 헤드측(210)에서 배출된 작동유 중 일부는 재순환 라인(630)을 따라 이동하다가 제2 붐 유압 라인(620)을 거쳐 붐 실린더(200)의 로드측(220)으로 유입된다. 이와 같이, 붐(170)의 하강 시 붐 실린더(200)의 헤드측(210)에서 배출된 작동유가 붐 실린더(200)의 로드측(220)으로 유입됨으로써 붐 실린더(200)의 압력을 높이고 에너지 이용 효율을 향상시킬 수 있다.
붐 밸브(410)는 재순환 라인(630) 상에 설치된다. 붐 밸브(410)는 붐 실린더(200)의 헤드측(210)에서 배출되는 작동유의 유량을 제어할 수 있다. 특히, 붐 밸브(410)는 붐 실린더(200)의 헤드측(210)에서 배출되어 붐 실린더(200)의 로드측(220)으로 유입되는 작동유의 유량을 제어할 수 있다. 이에, 붐 밸브(410)는 붐(170)의 속도, 특히 붐(170)의 하강 속도를 제어하게 된다.
예를 들어, 붐 밸브(410)가 개방되면, 고압의 헤드측(210) 압력이 로드측(220)으로 전달되어 로드측(220) 압력이 높아지고, 높아진 로드측(220) 압력으로 인해 헤드측(210) 압력이 다시 상승하게 된다. 이로 인하여, 붐(170)의 하강 작동 중 붐 실린더(200)의 헤드측(210)의 압력이 높아지고, 높아진 헤드측(210) 압력을 후술할 회생 밸브(420)를 통해 회생 모터(380)를 구동시키거나 어큐뮬레이터(800)에 저장함으로써 에너지 효율을 높일 수 있다.
구체적으로, 도 3에 도시한 바와 같이, 붐 밸브(410)는 슬리브(415)와, 슬리브(415) 내에서 이동하면서 작동유가 통과할 개구 면적을 조절하는 스풀(411), 그리고 스풀(411)의 위치를 복원시키는 스프링(418)을 포함할 수 있다. 즉, 붐 밸브(410)의 스풀(411)은 입력받은 파일럿 압력(PS1)에 따라 위치가 가변되고, 스풀(411)의 변위에 따라 개구 면적이 조절된다. 이때, 스풀(411)의 변위는 후술할 수학식 4를 통해 계산할 수 있다.
붐 밸브용 전자 비례 감압 밸브(electric proportional pressure reducing valve, EPPR valve)(460)는 붐 밸브(410)에 전달할 파일럿 압력(PS1)을 생성한다. 즉, 붐 밸브용 전자 비례 감압 밸브(460)가 생성한 파일럿 압력(PS1)은 붐 밸브(410)의 스풀(411)의 일단을 가압하여 스풀(411)을 변위시키게 된다.
파일럿 펌프(370)는 붐 밸브용 전자 비례 감압 밸브(460)가 파일럿 압력(PS1)을 생성하기 위해 필요한 작동유를 공급한다. 예를 들어, 파일럿 펌프(370)가 토출한 작동유의 압력을 1차 파일럿 압력이라고 하면, 붐 밸브용 전자 비례 감압 밸브(460)가 이를 가공하여 2차 파일럿 압력을 생성하고, 이렇게 생성된 2차 파일럿 압력이 붐 밸브(410)의 스풀(411)의 일단을 가압하게 된다.
조작 장치(770)는 붐(170)의 조작을 위한 조작 신호를 발생시킨다. 후술할 제어 장치는(700) 조작 장치(770)의 조작 신호를 받아 조작 신호에 대응하는 전류 지령값을 붐 밸브용 전자 비례 감압 밸브(460)에 전달한다. 그러면 붐 밸브용 전자 비례 감압 밸브(460)는 전달받은 전류 지령값에 따라 파일럿 압력(PS1)을 생성하게 된다.
또한, 조작 장치(770)는 각종 작업 장치(160)와 주행 장치를 사용자가 조작할 수 있도록 운전실(150) 내에 설치된 조이스틱, 조작 레버, 및 패달(pedal) 등을 포함할 수 있다.
