WO2019196006A1 - 纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法 - Google Patents

纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法 Download PDF

Info

Publication number
WO2019196006A1
WO2019196006A1 PCT/CN2018/082466 CN2018082466W WO2019196006A1 WO 2019196006 A1 WO2019196006 A1 WO 2019196006A1 CN 2018082466 W CN2018082466 W CN 2018082466W WO 2019196006 A1 WO2019196006 A1 WO 2019196006A1
Authority
WO
WIPO (PCT)
Prior art keywords
keel
installation
steel
main
section
Prior art date
Application number
PCT/CN2018/082466
Other languages
English (en)
French (fr)
Inventor
侯志峰
Original Assignee
侯志峰
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 侯志峰 filed Critical 侯志峰
Priority to PCT/CN2018/082466 priority Critical patent/WO2019196006A1/zh
Publication of WO2019196006A1 publication Critical patent/WO2019196006A1/zh

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls

Definitions

  • the invention relates to a construction method for a diamond-shaped aluminum veneer sunshade curtain wall suspended in an exhibition hall.
  • the traditional exhibition hall sunshade curtain wall has a complicated structure, complicated construction, lack of construction and use effects, and needs further improvement.
  • the object of the present invention is to provide a construction method for hanging a diamond-shaped aluminum veneer sunshade curtain wall in an exhibition hall with convenient construction and good construction quality.
  • a method for constructing a diamond-shaped aluminum veneer sunshade curtain wall in a textile enterprise exhibition hall characterized in that before the main keel is installed, according to the accurate calculation result of the building CAD, a plurality of vertical and vertical vertical aluminum squares are arranged at the side of the main keel.
  • the pipe is temporarily supported, the temporary support and the main structure are temporarily fixed.
  • the main and secondary keels arranged obliquely are made of 150mm ⁇ 60mm ⁇ 4mm aluminum alloy rectangular pipe, and the surface is made of fluorocarbon spray.
  • the angle between the main keel and the horizontal plane is clockwise. 24.35°, the angle between the main keel and the secondary keel in the clockwise direction is 45.82°;
  • the beef leg welded with the main structure is made of 120mm ⁇ 120mm ⁇ 12mm ⁇ 18mm hot-dip galvanized steel cross-shaped steel, the surface is fluorocarbon sprayed;
  • the aluminum veneer is 4mm thick , double-sided hem, surface fluorocarbon spray;
  • the specific steps include:
  • the bottom of the curtain wall is 4m above the indoor ground elevation; according to the deepening design drawings, the bottom surface of the curtain wall is the lower surface of the aluminum square tube of the ceiling of the ceiling outside the exhibition hall; before the official construction of the curtain wall keel, the ceiling will be provoked.
  • the keel and the head aluminum square tube are installed in place and leveled to meet the curtain wall design requirements;
  • the 12mm thick steel plate of Q345 material is used as the transfer plate between the beef leg and the main structure.
  • the transfer plate is directly welded to the steel beam of the floor structure.
  • the connection between the beef leg and the transfer plate is in two forms. It is connected with the transfer plate; the other is that the transfer plate is first welded with the 160mm ⁇ 160mm ⁇ 14mm hot-dip galvanized square steel support rod of Q345 material, and the support rod is connected with the beef leg;
  • each layer of steel structure side beam is installed, according to the layout pattern and elevation of the transfer steel plate, according to the steel beam column size control line, the position of the embedded part is divided on the steel beam, and the grid line is I-beam beam wing; use the red pen to mark the embedded welding control line;
  • the first embedded parts of the embedded parts from the right side of the axis are numbered, and the welding is performed one by one from one to several;
  • the welding shrinkage and the machining allowance are reserved during the stakeout and cutting, and the sample is prepared according to the stakeout;
  • the size of the mold is adjusted before the cross-shaped steel is produced, and the size of the welding is consistent with the drawing;
  • the welding of the cross-shaped steel during the welding process is consistent with the mold to prevent the deformation of the steel
  • the first section of the beef leg welding installation is the first section of the beef leg welding installation:
  • the fourth section of the beef leg referred to as the bracket hinge installation:
  • the temporary support rod for temporarily fixing the main keel of the curtain wall is made of 150mm ⁇ 70mm ⁇ 5mm aluminum alloy square tube, the length of which is larger than the height of the curtain wall, and the surface is smooth and straight;
  • the support rod is hoisted and installed by the crane, and is adjusted in position.
  • the temporary support lower mouth is placed on the top of the provocative ceiling head tube, and the outer side is flush with the outer surface of the head tube, and the angle steel is welded and fixed to the main steel beam.
  • the upper mouth is reliably connected with the square tube on the curtain wall, and the vertical deviation of the temporary support rod is controlled within a range of 1 mm;
  • the main keel is tilted from the lower left to the upper right direction, and the inner side of the main and secondary keels are attached to the outer side of the ceiling head pipe, and the lower and the lower keel bottoms are flush with the lower surface of the head pipe;
  • the main keel is lengthened within the long range of the vehicle boom, and the length is not more than 18m;
  • the main keel is socketed by the high-altitude personnel with the same angle main keel that has been installed in the previous position. After the socket length meets the design requirements, the long main keel is placed on the temporary support corner code;
  • the secondary keel is connected with the corner code by screws;
  • the ox bracket is installed, and the bracket can be installed according to the fourth section of the cross cantilever beam.
  • the bracket holds the main keel that has been installed in place and has a reliable connection with the main keel;
  • the diamond-shaped aluminum veneer has a three-dimensional shape, and the back side has a double-folded shape.
