WO2018133738A1 - Hydraulic engineering construction consisting of piles and walls and construction method therefor - Google Patents

Hydraulic engineering construction consisting of piles and walls and construction method therefor Download PDF

Info

Publication number
WO2018133738A1
WO2018133738A1 PCT/CN2018/072518 CN2018072518W WO2018133738A1 WO 2018133738 A1 WO2018133738 A1 WO 2018133738A1 CN 2018072518 W CN2018072518 W CN 2018072518W WO 2018133738 A1 WO2018133738 A1 WO 2018133738A1
Authority
WO
WIPO (PCT)
Prior art keywords
chain
pile
wall
cutter
piles
Prior art date
Application number
PCT/CN2018/072518
Other languages
French (fr)
Chinese (zh)
Inventor
王燏斌
Original Assignee
王燏斌
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王燏斌 filed Critical 王燏斌
Publication of WO2018133738A1 publication Critical patent/WO2018133738A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B1/00Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes

Definitions

  • the invention relates to a hydraulic structure composed of piles and walls and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
  • the existing breakwaters generally adopt a bottom riprap stack and a concrete face block on the rockfill prism, and also adopt a reinforced concrete caisson or a large-diameter cylinder structure; the engineering quantity is large, the construction period is long, and the cost is expensive.
  • the existing ship locks generally use the opening of the mountain to construct the ship locks.
  • the earthwork excavation project is huge, the construction period is long, and the cost is expensive.
  • the invention provides a hydraulic structure composed of piles and walls and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantages thereof: the hydraulic building is manufactured in the prefabricated field, the site After assembly, the overall decline, simple construction, good quality, short construction period, low cost, adapt to various areas.
  • a hydraulic structure composed of piles and walls, the bottom of the pile is constructed with a chain cutter for excavating the earth and soil, and the two ends of the wall and the pile are embedded or fixedly integrated with each other.
  • the pile is a grooved pile, and both ends of the wall are embedded in the pile groove when installed.
  • the bottom and sides of the grooved pile are provided with rails.
  • the rails are provided with chain cutters for excavating rock and earth.
  • the chain excavation device is composed of a chain cutter, a sprocket and a driving device.
  • the chain cutter is composed of a chain and a cutter fixed on the chain.
  • the bottom track has a height difference, which facilitates the operation of the intersection of the chain cutters; during construction, the drive unit drives the chain cutter, the chain cutter runs along the track, and the tool on the track at the bottom of the pile excavates the rock and soil, and the chain cutter will have been excavated when running from the bottom upward.
  • the rock belt is brought up to the top, and the chain cutter and the pile at the bottom of the pile are lowered together, descending to the design depth, and the chain cutter is removed and then grouted.
  • the bottom and side of the wall are provided with rails.
  • the rails are equipped with chain cutters for excavating rock and earth.
  • the chain excavation device is composed of a chain cutter, a sprocket and a driving device.
  • the chain cutter is composed of a chain and a cutter fixed on the chain;
  • the device drives the chain, the chain drives the tool to run along the track, and the tool at the bottom of the wall excavates the rock.
  • the chain knife runs from the bottom up, the excavated rock is brought to the top, and the chain knife and the wall at the bottom of the wall are simultaneously descended and lowered to Design depth, remove the chain knife and then grout.
  • the advantages of the invention are as follows: 1) When the breakwater is constructed, the prefabricated field is manufactured in sections, the assembly on the site is overall reduced, the quality is good, the construction period is short, and the cost is low; it is especially suitable for deep water areas.
  • the dam is constructed by using the segmented cofferdam construction method.
  • the cofferdam is also used as a component of the main structure of the dam.
  • the well-built dam body is used to guide the diversion. Increase the diversion building, and do not need to remove the cofferdam, reduce costs and shorten the construction period.
  • the ship lock foundation is reduced as a whole or as a block, and the construction period is short; the foundation frame can be used as a foundation pit support to excavate the rock and soil in the foundation frame, which is safe and convenient, and the earthwork excavation amount is small.
  • 1 is a schematic structural view of a word pile or wall 1, and is also a structural schematic view of the chain excavating device 2 when excavating the bottom rock of the foundation;
  • Figure 2 is a view in the direction of arrow A of Figure 1, and is also a schematic structural view of the chain cutter 3, the driving device 4, the tensioning device 5 and the sprocket 6 constituting the chain excavating device 2;
  • FIG. 3 is a cross-sectional view taken along line B-B of FIG. 1 , and is a schematic structural view of the chain cutter 3 excavating both the rock and the horizontal soil at the bottom of the foundation, and is also a structural schematic view of the rail 1-1 of the chain cutter 3 running at the bottom of the pile or wall 1;
  • Figure 4 is a cross-sectional view taken along line C-C of Figure 1, and is also a schematic structural view of a chain type geotechnical conveyor 7 composed of a chain cutter 3 and a chain cutter cover 1-3;
  • Fig. 5 is a schematic structural view of the chain cutter 3, which is also a schematic structural view of the chain 3-1 and the cutter 3-2, and is also a chain 3- consisting of A ten-byte 3-1-1 and B ten-byte 3-1-2.
  • Schematic diagram of the ten-byte structure of 1; also a schematic diagram of the structure of the chain 3-1 for realizing the space bending is a structural diagram of the chain cutter 3
  • (a) is a structural schematic diagram of the chain 3-1 and the cutter 3-2, also by the A cross Schematic diagram of the ten-byte structure of the chain 3-1 composed of the section 3-1-1 and the B-byte 3-1-2; and the structure diagram of the chain 3-1 to realize the space bending.
  • (b) is a schematic structural view of the chain cutter 3 composed of the flexible belt 3-1B and the cutter 3-2B; also a schematic structural view of the flexible belt 3-1B and the cutter 3-2B;
  • Figure 6 is a schematic view showing the construction process of the prefabricated on-site assembly method of the pile or wall 1, which is indicated by 1 to 4;
  • Figure 7 is a schematic diagram of the on-site installation and pouring formwork of the pile or wall 1 and the pouring process on the side of the falling side, indicated by 1 to 2, also the bottom track B-1, the intermediate frame B-2, the upper device B-3 and the pouring form B- 4 is a schematic diagram of the structure;
  • Fig. 8 is a structural schematic view of the A1 type pile 10-1, and is a structural schematic view of the A1 type pile 10-1 as it is integrally sunk together with the chain cutter 3 at the bottom, and is also a height difference of the bottom rail of the A1 type pile 10-1. Schematic diagram of the operation of the chain cutter 3 at the intersection;
  • Figure 9 is a view in the direction of arrow A of Figure 8, and is also a schematic structural view of the chain cutter 3, the driving device 4, the tensioning device 5 and the sprocket 6 constituting the chain excavating device 2;
  • Figure 10 is a cross-sectional view taken along line B-B of Figure 8.
  • Figure 11 is a schematic structural view of a linear breakwater composed of an A1 type pile 10-1 and an underground continuous wall 8-1;
  • Figure 12 is an enlarged view of I of Figure 11;
  • Figure 13 is a cross-sectional view taken along line A-A of Figure 11;
  • Figure 14 is a B-direction view of Figure 11;
  • Figure 15 is a schematic view showing the structure of the chain excavating device 2 for installing the underground continuous wall 8-1 on the top of the built A1 type pile 10-1;
  • Figure 16 is a view taken along line A in Figure 15;
  • 17 is a schematic structural view of a linear breakwater composed of an A1 type pile 10-1 and a floating wall 8-2;
  • Figure 18 is a view taken along line A of Figure 17;
  • Figure 19 is a schematic structural view of a curved breakwater composed of an A1 type pile 10-1 and a plug-in wall 8-3;
  • Figure 20 is a view taken along line A of Figure 19;
  • 21 is a structural schematic view of the bottom wall being a floating wall 8-2, and the upper wall being a plug-in wall 8-3 forming a breakwater;
  • Figure 22 is a view taken along the line A in Figure 21;
  • Figure 23 is a structural schematic view of a breakwater composed of two rows of piles and a hybrid wall, in which two ends or one ends of adjacent wall blocks are respectively inserted into pile grooves of different rows;
  • Figure 24 is a view taken along the line A in Figure 23;
  • Figure 25 is a cross-sectional view taken along line B-B of Figure 23;
  • Figure 26 is a schematic view showing the structure of the road above the breakwater
  • Figure 27 is a view taken along the line A in Figure 26;
  • Figure 28 is a schematic view showing the structure of the bottom frame 11 of the dam of the hydraulic structure, and also the B1 type pile 11-1, the B2 type pile 11-2, the bottom knives wall 11-3, and the gate 11 which constitute the dam bottom frame 11.
  • 4 is a schematic diagram of the structure;
  • Figure 29 is a schematic view showing the construction process of the segmented cofferdam of the bottom frame 11;
  • Figure 30 is a view of the A-A of Figure 28, and is also a schematic view of the dam pile B1 type pile 11-1, B2 pile 11-2;
  • Figure 31 is a B-direction view of Figure 28, and is also a schematic structural view of the gate 11-4 of the dam bottom frame 11;
  • Figure 32 is a partial enlarged view of I of Figure 28, and is a structural schematic view of the combination of the B1 type pile 11-2 and the wall 11-3 in the bottom frame of the dam, wherein the B1 type pile can also be called a word pile, and the chain knife 3,