제1 압력 센서(710)는 제1 붐 유압 라인 상(610)에 설치된다. 즉, 제1 압력 센서(710)가 측정한 압력은 붐 실린더(200)의 헤드측(210) 압력이 된다.
제2 압력 센서(720)는 제2 붐 유압 라인(620) 상에 설치된다. 즉, 제2 압력 센서(720)가 측정한 압력은 붐 실린더(200)의 로드측(220) 압력이 된다.
이와 같이, 제1 압력 센서(710)와 제2 압력 센서(720)를 사용하여 붐 밸브(410)의 전후단 압력 차이를 산출할 수 있다. 즉, 붐 밸브(410)의 일측 포트는 붐 실린더(200)의 헤드측(210)과 연결되고, 붐 밸브(410)의 타측 포트는 붐 실린더(200)의 로드측(220)과 연결되므로, 붐 밸브(410)의 양단에 걸리는 압력 차이(ΔP)는 아래 수학식 1과 같이 계산될 수 있다.
Figure PCTKR2021009626-appb-img-000001
여기서, Ph는 붐 실린더(200)의 헤드측(210) 압력으로 제1 압력 센서가(710) 측정한 압력이고, Pr은 붐 실린더(200)의 로드측(220) 압력으로 제2 압력 센서(720)가 측정한 압력이다.
파일럿 압력 센서(760)는 붐 밸브용 전자 비례 감압 밸브(460)가 생성하여 붐 밸브(410)에 전달하는 파일럿 압력을 측정한다.
제어 장치(700)는 조작 장치(770)의 조작 신호에 대응하는 붐 밸브(410)의 목표 통과 유량과, 목표 통과 유량을 통과시키기 위한 붐 밸브(410)의 개구 면적을 계산할 수 있다.
구체적으로, 제어 장치(700)는 조작 장치(770)의 조작 신호에 대응하는 붐(170)의 목표 속도를 결정하고, 목표 속도를 달성하기 위해 작동유가 붐 밸브(410)를 통과해야 할 목표 통과 유량을 계산한다.
예를 들어, 목표 통과 유량은 아래 수학식 2를 통해 계산할 수 있다.
Figure PCTKR2021009626-appb-img-000002
여기서, Vbm는 붐(170)의 목표 속도이고, Qrod는 붐 실린더(200)의 로드측(220)의 유량이며, Arod는 붐 실린더(200)의 로드측(220)의 면적이고, Qv1는 붐 밸브(410)를 통과해야 할 목표 통과 유량이다.
이와 같이, 붐 실린더(200)의 헤드측(210)에서 배출되어 붐 밸브(410)를 거쳐 붐 실린더(200)의 로드측(220)으로 유입되어야 할 목표 통과 유량을 전술한 수학식 2를 통해 계산할 수 있다.
다음, 제어 장치(700)는 전술한 바와 같은 목표 통과 유량을 통과시키기 위한 붐 밸브(410)의 개구 면적을 계산한다.
붐 밸브(410)의 개구 면적은 아래 수학식 3을 통해 계산할 수 있다.
Figure PCTKR2021009626-appb-img-000003
여기서, Av1 은 붐 밸브의 개구 면적이고, ρ는 밀도이다. Cd는 유출 계수로 기설정된 상수이다.
이와 같이, 목표 통과 유량을 통과시키기 위한 붐 밸브(410)의 개구 면적 계산에 제1 압력 센서(710)가 측정한 압력과 제2 압력 센서(720)가 측정한 압력 차이가 고려될 수 있다.
다음, 붐 밸브(410)의 개구 면적이 결정되면, 제어 장치(700)는 붐 밸브(410)의 설계된 스풀 형상에 따라 정의된 스풀 변위 - 면적 선도로부터 스풀(411)의 변위를 결정한다. 도 4에 도시한 바와 같이, 본 발명의 일 실시예에서는 스풀(411)의 변위가 증가할 수록 유량이 통과하는 개구 면적이 증가된다.
이때, 스풀(411)의 변위는 스풀(411)의 한쪽 면에 작용하는 파일럿 압력(PS1)에 의해 결정되며, 이는 스풀(411)의 단면적과 스풀(411)을 지지하는 스프링(418)의 관계에 따른다.
