WO2022022385A1 - 一种变电构架 - Google Patents
一种变电构架 Download PDFInfo
- Publication number
- WO2022022385A1 WO2022022385A1 PCT/CN2021/107919 CN2021107919W WO2022022385A1 WO 2022022385 A1 WO2022022385 A1 WO 2022022385A1 CN 2021107919 W CN2021107919 W CN 2021107919W WO 2022022385 A1 WO2022022385 A1 WO 2022022385A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- support
- assembly
- beam assembly
- hanging
- wire
- Prior art date
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/05—Suspension arrangements or devices for electric cables or lines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02B—BOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
- H02B5/00—Non-enclosed substations; Substations with enclosed and non-enclosed equipment
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/02—Structures made of specified materials
- E04H12/08—Structures made of specified materials of metal
-
- H—ELECTRICITY
- H01—ELECTRIC ELEMENTS
- H01B—CABLES; CONDUCTORS; INSULATORS; SELECTION OF MATERIALS FOR THEIR CONDUCTIVE, INSULATING OR DIELECTRIC PROPERTIES
- H01B17/00—Insulators or insulating bodies characterised by their form
- H01B17/02—Suspension insulators; Strain insulators
- H01B17/06—Fastening of insulator to support, to conductor, or to adjoining insulator
- H01B17/10—Fastening of insulator to support, to conductor, or to adjoining insulator by intermediate link
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G7/00—Overhead installations of electric lines or cables
- H02G7/20—Spatial arrangements or dispositions of lines or cables on poles, posts or towers
Definitions
- the present application relates to the technical field of substation equipment, and in particular, to a substation structure.
- the substation frame is used to suspend and support conductors to connect switchgear or other electrical equipment.
- the current substation frame is mostly a combination of traditional iron frame and tensile insulator strings, pendant insulator strings and jumper wires, which have defects such as heavy weight, easy corrosion or cracking, etc.
- the frame also occupies a large area. , transportation and installation difficulties, etc. Therefore, a mature substation architecture design solution is urgently needed to solve the above problems.
- the present application provides a substation structure, which can solve the problems that the existing substation structure occupies a large area and is difficult to transport, install and maintain.
- a technical solution adopted in the present application is to provide a substation structure, which includes: a support assembly, at least two are arranged at intervals along a first direction, and at least one support assembly includes a first support part and a first support part connected to each other.
- the second support part; the beam assembly is erected between two adjacent support assemblies; wherein, the first support part is located between the beam assembly and the second support part, and the first support part is made of composite insulating material, and the second support part for metal materials.
- all support assemblies include a first support portion and a second support portion.
- the beam assembly is a composite insulating material.
- a flange assembly is provided between the support assembly and the beam assembly, and the end of the support assembly and the end of the beam assembly are respectively connected to the flange assembly.
- the first wire hanging plate is provided with wire hanging holes for hanging wires.
- it includes: a shielding shell, the cover is provided outside the flange assembly.
- the beam assembly includes at least two beam sections, two adjacent beam sections are connected by flanges, and the substation frame includes: a second hanging plate, the second hanging plate is arranged on the two adjacent beams At the flanges between the segments, the second hanging plate is provided with hanging holes for hanging wires.
- it includes: a plurality of hoops, arranged on the beam assembly at intervals; a third wire hanging plate, arranged on the outer wall of the hooping, and the third wire hanging plate has wire hanging holes for hanging wires.
- the inner wall of the hoop is provided with a number of first slots arranged at intervals and a number of second slots arranged at intervals, the first slots are arranged around the outer wall of the beam assembly, and the second slots are staggered with the first slots set up.
- the wire hanging holes are used to connect with the wire hanging fittings, and at least one wire hanging hole is a waist-shaped hole or an arc-shaped hole, which is used for the effect of the wire hanging fittings on the beam assembly after the wire hanging fittings are rotated.
- the direction of the force remains intersecting the centerline of the beam assembly.
- a wiring post which is provided corresponding to the support component, the wiring post is made of composite insulating material, the wiring post includes a first end provided on the support component and a second end opposite to the first end, the first end The height of the two ends is higher than the height of the beam assembly, the second ends of all wiring posts are electrically connected, the second ends are used to hang the ground wire, and the ground lead wire connects the ground wire and the ground point along at least one wiring post.
- the beam assembly is gradually lifted upward in a direction away from the support assemblies on both sides to form an arch beam assembly.
- the beam assembly includes a middle section and side-phase sections disposed at both ends of the middle section, the side-phase sections are made of composite insulating material, and the middle section is made of metal material.
- three or a multiple of three hooking points for hooking wires are disposed between two adjacent support assemblies.
- the substation frame includes an auxiliary support member, which is disposed between two adjacent support assemblies and supports the beam assembly, and the auxiliary support member includes a first support member and a second support member that are connected to each other.
- the support is located between the beam assembly and the second support, and the first support is made of composite insulating material.
