WO2019156274A1 - Temporary bridge construction method employing tension of high tension bolt to control girder deflection - Google Patents

Temporary bridge construction method employing tension of high tension bolt to control girder deflection Download PDF

Info

Publication number
WO2019156274A1
WO2019156274A1 PCT/KR2018/002000 KR2018002000W WO2019156274A1 WO 2019156274 A1 WO2019156274 A1 WO 2019156274A1 KR 2018002000 W KR2018002000 W KR 2018002000W WO 2019156274 A1 WO2019156274 A1 WO 2019156274A1
Authority
WO
WIPO (PCT)
Prior art keywords
girder
tension
steel pipe
bolt
main
Prior art date
Application number
PCT/KR2018/002000
Other languages
French (fr)
Korean (ko)
Inventor
조채영
Original Assignee
조채영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 조채영 filed Critical 조채영
Publication of WO2019156274A1 publication Critical patent/WO2019156274A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • E01D2101/32Metal prestressed

Definitions

  • the present invention relates to a construction method of temporary bridges, in particular to control the deflection of the tip according to the introduction of the tension of the high-strength bolt at the joint to shorten the air by assembling the flow beam between the piled steel pipe pile and the girder quickly
  • the present invention relates to a method for constructing a temporary bridge for controlling girder deflection by introducing tension of a high tension bolt.
  • temporary bridges are used for various purposes, such as temporary detours for the construction of new bridges, moving passages of equipment, and temporary groups for construction.
  • the temporary bridge construction method used in Korea is mainly used the temporary bridge construction method using the simple H-beam or externally tensioned H-beam and the long-term prefabricated construction bridge construction method using the truss girder.
  • the main girder is later constructed in the state that the pile is pre-installed on the sea.
  • the installation position of the pile is at sea, it is difficult to locate the pile and the construction cost increases because the barge should be put on the barge when the pile is constructed.
  • a separate worktable for cutting the head and connecting the girder must be installed around the pile, thereby increasing the construction period. Therefore, the method to shorten the construction of the pile in the construction of the temporary bridge is required.
  • Korean Patent Registration No. 10-0939484, a temporary bridge and a construction method thereof are proposed. It comprises the steps of installing a plurality of temporary tents made of steel poles woven in a square or triangle at regular intervals; Fixing the mold consisting of upper, lower flange and abdomen in the longitudinal direction on the upper surface of the temporary vents; The reinforcement formed of a vertical portion welded vertically to the abdomen of the mold and a horizontal portion disposed horizontally at the lower end of the vertical portion and welded to the upper and lower flanges of the mold are integrally formed on both ends and the lower flange of the mold.
  • H beams consisting of upper and lower flanges and an abdomen are arranged, and at the same time, the lower flange of the H beam is cut at regular intervals, and a cross beam is formed at an incision, and is welded at right angles to the lower surface of the incision.
  • the horizontal beam assembly consisting of a reinforcing plate formed with bolt holes to fasten the high-strength bolt is fastened to the upper flange of the mold by the reinforcing plate is coupled to the reinforcement by the high-strength bolt in the direction perpendicular to the mold and fixed to the abdomen of the cross beam to the reinforcement ; It characterized in that the step consisting of fixing the deck plate in a perpendicular direction between the cross beam upper surface of the cross beam assembly.
  • the background art is to install a plurality of continuous cross beam assembly on the upper surface of the mold, and to install a deck plate thereon, to distribute the load to the mold to minimize direct load transfer, to reduce the damage of the deck plate to reduce the traffic Secure driving stability.
  • the background art is a method of installing a mold after installing the temporary vent at regular intervals, and when the temporary vent is installed at sea, it is difficult to accurately position the prop, and shorten the air of the temporary bridge according to the installation of the temporary vent. There is no problem.
  • Another technology that is the background of the present invention is Korean Patent Registration No. 10-1614253, 'cantilever construction method of the temporary bridge' has been proposed. This is to connect the girders that form the upper structure of temporary bridges in the form of cantilever beams so that steel pipe piles can be quickly constructed through the guiding guide beams, and the working platform and railings installed on the girders can be used to secure a safe working path for workers. It is.
  • the background art has a limitation in shortening the air by increasing the number of air due to the construction of the auxiliary pile, the installation of the beam for limiting the girder deflection, the installation of the chain block to prevent sagging of the girder during the construction process.
  • the present invention is to control the deflection of the tip according to the introduction of the high tension bolt tension in the girder to quickly assemble the flow beam between the piled steel pipe pile and the girder to shorten the air by introducing tension of the high tension bolt
  • the purpose is to provide a temporary bridge construction method to control the girder deflection.
  • the first flow beam is assembled in the transverse direction on the upper end of the first steel pipe pile, Arrange and fix a plurality of first girders on the first flow beam on a line designated in the throttle direction, install a deck plate on the upper surface of the first girder, and mount a crane on the deck plate to prepare for lifting of the main girder.
  • the clamp block is disposed on the upper surface of the girder junction side girder lower flange is fastened with a high tension bolt and the lower connecting plate disposed on the lower surface of the girder junction side girder lower flange;
  • the girder junction side girder lower flange is formed larger than the diameter of the high tension bolt and is characterized by having an expansion hole into which the high tension bolt is inserted.
  • the clamp block is made of a steel material characterized in that made of a bridge having a stepped portion between the footrest portion, the footrest portion in contact with the girder lower flange at both ends.
  • the main girder has a pair of H beams parallel to each other in the workshop and a cross beam connected at right intervals at regular intervals along a length direction between the pair of H beams in a state of integral assembly. It is lifted and characterized by installing two girder lines at once.
  • the last one girder line remaining is additionally installed with a single H beam and is connected to a neighboring main girder through a cross beam.
  • the main girder is introduced into the tension by the clamp block fastened with the high-strength bolt at the joint portion to form a lifting angle for preventing girder sagging at the tip 2
  • the flow beam can be quickly installed on the piled steel pipe pile.
  • the second flow beam is quickly moved between the driven steel pipe pile and the main girder by controlling the deflection of the tip of the main girder without the need of installing the auxiliary pile, installing the beam for limiting the girder deflection, and installing the chain block.
  • the air can be significantly shortened.
  • the deck plate is installed while the main girder is connected in the form of cantilever beam, it is possible to secure the head cutting arrangement of the steel pipe pile and the connection of the second flow beam, thereby improving construction safety and using barges at sea.
  • the use of the steering guide has the advantage of easy construction of the steel pipe pile.
  • 1a to 12b is a construction state diagram according to the construction procedure of the construction method of the construction bridge construction to control the girder deflection by the tension of the high-strength bolt according to the present invention.
  • 1A and 1B are a front view and a plan view showing a girder lifting preparation state of a crane.
  • FIGS. 2A and 2B are front and plan views showing the lifting and connecting states of the main girder by the crane;
  • FIG. 3A is an enlarged view of portion 'A' of FIG. 2A and is a diagram illustrating an installation state of the girder joint side clamp block.
  • FIG. 3A is an enlarged view of portion 'A' of FIG. 2A and is a diagram illustrating an installation state of the girder joint side clamp block.
  • FIG. 3B is a cross-sectional view of the high tension bolt side shown in FIG. 3A.
  • FIG. 3C is a perspective view of a part shown in FIG. 3A in a perspective view.
  • 3D is a perspective view of a clamp applied to the present method.
  • 3E is a state diagram in which a web connecting plate is fastened to the web of the girder after the sagging of the main girder is suppressed.
