WO2018166519A1 - Bridge building device and construction method therefor - Google Patents

Bridge building device and construction method therefor Download PDF

Info

Publication number
WO2018166519A1
WO2018166519A1 PCT/CN2018/079253 CN2018079253W WO2018166519A1 WO 2018166519 A1 WO2018166519 A1 WO 2018166519A1 CN 2018079253 W CN2018079253 W CN 2018079253W WO 2018166519 A1 WO2018166519 A1 WO 2018166519A1
Authority
WO
WIPO (PCT)
Prior art keywords
bridge
pier
crane
foundation
support
Prior art date
Application number
PCT/CN2018/079253
Other languages
French (fr)
Chinese (zh)
Inventor
王燏斌
Original Assignee
王燏斌
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王燏斌 filed Critical 王燏斌
Publication of WO2018166519A1 publication Critical patent/WO2018166519A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Definitions

  • the invention relates to a bridge building device and a construction method thereof, and belongs to the technical field of bridge engineering.
  • the existing cofferdam method In the construction of existing cross-river bridges, it is necessary to encircle the rivers and then piling and bridging.
  • the existing cofferdam method generally adopts steel sheet pile cofferdam, which has the problems of large investment, long construction period and difficult construction.
  • the existing bridge erecting machine can only be used for girders, and foundation and pier construction cannot be carried out.
  • the invention provides a bridge building device and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantages thereof are as follows: 1) the bridge device can construct a bridge foundation, can also install a pier, and can also build a bridge. , construction is fast; 2) The bridge foundation is prefabricated in sections, sinking in sections, without the need for cofferdams, and the construction is simple.
  • the bridge building device comprises a bridge machine 1, a moving rail 2, a mobile crane 3 and a bridge foundation construction device 4, and the bridge machine 1 is provided with a rear end support 1-1, a middle support 1-2 and
  • the front end support 1-3, the bottom end support 1-1 and the bottom support 1-2 are respectively provided with a running device 1-1-1 and a walking device 1-2-1, and a bottom portion of the front end support 1-3 is provided with a running device 1-3-1, the traveling device 1-1-1 and the traveling device 1-2-1 are operated on the erected beam, the traveling device 1-3-1 is operated on the moving rail 2, and the front end support 1-3 is further provided.
  • a lifting support device 1-3-2 a crane 1-4 provided on the upper part of the bridge machine 1, and the lifting support device 1-3-2 is supported on the pier when the bridge machine 1 is hoisting or when the moving rail 2 is running;
  • the function of the bridge machine 1 is: one is the frame beam; the other is to lift the foundation or pier from the erected beam to the front end of the framed beam;
  • the rear end of the moving track 2 is provided with the rear end lifting support device 2-1, the bottom of the rear end lifting support device 2-1 is supported on the pier;
  • the front end of the moving rail 2 is provided with a front end lifting support device 2-2, and the bottom of the front end lifting support device 2-2 is supported on the ground or the bottom;
  • the top of the mobile crane 3 is provided with a rail on which the top crane 3-1 is provided, and the top crane 3-1 runs from the front or the rear to the rear or front portion in the mobile crane 3 through the rail; the bottom of the mobile crane 3
  • the rear end is provided with a walking device 3-2.
  • the walking device 3-2 has two structures: one can only walk on the existing beam, and the other can walk on the existing beam and the moving rail 2; the bottom of the mobile crane 3 is moved.
  • the front end and the middle are provided with a running device 3-3 running on the moving rail 2, and the mobile crane 3 puts the prefabricated bridge foundation into the bridge foundation construction device 4, and completes the construction of the bridge foundation in the bridge foundation construction device 4;
  • the bridge foundation construction device 4 is also supported by the moving rail 2; the mobile crane 3 places the prefabricated pier above the constructed bridge foundation, and the mobile crane 3 will complete the bridge.
  • the bridge foundation construction device 4 for foundation construction is moved to the position where the bridge foundation construction is awaited, and the bridge foundation construction device 4 completes the construction of the foundation, and the bridge construction device can complete the construction of the bridge foundation, the pier and the beam.
  • the invention has the advantages that the bridging device can construct the bridge foundation or the bridge; the bridge foundation is prefabricated in sections, the section is sunken, no cofferdam is needed, the construction is simple, and the construction period is short.
  • FIG. 1 is a schematic structural view of a bridge-building device composed of a bridge machine 1, a moving rail 2, a mobile crane 3, a construction device 4-1 of a bridge foundation 6 with a chain cutter at the bottom during construction, and a mobile support device 5;
  • a walking device 1-2 having a rear support 1-1, a middle support 1-2, a front end support 1-3, a rear end support 1-1 bottom walking device 1-1-1, and a middle support 1-2 -1, the traveling device 1-3-1 at the bottom of the front end support 1-3, the jacking support device 1-3-2 at the bottom of the front end support 1-3, and the bridge machine 1 composed of the upper horizontally moving crane 1-4 Schematic;
  • FIG. 3 is a rear end lifting support device 2-1, a front end lifting support device 2-2, a front walking support device 2-3, a walking device 2-3-1, a traveling device 2-3-2, and a rear walking support device 2 4.
  • a schematic structural view of a moving track 2 composed of a traveling device 2-4-1 and a traveling device 2-4-2;
  • FIG. 4 is a schematic structural view of a mobile crane 3 composed of a top crane 3-1, a traveling device 3-2, and a traveling device 3-3;
  • Figure 5 is a basic construction device 4-1 consisting of a fixed guide 4-1-1, a chain cutter power transmission 4-1-2, a spoil treatment device 4-1-3, and a frame 4-1-4.
  • the structural schematic diagram is also a schematic structural view of the chain excavating device 12 composed of the device 4-1-2 and the foundation 6 and the chain cutter 11;
  • Figure 6 is a view in the direction of arrow A of Figure 5, and is also a schematic structural view of a chain conveyor composed of a side cover 10 and a chain cutter 11 at the bottom;
  • Figure 7 is a BB view of Figure 5, also a cross-sectional view of the frame 4-1-4 of the construction apparatus 4-1, and also the mud line 13-1 of the mud line unit 13 on the frame 4-1-4. Schematic;
  • Figure 8 is a C-C view of Figure 5, and is also a schematic structural view of the mud nozzle 13-2 at the bottom of the foundation 6 of the mud pipeline device 13;
  • Figure 9 is a schematic view showing the structure of the chain cutter 11, and is also a schematic structural view of the chain 11-1 and the cutter 11-2, and is also a chain 11 composed of A ten-byte 11-1-1 and B-tenbyte 11-1-2.
  • a schematic diagram of a ten-byte structure of 1 is also a schematic diagram of a structure in which the chain 11-1 realizes space bending;
  • Figure 10 is a schematic view showing the structure of the foundation construction device 4-2 by the fixed guiding device 4-2-1, the rotating device 4-2-2, and the descending speed controlling device 4-2-3, and also the excavation of the bottom of the spiral cylindrical foundation 9.
  • Figure 11 is a schematic structural view of a moving support device 5A composed of a traveling device 5-1 and a lifting support device 5-2;
  • FIG. 12 is a schematic structural view of the mobile supporting device 5B composed of the traveling device 5-1, the lifting support device 5-3 and the temporary base 5-4, and is also a schematic structural view of the mobile supporting device 5B supported on the bridge foundation 6;
  • Figure 13 is a schematic structural view of a bridge building device of a double pier 7;
  • Figure 14 shows that the installed beams 8 are the m-1th beam 8, the m-2th beam 8, ..., and the unmounted beams 8 are the m+1th beam 8, the m+2 beam 8, ... ..., the piers 7 corresponding to the mth beam 8 are the mth pier 7 and the m+1 pier 7, respectively, and the piers 7 corresponding to the m-1th beam 8 are the m-1 pier 7 and the m pier 7, respectively, m
  • the piers 7 of the +1 beam 8 are the m+1th pier 7 and the m+2 pier 7, respectively, and the foundation 6 corresponding to the mth pier 7 is a structural schematic of the mth foundation, and is also the mth pier 7 and the m+1 pier.
  • the rear end lifting support device 2-1 of the moving rail 2 is supported at the front end of the mth pier 7, the mobile supporting device 5 is located in front of the m+1th base, and the bridge foundation construction device 4-1 is located at the m+ 2 structural diagram of the basic set position;
  • Figure 15 is a schematic view showing the structure in which the lifting support device 1-3-2 supported by the front end of the bridge machine 1 is separated from the mth pier 7 and the bridge machine 1 moves forward on the moving rail 2 to reach the set position;
  • Figure 16 is a structural schematic view of the moving rail 2 running forward to the set position, and also transporting the mth beam 8 to the m-1th beam 8, located below the rear of the bridging machine 1, the crane above the bridge 1 1-4 is a schematic structural view of running above the mth beam 8;
  • Figure 17 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the mth beam 8;
  • Figure 18 is a crane 1-4 on the bridge machine 1 lowering the mth beam 8, the mth beam 8 and the mth beam 8 and the m-1th beam 8, the mth pier 7, and the m+1th pier 7 connected structure diagram;
  • Figure 19 is a structure in which the m+2th base is transported to the m-1th beam 8 and is located below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 is moved to the upper part of the m+2 base.
  • Figure 20 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the m+2 foundation 6 and running forward along the track above the bridge machine;
  • Figure 21 is a view showing that the crane 1-4 on the bridge machine 1 lowers the m+2 base 6, and the m+2 base 6 is placed at the front end of the m-1 beam 8, and the crane 1-4 above the bridge machine 1 Run to the rear, let the structure of the space above the m+2 base 6 be opened;
  • Figure 22 is a schematic view showing the structure of the crane 3-1 on the mobile crane 3 lifting the m+2 base 6 and moving forward along the track above the mobile crane 2;
  • Figure 23 is a schematic view showing the structure of the mobile crane 3 running forward along the moving rail 2 to the m+2 base 6 setting position;
  • Figure 24 is a schematic view showing the structure in which the m+2 base 6 is placed in the bridge foundation construction device 4-1, and the mobile crane 3 connects the chain cutter driving device 4-1-2 and the m+2 base 6 top;
  • Figure 25 is a schematic view showing the structure of the starting bridge construction device 4-1, the m+2 base is lowered to the set depth;
  • Figure 26 is the transport of the m+2 spiral cylindrical foundation 9 to the m-1th beam 8, below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 runs to the m+2 spiral Schematic diagram of the structure above the cylindrical foundation 9;
  • Figure 27 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the m+2 spiral cylindrical foundation 9 and running forward along the track above the bridge machine 1;
  • Figure 28 is a view showing that the crane 1-4 on the bridge machine 1 lowers the m+2 spiral cylindrical foundation 9, and the m+2 spiral cylindrical foundation 9 is placed at the front end of the m-1 beam 8, the bridge machine 1
  • the upper crane 1-4 runs backwards to allow a schematic view of the space above the m+2 spiral cylindrical foundation 9;
  • Figure 29 is a schematic view showing the structure of the crane 3-1 on the mobile crane 3 lifting the m+2 spiral cylindrical foundation 9 and moving forward along the track above the mobile crane 2;
  • Figure 30 is a schematic view showing the structure in which the mobile crane 3 is moved forward along the moving rail 2 to the set position of the m+2 spiral cylindrical foundation 9;
  • Figure 31 is a view in which the m+2 spiral cylindrical foundation 9 is placed in the bridge foundation construction device 4-2, and the mobile crane 3 connects the rotating device 4-2-2 with the top of the m+2 spiral cylindrical foundation 9.
  • Figure 32 is a schematic structural view showing the start of the bridge construction device 4-2, the m+2 spiral cylindrical foundation 9 is lowered to a set depth;
  • Figure 33 is a schematic view showing the structure in which the rear end lifting support device 2-1 of the moving rail 2 is separated from the mth bridge 7 and the front end lifting support device 2-2 is separated from the ground or the water bottom;
  • Figure 34 is a schematic view showing the structure in which the moving rail 2 is moved forward to the set position, the rear end lifting support device 2-1 is supported and extended, and the front end lifting support device 2-2 is supported and extended;
  • Figure 35 is a view in which the mobile supporting device 5 is moved to the rear of the bridge foundation construction device 4-1 located at the m+2 base position, and the mobile crane 3 is moved above the bridge foundation construction device 4-1 to move the track 2 forward.
  • Figure 36 is a schematic view showing the structure of the crane 3-1 above the mobile crane 3 lifting the bridge foundation construction device 4-1;
  • Figure 37 is a mobile crane 3 with a bridge foundation construction device 4-1 running forward on the moving rail 2 to the top of the m+3 base, and the crane 3-1 on the mobile crane 3 causes the bridge foundation device 4-1 to Schematic diagram of the exact clamping position of the m+3 position;
  • Figure 38 is a schematic view showing the structure of the mobile supporting device 5 moved to the front of the m+2 base;
  • Figure 39 is a schematic view showing the structure of the m+2 pier 7 being transported to the m-1th beam 8 and the crane 1-4 above the bridge machine 1 running above the m+2 pier 7;
  • Figure 40 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the m+2 pier 7 and walking to the front end of the m-th beam 8;
  • Figure 41 is a schematic view showing the structure of the crane 1-4 above the bridge crane 1 running backward, and the moving crane 3 running forward along the track above the moving crane 2 to the m+2 pier 7;
  • Figure 42 is a schematic view showing the structure in which the crane 3-1 at the rear of the mobile crane 3 is lifted from the rear of the m+2 pier 7 to the front of the mobile crane 3;
  • Figure 43 is a mobile crane 3 with the m+2 pier 7 running forward to the top of the m+2 base, placing the m+2 pier 7 on the m+2 base and accurately positioning and solidifying into one Schematic diagram of the structure.
  • 1 is the bridging machine of the bridge building device; 1-1 is the rear end support of the bridging machine; 1-1-1 is the running device at the bottom of the rear end support 1-1 of the bridging machine;
  • the middle support of the bridge machine; 1-2-1 is the walking device of the middle support of the bridge machine 1-2; 1-3 is the front support of the bridge machine; 1-3-1 is the front support of the bridge machine 1 -3 at the bottom of the walking device; 1-3-2 is the top support of the front end support 1-3;
  • 1-4 is the crane of the upper part of the bridge machine 1;
  • 2 is the moving track of the bridge building; 2-1 It is a rear end lifting support device provided at the rear end of the moving rail 2, supported on the pier 7; 2-2 is a front end lifting support device provided at the front end of the moving rail 2, supported on the ground or the water bottom;
  • 12 is a chain excavation device consisting of the device 4-1-2 and the bridge foundation 6 and the chain cutter 11; 13 is a mud pipeline device; 13-1 is the frame 4-1-4 in the device 4-1 Mud line; 13-2 is the mud nozzle on the bottom of the bridge foundation 6.
  • the bridge building device comprises a bridge machine 1, a moving rail 2, a mobile crane 3 and a bridge foundation construction device 4.
  • the bridge machine 1 is provided with a rear end support 1-1, a middle support 1-2 and a front end support 1-3, and thereafter
  • the bottom of the end support 1-1 and the middle support 1-2 are respectively provided with a running device 1-1-1 and a traveling device 1-2-1
  • the bottom of the front end support 1-3 is provided with a walking device 1-3-1, walking
  • the device 1-1-1 and the traveling device 1-2-1 are operated on the erected beam
  • the traveling device 1-3-1 is operated on the moving rail 2
  • the front end support 1-3 is further provided with the lifting support device 1-3.
  • the crane 1-4 is provided on the upper part of the bridge machine 1, and the lifting support device 1-3-2 is supported on the pier when the bridge machine 1 is hoisting or when the moving rail 2 is running;
  • the function of the bridge machine 1 is: The first is to erect the beam; the second is to lift the foundation or pier from the erected beam to the front end of the framed beam; the rear end of the moving track 2 is provided with the rear end lifting support device 2-1, and the rear end is lifted and lowered.
  • the bottom of the supporting device 2-1 is supported on the pier; the front end of the moving rail 2 is provided with a front end lifting support device 2-2, and the bottom of the front end lifting support device 2-2 is supported on the ground or the bottom; when the moving rail 2 moves, the rear end Rise