  • different types of aluminum veneers are set in the diamond-shaped frame, and the double-folded openings respectively catch the primary and secondary keels, and adjust the single-plate in the frame to make the surface of the plate Flat, the slits are straight and consistent, and are fastened with clips on the back of the board;
  • the invention has convenient construction and good construction quality; the temporary support is used to form the main keel installation control surface of the curtain wall, fully utilizes the accurate calculation result of the CAD, strictly controls the installation error, and effectively avoids the deformation generated when the main keel of the curtain wall is installed, so that the factory processed components A very fit installation is in place. It reproduces the rich imagination of the curtain wall designer and has a good quality perception.
  • a method for constructing a diamond-shaped aluminum veneer sunshade curtain wall in a textile enterprise exhibition hall Before the main keel hoisting installation, according to the accurate calculation result of the building CAD, a plurality of vertical vertical aluminum square pipes are arranged at the side of the main keel for temporary support. Temporary support and temporary suspension of the main structure, when the single main keel is hoisted one by one, first rest on the temporary support, then install the secondary keel, adjust the inclination of the ox leg bracket, fix the main keel on the bracket, and remove the temporary support.
  • the diamond-shaped aluminum veneer is embedded;
  • the main and secondary keels arranged obliquely are made of 150mm ⁇ 60mm ⁇ 4mm aluminum alloy rectangular pipe, and the surface is made of fluorocarbon spray.
  • the angle between the main keel and the horizontal plane is 24.35°.
  • the angle between the keel and the secondary keel in the clockwise direction is 45.82°;
  • the beef leg welded with the main structure is made of 120mm ⁇ 120mm ⁇ 12mm ⁇ 18mm hot-dip galvanized steel cross-shaped steel, and the surface is fluorocarbon sprayed;
  • the aluminum veneer is 4mm thick, double-sided folding Side, surface fluorocarbon coating;
  • the specific steps include:
  • the bottom of the curtain wall is 4m above the indoor ground elevation; according to the deepening design drawings, the bottom surface of the curtain wall is the lower surface of the aluminum square tube of the ceiling of the ceiling outside the exhibition hall; before the official construction of the curtain wall keel, the ceiling will be provoked.
  • the keel and the head aluminum square tube are installed in place and leveled to meet the curtain wall design requirements;
  • the 12mm thick steel plate of Q345 material is used as the transfer plate between the beef leg and the main structure.
  • the transfer plate is directly welded to the steel beam of the floor structure.
  • the connection between the beef leg and the transfer plate is in two forms. It is connected with the transfer plate; the other is that the transfer plate is first welded with the 160mm ⁇ 160mm ⁇ 14mm hot-dip galvanized square steel support rod of Q345 material, and the support rod is connected with the beef leg;
  • each layer of steel structure side beam is installed, according to the layout pattern and elevation of the transfer steel plate, according to the steel beam column size control line, the position of the embedded part is divided on the steel beam, and the grid line is I-beam beam wing; use the red pen to mark the embedded welding control line;
  • the first embedded parts of the embedded parts from the right side of the axis are numbered, and the welding is performed one by one from one to several;
  • the welding shrinkage and the machining allowance are reserved during the stakeout and cutting, and the sample is prepared according to the stakeout;
  • the size of the mold is adjusted before the cross-shaped steel is produced, and the size of the welding is consistent with the drawing;
  • the welding of the cross-shaped steel during the welding process is consistent with the mold to prevent the deformation of the steel
  • the first section of the beef leg welding installation is the first section of the beef leg welding installation:
  • the fourth section of the beef leg referred to as the bracket hinge installation:
  • the temporary support rod for temporarily fixing the main keel of the curtain wall is made of 150mm ⁇ 70mm ⁇ 5mm aluminum alloy square tube, the length of which is larger than the height of the curtain wall, and the surface is smooth and straight;
  • the support rod is hoisted and installed by the crane, and is adjusted in position.
  • the temporary support lower mouth is placed on the top of the provocative ceiling head tube, and the outer side is flush with the outer surface of the head tube, and the angle steel is welded and fixed to the main steel beam.
  • the upper mouth is reliably connected with the square tube on the curtain wall, and the vertical deviation of the temporary support rod is controlled within a range of 1 mm;
  • the main keel is tilted from the lower left to the upper right direction, and the inner side of the main and secondary keels are attached to the outer side of the ceiling head pipe, and the lower and the lower keel bottoms are flush with the lower surface of the head pipe;
  • the main keel is lengthened within the long range of the vehicle boom, and the length is not more than 18m;
  • the main keel is socketed by the high-altitude personnel with the same angle main keel that has been installed in the previous position. After the socket length meets the design requirements, the long main keel is placed on the temporary support corner code;
  • the secondary keel is connected with the corner code by screws;
  • the ox bracket is installed, and the bracket can be installed according to the fourth section of the cross cantilever beam.
  • the bracket holds the main keel that has been installed in place and has a reliable connection with the main keel;
  • the diamond-shaped aluminum veneer has a three-dimensional shape, and the back side has a double-folded shape.
  • different types of aluminum veneers are set in the diamond-shaped frame, and the double-folded openings respectively catch the primary and secondary keels, and adjust the single-plate in the frame to make the surface of the plate Flat, the slits are straight and consistent, and are fastened with clips on the back of the board;