  • 4A and 4B are a front view and a plan view showing a construction state of the deck plate after suppressing the deflection of the main girder.
  • 5A and 5B are a front view and a plan view showing an installation state of a steel pipe pile work bench.
  • 6A and 6B are a front view and a plan view showing a working state in which the steel pipe pile is driven with a vibratory hammer.
  • 7A and 7B are a front view and a plan view showing a working state in which the steel pipe pile is driven with a hydraulic hammer.
  • 8A and 8B are a front view and a plan view showing a working state for arranging the head of the steel pipe pile.
  • 9A and 9B are front and plan views showing the installation state of the second flow beam with the clamp removed;
  • 10a and 10b is a front view and a plan view showing the upper welding after bolted to the girder junction through the upper, lower connecting plate and the web connecting plate.
  • 11A and 11B are a front view and a plan view showing an installation state of a center girder.
  • 12A and 12B are front and plan views showing the installation state of the cross beam between the center girder and the main girder.
  • a 'bridge direction' a direction perpendicular to the bridge direction
  • a 'bridge perpendicular direction' a direction perpendicular direction
  • the first steel pipe pile 11 is double-inserted into the start end or the end side of the temporary bridge, and then the first flow beam 21 is throttled on the upper end of the first steel pipe pile 11. Assemble and install at right angles.
  • the plurality of first girders 31 are fixed on the first flow beam 21 on the line designated in the axial direction, and the deck plate 30 is installed on the upper surface of the first girders 31 before the crane. Mount the 100 to the deck plate 30 to prepare the lifting of the main girder 32 to be constructed.
  • the first steel pipe pile 11 is constructed in two rows and two columns, but may be additionally constructed in the direction perpendicular to the bridge according to the width of the temporary bridge.
  • the first flow beam 21 is assembled to a pile cap 11a whose lower surface is provided on the upper end side of the first steel pipe pile 11.
  • the first flow beam 21 is fastened by fastening means of bolts and nuts, respectively, while its upper surface is in contact with the lower flange of the first girder 31.
  • the temporary bridge has a structure in which the first girder 31 is constructed on the first to fifth lines, but is not limited to the number of such lines.
  • the crane 100 has a sufficient working radius to lift the main girder 32 described later from the work site beyond the entire area of the deck plate 30 disposed on the first girder 31.
  • the opening angle ⁇ has a step of introducing tension such that a constant girder prevention lifting angle ⁇ is generated at the tip of the main girder 32.
  • the lower connecting plate 41 is disposed on the lower surface of the girder joint side girder lower flanges 311 and 321
  • the clamp block 42 is disposed on the upper surface of the lower girder flanges 311 and 321
  • the lower connecting plate 41 is disposed.
  • the clamp block 42 are fastened by the high tension bolt 45 and the lock nut 46.
  • the girder joint side girder lower flanges 311 and 321 have expansion holes 311a and 321a which are formed larger than the diameter of the high tension bolt 45 as shown in FIG. 3B and into which the high tension bolt 45 is inserted, and as shown in FIG. 3D.
  • the 42 is made of steel and consists of the bridge 422 having the step portions 421 and 421 which are in contact with the lower girder flanges 311 and 321 at both ends, and the groove 422a elongated between the foot portions 421 and 421.
  • the groove portion 422a formed in the clamp block 42 is to allow bending of the bridge 422 according to the lifting angle ⁇ for preventing the drooping.
  • the main girder 32 is arranged at right angles at regular intervals along the longitudinal direction between the pair of H beams 32a and 32a and the pair of H beams 32a and 32a which are side by side in the workplace.
  • the connected cross beam 32b is lifted in a state of being assembled and fabricated integrally, and two girder lines are installed at one time.
  • the main girder 32 is installed to the left and right, respectively, and lines 1, 2 and 4 and 5 are respectively installed at once. Therefore, the girder is not yet installed in the third line in the center.
  • the web connecting plate 47 is fastened and connected to both webs 312 and 322 on the girder joint side by using a plurality of web fastening bolts 49 to maintain the lifting angle ⁇ for preventing the drooping.
  • the opening angle ⁇ is maintained together at the girder junction.
  • the deck plate 30 is installed on the upper surface of the main girder 32 as shown in Figs. 4a and 4b. Therefore, in the present embodiment, the deck plate 30 is installed on the 1,2 lines and 4,5 lines. At this time, the deck plate 30 is made only a partial section until the driving position of the steel pipe pile. This is for the installation of steel pipe pile work platform 50 to be described later.
  • the driving guide 52 is assembled in the surveyed position of the main girder 32. At this time, the measurement guide is made so that the driving guide 52 is placed in the set position.
  • the second steel pipe pile 12 is lifted by the crane 100 to receive the guide of the driving guide 52 and to intrude into the ground.
  • This penetration operation is primarily after the second steel pipe pile 12 is driven through the vibration hammer 200, and secondly remove the steel pipe pile work platform 50 as shown in Figure 7a and 7b after the hydraulic hammer 210 Can be achieved by driving until the allowable rebound is measured.
  • the deck plate 30 is installed in the remaining section on the upper surface of the main girder 32.
  • a pile cap 23 is installed on the second flow beam 22, and the second flow beam 22 is lifted by the crane 100 to the lower portion of the main girder 32.
  • the second flow beam 22 is provided.
  • the second flow beam 22 may be assembled to the lower portion of the main girder 32 through bolt fastening means.
  • the web connecting plate 47 is unfastened and the tension is removed so that the opening angle ⁇ and the lifting angle ⁇ for preventing the drooping are eliminated.
  • the tension is removed by removing the clamp block 42. That is, it is possible to disassemble the high tension bolt 45 and the lock nut 46 provided with the clamp block 42, and to loosen the web connecting plate 47 fastened to both webs 312 and 322.
  • the main girder 32 maintains the horizontal state by removing the lifting angle ⁇ for preventing the girder sag.
  • the web connecting plate 47 is again fastened to both webs 312 and 322 on the girder joint side, and the girder joint side flange is connected with the lower connecting plate 41 and the upper connecting plate 43. Fasten (311, 321) with bolts and nuts. Thereafter, the upper part of the joint surface of the main girder 32 and the first girder 31 is welded.
  • tension is introduced by the clamp block 42 in which the main girders 32 are fastened by the high tension bolts 45 at the joints, and a lifting angle ⁇ for preventing girder sagging is formed at the tip.
  • the second flow beam 22 can be quickly installed on the driven second steel pipe pile 12.
  • the second steel pipe pile 12 and the main girder driven by controlling the deflection of the tip of the main girder 32 without the need for the construction of the auxiliary pile, the installation of the beam for limiting the girder deflection, and the installation of the chain block.
  • the second flow beam 22 By allowing the second flow beam 22 to be assembled quickly between 32, the air can be significantly shortened.
  • the deck plate is installed while the main girders are connected in the form of cantilever beams, the head cutting arrangement of the second steel pipe pile 12 and the connection of the second flow beams 22 can be safely performed. Improved, there is no need to drive the pile using the barge at sea, and the use of the driving guide 52 has the advantage of easy construction of the steel pipe pile.
  • the main girder is introduced by the clamp block fastened with a high-tensile bolt at the joint portion to form a lifting angle for preventing girder droop at the tip, thereby rapidly constructing the second flow beam to the piled steel pipe pile, thereby providing air.
  • the deck plate is installed while the main girder is connected in the form of a cantilever beam, and the head cutting and arranging work of the steel pipe pile and the connection of the second flow beam can be safely performed. It is unnecessary to work the pile using the barge at sea, it is a very useful invention that the construction of the steel pipe pile is easy because the use of the navigation guide.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a temporary bridge construction method employing tension of a high tension bolt to control girder deflection, in which tension of a clamp is introduced into a connection portion of a girder to control deflection of a distal end portion thereof, so that a floor beam can be quickly assembled between a driven steel pipe pile and a girder and thus can reduce a construction period.