  • the relationship between the driving device 4, the tensioning device 5, the sprocket 6 and the like, and the structure and construction method are completed, which can be understood as a combination of four one-word piles 1;
  • Figure 33 is a partial enlarged view of II of Figure 28, and is a schematic view of the mechanism of the B2 type pile 11-1 and the wall 11-3 combined in the bottom frame of the dam, wherein the B2 type pile can also be called a word pile, and the chain knife 3,
  • the relationship between the driving device 4, the tensioning device 5, the sprocket 6 and the like, and the structure and construction method are completed, which can be understood as a combination of four one-word piles 1;
  • Figure 34 is a schematic structural view of a ship lock frame 12 composed of a wall 12-2 and a bottom plate 12-3 provided with a chain cutter at the bottom of both sides of the C1 type pile 12-1;
  • FIG. 35 is a view taken along the line A-A of FIG. 34, which is a schematic diagram of the basic structure of the gate position of the ship lock frame 12, and is also a structural schematic view of the gate position C1 type 12-1 pile as the whole chain knife 3 of the bottom sinks together;
  • Figure 36 is a B-B view of Figure 34, and is also a structural view of the connection between the chamber wall 12-2 and the bottom plate 12-3, the chamber wall 12-2 is a continuous wall with a chain excavation device 2 at the bottom;
  • Figure 37 is a schematic structural view of a hydraulic building revetment 13;
  • Figure 38 is a view of the A-A of Figure 37, and is also a schematic view of the structure of the D1 type pile 13-1 used by the bank 13;
  • Figure 39 is a B-B view of Figure 37, and is also a schematic structural view of a continuous wall 13-2 of the cross-type of the bank 13;
  • Figure 40 is a schematic structural view of a hydraulic building wharf 14;
  • FIG. 41 is a view of the A-A of FIG. 40, which is also a schematic structural view of the D1 type pile 13-1 of the dock 14, and is also a schematic structural view of the cable string on the dock;
  • Figure 42 is a schematic view showing the structure of the bottom rail and the side rail of a pile or wall 1.
  • the type of the rail includes five types of a1, a2, b, c and d, wherein a1 and a2 are concave, b is flat, and c is Convex type
  • Figure 43 is a schematic view showing the structure of a d-shaped rail and a chain cutter of a word pile or wall 1;
  • Fig. 44 is a structural schematic view showing that d is a longitudinally multi-row staggered orbit.
  • 1 is a pile or wall of a hydraulic structure
  • 1-1 is a track running the chain cutter 3 at the bottom of the pile or wall
  • 1-2 is a track running the chain cutter 3 on the side of the pile or wall
  • 1-3 is a side cover with a beveled edge at the bottom, the chain cutter 3 constitutes a vertical geotechnical conveyor when running upwards
  • 2 is a chain excavation device for the A, B, C and D type piles and the underground continuous wall 8, which is composed of a chain cutter 3
  • 3 is a chain cutter constituting the chain excavating device 2
  • 3-1 is a chain constituting the chain cutter 3, including a crawler belt, a rope and a flexible belt
  • 1 is a ten-byte A ten-byte constituting the chain 3-1
  • 3-1-2 is a ten-byte B octet constituting the chain 3-1
  • 3-1B is a flexible tape constituting the chain cutter
  • a hydraulic structure consisting of piles and walls.
  • the bottom of the pile is constructed with chain cutters for excavating the earth and soil.
  • the two ends of the wall and the piles are embedded or fixed together.
  • the pile is a grooved pile, and both ends of the wall are embedded in the pile groove when installed.
  • the bottom and side of the grooved pile are provided with a track, and the track is provided with a chain cutter for excavating rock and earth.
  • the chain excavation device is composed of a chain cutter, a sprocket and a driving device, and the chain cutter is fixed by the chain and fixed on the chain.
  • the composition of the tool has a height difference between the bottom rails, which facilitates the operation of the intersection of the chain cutters.
  • the drive unit drives the chain cutter, the chain cutter runs along the track, and the cutter on the track at the bottom of the pile excavates the rock and soil.
  • the excavated geotechnical belt is taken to the top, and the chain cutter and pile at the bottom of the pile are lowered together, descending to the design depth, and the chain cutter is removed and then grouted.
  • the bottom and sides of the wall are provided with rails, and the rails are provided with chain cutters for excavating rock and earth.
  • the chain excavation device is composed of a chain cutter, a sprocket and a driving device, and the chain cutter is composed of a chain and a cutter fixed on the chain;
  • the drive unit drives the chain, the chain drives the tool to run along the track, and the tool at the bottom of the wall excavates the rock and soil.
  • the chain knife runs from the bottom up, the excavated rock and soil is brought to the top, and the chain knife and the wall at the bottom of the wall are simultaneously descended. , descend to the design depth, remove the chain knife and then grout.
  • the hydraulic structure is a breakwater.
  • the pile of the breakwater is an A-type pile
  • the wall embedded in the pile trough has four structures: a wall with a chain knife, a floating wall, a plug-in wall and a mixed wall at the bottom of the construction at the bottom:
  • the pile In the mixed wall in the height direction, the pile consists of two rows, and the two ends or one end of the adjacent wall block are inserted into different pile grooves respectively.
  • the hydraulic structure is a dam bottom frame that is higher than the upstream water surface during construction.
  • the pile is a B-type pile
  • the bottom frame of the dam divides the dam into a plurality of areas in the longitudinal direction
  • the bottom frame of the dam is provided with a gate
  • the area when the gate is opened is a diversion area
  • the gate is closed when the gate is closed.
  • the bottom frame of the dam is a construction cofferdam.
  • the bottom of the dam is pumped, excavated and poured in the cofferdam.
  • the corresponding flow gate in the bottom of the dam body is provided with a water flow channel; the gate of the bottom frame of the dam body is opened, and the water flow channel is a diversion channel.
  • the hydraulic structure is a ship lock frame, and the ship lock frame is an integral part of the lock chamber.
  • the hydraulic structure is a revetment or a dock.
  • the hydraulic building is provided with a track for the operation of the chain excavating device 2
  • the chain excavating device 2 is composed of a chain cutter 3, a driving device 4, a tensioning device 5 and a sprocket 6,
  • a chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 fixed on the chain;
  • the driving device 4 drives the chain 3-1 during construction, the chain 3-1 drives the cutter 3-2 to run along the track, and the cutter 3-2 at the bottom of the foundation
  • Excavating the earth and soil, the horizontal chain cutter 3-2 at the bottom of the foundation is a horizontal geotechnical conveyor.
  • the chain cutter 3 and the side cover 1-3 moving upward from the bottom constitute a chain vertical geotechnical conveyor 7, which is excavated from the bottom of the foundation.
  • the rock soil reaches the upper part through the horizontal geotechnical conveyor to the chain vertical geotechnical conveyor 7, and the bottom chain cutter 3 and the foundation are simultaneously descended downward, and after descending to the set depth, the chain 3-1 is broken, and the chain cutter is driven by the driving device. 3 All are pumped up for recycling and then grouted.
  • the first pile or wall 1 is divided into the following steps by prefabrication:
  • the word pile or wall 1 is divided into the following steps by using the cast-in-place method:
  • pile or wall 1 The various structures of the lower wall and the pile can be considered to be composed of a plurality of piles or walls 1.
  • the hydraulic structure is the breakwater 10, and the pile is the A-type pile 10-1.
  • the wall embedded in the pile groove has the wall 8-1 with the chain knife at the bottom and the floating wall 8-8 during construction. 2.
  • plug-in wall 8-3 and hybrid wall 8-4 Four structures of plug-in wall 8-3 and hybrid wall 8-4:
  • the wall has a chain knife at the bottom of the construction.
  • the chain excavation device 2 of the underground continuous wall 8-1 is installed on the top of the built A1 pile 10-1.
  • the chain knife 3 excavates the rock and soil, and the continuous wall 8-1 and the chain knife 3 falling together;
  • the pile In the mixed wall in the height direction, the pile consists of two rows, and the two ends or one end of the adjacent wall block are inserted into different pile grooves respectively.
  • the hydraulic structure is a dam bottom frame 11 which is higher than the upstream water surface during construction, and the pile is divided into B1 type pile 11-1 and B2 type pile 11-2, and the wall embedded in the pile groove is At the bottom of the construction, there is a wall 11-3 of the knife.
  • the dam bottom frame 11 divides the dam into a plurality of areas in the longitudinal direction, the dam bottom frame 11 is provided with a gate 11-4, and the area opened by the gate 11-4 is a flow guiding area.
  • the bottom frame 11 of the dam is a construction cofferdam, and the bottom of the dam is pumped, excavated and poured in the cofferdam, and a water flow passage is provided at the corresponding gate 11-4 in the bottom of the dam; the bottom of the dam is opened.
  • the gate 11-4 water flow channel is the diversion channel.
  • the hydraulic structure is the ship lock frame 12, and the pile is the C1 type pile 12-1.
  • the wall embedded in the pile groove is the wall 12-2 with the knife at the bottom during construction.
  • the ship lock frame 12 is the construction cofferdam, and the ship locks such as pumping, excavation and pouring are carried out in the cofferdam.
  • the hydraulic structure is the revetment and the pier 13
  • the pile is the D-type pile 13-1
  • the D-type pile 13-1 is arranged at a certain distance
  • the pile in the adjacent D-type pile 13-1 A continuous wall 13-2 having a cross shape is embedded in the groove, and the wall 13-2 is a wall having a knife at the bottom during construction.