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法,在主龙骨吊装安装前,根据建筑CAD精确计算结果,在主龙骨里侧间隔设置若干根通长竖向垂直铝方管作临时支撑,临时支撑与主体结构临时固定,单根主龙骨逐一吊装安装时,先行搁置在临时支撑上,再安装次龙骨,调整牛腿托架倾角,将主龙骨固定在托架上,拆除临时支撑,最后嵌填菱形框铝单板。施工方便,施工质量好;利用临时支撑构成幕墙主龙骨安装控制面,充分利用CAD的精确计算结果,严格控制安装误差,有效避免了幕墙主龙骨安装时产生的变形,使得工厂加工的构件能够非常贴合的安装到位。

Description

纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法 技术领域
本发明涉及一种展览馆悬空菱形铝单板遮阳幕墙施工方法。
背景技术
传统的展览馆遮阳幕墙的结构复杂,施工麻烦,施工和使用效果存在欠缺,需要进一步改进。
技术问题
本发明的目的在于提供一种施工方便,施工质量好的展览馆悬空菱形铝单板遮阳幕墙施工方法。
技术解决方案
一种纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法,其特征是:在主龙骨吊装安装前,根据建筑CAD精确计算结果,在主龙骨里侧间隔设置若干根通长竖向垂直铝方管作临时支撑,临时支撑与主体结构临时固定,单根主龙骨逐一吊装安装时,先行搁置在临时支撑上,再安装次龙骨,调整牛腿托架倾角,将主龙骨固定在托架上,拆除临时支撑,最后嵌填菱形框铝单板;斜向设置的主、次龙骨均采用150mm×60mm×4mm的铝合金矩形管材,表面做氟碳喷涂,主龙骨与水平面顺时针方向夹角为24.35°,主龙骨与次龙骨顺时针方向夹角为45.82°;与主体结构焊接的牛腿采用120mm×120mm×12mm×18mm热镀锌钢十字型钢,表面氟碳喷涂;铝单板为4mm厚,双面折边,表面氟碳喷涂;
具体步骤包括:
(一)幕墙底标高定位
因幕墙为悬空结构,幕墙底在室内地面标高以上4m;按照深化设计图纸,幕墙底标高面为展览馆外挑檐吊顶封头铝方管下表面;幕墙龙骨正式施工前,将挑檐吊顶主龙骨、封头铝方管安装到位,并进行水平标高校准,以满足幕墙设计要求;
(二)牛腿转接钢板埋件定位
牛腿与主体结构之间采用Q345材质的12mm厚钢板做转接钢板,转接钢板直接焊接在楼层结构的钢梁上,牛腿与转接钢板连接采用二种形式,一种是牛腿直接与转接钢板连接;另一种是转接钢板先与Q345材质的160mm×160mm×14mm热镀锌方钢支撑杆件焊接,支撑杆件再与牛腿连接;
当每一层钢结构边梁安装完毕后,按照转接钢板点位布置图及标高尺寸,根据钢梁柱尺寸控制线,在钢梁上对埋件位置进行分格,将分格线弹在工字钢梁翼板处;用红笔标出预埋件焊接控制线;
根据转接钢板施工图埋件分布的情况,对埋件以轴线右边起第一个埋件进行编号,从1 至若干个进行逐个埋设焊接;
(三)检查转接钢板位置偏差
对已经焊接完毕的转接钢板进行复核检查;测量放线人员从首层与顶层用钢线检查,转接钢板位置偏差上下不大于5mm;
(四)十字悬臂梁,即牛腿的加工
按照施工图放样,放样和下料时预留焊接收缩量和加工余量,根据放样作样板;
钢材矫正:钢材下料前先进行矫正,矫正后的偏差值不超过规范规定的允许偏差值,以保证下料的质量;
热加工与冷拉弯型钢,在十字型钢制作前做好模具的大小调整、焊接的大小与图纸相符;
焊接过程中的十字型钢的焊接与模具相符,以防止型钢变形;
加工完成后整体热镀锌,氟碳喷涂二遍;
(五)全钢十字悬臂梁牛腿安装
工艺流程:
转接焊板安装→牛腿第一段焊接安装→牛腿第二段铰接安装→牛腿第三段铰接安装→牛腿第四段铰接安装→防锈喷漆及面漆处理→单项验收;
第一段牛腿焊接安装:
(1)利用外墙施工吊篮进行安装;
(2)根据线坐标在转接焊板面弹上准确的柱位中轴线、以便下一道工序施工;
(3)第一段牛腿和转接焊板相焊接时,先将第一段牛腿上的热镀锌方钢端头打坡口,将打好坡口的端头和转接焊板相焊接;
(4)焊接时按照在转接焊板面弹上的柱位中轴十字线 进行焊接;焊缝高度12mm;
第二段牛腿铰接安装:                            
(1)在内幕墙铝合金龙骨完工后利用外墙施工吊篮进行安装;
(2)第二段牛腿和第一段牛腿螺栓铰接;
(3)连接螺栓时按照在第一段牛腿连接钢板上弹的板面弹上的中轴十字线进行连接,做到第二段牛腿的水平、垂直、左右均符合图纸设计要求;
第三段牛腿铰接安装:
(1) 第三段牛腿和第二段牛腿利用外墙施工吊篮进行同步安装;
(2) 第三段牛腿和第二段牛腿螺栓铰接;
(3) 连接螺栓时按照在第二段牛腿两块连接钢夹板上弹的控制线进行连接,做到第三段牛腿的水平、垂直、左右均符合图纸设计要求;