Description

고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법Temporary bridge construction method to control girder deflection by introducing tension of high tension bolt
본 발명은 가설교량의 시공 방법에 관한 것으로, 특히 거더를 접합부에서 고장력 볼트의 장력 도입에 따른 선단의 처짐을 제어하여 항타된 강관 말뚝과 거더의 사이에 신속히 플로우 빔을 조립할 수 있도록 함으로써 공기를 단축할 수 있도록 한 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법에 관한 것이다.The present invention relates to a construction method of temporary bridges, in particular to control the deflection of the tip according to the introduction of the tension of the high-strength bolt at the joint to shorten the air by assembling the flow beam between the piled steel pipe pile and the girder quickly The present invention relates to a method for constructing a temporary bridge for controlling girder deflection by introducing tension of a high tension bolt.
일반적으로 가설교량은 교량의 신설을 위한 한시적인 우회도로로 활용되거나, 장비의 이동통로, 시공시의 임시 동바리로 활용되는 등 여러 용도로 활용되고 있다. 현재 국내에서 사용되는 가설교량 공법으로는 단순 H형강 또는 외부 긴장된 H형강을 이용한 가설교량 공법, 트러스 거더를 이용한 장지간 조립식 가설교량 공법 등이 주로 사용되고 있다.In general, temporary bridges are used for various purposes, such as temporary detours for the construction of new bridges, moving passages of equipment, and temporary groups for construction. Currently, the temporary bridge construction method used in Korea is mainly used the temporary bridge construction method using the simple H-beam or externally tensioned H-beam and the long-term prefabricated construction bridge construction method using the truss girder.
한편, 해상에 시공되는 가설교량에서는 해상에 말뚝이 선 시공된 상태에서 후에 메인 거더가 시공된다. 이 경우 말뚝의 설치 위치가 해상이 되므로 말뚝이 시공될 시 말뚝의 항타 작업을 바지선을 띄워놓고 해야 하므로 말뚝의 위치 잡기가 어려울 뿐만 아니라 가설 비용이 상승하게 된다. 또한 말뚝의 항타 후에 두부 절단 및 거더와의 연결작업을 위한 별도의 작업대를 말뚝 주변에 설치해야 하므로 시공기간이 길어지게 된다. 따라서 가설교량의 시공에 있어 말뚝의 시공을 단축할 수 있는 방안이 요구된다.On the other hand, in the temporary bridge to be constructed at sea, the main girder is later constructed in the state that the pile is pre-installed on the sea. In this case, since the installation position of the pile is at sea, it is difficult to locate the pile and the construction cost increases because the barge should be put on the barge when the pile is constructed. In addition, after the driving of the pile, a separate worktable for cutting the head and connecting the girder must be installed around the pile, thereby increasing the construction period. Therefore, the method to shorten the construction of the pile in the construction of the temporary bridge is required.
본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-0939484호로서, 가설교량 및 이의 시공방법이 제안되어 있다. 이는 사각형 또는 삼각형으로 짠 강철재 지주로 이루어진 가설벤트를 다수개 일정한 간격으로 설치하는 단계; 상기 가설벤트간의 상면에 상, 하부플랜지 및 복부로 이루어지는 주형을 길이방향으로 고정설치하는 단계; 상기 주형의 복부에 수직으로 용접 배치되는 수직부와, 상기 수직부의 하단에서 수평하게 배치됨과 동시에 주형의 상, 하부플랜지 내측에 용접 설치되는 수평부가 일체로 형성된 보강재를 상기 주형의 양단부 상, 하부플랜지 및 복부에 걸쳐 용접 설치하는 단계; 일정한 간격을 두고 상, 하부플랜지 및 복부로 이루어진 다수 개의 H빔이 배치됨과 동시에 H빔의 하부플랜지가 일정한 간격마다 절개되어 절개부가 형성된 가로보와, 상기 가로보의 절개부 하면에 직각방향으로 용접 설치됨과 동시에 고장력볼트가 관통 체결되도록 볼트공이 형성된 보강판으로 구성되는 가로보 조립체를 상기 주형의 상부플랜지에 주형의 직각방향으로 고장력볼트에 의해서 보강판이 결합됨과 동시에 보강재에 가로보의 복부가 접합되도록 고정 설치하는 단계; 상기 가로보 조립체의 가로보 상면 간에 데크플레이트를 직각방향으로 고정 설치하는 단계로 이루어짐을 특징으로 한다.As a background technology of the present invention, Korean Patent Registration No. 10-0939484, a temporary bridge and a construction method thereof are proposed. It comprises the steps of installing a plurality of temporary tents made of steel poles woven in a square or triangle at regular intervals; Fixing the mold consisting of upper, lower flange and abdomen in the longitudinal direction on the upper surface of the temporary vents; The reinforcement formed of a vertical portion welded vertically to the abdomen of the mold and a horizontal portion disposed horizontally at the lower end of the vertical portion and welded to the upper and lower flanges of the mold are integrally formed on both ends and the lower flange of the mold. And welding install over the abdomen; At the same time, a plurality of H beams consisting of upper and lower flanges and an abdomen are arranged, and at the same time, the lower flange of the H beam is cut at regular intervals, and a cross beam is formed at an incision, and is welded at right angles to the lower surface of the incision. At the same time, the horizontal beam assembly consisting of a reinforcing plate formed with bolt holes to fasten the high-strength bolt is fastened to the upper flange of the mold by the reinforcing plate is coupled to the reinforcement by the high-strength bolt in the direction perpendicular to the mold and fixed to the abdomen of the cross beam to the reinforcement ; It characterized in that the step consisting of fixing the deck plate in a perpendicular direction between the cross beam upper surface of the cross beam assembly.
상기 배경기술은 주형의 상부면에 다수개의 연속화된 가로보 조립체를 설치하고, 그 위에 데크플레이트를 설치함으로써, 주형에 하중을 분산하여 직접적인 하중 전달을 최소화하고, 데크플레이트의 파손을 줄여 차량 통행에 대한 주행의 안정성을 확보한다. The background art is to install a plurality of continuous cross beam assembly on the upper surface of the mold, and to install a deck plate thereon, to distribute the load to the mold to minimize direct load transfer, to reduce the damage of the deck plate to reduce the traffic Secure driving stability.
그러나 상기 배경기술은 가설벤트를 일정 간격으로 설치한 후 주형을 설치하는 방법으로서 가설벤트가 해상에 시공되는 경우 지주의 정확한 위치를 잡기가 어렵고, 가설벤트의 설치에 따른 가설교량의 공기를 단축할 수 없는 문제가 있다.However, the background art is a method of installing a mold after installing the temporary vent at regular intervals, and when the temporary vent is installed at sea, it is difficult to accurately position the prop, and shorten the air of the temporary bridge according to the installation of the temporary vent. There is no problem.
본 발명의 배경이 되는 다른 기술로는 한국 등록특허 등록번호 제10-1614253호로서, '가설교량의 캔틸레버식 시공방법'이 제안되어 있다. 이는 가설교량의 상부 구조물을 이루는 거더를 외팔보 형태로 연결해가면서 항타용 가이드 빔을 통해 강관 말뚝을 신속하게 시공할 수 있고, 거더에 가설된 작업 발판 및 난간으로 작업자의 안전한 작업통로가 확보될 수 있도록 한 것이다. 그러나 상기 배경기술은 시공 과정 중 거더의 처짐을 방지하기 위해 보조말뚝의 시공, 거더 처짐제한용 빔의 설치, 체인블럭의 설치에 따른 공수가 증가되어 공기를 단축하는데 한계를 갖는다.Another technology that is the background of the present invention is Korean Patent Registration No. 10-1614253, 'cantilever construction method of the temporary bridge' has been proposed. This is to connect the girders that form the upper structure of temporary bridges in the form of cantilever beams so that steel pipe piles can be quickly constructed through the guiding guide beams, and the working platform and railings installed on the girders can be used to secure a safe working path for workers. It is. However, the background art has a limitation in shortening the air by increasing the number of air due to the construction of the auxiliary pile, the installation of the beam for limiting the girder deflection, the installation of the chain block to prevent sagging of the girder during the construction process.
본 발명은 거더를 접합부에서 고장력 볼트의 장력 도입에 따른 선단의 처짐을 제어하여 항타된 강관 말뚝과 거더의 사이에 신속히 플로우 빔을 조립할 수 있도록 함으로써 공기를 단축할 수 있도록 한 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법을 제공함에 그 목적이 있다.The present invention is to control the deflection of the tip according to the introduction of the high tension bolt tension in the girder to quickly assemble the flow beam between the piled steel pipe pile and the girder to shorten the air by introducing tension of the high tension bolt The purpose is to provide a temporary bridge construction method to control the girder deflection.