- the beneficial effects of the present application are: different from the prior art, the first support part connected to the beam assembly in the support assembly is set to be a composite insulating material, and since the first support part connected to the beam assembly is a composite insulating material, it has excellent Therefore, the electrical safety distance between the wire and the support assembly can be reduced, thereby effectively reducing the width of the substation frame and the cost of land acquisition.
- the second support part is made of metal material, which can reduce the cost.
- the supporting components of the above-mentioned composite structure are light in weight and are not prone to rust and cracking, which correspondingly solves the problem of difficulty in transportation, installation and maintenance, and reduces transportation and installation costs.
- FIG. 1 is a schematic diagram of the overall structure of an embodiment of a substation structure of the present application
- FIG. 2 is a top-view structural schematic diagram of an embodiment of the substation structure of the present application.
- FIG. 3 is a partial structural schematic diagram of an embodiment of the substation structure of the present application, which is mainly used to display the first hanging board;
- FIG. 4 is a partial structural schematic diagram of an embodiment of the substation structure of the present application, which is mainly used for displaying the second wiring board;
- FIG. 5 is a schematic structural diagram of a hoop and a third hanging plate in another embodiment of the substation structure of the present application.
- FIG. 6 is a schematic diagram of a partial structure of an embodiment of the substation structure of the present application, which is mainly used for showing a voltage equalizing ring;
- FIG. 7 is a schematic diagram of the overall structure of another embodiment of the substation structure of the present application.
- FIG. 8 is a schematic diagram of the overall structure of another embodiment of the substation structure of the present application.
- FIG. 9 is a schematic diagram of the overall structure of a row substation frame in another embodiment of the substation frame of the present application.
- FIG. 10 is a schematic diagram of the overall structure of a row-line substation frame in another embodiment of the substation frame of the present application.
- An embodiment of the present application provides a substation structure 100, as shown in FIG. 1 and FIG. 2, including a support assembly 110 and a beam assembly 120, at least two support assemblies 110 are arranged at intervals along the first direction, and the beam assembly 120 is erected Between two adjacent support assemblies 110 , the support assemblies 110 support the beam assembly 120 .
- the beam assembly 120 is used to hook the wires.
- at least one support assembly 110 includes a first support portion 111 and a second support portion 112 connected to each other, the first support portion 111 is located between the beam assembly 120 and the second support portion 112, and the first support portion 111 is made of composite insulating material , the second support portion 112 is made of metal material.
- the first support portion 111 connected to the beam assembly 120 is made of composite insulating material, it has excellent electrical insulation performance, thereby reducing the electrical safety distance between the wire and the support assembly 110, thereby effectively reducing the width of the substation frame 100 and land acquisition.
- the second support part 112 is made of metal material, which can achieve the effect of reducing the cost.
- the support assembly 110 of the above-mentioned composite structure is light in weight, and is not prone to rust and cracking, which correspondingly solves the problem of difficulty in transportation, installation and maintenance, and reduces transportation, installation and maintenance costs.
- all the support components 110 include a first support portion 111 and a second support portion 112 , and the first support portion 111 is made of composite insulating materials to give full play to its electrical insulation. performance, and minimize the electrical safety distance between the conductor and the support assembly 110, thereby reducing the width of the substation structure and the cost of land acquisition.
- the beam assembly 120 is made of metal material, and a combination of tensile insulator strings, pendant insulator strings or jumpers is required to connect the wires, and the overall height of the substation frame 100 is relatively high.
- the beam assembly 120 is a composite insulating material, which has excellent electrical insulation properties, and can be directly connected to wires without using structures such as overhang insulators.
- the height of the substation frame 100 can be reduced as a whole, and the material consumption of the structures such as the hanging insulators and the supporting components 110 can be reduced; Eliminate the problem of wind deflection and discharge that may exist in the substation frame 100; the substation frame 100 using composite insulating materials is light in weight, not easy to rust and crack, has high transportation and installation efficiency, and can realize maintenance-free throughout the life cycle, reducing the original porcelain Operation and maintenance costs of insulator strings.
- two supporting components 110 are arranged at intervals along the first direction.
- the substation frame 100 is a single-span substation frame 100 .
- At least three, for example, three, four or more supporting components 110 are arranged at intervals along the first direction, and the substation frame 100 is a row substation frame in this case. 100.
- the beam assembly 120 and the first support portion 111 may adopt the structure of a strut insulator, and the strut insulator includes an insulator inside and a rubber shed covering the outside of the insulator.
- the insulator may be an insulating tube or an insulating mandrel.
- the insulating tube can be glass fiber or aramid fiber impregnated epoxy resin through winding and solidified glass steel pipe or a hollow pultruded tube formed by pultrusion;
- the insulating mandrel can be glass fiber or aramid fiber impregnated epoxy resin through A solid mandrel formed by winding and solidification or a pultruded mandrel formed by pultrusion;
- the rubber shed can be made of high-temperature vulcanized silicone rubber or other forms of rubber materials;
- flanges are provided at both ends of the insulator,
- the flanges at both ends of the beam assembly 120 are fixedly connected to the two flange assemblies 130 at both ends of the substation frame 100 (as described below) respectively, and the flanges at both ends of the first support portion 111 are respectively connected to the flange assemblies 130 and the second support portion.