第四段牛腿,简称托架的铰接安装:
(1)在菱形铝单板幕墙的铝龙骨安装完成后,利用外墙施工吊篮进行安装;
(2)托架和第三段牛腿螺栓铰接;
(3)连接螺栓时充分保证托架完全贴合托住主龙骨;
(六)临时支撑杆件设立
用于临时固定幕墙主龙骨的临时支撑杆件用150mm×70mm×5mm铝合金方管制作,其长度大于幕墙高度,表面平整,顺直;
每一跨间内设立两根临时支撑;将墙体主轴线投射到底层挑檐吊顶封头管上表面,并做清晰标识;
利用计算机CAD功能,精确计算主龙骨搁置于临时支撑杆件的位置点及高度数值,允许偏差控制在1mm以内,按照主龙骨的倾角,用铝角码在支撑上明确标出主龙骨经过的位置;
用吊车将支撑杆件吊装安装,并调整就位,临时支撑下口搁置在挑檐吊顶封头管上面,其外侧与封头管外面相平齐,中间用角钢与主体钢梁焊接连接固定,上口与幕墙上封方管作可靠连接,保持临时支撑杆件的垂直度偏差控制在1mm范围内;
(七)龙骨安装
第一段龙骨安装:
(1) 按照设计图纸,将主龙骨从左下向右上方向倾斜搁置,斜向主、次龙骨内侧与吊顶封头管外侧贴合,主、次龙骨下口与封头管下表面平齐;
(2) 将最底层主龙骨安装角度及位置详细标识在吊顶封头管外侧面,龙骨安装从左向右进行,主龙骨搁置在临时支撑角码上;
(3) 用水准仪测量、调整主龙骨安装位置及标高,以满足设计要求;
(4) 按照主龙骨上留置的铝角码安装次龙骨,用螺丝将次龙骨与角码连接固定;                 
(5) 安装、调整牛腿托架角度,将主龙骨固定在托架上;
接长龙骨安装:
(1)在地面上按照设计图纸及主龙骨杆件编号顺序,在汽车吊臂长范围内将主龙骨接长,长度不超过18m;
(2)起吊至安装位置,由高空人员将主龙骨与先前已安装就位的同角度主龙骨套接,套接长度满足设计要求后,将接长主龙骨搁置在临时支撑角码上;
次龙骨安装:
按照主龙骨上留置的角码,用螺丝把次龙骨与角码连接固定;
(八)主龙骨就位固定
在主龙骨安装完成后,安装牛腿托架,托架安装可按十字悬臂梁第四段要求实施。托架托住已安装到位的主龙骨,并与主龙骨有可靠连接;
(九) 拆除临时支撑杆件
待主次龙骨安装、就位、固定完成后,拆除临时支撑杆件;
先行拆除杆件上的铝角码,再拆除支撑杆件与结构的临时固定设施,最后用吊车将临时支撑杆件吊离;
(十) 安装成品菱形铝单板立体板块
菱形铝单板为立体形状,其背面为双折口,对照图纸要求,将不同式样的铝单板套装在菱形框内,其双折口分别卡住主次龙骨,调整框内单板,使板表面平整,留置的缝隙顺直、一致,并在板背面用卡子固定;
(十一)调整、清洗
对极少数不平整铝单板进行微调,以不影响整个幕墙立面的平整度、垂直度及幕墙表面的线条顺直;幕墙表面采用清水、柔软的毛巾擦洗。
有益效果
本发明施工方便,施工质量好;利用临时支撑构成幕墙主龙骨安装控制面,充分利用CAD的精确计算结果,严格控制安装误差,有效避免了幕墙主龙骨安装时产生的变形,使得工厂加工的构件能够非常贴合的安装到位。再现了幕墙设计师的丰富想象,质量观感好。
本发明的最佳实施方式
一种纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法,在主龙骨吊装安装前,根据建筑CAD精确计算结果,在主龙骨里侧间隔设置若干根通长竖向垂直铝方管作临时支撑,临时支撑与主体结构临时固定,单根主龙骨逐一吊装安装时,先行搁置在临时支撑上,再安装次龙骨,调整牛腿托架倾角,将主龙骨固定在托架上,拆除临时支撑,最后嵌填菱形框铝单板;斜向设置的主、次龙骨均采用150mm×60mm×4mm的铝合金矩形管材,表面做氟碳喷涂,主龙骨与水平面顺时针方向夹角为24.35°,主龙骨与次龙骨顺时针方向夹角为45.82°;与主体结构焊接的牛腿采用120mm×120mm×12mm×18mm热镀锌钢十字型钢,表面氟碳喷涂;铝单板为4mm厚,双面折边,表面氟碳喷涂;
具体步骤包括:
(一)幕墙底标高定位
因幕墙为悬空结构,幕墙底在室内地面标高以上4m;按照深化设计图纸,幕墙底标高面为展览馆外挑檐吊顶封头铝方管下表面;幕墙龙骨正式施工前,将挑檐吊顶主龙骨、封头铝方管安装到位,并进行水平标高校准,以满足幕墙设计要求;
(二)牛腿转接钢板埋件定位
牛腿与主体结构之间采用Q345材质的12mm厚钢板做转接钢板,转接钢板直接焊接在楼层结构的钢梁上,牛腿与转接钢板连接采用二种形式,一种是牛腿直接与转接钢板连接;另一种是转接钢板先与Q345材质的160mm×160mm×14mm热镀锌方钢支撑杆件焊接,支撑杆件再与牛腿连接;
当每一层钢结构边梁安装完毕后,按照转接钢板点位布置图及标高尺寸,根据钢梁柱尺寸控制线,在钢梁上对埋件位置进行分格,将分格线弹在工字钢梁翼板处;用红笔标出预埋件焊接控制线;