  • the support device 2-1 is separated from the bridge pier, the front end lifting support device 2-2 is separated from the ground or the water bottom, and the middle portion of the moving rail 2 is respectively moved on the pier and the bridge foundation construction device 4; when the bridge machine 1 is running on the moving rail 2, The middle and rear portions of the moving rail 2 are supported on the pier; when the mobile crane 3 is running on the moving rail 2 with the foundation or the pier, the middle and rear portions of the moving rail 2 are also supported on the pier, moving the front of the rail 2 The support is supported on the bridge foundation construction device 4.
  • the top of the mobile crane 3 is provided with a rail on which the top crane 3-1 is provided, and the top crane 3-1 runs from the front or the rear to the rear or front portion in the mobile crane 3 through the rail; the bottom of the mobile crane 3
  • the rear end is provided with a walking device 3-2.
  • the walking device 3-2 has two structures: one can only walk on the existing beam, and the other can walk on the existing beam and the moving rail 2; the bottom of the mobile crane 3 is moved.
  • the front end and the middle are provided with a running device 3-3 running on the moving rail 2, and the mobile crane 3 puts the prefabricated bridge foundation into the bridge foundation construction device 4, and completes the construction of the bridge foundation in the bridge foundation construction device 4;
  • the bridge foundation construction device 4 is also supported by the moving rail 2; the mobile crane 3 places the prefabricated pier above the constructed bridge foundation, and the mobile crane 3 will complete the bridge.
  • the bridge foundation construction device 4 for foundation construction is moved to a position waiting for the foundation construction of the bridge; the bridge foundation construction device 4 completes the construction of the foundation, and the bridge assembly device can complete the construction of the bridge foundation, the pier and the beam.
  • the bottom of the moving rail 2 is provided with a front walking support device 2-3 and a rear walking support device 2-4, and the front walking support device 2-3 is provided with a walking device 2-3-1, and the rear walking supporting device 2 4, the walking device 2-4-1 is provided, the rear walking support device 2-4 is supported on the bridge pier, the front walking support device 2-3 is supported on the bridge foundation construction device 4, and the rear end lifting support device 2-1 is separated from the pier
  • the moving rail 2 is moved from one position to another by the traveling device 2-3-1 and the traveling device 2-4-1.
  • the front travel support device 2-3 is provided with a travel device 2-3-2
  • the rear travel support device 2-4 is provided with a travel device 2-4-2
  • the mobile track 2 is provided with a travel device 2-3-2 and The track on which the traveling device 2-4-2 operates, the front walking support device 2-3 runs from one position to another through the traveling device 2-3-2, and the rear walking support device 2-4 passes the walking device 2-4-2 Run from one location to another.
  • the bridge building device further includes a moving support device 5 disposed behind the bridge foundation construction device 4.
  • the bottom of the mobile support device 5 supports two structures: one is supported on the ground or the bottom includes a water boat, and the other is supported at On the basis of the bridge; the upper part of the mobile supporting device 5 is the support of the moving rail 2, and the moving supporting device 5 is provided with the running device 5-1 running on the moving rail 2, and when the bottom of the moving supporting device 5 is separated from the support, the traveling device is passed 5-1 Walk from one position to another.
  • the installed beams are the m-1th beam, the m-2th beam, the m-3th beam, ..., and the unmounted beams are the m+1th beam, the m+2 beam, and the The m+3 beam, ..., the corresponding pier of the mth beam is the mth pier and the m+1th pier, respectively, and the corresponding piers of the m-1th beam are the m-1 pier and the mth pier, respectively, m+1 The bridge piers of the beam are the m+1th pier and the m+2 pier, respectively.
  • the foundation corresponding to the mth pier is the mth foundation.
  • the mth pier and the m+1 pier are installed, and the rear support of the moving track 2 is supported.
  • the device 2-1 is supported at the front end of the mth pier, the moving support device 5 is located in front of the m+1th base, and the bridge foundation construction device 4 is located at the set position of the m+2th base.
  • the construction method of the m-th beam has the following steps:
  • the traveling device of the rear end support 1-1 and the middle support 1-2 of the bridging machine 1 runs forward on the erected beam, and the running device 1-3-1 of the front end support 1-3 is on the moving rail 2 Moving forward, reaching the set position, supporting the lifting support device 1-3-2 of the front end support 1-3 of the bridging machine 1 at the front of the m+1th pier, so that the front end of the bridging machine 1 supports 1-3
  • the walking device 1-3-1 is separated from the moving track 2;
  • moving rail 2 forwardly reaches the set position, and the rear travel support device 2-4 of the moving rail 2 runs from the mth pier to the front of the m+1th pier and is supported on the m+1th pier;
  • the m+2 base has two structures: A and B:
  • the m+2 foundation is the foundation with a chain cutter at the bottom of the construction.
  • the chain cutter only excavates the rock at the bottom of the foundation;
  • the bridge foundation construction device 4-1 includes fixed guides 4-1-1, chain Knife power transmission device 4-1-2, spoil treatment device 4-1-3 and frame 4-1-4;
  • the m+2 base is a spiral cylindrical foundation with a cutter at the bottom, and the cutter only has the annular rock at the bottom of the spiral cylindrical foundation;
  • the bridge foundation construction device 4-2 includes a fixed guide 4-2 - 1, rotating device 4-2-2 and falling speed control device 4-2-3.
  • the m+2 base is a spiral cylindrical foundation with a cutter at the bottom, or a base with a chain cutter at the bottom during construction.
  • the specific construction method has the following steps:
  • the top crane 3-1 on the mobile crane 3 lifts the m+2 base and runs forward along the track above the mobile crane 3, making the top crane 3-1 and the m+2 base from the mobile crane The rear part of 3 moves to the front; the mobile crane 3 runs forward along the moving rail 2 to the m+2 basic setting position, and the m+2 foundation is placed into the bridge foundation construction device 4;
  • the mobile crane 3 connects the spiral cylindrical basic rotary driving device 4-2 or the chain cutter driving device 4-1 with the m+2 base top;
  • the construction method of the bridge foundation construction device 4 moving from the m+2 base position to the m+3 base position is as follows:
  • the moving rail 2 is moved forward to the set position, the rear end lifting support device 2-1 is supported at the front end of the m+1th pier, and the front end lifting support device 2-2 is supported in front of the m+3 basic position. Ground or underwater;
  • the mobile crane 3 runs above the bridge foundation construction device 4, disengages the bridge foundation construction device 4 from the m+2 bridge foundation, and disengages the front travel support device 2-3 of the moving rail 2 from the bridge foundation construction device 4. ;
  • the m-th beam and the m+2 base have been completed, and the rear end lifting support device 2-1 of the moving rail 2 and the lifting support device 1-3-2 of the front end support 1-3 of the bridging machine 1 are supported.
  • the mobile supporting device 5 is supported on the ground or the water bottom near the front of the m+2 foundation, and the bridge foundation construction device 4 is located at the set position of the m+3 foundation, and the concrete construction of the m+2 pier
  • the method has the following steps:
  • the mobile crane 3 runs backward through the bottom traveling device 3-2 and the traveling device 3-3, so that the top crane 3-1 at the upper rear portion of the mobile crane 3 reaches the set position above the m+2 pier;
  • the mobile crane 3 carries the m+2 pier through the bottom of the walking device 3-2 and the running device 3-3 forward to the top of the m+2 base, and the m+2 pier is placed at the m+th 2 Based on the basic positioning and accurate positioning.
  • the bridge-building device is composed of a bridge machine 1, a moving rail 2, a mobile crane 3, a bridge foundation construction device 4, and a mobile support device 5.
  • the bridge-building machine is provided with a rear support 1-1.
  • the central support 1-2 and the front end support 1-3, the bottom end support 1-1 and the bottom support 1-2 are respectively provided with a walking device 1-1-1 and a walking device 1-2-1, and the front end supports 1-
  • the bottom of the 3 is provided with a walking device 1-3-1, the traveling device 1-1-1 and the traveling device 1-2-1 are operated on the erected beam 8, and the running device 1-3-1 is operated on the moving rail 2
  • the front end support 1-3 is further provided with a lifting support device 1-3-2, and the upper portion of the bridge machine 1 is provided with a horizontally moving crane 1-4, and the lifting support device is used when the bridge machine 1 is hoisting or when the moving rail 2 is running 1-3-2 is supported on the pier 7; the function of the bridge machine 1 is: one is the frame beam 8; the
  • the top of the mobile crane 3 is provided with a rail on which the crane 3-1 is arranged, and the crane 3-1 runs from the front (or rear) portion to the rear (or front) portion in the mobile crane 3 through the rail; the mobile crane 3
  • the bottom rear end is provided with a running device 3-2.
  • the bottom front end of the mobile crane 3 is provided with a running device 3-3 running on the moving rail 2, and the mobile crane 3 places the prefabricated bridge foundation 6 into the bridge foundation.
  • the construction of the bridge foundation 6 is completed in the bridge foundation construction device 4; when the bottom of the bridge foundation construction device 4 is supported on the ground or the water bottom, the bridge foundation construction device 4 is also the support of the moving rail 2; the mobile crane 3 will The prefabricated pier 7 is placed above the constructed bridge foundation 6, and the mobile crane 3 moves the bridge foundation construction device 4 that has completed the bridge foundation construction to a position waiting for the bridge foundation construction; the bridge foundation construction device 4 completes the construction of the foundation.
  • the m+2 base has two structures, A and B:
  • the m+2 base is the foundation 6 with a chain knife at the bottom of the construction.
  • the chain cutter only has the rock at the bottom of the foundation;
  • the bridge foundation construction device 4-1 includes a fixed guide 4-1-1, Chain cutter power transmission 4-1-2, spoil treatment device 4-1-3 and frame 4-1-4; during construction, the frame 4-1-4 is integrated with the top of the foundation 6, device 4 -1-2 drive chain cutter 11 runs along the track on the foundation 6, the chain cutter 11 excavates the rock at the bottom of the foundation 6, and brings the excavated rock to the top, and the device 4-1-3 takes the chain cutter 11 from The rock soil brought up from the bottom of the foundation 6 is separated from the chain cutter 11, and the frames 4-1-4 are simultaneously descended along with the foundation 6;
  • the m+2 base is a spiral cylindrical foundation 9 with a cutter at the bottom, the cutter only has the annular rock at the bottom of the spiral cylindrical foundation;
  • the bridge foundation construction device (4-2) includes a fixed guide 4-2-1, drive rotating device 4-2-2 and descending speed control device 4-2-3; during construction, drive rotating device 4-2-2 rotates base 9, through descending speed control device 4-2- 3 controlling the descending speed of the spiral cylindrical foundation 9, so that the cutter 9-1 at the bottom of the spiral cylindrical foundation 9 cuts the annular rock at the bottom of the foundation 9, and the cut rock is introduced into the foundation under the action of the bottom tapered surface.
  • the spiral blade 9-2 transports the cut rock at the bottom to the upper portion and gradually descends to the set position.
  • the bottom of the mobile supporting device 5 supports two structures 5A and 5B: 5A is supported on the ground or underwater (including water boat), 5B is supported on the bridge foundation; and the mobile supporting device 5
  • the upper part is the support of the moving rail 2
  • the moving support device 5 is provided with a running device 5-1 running on the moving rail, and when the bottom of the moving supporting device 5 is separated from the support, the traveling device 5-1 walks from one position to another The position, the bridge building device can complete the construction of the bridge foundation 6, the pier 7 and the beam 8.
  • the bridge building device simultaneously constructs the double bridge pier 7, and the longitudinal width of the moving rail 2 and the mobile crane 3 of the bridge building device exceeds the width of the double bridge pier.
  • the construction method of the mth beam 8 has the following steps:
  • the traveling device 1-1-1 of the rear end support 1-1 of the bridge machine 1 and the traveling device 1-2-1 of the middle support run forward on the erected beam 8, and the front end supports the walking of 1-3
  • the device 1-3-1 moves forward on the moving rail 2 to reach the set position, and supports the lifting support device 1-3-2 supported by the front end of the bridge machine 1 at the front of the m+1th pier 7, so that the frame
  • the traveling device 1-3-1 supported by the front end of the bridge machine 1 is separated from the moving rail 2;
  • the moving rail 2 runs forward to reach the set position, and the rear travel support device of the moving rail 2 runs from the mth bridge pier 7 to the front portion of the m+1th pier 7, and is supported on the m+1th pier 7;
  • the m+2 basis is the foundation 6 with a chain knife at the bottom of the construction.
  • the specific construction method has the following steps:
  • the mobile crane 3 connects the chain cutter driving device 4-1-2 to the top of the m+2 base 6;
  • the m+2 basis is a spiral cylindrical foundation 9 with a digging knife at the bottom during construction.
  • the specific construction method has the following steps:
  • the mobile crane 3 connects the chain cutter driving device 4-1-2 to the top of the m+2 base 9;
  • the construction method of the bridge foundation construction device 4-1 moving from the m+2 base position to the m+3 base position is as follows:
  • the mobile crane 3 runs to the top of the bridge foundation construction device 4-1, and the bridge foundation construction device 4-1 is separated from the m+2 bridge foundation, and the front travel support device 2-3 of the moving rail 2 and the bridge foundation are Construction device 4-1 is detached;
  • the m-th beam 8 and the m+2 base have been completed, and the rear end lifting support device 2-1 of the moving rail and the lifting support device 1-3- supported by the front end of the bridge machine 1 are completed.
  • 2 is supported on the m+1th pier 7
  • the mobile support device 5 is supported on the ground or the water bottom near the front of the m+2 base
  • the bridge foundation construction device 4-1 is located at the set position of the m+3 base
  • the concrete construction method of +2 pier 7 has the following steps:
  • the mobile crane 3 carries the m+2 pier 7 through the bottom running device 3-2 and the running device 3-3 forward to the top of the m+2 base, and places the m+2 pier 7 Based on m+2 and accurately positioned and fixed into one.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A bridge building device and a construction method therefor. The bridge building device comprises a bridge erecting machine (1), a movement rail (2), a moving crane (3), and a bridge foundation construction device (4). The bridge erecting machine (1) is provided with a rear support (1-1), a middle support (1-2), and a front support (1-3). The bottoms of the rear support (1-1) and the middle support (1-2) are provided with traveling devices (1-1-1, 1-2-1), respectively. The bottom of the front support (1-3) is provided with a traveling device (1-3-1). The traveling devices (1-1-1, 1-2-1) of the rear support (1-1) and the middle support (1-2) operate on an erected beam (8), and the traveling device (1-3-1) of the front support (1-3) operates on the movement rail (2). The front support (1-3) is also provided with a lifting support device (1-3-2) which is supported on piers (7) when the bridge erecting machine (1) performs craning or the movement rail (2) is in operation. The rear end of the movement rail (2) is provided with a rear lifting support device (2-1). The bottom of the rear lifting support device (2-1) is supported on the piers (7). By means of the bridge building device, the bridge foundation (6), the piers (7) and the beam (8) can be constructed. The bridge building device is suitable for constructing the bridge foundation (6) and erecting a bridge; the bridge foundation (6) is prefabricated segment by segment or in a whole and is sunk segment by segment or in a whole, no cofferdam is required, construction is simple, and construction period is short.