Abstract

A hydraulic engineering construction consisting of piles and walls. The piles are provided at the bottom with a chain blade for excavating rock and soil during construction. Either extremity of the walls and the piles are embedded into each other or fixedly connected as one. The piles are piles having grooves. Either extremity of the walls are embedded into the grooves of the piles when mounted. Tracks are provided at the bottom and a side of the piles having the grooves and at the bottom and a side of the walls. The chain blade (3) for excavating rock and soil is mounted on the tracks. Chain-type excavating equipment (2) consists of the chain blade (3), chain wheels (6), and a driving apparatus (4). The bottom tracks are different in height so as to facilitate the operation of the chain blade (3) at an intersection. The driving apparatus (4) drives the chain blade (3) during construction. The chain blade (3) runs along the tracks. A cutter on the track at the bottom of the piles excavates rock and soil. The chain blade (3) takes excavated rock and soil to the top when running upwards. The chain blade (3) at the bottom of the piles descends with the piles. Also disclosed is a construction method for the hydraulic engineering construction consisting of the piles and the walls.

Description

一种由桩和墙组成的水工建筑物及其施工法Hydraulic structure composed of piles and walls and construction method thereof 技术领域Technical field
本发明涉及的是一种由桩和墙组成的水工建筑物及其施工法,属于土木工程基础施工技术领域。The invention relates to a hydraulic structure composed of piles and walls and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
背景技术Background technique
现有防波堤一般采用底部抛石堆筑和堆石棱体上加混凝土护面块体,也有采用钢筋混凝土沉箱或大直径圆筒结构;工程量浩大,施工周期长,造价昂贵。The existing breakwaters generally adopt a bottom riprap stack and a concrete face block on the rockfill prism, and also adopt a reinforced concrete caisson or a large-diameter cylinder structure; the engineering quantity is large, the construction period is long, and the cost is expensive.
现有大坝一般采用导流建筑、围堰建筑来创造干地施工条件,开挖土方量大,工程量浩大。大坝修建好后,围堰需拆除,施工周期长,造价昂贵。Existing dams generally use diversion construction and cofferdam construction to create dry construction conditions. The amount of excavation is large and the amount of construction is huge. After the dam is built, the cofferdam needs to be demolished, the construction period is long, and the cost is expensive.
现有驳岸、码头一般采用挖掘机开挖,设置排水沟或集水井进行排水,驳岸外侧还需要筑围堰。为防止沉降量大,每日砌筑高度有限,施工周期长,造价也高。Existing revetments and docks are generally excavated by excavators, and drainage or collection wells are used for drainage. In order to prevent a large amount of settlement, the daily masonry height is limited, the construction period is long, and the cost is high.
现有船闸一般采用在山体开凿通道修建船闸,土方开挖工程浩大,施工周期长,造价昂贵。The existing ship locks generally use the opening of the mountain to construct the ship locks. The earthwork excavation project is huge, the construction period is long, and the cost is expensive.
发明内容Summary of the invention
本发明提出的是一种由桩和墙组成的水工建筑物及其施工法,其目的旨在克服现有技术存在的缺陷,其主要优点:水工建筑物在预制场分段制造,现场组装后整体下降,施工简单,质量好,施工周期短,成本低,适应各种区域。The invention provides a hydraulic structure composed of piles and walls and a construction method thereof, the purpose of which is to overcome the defects existing in the prior art, and the main advantages thereof: the hydraulic building is manufactured in the prefabricated field, the site After assembly, the overall decline, simple construction, good quality, short construction period, low cost, adapt to various areas.
本发明的技术解决方案:桩和墙组成的水工建筑物,桩的底部施工时有挖掘岩土的链刀,墙的两端和桩是互相嵌入或固连成一体的。The technical solution of the invention: a hydraulic structure composed of piles and walls, the bottom of the pile is constructed with a chain cutter for excavating the earth and soil, and the two ends of the wall and the pile are embedded or fixedly integrated with each other.
桩是带槽的桩,墙的两端在安装时是嵌入桩槽内的。带槽的桩的底部和侧面设有轨道,轨道上装有挖掘岩土的链刀,链式挖掘装置由链刀、链轮和驱动装置组成,链刀由链条和固定于链条上的刀具组成,底部轨道有高度差,便于链刀相交处的运行;施工时驱动装置驱动链刀,链刀沿着轨道运行,桩底部轨道上的刀具挖掘岩土,链刀从底部向上运行时将已挖掘的岩土带至上方,桩底部的链刀和桩一起下降,下降至设计深度,拆除链刀后再灌浆。The pile is a grooved pile, and both ends of the wall are embedded in the pile groove when installed. The bottom and sides of the grooved pile are provided with rails. The rails are provided with chain cutters for excavating rock and earth. The chain excavation device is composed of a chain cutter, a sprocket and a driving device. The chain cutter is composed of a chain and a cutter fixed on the chain. The bottom track has a height difference, which facilitates the operation of the intersection of the chain cutters; during construction, the drive unit drives the chain cutter, the chain cutter runs along the track, and the tool on the track at the bottom of the pile excavates the rock and soil, and the chain cutter will have been excavated when running from the bottom upward. The rock belt is brought up to the top, and the chain cutter and the pile at the bottom of the pile are lowered together, descending to the design depth, and the chain cutter is removed and then grouted.
墙的底部和侧面设有轨道,轨道上装有挖掘岩土的链刀,链式挖掘装置由链刀、链轮和驱动装置组成,链刀由链条和固定于链条上的刀具组成;施工时驱动装置驱动链条,链条带动刀具沿着轨道运行,墙底部的刀具挖掘岩土,链刀从底部向上运行时将已挖掘的岩土带至上方,墙底部的链刀和墙一起同步下降,下降至设计深度,拆除链刀后再灌浆。The bottom and side of the wall are provided with rails. The rails are equipped with chain cutters for excavating rock and earth. The chain excavation device is composed of a chain cutter, a sprocket and a driving device. The chain cutter is composed of a chain and a cutter fixed on the chain; The device drives the chain, the chain drives the tool to run along the track, and the tool at the bottom of the wall excavates the rock. When the chain knife runs from the bottom up, the excavated rock is brought to the top, and the chain knife and the wall at the bottom of the wall are simultaneously descended and lowered to Design depth, remove the chain knife and then grout.
本发明的优点:1)防波堤施工时,在预制场分段制造,在现场的组装整体下降,质量好;施 工周期短,成本低;特别适合深水区域。The advantages of the invention are as follows: 1) When the breakwater is constructed, the prefabricated field is manufactured in sections, the assembly on the site is overall reduced, the quality is good, the construction period is short, and the cost is low; it is especially suitable for deep water areas.
2)大坝施工时,采用分段围堰施工法,利用围堰筑建大坝,围堰也是大坝主体结构的组成部分,修建好的坝体留置导流洞进行导流,不需要额外增加导流建筑,也不需要拆除围堰,减低成本,缩短工期。2) During the dam construction, the dam is constructed by using the segmented cofferdam construction method. The cofferdam is also used as a component of the main structure of the dam. The well-built dam body is used to guide the diversion. Increase the diversion building, and do not need to remove the cofferdam, reduce costs and shorten the construction period.
3)驳岸、码头施工时,不需要构筑围堰,施工简单;在现场整体下沉,施工周期短,成本低。3) When constructing the revetment and dock, there is no need to construct cofferdams, the construction is simple; the whole site sinks, the construction period is short, and the cost is low.
4)船闸基施工时,船闸基础整体或分块下降,施工周期短;基础框架可作为基坑支护,挖掘基础框架内的岩土,安全,方便,而且土方开挖量小。4) During the construction of the ship lock foundation, the ship lock foundation is reduced as a whole or as a block, and the construction period is short; the foundation frame can be used as a foundation pit support to excavate the rock and soil in the foundation frame, which is safe and convenient, and the earthwork excavation amount is small.
附图说明DRAWINGS
图1是一字桩或墙1的结构示意图,也是链式挖掘装置2挖掘基础底部岩土时的结构示意图;1 is a schematic structural view of a word pile or wall 1, and is also a structural schematic view of the chain excavating device 2 when excavating the bottom rock of the foundation;
图2是图1的A向视图,也是组成链式挖掘装置2的链刀3、驱动装置4、张紧装置5和链轮6的结构示意图;Figure 2 is a view in the direction of arrow A of Figure 1, and is also a schematic structural view of the chain cutter 3, the driving device 4, the tensioning device 5 and the sprocket 6 constituting the chain excavating device 2;
图3是图1的B-B剖视图,也是链刀3在基础底部既挖掘岩土又是岩土水平输送的结构示意图,也是桩或墙1底部运行链刀3的轨道1-1的结构示意图;3 is a cross-sectional view taken along line B-B of FIG. 1 , and is a schematic structural view of the chain cutter 3 excavating both the rock and the horizontal soil at the bottom of the foundation, and is also a structural schematic view of the rail 1-1 of the chain cutter 3 running at the bottom of the pile or wall 1;
图4是图1的C-C剖视图,也是由链刀3和链刀罩1-3组成的链式岩土输送机7的结构示意图;Figure 4 is a cross-sectional view taken along line C-C of Figure 1, and is also a schematic structural view of a chain type geotechnical conveyor 7 composed of a chain cutter 3 and a chain cutter cover 1-3;