- the fixed connection can be connected by other connecting pieces, or fixed by welding, or a combination of the above connection methods.
- the beam assembly 120 is gradually lifted upward along the direction away from the support assemblies 110 on both sides to form an arched beam assembly 120 , so that the substation frame 100 can use its arched structure to offset the vertical arc. vertical, reducing safety hazards.
- a flange assembly 130 is provided between the support assembly 110 and the beam assembly 120 , and the end of the support assembly 110 and the end of the beam assembly 120 are respectively connected with the flange assembly 130 .
- the flange assembly 130 includes a cylindrical body 133, the axis of the cylindrical body 133 is inclined upward and has an acute angle with the horizontal plane, so as to ensure that the cylindrical body 133 can have a tendency to pre-arch upward after installation.
- an interlocking pre-arch angle can be generated, so that the beam assembly 120 can be gradually lifted upward in a direction away from the support assemblies 110 on both sides to form an arched beam assembly 120 .
- the substation structure 100 further includes a first hanging plate 141 .
- the first hanging plate 141 is arranged at the connection between the beam assembly 120 and the flange assembly 130 .
- the first hanging plate 141 has several Wire hanging hole 144, the wire hanging hole 144 is used for hanging wires. That is, a hooking point is formed at the first hooking plate 141 .
- the end of the flange assembly 130 is provided with a first flange 132
- the end of the beam assembly 120 is provided with a second flange 123
- the flanges 123 are connected by a first fastener (not shown in the figure)
- the first hanging plate 141 is sandwiched between the first flange 132 and the second flange 123 .
- the first hanging plate 141 is provided with two hanging holes 144 and a reserved hole (not shown in the figure), wherein the reserved holes are located directly below the beam assembly 120, and the two hanging holes 144 are symmetrically arranged in the Leave holes on both sides.
- the beam assembly 120 includes at least two beam segments 121 , for example, two, three or more, and the adjacent two beam segments 121 are connected by flanges to change
- the electrical frame 100 includes a second hanging plate 142.
- the second hanging plate 142 is disposed at the flange between two adjacent beam sections 121.
- the second hanging plate 142 defines a plurality of hanging holes 144.
- the hanging holes 144 For hooking up the wire 200. That is, the second hooking plate 142 forms a hooking point.
- the beam assembly 120 includes two beam sections 121 , the adjacent ends of the two beam sections 121 are respectively connected to a third flange 124 , and the second hanging plate 142 is sandwiched between the two between the third flanges 124 .
- the second hanging plate 142 is provided with two hanging holes 144 and one reserved hole, wherein the reserved hole is located directly below the beam assembly 120, and the two hanging holes 144 are symmetrically arranged on both sides of the reserved hole.
- the substation structure 100 is a single-span substation structure 100 .
- the single-span substation frame 100 is provided with two support assemblies 110 spaced along the first direction, and two ends of the beam assembly 120 are respectively connected to the top ends of the two support assemblies 110 through flange assemblies 130 .
- the two first hanging plates 141 provided at both ends of the single-span substation structure 100 and the one second hanging plate 142 provided in the middle of the beam assembly 120 form three hanging points, which are respectively connected to the three-phase A, B, and C phases. wire.
- the beam assembly 120 may not be arranged in sections, that is, the entire beam assembly 120 is a long-strip composite strut insulator, and the long-strip composite strut insulator includes an inner insulator and a rubber shed covering the outside of the insulator. , the insulator and the rubber shed are the same as the above, and will not be repeated here. Among them, as shown in FIG.
- the substation structure 100 includes a plurality of hoops 122 and a third hanging plate 143 , the plurality of hoops 122 are sleeved on the beam assembly 120 at intervals, and the third hanging plate 143 is arranged on the outer wall of the hoops 122 , the third hanging plate 143 has a number of hanging holes 144, and the hanging holes 144 are used for hanging wires. That is, a hooking point is formed at the third hooking plate 143 .
- the hoop 122 can be glued and fixed on the beam assembly 120 .
- the hoop 122 is first glued and fixed on the insulator, and then the whole is covered with a rubber shed, and the rubber shed is covered on the side of the hoop 122 . At both ends, the hoop 122 is sealed with the rubber shed.
- the inner wall of the hoop 122 is provided with a number of first slots 1221 arranged at intervals and a number of second slots 1222 arranged at intervals.
- the first slots 1221 are arranged around the outer wall of the beam assembly 120, and the second slots 1222 are staggered with the first slots 1221.
- the first slot 1221 and the second slot 1222 work together to limit the axial sliding and radial rotation of the hoop 122 in the beam assembly 120, and keep the connection between the hoop 122 and the beam assembly 120 stable;
- the first slot 1221 and the second slot 1222 are alternately arranged.
- the glue material can flow evenly in the first slot 1221 and the second slot 1222, which is beneficial to the bonding between the hoop 122 and the insulator. Glue pack, improve the bonding strength.