구체적으로, 도 3을 참조하여 스풀(411)의 변위는 아래 수학식 4를 통해 계산할 수 있다.
Figure PCTKR2021009626-appb-img-000004
여기서, x는 스풀(411)의 변위이고, k는 스프링 계수이고, F0는 초기 스프링 예압력이고, PS1은 스풀(411)의 수압면에 작용하는 파일럿 압력이고, As는 압력을 받는 스풀(411)의 면적이다.
이와 같이, 수학식 4에 의해 스풀(411)을 x 만큼 이동시키기 위한 파일럿 압력(PS1)을 계산할 수 있다.
전술한 바와 같이, 붐 밸브(410)의 개구 면적을 달성하기 위해 붐 밸브(410)에 전달되어 스풀(411)에 가해져야 하는 상기 파일럿 압력이 산출되면, 제어 장치(700)는 산출된 파일럿 압력을 생성하도록 전류 지령값을 붐 밸브용 전자 비례 감압 밸브(460)에 전달한다.
스풀(411)에 작용하는 파일럿 압력(PS1)은 붐 밸브용 전자 비례 감압 밸브(460)에 의해 제어되며, 붐 밸브용 전자 비례 감압 밸브(460)에 인가되는 전류가 증가함에 따라 파일럿 압력(PS1)은 이상적으로는 도 5와 같이 증가하는 특성을 보인다. 이때, 붐 밸브용 전자 비례 감압 밸브(460)에 작용하는 전류와 그에 의해 생성되는 파일럿 압력(PS1)이 도 5와 같이 정확히 일치하면 목표로 하는 속도가 달성될 수 있다.
그러나 실제로는, 도 6과 같이 유체의 압축성, 마찰, 유동력 등에 의해 압력 상승 및 하강 시 히스테리시스(hysteresis) 및 응답 지연이 발생하게 된다. 예를 들어, 특정 시점에서 압력(P1)에 해당하는 전류값은 A1 또는 A2가 될 수 있다. 상시 상황에서 도 6에서 P1 압력에 해당하는 전류가 A1으로 사전 정의되어 있는 경우, 압력이 상승하는 경우 실제 밸브에는 P2 압력이 형성되며, 이는 곧 목표로 한 붐 속도에 도달할 수 없음을 의미한다. 특히 급 조작 조건인 경우 붐의 반응이 크게 느려지는 악영향이 나타난다.
하지만, 본 발명의 일 실시예에서, 제어 장치(700)는 산출된 파일럿 압력과 파일럿 압력 센서(760)가 측정한 파일럿 압력을 비교하고, 산출된 파일럿 압력과 측정된 파일럿 압력이 상이하다면 붐 밸브용 전자 비례 감압 밸브(460)에 전달되는 전류 지령값을 보정하여 측정된 파일럿 압력이 산출된 파일럿 압력을 추종하도록 붐 밸브용 전자 비례 감압 밸브(460)를 제어함으로써, 도 5에서 발생한 히스테리시스(hysteresis) 및 응답 지연을 개선할 수 있으며 붐(170)의 제어성을 향상시킬 수 있다.
또한, 제어 장치(700)는 조작 장치(770)의 조작 신호에 대응하는 붐(170)의 목표 속도를 계산하고 붐(170)의 실제 속도가 붐(170)의 목표 속도를 추종하도록 붐 밸브용 전자 비례 감압 밸브(460)를 제어할 수 있다.
한편, 제어 장치(700)는 조작 장치(770)의 조작 신호에 대응하는 붐(170)의 목표 속도를 추종하도록 붐 밸브용 전자 비례 감압 밸브(460)를 제어하여, 붐(170)의 실제 속도와 붐(170)의 목표 속도 간에 오차가 발생하는 경우, 붐(170)의 목표 속도를 추종하기 위해 붐 밸브(410)에 전달되어야 하는 파일럿 압력을 산출하고 산출된 파일럿 압력을 생성하도록 전류 지령값을 붐 밸브용 전자 비례 감압 밸브(460)에 전달할 수도 있다.
또한, 제어 장치(700)는 엔진(100), 메인 펌프(310), 회생 모터(380), 및 제어 밸브(500) 등 건설 기계(101)의 여러 구성들을 제어할 수 있다. 그리고 제어 장치(700)는 엔진 제어 장치(engine control unit, ECU) 및 차량 제어 장치(vehicle control unit, VCU) 중 하나 이상을 포함할 수 있다.