图5是链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图,也是由A十字节3-1-1和B十字节3-1-2组成的链条3-1的十字节的结构示意图;也是链条3-1实现空间弯曲的结构示意图是链刀3的结构示意图,(a)是链条3-1和刀具3-2的结构示意图,也是由A十字节3-1-1和B十字节3-1-2组成的链条3-1的十字节的结构示意图;也是链条3-1实现空间弯曲的结构示意图。(b)是链刀3由柔性带3-1B和刀具3-2B组成的结构示意图;也是柔性带3-1B和刀具3-2B的结构示意图;Fig. 5 is a schematic structural view of the chain cutter 3, which is also a schematic structural view of the chain 3-1 and the cutter 3-2, and is also a chain 3- consisting of A ten-byte 3-1-1 and B ten-byte 3-1-2. Schematic diagram of the ten-byte structure of 1; also a schematic diagram of the structure of the chain 3-1 for realizing the space bending is a structural diagram of the chain cutter 3, (a) is a structural schematic diagram of the chain 3-1 and the cutter 3-2, also by the A cross Schematic diagram of the ten-byte structure of the chain 3-1 composed of the section 3-1-1 and the B-byte 3-1-2; and the structure diagram of the chain 3-1 to realize the space bending. (b) is a schematic structural view of the chain cutter 3 composed of the flexible belt 3-1B and the cutter 3-2B; also a schematic structural view of the flexible belt 3-1B and the cutter 3-2B;
图6是桩或墙1的预制现场组装法施工过程示意图,由1到4表示;Figure 6 is a schematic view showing the construction process of the prefabricated on-site assembly method of the pile or wall 1, which is indicated by 1 to 4;
图7是桩或墙1的现场安装浇筑模板,边下降边浇筑过程示意图,由1到2表示,也是底部轨道B-1、中间机架B-2、上部装置B-3和浇筑模板B-4的结构示意图;Figure 7 is a schematic diagram of the on-site installation and pouring formwork of the pile or wall 1 and the pouring process on the side of the falling side, indicated by 1 to 2, also the bottom track B-1, the intermediate frame B-2, the upper device B-3 and the pouring form B- 4 is a schematic diagram of the structure;
图8是A1型桩10-1的结构示意图,也是A1型桩10-1随着底部的链刀3一起整体下沉时的结构示意图,也是A1型桩10-1的底部轨道是有高度差的,便于链刀3在相交处的运行的结构示意图;Fig. 8 is a structural schematic view of the A1 type pile 10-1, and is a structural schematic view of the A1 type pile 10-1 as it is integrally sunk together with the chain cutter 3 at the bottom, and is also a height difference of the bottom rail of the A1 type pile 10-1. Schematic diagram of the operation of the chain cutter 3 at the intersection;
图9是图8的A向视图,也是组成链式挖掘装置2的链刀3、驱动装置4、张紧装置5和链轮6的结构示意图;Figure 9 is a view in the direction of arrow A of Figure 8, and is also a schematic structural view of the chain cutter 3, the driving device 4, the tensioning device 5 and the sprocket 6 constituting the chain excavating device 2;
图10是图8的B-B剖视图;Figure 10 is a cross-sectional view taken along line B-B of Figure 8;
图11是A1型桩10-1与地下连续墙8-1组成的直线防波堤的结构示意图;Figure 11 is a schematic structural view of a linear breakwater composed of an A1 type pile 10-1 and an underground continuous wall 8-1;
图12是图11的I处放大图;Figure 12 is an enlarged view of I of Figure 11;
图13是图11的A-A剖视图;Figure 13 is a cross-sectional view taken along line A-A of Figure 11;
图14是图11的B向视图;Figure 14 is a B-direction view of Figure 11;
图15是在已建A1型桩10-1顶部安装地下连续墙8-1的链式挖掘装置2的结构示意图;Figure 15 is a schematic view showing the structure of the chain excavating device 2 for installing the underground continuous wall 8-1 on the top of the built A1 type pile 10-1;
图16是图15的A向视图;Figure 16 is a view taken along line A in Figure 15;
图17是A1型桩10-1与浮式墙8-2组成的直线防波堤的结构示意图;17 is a schematic structural view of a linear breakwater composed of an A1 type pile 10-1 and a floating wall 8-2;
图18是图17的A向视图;Figure 18 is a view taken along line A of Figure 17;
图19是A1型桩10-1与插入式墙8-3组成的曲线防波堤的结构示意图;Figure 19 is a schematic structural view of a curved breakwater composed of an A1 type pile 10-1 and a plug-in wall 8-3;
图20是图19的A向视图;Figure 20 is a view taken along line A of Figure 19;
图21是底部墙是浮式墙8-2,上部墙是插入式墙8-3组成防波堤的结构示意图;21 is a structural schematic view of the bottom wall being a floating wall 8-2, and the upper wall being a plug-in wall 8-3 forming a breakwater;
图22是图21的A向视图;Figure 22 is a view taken along the line A in Figure 21;
图23是由两排桩和混合墙组成的防波堤的结构示意图,高度上相邻墙块的两端或一端分别插入不同排的桩槽中;Figure 23 is a structural schematic view of a breakwater composed of two rows of piles and a hybrid wall, in which two ends or one ends of adjacent wall blocks are respectively inserted into pile grooves of different rows;
图24是图23的A向视图;Figure 24 is a view taken along the line A in Figure 23;
图25是图23的B-B剖视图;Figure 25 is a cross-sectional view taken along line B-B of Figure 23;
图26是防波堤的上方是路的结构示意图;Figure 26 is a schematic view showing the structure of the road above the breakwater;
图27是图26的A向视图;Figure 27 is a view taken along the line A in Figure 26;
图28是水工建筑物大坝底部框架11的结构示意图,也是组成大坝底部框架11的B1型桩11-1、B2型桩11-2、底部有刀的墙11-3和闸门11-4的结构示意图;Figure 28 is a schematic view showing the structure of the bottom frame 11 of the dam of the hydraulic structure, and also the B1 type pile 11-1, the B2 type pile 11-2, the bottom knives wall 11-3, and the gate 11 which constitute the dam bottom frame 11. 4 is a schematic diagram of the structure;
图29是底部框架11分段围堰的施工过程示意图;Figure 29 is a schematic view showing the construction process of the segmented cofferdam of the bottom frame 11;
图30是图28的A-A视图,也是大坝桩B1型桩11-1、B2桩11-2的结构示意图;Figure 30 is a view of the A-A of Figure 28, and is also a schematic view of the dam pile B1 type pile 11-1, B2 pile 11-2;
图31是图28的B向视图,也是大坝底部框架11的闸门11-4的结构示意图;Figure 31 is a B-direction view of Figure 28, and is also a schematic structural view of the gate 11-4 of the dam bottom frame 11;
图32是图28的Ⅰ局部放大视图,也是大坝底部框架中B1型桩11-2与墙11-3结合的结构示意图,其中B1型桩也可称为口字桩,由链刀3、驱动装置4、张紧装置5、链轮6等相互关系及结构和施工法完成,可以理解为四个一字桩1的组合;Figure 32 is a partial enlarged view of I of Figure 28, and is a structural schematic view of the combination of the B1 type pile 11-2 and the wall 11-3 in the bottom frame of the dam, wherein the B1 type pile can also be called a word pile, and the chain knife 3, The relationship between the driving device 4, the tensioning device 5, the sprocket 6 and the like, and the structure and construction method are completed, which can be understood as a combination of four one-word piles 1;
图33是图28的Ⅱ局部放大视图,也是大坝底部框架中B2型桩11-1与墙11-3结合的机构示意图,其中B2型桩也可称为口字桩,由链刀3、驱动装置4、张紧装置5、链轮6等相互关系及结构和施工法完成,可以理解为四个一字桩1的组合;Figure 33 is a partial enlarged view of II of Figure 28, and is a schematic view of the mechanism of the B2 type pile 11-1 and the wall 11-3 combined in the bottom frame of the dam, wherein the B2 type pile can also be called a word pile, and the chain knife 3, The relationship between the driving device 4, the tensioning device 5, the sprocket 6 and the like, and the structure and construction method are completed, which can be understood as a combination of four one-word piles 1;
图34是由C1型桩12-1两侧底部设有链刀的墙12-2和底板12-3组成的船闸框架12的结构示意图;Figure 34 is a schematic structural view of a ship lock frame 12 composed of a wall 12-2 and a bottom plate 12-3 provided with a chain cutter at the bottom of both sides of the C1 type pile 12-1;
图35是图34的A-A视图,是船闸框架12的闸门位置基础结构示意图,也是闸门位置C1型12-1桩随着底部的链刀3一起整体下沉时的结构示意图;35 is a view taken along the line A-A of FIG. 34, which is a schematic diagram of the basic structure of the gate position of the ship lock frame 12, and is also a structural schematic view of the gate position C1 type 12-1 pile as the whole chain knife 3 of the bottom sinks together;
图36是图34的B-B视图,也是闸室墙体12-2与底板12-3连接的结构示意图,闸室墙体12-2是底部带有链式挖掘装置2的连续墙;Figure 36 is a B-B view of Figure 34, and is also a structural view of the connection between the chamber wall 12-2 and the bottom plate 12-3, the chamber wall 12-2 is a continuous wall with a chain excavation device 2 at the bottom;
图37是水工建筑物驳岸13的结构示意图;Figure 37 is a schematic structural view of a hydraulic building revetment 13;
图38是图37的A-A视图,也是驳岸13使用的D1型桩13-1的结构示意图;Figure 38 is a view of the A-A of Figure 37, and is also a schematic view of the structure of the D1 type pile 13-1 used by the bank 13;
图39是图37的B-B视图,也是驳岸13的中间成十字型的连续墙13-2的结构示意图;Figure 39 is a B-B view of Figure 37, and is also a schematic structural view of a continuous wall 13-2 of the cross-type of the bank 13;
图40是水工建筑物码头14结构示意图;Figure 40 is a schematic structural view of a hydraulic building wharf 14;
图41是图40的A-A视图,也是码头14的D1型桩13-1的结构示意图,也是码头上缆绳柱的结构示意图;41 is a view of the A-A of FIG. 40, which is also a schematic structural view of the D1 type pile 13-1 of the dock 14, and is also a schematic structural view of the cable string on the dock;
图42是一字桩或墙1的底部轨道和侧面轨道的结构示意图,轨道的类型包括a1、a2、b、c和d共5种,其中a1、a2是凹型,b是平面型,c是凸型;Figure 42 is a schematic view showing the structure of the bottom rail and the side rail of a pile or wall 1. The type of the rail includes five types of a1, a2, b, c and d, wherein a1 and a2 are concave, b is flat, and c is Convex type
图43是一字桩或墙1的d型轨道和链刀的结构示意图;Figure 43 is a schematic view showing the structure of a d-shaped rail and a chain cutter of a word pile or wall 1;
图44是d为纵向多排错开成锥型的轨道的结构示意图。Fig. 44 is a structural schematic view showing that d is a longitudinally multi-row staggered orbit.