- the third hanging plate 143 is integrally formed with the hoop 122 , the first slot 1221 and the second slot 1222 on the inner wall of the hoop 122 are vertically arranged, and the third hanging plate 143 is provided with There are two wire hanging holes 144 and one reserved hole, wherein the reserved hole is located directly below the beam assembly 120 , and the two wire hanging holes 144 are symmetrically arranged on both sides of the reserved hole.
- a plurality of beam sections 121 can also be spliced and combined with the hoop 122.
- the beam assembly 120 includes a long beam section 121 and a short beam section 121, and the long beam section 121 and the short beam section 121.
- the flanges are spliced together, and the flange is provided with a second hanging plate 142, and the long beam section 121 is covered with a hoop 122.
- the specific implementation is selected according to the actual situation, and is not limited here.
- the beam assembly 220 of the substation frame 200 includes a middle section 221 and side phase sections 222 disposed at both ends of the middle section 221, and the side phase sections 222 are composite insulating materials.
- the middle section 221 is made of metal material.
- the side-phase section 222 is a composite insulating material, which has excellent electrical insulating properties, and can be directly connected to wires, thereby reducing structures such as overhang insulators to a certain extent. It can also eliminate the problem of wind bias discharge that may exist in the side-phase conductors.
- the edge phase section 222 made of composite insulating material is light in weight, not easy to rust and crack, has high transportation and installation efficiency, and can achieve maintenance-free throughout the life cycle, reducing the operation and maintenance costs of the original porcelain insulator strings.
- the middle section 221 is made of metal material, which can reduce the material cost.
- the structure and material of the side-phase segment 222 are similar to those of the aforementioned beam assembly 120 using composite insulating materials, and will not be repeated here.
- the edge-phase section 222 of the composite insulating material is light in weight, not easy to rust and crack, has high transportation and installation efficiency, can realize maintenance-free throughout the life cycle, and reduce the operation and maintenance cost of the original porcelain insulator string.
- the middle section 221 is made of metal material, which can reduce the material cost.
- the middle section 221 is still made of metal material, the middle section 221 still needs to be connected to the wire through the suspension insulator.
- the middle section 221 may include at least two metal pipe parts 2211 , and two adjacent metal pipe parts 2211 are connected by flanges. Specifically, the middle section 221 may include two, three or more metal pipe pieces 2211 . In addition, in other embodiments, the middle section 221 may also include only one metal pipe.
- the middle section 221 may also be a metal lattice column.
- the middle section 221 may also be other structures made of other metal materials, which is not limited here.
- the side phase segment 222 may be a beam segment, or as shown in FIG. 4 , the side phase segment 222 includes at least two beam segments 121 spliced together, and the adjacent ends of the two beam segments 121 are respectively A third flange 124 is provided, the two third flanges 124 are connected by fasteners, and a second hanging plate 142 can be sandwiched between the two third flanges 124 .
- the second hanging plate 142 is provided with two hanging holes 144 and one reserved hole, wherein the reserved hole is located directly below the beam assembly 120, and the two hanging holes 144 are symmetrically arranged on both sides of the reserved hole for hanging Connect wire 200. That is, a hooking point is formed at the second hooking plate 142 .
- the side-phase segment 222 when the side-phase segment 222 is relatively long, the side-phase segment 222 may be provided with a hanging point. At this time, the side-phase segment 222 may be a long-strip composite post insulator, wherein the long-strip composite post insulator is the same as the above, No longer.
- the side phase section 222 also includes a plurality of hoops 122 and a third hanging plate 143, a plurality of hoops 122 are sleeved on the edge phase section 222 at intervals, and the third hanging plate 143 is arranged on the hoops On the outer wall of 122, the third hanging plate 143 has a number of hanging holes 144, and the hanging holes 144 are used for hanging wires.
- a hooking point is formed at the third hooking plate 143 .
- the hoop 122 can be glued and fixed on the edge phase segment 222, and the specific glued structure and method are the same as the above, and will not be repeated here.
- the edge phase segment 222 can also be formed by using a plurality of beam segments 121 to be spliced and combined with the hoop 122 .
- the wire hanging holes 144 of the above-mentioned wire hanging plates are used to connect with the wire hanging fittings 210 , and the wires are connected to the wire hanging fittings 210 so that the wire hanging holes 144 can be hung with wires.
- the wire hanging hole 144 on the wire hanging plate for hanging the wire hanging fitting 210 is circular, but considering that the wire hanging fitting 210 may rotate at a certain angle under the action of external force, when the wire hanging fitting 210 rotates , the direction of the force between the wire hanging fittings 210 and each wire hanging plate cannot intersect with the center line of each wire hanging plate, that is, a torsion force is generated on each wire hanging plate, which will lead to loose connection or even reduce the support life.
- the direction of the force between the wire hanging fitting 210 and each wire hanging plate still intersects with the center line of each wire hanging plate
- at least one wire hanging hole on each wire hanging plate is used.