회생 모터(380)는 붐 실린더(200)에서 배출된 작동유로 회생 동작을 수행하여 재생 에너지를 생성한다. 회생 모터(380)는 후술할 회생 라인(640)과 연결되어 회생 라인(640)을 통해 공급받은 작동유의 압력으로 동작한다. 회생 모터(380)는 엔진(100)을 보조하여 메인 펌프(310)를 구동시킬 수 있다. 즉, 회생 모터(380)가 메인 펌프(310)를 구동시킨 만큼 엔진(100)의 연비를 절감할 수 있다. 또한, 회생 모터(380)도 가변 용량형일 수 있으며, 제어 장치(700)의 신호에 따라 사판각이 조절될 수 있다.
일례로, 엔진(100)과, 메인 펌프(310), 파일럿 펌프(370), 그리고 회생 모터(380)는 직결될 수 있다.
회생 라인(640)은 제1 붐 유압 라인(610)에서 분기되어 회생 모터(380)와 연결된다. 이와 같이, 회생 라인(640)은 제1 붐 유압 라인(610)에서 분기되어 붐(170)의 하강 동작 시 붐 실린더(200)의 헤드측(210)에서 배출된 작동유를 이동시킨다. 즉, 붐 실린더(200)에서 배출되어 회생 라인(640)을 따라 이동한 작동유는 회생 모터(380)를 동작시킨다.
회생 밸브(420)는 회생 라인(640) 상에 설치되어 붐 실린더(200)의 헤드측(210)으로 배출되는 작동유의 유량을 제어하며, 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절될 수 있다.
회생 밸브용 전자 비례 감압 밸브(470)는 회생 밸브(420)에 전달할 파일럿 압력을 생성한다.
본 발명의 일 실시예에서, 회생 밸브(420) 및 회생 밸브용 전자 비례 감압 밸브(470)는 전술한 붐 밸브(410) 및 붐 밸브용 전자 비례 감압 밸브(460)와 동일한 동작 원리에 따라 동작할 수 있다.
예를 들어, 제어 장치(700)는 조작 장치(770)의 조작 신호에 대응하는 회생 밸브(420)의 목표 통과 유량과, 목표 통과 유량을 통과시키기 위한 회생 밸브(420)의 개구 면적을 계산하고, 개구 면적을 달성하기 위해 회생 밸브(420)에 전달되어야 하는 파일럿 압력을 산출하고, 산출된 파일럿 압력을 생성하도록 전류 지령값을 회생 밸브용 전자 비례 감압 밸브(470)에 전달할 수 있다.
어큐뮬레이터(800)는 회생 라인(640)과 연결되어 작동유를 축적한다. 즉, 어큐뮬레이터(800)는 붐(170)의 하강 시 붐 실린더(200)에서 배출된 작동유를 저장하였다가 저장된 작동유를 회생 모터(380)로 공급하여 에너지를 회생시킬 수 있다.
어큐뮬레이터 밸브(480)는 어큐뮬레이터로(800)의 작동유 유출입을 제어한다. 어큐뮬레이터 밸브(480)는 제어 장치(700)의 전류 지령값에 따라 동작할 수 있다.
이와 같은 구성에 의하여, 본 발명의 일 실시예에 따른 건설 기계(101)는 붐(170)의 속도를 사용자의 의도대로 제어할 수 있게 된다.
즉, 제어 과정에서 히스테리시스(hysteresis) 및 응답 지연이 발생하는 것을 억제하고 붐(170)의 제어성을 향상시킬 수 있다.
이하, 도 6을 참조하여 본 발명의 일 실시예에 따른 건설 기계 (101)의 제어 방법을 상세히 설명한다.
먼저, 사용자가 붐(170)을 조작하기 위해 조작 장치(770)를 조작하여 조작 신호를 발생시키면, 제어 장치(700)가 조작 신호를 수신하여 조작 신호에 따른 봄(170)의 목표 속도를 결정한다. 즉, 사용자가 요구하는 붐(170)의 목표 속도를 결정한다.
그리고 제어 장치(700)는 목표 속도를 달성하기 위한 붐 밸브(410)의 목표 통과 유량을 계산하고, 계산된 목표 통과 유량을 통과시키기 위해 요구되는 붐 밸브(410)의 개구 면적을 계산한다.
다음, 제어 장치(700)는 붐 밸브(410)의 개구 면적이 계산되면, 개구 면적에 대응하는 스풀(411)의 변위를 결정한다. 스풀(411)의 변위가 결정되면, 스풀(411)을 변위시키기 위해 필요한 파일럿 압력을 산출한다.
그리고 제어 장치(700)는 산출된 파일럿 압력을 생성하기 위한 전류 지령값을 붐 밸브용 전자 비례 감압 밸브(460)에 전달하고, 붐 밸브용 전자 비례 감압 밸브(460)는 전달받은 전류 지령값에 따라 파일럿 압력을 생성한다.
다음, 붐 밸브용 전자 비례 감압 밸브(460)가 실제 생성한 파일럿 압력을 측정하고, 제어 장치(700)가 산출한 파일럿 압력과 전자 비례 감압 밸브(460)가 실제 생성한 파일럿 압력을 비교한다.
만약 산출된 파일럿 압력과 측정된 파일럿 압력이 상이하다면, 제어 장치(700)는 측정된 파일럿 압력이 산출된 파일럿 압력을 추종하도록 전류 지령값을 보정한다.
이어, 붐 밸브(410)의 스풀(411)은 파일럿 압력에 따라 변위되고, 붐 밸브(410)의 스풀(411)이 변위되면서 붐 실린더(200)의 압력이 변화된다.
이후, 변화된 붐 실린더(200)의 압력을 기준으로 목표 속도를 달성하기 위한 목표 통과 유량을 계산하면서 전술한 제어 과정을 반복하게 된다.
전술한 바와 같은, 건설 기계(101)의 제어 방법에 따르면, 붐(170)의 속도를 사용자의 의도대로 제어할 수 있게 된다. 즉, 제어 과정에서 히스테리시스(hysteresis) 및 응답 지연이 발생하는 것을 억제하고 붐(170)의 제어성을 향상시킬 수 있다.
이상 첨부된 도면을 참조하여 본 발명의 실시예를 설명하였지만, 본 발명이 속하는 기술분야의 당업자는 본 발명이 그 기술적 사상이나 필수적 특징을 변경하지 않고 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다.
그러므로 이상에서 기술한 실시예는 모든 면에서 예시적인 것이며 한정적인 것이 아닌 것으로서 이해되어야 하고, 본 발명의 범위는 상기 상세한 설명은 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 등가개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.
< 부호의 설명 >
100: 엔진 101: 건설 기계
120: 하부 주행체 130: 상부 선회체
135: 상부 프레임 150: 운전실
160: 작업 장치 170: 붐
180: 암 182: 암 실런더
200: 붐 실린더 210: 헤드측
220: 로드측 310: 메인 펌프
370: 파일럿 펌프 380: 회생 모터
410: 붐 밸브 411: 스풀
415: 슬리브 418: 스프링
420: 회생 밸브
460: 붐 밸브용 전자 비례 감압 밸브
470: 회생 밸브용 전자 비례 감압 밸브
480: 어큐뮬레이터 밸브 500: 제어 밸브
610: 제1 붐 유압 라인 620: 제2 붐 유압 라인
630: 재순환 라인 640: 회생 라인
700: 제어 장치 710: 제1 압력 센서
720: 제2 압력 센서 760: 파일럿 압력 센서
770: 조작 장치 800: 어큐뮬레이터
본 발명의 실시예는 붐의 속도를 사용자의 의도대로 제어할 수 있는 건설 기계를 제공할 수 있다.