본 발명의 적절한 실시 형태에 따르면, (a) 가설교량의 시작단 또는 종단측에 제1 강관 말뚝을 복열로 관입한 후 제1 강관 말뚝의 상단에 제1 플로우 빔을 횡방향으로 조립 설치하고, 제1 플로우 빔 상에 복수개 이상의 제1 거더를 교축방향으로 지정된 라인상에 배치 고정하고, 제1 거더의 상면에 데크플레이트를 설치한 후 크레인을 데크플레이트에 탑재시켜 추가 설치되는 메인 거더의 인양준비를 하는 단계와; (b) 메인 거더를 크레인으로 인양한 후 교축방향으로 자세를 잡아 선 시공된 제1 거더들의 전단부에 위치시킨 후, 거더 접합부에 클램프 블럭을 고장력 볼트로 체결하여 메인 거더의 선단부에 거더처짐방지용 들림각이 발생되고 동시에 거더접합부에 벌림각이 이루어지도록 메인 거더에 장력을 도입하는 단계와; (c) 거더 접합부측 양쪽 웨브에 웨브 연결판을 볼트로 체결하여 거더처짐방지용 들림각이 유지되도록 하는 단계와; (d) 메인 거더의 상면에 데크플레이트를 설치하는 단계와; (e) 메인 거더의 측량된 위치에 항타용 가이드가 조립되어 있는 강관 말뚝 작업대를 설치한 후, 제2 강관 말뚝을 인양하여 항타용 가이드의 안내를 받아가며 지반으로 관입시키는 단계와; (f) 제2 강관 말뚝의 두부를 정리한 후 메인 거더의 상면에 데크플레이트를 설치하는 단계와; (g) 제2 플로우 빔에 말뚝 캡을 설치하고, 제2 플로우 빔을 인양하여 메인 거더의 하부에 제2 플로우 빔을 설치한 후, 웨브 연결판의 체결을 풀고 클램프 블럭을 해체하여 벌림각과 거더처짐방지용 들림각이 없어지도록 하여 메인 거더에 도입된 장력을 제거하는 단계와; (h) 웨브 연결판을 거더 접합부측 양쪽 웨브에 웨브 체결볼트로 다시 체결하고, 하부연결판과 상부연결판으로 거더 접합부측 거더 하부플랜지를 연결시켜 놓고, 메인 거더의 상면에 데크플레이트를 설치하는 단계와; (i) 가설 교량의 교축방향으로 상기 (b) 단계부터 상기 (h) 단계까지를 수회 반복하여 가교가 시공되는 것을 특징으로 한다.According to a preferred embodiment of the present invention, (a) after the first steel pipe pile is double-inserted into the start end or the end side of the temporary bridge, the first flow beam is assembled in the transverse direction on the upper end of the first steel pipe pile, Arrange and fix a plurality of first girders on the first flow beam on a line designated in the throttle direction, install a deck plate on the upper surface of the first girder, and mount a crane on the deck plate to prepare for lifting of the main girder. And a step; (b) After lifting the main girder with a crane and positioning it in the front end of the first girder, which is erected in the axial direction, the clamp block is fastened to the girder joint with high tension bolts to prevent drooping at the tip of the main girder. Introducing tension to the main girder so that a lifting angle is generated and at the same time an opening angle is made in the girder joint; (c) fastening the web connecting plate to both webs of the girder joint side with bolts to maintain the lifting angle for preventing girder droop; (d) installing a deck plate on an upper surface of the main girder; (e) installing a steel pipe pile work platform on which the steering guide is assembled at the surveyed position of the main girder, and then lifting the second steel pipe pile to guide the ground while receiving the guide of the driving guide; (f) arranging the head of the second steel pipe pile and installing a deck plate on an upper surface of the main girder; (g) Install the pile cap on the second flow beam, lift the second flow beam to install the second flow beam on the lower part of the main girder, then unfasten the web connecting plate and disassemble the clamp block to open the gap angle and the girder. Removing the tension introduced into the main girder such that the lifting angle for preventing deflection is eliminated; (h) Refasten the web connecting plate to both webs of the girder joint side with web fastening bolts, connect the lower flange of the girder joint side to the girder joint side with the lower connecting plate and the upper connecting plate, and install the deck plate on the upper surface of the main girder. Steps; (i) cross-linking is repeated several times from step (b) to step (h) in the axial direction of the temporary bridge.
또한, 상기 (b) 단계에서, 클램프 블럭은 거더 접합부측 거더 하부플랜지의 상면에 배치되어 거더 접합부측 거더 하부플랜지의 하면에 배치된 하부연결판과 고장력 볼트로 체결되되; 거더 접합부측 거더 하부플랜지에는 고장력 볼트의 직경보다 크게 형성되어 고장력 볼트가 삽입되는 확장구멍을 갖는 것을 특징으로 한다.Further, in the step (b), the clamp block is disposed on the upper surface of the girder junction side girder lower flange is fastened with a high tension bolt and the lower connecting plate disposed on the lower surface of the girder junction side girder lower flange; The girder junction side girder lower flange is formed larger than the diameter of the high tension bolt and is characterized by having an expansion hole into which the high tension bolt is inserted.
또한, 상기 클램프 블럭은 강재로 제작되어 양단에 거더 하부플랜지에 접하는 발판부, 발판부의 사이로 길게 개방된 홈부를 갖는 브릿지로 이루어진 것을 특징으로 한다.In addition, the clamp block is made of a steel material characterized in that made of a bridge having a stepped portion between the footrest portion, the footrest portion in contact with the girder lower flange at both ends.
또한, 상기 (b) 단계에서 메인 거더는 작업장에서 나란한 한 쌍의 H 빔과, 한 쌍의 H 빔의 사이에 길이 방향을 따라 일정 간격마다 직각 방향으로 연결된 크로스 빔이 일체로 조립 제작된 상태에서 인양되어 2개의 거더 라인을 한 번에 설치하는 것을 특징으로 한다.In addition, in the step (b), the main girder has a pair of H beams parallel to each other in the workshop and a cross beam connected at right intervals at regular intervals along a length direction between the pair of H beams in a state of integral assembly. It is lifted and characterized by installing two girder lines at once.
또한, 홀수개의 거더 라인을 갖을 경우 남아있는 마지막 1개의 거더 라인에는 단일의 H 빔을 추가적으로 설치한 후 이웃한 메인 거더와 크로스 빔을 통해 연결되는 것을 특징으로 한다.In addition, in the case of having an odd number of girder lines, the last one girder line remaining is additionally installed with a single H beam and is connected to a neighboring main girder through a cross beam.
본 발명의 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법에 따르면, 메인 거더가 접합부에서 고장력 볼트로 체결된 클램프 블럭에 의해 장력이 도입되어 선단에 거더처짐방지용 들림각이 형성되어 제2 플로우 빔을 항타된 강관 말뚝에 신속히 시공할 수 있다.According to the construction method of the construction bridge to control the girder deflection by the tension of the high-strength bolt of the present invention, the main girder is introduced into the tension by the clamp block fastened with the high-strength bolt at the joint portion to form a lifting angle for preventing girder sagging at the tip 2 The flow beam can be quickly installed on the piled steel pipe pile.
즉, 종래와 같이 보조말뚝의 시공, 거더 처짐제한용 빔의 설치, 체인블럭의 설치 조작이 필요없이 메인 거더 선단의 처짐을 제어하여 항타된 강관 말뚝과 메인 거더의 사이에 신속히 제2 플로우 빔을 조립할 수 있도록 함으로써 공기를 현저히 단축할 수 있다.That is, the second flow beam is quickly moved between the driven steel pipe pile and the main girder by controlling the deflection of the tip of the main girder without the need of installing the auxiliary pile, installing the beam for limiting the girder deflection, and installing the chain block. By assembling, the air can be significantly shortened.
물론, 메인 거더를 외팔보 형태로 연결 작업이 이루어지면서 데크플레이트가 설치되므로, 강관 말뚝의 두부 절단 정리 작업 및 제2 플로우 빔의 연결작업을 안전하게 할 수 있어 시공 안전성이 향상되고, 해상에서 바지선을 이용하여 말뚝을 항타하는 작업이 불필요해지며, 항타용 가이드를 이용하므로 강관 말뚝의 시공이 용이한 장점을 갖는다.Of course, since the deck plate is installed while the main girder is connected in the form of cantilever beam, it is possible to secure the head cutting arrangement of the steel pipe pile and the connection of the second flow beam, thereby improving construction safety and using barges at sea. There is no need to drive the pile, the use of the steering guide has the advantage of easy construction of the steel pipe pile.
본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.The following drawings, which are attached in this specification, illustrate the preferred embodiments of the present invention, and together with the detailed description thereof, serve to further understand the technical spirit of the present invention. It should not be construed as limited.
도 1a 내지 도 12b는 본 발명에 따른 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법의 시공순서에 따른 시공상태도이다.1a to 12b is a construction state diagram according to the construction procedure of the construction method of the construction bridge construction to control the girder deflection by the tension of the high-strength bolt according to the present invention.
도 1a 및 도 1b는 크레인의 거더 인양 준비 상태를 나타내는 정면도 및 평면도이다.1A and 1B are a front view and a plan view showing a girder lifting preparation state of a crane.
도 2a 및 도 2b는 크레인에 의한 메인 거더의 인양 및 연결 상태를 나타내는 정면도 및 평면도이다.2A and 2B are front and plan views showing the lifting and connecting states of the main girder by the crane;
도 3a는 도 2a의 'A'부 확대도로서 거더 접합부측 클램프 블록의 설치상태도이다.FIG. 3A is an enlarged view of portion 'A' of FIG. 2A and is a diagram illustrating an installation state of the girder joint side clamp block. FIG.
도 3b는 도 3a에 도시된 고장력 볼트측 단면도이다.3B is a cross-sectional view of the high tension bolt side shown in FIG. 3A.
도 3c는 도 3a에 도시된 부분을 사시도로 나타낸 사시도이다.FIG. 3C is a perspective view of a part shown in FIG. 3A in a perspective view. FIG.
도 3d는 본 공법에 적용되는 클램프의 사시도이다.3D is a perspective view of a clamp applied to the present method.
도 3e는 메인 거더의 처짐 억제 후 거더의 웨브에 웨브 연결판을 체결한 상태도이다.3E is a state diagram in which a web connecting plate is fastened to the web of the girder after the sagging of the main girder is suppressed.
도 4a 및 도 4b는 메인 거더의 처짐 억제 후 데크플레이트의 시공상태를 나타내는 정면도 및 평면도이다.4A and 4B are a front view and a plan view showing a construction state of the deck plate after suppressing the deflection of the main girder.
도 5a 및 도 5b는 강관 말뚝 작업대의 설치 상태를 나타내는 정면도 및 평면도이다.5A and 5B are a front view and a plan view showing an installation state of a steel pipe pile work bench.