- 144 is set as a waist-shaped hole or an arc-shaped hole. After the wire hanging fitting 210 rotates, it automatically moves in the wire hanging hole 144, so that the direction of the force of the wire hanging fitting 210 on each wire hanging plate is kept in line with the center of each wire hanging plate.
- the lines intersect, so as to keep the connection of each hanging plate stable, enhance the stability of the substation structure 100, and prolong its service life.
- the center line of each hanging plate is coincident with the center line of the beam assembly 120, so the hanging hole 144 is set as a waist-shaped hole or an arc hole, which ensures that the hanging wire fittings 210 are paired with each other.
- the direction of the force of the beam assembly 120 remains to intersect the centerline of the beam assembly 120 .
- the substation structure 100 further includes a shielding shell 131 , and the shielding shell 131 is covered outside the flange assembly 130 to prevent abnormal discharge from occurring.
- a pressure equalizing ring 160 is also provided on the beam assembly 120 on the side of the first hanging plate 141 away from the flange assembly 130 , and the pressure equalizing ring 160 can evenly distribute the high pressure around, It is ensured that there is no potential difference between the various parts of the ring, so as to achieve the effect of voltage equalization and prevent abnormal discharge from occurring.
- At least one side of the second hanging plate 142 is also provided with a voltage equalizing ring 160 , so as to equalize the electric field and prevent discharge from occurring.
- pressure equalizing rings 160 are provided on both sides of the second hanging plate 142, respectively.
- the third hanging plate 143 is also provided with equalizing rings (not shown in the figure), so as to equalize the electric field and prevent the occurrence of discharge.
- pressure equalizing rings are respectively provided on both sides of the third hanging plate 143 .
- each support assembly 110 includes two main support columns 113 , and each main support column 113 includes a first support portion 111 and a second support portion 112 .
- the support portion 111 is a composite insulating material.
- the two main support columns 113 are respectively connected to the flange assembly 130 , the planes where the axes of the two main support columns 113 lie are perpendicular to the first direction, and an included angle of 5°-70° is formed between the two main support columns 113 .
- At least one of the support assemblies 110 further includes an oblique support column 114 , and the oblique support column 114 is connected to the flange assembly 130 and includes a first The support part 111 and the second support part 112, and the first support part 111 are composite insulating materials.
- the oblique support columns 114 are located outside the plane of the two main support columns 113 to limit the deflection of the substation frame 100 along the first direction. It should be noted that the oblique support column 114 is disposed on the side away from the beam assembly 120 .
- the substation frame 100 needs to be grounded, especially the row substation frame 100.
- the beam assembly 120 is made of composite insulating material and can be directly connected to the wire, since the ground wire must maintain a sufficient electrical safety distance from the wire, and lightning protection must be taken into account. The problem, how to hang the ground wire is particularly important.
- the substation structure 100 further includes a wiring post 150 , the wiring post 150 is arranged opposite to the support component 110 , the wiring post 150 is made of composite insulating material, and the wiring post 150 includes a wiring post 150 disposed on the support component 110 .
- the second ends 152 are electrically connected.
- the entire grounding of the substation structure 100 can be achieved by simply connecting the grounding down-conductor 153 to the ground point along one of the wiring posts 150 , and the installation process is convenient.
- the grounding down-conductors 153 may also be connected to the grounding points along a plurality or all of the wiring posts 150 , which is not limited here.
- the electrical connection between the second ends 152 of the wiring posts 150 may be specifically implemented by connecting wires between the second ends 152 of the wiring posts 150 .
- the direction of the wiring column 150 and the axis of the support assembly 110 are on the same line, that is, the wiring column 150 is vertically arranged on the beam assembly 120, and the axis direction of the wiring column 150 and its gravity direction Consistently, the wiring post 150 can be stably disposed on the support assembly 110 , specifically, the wiring post 150 is disposed on the flange assembly 130 between the support assembly 110 and the beam assembly 120 .
- the first end 151 of the wiring post 150 and the top end of the flange assembly 130 may be connected by a flange, or fixed by welding, or a combination of the above connection methods, which is not limited herein.
- the grounding down-conductor 153 can be arranged to fit the wiring post 150 .
- the substation frame 100 when the substation frame 100 is a row substation frame 100, three or multiples of three hooking points for hooking wires, such as three or six, are arranged between two adjacent supporting components 110. Or nine, etc., for the connection of three-phase wires. Three adjacent hanging points are respectively connected with A, B, C three-phase conductors, and sufficient in-phase electrical safety distance must be ensured between A, B, and C three-phase. It should be noted that, in order to ensure the electrical safety distance between adjacent connection points, when the substation frame 100 is a row substation frame 100, the connection between the flange assembly 130 located in the middle position and the beam assemblies 120 on both sides Do not set the hanging point, or only set the hanging point on one side.
- the interphase safe electrical distance of the wires to which the substation frame 100 is connected needs to be satisfied between the two closest wire hanging points on both sides of the support assembly 110 in the middle position.