Description

一种造桥装置及其施工法Bridge building device and construction method thereof 技术领域Technical field
本发明涉及的是一种造桥装置及其施工法,属于桥梁工程技术领域。The invention relates to a bridge building device and a construction method thereof, and belongs to the technical field of bridge engineering.
背景技术Background technique
一、现有跨河大桥施工中,需要将河道围堰,再进行打桩、架桥等施工。现有的围堰方法一般采用钢板桩围堰,具有投入大、工期长、施工难度大的问题。1. In the construction of existing cross-river bridges, it is necessary to encircle the rivers and then piling and bridging. The existing cofferdam method generally adopts steel sheet pile cofferdam, which has the problems of large investment, long construction period and difficult construction.
二、现有的架桥机仅能架梁,不能进行基础和桥墩施工。Second, the existing bridge erecting machine can only be used for girders, and foundation and pier construction cannot be carried out.
发明内容Summary of the invention
本发明提出的是一种造桥装置及其施工法,其目的旨在克服现有技术存在的缺陷,其主要优点:1)架桥装置可以施工桥梁基础,也可以安装桥墩,还可以架设桥梁,施工快捷;2)桥梁基础分段预制,分段下沉,不需要围堰,施工简单。The invention provides a bridge building device and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantages thereof are as follows: 1) the bridge device can construct a bridge foundation, can also install a pier, and can also build a bridge. , construction is fast; 2) The bridge foundation is prefabricated in sections, sinking in sections, without the need for cofferdams, and the construction is simple.
本发明的技术解决方案:造桥装置包括架桥机1、移动轨道2、移动吊机3和桥梁基础施工装置4,架桥机1设有后端支撑1-1、中部支撑1-2和前端支撑1-3,后端支撑1-1和中部支撑1-2的底部分别设有行走装置1-1-1和行走装置1-2-1,前端支撑1-3的底部设有行走装置1-3-1,行走装置1-1-1和行走装置1-2-1在已架设的梁上运行,行走装置1-3-1在移动轨道2上运行,前端支撑1-3还设有升降支撑装置1-3-2,架桥机1的上部设有的起重机1-4,架桥机1起重时或移动轨道2运行时升降支撑装置1-3-2支撑在桥墩上;架桥机1的功能:一是架梁;二是将从已架设的梁上运来的基础或桥墩吊起放在已架好的梁的前端;移动轨道2的后端设有后端升降支撑装置2-1,后端升降支撑装置2-1的底部支撑在桥墩上;移动轨道2的前端设有前端升降支撑装置2-2,前端升降支撑装置2-2的底部支撑在地面或水底;移动轨道2移动时,后端升降支撑装置2-1脱离桥墩,前端升降支撑装置2-2脱离地面或水底,移动轨道2的中部分别在桥墩和桥梁基础施工装置4上移动;当架桥机1在移动轨道2上运行时,移动轨道2的中部和后部支撑在桥墩上;当移动吊机3带着基础或桥墩在移动轨道2上运行时,移动轨道2的中部和后部也支撑在桥墩上,移动轨道2的前部支撑在桥梁基础施工装置4上。移动吊机3的顶部设有轨道,轨道上设有顶部起重机3-1,顶部起重机3-1通过轨道在移动吊机3内从前或后部运行至后或前部;移动吊机3的底部后端设 有行走装置3-2,行走装置3-2有两种结构:一仅在已建梁上行走,二在已建梁上和移动轨道2上均能行走;移动吊机3的底部前端和中间设有在移动轨道2上运行的行走装置3-3,移动吊机3将预制的桥梁基础放入桥梁基础施工装置4内,在桥梁基础施工装置4内完成桥梁基础的施工;桥梁基础施工装置4的底部支撑在地面或水底时,桥梁基础施工装置4也是移动轨道2的支撑;移动吊机3将预制的桥墩放在施工好的桥梁基础上方,移动吊机3将已完成桥梁基础施工的桥梁基础施工装置4移至等待桥梁基础施工的位置,桥梁基础施工装置4完成对基础的施工,造桥装置能完成桥梁基础、桥墩和梁的施工。Technical solution of the invention: the bridge building device comprises a bridge machine 1, a moving rail 2, a mobile crane 3 and a bridge foundation construction device 4, and the bridge machine 1 is provided with a rear end support 1-1, a middle support 1-2 and The front end support 1-3, the bottom end support 1-1 and the bottom support 1-2 are respectively provided with a running device 1-1-1 and a walking device 1-2-1, and a bottom portion of the front end support 1-3 is provided with a running device 1-3-1, the traveling device 1-1-1 and the traveling device 1-2-1 are operated on the erected beam, the traveling device 1-3-1 is operated on the moving rail 2, and the front end support 1-3 is further provided. There is a lifting support device 1-3-2, a crane 1-4 provided on the upper part of the bridge machine 1, and the lifting support device 1-3-2 is supported on the pier when the bridge machine 1 is hoisting or when the moving rail 2 is running; The function of the bridge machine 1 is: one is the frame beam; the other is to lift the foundation or pier from the erected beam to the front end of the framed beam; the rear end of the moving track 2 is provided with the rear end lifting support device 2-1, the bottom of the rear end lifting support device 2-1 is supported on the pier; the front end of the moving rail 2 is provided with a front end lifting support device 2-2, and the bottom of the front end lifting support device 2-2 is supported on the ground or the bottom; When the moving rail 2 moves, the rear end lifting support device 2-1 is disengaged from the bridge pier, the front end lifting support device 2-2 is separated from the ground or the bottom of the water, and the middle portion of the moving rail 2 is moved on the pier and the bridge foundation construction device 4 respectively; 1 When running on the moving rail 2, the middle and rear portions of the moving rail 2 are supported on the pier; when the mobile crane 3 is running on the moving rail 2 with the foundation or the pier, the middle and rear portions of the moving rail 2 are also supported. On the pier, the front portion of the moving rail 2 is supported on the bridge foundation construction device 4. The top of the mobile crane 3 is provided with a rail on which the top crane 3-1 is provided, and the top crane 3-1 runs from the front or the rear to the rear or front portion in the mobile crane 3 through the rail; the bottom of the mobile crane 3 The rear end is provided with a walking device 3-2. The walking device 3-2 has two structures: one can only walk on the existing beam, and the other can walk on the existing beam and the moving rail 2; the bottom of the mobile crane 3 is moved. The front end and the middle are provided with a running device 3-3 running on the moving rail 2, and the mobile crane 3 puts the prefabricated bridge foundation into the bridge foundation construction device 4, and completes the construction of the bridge foundation in the bridge foundation construction device 4; When the bottom of the foundation construction device 4 is supported on the ground or the bottom of the water, the bridge foundation construction device 4 is also supported by the moving rail 2; the mobile crane 3 places the prefabricated pier above the constructed bridge foundation, and the mobile crane 3 will complete the bridge. The bridge foundation construction device 4 for foundation construction is moved to the position where the bridge foundation construction is awaited, and the bridge foundation construction device 4 completes the construction of the foundation, and the bridge construction device can complete the construction of the bridge foundation, the pier and the beam.
本发明的优点:架桥装置可以施工桥梁基础,也可以架设桥梁;桥梁基础分段预制,分段下沉,不需要围堰,施工简单、施工周期短。The invention has the advantages that the bridging device can construct the bridge foundation or the bridge; the bridge foundation is prefabricated in sections, the section is sunken, no cofferdam is needed, the construction is simple, and the construction period is short.
附图说明DRAWINGS
图1是由架桥机1、移动轨道2、移动吊机3、施工时底部带有链刀的桥梁基础6的施工装置4-1和移动支撑装置5组成的造桥装置的结构示意图;1 is a schematic structural view of a bridge-building device composed of a bridge machine 1, a moving rail 2, a mobile crane 3, a construction device 4-1 of a bridge foundation 6 with a chain cutter at the bottom during construction, and a mobile support device 5;
图2是由后端支撑1-1、中部支撑1-2、前端支撑1-3、后端支撑1-1底部的行走装置1-1-1、中部支撑1-2的行走装置1-2-1、前端支撑1-3底部的行走装置1-3-1、前端支撑1-3底部的顶升支撑装置1-3-2和上部水平移动的起重机1-4组成的架桥机1的结构示意图;2 is a walking device 1-2 having a rear support 1-1, a middle support 1-2, a front end support 1-3, a rear end support 1-1 bottom walking device 1-1-1, and a middle support 1-2 -1, the traveling device 1-3-1 at the bottom of the front end support 1-3, the jacking support device 1-3-2 at the bottom of the front end support 1-3, and the bridge machine 1 composed of the upper horizontally moving crane 1-4 Schematic;
图3是后端升降支撑装置2-1、前端升降支撑装置2-2、前行走支撑装置2-3、行走装置2-3-1、行走装置2-3-2、后行走支撑装置2-4、行走装置2-4-1和行走装置2-4-2组成的移动轨道2的结构示意图;3 is a rear end lifting support device 2-1, a front end lifting support device 2-2, a front walking support device 2-3, a walking device 2-3-1, a traveling device 2-3-2, and a rear walking support device 2 4. A schematic structural view of a moving track 2 composed of a traveling device 2-4-1 and a traveling device 2-4-2;
图4是由顶部起重机3-1、行走装置3-2和行走装置3-3组成的移动吊机3的结构示意图;4 is a schematic structural view of a mobile crane 3 composed of a top crane 3-1, a traveling device 3-2, and a traveling device 3-3;
图5是由固定导向装置4-1-1、链刀动力传动装置4-1-2、弃土处理装置4-1-3和机架4-1-4组成的基础施工装置4-1的结构示意图,也是由装置4-1-2和基础6及链刀11组成的链式挖掘装置12的结构示意图;Figure 5 is a basic construction device 4-1 consisting of a fixed guide 4-1-1, a chain cutter power transmission 4-1-2, a spoil treatment device 4-1-3, and a frame 4-1-4. The structural schematic diagram is also a schematic structural view of the chain excavating device 12 composed of the device 4-1-2 and the foundation 6 and the chain cutter 11;
图6是图5的A向视图,也是底部带刃角的侧面罩10与链刀11组成的链式输送机的结构示意图;Figure 6 is a view in the direction of arrow A of Figure 5, and is also a schematic structural view of a chain conveyor composed of a side cover 10 and a chain cutter 11 at the bottom;
图7是图5的B-B视图,也是施工装置4-1的机架4-1-4的截面视图,也是泥浆管路装置13在机架4-1-4上的泥浆管路13-1的结构示意图;Figure 7 is a BB view of Figure 5, also a cross-sectional view of the frame 4-1-4 of the construction apparatus 4-1, and also the mud line 13-1 of the mud line unit 13 on the frame 4-1-4. Schematic;
图8是图5的C-C视图,也是泥浆管路装置13在基础6底部的泥浆喷嘴13-2的结构示意图;Figure 8 is a C-C view of Figure 5, and is also a schematic structural view of the mud nozzle 13-2 at the bottom of the foundation 6 of the mud pipeline device 13;
图9是链刀11的结构示意图,也是链条11-1和刀具11-2的结构示意图,也是由A十字节11-1-1和B十字节11-1-2组成的链条11-1的十字节的结构示意图,也是链条11-1实现空间弯曲的结构示意图;Figure 9 is a schematic view showing the structure of the chain cutter 11, and is also a schematic structural view of the chain 11-1 and the cutter 11-2, and is also a chain 11 composed of A ten-byte 11-1-1 and B-tenbyte 11-1-2. A schematic diagram of a ten-byte structure of 1 is also a schematic diagram of a structure in which the chain 11-1 realizes space bending;
图10是由固定导向装置4-2-1、旋转装置4-2-2和下降速度控制装置4-2-3的基础施工装置4-2的结构示意图,也是螺旋筒形基础9底部的挖掘刀9-1和输送岩土的螺旋叶片9-2的结构示意图;Figure 10 is a schematic view showing the structure of the foundation construction device 4-2 by the fixed guiding device 4-2-1, the rotating device 4-2-2, and the descending speed controlling device 4-2-3, and also the excavation of the bottom of the spiral cylindrical foundation 9. Schematic diagram of the cutter 9-1 and the spiral blade 9-2 for conveying the rock;
图11是由行走装置5-1和升降支撑装置5-2组成的移动支撑装置5A的结构示意图;Figure 11 is a schematic structural view of a moving support device 5A composed of a traveling device 5-1 and a lifting support device 5-2;
图12是由行走装置5-1、升降支撑装置5-3和临时底座5-4组成移动支撑装置5B的结构示意图,也是移动支撑装置5B是支撑在桥梁基础6上的结构示意图;12 is a schematic structural view of the mobile supporting device 5B composed of the traveling device 5-1, the lifting support device 5-3 and the temporary base 5-4, and is also a schematic structural view of the mobile supporting device 5B supported on the bridge foundation 6;
图13是双桥墩7的造桥装置的结构示意图;Figure 13 is a schematic structural view of a bridge building device of a double pier 7;
图14是已安装好的梁8分别为第m-1梁8、第m-2梁8、……,未安装的梁8分别为第m+1梁8、第m+2梁8、……,第m梁8对应的桥墩7分别为第m桥墩7和第m+1桥墩7,第m-1梁8对应的桥墩7分别为第m-1桥墩7和第m桥墩7,第m+1梁8的桥墩7分别为第m+1桥墩7和第m+2桥墩7,第m桥墩7对应的基础6为第m基础的结构示意图,也是第m桥墩7和第m+1桥墩7已安装好,移动轨道2的后端升降支撑装置2-1支撑在第m桥墩7前端,移动支撑装置5位于靠近第m+1基础的前方,桥梁基础施工装置4-1位于第m+2基础的设定位置的结构示意图;Figure 14 shows that the installed beams 8 are the m-1th beam 8, the m-2th beam 8, ..., and the unmounted beams 8 are the m+1th beam 8, the m+2 beam 8, ... ..., the piers 7 corresponding to the mth beam 8 are the mth pier 7 and the m+1 pier 7, respectively, and the piers 7 corresponding to the m-1th beam 8 are the m-1 pier 7 and the m pier 7, respectively, m The piers 7 of the +1 beam 8 are the m+1th pier 7 and the m+2 pier 7, respectively, and the foundation 6 corresponding to the mth pier 7 is a structural schematic of the mth foundation, and is also the mth pier 7 and the m+1 pier. 7 has been installed, the rear end lifting support device 2-1 of the moving rail 2 is supported at the front end of the mth pier 7, the mobile supporting device 5 is located in front of the m+1th base, and the bridge foundation construction device 4-1 is located at the m+ 2 structural diagram of the basic set position;
图15是架桥机1前端支撑的升降支撑装置1-3-2与第m桥墩7脱离,架桥机1在移动轨道2上向前运动,到达设定位置的结构示意图;Figure 15 is a schematic view showing the structure in which the lifting support device 1-3-2 supported by the front end of the bridge machine 1 is separated from the mth pier 7 and the bridge machine 1 moves forward on the moving rail 2 to reach the set position;
图16是移动轨道2向前运行到达设定位置的结构示意图,也是将第m梁8运至第m-1梁8处,位于架桥机1后部的下方,架桥1机上方的起重机1-4运行至第m梁8的上方的结构示意图;Figure 16 is a structural schematic view of the moving rail 2 running forward to the set position, and also transporting the mth beam 8 to the m-1th beam 8, located below the rear of the bridging machine 1, the crane above the bridge 1 1-4 is a schematic structural view of running above the mth beam 8;
图17是架桥机1上方的起重机1-4将第m梁8吊起的结构示意图;Figure 17 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the mth beam 8;
图18是架桥机1上的起重机1-4使第m梁8下降、第m梁8蹲位并将第m 梁8与第m-1梁8、第m桥墩7和第m+1桥墩7相连的结构示意图;Figure 18 is a crane 1-4 on the bridge machine 1 lowering the mth beam 8, the mth beam 8 and the mth beam 8 and the m-1th beam 8, the mth pier 7, and the m+1th pier 7 connected structure diagram;
图19是将第m+2基础运至第m-1梁8处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m+2基础的上方的结构示意图;Figure 19 is a structure in which the m+2th base is transported to the m-1th beam 8 and is located below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 is moved to the upper part of the m+2 base. schematic diagram;
图20是架桥机1上方的起重机1-4将第m+2基础6吊起,沿着架桥机上方的轨道向前运行的结构示意图;Figure 20 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the m+2 foundation 6 and running forward along the track above the bridge machine;
图21是架桥机1上的起重机1-4使第m+2基础6下降,将第m+2基础6放在第m-1梁8的前端,架桥机1上方的起重机1-4向后方运行,让开第m+2基础6上方的空间的结构示意图;Figure 21 is a view showing that the crane 1-4 on the bridge machine 1 lowers the m+2 base 6, and the m+2 base 6 is placed at the front end of the m-1 beam 8, and the crane 1-4 above the bridge machine 1 Run to the rear, let the structure of the space above the m+2 base 6 be opened;
图22是移动吊机3上的起重机3-1吊起第m+2基础6,沿着移动吊机2上方的轨道向前运行的结构示意图;Figure 22 is a schematic view showing the structure of the crane 3-1 on the mobile crane 3 lifting the m+2 base 6 and moving forward along the track above the mobile crane 2;
图23是移动吊机3沿着移动轨道2向前运行至第m+2基础6设定位置的结构示意图;Figure 23 is a schematic view showing the structure of the mobile crane 3 running forward along the moving rail 2 to the m+2 base 6 setting position;
图24是将第m+2基础6放入桥梁基础施工装置4-1内,移动吊机3将链刀驱动装置4-1-2与第m+2基础6顶部连在一起的结构示意图;Figure 24 is a schematic view showing the structure in which the m+2 base 6 is placed in the bridge foundation construction device 4-1, and the mobile crane 3 connects the chain cutter driving device 4-1-2 and the m+2 base 6 top;
图25是启动桥梁施工装置4-1,第m+2基础下降至设定深度的结构示意图;Figure 25 is a schematic view showing the structure of the starting bridge construction device 4-1, the m+2 base is lowered to the set depth;
图26是将第m+2螺旋筒形基础9运至第m-1梁8处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m+2螺旋筒形基础9的上方的结构示意图;Figure 26 is the transport of the m+2 spiral cylindrical foundation 9 to the m-1th beam 8, below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 runs to the m+2 spiral Schematic diagram of the structure above the cylindrical foundation 9;
图27是架桥机1上方的起重机1-4将第m+2螺旋筒形基础9吊起,沿着架桥机1上方的轨道向前运行的结构示意图;Figure 27 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the m+2 spiral cylindrical foundation 9 and running forward along the track above the bridge machine 1;
图28是架桥机1上的起重机1-4使第m+2螺旋筒形基础9下降,将第m+2螺旋筒形基础9放在第m-1梁8的前端,架桥机1上方的起重机1-4向后方运行,让开第m+2螺旋筒形基础9上方的空间的结构示意图;Figure 28 is a view showing that the crane 1-4 on the bridge machine 1 lowers the m+2 spiral cylindrical foundation 9, and the m+2 spiral cylindrical foundation 9 is placed at the front end of the m-1 beam 8, the bridge machine 1 The upper crane 1-4 runs backwards to allow a schematic view of the space above the m+2 spiral cylindrical foundation 9;