도 6a 및 도 6b는 강관 말뚝을 진동 해머로 항타하는 작업상태를 나타내는 정면도 및 평면도이다.6A and 6B are a front view and a plan view showing a working state in which the steel pipe pile is driven with a vibratory hammer.
도 7a 및 도 7b는 강관 말뚝을 유압 해머로 항타하는 작업상태를 나타내는 정면도 및 평면도이다.7A and 7B are a front view and a plan view showing a working state in which the steel pipe pile is driven with a hydraulic hammer.
도 8a 및 도 8b는 강관 말뚝의 두부를 정리하는 작업상태를 나타내는 정면도 및 평면도이다.8A and 8B are a front view and a plan view showing a working state for arranging the head of the steel pipe pile.
도 9a 및 도 9b는 클램프가 제거된 상태에서의 제 2플로우 빔의 설치 상태를 나타내는 정면도 및 평면도이다.9A and 9B are front and plan views showing the installation state of the second flow beam with the clamp removed;
도 10a 및 도 10b는 상,하부연결판 및 웨브 연결판을 통해 거더 접합부에 볼트 체결한 후 상부 용접을 나타낸 정면도 및 평면도이다.10a and 10b is a front view and a plan view showing the upper welding after bolted to the girder junction through the upper, lower connecting plate and the web connecting plate.
도 11a 및 도 11b는 중앙 거더의 설치상태를 나타내는 정면도 및 평면도이다.11A and 11B are a front view and a plan view showing an installation state of a center girder.
도 12a 및 도 12b는 중앙 거더와 메인 거더의 사이에 크로스 빔의 설치상태를 나타내는 정면도 및 평면도이다.12A and 12B are front and plan views showing the installation state of the cross beam between the center girder and the main girder.
아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.In the following the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings, but the embodiments presented are exemplary for a clear understanding of the present invention is not limited thereto.
본 명세서에서 가설 교량의 길이 방향을 '교축방향'이라 하고, 교축방향에 직각이 되는 방향을 '교축 직각방향'이라 칭한다.In the present specification, the longitudinal direction of a temporary bridge is referred to as a 'bridge direction', and a direction perpendicular to the bridge direction is referred to as a 'bridge perpendicular direction'.
<크레인의 메인 거더 인양 준비><Preparation of Crane Main Girder>
먼저, 도 1a 및 도 1b와 같이 가설교량의 시작단 또는 종단측에 제1 강관 말뚝(11)을 복열로 관입한 후 제1 플로우 빔(21)을 제1 강관 말뚝(11)의 상단에 교축 직각방향으로 조립 설치한다.First, as shown in FIGS. 1A and 1B, the first steel pipe pile 11 is double-inserted into the start end or the end side of the temporary bridge, and then the first flow beam 21 is throttled on the upper end of the first steel pipe pile 11. Assemble and install at right angles.
이후, 복수개 이상의 제1 거더(31)를 제1 플로우 빔(21) 상에 교축방향으로 지정된 라인상에 배치 고정하고, 데크플레이트(30)를 제1 거더(31)의 상면에 설치한 후 크레인(100)을 데크플레이트(30)에 탑재시켜 후 시공될 메인 거더(32)의 인양을 준비한다.Thereafter, the plurality of first girders 31 are fixed on the first flow beam 21 on the line designated in the axial direction, and the deck plate 30 is installed on the upper surface of the first girders 31 before the crane. Mount the 100 to the deck plate 30 to prepare the lifting of the main girder 32 to be constructed.
본 실시 예에서 제1 강관 말뚝(11)은 2행 2열로 시공되어 있으나 가설 교량의 폭에 따라 교축 직각방향으로 추가적으로 시공될 수 있다.In this embodiment, the first steel pipe pile 11 is constructed in two rows and two columns, but may be additionally constructed in the direction perpendicular to the bridge according to the width of the temporary bridge.
제1 플로우 빔(21)은 그의 하면이 제1 강관 말뚝(11)의 상단측에 설치된 말뚝 캡(11a)에 조립된다. 또한, 제1 플로우 빔(21)은 그의 상면이 제1 거더(31)의 하부 플랜지에 접한 상태에서 각기 볼트 및 너트의 체결수단으로 체결되어 고정된다.The first flow beam 21 is assembled to a pile cap 11a whose lower surface is provided on the upper end side of the first steel pipe pile 11. In addition, the first flow beam 21 is fastened by fastening means of bolts and nuts, respectively, while its upper surface is in contact with the lower flange of the first girder 31.
본 실시 예에서 가설 교량은 제1 거더(31)가 제1 내지 제 5라인에 시공되어 있는 구조를 가지고 있으나 이러한 라인 개수에 한정되어 시공되는 것은 아니다.In this embodiment, the temporary bridge has a structure in which the first girder 31 is constructed on the first to fifth lines, but is not limited to the number of such lines.
이때 크레인(100)은 제1 거더(31)에 배치된 데크플레이트(30)의 전 영역을 벗어나 작업장으로부터 후술한 메인 거더(32)를 인양할 수 있는 충분한 작업 반경을 갖는다.In this case, the crane 100 has a sufficient working radius to lift the main girder 32 described later from the work site beyond the entire area of the deck plate 30 disposed on the first girder 31.
<메인 거더의 인양 및 처짐제어를 위한 장력 도입><Tension introduction for lifting and deflection control of main girder>
그 다음, 도 2a 내지 도 3b와 같이 메인 거더(32)를 크레인(100)으로 인양한 후 교축방향으로 자세를 잡아 선 시공된 제1 거더(31)들의 전단부에 위치시킨 후, 거더접합부에 벌림각(δ)이 메인 거더(32)의 선단부에 일정한 거더처짐방지용 들림각(θ)이 발생되도록 장력을 도입하는 단계를 갖는다.Next, the main girder 32 is lifted by the crane 100 and positioned in the front end of the first girder 31, which is pre-positioned in the axial direction, as shown in FIGS. 2A to 3B. The opening angle δ has a step of introducing tension such that a constant girder prevention lifting angle θ is generated at the tip of the main girder 32.
여기서, 장력 도입은 거더 접합부측 거더 하부플랜지(311,321)의 하면에 하부연결판(41)을 배치하고, 거더 하부플랜지(311,321)의 상면에 클램프 블럭(42)을 배치하고, 하부연결판(41)과 클램프 블럭(42)을 고장력 볼트(45)와 잠금너트(46)로 체결하여 이루어진다.Here, in the tension introduction, the lower connecting plate 41 is disposed on the lower surface of the girder joint side girder lower flanges 311 and 321, the clamp block 42 is disposed on the upper surface of the lower girder flanges 311 and 321, and the lower connecting plate 41 is disposed. ) And the clamp block 42 are fastened by the high tension bolt 45 and the lock nut 46.
이때 거더 접합부측 거더 하부플랜지(311,321)에는 도 3b와 같이 고장력 볼트(45)의 직경보다 크게 형성되어 고장력 볼트(45)가 삽입되는 확장구멍(311a,321a)을 갖고, 도 3d와 같이 클램프 블럭(42)은 강재로 제작되어 양단에 거더 하부플랜지(311,321)에 접하는 발판부(421,421), 발판부(421과 421)의 사이로 긴 홈부(422a)를 갖는 브릿지(422)로 이루어진다. 여기서 클램프 블럭(42)에 형성된 홈부(422a)는 거더처짐방지용 들림각(θ)에 따른 브릿지(422)의 휨을 허용하기 위함이다.At this time, the girder joint side girder lower flanges 311 and 321 have expansion holes 311a and 321a which are formed larger than the diameter of the high tension bolt 45 as shown in FIG. 3B and into which the high tension bolt 45 is inserted, and as shown in FIG. 3D. The 42 is made of steel and consists of the bridge 422 having the step portions 421 and 421 which are in contact with the lower girder flanges 311 and 321 at both ends, and the groove 422a elongated between the foot portions 421 and 421. The groove portion 422a formed in the clamp block 42 is to allow bending of the bridge 422 according to the lifting angle θ for preventing the drooping.
한편, 본 실시 예에서 메인 거더(32)는 작업장에서 나란한 한 쌍의 H 빔(32a,32a)과, 한 쌍의 H 빔(32a,32a)의 사이에 길이 방향을 따라 일정 간격마다 직각 방향으로 연결된 크로스 빔(32b)이 일체로 조립 제작된 상태에서 인양되어 2개의 거더 라인이 한 번에 설치된다.On the other hand, in the present embodiment, the main girder 32 is arranged at right angles at regular intervals along the longitudinal direction between the pair of H beams 32a and 32a and the pair of H beams 32a and 32a which are side by side in the workplace. The connected cross beam 32b is lifted in a state of being assembled and fabricated integrally, and two girder lines are installed at one time.
본 실시 예에서는 총 5라인에 거더가 설치되는 구조이므로 좌,우로 각기 메인 거더(32)가 설치되어 도 4와 같이 1,2라인과 4,5라인이 각기 한 번에 설치된다. 따라서 중앙의 제 3라인에는 아직 거더가 설치되지 않은 상태가 된다.In this embodiment, since the girder is installed on a total of five lines, the main girder 32 is installed to the left and right, respectively, and lines 1, 2 and 4 and 5 are respectively installed at once. Therefore, the girder is not yet installed in the third line in the center.
< 웨브 연결판 볼트 체결><Web Connecting Plate Bolt Fastening>
그 다음, 도 3e와 같이 거더 접합부측 양쪽 웨브(312,322)에 웨브 연결판(47)을 다수의 웨브 체결볼트(49)로 체결 연결하여 거더처짐방지용 들림각(θ)이 유지되도록 한다. 이때 거더 접합부에 벌림각(δ)이 함께 유지된다.Then, as shown in FIG. 3e, the web connecting plate 47 is fastened and connected to both webs 312 and 322 on the girder joint side by using a plurality of web fastening bolts 49 to maintain the lifting angle θ for preventing the drooping. At this time, the opening angle δ is maintained together at the girder junction.
< 데크플레이트 설치><Deck Plate Installation>
그 다음, 도 4a 및 도 4b와 같이 메인 거더(32)의 상면에 데크플레이트(30)를 설치한다. 따라서 본 실시 예에서는 1,2라인과 4,5라인에 데크플레이트(30)가 설치된다. 이때 데크플레이트(30)는 강관 말뚝의 항타 위치 전까지 부분 구간만 이루어진다. 이는 후술할 강관 말뚝 작업대(50)의 설치를 위한 것이다.Next, the deck plate 30 is installed on the upper surface of the main girder 32 as shown in Figs. 4a and 4b. Therefore, in the present embodiment, the deck plate 30 is installed on the 1,2 lines and 4,5 lines. At this time, the deck plate 30 is made only a partial section until the driving position of the steel pipe pile. This is for the installation of steel pipe pile work platform 50 to be described later.