- the connecting end of the wiring post 150 and the supporting assembly 110 is provided with a post insulator (not shown in the figure) to form a supporting structure
- the post insulator includes a proximal end provided on the supporting assembly 110 and a distal end opposite to the proximal end.
- the distance between the distal end of the pillar insulator and the wire is greater than the first preset value
- the grounding down-conductor 153 is hooked from the second end 152 of the wiring pillar 150 to the distal end of the pillar insulator and then grounded, so as to ensure that the grounding lead is down The safe electrical distance between wire 153 and the wire hooked at the hooking point.
- the substation frame 100 further includes an auxiliary support member 170 .
- the auxiliary support member 170 is disposed between two adjacent support assemblies 110 and is used to support the beam assembly 120 , thereby When the distance between the two support assemblies 110 is certain, the diameter of the beam assembly 120 provided with the auxiliary support 170 can be set below the first diameter, which is smaller than the diameter of the beam assembly 120 without the auxiliary support 170 , reducing the cost of the beam assembly 120 .
- the overall comprehensive cost of the substation structure 100 is reduced, reflecting the advantages of composite insulating materials.
- the auxiliary support 170 includes a first support 171 and a second support 172 , and the first support 171 is located between the beam assembly 120 and the second support 172 , the first support member 171 is a composite insulating material, and the second support member 172 is a metal material.
- first support member 117, the beam assembly 120, and the first support portion 111 may also adopt a pillar insulator structure, and may also be other composite insulating materials, which will not be described in detail.
- auxiliary support 170 there are three hanging points between the auxiliary support 170 and the supporting component 110 adjacent to the first side thereof for hanging wires, and the auxiliary support 170 is opposite to its second side. No wires are hung between the adjacent support assemblies 110, and the second side is opposite to the first side.
- the first support portion 111 of the support assembly 110 connected with the beam assembly 120 has excellent electrical insulation properties, thereby reducing the electrical safety distance between the wire and the support assembly 110 , thereby effectively reducing the width of the substation structure 100 and the cost of land acquisition, and at the same time, the second support portion 112 is made of metal material, which can achieve the effect of reducing the cost.
- the support assembly 110 of the above-mentioned composite structure is light in weight, and is not prone to rust and cracking, correspondingly solving the problem of transportation, installation and maintenance, and reducing transportation and installation costs.
- the beam assembly 120 is made of composite insulating material, which has excellent mechanical properties and electrical insulation properties, and can be directly connected to wires without using overhang insulators.
- the overall height of the substation frame 100 is reduced, and the material consumption of structures such as suspension insulators and the support assembly 110 is reduced; and, since the tensile insulator strings, suspension insulator strings and jumpers are eliminated, the possible wind deflection of the substation frame 100 is eliminated.
- the problem of discharge; the substation frame 100 using composite insulating materials is light in weight, not easy to rust and crack, has low transportation and installation costs, high efficiency, and can achieve maintenance-free throughout the life cycle, reducing the operation and maintenance costs of the original porcelain insulator strings.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Power Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Materials Engineering (AREA)