图29是移动吊机3上的起重机3-1吊起第m+2螺旋筒形基础9,沿着移动吊机2上方的轨道向前运行的结构示意图;Figure 29 is a schematic view showing the structure of the crane 3-1 on the mobile crane 3 lifting the m+2 spiral cylindrical foundation 9 and moving forward along the track above the mobile crane 2;
图30是移动吊机3沿着移动轨道2向前运行至第m+2螺旋筒形基础9设定位置的结构示意图;Figure 30 is a schematic view showing the structure in which the mobile crane 3 is moved forward along the moving rail 2 to the set position of the m+2 spiral cylindrical foundation 9;
图31是将第m+2螺旋筒形基础9放入桥梁基础施工装置4-2内,移动吊机3将旋转装置4-2-2与第m+2螺旋筒形基础9顶部连在一起的结构示意图;Figure 31 is a view in which the m+2 spiral cylindrical foundation 9 is placed in the bridge foundation construction device 4-2, and the mobile crane 3 connects the rotating device 4-2-2 with the top of the m+2 spiral cylindrical foundation 9. Schematic diagram of the structure;
图32是启动桥梁施工装置4-2,第m+2螺旋筒形基础9下降至设定深度的结构示意图;Figure 32 is a schematic structural view showing the start of the bridge construction device 4-2, the m+2 spiral cylindrical foundation 9 is lowered to a set depth;
图33是移动轨道2的后端升降支撑装置2-1脱离第m桥墩7,前端升降支撑装置2-2脱离地面或水底的结构示意图;Figure 33 is a schematic view showing the structure in which the rear end lifting support device 2-1 of the moving rail 2 is separated from the mth bridge 7 and the front end lifting support device 2-2 is separated from the ground or the water bottom;
图34是移动轨道2向前运行至设定位置,后端升降支撑装置2-1支撑伸出,前端升降支撑装置2-2支撑伸出的结构示意图;Figure 34 is a schematic view showing the structure in which the moving rail 2 is moved forward to the set position, the rear end lifting support device 2-1 is supported and extended, and the front end lifting support device 2-2 is supported and extended;
图35是移动支撑装置5移至靠近位于第m+2基础位置的桥梁基础施工装置4-1的后方,移动吊机3运行至桥梁基础施工装置4-1的上方,移动轨道2的前行走支撑装置2-3-1与桥梁基础施工装置4-1脱离的结构示意图;Figure 35 is a view in which the mobile supporting device 5 is moved to the rear of the bridge foundation construction device 4-1 located at the m+2 base position, and the mobile crane 3 is moved above the bridge foundation construction device 4-1 to move the track 2 forward. A schematic structural view of the support device 2-3-1 being separated from the bridge foundation construction device 4-1;
图36是移动吊机3上方的起重机3-1将桥梁基础施工装置4-1吊起的结构示意图;Figure 36 is a schematic view showing the structure of the crane 3-1 above the mobile crane 3 lifting the bridge foundation construction device 4-1;
图37是移动吊机3带着桥梁基础施工装置4-1在移动轨道2上向前运行至第m+3基础上方,移动吊机3上的起重机3-1使桥梁基础装置4-1在第m+3位置准确蹲位的结构示意图;Figure 37 is a mobile crane 3 with a bridge foundation construction device 4-1 running forward on the moving rail 2 to the top of the m+3 base, and the crane 3-1 on the mobile crane 3 causes the bridge foundation device 4-1 to Schematic diagram of the exact clamping position of the m+3 position;
图38是移动支撑装置5移至靠近第m+2基础的前方的结构示意图;Figure 38 is a schematic view showing the structure of the mobile supporting device 5 moved to the front of the m+2 base;
图39是第m+2桥墩7运至第m-1梁8处,架桥机1上方的起重机1-4运行至第m+2桥墩7的上方的结构示意图;Figure 39 is a schematic view showing the structure of the m+2 pier 7 being transported to the m-1th beam 8 and the crane 1-4 above the bridge machine 1 running above the m+2 pier 7;
图40是架桥机1上方的起重机1-4将第m+2桥墩7吊起,行走至第m梁8前端位置的结构示意图;Figure 40 is a schematic view showing the structure of the crane 1-4 above the bridge machine 1 lifting the m+2 pier 7 and walking to the front end of the m-th beam 8;
图41是架桥机1上方的起重机1-4向后方运行,移动吊机3沿着移动吊机2上方的轨道向前运行至第m+2桥墩7上方的结构示意图;Figure 41 is a schematic view showing the structure of the crane 1-4 above the bridge crane 1 running backward, and the moving crane 3 running forward along the track above the moving crane 2 to the m+2 pier 7;
图42是移动吊机3上方后部的起重机3-1吊起第m+2桥墩7后部移至移动吊机3的前部的结构示意图;Figure 42 is a schematic view showing the structure in which the crane 3-1 at the rear of the mobile crane 3 is lifted from the rear of the m+2 pier 7 to the front of the mobile crane 3;
图43是移动吊机3带着第m+2桥墩7通过向前运行至第m+2基础的上方,将第m+2桥墩7放在第m+2基础上并准确定位固连成一体的结构示意图。Figure 43 is a mobile crane 3 with the m+2 pier 7 running forward to the top of the m+2 base, placing the m+2 pier 7 on the m+2 base and accurately positioning and solidifying into one Schematic diagram of the structure.
图中的1是造桥装置的架桥机;1-1是架桥机的后端支撑;1-1-1是架桥机的后端支撑1-1底部的行走装置;1-2是架桥机的中部支撑;1-2-1是架桥机的中部支撑1-2的行走装置;1-3是架桥机的前端支撑;1-3-1是架桥机的前端支撑1-3底部的行走装置;1-3-2是前端支撑1-3底部的顶升支撑装置;1-4是架桥机 1的上部的起重机;2是造桥装置的移动轨道;2-1是移动轨道2的后端设有的后端升降支撑装置,支撑在桥墩7上;2-2是移动轨道2前端设有的前端升降支撑装置,支撑在地面或水底上;2-3是前行走支撑装置;2-3-1是前行走支撑装置2-3上的行走装置,移动轨道2通过行走装置2-3-1从一个位置运行至另一位置;2-3-2是前行走支撑装置2-3从一个位置运行至另一位置的行走装置;2-4是后行走支撑装置;2-4-1是后行走支撑装置2-4上的行走装置,移动轨道2通过行走装置2-4-1从一个位置运行至另一位置;2-4-2是后行走支撑装置2-4从一个位置运行至另一位置的行走装置;3是造桥装置的移动吊机;3-1是移动吊机的顶部起重机;3-2是移动吊机3的底部后端的行走装置;3-3是移动吊机3的底部前端和中间的在移动轨道2上运行的行走装置;4是造桥装置的桥梁基础施工装置;4-1是施工时底部带有链刀的桥梁基础6的施工装置,包括固定导向装置4-1-1、链刀动力传动装置4-1-2、弃土处理装置4-1-3和机架4-1-4;4-1-1是组成装置4-1的固定导向装置;4-1-2是组成装置4-1的链刀动力传动装置;4-1-3是组成装置4-1的弃土处理装置;4-1-4是组成装置4-1的机架;4-2是施工时底部带有挖掘刀的螺旋筒形基础9的施工装置,包括固定导向装置4-2-1、旋转装置4-2-2和下降速度控制装置4-2-3;4-2-1是组成装置4-2的固定导向装置;4-2-2是组成装置4-2的旋转装置;4-2-3是组成装置4-2的螺旋筒形基础9的下降速度控制装置;5是造桥装置的移动支撑装置,底部支撑有两种结构5A和5B;5A是支撑在地面或水底(包括水中船)的移动支撑装置,由行走装置5-1和升降支撑装置5-2组成;5B是支撑在桥梁基础6上,但在此基础6架设桥墩7时,与桥墩7不干涉的移动支撑装置,由行走装置5-1、升降支撑装置5-3和支持底座5-4组成;5-1是移动支撑装置5在移动轨道2上运行的行走装置;5-2是移动支撑装置5A的底部支撑在地面或水底时其顶部是移动轨道3的升降支撑装置;5-3是移动支撑装置5B的底部支撑在桥梁基础6上的升降支撑装置;5-4是移动支撑装置5B中临时固定于基础的支持底座;6是施工时底部带有链刀的桥梁基础;7是桥墩;8是梁;9是施工时底部带有挖掘刀的螺旋筒形基础,包括底部挖掘刀9-1和螺旋叶片9-2;9-1是螺旋筒形基础9的底部挖掘刀;9-2是输送岩土的螺旋叶片;10是底部带刃角的桥梁基础6的侧面罩;11是挖掘岩土的链刀,由链条11-1和固定于链条11-1上的刀具11-2组成;11-1是组成链刀11的链条;11-1-1是组成链 条十字节的A十字节;11-1-2是组成链条十字节的B十字节;11-2是组成链刀11的刀具。12是链式挖掘装置,由装置4-1-2和桥梁基础6及链刀11组成;13是泥浆管路装置;13-1是装置4-1中的机架4-1-4上的泥浆管路;13-2是桥梁基础6底部上的泥浆喷嘴。1 is the bridging machine of the bridge building device; 1-1 is the rear end support of the bridging machine; 1-1-1 is the running device at the bottom of the rear end support 1-1 of the bridging machine; The middle support of the bridge machine; 1-2-1 is the walking device of the middle support of the bridge machine 1-2; 1-3 is the front support of the bridge machine; 1-3-1 is the front support of the bridge machine 1 -3 at the bottom of the walking device; 1-3-2 is the top support of the front end support 1-3; 1-4 is the crane of the upper part of the bridge machine 1; 2 is the moving track of the bridge building; 2-1 It is a rear end lifting support device provided at the rear end of the moving rail 2, supported on the pier 7; 2-2 is a front end lifting support device provided at the front end of the moving rail 2, supported on the ground or the water bottom; 2-3 is the front Walking support device; 2-3-1 is the walking device on the front walking support device 2-3, the moving track 2 is moved from one position to another through the walking device 2-3-1; 2-3-2 is walking ahead The supporting device 2-3 runs from one position to another; the 2-4 is the rear walking support device; 2-4-1 is the walking device on the rear walking support device 2-4, and the moving track 2 passes the running device 2-4-1 runs from one location Another position; 2-4-2 is a running device for the rear walking support device 2-4 to run from one position to another; 3 is a mobile crane for the bridge building device; 3-1 is a top crane for the mobile crane; 3-2 is a walking device at the bottom rear end of the mobile crane 3; 3-3 is a bottom front end of the mobile crane 3 and a running device running on the moving rail 2 in the middle; 4 is a bridge foundation construction device of the bridge building device; 4-1 is the construction device of the bridge foundation 6 with a chain knife at the bottom of the construction, including the fixed guide 4-1-1, the chain cutter power transmission 4-1-2, the spoil disposal device 4-1-3 and Rack 4-1-4; 4-1-1 is a fixed guide device constituting device 4-1; 4-1-2 is a chain cutter power transmission device constituting device 4-1; 4-1-3 is a component device a spoil disposal device of 4-1; 4-1-4 is a frame constituting the device 4-1; 4-2 is a construction device of a spiral cylindrical foundation 9 with a digging knife at the bottom during construction, including a fixed guide 4 -2-1, rotating device 4-2-2 and descending speed control device 4-2-3; 4-2-1 is a fixed guiding device for component device 4-2; 4-2-2 is component device 4-2 Rotating device; 4-2-3 is a spiral barrel that constitutes device 4-2 The descending speed control device of the foundation 9; 5 is a mobile supporting device of the bridge building device, the bottom supports two structures 5A and 5B; 5A is a mobile supporting device supported on the ground or the water bottom (including the water boat), and the traveling device 5- 1 and the lifting support device 5-2; 5B is supported on the bridge foundation 6, but when the foundation 6 is provided with the pier 7, the mobile supporting device does not interfere with the pier 7, the traveling device 5-1, the lifting support device 5 -3 and support base 5-4; 5-1 is a mobile support device 5 running on the moving track 2; 5-2 is the bottom of the mobile support device 5A supported on the ground or underwater, the top is a moving track 3 Lifting support device; 5-3 is a lifting support device supported by the bottom of the mobile supporting device 5B on the bridge foundation 6; 5-4 is a supporting base temporarily fixed to the foundation in the moving supporting device 5B; The bridge foundation of the chain cutter; 7 is the pier; 8 is the beam; 9 is the spiral cylindrical foundation with the excavation knife at the bottom during construction, including the bottom excavation knife 9-1 and the spiral blade 9-2; 9-1 is a spiral cylinder Bottom excavation knives for foundation 9; 9-2 is spiral blades for conveying geotechnical 10 is a side cover of the bridge foundation 6 with a bottomed edge; 11 is a chain cutter for excavating the earth, consisting of a chain 11-1 and a cutter 11-2 fixed to the chain 11-1; 11-1 is a chain cutter 11 chain; 11-1-1 is A ten bytes constituting the chain ten bytes; 11-1-2 is B ten bytes constituting the chain ten bytes; 11-2 is a cutter constituting the chain cutter 11. 12 is a chain excavation device consisting of the device 4-1-2 and the bridge foundation 6 and the chain cutter 11; 13 is a mud pipeline device; 13-1 is the frame 4-1-4 in the device 4-1 Mud line; 13-2 is the mud nozzle on the bottom of the bridge foundation 6.
具体实施方式detailed description
造桥装置包括架桥机1、移动轨道2、移动吊机3和桥梁基础施工装置4,架桥机1设有后端支撑1-1、中部支撑1-2和前端支撑1-3,后端支撑1-1和中部支撑1-2的底部分别设有行走装置1-1-1和行走装置1-2-1,前端支撑1-3的底部设有行走装置1-3-1,行走装置1-1-1和行走装置1-2-1在已架设的梁上运行,行走装置1-3-1在移动轨道2上运行,前端支撑1-3还设有升降支撑装置1-3-2,架桥机1的上部设有的起重机1-4,架桥机1起重时或移动轨道2运行时升降支撑装置1-3-2支撑在桥墩上;架桥机1的功能:一是架梁;二是将从已架设的梁上运来的基础或桥墩吊起放在已架好的梁的前端;移动轨道2的后端设有后端升降支撑装置2-1,后端升降支撑装置2-1的底部支撑在桥墩上;移动轨道2的前端设有前端升降支撑装置2-2,前端升降支撑装置2-2的底部支撑在地面或水底;移动轨道2移动时,后端升降支撑装置2-1脱离桥墩,前端升降支撑装置2-2脱离地面或水底,移动轨道2的中部分别在桥墩和桥梁基础施工装置4上移动;当架桥机1在移动轨道2上运行时,移动轨道2的中部和后部支撑在桥墩上;当移动吊机3带着基础或桥墩在移动轨道2上运行时,移动轨道2的中部和后部也支撑在桥墩上,移动轨道2的前部支撑在桥梁基础施工装置4上。移动吊机3的顶部设有轨道,轨道上设有顶部起重机3-1,顶部起重机3-1通过轨道在移动吊机3内从前或后部运行至后或前部;移动吊机3的底部后端设有行走装置3-2,行走装置3-2有两种结构:一仅在已建梁上行走,二在已建梁上和移动轨道2上均能行走;移动吊机3的底部前端和中间设有在移动轨道2上运行的行走装置3-3,移动吊机3将预制的桥梁基础放入桥梁基础施工装置4内,在桥梁基础施工装置4内完成桥梁基础的施工;桥梁基础施工装置4的底部支撑在地面或水底时,桥梁基础施工装置4也是移动轨道2的支撑;移动吊机3将预制的桥墩放在施工好的桥梁基础上方,移动吊机3将已完成桥梁基础施工的桥梁基础施工装置4移至等待桥梁基础施工的位置;桥梁基础施工装置4完成对基础的施工,造桥装置能 完成桥梁基础、桥墩和梁的施工。The bridge building device comprises a bridge machine 1, a moving rail 2, a mobile crane 3 and a bridge foundation construction device 4. The bridge machine 1 is provided with a rear end support 1-1, a middle support 1-2 and a front end support 1-3, and thereafter The bottom of the end support 1-1 and the middle support 1-2 are respectively provided with a running device 1-1-1 and a traveling device 1-2-1, and the bottom of the front end support 1-3 is provided with a walking device 1-3-1, walking The device 1-1-1 and the traveling device 1-2-1 are operated on the erected beam, the traveling device 1-3-1 is operated on the moving rail 2, and the front end support 1-3 is further provided with the lifting support device 1-3. -2, the crane 1-4 is provided on the upper part of the bridge machine 1, and the lifting support device 1-3-2 is supported on the pier when the bridge machine 1 is hoisting or when the moving rail 2 is running; the function of the bridge machine 1 is: The first is to erect the beam; the second is to lift the foundation or pier from the erected beam to the front end of the framed beam; the rear end of the moving track 2 is provided with the rear end lifting support device 2-1, and the rear end is lifted and lowered. The bottom of the supporting device 2-1 is supported on the pier; the front end of the moving rail 2 is provided with a front end lifting support device 2-2, and the bottom of the front end lifting support device 2-2 is supported on the ground or the bottom; when the moving rail 2 moves, the rear end Rise The support device 2-1 is separated from the bridge pier, the front end lifting support device 2-2 is separated from the ground or the water bottom, and the middle portion of the moving rail 2 is respectively moved on the pier and the bridge foundation construction device 4; when the bridge machine 1 is running on the moving rail 2, The middle and rear portions of the moving rail 2 are supported on the pier; when the mobile crane 3 is running on the moving rail 2 with the foundation or the pier, the middle and rear portions of the moving rail 2 are also supported on the pier, moving the front of the rail 2 The support is supported on the bridge foundation construction device 4. The top of the mobile crane 3 is provided with a rail on which the top crane 3-1 is provided, and the top crane 3-1 runs from the front or the rear to the rear or front portion in the mobile crane 3 through the rail; the bottom of the mobile crane 3 The rear end is provided with a walking device 3-2. The walking device 3-2 has two structures: one can only walk on the existing beam, and the other can walk on the existing beam and the moving rail 2; the bottom of the mobile crane 3 is moved. The front end and the middle are provided with a running device 3-3 running on the moving rail 2, and the mobile crane 3 puts the prefabricated bridge foundation into the bridge foundation construction device 4, and completes the construction of the bridge foundation in the bridge foundation construction device 4; When the bottom of the foundation construction device 4 is supported on the ground or the bottom of the water, the bridge foundation construction device 4 is also supported by the moving rail 2; the mobile crane 3 places the prefabricated pier above the constructed bridge foundation, and the mobile crane 3 will complete the bridge. The bridge foundation construction device 4 for foundation construction is moved to a position waiting for the foundation construction of the bridge; the bridge foundation construction device 4 completes the construction of the foundation, and the bridge assembly device can complete the construction of the bridge foundation, the pier and the beam.
所述的移动轨道2中间的底部设有前行走支撑装置2-3和后行走支撑装置2-4,前行走支撑装置2-3设有行走装置2-3-1,后行走支撑装置2-4设有行走装置2-4-1,后行走支撑装置2-4支撑在桥墩上,前行走支撑装置2-3支撑在桥梁基础施工装置4上,当后端升降支撑装置2-1脱离桥墩,前端升降支撑装置2-2脱离地面或水底时,移动轨道2通过行走装置2-3-1和行走装置2-4-1从一个位置运行至另一位置。The bottom of the moving rail 2 is provided with a front walking support device 2-3 and a rear walking support device 2-4, and the front walking support device 2-3 is provided with a walking device 2-3-1, and the rear walking supporting device 2 4, the walking device 2-4-1 is provided, the rear walking support device 2-4 is supported on the bridge pier, the front walking support device 2-3 is supported on the bridge foundation construction device 4, and the rear end lifting support device 2-1 is separated from the pier When the front end lifting support device 2-2 is separated from the ground or the bottom of the water, the moving rail 2 is moved from one position to another by the traveling device 2-3-1 and the traveling device 2-4-1.