图中的1是水工建筑物的一字桩或墙;1-1是桩或墙底部运行链刀3的轨道;1-2是桩或者墙侧面运行链刀3的轨道;1-3是底部带刃角的侧面罩,链刀3向上运行时构成岩土垂直输送机;2是用于A、B、C和D型桩和地下连续墙8的链式挖掘装置,由链刀3、驱动装置4、张紧装置5、链轮6等组成;3是组成链式挖掘装置2的链刀;3-1是组成链刀3的链条,包括履带、绳索和柔性带;3-1-1是组成链条3-1的十字节的A十字节;3-1-2是组成链条3-1的十字节的B十字节;3-1B是组成链刀3的柔性带;3-2是固定在链条3-1上的挖掘岩土的刀具;3-2B是固定在柔性带3-1B上的挖掘岩土的刀具;4是链条3-1的驱动装置;5是链条3-1的张紧装置;6是运行链条3-1的链轮;7是链式岩土输送机;8是组成水工建筑物的墙;8-1是由加长的一字桩或墙1组成的底部设有链刀3的地下连续墙;8-2是浮式墙;8-3是插入式墙;8-4是混合墙;B-1是现浇法中的底部轨道;B-2是现浇法中的中间机架;B-3是现浇法中的上部装置;B-4是现浇法中的浇筑模板;9是桥梁;10是防波提;10-1是底部带有链式挖掘装置2的防波堤的A1型桩;11是施工时高于上游水面的大坝底部框架;11-1是大坝底部框架11的B1型桩;11-2是大坝底部框架11的B2型桩;11-3是大坝底部框架11的底部设有链刀的墙;11-4是大坝底部框架11的闸门;12是船闸框架;12-1是船闸框架12的 C1型桩;12-2是船闸框架12的两侧底部设有链刀的墙;12-3是船闸框架12的底板;13是驳岸;13-1是驳岸或码头D1型桩;13-2是驳岸或码头的中间成十字型的连续墙;14是码头。1 is a pile or wall of a hydraulic structure; 1-1 is a track running the chain cutter 3 at the bottom of the pile or wall; 1-2 is a track running the chain cutter 3 on the side of the pile or wall; 1-3 is a side cover with a beveled edge at the bottom, the chain cutter 3 constitutes a vertical geotechnical conveyor when running upwards; 2 is a chain excavation device for the A, B, C and D type piles and the underground continuous wall 8, which is composed of a chain cutter 3, The driving device 4, the tensioning device 5, the sprocket 6 and the like; 3 is a chain cutter constituting the chain excavating device 2; 3-1 is a chain constituting the chain cutter 3, including a crawler belt, a rope and a flexible belt; 1 is a ten-byte A ten-byte constituting the chain 3-1; 3-1-2 is a ten-byte B octet constituting the chain 3-1; 3-1B is a flexible tape constituting the chain cutter 3; 3-2 is a tool for excavating geotechnical soil fixed on chain 3-1; 3-2B is a tool for excavating geotechnical soil fixed on flexible belt 3-1B; 4 is a driving device for chain 3-1; 5 is a chain 3-1 tensioning device; 6 is a sprocket running chain 3-1; 7 is a chain geotechnical conveyor; 8 is a wall constituting a hydraulic building; 8-1 is a lengthened pile or wall 1 consists of a base continuous wall with a chain knife 3 at the bottom; 8-2 is a floating wall; 8-3 is a plug-in wall 8-4 is a hybrid wall; B-1 is the bottom rail in the cast-in-place method; B-2 is the intermediate frame in the cast-in-place method; B-3 is the upper device in the cast-in-place method; B-4 is now a pouring form in the pouring method; 9 is a bridge; 10 is anti-wave lifting; 10-1 is an A1 type pile with a breakwater of the chain excavating device 2 at the bottom; 11 is a bottom frame of the dam higher than the upstream water surface during construction; 11-1 is a B1 type pile of the bottom frame 11 of the dam; 11-2 is a B2 type pile of the bottom frame 11 of the dam; 11-3 is a wall with a chain knife at the bottom of the bottom frame 11 of the dam; 11-4 is The gate of the dam bottom frame 11; 12 is the ship lock frame; 12-1 is the C1 type pile of the ship lock frame 12; 12-2 is the wall with the chain knife at the bottom of both sides of the ship lock frame 12; 12-3 is the ship lock frame 12 The bottom plate; 13 is the revetment; 13-1 is the revetment or dock D1 type pile; 13-2 is the cross-type continuous wall in the middle of the revetment or dock; 14 is the pier.
具体实施方式detailed description
一种由桩和墙组成的水工建筑物,桩的底部施工时有挖掘岩土的链刀,墙的两端和桩是互相嵌入或固连成一体的。A hydraulic structure consisting of piles and walls. The bottom of the pile is constructed with chain cutters for excavating the earth and soil. The two ends of the wall and the piles are embedded or fixed together.
所述的桩是带槽的桩,墙的两端在安装时是嵌入桩槽内的。The pile is a grooved pile, and both ends of the wall are embedded in the pile groove when installed.
所述的带槽的桩的底部和侧面设有轨道,轨道上装有挖掘岩土的链刀,链式挖掘装置由链刀、链轮和驱动装置组成,链刀由链条和固定于链条上的刀具组成,底部轨道有高度差,便于链刀相交处的运行;施工时驱动装置驱动链刀,链刀沿着轨道运行,桩底部轨道上的刀具挖掘岩土,链刀从底部向上运行时将已挖掘的岩土带至上方,桩底部的链刀和桩一起下降,下降至设计深度,拆除链刀后再灌浆。The bottom and side of the grooved pile are provided with a track, and the track is provided with a chain cutter for excavating rock and earth. The chain excavation device is composed of a chain cutter, a sprocket and a driving device, and the chain cutter is fixed by the chain and fixed on the chain. The composition of the tool has a height difference between the bottom rails, which facilitates the operation of the intersection of the chain cutters. During the construction, the drive unit drives the chain cutter, the chain cutter runs along the track, and the cutter on the track at the bottom of the pile excavates the rock and soil. When the chain cutter runs from the bottom upwards, The excavated geotechnical belt is taken to the top, and the chain cutter and pile at the bottom of the pile are lowered together, descending to the design depth, and the chain cutter is removed and then grouted.
所述的墙的底部和侧面设有轨道,轨道上装有挖掘岩土的链刀,链式挖掘装置由链刀、链轮和驱动装置组成,链刀由链条和固定于链条上的刀具组成;施工时驱动装置驱动链条,链条带动刀具沿着轨道运行,墙底部的刀具挖掘岩土,链刀从底部向上运行时将已挖掘的岩土带至上方,墙底部的链刀和墙一起同步下降,下降至设计深度,拆除链刀后再灌浆。The bottom and sides of the wall are provided with rails, and the rails are provided with chain cutters for excavating rock and earth. The chain excavation device is composed of a chain cutter, a sprocket and a driving device, and the chain cutter is composed of a chain and a cutter fixed on the chain; During the construction, the drive unit drives the chain, the chain drives the tool to run along the track, and the tool at the bottom of the wall excavates the rock and soil. When the chain knife runs from the bottom up, the excavated rock and soil is brought to the top, and the chain knife and the wall at the bottom of the wall are simultaneously descended. , descend to the design depth, remove the chain knife and then grout.
所述的桩的施工步骤如下:The construction steps of the pile are as follows:
1)预制桩的底部;1) the bottom of the precast pile;
2)在现场安装桩的底部,并在其轨道上安装链刀;2) Install the bottom of the pile on site and install a chain knife on its track;
3)桩的上部分两种方式:3) Two ways of the upper part of the pile:
(a)工厂预制,现场组装;(a) Factory prefabrication, on-site assembly;
(b)现场安装固定浇筑模板,桩边下降边浇筑;(b) Install a fixed pouring formwork on site, and pour the pile side down;
4)安装链轮、驱动装置和链刀,形成链式挖掘装置;4) installing a sprocket, a driving device and a chain cutter to form a chain excavating device;
5)驱动链条,桩底部的链刀挖掘岩土,链刀由底部向上运行时将已挖掘的岩土输送至上方,桩底部的链刀和桩随之下降;5) Drive the chain, the chain knife at the bottom of the pile excavates the rock and soil. When the chain knife runs from the bottom upwards, the excavated rock and soil will be transported to the top, and the chain cutter and pile at the bottom of the pile will descend;
6)下降至设计深度,拆除桩上的链刀后再灌浆。6) Decrease to the design depth, remove the chain cutter on the pile and grout.
所述的墙的施工步骤如下:The construction steps of the wall are as follows:
1)预制墙的底部;1) the bottom of the prefabricated wall;
2)在现场安装墙的底部,并在其轨道上安装链刀;2) Install the bottom of the wall at the site and install a chain knife on its track;
3)墙的上部分两种方式:3) The upper part of the wall is in two ways:
(a)工厂预制,现场组装;(a) Factory prefabrication, on-site assembly;
(b)现场安装固定浇筑模板,墙上边下降边浇筑;(b) Install a fixed pouring formwork on site, and pour the wall side down;
4)安装链轮、驱动装置和链刀,形成链式挖掘装置;4) installing a sprocket, a driving device and a chain cutter to form a chain excavating device;
5)驱动链条,墙底部的链刀挖掘岩土,由底部向上运行的链刀将已挖掘的岩土输送至上方,墙底部的链刀和墙随之下降;5) Drive the chain, the chain knife at the bottom of the wall excavates the rock and soil, and the chain cutter running from the bottom up will transport the excavated rock and soil to the upper part, and the chain knife and wall at the bottom of the wall will drop;
6)下降至设计深度,拆除墙上的链刀后再灌浆。6) Drop to the design depth, remove the chain knife on the wall and grout.
所述的水工建筑物是防波堤。The hydraulic structure is a breakwater.
所述的防波堤的桩是A型桩,所述的嵌入桩槽中的墙,有位于底部的施工时底部有链刀的墙、浮式墙、插入式墙和混合墙四种结构:The pile of the breakwater is an A-type pile, and the wall embedded in the pile trough has four structures: a wall with a chain knife, a floating wall, a plug-in wall and a mixed wall at the bottom of the construction at the bottom:
1)施工时底部有链刀的墙,自重由基础承担,水平力由基础和桩共同承受;1) The wall with the chain knife at the bottom of the construction, the self-weight shall be borne by the foundation, and the horizontal force shall be shared by the foundation and the pile;
2)浮式墙的自重主要由浮力来承受,水平力通过两端传递至桩槽由桩承受;2) The self-weight of the floating wall is mainly tolerated by buoyancy, and the horizontal force is transmitted to the pile trough through the two ends to be received by the pile;
3)插入式墙两端的底部是搁在桩基上的,水平力通过两端传递至桩槽由桩承受;3) The bottom of the two ends of the plug-in wall is resting on the pile foundation, and the horizontal force is transmitted to the pile trough through the two ends to be received by the pile;
4)混合墙分两种:4) There are two types of hybrid walls:
(1)在长度方向由地下连续墙、浮式墙、插入式墙组合而成;(1) It is composed of underground continuous wall, floating wall and plug-in wall in the longitudinal direction;
(2)在高度方向上的混合墙,桩由两排组成,高度上相邻墙块的两端或一端分别插入不同的桩槽中。(2) In the mixed wall in the height direction, the pile consists of two rows, and the two ends or one end of the adjacent wall block are inserted into different pile grooves respectively.
所述的水工建筑物是施工时高于上游水面的大坝底部框架。The hydraulic structure is a dam bottom frame that is higher than the upstream water surface during construction.