< 항타용 가이드 설치 및 항타 ><Driving Guide Installation and Driving>
그 다음, 도 5a 및 도 5b와 같이 메인 거더(32)의 측량된 위치에 항타용 가이드(52)가 조립되어 있는 강관 말뚝 작업대(50)를 설치한다. 이때 항타용 가이드(52)가 설정된 위치에 놓이도록 측량이 함께 이루어진다.Next, as shown in Figure 5a and 5b to install the steel pipe pile work platform 50, the driving guide 52 is assembled in the surveyed position of the main girder 32. At this time, the measurement guide is made so that the driving guide 52 is placed in the set position.
이후 도 6a 및 도 6b와 같이 제2 강관 말뚝(12)을 크레인(100)으로 인양하여 항타용 가이드(52)의 안내를 받아가며 지반으로 관입시키는 작업이 이루어진다. 이러한 관입 작업은 진동 해머(200)를 통해 1차적으로 제2 강관 말뚝(12)을 항타 한 후, 2차적으로 도 7a 및 도 7b와 같이 강관 말뚝 작업대(50)를 제거한 후 유압 해머(210)를 사용하여 허용 리바운드가 측정될 때까지 항타하여서 이루어질 수 있다.Thereafter, as shown in FIGS. 6A and 6B, the second steel pipe pile 12 is lifted by the crane 100 to receive the guide of the driving guide 52 and to intrude into the ground. This penetration operation is primarily after the second steel pipe pile 12 is driven through the vibration hammer 200, and secondly remove the steel pipe pile work platform 50 as shown in Figure 7a and 7b after the hydraulic hammer 210 Can be achieved by driving until the allowable rebound is measured.
< 강관 말뚝 두부 정리 및 데크플레트 설치 ><Steel pipe pile tofu cleaning and deck plate installation>
그 다음, 도 8a 및 도 8b와 같이 제2 강관 말뚝(12)의 두부를 절단 정리한 후, 메인 거더(32)의 상면에 나머지 구간에 데크플레이트(30)를 설치한다.Then, after cutting and arranging the head of the second steel pipe pile 12, as shown in Figure 8a and 8b, the deck plate 30 is installed in the remaining section on the upper surface of the main girder 32.
< 플로우 빔 설치 및 메인거더의 처짐 제거><Flow beam installation and sagging of main girder>
그 다음, 도 9a 및 도 9b와 같이 제2 플로우 빔(22)에 말뚝 캡(23)을 설치하고, 제2 플로우 빔(22)을 크레인(100)으로 인양하여 메인 거더(32)의 하부에 제2 플로우 빔(22)을 설치한다. 제2 플로우 빔(22)은 메인 거더(32)의 하부에 볼트 체결수단을 통해 조립될 수 있다.Next, as shown in FIGS. 9A and 9B, a pile cap 23 is installed on the second flow beam 22, and the second flow beam 22 is lifted by the crane 100 to the lower portion of the main girder 32. The second flow beam 22 is provided. The second flow beam 22 may be assembled to the lower portion of the main girder 32 through bolt fastening means.
이후, 도 10a 및 도 10b와 같이 웨브 연결판(47)의 체결을 풀고 벌림각(δ)과 거더처짐방지용 들림각(θ)이 없어지도록 장력을 제거하는 단계를 갖는다. 장력 제거는 클램프 블럭(42)을 제거해 냄으로써 이루어진다. 즉, 클램프 블럭(42)이 설치된 고장력 볼트(45)와 잠금너트(46)를 해체하고, 양쪽 웨브(312,322)에 체결된 웨브 연결판(47)을 풀어서 가능해진다.Thereafter, as shown in FIGS. 10A and 10B, the web connecting plate 47 is unfastened and the tension is removed so that the opening angle δ and the lifting angle θ for preventing the drooping are eliminated. The tension is removed by removing the clamp block 42. That is, it is possible to disassemble the high tension bolt 45 and the lock nut 46 provided with the clamp block 42, and to loosen the web connecting plate 47 fastened to both webs 312 and 322.
따라서 메인 거더(32)는 거더처짐방지용 들림각(θ)이 제거되어 수평 상태를 유지하게 된다.Therefore, the main girder 32 maintains the horizontal state by removing the lifting angle θ for preventing the girder sag.
< 웨브 연결판 볼트 체결 및 데크플레이트 설치><Bolting web connection plate and installing deck plate>
그 다음, 도 10a 및 도 10b와 같이 웨브 연결판(47)을 거더 접합부측 양쪽 웨브(312,322)에 다시 체결하고, 하부연결판(41)과 상부연결판(43)으로 거더 접합부측 거더 하부플랜지(311,321)를 볼트 및 너트로 체결시켜 놓는다. 이후, 메인 거더(32)와 제1 거더(31)의 접합면 상부를 용접시킨다.10A and 10B, the web connecting plate 47 is again fastened to both webs 312 and 322 on the girder joint side, and the girder joint side flange is connected with the lower connecting plate 41 and the upper connecting plate 43. Fasten (311, 321) with bolts and nuts. Thereafter, the upper part of the joint surface of the main girder 32 and the first girder 31 is welded.
그 다음, 도 11a 및 도 11b와 같이 본 실시 예에서 홀수개의 거더 라인이 남아 있으므로, 남아있는 마지막 1개의 거더 라인에는 단일의 H 빔(32a)을 추가적으로 설치한 후 이웃한 메인 거더(32와 32)와 크로스 빔(32b)을 통해 연결될 수 있다. 이후, 메인 거더(32)의 상면에 도 12a 및 도 12b와 같이 데크플레이트(30)를 설치한다.Then, since the odd number of girder lines remain in this embodiment as shown in Figs. 11A and 11B, neighboring main girders 32 and 32 after additionally installing a single H beam 32a in the last one girder line remaining. ) And the cross beam 32b. Thereafter, the deck plate 30 is installed on the upper surface of the main girder 32 as shown in FIGS. 12A and 12B.
<반복 시공><Repeat construction>
그 다음, 가설 교량의 교축방향으로 상술한 메인 거더(32)의 설치부터 데크플레이트 설치 단계를 순차적으로 수회 반복함으로써 가교의 시공이 완료된다.Then, the construction of crosslinking is completed by repeatedly repeating the deck plate installation step several times from the installation of the main girder 32 described above in the axial direction of the temporary bridge.
이와 같이 본 가교의 시공 방법에 따르면, 메인 거더(32)가 접합부에서 고장력 볼트(45)로 체결된 클램프 블럭(42)에 의해 장력이 도입되어 선단에 거더처짐방지용 들림각(θ)이 형성되어 제2 플로우 빔(22)을 항타된 제2 강관 말뚝(12)에 신속히 시공할 수 있다.As described above, according to the construction method of crosslinking, tension is introduced by the clamp block 42 in which the main girders 32 are fastened by the high tension bolts 45 at the joints, and a lifting angle θ for preventing girder sagging is formed at the tip. The second flow beam 22 can be quickly installed on the driven second steel pipe pile 12.
즉, 종래와 같이 보조말뚝의 시공, 거더 처짐제한용 빔의 설치, 체인블럭의 설치 조작이 필요없이 메인 거더(32) 선단의 처짐을 제어하여 항타된 제2 강관 말뚝(12)과 메인 거더(32)의 사이에 신속히 제2 플로우 빔(22)을 조립할 수 있도록 함으로써 공기를 현저히 단축할 수 있다.That is, the second steel pipe pile 12 and the main girder driven by controlling the deflection of the tip of the main girder 32 without the need for the construction of the auxiliary pile, the installation of the beam for limiting the girder deflection, and the installation of the chain block. By allowing the second flow beam 22 to be assembled quickly between 32, the air can be significantly shortened.
물론, 메인 거더를 외팔보 형태로 연결 작업이 이루어지면서 데크플레이트가 설치되므로, 제2 강관 말뚝(12)의 두부 절단 정리 작업 및 제2 플로우 빔(22)의 연결작업을 안전하게 할 수 있어 시공 안전성이 향상되고, 해상에서 바지선을 이용하여 말뚝을 항타하는 작업이 불필요해지며, 항타용 가이드(52)를 이용하므로 강관 말뚝의 시공이 용이한 장점을 갖는다.Of course, since the deck plate is installed while the main girders are connected in the form of cantilever beams, the head cutting arrangement of the second steel pipe pile 12 and the connection of the second flow beams 22 can be safely performed. Improved, there is no need to drive the pile using the barge at sea, and the use of the driving guide 52 has the advantage of easy construction of the steel pipe pile.
지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. So far, the present invention has been described in detail with reference to the presented embodiments, but those skilled in the art may make various modifications and modifications without departing from the technical spirit of the present invention with reference to the presented embodiments. will be. The invention is not limited by the invention as such variations and modifications but only by the claims appended hereto.
본 발명의 가설교량 시공 방법은 메인 거더가 접합부에서 고장력 볼트로 체결된 클램프 블럭에 의해 장력이 도입되어 선단에 거더처짐방지용 들림각이 형성되어 제2 플로우 빔을 항타된 강관 말뚝에 신속히 시공함으로써 공기를 현저히 단축할 수 있으며, 메인 거더를 외팔보 형태로 연결 작업이 이루어지면서 데크플레이트가 설치되므로, 강관 말뚝의 두부 절단 정리 작업 및 제2 플로우 빔의 연결작업을 안전하게 할 수 있어 시공 안전성이 향상되고, 해상에서 바지선을 이용하여 말뚝을 항타하는 작업이 불필요해지며, 항타용 가이드를 이용하므로 강관 말뚝의 시공이 용이한 매우 유용한 발명이다.In the construction method of the temporary bridge construction of the present invention, the main girder is introduced by the clamp block fastened with a high-tensile bolt at the joint portion to form a lifting angle for preventing girder droop at the tip, thereby rapidly constructing the second flow beam to the piled steel pipe pile, thereby providing air. The deck plate is installed while the main girder is connected in the form of a cantilever beam, and the head cutting and arranging work of the steel pipe pile and the connection of the second flow beam can be safely performed. It is unnecessary to work the pile using the barge at sea, it is a very useful invention that the construction of the steel pipe pile is easy because the use of the navigation guide.