- Wood Science & Technology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Insulators (AREA)
- Distribution Board (AREA)
Abstract
Description
Claims (14)
- 一种变电构架,其特征在于,包括:支撑组件,沿第一方向间隔设置有至少两个,至少一个所述支撑组件包括相互连接的第一支撑部和第二支撑部;横梁组件,架设于相邻两个所述支撑组件之间;其中,所述第一支撑部位于所述横梁组件和所述第二支撑部之间,且所述第一支撑部为复合绝缘材料,所述第二支撑部为金属材料。
- 根据权利要求1所述的变电构架,其特征在于,所有所述支撑组件均包括所述第一支撑部和所述第二支撑部。
- 根据权利要求2所述的变电构架,其特征在于,所述横梁组件为复合绝缘材料。
- 根据权利要求3所述的变电构架,其特征在于,所述支撑组件和所述横梁组件之间设有法兰组件,所述支撑组件的端部和所述横梁组件的端部分别与所述法兰组件连接,所述变电构架包括:第一挂线板,设置于所述横梁组件与所述法兰组件的连接处,所述第一挂线板开设挂线孔,用于挂接导线。
- 根据权利要求4所述的变电构架,其特征在于,包括:屏蔽壳,罩设于所述法兰组件外部。
- 根据权利要求3所述的变电构架,其特征在于,所述横梁组件包括至少两个横梁段,相邻两个所述横梁段通过法兰连接,所述变电构架包括:第二挂线板,所述第二挂线板设置在相邻两个所述横梁段之间的所述法兰处,所述第二挂线板开设挂线孔,用于挂接导线。
- 根据权利要求3所述的变电构架,其特征在于,包括:若干抱箍,间隔设于所述横梁组件上;第三挂线板,设置于所述抱箍外壁,所述第三挂线板开设挂线孔,用于挂接导线。
- 根据权利要求7所述的变电构架,其特征在于,所述抱箍内壁 开设有若干间隔设置的第一开槽和若干间隔设置的第二开槽,所述第一开槽环绕所述横梁组件外壁设置,所述第二开槽与所述第一开槽交错设置。
- 根据权利要求4-8中任一项所述的变电构架,其特征在于,所述挂线孔用于与挂线金具连接,至少一个所述挂线孔为腰形孔或弧形孔,用于使得所述挂线金具发生旋转之后,所述挂线金具对所述横梁组件的作用力的方向保持与所述横梁组件的中心线相交。
- 根据权利要求3所述的变电构架,其特征在于,包括:布线柱,与所述支撑组件对应设置,所述布线柱为复合绝缘材料,所述布线柱包括设置于所述支撑组件的第一端和与所述第一端相对的第二端,所述第二端的高度高于所述横梁组件的高度,所有所述布线柱的所述第二端之间电连接,所述第二端用于挂接地线,接地引下线沿至少一个所述布线柱连接所述地线与接地点。
- 根据权利要求1所述的变电构架,其特征在于,所述横梁组件沿远离两侧所述支撑组件的方向逐渐向上抬升以形成拱形横梁组件。
- 根据权利要求1所述的变电构架,其特征在于,所述横梁组件包括中间段和设置于所述中间段两端的边相段,所述边相段为复合绝缘材料,所述中间段为金属材料。
- 根据权利要求1所述的变电构架,其特征在于,相邻两个所述支撑组件之间设置有三个或三的倍数个挂接导线的挂线点。
- 根据权利要求1所述的变电构架,其特征在于,所述变电构架包括辅助支撑件,设置于相邻两个所述支撑组件之间,且支撑所述横梁组件,所述辅助支撑件包括相互连接的第一支撑件和第二支撑件,所述第一支撑件位于所述横梁组件和所述第二支撑件之间,所述第一支撑件为复合绝缘材料。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP21793838.0A EP3975352A4 (en) | 2020-07-31 | 2021-07-22 | FRAME FOR SUBSTATION |
BR112021021812A BR112021021812A2 (pt) | 2020-07-31 | 2021-07-22 | Quadro de subestação |
US17/612,278 US12119635B2 (en) | 2020-07-31 | 2021-07-22 | Substation frame |
Applications Claiming Priority (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010761554.9A CN111864544A (zh) | 2020-07-31 | 2020-07-31 | 一种变电构架 |
CN202010763332.0 | 2020-07-31 | ||
CN202010761554.9 | 2020-07-31 | ||
CN202010763324.6A CN111864545A (zh) | 2020-07-31 | 2020-07-31 | 一种变电构架 |
CN202010763332.0A CN111864546A (zh) | 2020-07-31 | 2020-07-31 | 一种变电构架 |
CN202010763324.6 | 2020-07-31 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2022022385A1 true WO2022022385A1 (zh) | 2022-02-03 |
Family
ID=80037124
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2021/107919 WO2022022385A1 (zh) | 2020-07-31 | 2021-07-22 | 一种变电构架 |
Country Status (4)
Country | Link |
---|---|
US (1) | US12119635B2 (zh) |
EP (1) | EP3975352A4 (zh) |
BR (1) | BR112021021812A2 (zh) |
WO (1) | WO2022022385A1 (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115506614A (zh) * | 2022-09-16 | 2022-12-23 | 安徽宏源电力建设投资有限公司 | 变电站带电间隔内作业安全防护装置 |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100917420B1 (ko) * | 2009-04-21 | 2009-09-15 | (주)경성관리단 | 가공전선 지지용 전주의 배전함 |
JP2014193068A (ja) * | 2013-03-28 | 2014-10-06 | Chugoku Electric Power Co Inc:The | 碍子連用形態保持具、並びにこれを用いた耐張碍子の装着方法及び耐張碍子の取り扱い方法 |
CN104481178A (zh) * | 2014-12-15 | 2015-04-01 | 中国能建集团装备有限公司南京技术中心 | 一种复合材料变电站构架 |
CN205646718U (zh) * | 2016-04-29 | 2016-10-12 | 国网山东省电力公司平原县供电公司 | 一种新型变电站支架 |
CN110159051A (zh) * | 2019-04-29 | 2019-08-23 | 国网甘肃省电力公司建设分公司 | 变电构架 |
CN110159052A (zh) * | 2019-04-29 | 2019-08-23 | 国网甘肃省电力公司建设分公司 | 变电构架 |
CN210074720U (zh) * | 2019-04-29 | 2020-02-14 | 国网甘肃省电力公司建设分公司 | 挂线板及绝缘横梁 |
CN111864545A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
CN111864544A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
CN111864543A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
CN111864546A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US842222A (en) * | 1904-11-23 | 1907-01-29 | George A Mead | Catenary suspension for trolley-wires. |