所述的前行走支撑装置2-3设有行走装置2-3-2,后行走支撑装置2-4设有行走装置2-4-2,移动轨道2设有行走装置2-3-2和行走装置2-4-2运行的轨道,前行走支撑装置2-3通过行走装置2-3-2从一个位置运行至另一位置,后行走支撑装置2-4通过行走装置2-4-2从一个位置运行至另一位置。The front travel support device 2-3 is provided with a travel device 2-3-2, the rear travel support device 2-4 is provided with a travel device 2-4-2, and the mobile track 2 is provided with a travel device 2-3-2 and The track on which the traveling device 2-4-2 operates, the front walking support device 2-3 runs from one position to another through the traveling device 2-3-2, and the rear walking support device 2-4 passes the walking device 2-4-2 Run from one location to another.
所述的造桥装置还包括在桥梁基础施工装置4的后面设有移动支撑装置5,移动支撑装置5的底部支撑有两种结构:一是支撑在地面或水底包括水中船,二是支撑在桥梁基础上;移动支撑装置5的上部是移动轨道2的支撑,移动支撑装置5设有在移动轨道2上运行的行走装置5-1,当移动支撑装置5底部脱离支撑物时,通过行走装置5-1从一个位置行走至另一位置。The bridge building device further includes a moving support device 5 disposed behind the bridge foundation construction device 4. The bottom of the mobile support device 5 supports two structures: one is supported on the ground or the bottom includes a water boat, and the other is supported at On the basis of the bridge; the upper part of the mobile supporting device 5 is the support of the moving rail 2, and the moving supporting device 5 is provided with the running device 5-1 running on the moving rail 2, and when the bottom of the moving supporting device 5 is separated from the support, the traveling device is passed 5-1 Walk from one position to another.
所述的已安装好的梁分别为第m-1梁、第m-2梁、第m-3梁、……,未安装的梁分别为第m+1梁、第m+2梁、第m+3梁、……,第m梁对应的桥墩分别为第m桥墩和第m+1桥墩,第m-1梁对应的桥墩分别为第m-1桥墩和第m桥墩,第m+1梁的桥墩分别为第m+1桥墩和第m+2桥墩,第m桥墩对应的基础为第m基础,设第m桥墩和第m+1桥墩已安装好,移动轨道2的后端升降支撑装置2-1支撑在第m桥墩前端,移动支撑装置5位于靠近第m+1基础的前方,桥梁基础施工装置4位于第m+2基础的设定位置。The installed beams are the m-1th beam, the m-2th beam, the m-3th beam, ..., and the unmounted beams are the m+1th beam, the m+2 beam, and the The m+3 beam, ..., the corresponding pier of the mth beam is the mth pier and the m+1th pier, respectively, and the corresponding piers of the m-1th beam are the m-1 pier and the mth pier, respectively, m+1 The bridge piers of the beam are the m+1th pier and the m+2 pier, respectively. The foundation corresponding to the mth pier is the mth foundation. The mth pier and the m+1 pier are installed, and the rear support of the moving track 2 is supported. The device 2-1 is supported at the front end of the mth pier, the moving support device 5 is located in front of the m+1th base, and the bridge foundation construction device 4 is located at the set position of the m+2th base.
所述的第m梁的施工法有如下步骤:The construction method of the m-th beam has the following steps:
1)将架桥机1前端支撑1-3的升降支撑装置与第m桥墩脱离;1) detaching the lifting support device of the front end support 1-3 of the bridge machine 1 from the mth bridge pier;
2)架桥机1的后端支撑1-1和中部支撑1-2的行走装置在已架设的梁上向前运行,前端支撑1-3的行走装置1-3-1在移动轨道2上向前运动,到达设定位置,将架桥机1前端支撑1-3的升降支撑装置1-3-2支撑在第m+1桥墩的前部,使架桥机1的前端支撑1-3的行走装置1-3-1脱离移动轨道2;2) The traveling device of the rear end support 1-1 and the middle support 1-2 of the bridging machine 1 runs forward on the erected beam, and the running device 1-3-1 of the front end support 1-3 is on the moving rail 2 Moving forward, reaching the set position, supporting the lifting support device 1-3-2 of the front end support 1-3 of the bridging machine 1 at the front of the m+1th pier, so that the front end of the bridging machine 1 supports 1-3 The walking device 1-3-1 is separated from the moving track 2;
3)移动轨道2向前运行到达设定位置,移动轨道2的后行走支撑装置2-4从第m桥墩运行至第m+1桥墩的前部,并支撑在第m+1桥墩上;3) moving rail 2 forwardly reaches the set position, and the rear travel support device 2-4 of the moving rail 2 runs from the mth pier to the front of the m+1th pier and is supported on the m+1th pier;
4)将第m梁运至第m-1梁处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m梁的上方;4) transporting the mth beam to the m-1th beam, below the rear of the bridging machine 1, and the crane 1-4 above the bridging machine 1 runs above the mth beam;
5)架桥机1上方的起重机1-4将第m梁吊起,沿着架桥机1上方的轨道向前运行至第m桥墩和第m+1桥墩之间的设定位置;5) The crane 1-4 above the bridge machine 1 lifts the mth beam and runs forward along the track above the bridge machine 1 to a set position between the mth pier and the m+1 pier;
6)架桥机1上的起重机1-4使第m梁下降,第m梁蹲位并满足设计安装要求;6) The crane 1-4 on the bridge machine 1 lowers the mth beam, and the mth beam is clamped and meets the design and installation requirements;
7)将第m梁与第m-1梁、第m桥墩和第m+1桥墩相连;7) connecting the mth beam to the m-1th beam, the mth pier and the m+1th pier;
重复上述步骤完成其余梁的安装。Repeat the above steps to complete the installation of the remaining beams.
所述的第m+2基础有A和B两种结构:The m+2 base has two structures: A and B:
A)第m+2基础是施工时底部带有链刀的基础,链刀仅有挖掘基础底部的岩土;所述的桥梁基础施工装置4-1包括固定导向装置4-1-1、链刀动力传动装置4-1-2、弃土处理装置4-1-3和机架4-1-4;A) The m+2 foundation is the foundation with a chain cutter at the bottom of the construction. The chain cutter only excavates the rock at the bottom of the foundation; the bridge foundation construction device 4-1 includes fixed guides 4-1-1, chain Knife power transmission device 4-1-2, spoil treatment device 4-1-3 and frame 4-1-4;
B)第m+2基础是底部带有刀具的螺旋筒形基础,刀具仅有挖掘螺旋筒形基础底部的环状岩土;所述的桥梁基础施工装置4-2包括固定导向装置4-2-1、旋转装置4-2-2和下降速度控制装置4-2-3。B) The m+2 base is a spiral cylindrical foundation with a cutter at the bottom, and the cutter only has the annular rock at the bottom of the spiral cylindrical foundation; the bridge foundation construction device 4-2 includes a fixed guide 4-2 - 1, rotating device 4-2-2 and falling speed control device 4-2-3.
所述的第m+2基础是底部带有刀具的螺旋筒形基础,或者是施工时底部带有链刀的基础,具体的施工法有如下步骤:The m+2 base is a spiral cylindrical foundation with a cutter at the bottom, or a base with a chain cutter at the bottom during construction. The specific construction method has the following steps:
1)将第m+2基础运至第m-1梁处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m+2基础的上方;1) transporting the m+2 base to the m-1 beam, below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 runs above the m+2 base;
2)架桥机1上方的起重机1-4将第m+2基础吊起,沿着架桥机1上方的轨道向前运行至第m-1梁前方的设定位置;2) The crane 1-4 above the bridge machine 1 lifts the m+2 foundation and runs forward along the track above the bridge machine 1 to the set position in front of the m-1 beam;
3)架桥机1上的起重机1-4使第m+2基础下降,将第m+2基础放在第m-1梁的前端;3) The crane 1-4 on the bridge machine 1 lowers the m+2 base, and places the m+2 base on the front end of the m-1th beam;
4)架桥机1上方的起重机1-4向后方运行,让开第m+2基础上方的空间;4) The crane 1-4 above the bridging machine 1 runs backwards, allowing the space above the m+2 base to be opened;
5)移动吊机3在移动轨道2上向后运行,使移动吊机3上方的起重机3-1到达第m+2基础上方设定位置;5) The mobile crane 3 runs backward on the moving rail 2, so that the crane 3-1 above the mobile crane 3 reaches the set position above the m+2 base;
6)移动吊机3上的顶部起重机3-1吊起第m+2基础,沿着移动吊机3上方 的轨道向前运行,使顶部起重机3-1和第m+2基础从移动吊机3内的后部移动至前部;移动吊机3沿着移动轨道2向前运行至第m+2基础设定位置,将第m+2基础放入桥梁基础施工装置4内;6) The top crane 3-1 on the mobile crane 3 lifts the m+2 base and runs forward along the track above the mobile crane 3, making the top crane 3-1 and the m+2 base from the mobile crane The rear part of 3 moves to the front; the mobile crane 3 runs forward along the moving rail 2 to the m+2 basic setting position, and the m+2 foundation is placed into the bridge foundation construction device 4;
7)移动吊机3将螺旋筒形基础旋转驱动装置4-2或者链刀驱动装置4-1与第m+2基础顶部连在一起;7) the mobile crane 3 connects the spiral cylindrical basic rotary driving device 4-2 or the chain cutter driving device 4-1 with the m+2 base top;
8)启动桥梁基础施工装置4,第m+2基础下降至设定深度,完成施工;8) Start the bridge foundation construction device 4, the m+2 foundation is lowered to the set depth, and the construction is completed;
重复上述步骤完成其余基础的安装。Repeat the above steps to complete the rest of the basic installation.
所述的桥梁基础施工装置4从第m+2基础位置移至第m+3基础位置的施工法分如下步骤:The construction method of the bridge foundation construction device 4 moving from the m+2 base position to the m+3 base position is as follows:
1)将移动轨道2的后端升降支撑装置2-1脱离第m桥墩,前端升降支撑装置2-2脱离地面或水底;1) disengaging the rear end lifting support device 2-1 of the moving rail 2 from the mth bridge pier, and the front end lifting support device 2-2 is separated from the ground or the water bottom;
2)移动轨道2向前运行至设定位置,将后端升降支撑装置2-1支撑在第m+1桥墩的前端,将前端升降支撑装置2-2支撑在第m+3基础位置前方的地面或水底;2) The moving rail 2 is moved forward to the set position, the rear end lifting support device 2-1 is supported at the front end of the m+1th pier, and the front end lifting support device 2-2 is supported in front of the m+3 basic position. Ground or underwater;
3)将移动支撑装置5从靠近第m+1基础的前方,移至靠近位于第m+2基础位置的桥梁基础施工装置4的后方;3) moving the mobile supporting device 5 from the front side close to the m+1th base to the rear of the bridge foundation construction device 4 located at the m+2 base position;
4)移动吊机3运行至桥梁基础施工装置4的上方,将桥梁基础施工装置4与第m+2桥梁基础脱离,将移动轨道2的前行走支撑装置2-3与桥梁基础施工装置4脱离;4) The mobile crane 3 runs above the bridge foundation construction device 4, disengages the bridge foundation construction device 4 from the m+2 bridge foundation, and disengages the front travel support device 2-3 of the moving rail 2 from the bridge foundation construction device 4. ;
5)移动吊机3上方的顶部起重机3-1将桥梁基础施工装置4吊起,移动吊机3带着桥梁基础施工装置4在移动轨道2上向前运行至第m+3基础上方;5) The top crane 3-1 above the mobile crane 3 lifts the bridge foundation construction device 4, and the mobile crane 3 carries the bridge foundation construction device 4 on the moving rail 2 to move forward to the m+3 base;
6)移动吊机3上的顶部起重机3-1使桥梁基础施工装置4下降,并使桥梁基础施工装置4在第m+3位置准确蹲位;6) The top crane 3-1 on the mobile crane 3 lowers the bridge foundation construction device 4 and causes the bridge foundation construction device 4 to be accurately clamped at the m+3 position;
7)移动轨道2的前行走支撑装置2-3移动至桥梁基础施工装置4位置,将移动轨道2的前行走支撑装置2-3支撑在桥梁基础施工装置4上;7) The front travel support device 2-3 of the moving rail 2 is moved to the position of the bridge foundation construction device 4, and the front travel support device 2-3 of the moving rail 2 is supported on the bridge foundation construction device 4;
8)将移动支撑装置5从第m+2基础的后方移至靠近第m+2基础的前方。8) Move the mobile support device 5 from the rear of the m+2 base to the front of the m+2 base.
所述的第m梁和第m+2基础均已施工完成,移动轨道2的后端升降支撑装置2-1和架桥机1前端支撑1-3的升降支撑装置1-3-2都支撑在第m+1桥墩上,移动支撑装置5支撑在靠近第m+2基础前方的地面或水底,桥梁基础施 工装置4位于第m+3基础的设定位置,第m+2桥墩的具体施工法有如下步骤:The m-th beam and the m+2 base have been completed, and the rear end lifting support device 2-1 of the moving rail 2 and the lifting support device 1-3-2 of the front end support 1-3 of the bridging machine 1 are supported. On the m+1th pier, the mobile supporting device 5 is supported on the ground or the water bottom near the front of the m+2 foundation, and the bridge foundation construction device 4 is located at the set position of the m+3 foundation, and the concrete construction of the m+2 pier The method has the following steps:
1)将第m+2桥墩运至第m梁处,位于架桥机1的下方,架桥机1上方的起重机1-4运行至第m+2桥墩的上方;1) transporting the m+2 pier to the mth beam, below the bridge machine 1, and the crane 1-4 above the bridge machine 1 runs above the m+2 pier;
2)架桥机1上方的起重机1-4将第m+2桥墩吊起,并将第m+2桥墩正确的放置在第m梁前端的设定位置;2) The crane 1-4 above the bridge machine 1 lifts the m+2 pier and correctly positions the m+2 pier at the set position of the front end of the mth beam;
3)架桥机1上方的起重机1-4向后方运行,让开第m+2桥墩上方的空间;3) The crane 1-4 above the bridging machine 1 runs backwards, allowing the space above the m+2 pier to be opened;
4)移动吊机3通过底部的行走装置3-2和行走装置3-3向后运行,使移动吊机3上方后部的顶部起重机3-1到达第m+2桥墩上方设定位置;4) The mobile crane 3 runs backward through the bottom traveling device 3-2 and the traveling device 3-3, so that the top crane 3-1 at the upper rear portion of the mobile crane 3 reaches the set position above the m+2 pier;
5)移动吊机3上方后部的顶部起重机3-1将第m+2桥墩吊起,并将第m+2桥墩从移动吊机3的后部移至移动吊机3的前部;5) The top crane 3-1 at the rear of the mobile crane 3 lifts the m+2 pier and moves the m+2 pier from the rear of the mobile crane 3 to the front of the mobile crane 3;
6)移动吊机3带着第m+2桥墩通过底部的行走装置3-2和行走装置3-3向前运行至第m+2基础的上方,将第m+2桥墩放在第m+2基础上并准确定位固连成一体。6) The mobile crane 3 carries the m+2 pier through the bottom of the walking device 3-2 and the running device 3-3 forward to the top of the m+2 base, and the m+2 pier is placed at the m+th 2 Based on the basic positioning and accurate positioning.
重复上述步骤完成其余桥墩的安装。Repeat the above steps to complete the installation of the remaining piers.
下面结合附图进一步描述本发明的技术方案:The technical solution of the present invention is further described below with reference to the accompanying drawings:
如图1~图4所示,造桥装置由架桥机1、移动轨道2、移动吊机3、桥梁基础施工装置4和移动支撑装置5组成,架桥机设有后端支撑1-1、中部支撑1-2和前端支撑1-3,后端支撑1-1和中部支撑1-2的底部分别设有行走装置1-1-1和行走装置1-2-1,前端支撑1-3的底部设有行走装置1-3-1,行走装置1-1-1和行走装置1-2-1在已架设的梁8上运行,行走装置1-3-1在移动轨道2上运行,前端支撑1-3还设有升降支撑装置1-3-2,架桥机1的上部设有水平移动的起重机1-4,架桥机1起重时或移动轨道2运行时升降支撑装置1-3-2支撑在桥墩7上;架桥机1的功能:一是架梁8;二是将从已架设的梁8上运来的基础6或桥墩7吊起放在已架好的梁8的前端;移动轨道2的后端设有后端升降支撑装置2-1,后端升降支撑装置2-1的底部支撑在桥墩7上;移动轨道2的前端设有前端升降支撑装置2-2,前端升降支撑装置2-2的底部支撑在地面或水底;移动轨道2移动时,后端升降支撑装置2-1脱离桥墩7,前端升降支撑装置2-2脱离地面或水底,移动轨道2的中部分别在桥墩7、移动支撑装置5和桥梁基础施工装置4上移动;当架桥机1在移动轨道2上运行时,移动轨道2的中部和后部支撑 在桥墩7上;当移动吊机3带着基础6或桥墩7在移动轨道2上运行时,移动轨道2的中部和后部也支撑在桥墩7上,移动轨道2的中部和前部同时支撑在移动支撑装置5和/或桥梁基础施工装置4上。移动吊机3的顶部设有轨道,轨道上设有起重机3-1,起重机3-1通过轨道在移动吊机3内从前(或后)部运行至后(或前)部;移动吊机3的底部后端设有行走装置3-2,移动吊机3的底部前端和中间设有在移动轨道2上运行的行走装置3-3,移动吊机3将预制的桥梁基础6放入桥梁基础施工装置4内,在桥梁基础施工装置4内完成桥梁基础6的施工;桥梁基础施工装置4的底部支撑在地面或水底时,桥梁基础施工装置4也是移动轨道2的支撑;移动吊机3将预制的桥墩7放在施工好的桥梁基础6上方,移动吊机3将已完成桥梁基础施工的桥梁基础施工装置4移至等待桥梁基础施工的位置;桥梁基础施工装置4完成对基础的施工。As shown in FIG. 1 to FIG. 4, the bridge-building device is composed of a bridge machine 1, a moving rail 2, a mobile crane 3, a bridge foundation construction device 4, and a mobile support device 5. The bridge-building machine is provided with a rear support 1-1. , the central support 1-2 and the front end support 1-3, the bottom end support 1-1 and the bottom support 1-2 are respectively provided with a walking device 1-1-1 and a walking device 1-2-1, and the front end supports 1- The bottom of the 3 is provided with a walking device 1-3-1, the traveling device 1-1-1 and the traveling device 1-2-1 are operated on the erected beam 8, and the running device 1-3-1 is operated on the moving rail 2 The front end support 1-3 is further provided with a lifting support device 1-3-2, and the upper portion of the bridge machine 1 is provided with a horizontally moving crane 1-4, and the lifting support device is used when the bridge machine 1 is hoisting or when the moving rail 2 is running 1-3-2 is supported on the pier 7; the function of the bridge machine 1 is: one is the frame beam 8; the other is that the foundation 6 or the pier 7 transported from the already-mounted beam 8 is hoisted and placed The front end of the beam 8; the rear end of the moving rail 2 is provided with a rear end lifting support device 2-1, the bottom of the rear end lifting support device 2-1 is supported on the pier 7; the front end of the moving rail 2 is provided with a front end lifting support device 2 -2, front end lifting support device 2-2 The support is on the ground or the bottom of the water; when the moving rail 2 moves, the rear end lifting support device 2-1 is separated from the bridge pier 7, the front end lifting support device 2-2 is separated from the ground or the bottom of the water, and the middle portion of the moving rail 2 is respectively at the pier 7, the mobile supporting device 5 and moving on the bridge foundation construction device 4; when the bridge machine 1 is running on the moving rail 2, the middle and rear portions of the moving rail 2 are supported on the pier 7; when the mobile crane 3 carries the foundation 6 or the pier 7 When running on the moving rail 2, the middle and rear portions of the moving rail 2 are also supported on the pier 7, and the middle portion and the front portion of the moving rail 2 are simultaneously supported on the moving support device 5 and/or the bridge foundation construction device 4. The top of the mobile crane 3 is provided with a rail on which the crane 3-1 is arranged, and the crane 3-1 runs from the front (or rear) portion to the rear (or front) portion in the mobile crane 3 through the rail; the mobile crane 3 The bottom rear end is provided with a running device 3-2. The bottom front end of the mobile crane 3 is provided with a running device 3-3 running on the moving rail 2, and the mobile crane 3 places the prefabricated bridge foundation 6 into the bridge foundation. In the construction device 4, the construction of the bridge foundation 6 is completed in the bridge foundation construction device 4; when the bottom of the bridge foundation construction device 4 is supported on the ground or the water bottom, the bridge foundation construction device 4 is also the support of the moving rail 2; the mobile crane 3 will The prefabricated pier 7 is placed above the constructed bridge foundation 6, and the mobile crane 3 moves the bridge foundation construction device 4 that has completed the bridge foundation construction to a position waiting for the bridge foundation construction; the bridge foundation construction device 4 completes the construction of the foundation.