Claims (10)

  1. 붐을 포함하는 건설 기계에 있어서,
    상기 붐을 승강시키며 헤드측과 로드측으로 구분된 붐 실린더;
    상기 붐 실린더의 헤드측에서 배출되는 작동유의 유량을 제어하며, 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 붐 밸브;
    상기 붐 밸브에 전달할 상기 파일럿 압력을 생성하는 붐 밸브용 전자 비례 감압 밸브;
    상기 붐의 조작을 위한 조작 신호를 발생시키는 조작 장치; 및
    상기 조작 장치의 조작 신호에 대응하는 상기 붐 밸브의 목표 통과 유량과 상기 목표 통과 유량을 통과시키기 위한 상기 붐 밸브의 개구 면적을 계산하고, 상기 개구 면적을 달성하기 위해 상기 붐 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고, 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 붐 밸브용 전자 비례 감압 밸브에 전달하는 제어 장치
    를 포함하는 건설 기계.
  2. 제1항에 있어서,
    상기 붐 밸브용 전자 비례 감압 밸브가 생성한 파일럿 압력을 측정하는 파일럿 압력 센서를 더 포함하며,
    상기 제어 장치는 산출된 상기 파일럿 압력과 상기 파일럿 압력 센서가 측정한 상기 파일럿 압력을 비교하고, 측정된 상기 파일럿 압력이 산출된 상기 파일럿 압력을 추종하도록 상기 붐 밸브용 전자 비례 감압 밸브를 제어하는 것을 특징으로 하는 건설 기계.
  3. 제1항에 있어서,
    상기 붐 실린더에 대한 작동유의 공급을 제어하는 제어 밸브;
    상기 제어 밸브와 상기 붐 실린더의 헤드측을 연결하는 제1 붐 유압 라인;
    상기 제어 밸브와 상기 붐 실린더의 로드측을 연결하는 제2 붐 유압 라인; 및
    상기 제1 붐 유압 라인에서 분기되어 상기 제2 붐 유압 라인과 연결된 재순환 라인
    을 더 포함하며,
    상기 붐 밸브는 상기 재순환 라인 상에 설치된 것을 특징으로 하는 건설 기계.
  4. 제3항에 있어서,
    상기 제1 붐 유압 라인 상에 설치된 제1 압력 센서; 및
    상기 제2 붐 유압 라인 상에 설치된 제2 압력 센서
    를 더 포함하며,
    상기 제어 장치는 상기 제1 압력 센서가 측정한 압력과 상기 제2 압력 센서가 측정한 압력 차이를 고려하여 상기 목표 통과 유량을 통과시키기 위한 상기 붐 밸브의 개구 면적을 계산하는 것을 특징으로 하는 건설 기계.
  5. 제3항에 있어서,
    상기 제어 밸브로 작동유를 공급하는 메인 펌프;
    상기 붐 밸브용 전자 비례 감압 밸브가 상기 파일럿 압력을 생성하기 위해 필요한 작동유를 공급하는 파일럿 펌프; 및
    상기 메인 펌프 및 상기 파일럿 펌프에 회전 동력을 제공하는 엔진
    을 더 포함하는 것을 특징으로 하는 건설 기계.
  6. 제3항에 있어서,
    상기 붐 실린더에서 배출된 작동유로 회생 동작을 수행하여 재생 에너지를 생성하는 회생 모터;
    상기 제1 붐 유압 라인에서 분기되어 상기 회생 모터와 연결된 회생 라인;
    상기 회생 라인 상에 설치되어 상기 붐 실린더의 헤드측으로 배출되는 작동유의 유량을 제어하며, 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 회생 밸브; 및
    상기 회생 밸브에 전달할 상기 파일럿 압력을 생성하는 회생 밸브용 전자 비례 감압 밸브
    를 더 포함하는 것을 특징으로 하는 건설 기계.
  7. 제6항에 있어서,
    상기 제어 장치는 상기 조작 장치의 조작 신호에 대응하는 상기 회생 밸브의 목표 통과 유량과 상기 목표 통과 유량을 통과시키기 위한 상기 회생 밸브의 개구 면적을 계산하고, 상기 개구 면적을 달성하기 위해 상기 회생 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고, 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 회생 밸브용 전자 비례 감압 밸브에 전달하는 것을 특징으로 하는 건설 기계.
  8. 제6항에 있어서,
    상기 회생 라인과 연결되어 작동유를 축적하는 어큐뮬레이터; 및
    상기 어큐뮬레이터로의 작동유 유출입을 제어하는 어큐뮬레이터 밸브
    를 더 포함하는 것을 특징으로 하는 건설 기계.
  9. 제1항에 있어서,
    상기 조작 장치의 조작 신호에 대응하는 상기 붐의 목표 속도를 계산하고 상기 붐의 실제 속도가 상기 붐의 목표 속도를 추종하도록 상기 붐 밸브용 전자 비례 감압 밸브를 제어하는 것을 특징으로 하는 건설 기계.
  10. 붐을 포함하는 건설 기계에 있어서,
    상기 붐을 승강시키며 헤드측과 로드측으로 구분된 붐 실린더;
    상기 붐 실린더의 헤드측에서 배출되는 작동유의 유량을 제어하며, 입력받은 파일럿 압력에 따라 스풀이 변위되면서 개구 면적이 조절되는 붐 밸브;
    상기 붐 밸브에 전달할 상기 파일럿 압력을 생성하는 붐 밸브용 전자 비례 감압 밸브;
    상기 붐의 조작을 위한 조작 신호를 발생시키는 조작 장치; 및
    상기 조작 장치의 조작 신호에 대응하는 상기 붐의 목표 속도를 추종하도록 상기 붐 밸브용 전자 비례 감압 밸브를 제어하고, 상기 붐의 실제 속도와 상기 붐의 목표 속도 간에 오차가 발생하는 경우, 상기 붐의 목표 속도를 추종하기 위해 상기 붐 밸브에 전달되어야 하는 상기 파일럿 압력을 산출하고, 산출된 상기 파일럿 압력을 생성하도록 전류 지령값을 상기 붐 밸브용 전자 비례 감압 밸브에 전달하는 제어 장치
    를 포함하는 건설 기계.
PCT/KR2021/009626 2020-07-28 2021-07-26 건설 기계 WO2022025556A1 (ko)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020200093942A KR20220014177A (ko) 2020-07-28 2020-07-28 건설 기계
KR10-2020-0093942 2020-07-28