所述的桩是B型桩,所述的大坝底部框架在长度方向将大坝分成若干的区域,大坝底部框架设有闸门,闸门打开时的区域是导流区域;闸门闭合时的大坝底部框架是施工围堰,在围堰内进行抽水、挖掘、浇筑坝体底部,坝体底部内对应闸门处设有水流通道;打开坝体底部框架的闸门,水流通道就是导流渠。The pile is a B-type pile, and the bottom frame of the dam divides the dam into a plurality of areas in the longitudinal direction, the bottom frame of the dam is provided with a gate, the area when the gate is opened is a diversion area; and the gate is closed when the gate is closed. The bottom frame of the dam is a construction cofferdam. The bottom of the dam is pumped, excavated and poured in the cofferdam. The corresponding flow gate in the bottom of the dam body is provided with a water flow channel; the gate of the bottom frame of the dam body is opened, and the water flow channel is a diversion channel.
所述的水工建筑物是船闸框架,船闸框架是闸室的组成部分。The hydraulic structure is a ship lock frame, and the ship lock frame is an integral part of the lock chamber.
所述的水工建筑物是驳岸或码头。The hydraulic structure is a revetment or a dock.
下面结合附图进一步描述本发明的技术方案:The technical solution of the present invention is further described below with reference to the accompanying drawings:
图1~图5所示,水工建筑物上设有链式挖掘装置2运行的轨道,链式挖掘装置2由链刀3、驱动装置4、张紧装置5和链轮6组成,链刀3由链条3-1和固定于链条上的刀具3-2组成;施工时驱动装置4驱动链条3-1,链条3-1带动刀具3-2沿着轨道运行,基础底部的刀具3-2挖掘岩土,基础底部的水平链刀3-2同时是水平岩土输送机,从底部向上运动的链刀3和侧面罩1-3组成了链式垂直岩土输送机7,从基础底部挖掘的岩土经水平岩土输送机至链式垂直岩土输送机7到达上方,底部链刀3和基础一起同步下降,下降至设定深度后断开链条3-1,经驱动装置将链刀3全部抽上回收,再予以灌浆。1 to 5, the hydraulic building is provided with a track for the operation of the chain excavating device 2, and the chain excavating device 2 is composed of a chain cutter 3, a driving device 4, a tensioning device 5 and a sprocket 6, a chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 fixed on the chain; the driving device 4 drives the chain 3-1 during construction, the chain 3-1 drives the cutter 3-2 to run along the track, and the cutter 3-2 at the bottom of the foundation Excavating the earth and soil, the horizontal chain cutter 3-2 at the bottom of the foundation is a horizontal geotechnical conveyor. The chain cutter 3 and the side cover 1-3 moving upward from the bottom constitute a chain vertical geotechnical conveyor 7, which is excavated from the bottom of the foundation. The rock soil reaches the upper part through the horizontal geotechnical conveyor to the chain vertical geotechnical conveyor 7, and the bottom chain cutter 3 and the foundation are simultaneously descended downward, and after descending to the set depth, the chain 3-1 is broken, and the chain cutter is driven by the driving device. 3 All are pumped up for recycling and then grouted.
图6所示,一字桩或墙1采用预制法分如下步骤:As shown in Fig. 6, the first pile or wall 1 is divided into the following steps by prefabrication:
1)在工场分块预制桩,运至现场拼装桩并蹲位,并在其底部的轨道上安装链刀3,安装链条驱动装置4等装置,连接安装链刀3的链条3-1,如图中的1所示;1) Pre-cast piles in the workshop, transport them to the site to assemble the piles and clamp them, and install the chain cutters 3 on the rails at the bottom, install the chain drive device 4 and other devices, and connect the chain 3-1 of the chain cutter 3, such as 1 in the figure;
2)驱动链条3-1,链刀挖掘底部的岩土,经岩土输送装置7送至上方,桩随之下降,如图中2所示;2) Drive the chain 3-1, the chain knife excavates the rock at the bottom, and the pile is sent to the upper part through the geotechnical conveying device 7, and the pile descends, as shown in Fig. 2;
3)下降至一定深度后,在地面拼装桩的预制件,也可边下沉边拼装,如图中3所示;3) After descending to a certain depth, the prefabricated parts of the piles assembled on the ground can also be assembled while sinking, as shown in Figure 3;
4)下降至设计深度后灌浆,或拆除链刀3后再灌浆,如图中4所示。4) Grout after falling to the design depth, or remove the chain knife 3 and then grout, as shown in Figure 4.
图7所示,一字桩或墙1采用现浇法分如下步骤:As shown in Fig. 7, the word pile or wall 1 is divided into the following steps by using the cast-in-place method:
1)清理现场,搭建作业平台;1) Clean up the site and build an operating platform;
2)组装底部轨道B-1和浇筑模板B-4,即桩或墙1的底部蹲位,并在其底部的轨道上安装链刀3;2) assembling the bottom rail B-1 and the pouring formwork B-4, that is, the bottom of the pile or the wall 1 is clamped, and the chain knife 3 is mounted on the rail at the bottom thereof;
3)组装中间机架B-2、上部装置B-3;3) assembling the intermediate frame B-2 and the upper device B-3;
4)安装链条驱动装置4、张紧装置5,将底部轨道B-1、中间机架B-2、上部装置B-3和链条3-1连接成一体,组成链式挖掘装置2;4) Install the chain drive device 4, the tensioning device 5, the bottom rail B-1, the intermediate frame B-2, the upper device B-3 and the chain 3-1 are integrated to form a chain excavation device 2;
5)制作钢筋笼,将中间机架B-2与钢筋笼焊接成一体,中间机架B-2同时也是浇筑模板的组成部分;5) Making a steel cage, welding the intermediate frame B-2 with the steel cage, and the intermediate frame B-2 is also a component of the pouring template;
6)在模板B-4中浇筑混凝土;6) pouring concrete in template B-4;
7)驱动链条3-1,链刀3挖掘底部的岩土,并将已挖掘的岩土经中间装置B-2输送至上方,桩或墙1随之下降;7) Drive the chain 3-1, the chain cutter 3 excavates the rock at the bottom, and transports the excavated rock and soil to the upper part through the intermediate device B-2, and the pile or wall 1 descends accordingly;
8)随着桩或墙1底部的挖掘,模板B-4中的桩1边浇筑边下降;8) With the excavation of the bottom of the pile or wall 1, the side of the pile 1 in the form B-4 is lowered;
9)下降至设计深度拆除链刀3后灌浆;9) Drop to the design depth to remove the chain cutter 3 after grouting;
10)拆除上部装置和中间装置高于桩1的部分,拆除浇筑模板;10) Remove the upper device and the intermediate device above the pile 1 and remove the pouring formwork;
以上对一字桩或墙1进行了描述,下面墙和桩的各种结构可以认为是由若干个一字桩或墙1组合而成的。The above description has been made on the word pile or wall 1. The various structures of the lower wall and the pile can be considered to be composed of a plurality of piles or walls 1.
图8~图27所示,水工建筑物为防波堤10,其桩为A型桩10-1,嵌入桩槽中的墙有施工时底部有链刀的墙8-1、浮式墙8-2、插入式墙8-3和混合墙8-4四种结构:As shown in Fig. 8 to Fig. 27, the hydraulic structure is the breakwater 10, and the pile is the A-type pile 10-1. The wall embedded in the pile groove has the wall 8-1 with the chain knife at the bottom and the floating wall 8-8 during construction. 2. Four structures of plug-in wall 8-3 and hybrid wall 8-4:
1)施工时底部有链刀的墙,在已建A1型桩10-1顶部安装地下连续墙8-1的链式挖掘装置2,链刀3挖掘岩土,连续墙8-1跟链刀3一起下降;1) The wall has a chain knife at the bottom of the construction. The chain excavation device 2 of the underground continuous wall 8-1 is installed on the top of the built A1 pile 10-1. The chain knife 3 excavates the rock and soil, and the continuous wall 8-1 and the chain knife 3 falling together;
2)浮式墙8-2的自重主要由浮力来承受,水平力通过两端传递至桩10-1槽由桩承受;2) The self-weight of the floating wall 8-2 is mainly absorbed by buoyancy, and the horizontal force is transmitted to the pile 10-1 through the two ends to be received by the pile;
3)插入式墙8-3两端的底部是搁在桩基上的,水平力通过两端传递至桩槽由桩承受;3) The bottom of the two ends of the plug-in wall 8-3 is resting on the pile foundation, and the horizontal force is transmitted to the pile groove through the two ends to be received by the pile;
4)混合墙分两种:4) There are two types of hybrid walls:
(1)在长度方向由地下连续墙8-1、浮式墙8-2、插入式墙8-3组合而成;(1) in the longitudinal direction by a combination of underground continuous wall 8-1, floating wall 8-2, and plug-in wall 8-3;
(2)在高度方向上的混合墙,桩由两排组成,高度上相邻墙块的两端或一端分别插入不同的桩槽中。(2) In the mixed wall in the height direction, the pile consists of two rows, and the two ends or one end of the adjacent wall block are inserted into different pile grooves respectively.
图28~图33所示,水工建筑物为施工时高于上游水面的大坝底部框架11,其桩分B1型桩11-1和B2型桩11-2,嵌入桩槽中的墙是施工时底部有刀的墙11-3。大坝底部框架11在长度方向将大坝分成若干的区域,大坝底部框架11设有闸门11-4,闸门11-4打开的区域是导流区域。闸门11-4闭合时的大坝底部框架11是施工围堰,在围堰内进行抽水、挖掘、浇筑坝体底部,坝体底部内对应闸门11-4处设有水流通道;打开坝体底部的闸门11-4水流通道就是导流渠。As shown in Fig. 28 to Fig. 33, the hydraulic structure is a dam bottom frame 11 which is higher than the upstream water surface during construction, and the pile is divided into B1 type pile 11-1 and B2 type pile 11-2, and the wall embedded in the pile groove is At the bottom of the construction, there is a wall 11-3 of the knife. The dam bottom frame 11 divides the dam into a plurality of areas in the longitudinal direction, the dam bottom frame 11 is provided with a gate 11-4, and the area opened by the gate 11-4 is a flow guiding area. When the gate 11-4 is closed, the bottom frame 11 of the dam is a construction cofferdam, and the bottom of the dam is pumped, excavated and poured in the cofferdam, and a water flow passage is provided at the corresponding gate 11-4 in the bottom of the dam; the bottom of the dam is opened. The gate 11-4 water flow channel is the diversion channel.
图34~图36所示,水工建筑物为船闸框架12,其桩是C1型桩12-1,嵌入桩槽中的墙是施工时底部有刀的墙12-2,施工时,船闸框架12是施工围堰,在围堰内进行抽水、挖掘、浇筑等船闸施工。As shown in Fig. 34 to Fig. 36, the hydraulic structure is the ship lock frame 12, and the pile is the C1 type pile 12-1. The wall embedded in the pile groove is the wall 12-2 with the knife at the bottom during construction. During construction, the ship lock frame 12 is the construction cofferdam, and the ship locks such as pumping, excavation and pouring are carried out in the cofferdam.
图37~图39所示,水工建筑物为驳岸和码头13,其桩是D型桩13-1,相隔一定距离布置D型桩13-1,在相邻D型桩13-1的桩槽内嵌入中间成十字型的连续墙13-2,墙13-2是施工时底部有刀的墙。37 to 39, the hydraulic structure is the revetment and the pier 13, the pile is the D-type pile 13-1, the D-type pile 13-1 is arranged at a certain distance, and the pile in the adjacent D-type pile 13-1 A continuous wall 13-2 having a cross shape is embedded in the groove, and the wall 13-2 is a wall having a knife at the bottom during construction.