如图5~图10所示,第m+2基础有A和B两种结构:As shown in Figures 5 to 10, the m+2 base has two structures, A and B:
A)第m+2基础是施工时底部带有链刀的基础6,链刀仅有挖掘基础底部的岩土;所述的桥梁基础施工装置4-1包括固定导向装置4-1-1、链刀动力传动装置4-1-2、弃土处理装置4-1-3和机架4-1-4;施工时,机架4-1-4与基础6的顶部连接成一体,装置4-1-2驱动链刀11沿着基础6上的轨道运行,链刀11挖掘基础6底部的岩土,并将已挖掘的岩土带至上方,装置4-1-3将链刀11从基础6底部带上来的岩土与链刀11分离,机架4-1-4随着基础6一起同步下降;A) The m+2 base is the foundation 6 with a chain knife at the bottom of the construction. The chain cutter only has the rock at the bottom of the foundation; the bridge foundation construction device 4-1 includes a fixed guide 4-1-1, Chain cutter power transmission 4-1-2, spoil treatment device 4-1-3 and frame 4-1-4; during construction, the frame 4-1-4 is integrated with the top of the foundation 6, device 4 -1-2 drive chain cutter 11 runs along the track on the foundation 6, the chain cutter 11 excavates the rock at the bottom of the foundation 6, and brings the excavated rock to the top, and the device 4-1-3 takes the chain cutter 11 from The rock soil brought up from the bottom of the foundation 6 is separated from the chain cutter 11, and the frames 4-1-4 are simultaneously descended along with the foundation 6;
B)第m+2基础是底部带有刀具的螺旋筒形基础9,刀具仅有挖掘螺旋筒形基础底部的环状岩土;所述的桥梁基础施工装置(4-2)包括固定导向装置4-2-1、驱动旋转装置4-2-2和下降速度控制装置4-2-3;施工时,驱动旋转装置4-2-2使基础9旋转,通过下降速度控制装置4-2-3控制螺旋筒形基础9的下降速度,使螺旋筒形基础9底部的刀具9-1切削基础9底部的环状岩土,在底部锥面的作用下,将已切削的岩土导入基础9的螺旋叶片9-2内,螺旋叶片9-2将底部已切削的岩土输送至上方,并逐渐下降至设定位置。B) The m+2 base is a spiral cylindrical foundation 9 with a cutter at the bottom, the cutter only has the annular rock at the bottom of the spiral cylindrical foundation; the bridge foundation construction device (4-2) includes a fixed guide 4-2-1, drive rotating device 4-2-2 and descending speed control device 4-2-3; during construction, drive rotating device 4-2-2 rotates base 9, through descending speed control device 4-2- 3 controlling the descending speed of the spiral cylindrical foundation 9, so that the cutter 9-1 at the bottom of the spiral cylindrical foundation 9 cuts the annular rock at the bottom of the foundation 9, and the cut rock is introduced into the foundation under the action of the bottom tapered surface. In the spiral blade 9-2, the spiral blade 9-2 transports the cut rock at the bottom to the upper portion and gradually descends to the set position.
如图11~图12所示,移动支撑装置5的底部支撑有两种结构5A和5B:5A是支撑在地面或水底(包括水中船),5B是支撑在桥梁基础上;移动支撑装置5的上部是移动轨道2的支撑,移动支撑装置5设有在移动轨道上运行的行走装置5-1,当移动支撑装置5底部脱离支撑物时,通过行走装置5-1从一个位置 行走至另一位置,造桥装置能完成桥梁基础6、桥墩7和梁8的施工。As shown in FIG. 11 to FIG. 12, the bottom of the mobile supporting device 5 supports two structures 5A and 5B: 5A is supported on the ground or underwater (including water boat), 5B is supported on the bridge foundation; and the mobile supporting device 5 The upper part is the support of the moving rail 2, and the moving support device 5 is provided with a running device 5-1 running on the moving rail, and when the bottom of the moving supporting device 5 is separated from the support, the traveling device 5-1 walks from one position to another The position, the bridge building device can complete the construction of the bridge foundation 6, the pier 7 and the beam 8.
如图13所示,造桥装置是同时施工双桥墩7,造桥装置的移动轨道2和移动吊机3的纵向宽度超过双桥墩宽度。As shown in Fig. 13, the bridge building device simultaneously constructs the double bridge pier 7, and the longitudinal width of the moving rail 2 and the mobile crane 3 of the bridge building device exceeds the width of the double bridge pier.
如图14~图18所示,第m梁8的施工法有如下步骤:As shown in FIGS. 14 to 18, the construction method of the mth beam 8 has the following steps:
1)将架桥机1前端支撑的升降支撑装置1-3-2与第m桥墩7脱离;1) detaching the lifting support device 1-3-2 supported by the front end of the bridge machine 1 from the mth pier 7;
2)架桥机1的后端支撑1-1的行走装置1-1-1和中部支撑的行走装置1-2-1在已架设的梁8上向前运行,前端支撑1-3的行走装置1-3-1在移动轨道2上向前运动,到达设定位置,将架桥机1前端支撑的升降支撑装置1-3-2支撑在第m+1桥墩7的前部,使架桥机1的前端支撑的行走装置1-3-1脱离移动轨道2;2) The traveling device 1-1-1 of the rear end support 1-1 of the bridge machine 1 and the traveling device 1-2-1 of the middle support run forward on the erected beam 8, and the front end supports the walking of 1-3 The device 1-3-1 moves forward on the moving rail 2 to reach the set position, and supports the lifting support device 1-3-2 supported by the front end of the bridge machine 1 at the front of the m+1th pier 7, so that the frame The traveling device 1-3-1 supported by the front end of the bridge machine 1 is separated from the moving rail 2;
3)移动轨道2向前运行到达设定位置,移动轨道2的后行走支撑装置从第m桥墩7运行至第m+1桥墩7的前部,并支撑在第m+1桥墩7上;3) The moving rail 2 runs forward to reach the set position, and the rear travel support device of the moving rail 2 runs from the mth bridge pier 7 to the front portion of the m+1th pier 7, and is supported on the m+1th pier 7;
4)将第m梁8运至第m-1梁8处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m梁8的上方;4) transporting the mth beam 8 to the m-1th beam 8 below the rear of the bridging machine 1, and the crane 1-4 above the bridging machine 1 runs above the mth beam 8;
5)架桥机1上方的起重机1-4将第m梁8吊起,沿着架桥机1上方的轨道向前运行至第m桥墩7和第m+1桥墩7之间的设定位置;5) The crane 1-4 above the bridge machine 1 lifts the mth beam 8 and travels along the track above the bridge machine 1 to the set position between the mth pier 7 and the m+1 pier 7 ;
6)架桥机1上的起重机1-4使第m梁8下降,第m梁8蹲位并满足设计安装要求;6) The crane 1-4 on the bridge machine 1 lowers the mth beam 8, and the mth beam 8 is clamped and meets the design and installation requirements;
7)将第m梁8与第m-1梁8、第m桥墩7和第m+1桥墩7相连;7) connecting the mth beam 8 with the m-1th beam 8, the mth pier 7 and the m+1th pier 7;
重复上述步骤完成其余梁8的安装。Repeat the above steps to complete the installation of the remaining beams 8.
如图19~图25所示,第m+2基础是施工时底部带有链刀的基础6,具体的施工法有如下步骤:As shown in Fig. 19 to Fig. 25, the m+2 basis is the foundation 6 with a chain knife at the bottom of the construction. The specific construction method has the following steps:
1)将第m+2基础6运至第m-1梁8处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m+2基础6的上方;1) transporting the m+2 base 6 to the m-1th beam 8 at a position below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 is operated above the m+2 base 6;
2)架桥机1上方的起重机1-4将第m+2基础6吊起,沿着架桥机1上方的轨道向前运行至第m-1梁8前方的设定位置;2) The crane 1-4 above the bridge machine 1 lifts the m+2 base 6 and runs forward along the track above the bridge machine 1 to the set position in front of the m-1 beam 8;
3)架桥机1上的起重机1-4使第m+2基础6下降,将第m+2基础6放在第m-1梁8的前端;3) The crane 1-4 on the bridge machine 1 lowers the m+2 base 6 and places the m+2 base 6 at the front end of the m-1 beam 8;
4)架桥机1上方的起重机1-4向后方运行,让开第m+2基础6上方的空间;4) The crane 1-4 above the bridging machine 1 runs backwards, allowing the space above the m+2 base 6 to be opened;
5)移动吊机3在移动轨道2上向后运行,使移动吊机3上方的起重机3-1到 达第m+2基础6上方设定位置;5) The mobile crane 3 is operated backward on the moving rail 2, so that the crane 3-1 above the mobile crane 3 reaches the set position above the m+2 base 6;
6)移动吊机3上的起重机3-1吊起第m+2基础6,沿着移动吊机3上方的轨道向前运行,使起重机3-1和第m+2基础6从移动吊机3内的后部移动至前部;移动吊机3沿着移动轨道2向前运行至第m+2基础6设定位置,将第m+2基础6放入桥梁基础施工装置4-1内;6) The crane 3-1 on the mobile crane 3 lifts the m+2 base 6 and moves forward along the track above the mobile crane 3, so that the crane 3-1 and the m+2 base 6 are moved from the crane The rear part of 3 moves to the front; the mobile crane 3 runs forward along the moving rail 2 to the m+2 base 6 setting position, and the m+2 base 6 is placed in the bridge foundation construction device 4-1. ;
7)移动吊机3将链刀驱动装置4-1-2与第m+2基础6顶部连在一起;7) the mobile crane 3 connects the chain cutter driving device 4-1-2 to the top of the m+2 base 6;
8)启动桥梁施工装置4-1,第m+2基础6下降至设定深度,完成施工;8) Start the bridge construction device 4-1, and the m+2 foundation 6 is lowered to the set depth to complete the construction;
重复上述步骤完成其余基础6的安装。Repeat the above steps to complete the installation of the remaining base 6.
如图26~图32所示,第m+2基础是施工时底部带有挖掘刀的螺旋筒形基础9,具体的施工法有如下步骤:As shown in Fig. 26 to Fig. 32, the m+2 basis is a spiral cylindrical foundation 9 with a digging knife at the bottom during construction. The specific construction method has the following steps:
1)将第m+2基础9运至第m-1梁8处,位于架桥机1后部的下方,架桥机1上方的起重机1-4运行至第m+2基础9的上方;1) transporting the m+2 base 9 to the m-1th beam 8 at a position below the rear of the bridge machine 1, and the crane 1-4 above the bridge machine 1 is operated above the m+2 base 9;
2)架桥机1上方的起重机1-4将第m+2基础9吊起,沿着架桥机1上方的轨道向前运行至第m-1梁8前方的设定位置;2) The crane 1-4 above the bridge machine 1 lifts the m+2 base 9 and runs forward along the track above the bridge machine 1 to the set position in front of the m-1 beam 8;
3)架桥机1上的起重机1-4使第m+2基础9下降,将第m+2基础9放在第m-1梁8的前端;3) The crane 1-4 on the bridge machine 1 lowers the m+2 base 9 and places the m+2 base 9 at the front end of the m-1 beam 8;
4)架桥机1上方的起重机1-4向后方运行,让开第m+2基础9上方的空间;4) The crane 1-4 above the bridging machine 1 runs backwards, allowing the space above the m+2 base 9 to be opened;
5)移动吊机3在移动轨道2上向后运行,使移动吊机3上方的起重机3-1到达第m+2基础9上方设定位置;5) the mobile crane 3 runs backward on the moving rail 2, so that the crane 3-1 above the mobile crane 3 reaches the set position above the m+2 base 9;
6)移动吊机3上的起重机3-1吊起第m+2基础9,沿着移动吊机3上方的轨道向前运行,使起重机3-1和第m+2基础9从移动吊机3内的后部移动至前部;移动吊机3沿着移动轨道2向前运行至第m+2基础9设定位置,将第m+2基础9放入桥梁基础施工装置4-2内;6) The crane 3-1 on the mobile crane 3 lifts the m+2 base 9 and runs forward along the track above the mobile crane 3, so that the crane 3-1 and the m+2 base 9 are moved from the crane The rear portion of 3 moves to the front; the mobile crane 3 moves forward along the moving rail 2 to the m+2 base 9 setting position, and the m+2 base 9 is placed into the bridge foundation construction device 4-2. ;
7)移动吊机3将链刀驱动装置4-1-2与第m+2基础9顶部连在一起;7) the mobile crane 3 connects the chain cutter driving device 4-1-2 to the top of the m+2 base 9;
8)启动桥梁施工装置4-1,第m+2基础9下降至设定深度,完成施工;8) Start the bridge construction device 4-1, the m+2 foundation 9 is lowered to the set depth, and the construction is completed;
重复上述步骤完成其余基础9的安装。Repeat the above steps to complete the installation of the remaining base 9.
如图33~图38所示,桥梁基础施工装置4-1从第m+2基础位置移至第m+3基础位置的施工法分如下步骤:As shown in FIGS. 33 to 38, the construction method of the bridge foundation construction device 4-1 moving from the m+2 base position to the m+3 base position is as follows:
1)将移动轨道2的后端升降支撑装置2-1脱离第m桥墩7,前端升降支撑装 置2-2脱离地面或水底;1) separating the rear end lifting support device 2-1 of the moving rail 2 from the mth pier 7, and the front end lifting support device 2-2 is separated from the ground or the water bottom;
2)移动轨道2向前运行至设定位置,将后端升降支撑装置2-1支撑在第m+1桥墩7的前端,将前端升降支撑装置2-2支撑在第m+3基础位置前方的地面或水底;2) The moving rail 2 is moved forward to the set position, the rear end lifting support device 2-1 is supported at the front end of the m+1th pier 7, and the front end lifting support device 2-2 is supported in front of the m+3 base position. Ground or underwater;
3)将移动支撑装置5从靠近第m+1基础的前方,移至靠近位于第m+2基础位置的桥梁基础施工装置4-1的后方;3) moving the mobile supporting device 5 from the front side close to the m+1th base to the rear of the bridge foundation construction device 4-1 located at the m+2 base position;
4)移动吊机3运行至桥梁基础施工装置4-1的上方,将桥梁基础施工装置4-1与第m+2桥梁基础脱离,将移动轨道2的前行走支撑装置2-3与桥梁基础施工装置4-1脱离;4) The mobile crane 3 runs to the top of the bridge foundation construction device 4-1, and the bridge foundation construction device 4-1 is separated from the m+2 bridge foundation, and the front travel support device 2-3 of the moving rail 2 and the bridge foundation are Construction device 4-1 is detached;
5)移动吊机3上方的起重机3-1将桥梁基础施工装置4-1吊起,移动吊机3带着桥梁基础施工装置4-1在移动轨道2上向前运行至第m+3基础上方;5) The crane 3-1 above the mobile crane 3 lifts the bridge foundation construction device 4-1, and the mobile crane 3 carries the bridge foundation construction device 4-1 to move forward on the moving rail 2 to the m+3 basis. Above
6)移动吊机3上的起重机3-1使桥梁基础装置4-1下降,并使桥梁基础施工装置4-1在第m+3位置准确蹲位;6) The crane 3-1 on the mobile crane 3 lowers the bridge foundation device 4-1 and causes the bridge foundation construction device 4-1 to be accurately clamped at the m+3 position;
7)移动轨道2的前行走支撑装置2-3移动至桥梁基础施工装置4-1位置,将移动轨道2的前行走支撑装置2-3支撑在桥梁基础施工装置4-1上;7) The front travel support device 2-3 of the moving rail 2 is moved to the position of the bridge foundation construction device 4-1, and the front travel support device 2-3 of the moving rail 2 is supported on the bridge foundation construction device 4-1;
8)将移动支撑装置5从第m+2基础的后方移至靠近第m+2基础的前方。8) Move the mobile support device 5 from the rear of the m+2 base to the front of the m+2 base.
如图39~图43所示,第m梁8和第m+2基础均已施工完成,移动轨道的后端升降支撑装置2-1和架桥机1前端支撑的升降支撑装置1-3-2都支撑在第m+1桥墩7上,移动支撑装置5支撑在靠近第m+2基础前方的地面或水底,桥梁基础施工装置4-1位于第m+3基础的设定位置,第m+2桥墩7的具体施工法有如下步骤:As shown in FIG. 39 to FIG. 43, the m-th beam 8 and the m+2 base have been completed, and the rear end lifting support device 2-1 of the moving rail and the lifting support device 1-3- supported by the front end of the bridge machine 1 are completed. 2 is supported on the m+1th pier 7, the mobile support device 5 is supported on the ground or the water bottom near the front of the m+2 base, and the bridge foundation construction device 4-1 is located at the set position of the m+3 base, mth The concrete construction method of +2 pier 7 has the following steps:
1)将移动支撑装置移至靠近第m+2基础的前方;1) moving the mobile support device to the front of the m+2 base;
2)将第m+2桥墩7运至第m-1梁8处,位于架桥机1的下方,架桥机上方的起重机运行至第m+2桥墩7的上方;2) transporting the m+2 pier 7 to the m-1th beam 8 below the bridge machine 1, and the crane above the bridge machine runs above the m+2 pier 7;
3)架桥机1上方的起重机1-4将第m+2桥墩7吊起,并将第m+2桥墩7正确的放置在第m梁8前端的设定位置;3) The crane 1-4 above the bridging machine 1 lifts the m+2 pier 7 and correctly places the m+2 pier 7 at the set position of the front end of the mth beam 8;
4)架桥机1上方的起重机1-4向后方运行,让开第m+2桥墩7上方的空间;4) The crane 1-4 above the bridging machine 1 runs backwards, allowing the space above the m+2 pier 7 to be opened;
5)移动吊机3通过底部的行走装置3-2和行走装置3-3向后运行,使移动吊机3上方后部的起重机3-1到达第m+2桥墩7上方设定位置;5) The mobile crane 3 runs backward through the bottom traveling device 3-2 and the traveling device 3-3, so that the crane 3-1 at the upper rear portion of the mobile crane 3 reaches the set position above the m+2 pier 7;
6)移动吊机3上方后部的起重机3-1将第m+2桥墩7吊起,并将第m+2桥墩7从移动吊机3的后部移至移动吊机3的前部;6) The crane 3-1 at the upper rear of the mobile crane 3 lifts the m+2 pier 7 and moves the m+2 pier 7 from the rear of the mobile crane 3 to the front of the mobile crane 3;
7)移动吊机3带着第m+2桥墩7通过底部的行走装置3-2和行走装置3-3向前运行至第m+2基础的上方,将第m+2桥墩7放在第m+2基础上并准确定位固连成一体。7) The mobile crane 3 carries the m+2 pier 7 through the bottom running device 3-2 and the running device 3-3 forward to the top of the m+2 base, and places the m+2 pier 7 Based on m+2 and accurately positioned and fixed into one.
重复上述步骤完成其余桥墩7的安装。Repeat the above steps to complete the installation of the remaining piers 7.