Claims (5)

  1. (a) 가설교량의 시작단 또는 종단측에 제1 강관 말뚝(11)을 복열로 관입한 후 제1 강관 말뚝(11)의 상단에 제1 플로우 빔(21)을 횡방향으로 조립 설치하고, 제1 플로우 빔(21) 상에 복수개 이상의 제1 거더(31)를 교축방향으로 지정된 라인상에 배치 고정하고, 제1 거더(31)의 상면에 데크플레이트(30)를 설치한 후 크레인(100)을 데크플레이트(30)에 탑재시켜 추가 설치되는 메인 거더(32)의 인양준비를 하는 단계와;(a) injecting the first steel pipe pile 11 into a double row at the start end or the end side of the temporary bridge, and assembling and installing the first flow beam 21 on the upper end of the first steel pipe pile 11 in the transverse direction, After the plurality of first girders 31 are fixed on the first flow beam 21 on a line designated in the axial direction, the deck plate 30 is installed on the upper surface of the first girders 31, and then the crane 100 is mounted. Mounting the deck plate 30 and preparing the main girder 32 to be additionally installed;
    (b) 메인 거더(32)를 크레인(100)으로 인양한 후 교축방향으로 자세를 잡아 선 시공된 제1 거더(31)들의 전단부에 위치시킨 후, 거더 접합부에 클램프 블럭(42)을 고장력 볼트(45)로 체결하여 메인 거더(32)의 선단부에 거더처짐방지용 들림각(θ)이 발생되고 동시에 거더접합부에 벌림각(δ)이 이루어지도록 메인 거더에 장력을 도입하는 단계와;(b) the main girder 32 is lifted by the crane 100 and then positioned in the front end of the first girder 31 which is constructed in the axial direction, and then clamps the clamp block 42 to the girder joint. Introducing a tension to the main girder such that a lifting angle θ for preventing the drooping of the girder is generated at the distal end of the main girder 32 while the bolt 45 is fastened;
    (c) 거더 접합부측 양쪽 웨브(312,322)에 웨브 연결판(47)을 볼트(49)로 체결 연결하여 거더처짐방지용 들림각(θ)이 유지되도록 하는 단계와;(c) fastening and connecting the web connecting plate 47 with bolts 49 to both webs 312 and 322 on the girder joint side to maintain the lifting angle?
    (d) 메인 거더(32)의 상면에 데크플레이트(30)를 설치하는 단계와;(d) installing the deck plate 30 on the upper surface of the main girder 32;
    (e) 메인 거더(32)의 측량된 위치에 항타용 가이드(52)가 조립되어 있는 강관 말뚝 작업대(50)를 설치한 후, 제2 강관 말뚝(12)을 인양하여 항타용 가이드(52)의 안내를 받아가며 지반으로 관입시키는 단계와;(e) After installing the steel pipe pile work platform 50 in which the driving guide 52 is assembled at the surveyed position of the main girder 32, the second steel pipe pile 12 is lifted and the driving guide 52 is driven. Intruding into the ground under the guidance of;
    (f) 제2 강관 말뚝(12)의 두부를 정리한 후 메인 거더(32)의 상면에 데크플레이트(30)를 설치하는 단계와;(f) arranging the head of the second steel pipe pile 12 and installing the deck plate 30 on the upper surface of the main girder 32;
    (g) 제2 플로우 빔(22)에 말뚝 캡(23)을 설치하고, 제2 플로우 빔(22)을 인양하여 메인 거더(32)의 하부에 제2 플로우 빔(22)을 설치한 후, 웨브 연결판(47)의 체결을 풀고 클램프 블럭(42)을 해체하여 벌림각(δ)과 거더처짐방지용 들림각(θ)이 없어지도록 하여 메인 거더(32)에 도입된 장력을 제거하는 단계와;(g) After installing the pile cap 23 in the second flow beam 22, lifting the second flow beam 22 and installing the second flow beam 22 in the lower part of the main girder 32, Removing the tension introduced into the main girder 32 by loosening the web connecting plate 47 and dismantling the clamp block 42 so that the opening angle δ and the lifting angle θ for preventing the drooping are removed. ;
    (h) 웨브 연결판(47)을 거더 접합부측 양쪽 웨브(312,322)에 웨브 체결볼트(49)로 다시 체결하고, 하부연결판(41)과 상부연결판(43)으로 거더 접합부측 거더 하부플랜지(311,321)를 연결시켜 놓고, 메인 거더(32)의 상면에 데크플레이트(30)를 설치하는 단계와;(h) Reattach the web connecting plate 47 to both webs 312 and 322 of the girder joint side with web fastening bolts 49, and to the girder joint side girder bottom flange with the lower connecting plate 41 and the upper connecting plate 43. Connecting the 311 and 321 and installing the deck plate 30 on the upper surface of the main girder 32;
    (i) 가설 교량의 교축방향으로 상기 (b) 단계부터 상기 (h) 단계까지를 수회 반복하여 가교가 시공되는 것을 특징으로 하는 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법.(i) The construction method of the temporary bridge construction to control the girder deflection by the tension introduction of the high-strength bolt, characterized in that the bridge is constructed by repeating the steps (b) to (h) several times in the axial direction of the temporary bridge.
  2. 제 1항에 있어서,The method of claim 1,
    상기 (b) 단계에서, 클램프 블럭(42)은 거더 접합부측 거더 하부플랜지(311,321)의 상면에 배치되어 거더 접합부측 거더 하부플랜지(311,321)의 하면에 배치된 하부연결판(41)과 고장력 볼트(45)로 체결되되; 거더 접합부측 거더 하부플랜지(311,321)에는 고장력 볼트(45)의 직경보다 크게 형성되어 고장력 볼트(45)가 삽입되는 확장구멍(311a,321a)을 갖는 것을 특징으로 하는 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법.In the step (b), the clamp block 42 is disposed on the upper surface of the girder junction side girder lower flanges 311 and 321, and the lower connection plate 41 and the high tension bolt disposed on the lower surface of the girder junction side girder lower flanges 311 and 321. Fastened to 45; Girder sagging due to tension introduction of the high tension bolt, which is formed in the girder joint side girder lower flanges 311 and 321 to be larger than the diameter of the high tension bolt 45 and has expansion holes 311 a and 321 a into which the high tension bolt 45 is inserted. Construction method of the construction bridge to control the.
  3. 제 2항에 있어서,The method of claim 2,
    상기 클램프 블럭(42)은 강재로 제작되어 양단에 거더 하부플랜지(311,321)에 접하는 발판부(421,421), 발판부(421과 421)의 사이로 길게 개방된 홈부(422a)를 갖는 브릿지(422)로 이루어진 것을 특징으로 하는 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법.The clamp block 42 is made of a steel material and has bridges 422 and 422a which are open at both ends to contact the lower girder flanges 311 and 321, and the grooves 422a that are long opened between the footrests 421 and 421. Temporary bridge construction method for controlling the deflection of the girder by the introduction of high tension bolt tension.
  4. 제 1항에 있어서,The method of claim 1,
    상기 (b) 단계에서 In step (b)
    메인 거더(32)는 작업장에서 나란한 한 쌍의 H 빔(32a,32a)과, 한 쌍의 H 빔(32a,32a)의 사이에 길이 방향을 따라 일정 간격마다 직각 방향으로 연결된 크로스 빔(32b)이 일체로 조립 제작된 상태에서 인양되어 2개의 거더 라인을 한 번에 설치하는 것을 특징으로 하는 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법.The main girder 32 is a cross beam 32b connected at right angles at regular intervals along a longitudinal direction between a pair of H beams 32a and 32a and a pair of H beams 32a and 32a which are side by side in a workplace. A temporary bridge construction method for controlling girder deflection by introducing tension of a high-strength bolt, which is lifted in the state of being integrally assembled and installed, and two girder lines are installed at one time.
  5. 제 4항에 있어서,The method of claim 4, wherein
    홀수개의 거더 라인을 갖을 경우 남아있는 마지막 1개의 거더 라인에는 단일의 H 빔(32a)을 추가적으로 설치한 후 이웃한 메인 거더(32와 32)와 크로스 빔(32b)을 통해 연결되는 것을 특징으로 하는 고장력 볼트의 장력 도입으로 거더 처짐을 제어하는 가설교량 시공 방법.In the case of having an odd number of girders, the remaining one girder line is additionally installed with a single H beam 32a, and is connected to neighboring main girders 32 and 32 through a cross beam 32b. Temporary bridge construction method to control girder deflection by introducing tension of high tension bolt.
PCT/KR2018/002000 2018-02-09 2018-02-19 Temporary bridge construction method employing tension of high tension bolt to control girder deflection WO2019156274A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2018-0016525 2018-02-09
KR1020180016525A KR101914002B1 (en) 2018-02-09 2018-02-09 Temporary bridge construction method having girder droop control by tension of high strength bolt