Publications (1)

Publication Number Publication Date
WO2022025556A1 true WO2022025556A1 (ko) 2022-02-03

Family

ID=80035838

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2021/009626 WO2022025556A1 (ko) 2020-07-28 2021-07-26 건설 기계

Country Status (2)

Country Link
KR (1) KR20220014177A (ko)
WO (1) WO2022025556A1 (ko)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114809174A (zh) * 2022-04-12 2022-07-29 三一重机有限公司 液压系统控制方法、装置及挖掘机
CN116717511A (zh) * 2023-08-10 2023-09-08 江苏徐工工程机械研究院有限公司 一种动臂独立油路再生控制系统及方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007292316A (ja) * 2007-06-21 2007-11-08 Kobelco Contstruction Machinery Ltd 油圧回路の自己診断装置
US20080072749A1 (en) * 2006-09-27 2008-03-27 Pfaff Joseph L Hydraulic valve assembly with a pressure compensated directional spool valve and a regeneration shunt valve
KR20170066085A (ko) * 2015-12-04 2017-06-14 두산인프라코어 주식회사 건설기계의 유압 시스템 및 유압 제어 방법
KR101760589B1 (ko) * 2013-04-03 2017-07-24 두산인프라코어 주식회사 건설기계의 스풀 변위 가변 제어장치 및 제어방법
KR20190124289A (ko) * 2017-04-10 2019-11-04 두산인프라코어 주식회사 건설 기계의 유압 시스템