Claims (10)

  1. 一种造桥装置,其特征是造桥装置包括架桥机(1)、移动轨道(2)、移动吊机(3)和桥梁基础施工装置(4),架桥机(1)设有后端支撑(1-1)、中部支撑(1-2)和前端支撑(1-3),后端支撑(1-1)和中部支撑(1-2)的底部分别设有行走装置(1-1-1)和行走装置(1-2-1),前端支撑(1-3)的底部设有行走装置(1-3-1),行走装置(1-1-1)和行走装置(1-2-1)在已架设的梁上运行,行走装置(1-3-1)在移动轨道(2)上运行,前端支撑(1-3)还设有升降支撑装置(1-3-2),架桥机(1)的上部设有的起重机(1-4),架桥机(1)起重时或移动轨道(2)运行时升降支撑装置(1-3-2)支撑在桥墩上;架桥机(1)的功能:一是架梁;二是将从已架设的梁上运来的基础或桥墩吊起放在已架好的梁的前端;移动轨道(2)的后端设有后端升降支撑装置(2-1),后端升降支撑装置(2-1)的底部支撑在桥墩上;移动轨道(2)的前端设有前端升降支撑装置(2-2),前端升降支撑装置(2-2)的底部支撑在地面或水底;移动轨道(2)移动时,后端升降支撑装置(2-1)脱离桥墩,前端升降支撑装置(2-2)脱离地面或水底,移动轨道(2)的中部分别在桥墩和桥梁基础施工装置(4)上移动;当架桥机(1)在移动轨道(2)上运行时,移动轨道(2)的中部和后部支撑在桥墩上;当移动吊机(3)带着基础或桥墩在移动轨道(2)上运行时,移动轨道(2)的中部和后部也支撑在桥墩上,移动轨道(2)的前部支撑在桥梁基础施工装置(4)上;A bridge building device, characterized in that the bridge building device comprises a bridge machine (1), a moving rail (2), a mobile crane (3) and a bridge foundation construction device (4), and the bridge machine (1) is provided The end support (1-1), the middle support (1-2), and the front support (1-3), and the bottom of the rear support (1-1) and the middle support (1-2) are respectively provided with a traveling device (1- 1-1) and the traveling device (1-2-1), the bottom of the front end support (1-3) is provided with a traveling device (1-3-1), a traveling device (1-1-1), and a traveling device (1) -2-1) Running on the erected beam, the traveling device (1-3-1) runs on the moving rail (2), and the front end support (1-3) is also provided with lifting support device (1-3-2) ), the crane (1-4) is provided on the upper part of the bridge machine (1), and the bridge support is supported by the lifting support device (1-3-2) when the bridge machine (1) is hoisting or when the moving rail (2) is running. The function of the bridge machine (1): one is the frame beam; the other is to lift the foundation or pier from the erected beam to the front end of the framed beam; the rear end of the moving track (2) There is a rear end lifting support device (2-1), the bottom of the rear end lifting support device (2-1) is supported on the pier; the front end of the moving rail (2) is provided with a front end lifting support device (2-2), front The bottom of the lifting support device (2-2) is supported on the ground or the bottom of the water; when the moving rail (2) is moved, the rear end lifting support device (2-1) is separated from the pier, and the front end lifting support device (2-2) is separated from the ground or the bottom. The middle part of the moving track (2) moves on the pier and the bridge foundation construction device (4) respectively; when the bridge machine (1) runs on the moving track (2), the middle and rear supports of the moving track (2) On the pier; when the mobile crane (3) is running on the moving track (2) with the foundation or the pier, the middle and rear of the moving track (2) are also supported on the pier, moving the front of the track (2) Supported on the bridge foundation construction device (4);
    移动吊机(3)的顶部设有轨道,轨道上设有顶部起重机(3-1),顶部起重机(3-1)通过轨道在移动吊机(3)内从前(或后)部运行至后(或前)部;移动吊机(3)的底部后端设有行走装置(3-2),行走装置(3-2)有两种结构:一仅在已建梁上行走,二在已建梁上和移动轨道(2)上均能行走;移动吊机(3)的底部前端和中间设有在移动轨道(2)上运行的行走装置(3-3),移动吊机(3)将预制的桥梁基础放入桥梁基础施工装置(4)内,在桥梁基础施工装置(4)内完成桥梁基础的施工;桥梁基础施工装置(4)的底部支撑在地面或水底时,桥梁基础施工装置(4)也是移动轨道(2)的支撑;移动吊机(3)将预制的桥墩放在施工好的桥梁基础上方,移动吊机(3)将已完成桥梁基础施工的桥梁基础施工装置(4)移至等待桥梁基础施工的位置;桥梁基础施工装置(4)完成对基础的施工;The top of the mobile crane (3) is provided with a rail with a top crane (3-1) on the rail, and the top crane (3-1) runs from the front (or rear) part to the moving crane (3) through the rail to the rear. (or front); the bottom end of the mobile crane (3) is provided with a walking device (3-2), and the traveling device (3-2) has two structures: one is only walking on the built beam, and the second is already Both the upper beam and the moving rail (2) can walk; the bottom front end of the mobile crane (3) and the middle of the moving device (3-3) running on the moving rail (2), the mobile crane (3) Put the prefabricated bridge foundation into the bridge foundation construction device (4), complete the construction of the bridge foundation in the bridge foundation construction device (4); when the bottom of the bridge foundation construction device (4) is supported on the ground or the bottom of the water, the bridge foundation construction The device (4) is also the support of the moving rail (2); the mobile crane (3) places the prefabricated pier above the constructed bridge foundation, and the mobile crane (3) will complete the bridge foundation construction device for the bridge foundation construction ( 4) Move to the position waiting for the foundation construction of the bridge; the bridge foundation construction device (4) completes the construction of the foundation;
    造桥装置能完成桥梁基础、桥墩和梁的施工。The bridge building device can complete the construction of the bridge foundation, piers and beams.
  2. 根据权利要求1所述的一种造桥装置,其特征是所述的移动轨道(2)中间的底部设有前行走支撑装置(2-3)和后行走支撑装置(2-4),前行走支撑装置(2-3) 设有行走装置(2-3-1),后行走支撑装置(2-4)设有行走装置(2-4-1),后行走支撑装置(2-4)支撑在桥墩上,前行走支撑装置(2-3)支撑在桥梁基础施工装置(4)上,当后端升降支撑装置(2-1)脱离桥墩,前端升降支撑装置(2-2)脱离地面或水底时,移动轨道(2)通过行走装置(2-3-1)和行走装置(2-4-1)从一个位置运行至另一位置。A bridging device according to claim 1, characterized in that the bottom of the moving rail (2) is provided with a front walking support device (2-3) and a rear walking support device (2-4), front The walking support device (2-3) is provided with a traveling device (2-3-1), the rear walking support device (2-4) is provided with a walking device (2-4-1), and the rear walking supporting device (2-4) Supported on the pier, the front walking support device (2-3) is supported on the bridge foundation construction device (4), and when the rear end lifting support device (2-1) is separated from the pier, the front end lifting support device (2-2) is separated from the ground. Or at the bottom of the water, the moving rail (2) is moved from one position to another by the traveling device (2-3-1) and the traveling device (2-4-1).
  3. 根据权利要求2所述的一种造桥装置,其特征是所述的前行走支撑装置(2-3)设有行走装置(2-3-2),后行走支撑装置(2-4)设有行走装置(2-4-2),移动轨道(2)设有行走装置(2-3-2)和行走装置(2-4-2)运行的轨道,前行走支撑装置(2-3)通过行走装置(2-3-2)从一个位置运行至另一位置,后行走支撑装置(2-4)通过行走装置(2-4-2)从一个位置运行至另一位置。A bridge-building apparatus according to claim 2, wherein said front walking support device (2-3) is provided with a traveling device (2-3-2), and the rear walking supporting device (2-4) is provided. There is a walking device (2-4-2), the moving rail (2) is provided with a running device (2-3-2) and a running device (2-4-2) running track, and the front walking support device (2-3) The traveling support device (2-3-2) is moved from one position to another by the running device (2-3-2), and the rear walking support device (2-4) is operated from one position to another through the traveling device (2-4-2).
  4. 根据权利要求1所述的一种造桥装置施工法,其特征是所述的造桥装置还包括在桥梁基础施工装置(4)的后面设有移动支撑装置(5),移动支撑装置(5)的底部支撑有两种结构:一是支撑在地面或水底(包括水中船),二是支撑在桥梁基础上;移动支撑装置(5)的上部是移动轨道(2)的支撑,移动支撑装置(5)设有在移动轨道(2)上运行的行走装置(5-1),当移动支撑装置(5)底部脱离支撑物时,通过行走装置(5-1)从一个位置行走至另一位置。A bridge building construction method according to claim 1, wherein said bridge building device further comprises a moving support device (5) behind the bridge foundation construction device (4), and a mobile support device (5) The bottom support has two structures: one is supported on the ground or the bottom of the water (including the water boat), and the other is supported on the bridge foundation; the upper part of the mobile support device (5) is the support of the moving rail (2), and the mobile support device (5) provided with a running device (5-1) running on the moving rail (2), walking from one position to the other through the running device (5-1) when the bottom of the moving supporting device (5) is separated from the support position.
  5. 根据权利要求4所述的一种造桥装置施工法,其特征是所述的已安装好的梁分别为第m-1梁、第m-2梁、第m-3梁、……,未安装的梁分别为第m+1梁、第m+2梁、第m+3梁、……,第m梁对应的桥墩分别为第m桥墩和第m+1桥墩,第m-1梁对应的桥墩分别为第m-1桥墩和第m桥墩,第m+1梁的桥墩分别为第m+1桥墩和第m+2桥墩,第m桥墩对应的基础为第m基础,设第m桥墩和第m+1桥墩已安装好,移动轨道(2)的后端升降支撑装置(2-1)支撑在第m桥墩前端,移动支撑装置(5)位于靠近第m+1基础的前方,桥梁基础施工装置(4)位于第m+2基础的设定位置。A bridge construction method according to claim 4, wherein said installed beams are respectively m-1 beam, m-2 beam, m-3 beam, ..., not The installed beams are the m+1th beam, the m+2 beam, the m+3 beam, ..., and the corresponding piers of the mth beam are the mth pier and the m+1th pier, respectively, and the m-1th beam corresponds to The piers are the m-1 pier and the mth pier, and the m+1 beam piers are the m+1 pier and the m+2 pier, respectively, and the mth pier corresponds to the mth foundation, and the mth pier And the m+1th pier has been installed, the rear end lifting support device (2-1) of the moving rail (2) is supported at the front end of the mth pier, and the mobile supporting device (5) is located in front of the m+1th foundation, the bridge The foundation construction device (4) is located at the set position of the m+2th base.
  6. 根据权利要求3、5所述的一种造桥装置施工法,其特征是所述的第m梁的施工法有如下步骤:A bridge construction method according to claims 3 and 5, characterized in that the construction method of the mth beam has the following steps:
    1)将架桥机(1)前端支撑(1-3)的升降支撑装置与第m桥墩脱离;1) detaching the lifting support device of the front end support (1-3) of the bridge machine (1) from the mth bridge pier;
    2)架桥机(1)的后端支撑(1-1)和中部支撑(1-2)的行走装置在已架设的梁上向前运行,前端支撑(1-3)的行走装置(1-3-1)在移动轨道(2)上向前运动,到达设定 位置,将架桥机(1)前端支撑(1-3)的升降支撑装置(1-3-2)支撑在第m+1桥墩的前部,使架桥机(1)的前端支撑(1-3)的行走装置(1-3-1)脱离移动轨道(2);2) The traveling device of the rear end support (1-1) and the middle support (1-2) of the bridge machine (1) runs forward on the erected beam, and the front end supports the travel device of (1-3) (1) -3-1) Move forward on the moving rail (2) to reach the set position, and support the lifting support device (1-3-2) of the front end support (1-3) of the bridge machine (1) at the mth +1 the front of the pier, so that the front end support (1-3) of the bridge machine (1) supports the travel device (1-3-1) off the moving track (2);
    3)移动轨道(2)向前运行到达设定位置,移动轨道(2)的后行走支撑装置(2-4)从第m桥墩运行至第m+1桥墩的前部,并支撑在第m+1桥墩上;3) The moving rail (2) moves forward to reach the set position, and the rear travel support device (2-4) of the moving rail (2) runs from the mth pier to the front of the m+1th pier and is supported at the mth +1 bridge pier;
    4)将第m梁运至第m-1梁处,位于架桥机(1)后部的下方,架桥机(1)上方的起重机(1-4)运行至第m梁的上方;4) transporting the mth beam to the m-1 beam, below the rear of the bridge machine (1), and the crane (1-4) above the bridge machine (1) running above the mth beam;
    5)架桥机(1)上方的起重机(1-4)将第m梁吊起,沿着架桥机(1)上方的轨道向前运行至第m桥墩和第m+1桥墩之间的设定位置;5) The crane (1-4) above the bridge machine (1) lifts the mth beam and runs forward along the track above the bridge machine (1) to the m-bridge pier and the m+1 pier. Set position
    6)架桥机(1)上的起重机(1-4)使第m梁下降,第m梁蹲位并满足设计安装要求;6) The crane (1-4) on the bridge machine (1) lowers the mth beam, and the mth beam is clamped and meets the design and installation requirements;
    7)将第m梁与第m-1梁、第m桥墩和第m+1桥墩相连;7) connecting the mth beam to the m-1th beam, the mth pier and the m+1th pier;
    重复上述步骤完成其余梁的安装。Repeat the above steps to complete the installation of the remaining beams.
  7. 根据权利要求5所述的一种造桥装置,其特征是所述的第m+2基础有A和B两种结构:A bridge-building apparatus according to claim 5, wherein said m+2 base has two structures A and B:
    A)第m+2基础是施工时底部带有链刀的基础,链刀仅有挖掘基础底部的岩土;所述的桥梁基础施工装置(4-1)包括固定导向装置(4-1-1)、链刀动力传动装置(4-1-2)、弃土处理装置(4-1-3)和机架(4-1-4);A) The m+2 foundation is the foundation with a chain cutter at the bottom of the construction. The chain cutter only excavates the rock at the bottom of the foundation; the bridge foundation construction device (4-1) includes fixed guides (4-1- 1), chain cutter power transmission device (4-1-2), spoil disposal device (4-1-3) and frame (4-1-4);
    B)第m+2基础是底部带有刀具的螺旋筒形基础,刀具仅有挖掘螺旋筒形基础底部的环状岩土;所述的桥梁基础施工装置(4-2)包括固定导向装置(4-2-1)、旋转装置(4-2-2)和下降速度控制装置(4-2-3)。B) The m+2 base is a spiral cylindrical foundation with a cutter at the bottom, and the cutter only has the annular rock at the bottom of the spiral cylindrical foundation; the bridge foundation construction device (4-2) includes a fixed guide ( 4-2-1), rotating device (4-2-2) and falling speed control device (4-2-3).
  8. 根据权利要求7所述的一种造桥装置施工法,其特征是所述的第m+2基础是底部带有刀具的螺旋筒形基础,或者是施工时底部带有链刀的基础,具体的施工法有如下步骤:A bridge building construction method according to claim 7, wherein said m+2 foundation is a spiral cylindrical foundation with a cutter at the bottom, or a base with a chain cutter at the bottom during construction, specifically The construction method has the following steps:
    1)将第m+2基础运至第m-1梁处,位于架桥机(1)后部的下方,架桥机(1)上方的起重机(1-4)运行至第m+2基础的上方;1) Transport the m+2 base to the m-1 beam, below the rear of the bridge machine (1), and the crane (1-4) above the bridge machine (1) runs to the m+2 base. Above
    2)架桥机(1)上方的起重机(1-4)将第m+2基础吊起,沿着架桥机(1)上方的轨道向前运行至第m-1梁前方的设定位置;2) The crane (1-4) above the bridge machine (1) lifts the m+2 base and moves forward along the track above the bridge machine (1) to the set position in front of the m-1 beam. ;
    3)架桥机(1)上的起重机(1-4)使第m+2基础下降,将第m+2基础放在第m-1梁的前端;3) The crane (1-4) on the bridge machine (1) lowers the m+2 base and places the m+2 base on the front end of the m-1th beam;
    4)架桥机(1)上方的起重机(1-4)向后方运行,让开第m+2基础上方的空间;4) The crane (1-4) above the bridge machine (1) runs backwards, allowing the space above the m+2 base to be opened;
    5)移动吊机(3)在移动轨道(2)上向后运行,使移动吊机(3)上方的起重机(3-1)到达第m+2基础上方设定位置;5) The mobile crane (3) runs backward on the moving rail (2), so that the crane (3-1) above the mobile crane (3) reaches the set position above the m+2 base;
    6)移动吊机(3)上的顶部起重机(3-1)吊起第m+2基础,沿着移动吊机(3)上方的轨道向前运行,使顶部起重机(3-1)和第m+2基础从移动吊机(3)内的后部移动至前部;移动吊机(3)沿着移动轨道(2)向前运行至第m+2基础设定位置,将第m+2基础放入桥梁基础施工装置(4)内;6) The top crane (3-1) on the mobile crane (3) lifts the m+2 base and runs forward along the track above the moving crane (3), making the top crane (3-1) and The m+2 base moves from the rear of the mobile crane (3) to the front; the mobile crane (3) moves forward along the moving track (2) to the m+2 basic setting position, and the m+ 2 The foundation is placed in the bridge foundation construction device (4);
    7)移动吊机(3)将链刀驱动装置(4-1-2)或者螺旋筒形基础旋转驱动装置(4-2-2)与第m+2基础顶部连在一起;7) The mobile crane (3) connects the chain cutter drive device (4-1-2) or the spiral cylindrical base rotary drive device (4-2-2) to the m+2 base top;
    8)启动桥梁基础施工装置(4),第m+2基础下降至设定深度,完成施工;8) Start the bridge foundation construction device (4), and the m+2 foundation is lowered to the set depth to complete the construction;
    重复上述步骤完成其余基础的安装。Repeat the above steps to complete the rest of the basic installation.
  9. 根据权利要求3、5所述的一种造桥装置施工法,其特征是所述的桥梁基础施工装置(4)从第m+2基础位置移至第m+3基础位置的施工法分如下步骤:A bridge building construction method according to claims 3 and 5, characterized in that the construction method of the bridge foundation construction device (4) moving from the m+2 base position to the m+3 base position is as follows step:
    1)将移动轨道(2)的后端升降支撑装置(2-1)脱离第m桥墩,前端升降支撑装置(2-2)脱离地面或水底;1) The rear end lifting support device (2-1) of the moving rail (2) is separated from the mth bridge pier, and the front end lifting support device (2-2) is separated from the ground or the water bottom;
    2)移动轨道(2)向前运行至设定位置,将后端升降支撑装置(2-1)支撑在第m+1桥墩的前端,将前端升降支撑装置(2-2)支撑在第m+3基础位置前方的地面或水底;2) The moving rail (2) is moved forward to the set position, the rear end lifting support device (2-1) is supported at the front end of the m+1th pier, and the front end lifting support device (2-2) is supported at the mth +3 the ground or water bottom in front of the base position;
    3)将移动支撑装置(5)从靠近第m+1基础的前方,移至靠近位于第m+2基础位置的桥梁基础施工装置(4)的后方;3) moving the mobile supporting device (5) from the front side close to the m+1th base to the rear of the bridge foundation construction device (4) located at the m+2 base position;
    4)移动吊机(3)运行至桥梁基础施工装置(4)的上方,将桥梁基础施工装置(4)与第m+2桥梁基础脱离,将移动轨道(2)的前行走支撑装置(2-3)与桥梁基础施工装置(4)脱离;4) The mobile crane (3) runs to the top of the bridge foundation construction device (4), and the bridge foundation construction device (4) is separated from the m+2 bridge foundation, and the front travel support device of the moving rail (2) is moved (2) -3) detached from the bridge foundation construction device (4);
    5)移动吊机(3)上方的顶部起重机(3-1)将桥梁基础施工装置(4)吊起,移动吊机(3)带着桥梁基础施工装置(4)在移动轨道(2)上向前运行至第m+3基础上方;5) The top crane (3-1) above the mobile crane (3) hoists the bridge foundation construction device (4), and the mobile crane (3) carries the bridge foundation construction device (4) on the moving track (2) Run forward to the top of the m+3 base;
    6)移动吊机(3)上的顶部起重机(3-1)使桥梁基础施工装置(4)下降,并使桥梁基础施工装置(4)在第m+3位置准确蹲位;6) The top crane (3-1) on the mobile crane (3) lowers the bridge foundation construction device (4) and makes the bridge foundation construction device (4) accurately clamped at the m+3 position;
    7)移动轨道(2)的前行走支撑装置(2-3)移动至桥梁基础施工装置(4)位置,将移动轨道(2)的前行走支撑装置(2-3)支撑在桥梁基础施工装置(4)上;7) The front travel support device (2-3) of the moving rail (2) is moved to the position of the bridge foundation construction device (4), and the front travel support device (2-3) of the moving rail (2) is supported on the bridge foundation construction device. (4) above;
    8)将移动支撑装置(5)从第m+2基础的后方移至靠近第m+2基础的前方。8) Move the mobile support device (5) from the rear of the m+2 base to the front of the m+2 base.
  10. 根据权利要求6、8、9所述的一种造桥装置,其特征是所述的第m梁和第m+2基础均已施工完成,移动轨道(2)的后端升降支撑装置(2-1)和架桥机(1)前端支撑(1-3)的升降支撑装置(1-3-2)都支撑在第m+1桥墩上,移动支撑装置(5)支撑在靠近第m+2基础前方的地面或水底,桥梁基础施工装置(4)位于第m+3基础的设定位置,第m+2桥墩的具体施工法有如下步骤:A bridge-building apparatus according to claims 6, 8, and 9, wherein said m-th beam and said m+2-base are both completed, and a rear-end lifting support device for moving rail (2) (2) -1) and the lifting support device (1-3-2) of the front end support (1-3) of the bridge machine (1) are supported on the m+1th pier, and the moving support device (5) is supported near the m+ 2 The ground or water bottom in front of the foundation, the bridge foundation construction device (4) is located at the set position of the m+3 foundation. The specific construction method of the m+2 pier has the following steps:
    1)将第m+2桥墩运至第m梁处,位于架桥机(1)的下方,架桥机(1)上方的起重机(1-4)运行至第m+2桥墩的上方;1) transport the m+2 pier to the mth beam, below the bridge machine (1), and the crane (1-4) above the bridge machine (1) runs above the m+2 pier;
    2)架桥机(1)上方的起重机(1-4)将第m+2桥墩吊起,并将第m+2桥墩正确的放置在第m梁前端的设定位置;2) The crane (1-4) above the bridge erecting machine (1) lifts the m+2 pier and positions the m+2 pier correctly at the set position of the front end of the mth beam;
    3)架桥机(1)上方的起重机(1-4)向后方运行,让开第m+2桥墩上方的空间;3) The crane (1-4) above the bridging machine (1) runs backwards, allowing the space above the m+2 pier to be opened;
    4)移动吊机(3)通过底部的行走装置(3-2)和行走装置(3-3)向后运行,使移动吊机(3)上方后部的顶部起重机(3-1)到达第m+2桥墩上方设定位置;4) The mobile crane (3) runs backward through the bottom travel device (3-2) and the travel device (3-3), so that the top crane (3-1) at the upper rear of the mobile crane (3) reaches the first Setting position above the m+2 pier;
    5)移动吊机(3)上方后部的顶部起重机(3-1)将第m+2桥墩吊起,并将第m+2桥墩从移动吊机(3)的后部移至移动吊机(3)的前部;5) The top crane (3-1) at the upper rear of the mobile crane (3) lifts the m+2 pier and moves the m+2 pier from the rear of the mobile crane (3) to the mobile crane The front part of (3);
    6)移动吊机(3)带着第m+2桥墩通过底部的行走装置(3-2)和行走装置(3-3)向前运行至第m+2基础的上方,将第m+2桥墩放在第m+2基础上并准确定位固连成一体;6) The mobile crane (3) with the m+2 pier through the bottom of the walking device (3-2) and the running device (3-3) forward to the top of the m+2 base, the m+2 The pier is placed on the basis of the m+2 and is accurately positioned and fixed into one body;
    重复上述步骤完成其余桥墩的安装。Repeat the above steps to complete the installation of the remaining piers.
PCT/CN2018/079253 2017-03-17 2018-03-16 Bridge building device and construction method therefor WO2018166519A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710162354.XA CN106758861A (en) 2017-03-17 2017-03-17 A kind of bridging device and its construction method
CN201710162354.X 2017-03-17