根据转接钢板施工图埋件分布的情况,对埋件以轴线右边起第一个埋件进行编号,从1 至若干个进行逐个埋设焊接;
(三)检查转接钢板位置偏差
对已经焊接完毕的转接钢板进行复核检查;测量放线人员从首层与顶层用钢线检查,转接钢板位置偏差上下不大于5mm;
(四)十字悬臂梁,即牛腿的加工
按照施工图放样,放样和下料时预留焊接收缩量和加工余量,根据放样作样板;
钢材矫正:钢材下料前先进行矫正,矫正后的偏差值不超过规范规定的允许偏差值,以保证下料的质量;
热加工与冷拉弯型钢,在十字型钢制作前做好模具的大小调整、焊接的大小与图纸相符;
焊接过程中的十字型钢的焊接与模具相符,以防止型钢变形;
加工完成后整体热镀锌,氟碳喷涂二遍;
(五)全钢十字悬臂梁牛腿安装
工艺流程:
转接焊板安装→牛腿第一段焊接安装→牛腿第二段铰接安装→牛腿第三段铰接安装→牛腿第四段铰接安装→防锈喷漆及面漆处理→单项验收;
第一段牛腿焊接安装:
(1)利用外墙施工吊篮进行安装;
(2)根据线坐标在转接焊板面弹上准确的柱位中轴线、以便下一道工序施工;
(3)第一段牛腿和转接焊板相焊接时,先将第一段牛腿上的热镀锌方钢端头打坡口,将打好坡口的端头和转接焊板相焊接;
(4)焊接时按照在转接焊板面弹上的柱位中轴十字线 进行焊接;焊缝高度12mm;
第二段牛腿铰接安装:                            
(1)在内幕墙铝合金龙骨完工后利用外墙施工吊篮进行安装;
(2)第二段牛腿和第一段牛腿螺栓铰接;
(3)连接螺栓时按照在第一段牛腿连接钢板上弹的板面弹上的中轴十字线进行连接,做到第二段牛腿的水平、垂直、左右均符合图纸设计要求;
第三段牛腿铰接安装:
(1) 第三段牛腿和第二段牛腿利用外墙施工吊篮进行同步安装;
(2) 第三段牛腿和第二段牛腿螺栓铰接;
(3) 连接螺栓时按照在第二段牛腿两块连接钢夹板上弹的控制线进行连接,做到第三段牛腿的水平、垂直、左右均符合图纸设计要求;
第四段牛腿,简称托架的铰接安装:
(1)在菱形铝单板幕墙的铝龙骨安装完成后,利用外墙施工吊篮进行安装;
(2)托架和第三段牛腿螺栓铰接;
(3)连接螺栓时充分保证托架完全贴合托住主龙骨;
(六)临时支撑杆件设立
用于临时固定幕墙主龙骨的临时支撑杆件用150mm×70mm×5mm铝合金方管制作,其长度大于幕墙高度,表面平整,顺直;
每一跨间内设立两根临时支撑;将墙体主轴线投射到底层挑檐吊顶封头管上表面,并做清晰标识;
利用计算机CAD功能,精确计算主龙骨搁置于临时支撑杆件的位置点及高度数值,允许偏差控制在1mm以内,按照主龙骨的倾角,用铝角码在支撑上明确标出主龙骨经过的位置;
用吊车将支撑杆件吊装安装,并调整就位,临时支撑下口搁置在挑檐吊顶封头管上面,其外侧与封头管外面相平齐,中间用角钢与主体钢梁焊接连接固定,上口与幕墙上封方管作可靠连接,保持临时支撑杆件的垂直度偏差控制在1mm范围内;
(七)龙骨安装
第一段龙骨安装:
(1) 按照设计图纸,将主龙骨从左下向右上方向倾斜搁置,斜向主、次龙骨内侧与吊顶封头管外侧贴合,主、次龙骨下口与封头管下表面平齐;
(2) 将最底层主龙骨安装角度及位置详细标识在吊顶封头管外侧面,龙骨安装从左向右进行,主龙骨搁置在临时支撑角码上;
(3) 用水准仪测量、调整主龙骨安装位置及标高,以满足设计要求;
(4) 按照主龙骨上留置的铝角码安装次龙骨,用螺丝将次龙骨与角码连接固定;                 
(5) 安装、调整牛腿托架角度,将主龙骨固定在托架上;
接长龙骨安装:
(1)在地面上按照设计图纸及主龙骨杆件编号顺序,在汽车吊臂长范围内将主龙骨接长,长度不超过18m;
(2)起吊至安装位置,由高空人员将主龙骨与先前已安装就位的同角度主龙骨套接,套接长度满足设计要求后,将接长主龙骨搁置在临时支撑角码上;
次龙骨安装:
按照主龙骨上留置的角码,用螺丝把次龙骨与角码连接固定;
(八)主龙骨就位固定
在主龙骨安装完成后,安装牛腿托架,托架安装可按十字悬臂梁第四段要求实施。托架托住已安装到位的主龙骨,并与主龙骨有可靠连接;
(九) 拆除临时支撑杆件
待主次龙骨安装、就位、固定完成后,拆除临时支撑杆件;
先行拆除杆件上的铝角码,再拆除支撑杆件与结构的临时固定设施,最后用吊车将临时支撑杆件吊离;
(十) 安装成品菱形铝单板立体板块
菱形铝单板为立体形状,其背面为双折口,对照图纸要求,将不同式样的铝单板套装在菱形框内,其双折口分别卡住主次龙骨,调整框内单板,使板表面平整,留置的缝隙顺直、一致,并在板背面用卡子固定;
(十一)调整、清洗
对极少数不平整铝单板进行微调,以不影响整个幕墙立面的平整度、垂直度及幕墙表面的线条顺直;幕墙表面采用清水、柔软的毛巾擦洗。