Publications (1)

Publication Number Publication Date
WO2019156274A1 true WO2019156274A1 (en) 2019-08-15

Family

ID=64099929

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2018/002000 WO2019156274A1 (en) 2018-02-09 2018-02-19 Temporary bridge construction method employing tension of high tension bolt to control girder deflection

Country Status (2)

Country Link
KR (1) KR101914002B1 (en)
WO (1) WO2019156274A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112095439A (en) * 2020-09-07 2020-12-18 中国建筑第八工程局有限公司 Method for constructing transportation platform between canyon tunnels and structure of transportation platform
CN112411380A (en) * 2020-09-27 2021-02-26 中铁城建集团有限公司 Multi-machine combined-hoisting river-crossing erection construction method for prefabricated box girder

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102273565B1 (en) 2019-02-12 2021-07-05 박상현 Temporary bridge having a software girder and method of constructing the temporary bridge
CN112144413B (en) * 2020-09-28 2021-11-05 贵州大通路桥工程建设有限公司 Whole-span in-situ splicing and erecting method for steel-concrete composite beam in mountainous area
CN114214955B (en) * 2021-12-28 2024-03-22 武船重型工程股份有限公司 Method for erecting bridge-crossing steel plate girder

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04166527A (en) * 1990-10-29 1992-06-12 Ohbayashi Corp Connection structure for beam member
JPH0853883A (en) * 1994-08-10 1996-02-27 Sekisui Chem Co Ltd Beam joint structure in building unit provided with inclined plane of structure
JPH10273935A (en) * 1997-01-31 1998-10-13 Nippon Light Metal Co Ltd Connection structure of structural material
JPH10317509A (en) * 1997-05-20 1998-12-02 Nippon Steel Corp Bolt joining structure in steel structure
KR101744437B1 (en) * 2016-02-23 2017-06-07 이종란 Construction method of temporary bridge using camber

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04166527A (en) * 1990-10-29 1992-06-12 Ohbayashi Corp Connection structure for beam member
JPH0853883A (en) * 1994-08-10 1996-02-27 Sekisui Chem Co Ltd Beam joint structure in building unit provided with inclined plane of structure
JPH10273935A (en) * 1997-01-31 1998-10-13 Nippon Light Metal Co Ltd Connection structure of structural material
JPH10317509A (en) * 1997-05-20 1998-12-02 Nippon Steel Corp Bolt joining structure in steel structure
KR101744437B1 (en) * 2016-02-23 2017-06-07 이종란 Construction method of temporary bridge using camber

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112095439A (en) * 2020-09-07 2020-12-18 中国建筑第八工程局有限公司 Method for constructing transportation platform between canyon tunnels and structure of transportation platform
CN112411380A (en) * 2020-09-27 2021-02-26 中铁城建集团有限公司 Multi-machine combined-hoisting river-crossing erection construction method for prefabricated box girder
CN112411380B (en) * 2020-09-27 2023-11-14 中铁城建集团有限公司 Construction method for connecting prefabricated boxes Liang Duoji to hoist and span river

Also Published As

Publication number Publication date
KR101914002B1 (en) 2018-10-31

Similar Documents

Publication Publication Date Title
WO2019156274A1 (en) Temporary bridge construction method employing tension of high tension bolt to control girder deflection
KR101614253B1 (en) Cantilever construction method of temporary bridge
US5412913A (en) Self-aligning beam joint suited for use in modular construction
US5653556A (en) Clamping apparatus and methods for driving caissons into the earth
CN109629569B (en) Steel pipe pile guide frame structure and construction method
JP6917318B2 (en) Bridge construction method
CN110670488A (en) Full-prefabricated assembled bridge construction platform and construction method
WO2020085590A1 (en) Annular cofferdam using tapered square pipes, temporary structure for pit excavation construction, and construction method
JP3440422B2 (en) Bridge construction method and bridge construction device
KR101744437B1 (en) Construction method of temporary bridge using camber
WO2018190444A1 (en) Prefabricated double composite plate girder bridge and construction method therefor
CN209780193U (en) Suspension type scaffold
CN108221702B (en) Integral lifting device for arch rib of inward-tilting steel box arch bridge
CN218405428U (en) Operation device is transported to cylinder
JP2006265976A (en) Corrugated steel-plate web u component bridge and its construction method
KR100627102B1 (en) Upper bridge structure construcion method with precast segment deck or box using a lifting traveller
CN211228142U (en) Full prefabricated assembled bridge construction platform
KR200363059Y1 (en) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
CN113982281A (en) Super-tonnage space truss lifting and reinforcing structure and construction method thereof
JPH06218471A (en) Method of manufacturing reinforcing bar net
JP3749602B2 (en) Directly erected construction method of large roof
KR100245801B1 (en) A clamp for beam
CN115596247B (en) Inclined-pulling type full-column dismantling and transferring operation frame and construction method thereof
CN213951987U (en) Operation platform for maintaining high-speed railway pier
JP7011613B2 (en) How to build a simple temporary bridge

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18905495

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18905495

Country of ref document: EP

Kind code of ref document: A1