Publications (1)

Publication Number Publication Date
WO2018166519A1 true WO2018166519A1 (en) 2018-09-20

Family

ID=58966318

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/079253 WO2018166519A1 (en) 2017-03-17 2018-03-16 Bridge building device and construction method therefor

Country Status (2)

Country Link
CN (1) CN106758861A (en)
WO (1) WO2018166519A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756190A (en) * 2021-08-04 2021-12-07 中铁上海工程局集团有限公司 Small-spacing multi-bridge parallel section box girder synchronous frame transporting construction method
CN116991108A (en) * 2023-09-25 2023-11-03 四川公路桥梁建设集团有限公司 Intelligent management and control method, system and device for bridge girder erection machine and storage medium

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758861A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of bridging device and its construction method
CN109137735A (en) * 2018-08-31 2019-01-04 沙焕焕 A kind of pile-driving method and special equipment using Bridge Erector
CN111676826B (en) * 2020-06-23 2021-09-14 青岛同创旷远企业发展有限公司 Urban overhead construction system and integration method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009287312A (en) * 2008-05-30 2009-12-10 Nippon Steel Engineering Co Ltd Bridge construction apparatus
CN204703068U (en) * 2015-04-22 2015-10-14 北京中铁建北方路桥工程有限公司 A kind of up suspention section assembling traversing carriage bridge fabrication machine
CN106758861A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of bridging device and its construction method

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04179726A (en) * 1990-11-13 1992-06-26 Kazutoshi Isachi Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
NL9201777A (en) * 1992-10-13 1994-05-02 Grootint B V Elevated train track and method for its construction
CN201250064Y (en) * 2008-03-14 2009-06-03 上海港机重工有限公司 Front launching nose type bridge girder erection machine for bridge erection
CN201915333U (en) * 2010-11-09 2011-08-03 秦皇岛天业通联重工股份有限公司 Bridge erecting machine for erecting curved double-line twin girders at tunnel portal in zero-distance manner
CN105821874A (en) * 2016-03-28 2016-08-03 王燏斌 Construction method for spiral barrel-shaped foundation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009287312A (en) * 2008-05-30 2009-12-10 Nippon Steel Engineering Co Ltd Bridge construction apparatus
CN204703068U (en) * 2015-04-22 2015-10-14 北京中铁建北方路桥工程有限公司 A kind of up suspention section assembling traversing carriage bridge fabrication machine
CN106758861A (en) * 2017-03-17 2017-05-31 王燏斌 A kind of bridging device and its construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756190A (en) * 2021-08-04 2021-12-07 中铁上海工程局集团有限公司 Small-spacing multi-bridge parallel section box girder synchronous frame transporting construction method
CN113756190B (en) * 2021-08-04 2023-01-24 中铁上海工程局集团有限公司 Small-spacing multi-bridge parallel section box girder synchronous frame transporting construction method
CN116991108A (en) * 2023-09-25 2023-11-03 四川公路桥梁建设集团有限公司 Intelligent management and control method, system and device for bridge girder erection machine and storage medium
CN116991108B (en) * 2023-09-25 2023-12-12 四川公路桥梁建设集团有限公司 Intelligent management and control method, system and device for bridge girder erection machine and storage medium

Also Published As

Publication number Publication date
CN106758861A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
WO2018166519A1 (en) Bridge building device and construction method therefor
WO2018166518A1 (en) Foundation construction device and construction method therefor
CN106223967B (en) A kind of great burying rectangle or class rectangle tunneling shield constructing device and method
CN106761763A (en) A kind of novel silo development machine and its construction method
CN206267851U (en) A kind of novel silo development machine
CN110952552A (en) Large-diameter PHC precast tubular pile construction method and pile driver for implementing same
CN105625425A (en) Construction method for carrying out pile sinking based on floating walking platform
CN105155579A (en) Construction method for penetrating existing underground passage in open cutting of subway foundation pit
WO2018166521A1 (en) Construction device for shore foundation and construction method therefor
WO2018133740A1 (en) Underground building and construction method for same
CN111058458A (en) Construction method and structure based on cutter suction type ground connecting wall local replacement row pile support
CN105780837A (en) Continuous excavation method and device for underground continuous wall
CN109339096A (en) A kind of construction integrated constructing device of pipe gallery open cut precast assembly and its construction method
WO2018166522A1 (en) Construction device for revetment and construction method therefor
CN215211021U (en) Construction equipment based on synchronous drilling and precast pile splicing
WO2018133745A1 (en) Pipe jacking tunneling device for underwater tunnels and construction method thereof
WO2018166520A1 (en) Workboat for underwater foundation and construction method therefor
CN101200892A (en) Ballastless track steel reinforced concrete pile-net construction method
CN109630123A (en) Deep shaft rock ripper
CN209115129U (en) A kind of small pilot tunnel leading support equipment
WO2018166523A1 (en) Deep-water foundation and construction device and construction method therefor
WO2018133748A1 (en) Construction ship for underwater tunnel and construction method therefor
CN115596453A (en) Micro-brush slope tunnel entering method for tunnel long-distance side to pass through accumulation body
CN211549698U (en) Jacking working pit
CN114991777A (en) Climbing section excavation method for subway entrance and exit

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18766642

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18766642

Country of ref document: EP

Kind code of ref document: A1