Claims (1)

  1. 一种纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法,其特征是:包括下列步骤:在主龙骨吊装安装前,根据建筑CAD精确计算结果,在主龙骨里侧间隔设置若干根通长竖向垂直铝方管作临时支撑,临时支撑与主体结构临时固定,单根主龙骨逐一吊装安装时,先行搁置在临时支撑上,再安装次龙骨,调整牛腿托架倾角,将主龙骨固定在托架上,拆除临时支撑,最后嵌填菱形框铝单板;斜向设置的主、次龙骨均采用150mm×60mm×4mm的铝合金矩形管材,表面做氟碳喷涂,主龙骨与水平面顺时针方向夹角为24.35°,主龙骨与次龙骨顺时针方向夹角为45.82°;与主体结构焊接的牛腿采用120mm×120mm×12mm×18mm热镀锌钢十字型钢,表面氟碳喷涂;铝单板为4mm厚,双面折边,表面氟碳喷涂;
    具体步骤包括:
    (一)幕墙底标高定位
    因幕墙为悬空结构,幕墙底在室内地面标高以上4m;按照深化设计图纸,幕墙底标高面为展览馆外挑檐吊顶封头铝方管下表面;幕墙龙骨正式施工前,将挑檐吊顶主龙骨、封头铝方管安装到位,并进行水平标高校准,以满足幕墙设计要求;
    (二)牛腿转接钢板埋件定位
    牛腿与主体结构之间采用Q345材质的12mm厚钢板做转接钢板,转接钢板直接焊接在楼层结构的钢梁上,牛腿与转接钢板连接采用二种形式,一种是牛腿直接与转接钢板连接;另一种是转接钢板先与Q345材质的160mm×160mm×14mm热镀锌方钢支撑杆件焊接,支撑杆件再与牛腿连接;
    当每一层钢结构边梁安装完毕后,按照转接钢板点位布置图及标高尺寸,根据钢梁柱尺寸控制线,在钢梁上对埋件位置进行分格,将分格线弹在工字钢梁翼板处;用红笔标出预埋件焊接控制线;
    根据转接钢板施工图埋件分布的情况,对埋件以轴线右边起第一个埋件进行编号,从1 至若干个进行逐个埋设焊接;
    (三)检查转接钢板位置偏差
    对已经焊接完毕的转接钢板进行复核检查;测量放线人员从首层与顶层用钢线检查,转接钢板位置偏差上下不大于5mm;
    (四)十字悬臂梁,即牛腿的加工
    按照施工图放样,放样和下料时预留焊接收缩量和加工余量,根据放样作样板;
    钢材矫正:钢材下料前先进行矫正,矫正后的偏差值不超过规范规定的允许偏差值,以保证下料的质量;
    热加工与冷拉弯型钢,在十字型钢制作前做好模具的大小调整、焊接的大小与图纸相符;
    焊接过程中的十字型钢的焊接与模具相符,以防止型钢变形;
    加工完成后整体热镀锌,氟碳喷涂二遍;
    (五)全钢十字悬臂梁牛腿安装
    工艺流程:
    转接焊板安装→牛腿第一段焊接安装→牛腿第二段铰接安装→牛腿第三段铰接安装→牛腿第四段铰接安装→防锈喷漆及面漆处理→单项验收;
    第一段牛腿焊接安装:
    (1)利用外墙施工吊篮进行安装;
    (2)根据线坐标在转接焊板面弹上准确的柱位中轴线、以便下一道工序施工;
    (3)第一段牛腿和转接焊板相焊接时,先将第一段牛腿上的热镀锌方钢端头打坡口,将打好坡口的端头和转接焊板相焊接;
    (4)焊接时按照在转接焊板面弹上的柱位中轴十字线 进行焊接;焊缝高度12mm;
    第二段牛腿铰接安装:                             
    (1)在内幕墙铝合金龙骨完工后利用外墙施工吊篮进行安装;
    (2)第二段牛腿和第一段牛腿螺栓铰接;
    (3)连接螺栓时按照在第一段牛腿连接钢板上弹的板面弹上的中轴十字线进行连接,做到第二段牛腿的水平、垂直、左右均符合图纸设计要求;
    第三段牛腿铰接安装:
    (1) 第三段牛腿和第二段牛腿利用外墙施工吊篮进行同步安装;
    (2) 第三段牛腿和第二段牛腿螺栓铰接;
    (3) 连接螺栓时按照在第二段牛腿两块连接钢夹板上弹的控制线进行连接,做到第三段牛腿的水平、垂直、左右均符合图纸设计要求;