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080072749A1 (en) * 2006-09-27 2008-03-27 Pfaff Joseph L Hydraulic valve assembly with a pressure compensated directional spool valve and a regeneration shunt valve
JP2007292316A (ja) * 2007-06-21 2007-11-08 Kobelco Contstruction Machinery Ltd 油圧回路の自己診断装置
KR101760589B1 (ko) * 2013-04-03 2017-07-24 두산인프라코어 주식회사 건설기계의 스풀 변위 가변 제어장치 및 제어방법
KR20170066085A (ko) * 2015-12-04 2017-06-14 두산인프라코어 주식회사 건설기계의 유압 시스템 및 유압 제어 방법
KR20190124289A (ko) * 2017-04-10 2019-11-04 두산인프라코어 주식회사 건설 기계의 유압 시스템

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114809174A (zh) * 2022-04-12 2022-07-29 三一重机有限公司 液压系统控制方法、装置及挖掘机
CN116717511A (zh) * 2023-08-10 2023-09-08 江苏徐工工程机械研究院有限公司 一种动臂独立油路再生控制系统及方法
CN116717511B (zh) * 2023-08-10 2023-12-08 江苏徐工工程机械研究院有限公司 一种动臂独立油路再生控制系统及方法

Also Published As

Publication number Publication date
KR20220014177A (ko) 2022-02-04

Similar Documents

Publication Publication Date Title
WO2022025556A1 (ko) 건설 기계
WO2018190615A1 (ko) 건설 기계의 유압 시스템
WO2018048291A1 (ko) 건설기계의 제어 시스템 및 건설기계의 제어 방법
WO2011078586A2 (ko) 하이브리드 굴삭기 붐 구동시스템 및 그 제어방법
WO2012153880A1 (ko) 하이브리드 액츄에이터의 급정지 장치가 구비되는 하이브리드 굴삭기
WO2017094986A1 (ko) 건설기계의 유압 시스템 및 유압 제어 방법
WO2013051737A1 (ko) 굴삭기를 이용한 평탄화 작업 제어시스템
WO2014112668A1 (ko) 건설기계의 유량 제어장치 및 제어방법
JP4023740B2 (ja) 圧油のエネルギー回収装置
WO2014092355A1 (ko) 조이스틱 컨트롤 기반의 건설장비 자동 제어 시스템 및 방법
WO2015111775A1 (ko) 건설기계용 재생유량 제어장치 및 그 제어방법
WO2012015087A1 (ko) 건설기계용 선회유량 제어시스템 및 그 제어방법
WO2012002589A1 (ko) 건설기계의 유압펌프 제어장치
WO2017094985A1 (ko) 건설기계의 유압 제어 장치 및 유압 제어 방법
WO2015099353A1 (ko) 붐 에너지 회생 제어 회로 및 제어 방법
WO2019074301A1 (ko) 건설기계의 붐 증속 유압 시스템
EP3647500B1 (en) Travel control system for construction machinery and travel control method for construction machinery
WO2020067584A1 (en) Regeneration system and method of energy released from working implement
WO2016043365A1 (ko) 건설기계용 유압회로
WO2022019691A1 (ko) 건설 기계 및 그 제어 방법
WO2013103157A2 (ko) 건설기계용 덤프 구동 제어방법
WO2014163362A1 (ko) 건설기계의 스풀 변위 가변 제어장치 및 제어방법
WO2018044099A1 (ko) 건설기계의 제어 시스템 및 건설기계의 제어 방법
WO2018164465A1 (ko) 건설기계의 제어 시스템 및 건설기계의 제어 방법
WO2019117375A1 (en) Hydraulic machine

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21850489

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 10.07.2023)

122 Ep: pct application non-entry in european phase

Ref document number: 21850489

Country of ref document: EP

Kind code of ref document: A1