Claims (6)

  1. 一种由桩和墙组成的水工建筑物,其特征是桩的底部施工时有挖掘岩土的链刀,墙的两端和桩是互相嵌入或固连成一体的。A hydraulic structure consisting of piles and walls, characterized in that the bottom of the pile is constructed with a chain cutter for excavating the earth and soil, and the two ends of the wall and the piles are embedded or fixedly integrated with each other.
  2. 根据权利要求1所述的一种由桩和墙组成的水工建筑物,其特征在于所述的桩是带槽的桩,墙的两端在安装时是嵌入桩槽内的。A hydraulic structure consisting of a pile and a wall according to claim 1, wherein the pile is a grooved pile, and both ends of the wall are embedded in the pile groove when installed.
  3. 根据权利要求2所述的一种由桩和墙组成的水工建筑物,其特征是所述的带槽的桩的底部和侧面设有轨道,轨道上装有挖掘岩土的链刀,链式挖掘装置由链刀、链轮和驱动装置组成,链刀由链条和固定于链条上的刀具组成,底部轨道有高度差,便于链刀相交处的运行;施工时驱动装置驱动链刀,链刀沿着轨道运行,桩底部轨道上的刀具挖掘岩土,链刀从底部向上运行时将已挖掘的岩土带至上方,桩底部的链刀和桩一起下降,下降至设计深度,拆除链刀后再灌浆。A hydraulic structure consisting of a pile and a wall according to claim 2, wherein the grooved pile has a rail at the bottom and the side thereof, and the chain is provided with a chain cutter for excavating rock and soil, and the chain type The excavating device is composed of a chain cutter, a sprocket and a driving device. The chain cutter is composed of a chain and a cutter fixed on the chain, and the bottom rail has a height difference, which facilitates the operation of the intersection of the chain cutters; the driving device drives the chain cutter and the chain cutter during construction; Running along the track, the tool on the bottom track of the pile excavates the rock and soil. When the chain knife runs from the bottom up, the excavated geotechnical soil is brought to the top. The chain knife and the pile at the bottom of the pile are lowered together, descending to the design depth, and the chain cutter is removed. Then grout.
  4. 根据权利要求2所述的一种由桩和墙组成的水工建筑物,其特征是所述的墙的底部和侧面设有轨道,轨道上装有挖掘岩土的链刀,链式挖掘装置由链刀、链轮和驱动装置组成,链刀由链条和固定于链条上的刀具组成;施工时驱动装置驱动链条,链条带动刀具沿着轨道运行,墙底部的刀具挖掘岩土,链刀从底部向上运行时将已挖掘的岩土带至上方,墙底部的链刀和墙一起同步下降,下降至设计深度,拆除链刀后再灌浆。A hydraulic structure consisting of piles and walls according to claim 2, characterized in that the bottom and sides of the wall are provided with rails, and the rails are provided with chain cutters for excavating rock and earth, and the chain excavating device is The chain knife, the sprocket and the driving device are composed of a chain cutter and a cutter fixed on the chain; the driving device drives the chain during construction, the chain drives the cutter to run along the track, the cutter at the bottom of the wall excavates the rock and soil, and the chain cutter is from the bottom When the upward movement, the excavated geotechnical soil is brought to the top, and the chain cutter at the bottom of the wall and the wall are simultaneously lowered, descending to the design depth, and the chain cutter is removed and then grouted.
  5. 根据权利要求3所述的一种由桩和墙组成的水工建筑物,其特征是所述的桩的施工步骤如下:A hydraulic structure consisting of a pile and a wall according to claim 3, wherein the construction steps of the pile are as follows:
    1)预制桩的底部;1) the bottom of the precast pile;
    2)在现场安装桩的底部,并在其轨道上安装链刀;2) Install the bottom of the pile on site and install a chain knife on its track;
    3)桩的上部分两种方式:3) Two ways of the upper part of the pile:
    (a)工厂预制,现场组装;(a) Factory prefabrication, on-site assembly;
    (b)现场安装固定浇筑模板,桩边下降边浇筑;(b) Install a fixed pouring formwork on site, and pour the pile side down;
    4)安装链轮、驱动装置和链刀,形成链式挖掘装置;4) installing a sprocket, a driving device and a chain cutter to form a chain excavating device;
    5)驱动链条,桩底部的链刀挖掘岩土,链刀由底部向上运行时将已挖掘的岩土输送至上方,桩底部的链刀和桩随之下降;5) Drive the chain, the chain knife at the bottom of the pile excavates the rock and soil. When the chain knife runs from the bottom upwards, the excavated rock and soil will be transported to the top, and the chain cutter and pile at the bottom of the pile will descend;
    6)下降至设计深度,拆除桩上的链刀后再灌浆。6) Decrease to the design depth, remove the chain cutter on the pile and grout.
  6. 根据权利要求4所述的一种由桩和墙组成的水工建筑物,其特征是所述的墙的施工步骤如下:A hydraulic structure consisting of a pile and a wall according to claim 4, wherein the construction steps of the wall are as follows:
    1)预制墙的底部;1) the bottom of the prefabricated wall;
    2)在现场安装墙的底部,并在其轨道上安装链刀;2) Install the bottom of the wall at the site and install a chain knife on its track;
PCT/CN2018/072518 2017-01-18 2018-01-13 Hydraulic engineering construction consisting of piles and walls and construction method therefor WO2018133738A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710037725.1A CN106759068A (en) 2017-01-18 2017-01-18 A kind of hydraulic structure and its construction method being made up of stake and wall
CN201710037725.1 2017-01-18

Publications (1)

Publication Number Publication Date
WO2018133738A1 true WO2018133738A1 (en) 2018-07-26

Family

ID=58943390

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/072518 WO2018133738A1 (en) 2017-01-18 2018-01-13 Hydraulic engineering construction consisting of piles and walls and construction method therefor

Country Status (2)

Country Link
CN (1) CN106759068A (en)
WO (1) WO2018133738A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759068A (en) * 2017-01-18 2017-05-31 王燏斌 A kind of hydraulic structure and its construction method being made up of stake and wall

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1010701B (en) * 1986-06-13 1990-12-05 连续混凝土浇筑有限公司 Trenching apparatus
DE4108873A1 (en) * 1991-03-19 1992-10-08 Johannes Kruse Machine forming foundation slit wall - has two endless cutter chains mounted side by side and equipped with buckets
JPH09111753A (en) * 1995-10-18 1997-04-28 Kobe Steel Ltd Construction method of underground continuous wall and device therefor
CN101619573A (en) * 2009-07-24 2010-01-06 徐州文鹏工程机械制造有限公司 Machine for forming underground continuous water-retaining walls by one step
CN205475087U (en) * 2016-01-29 2016-08-17 俞向阳 Bank dyke revetment
CN106759068A (en) * 2017-01-18 2017-05-31 王燏斌 A kind of hydraulic structure and its construction method being made up of stake and wall

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62233328A (en) * 1986-04-01 1987-10-13 Fusao Sakano Method and apparatus for setting retaining wall by excavator
JP2527486B2 (en) * 1989-12-11 1996-08-21 株式会社大林組 Construction method of earth retaining wall for underground structure
CN102535559A (en) * 2012-03-15 2012-07-04 中国铁建重工集团有限公司 Chain cutter type mixing pile wall forming equipment

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1010701B (en) * 1986-06-13 1990-12-05 连续混凝土浇筑有限公司 Trenching apparatus
DE4108873A1 (en) * 1991-03-19 1992-10-08 Johannes Kruse Machine forming foundation slit wall - has two endless cutter chains mounted side by side and equipped with buckets
JPH09111753A (en) * 1995-10-18 1997-04-28 Kobe Steel Ltd Construction method of underground continuous wall and device therefor
CN101619573A (en) * 2009-07-24 2010-01-06 徐州文鹏工程机械制造有限公司 Machine for forming underground continuous water-retaining walls by one step
CN205475087U (en) * 2016-01-29 2016-08-17 俞向阳 Bank dyke revetment
CN106759068A (en) * 2017-01-18 2017-05-31 王燏斌 A kind of hydraulic structure and its construction method being made up of stake and wall

Also Published As

Publication number Publication date
CN106759068A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
WO2018133739A1 (en) Foundation having chain cutter at base during construction and construction method of same
WO2018133740A1 (en) Underground building and construction method for same
US1943800A (en) Sectional wall and method of erecting it
WO2018133746A1 (en) Underground building formed of piles and walls, and method for constructing same
WO2018133711A1 (en) Pier foundation and construction method therefor
WO2018177307A1 (en) Fabricated underground building and construction method thereof
CN109339079A (en) A kind of foundation pit water-stopping system and its construction technology close to river permeable stratum
KR20110107888A (en) Construction method of the pier without the temporary dam in the sea or the river
WO2018177304A1 (en) Fabricated underground building and construction method thereof
WO2018133738A1 (en) Hydraulic engineering construction consisting of piles and walls and construction method therefor
CN209260739U (en) A kind of foundation pit water-stopping system close to river permeable stratum
CN207228156U (en) A kind of underground structure being made of stake and wall
WO2018133748A1 (en) Construction ship for underwater tunnel and construction method therefor
CN210887256U (en) Straight combined sheet pile-ground wall-connecting type frame of water retaining cofferdam
CN212200477U (en) River-blocking weir gate anti-impact sinking well group and connecting structure comprising same
CN110565666A (en) Construction method of flat combined sheet pile ground connecting wall type water retaining cofferdam
US4881848A (en) Method of forming an immersed dam foundation and a dam structure thereon
CN106567381B (en) Construction process of large U-shaped steel sheet pile
CN110984143A (en) Prefabricated rectangular slide-resistant pile retaining wall and construction method thereof
CN220035476U (en) Water shutoff water conservancy diversion structure in hasp steel-pipe pile cofferdam
CN112814688B (en) Suspended river treatment method based on riverbed sedimentation
CN115045239B (en) River reservoir tributary barrier sand natural ditch breaking system
RU2791119C1 (en) Method for construction of geotechnical structures in the water area of urban rivers and canals
CN212335895U (en) Improved generation assembled mountain area river course shore protection structure
CN213142969U (en) Diversion open channel structure suitable for narrow place

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18741164

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18741164

Country of ref document: EP

Kind code of ref document: A1