    第四段牛腿,简称托架的铰接安装:
    (1)在菱形铝单板幕墙的铝龙骨安装完成后,利用外墙施工吊篮进行安装;
    (2)托架和第三段牛腿螺栓铰接;
    (3)连接螺栓时充分保证托架完全贴合托住主龙骨;
    (六)临时支撑杆件设立
    用于临时固定幕墙主龙骨的临时支撑杆件用150mm×70mm×5mm铝合金方管制作,其长度大于幕墙高度,表面平整,顺直;
    每一跨间内设立两根临时支撑;将墙体主轴线投射到底层挑檐吊顶封头管上表面,并做清晰标识;
    利用计算机CAD功能,精确计算主龙骨搁置于临时支撑杆件的位置点及高度数值,允许偏差控制在1mm以内,按照主龙骨的倾角,用铝角码在支撑上明确标出主龙骨经过的位置;
    用吊车将支撑杆件吊装安装,并调整就位,临时支撑下口搁置在挑檐吊顶封头管上面,其外侧与封头管外面相平齐,中间用角钢与主体钢梁焊接连接固定,上口与幕墙上封方管作可靠连接,保持临时支撑杆件的垂直度偏差控制在1mm范围内;
    (七)龙骨安装
    第一段龙骨安装:
    (1) 按照设计图纸,将主龙骨从左下向右上方向倾斜搁置,斜向主、次龙骨内侧与吊顶封头管外侧贴合,主、次龙骨下口与封头管下表面平齐;
    (2) 将最底层主龙骨安装角度及位置详细标识在吊顶封头管外侧面,龙骨安装从左向右进行,主龙骨搁置在临时支撑角码上;
    (3) 用水准仪测量、调整主龙骨安装位置及标高,以满足设计要求;
    (4) 按照主龙骨上留置的铝角码安装次龙骨,用螺丝将次龙骨与角码连接固定;                 
    (5) 安装、调整牛腿托架角度,将主龙骨固定在托架上;
    接长龙骨安装:
    (1)在地面上按照设计图纸及主龙骨杆件编号顺序,在汽车吊臂长范围内将主龙骨接长,长度不超过18m;
    (2)起吊至安装位置,由高空人员将主龙骨与先前已安装就位的同角度主龙骨套接,套接长度满足设计要求后,将接长主龙骨搁置在临时支撑角码上;
    次龙骨安装:
    按照主龙骨上留置的角码,用螺丝把次龙骨与角码连接固定;
    (八)主龙骨就位固定
    在主龙骨安装完成后,安装牛腿托架,托架安装可按十字悬臂梁第四段要求实施。托架托住已安装到位的主龙骨,并与主龙骨有可靠连接;
    (九) 拆除临时支撑杆件
    待主次龙骨安装、就位、固定完成后,拆除临时支撑杆件;
    先行拆除杆件上的铝角码,再拆除支撑杆件与结构的临时固定设施,最后用吊车将临时支撑杆件吊离;
    (十) 安装成品菱形铝单板立体板块
    菱形铝单板为立体形状,其背面为双折口,对照图纸要求,将不同式样的铝单板套装在菱形框内,其双折口分别卡住主次龙骨,调整框内单板,使板表面平整,留置的缝隙顺直、一致,并在板背面用卡子固定;
    (十一)调整、清洗
    对极少数不平整铝单板进行微调,以不影响整个幕墙立面的平整度、垂直度及幕墙表面的线条顺直;幕墙表面采用清水、柔软的毛巾擦洗。
PCT/CN2018/082466 2018-04-10 2018-04-10 纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法 WO2019196006A1 (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/CN2018/082466 WO2019196006A1 (zh) 2018-04-10 2018-04-10 纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2018/082466 WO2019196006A1 (zh) 2018-04-10 2018-04-10 纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法

Publications (1)

Publication Number Publication Date
WO2019196006A1 true WO2019196006A1 (zh) 2019-10-17

Family

ID=68162763

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/082466 WO2019196006A1 (zh) 2018-04-10 2018-04-10 纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法

Country Status (1)

Country Link
WO (1) WO2019196006A1 (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1916311A (zh) * 2006-09-01 2007-02-21 蔡贤慈 集成通道幕墙装置的建筑方法及集成通道幕墙装置
CN201254771Y (zh) * 2008-08-26 2009-06-10 北京江河幕墙股份有限公司 大跨度无立柱幕墙系统
CN103982111A (zh) * 2014-05-08 2014-08-13 华汇工程设计集团股份有限公司 一种具有导光遮阳通风功能的被动式窗墙系统
WO2016033770A1 (zh) * 2014-09-04 2016-03-10 冯新林 展览馆悬空菱形铝单板遮阳幕墙施工方法
CN206737218U (zh) * 2017-05-24 2017-12-12 浙江英瑞幕墙装饰有限公司 一种悬空幕墙的固定连接装置
CN206941904U (zh) * 2017-07-17 2018-01-30 宁夏中科天际防雷检测有限公司 一种具有展示功能的玻璃幕墙

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1916311A (zh) * 2006-09-01 2007-02-21 蔡贤慈 集成通道幕墙装置的建筑方法及集成通道幕墙装置
CN201254771Y (zh) * 2008-08-26 2009-06-10 北京江河幕墙股份有限公司 大跨度无立柱幕墙系统
CN103982111A (zh) * 2014-05-08 2014-08-13 华汇工程设计集团股份有限公司 一种具有导光遮阳通风功能的被动式窗墙系统
WO2016033770A1 (zh) * 2014-09-04 2016-03-10 冯新林 展览馆悬空菱形铝单板遮阳幕墙施工方法
CN206737218U (zh) * 2017-05-24 2017-12-12 浙江英瑞幕墙装饰有限公司 一种悬空幕墙的固定连接装置
CN206941904U (zh) * 2017-07-17 2018-01-30 宁夏中科天际防雷检测有限公司 一种具有展示功能的玻璃幕墙

Similar Documents

Publication Publication Date Title
CN104110140B (zh) 一种网架节点定位调节装置及定位调节方法
CN105113671B (zh) 一种大型贝壳状双曲弧形幕墙施工方法
WO2016033770A1 (zh) 展览馆悬空菱形铝单板遮阳幕墙施工方法
CN114086669B (zh) 一种大型空间异形曲面钢网架模块化快速建造方法
CN104264920B (zh) 超高大曲率圆形螺旋清水楼梯的施工方法
CN109267671A (zh) 一种室内墙体系统的装修方法
CN107882220A (zh) 一种l形双翼式双曲铝板幕墙的施工方法
CN105587127B (zh) 借助于激光标线仪实现的外墙预制挂板定位方法
CN103114732A (zh) 铸钢相贯管节点空间定位方法
CN104831938B (zh) 框架式曲面玻璃幕墙的施工方法
CN203403674U (zh) 一种工具式可调节楼梯钢模板
CN116771026A (zh) 一种连续多曲面吸音吊顶及施工方法
CN106437093B (zh) 一种建筑装修暗装瓷砖地脚线结构及其施工工艺
WO2019196006A1 (zh) 纺织企业展览馆悬空菱形铝单板遮阳幕墙施工方法
CN113374221B (zh) 铝模成型剪力墙与砌块抹灰面平整度、垂直度控制方法
CN106760275A (zh) 采用组合支架安装不锈钢旋转楼梯的施工方法
CN102287034A (zh) 异形栏杆及其施工方法
CN107675867A (zh) 用于地面找平的高精度找平装置
CN113107101B (zh) 一种基于bim的折线钢管柱与弧形箱梁斜交连接施工工法
CN213976724U (zh) 一种幕墙单元体轨道吊装结构
CN115637809A (zh) 一种仿古建筑室内高大空间造型铝板吊顶装配式施工方法
CN108625549A (zh) 建筑外檐异形装饰片抗风压构造系统及施工方法
CN113356452A (zh) 一种双曲面弧形吊顶的施工方法
CN106193412A (zh) 一种矿棉板吊顶形式下消防喷淋下挂安装方法
CN111895184A (zh) 一种有限空间内综合管道支吊架

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18914015

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18914015

Country of ref document: EP

Kind code of ref document: A1