US1783272A (en) * | 1925-05-25 | 1930-12-02 | Ohio Brass Co | Support for transmission lines |
US2036225A (en) * | 1931-08-28 | 1936-04-07 | Ohio Brass Co | Lightning guard for transmission lines |
US2606952A (en) * | 1947-08-20 | 1952-08-12 | Thomas N Cofer | Transmission line support |
DE19654687A1 (de) * | 1996-12-30 | 1998-07-02 | Abb Research Ltd | Mastkopf zum Stützen von Leitern und dergleichen auf Masten für oberirdische Mittel- und Hochspannungsnetzleitungen |
US7057103B1 (en) * | 2004-05-07 | 2006-06-06 | Alan B Peabody | Transmission tower devices for reducing longitudinal shock loads |
CN105239817B (zh) * | 2015-10-31 | 2017-08-29 | 国家电网公司 | 一种复合材料变电构架 |
-
2021
- 2021-07-22 BR BR112021021812A patent/BR112021021812A2/pt unknown
- 2021-07-22 EP EP21793838.0A patent/EP3975352A4/en active Pending
- 2021-07-22 US US17/612,278 patent/US12119635B2/en active Active
- 2021-07-22 WO PCT/CN2021/107919 patent/WO2022022385A1/zh unknown
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100917420B1 (ko) * | 2009-04-21 | 2009-09-15 | (주)경성관리단 | 가공전선 지지용 전주의 배전함 |
JP2014193068A (ja) * | 2013-03-28 | 2014-10-06 | Chugoku Electric Power Co Inc:The | 碍子連用形態保持具、並びにこれを用いた耐張碍子の装着方法及び耐張碍子の取り扱い方法 |
CN104481178A (zh) * | 2014-12-15 | 2015-04-01 | 中国能建集团装备有限公司南京技术中心 | 一种复合材料变电站构架 |
CN205646718U (zh) * | 2016-04-29 | 2016-10-12 | 国网山东省电力公司平原县供电公司 | 一种新型变电站支架 |
CN110159051A (zh) * | 2019-04-29 | 2019-08-23 | 国网甘肃省电力公司建设分公司 | 变电构架 |
CN110159052A (zh) * | 2019-04-29 | 2019-08-23 | 国网甘肃省电力公司建设分公司 | 变电构架 |
CN210074720U (zh) * | 2019-04-29 | 2020-02-14 | 国网甘肃省电力公司建设分公司 | 挂线板及绝缘横梁 |
CN111864545A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
CN111864544A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
CN111864543A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
CN111864546A (zh) * | 2020-07-31 | 2020-10-30 | 江苏神马电力股份有限公司 | 一种变电构架 |
Non-Patent Citations (1)
Title |
---|
See also references of EP3975352A4 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115506614A (zh) * | 2022-09-16 | 2022-12-23 | 安徽宏源电力建设投资有限公司 | 变电站带电间隔内作业安全防护装置 |
CN115506614B (zh) * | 2022-09-16 | 2024-04-09 | 安徽宏源电力建设投资有限公司 | 变电站带电间隔内作业安全防护装置 |
Also Published As
Publication number | Publication date |
---|---|
US12119635B2 (en) | 2024-10-15 |
EP3975352A1 (en) | 2022-03-30 |
US20230081859A1 (en) | 2023-03-16 |
BR112021021812A2 (pt) | 2022-03-03 |
EP3975352A4 (en) | 2022-08-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP2921613B1 (en) | A composite tower comprising across arm structure for power transmission lines | |
WO2022042263A1 (zh) | 一种变电构架 | |
CN104481178B (zh) | 一种复合材料变电站构架 | |
CN103437586B (zh) | 复合转动横担 | |
CN111864545A (zh) | 一种变电构架 | |
US20190267787A1 (en) | Cross Arm And Angle Tower And Tension Tower Comprising The Same | |
WO2022022385A1 (zh) | 一种变电构架 | |
WO2022179103A1 (zh) | 复合横担以及输电塔 | |
CN209212028U (zh) | 一种快速抢修塔 | |
CN202997476U (zh) | 一种水平支撑跳线的复合材料绝缘横担 | |
CN109449867A (zh) | ±1100kv直流线路耐张塔避雷器装置及拆装方法 | |
WO2024192938A1 (zh) | 一种横担组件及输电塔 | |
CN111864543A (zh) | 一种变电构架 | |
CN111864546A (zh) | 一种变电构架 | |
CN111864544A (zh) | 一种变电构架 | |
CN212359263U (zh) | 一种变电构架 | |
CN213043236U (zh) | 一种变电构架 | |
CN212626525U (zh) | 一种变电构架 | |
CN212626526U (zh) | 一种变电构架 | |
CN212849300U (zh) | 一种变电构架 | |
CN212626524U (zh) | 一种变电构架 | |
CN212626527U (zh) | 一种变电构架 | |
CN212836964U (zh) | 变电构架 | |
CN213243115U (zh) | 一种变电构架 | |
CN210074720U (zh) | 挂线板及绝缘横梁 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
ENP | Entry into the national phase |
Ref document number: 2021793838 Country of ref document: EP Effective date: 20211101 |
|
REG | Reference to national code |
Ref country code: BR Ref legal event code: B01A Ref document number: 112021021812 Country of ref document: BR |
|
ENP | Entry into the national phase |
Ref document number: 112021021812 Country of ref document: BR Kind code of ref document: A2 Effective date: 20211029 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |