CN115045239B - A natural ditch removal system for damming sand in tributaries of rivers and reservoirs - Google Patents

A natural ditch removal system for damming sand in tributaries of rivers and reservoirs Download PDF

Info

Publication number
CN115045239B
CN115045239B CN202210679511.5A CN202210679511A CN115045239B CN 115045239 B CN115045239 B CN 115045239B CN 202210679511 A CN202210679511 A CN 202210679511A CN 115045239 B CN115045239 B CN 115045239B
Authority
CN
China
Prior art keywords
sand
gate
blocking
assembled
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210679511.5A
Other languages
Chinese (zh)
Other versions
CN115045239A (en
Inventor
耿继涛
耿明全
荆林
曹林燕
姚秀芝
耿淼蕊
靳学东
张瑞艳
仓博
孙伟芳
张晓雪
江恩慧
赵连军
耿金艳
李燕
李海青
王振涵
杨俊杰
齐海龙
李涛
殷娅楠
张振寒
苏茂荣
刘欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Yellow River Survey Planning Design And Research Institute Co ltd
Yellow River Institute of Hydraulic Research
Original Assignee
Henan Yellow River Survey Planning Design And Research Institute Co ltd
Yellow River Institute of Hydraulic Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Yellow River Survey Planning Design And Research Institute Co ltd, Yellow River Institute of Hydraulic Research filed Critical Henan Yellow River Survey Planning Design And Research Institute Co ltd
Priority to CN202210679511.5A priority Critical patent/CN115045239B/en
Publication of CN115045239A publication Critical patent/CN115045239A/en
Application granted granted Critical
Publication of CN115045239B publication Critical patent/CN115045239B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B8/00—Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/02—Sediment base gates; Sand sluices; Structures for retaining arresting waterborne material
    • E02B8/023—Arresting devices for waterborne materials
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B1/00—Equipment or apparatus for, or methods of, general hydraulic engineering, e.g. protection of constructions against ice-strains
    • E02B1/003—Mechanically induced gas or liquid streams in seas, lakes or water-courses for forming weirs or breakwaters; making or keeping water surfaces free from ice, aerating or circulating water, e.g. screens of air-bubbles against sludge formation or salt water entry, pump-assisted water circulation
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20—Movable barrages; Lock or dry-dock gates
    • E02B7/26—Vertical-lift gates
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20—Movable barrages; Lock or dry-dock gates
    • E02B7/26—Vertical-lift gates
    • E02B7/36—Elevating mechanisms for vertical-lift gates
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20—Movable barrages; Lock or dry-dock gates
    • E02B7/54—Sealings for gates
    • E—FIXED CONSTRUCTIONS
    • E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02B—HYDRAULIC ENGINEERING
    • E02B8/00—Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/04—Valves, slides, or the like; Arrangements therefor; Submerged sluice gates
    • E02B8/045—Valves, slides, or the like; Arrangements therefor; Submerged sluice gates automatically movable

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Barrages (AREA)

Abstract

The invention relates to a scouring and breaking system for reservoir tributary barrier sand, in particular to a natural ditch-pulling breaking system for the reservoir tributary barrier sand, belonging to the field of hydraulic engineering, and having IPC classification numbers of E02B8/02 and E02B 1/00. The breaking system comprises an assembled water retaining and sand blocking dam, a sand blocking and sand discharging gate, a water retaining and sand blocking gate and an assembled guide wall, wherein the assembled water retaining and sand blocking dam is arranged at the top of a sand blocking gate and consists of a hollow row pile, a sand filling work bag and a high-strength lacing wire belt, the assembled guide wall is utilized to form a flushing water flow form of a gate hole, and a high-speed outflow lacing wire flushes to penetrate through the sand blocking gate, so that the storage capacity of a dry branch flow of a reservoir is communicated and effectively utilized, and the system has remarkable social and economic benefits.

Description

一种江河水库支流拦门沙自然拉沟破除系统A natural ditch removal system for damming sand in tributaries of rivers and reservoirs

技术领域technical field

本发明涉及水库支流拦门沙冲刷破除系统,特别涉及一种江河水库支流拦门沙自然拉沟破除系统,属于水利工程领域,其IPC分类号为E02B 8/02,E02B 1/00。The invention relates to a sand scouring system for tributary streams of reservoirs, in particular to a natural ditch removal system for sand dams of tributary streams of rivers and reservoirs, which belongs to the field of water conservancy engineering.

背景技术Background technique

拦河筑坝建立水库,使库区河道落差集中到坝址,改变了河道的水沙流速,造成河道水流自然环境变化和河床演变,其中一个重要特点就是引起泥沙主要淤积于水库运行的低水位至上游末端和各支流入库的支流口区,形成拦门沙。例如官厅水库遭遇的支流妫水河拦门沙问题,丹江口水库众多支流出现的拦门沙问题。特别是近年来随着黄河小浪底水库进入拦沙后期,黄河汛期水库不得不采用低水位运用,畛河、大峪河等水库支流拦门沙阻断了支流库容和干流库容的连通,造成3亿多方支流库容不能有效利用而问题突出。伴随工程问题而引发的水库干支流不同流态互灌机理和支流拦门沙形成与消减支流无效库容等成为面临的科学技术问题,针对该科学技术问题开展深入研究其重要意义日益凸显,发明一种消除或破坏水库支流拦门沙系统就显得尤为迫切和需要。Damming the river to build a reservoir makes the river drop in the reservoir area concentrate on the dam site, changes the flow rate of water and sand in the river, and causes changes in the natural environment of the river flow and the evolution of the river bed. One of the important characteristics is that the sediment is mainly deposited at the low point of the reservoir operation. The water level reaches the upstream end and the tributary mouth area where each tributary flows into the reservoir, forming gate sand. For example, the tributary of the Guanting Reservoir encountered the sand-blocking problem of the Guishui River, and the sand-blocking problem of many tributaries of the Danjiangkou Reservoir. Especially in recent years, as the Xiaolangdi Reservoir of the Yellow River has entered the later stage of sand blocking, the reservoirs of the Yellow River had to be used at low water levels during the flood season. The multi-tributary storage capacity cannot be effectively utilized and the problem is prominent. The inter-irrigation mechanism of different flow regimes of the main and tributary streams of the reservoir, the formation of tributary gate sand and the reduction of ineffective storage capacity of tributary streams caused by engineering problems have become scientific and technological problems. The importance of in-depth research on this scientific and technological problem has become increasingly prominent. It is particularly urgent and necessary to eliminate or destroy the sediment barrier system of the tributary of the reservoir.

目前,为减小拦门沙对水库支流库容有效利用的影响,小浪底、官厅、柘溪、丹江口和白石等水库管理单位进行了长期和多方面研究和探索,主要措施和技术集中在四个方面:(1)开挖破口措施,利用挖泥机械在拦门沙上开挖一条河槽连通支流和干流两库区,开挖的泥沙利用管道输送至装闸门的水坝底孔,排出库区到下游河道或将挖出的泥沙用来淤临造滩、淤改土地、维护河岸等。但根据小浪底、官厅、柘溪水库实践经验,泥沙淤积三角洲在拦门沙附近推移和挖泥槽内的泥沙回淤不可避免,以及挖泥作业窗口时间短、工程量大、施工条件差、反复开挖等因素影响,这种措施也仅仅是试验研究阶段,没有形成成熟的技术和经验,没能较好解决支流拦门沙阻碍支流库容有效利用问题。(2)优化水库调度、塑造降水冲刷措施,在水库运用过程中汛前泄水腾库或若遇长历时大洪水过程,水库低水位运用,库区冲刷自下而上的溯源冲刷,当冲刷发展至支流口门时,拦门沙会随着干流河槽下切而坍塌,支流的蓄水泄放,加速拦门沙的冲刷破口。但由于长历时大洪水过程难得、支流拦门沙宽度较大,加之水资源利用要求水库不能过低水位或频繁、长时间低水位运用,根据小浪底水库近几年的运用情况和经验,这种措施难以有效破除拦门沙不利影响,不能彻底解决支流拦门沙问题。(3)修筑防淤堤(导沙堤)方案,是官厅水库防止沟通妫水河水库和永定河水库间的疏浚河槽再发生淤积的一个治理方案,其主要目的是迫使来水来沙改变流路使之进入妫水河水库或永定河水库,将今后入库泥沙尽可能导入妫水河水库死库容,减缓坝前淤积,实际运行情况没有达到预期目标,妫水河水库和永定河水库间的疏浚河槽仍然发生了回淤,且拦门沙持续发育,没有根本性解决妫水河水库库容的有效利用问题。(4)支流修建蓄水工程措施,是黄河水利科学研究院利用实体模型和数学模型研究小浪底水库畛河拦门沙破除提出的一个设想,没有具体、可操作的建设方案,如果采用常规的修坝建设方案,需要进行环境、地质等多方面论证分析,目前还没有被小浪底管理局采纳和实施,即使将来实施也具有投资大、工期长和投资效益不合理等缺点。综合分析以上各种解决方案的成效和运用要求,可以说目前水库支流拦门沙处理还缺乏可靠、有效的措施和技术,根本上解决问题必须另辟新径,发明探索新的方式和方法。At present, in order to reduce the impact of sand blocking on the effective utilization of reservoir tributary storage capacity, reservoir management units such as Xiaolangdi, Guanting, Zhexi, Danjiangkou and Baishi have conducted long-term and multi-faceted research and exploration. The main measures and technologies are concentrated in four aspects : (1) Measures for excavating breaches, using dredgers to excavate a river channel on the gate sand to connect the two reservoir areas of the tributary and the main stream. Go to the downstream river course or use the excavated sand to silt up the beach, silt up the land, maintain the river bank, etc. However, according to the practical experience of Xiaolangdi, Guanting, and Zhexi reservoirs, the movement of the sedimentation delta near the gate sand and the sediment back-silting in the dredging tank are inevitable, and the dredging operation window is short, the project volume is large, and the construction conditions are poor , Repeated excavation and other factors, this measure is only in the experimental research stage, without mature technology and experience, and failed to solve the problem that tributary barrage sand hinders the effective use of tributary storage capacity. (2) Optimizing reservoir regulation and shaping precipitation scour measures. During the operation of the reservoir, discharge water before the flood or in case of a long-duration flood process, the reservoir will be used at a low water level, and the reservoir area will be scoured from bottom to top. When it develops to the mouth of a tributary, the barrier sand will collapse as the channel of the main stream cuts down, and the water storage and discharge of the tributary will accelerate the erosion of the barrier sand. However, due to the rare long-duration flood process, the large width of tributary barricades, and the use of water resources, the reservoir must not be used at too low water level or frequently and for a long time at low water level. According to the operating conditions and experience of Xiaolangdi Reservoir in recent years, this Measures are difficult to effectively eliminate the adverse effects of sand blocking, and cannot completely solve the problem of sand blocking in tributaries. (3) The plan of building anti-silting embankment (sand diversion embankment) is a treatment plan for Guanting Reservoir to prevent further siltation in the dredged channel connecting Guishui River Reservoir and Yongding River Reservoir. Its main purpose is to force incoming water and sand to change the flow The road will make it enter the Guishui River Reservoir or Yongding River Reservoir, and the sediment in the future will be introduced into the dead storage capacity of the Guishui River Reservoir as much as possible to slow down the siltation in front of the dam. The actual operation has not reached the expected target. However, the dredged river channel still has back-silting, and the gate sand continues to grow, which has not fundamentally solved the problem of effective utilization of the storage capacity of the Guishui River reservoir. (4) The construction of tributary water storage works is an idea put forward by the Yellow River Water Conservancy Research Institute using solid models and mathematical models to study the breaking of sand barriers in the Xiaolangdi Reservoir. There is no specific and operable construction plan. If conventional repairs are adopted The dam construction plan needs to be demonstrated and analyzed in many aspects such as environment and geology. It has not been adopted and implemented by the Xiaolangdi Administration Bureau. Even if it is implemented in the future, it will have disadvantages such as large investment, long construction period and unreasonable investment returns. Based on the comprehensive analysis of the effectiveness and application requirements of the various solutions above, it can be said that there is still a lack of reliable and effective measures and technologies for the treatment of sand blocking in tributaries of reservoirs. Fundamentally, to solve the problem, we must find a new way and invent and explore new methods and methods.

发明内容Contents of the invention

本发明为了解决现有江河水库支流拦门沙破除技术中的不足,提供一种施工成本低、安全可靠的江河水库拦门沙破除系统。本发明的技术解决方案如下:In order to solve the deficiencies in the existing technologies for removing sand from tributaries of rivers and reservoirs, the present invention provides a low construction cost, safe and reliable system for removing sand from rivers and reservoirs. Technical solution of the present invention is as follows:

一种江河水库支流拦门沙自然拉沟破除系统,其特征在于,包括组装式挡水拦沙坝、闸门、组装式导流墙、组装式闸门中墩和移动吊机;A system for breaking natural ditches for retaining sand in tributaries of rivers and reservoirs, characterized in that it includes an assembled water retaining and sand retaining dam, a gate, an assembled diversion wall, an assembled gate middle pier and a mobile crane;

所述组装式挡水拦沙坝设置在支流与干流交界处的拦门沙淤积体上,由两排预应力空心排桩、充沙土工袋和高强拉筋带组成;所述预应力空心排桩为预制钢筋混凝土空心方桩,采用高压射水方式插入拦门沙淤积体内;在两排所述预应力空心排桩之间设置多层所述充沙土工袋,所述充沙土工袋由挖沙船就近输送泥沙充填;在两排所述空心排桩的不同高度设置所述高强拉筋带,将两排所述空心排桩对拉固定,防止所述空心排桩因为所述充沙土工袋的挤压而倾倒;The assembled water-retaining and sand-retaining dam is set on the sand-blocking deposit at the junction of the tributary and the main stream, and is composed of two rows of prestressed hollow piles, sand-filled geotechnical bags and high-strength tension belts; the prestressed hollow row The piles are prefabricated reinforced concrete hollow square piles, which are inserted into the barrier sand sedimentation body by high-pressure water injection; multiple layers of the sand-filled geotechnical bags are arranged between the two rows of prestressed hollow piles, and the sand-filled geotechnical bags are excavated The sand ship transports the nearby sand and fills it; the high-strength tension belts are set at different heights of the two rows of the hollow piles, and the two rows of the hollow piles are pulled and fixed to prevent the hollow piles from being damaged by the sand-filled geotechnical The bag is squeezed and dumped;

所述组装式导流墙和所述组装式闸门中墩均为预制钢筋混凝土空心方桩,采用高压射水方式插入拦门沙淤积体内,所述组装式导流墙和所述组装式闸门中墩之间设置支撑梁;The assembled diversion wall and the assembled gate middle pier are both prefabricated reinforced concrete hollow square piles, which are inserted into the gate sand deposit by high-pressure jetting, and the assembled diversion wall and the assembled gate middle pier Support beams are set between;

所述闸门分为上下两部分,包括下部的拦沙排沙闸门和上部的挡水拦沙闸门,且所述拦沙排沙闸门与所述挡水拦沙闸门前后间隔布置,所述拦沙排沙闸门位于所述挡水拦沙闸门的上游侧,两者之间的空隙设有封堵叠梁闸板;所述拦沙排沙闸门与所述挡水拦沙闸门都是叠梁闸门,由若干叠梁闸板组成;所述拦沙排沙闸门的底部坐落在淤积河床上,所述挡水拦沙闸门底部坐落在支撑方桩上,所述支撑方桩位于所述挡水拦沙闸门的闸门槽中;The gate is divided into upper and lower parts, including the lower sand-retaining and sand-retaining gate and the upper water-retaining and sand-retaining gate. The sand discharge gate is located on the upstream side of the water and sand retaining gate, and the gap between the two is provided with a plugging beam gate; the sand retaining and sand discharge gate and the water and sand retaining gate are both stacked beam gates , consisting of a number of stacked beam gates; the bottom of the sand-retaining and sand-discharging gate is located on the silted river bed, the bottom of the water-retaining and sand-retaining gate is located on the support square pile, and the support square pile is located on the water retaining bar in the gate slot of the sand gate;

所述空心排桩、所述组装式导流墙和所述组装式闸门中墩顶部设有吊机轨道,所述移动吊机设置在所述吊机轨道上,用于调运所述叠梁闸板和所述封堵叠梁闸板。The hollow pile row, the assembled diversion wall and the top of the assembled gate pier are provided with a crane track, and the mobile crane is arranged on the crane track for transporting the stacker gate plate and the plugging log ram.

进一步地,所述支撑方桩采用高压射水法设置在所述挡水拦沙闸门的闸门槽内。Further, the supporting square piles are installed in the gate groove of the water and sand retaining gate by high-pressure water jetting.

本发明的发明点及其技术效果在于:Invention point of the present invention and technical effect thereof are:

(1)本发明的江河水库支流拦门沙自然拉沟破除系统,紧密结合江河水库支流拦门沙形成、阻碍水库干支流不同流态互灌连通机理和水库防洪调度运用实际,依据支流拦门沙抗冲刷能力较低特点和束水冲刷原理,在拦门沙淤积体上修筑一定高度的组装式挡水拦沙坝、上下层分布的拦沙排沙闸门、挡水拦沙闸门以及组装式导流墙等结构,利用各结构的巧妙配合,实现了高水位时干流上层低含沙水体选择性倒灌支流,减少干流多沙水流对支流的淤积,低水位时支流水体高速冲刷过流通道内淤积泥沙,从而造成支流拦门沙破口、拉沟,支流库容挖掘和支流库容永续利用,最大限度的发挥支流水库的防洪减淤、供水发电等各方面综合效益。(1) The river and reservoir tributary dam sand natural ditch removal system of the present invention is closely combined with the formation of river dam tributary dam sand, hindering the inter-irrigation and connection mechanism of different flow states of the main and tributary reservoirs and the practical application of reservoir flood control dispatching, according to the tributary dam Due to the low anti-scouring ability of sand and the principle of water scouring, an assembled water-retaining and sand-retaining dam of a certain height, sand-retaining and sand-discharging gates distributed on the upper and lower layers, water-retaining and sand-retaining gates and assembled guiding Structures such as flow walls, using the ingenious cooperation of various structures, realize the selective backflow of the low-sedinity water body in the upper layer of the main stream at high water levels to reduce the sedimentation of the tributary stream by the sandy water flow in the main stream, and the tributary water body washes away the silt in the flow channel at a high speed when the water level is low As a result, tributary barrage sand breaks and ditches are formed, tributary storage capacity is excavated and tributary storage capacity is continuously utilized, and the comprehensive benefits of tributary reservoirs such as flood control and silt reduction, water supply and power generation are maximized.

(2)本发明的水库支流拦门沙自然拉沟破除系统,主体结构包括坝体、叠梁式闸门、导流墙和闸门中墩,都是组装式结构,采用水力插桩、水力充填等施工作业模式,水、沙就地取材,能够在较短的作业窗口期内快速施工完成,结构简单,操作方便,机动灵活,安全可靠,最大限度地利用水力自然力量控制性冲刷拉沟,破坏、贯通拦门沙淤积体,投资小、见效快、一劳永逸,具有很高的推广应用价值。(2) The natural ditch breaking system for retaining sand in the tributary of the reservoir of the present invention, the main structure includes the dam body, the stacked beam gate, the diversion wall and the middle pier of the gate, all of which are assembled structures, and adopt hydraulic pile insertion, hydraulic filling, etc. The construction operation mode, water and sand are obtained locally, and the construction can be completed quickly within a relatively short operation window. , Penetrating through the gate-blocking sand siltation body, small investment, quick effect, once and for all, and has high promotion and application value.

附图说明Description of drawings

图1是江河水库支流拦门沙自然拉沟破除系统平面布置图;Fig. 1 is the plane layout diagram of the natural ditch breaking system for blocking sand in tributaries of river reservoirs;

图2是图1的右侧立视图;Fig. 2 is the right elevation view of Fig. 1;

图3是图1中A-A剖面图;Fig. 3 is A-A sectional view among Fig. 1;

图4是江河水库支流拦门沙自然拉沟破除系统的闸室结构平面图;Fig. 4 is a plan view of the sluice chamber structure of the natural ditch breaking system for retaining sand in tributaries of river reservoirs;

图5是图4中闸室结构的B-B剖面图。Fig. 5 is a B-B sectional view of the lock chamber structure in Fig. 4 .

图中,拦沙排沙闸门1,挡水拦沙闸门2,组装式导流墙3,预应力空心排桩4,组装式闸门中墩5,支撑梁6,充沙土工袋7,叠梁闸板8,移动吊机9,吊机轨道10,吊耳11,封堵叠梁闸板12,支撑方桩13,高强拉筋带14。In the figure, sand-retaining and sand-discharging gate 1, water-retaining and sand-retaining gate 2, assembled diversion wall 3, prestressed hollow row pile 4, middle pier of assembled gate 5, supporting beam 6, sand-filled geotechnical bag 7, stacked beam Flashboard 8, mobile crane 9, crane track 10, lifting lug 11, blocking stacked beam flashboard 12, supporting square pile 13, high-strength tie bar 14.

具体实施方式Detailed ways

下面结合图1-图5,对本发明的江河水库支流拦门沙自然拉沟破除系统做详细说明。Below in conjunction with Fig. 1-Fig. 5, the river reservoir tributary bar gate sand natural ditch breaking system of the present invention is described in detail.

一种江河水库支流拦门沙自然拉沟破除系统,包括组装式挡水拦沙坝、闸门、组装式导流墙3和组装式闸门中墩5和移动吊机9;A natural ditch removal system for retaining sand in tributaries of rivers and reservoirs, including an assembled water retaining and sand retaining dam, a gate, an assembled diversion wall 3, an assembled gate middle pier 5, and a mobile crane 9;

所述组装式挡水拦沙坝设置在支流水库与干流河道交界处的拦门沙淤积体上,由两排预应力空心排桩4、充沙土工袋7和高强拉筋带14组成,所述预应力空心排桩4为预制钢筋混凝土空心方桩,长度主要根据拦门沙淤积厚度变化确定,可选长度为3.0~40.0m,横截面主要依据挡土高度和施工要求确定,本实施方式采用0.6×0.6m的预制钢筋混凝土空心方桩,采用高压射水方式插入拦门沙淤积体内。在两排所述预应力空心排桩4之间设置多层所述充沙土工袋7,所述充沙土工袋7可选用多种规格,本实施方式采用直径1.0m,长度30.0m的巨型土工袋,由挖沙船就近输送泥沙充填,在两排所述空心排桩4的不同高度设置所述高强拉筋带14,将两排所述空心排桩4对拉固定,防止所述空心排桩4因为所述充沙土工袋7的挤压而倾倒。The assembled water-retaining and sand-retaining dam is set on the sand-blocking deposit at the junction of the tributary reservoir and the main river, and consists of two rows of prestressed hollow piles 4, sand-filled geotechnical bags 7 and high-strength tension belts 14. The above-mentioned prestressed hollow piles 4 are prefabricated reinforced concrete hollow square piles, the length of which is mainly determined according to the thickness change of the barricade deposit, the optional length is 3.0-40.0m, and the cross section is mainly determined according to the retaining height and construction requirements. Prefabricated reinforced concrete hollow square piles of 0.6×0.6m are used, and are inserted into the sand deposit body of the barrier by means of high-pressure water injection. Multiple layers of sand-filled geotechnical bags 7 are arranged between the two rows of prestressed hollow piles 4. The sand-filled geotechnical bags 7 can be selected in various specifications. Geotechnical bags are filled with sand transported nearby by dredgers, and the high-strength tie bands 14 are set at different heights of the two rows of hollow piles 4, and the two rows of hollow piles 4 are fixed to prevent the hollow The row of piles 4 topples because of the extrusion of the sand-filled geotechnical bag 7 .

所述组装式导流墙3和所述组装式闸门中墩5采用预制钢筋混凝土空心方桩,采用高压射水方式插入拦门沙淤积体内。所述组装式导流墙3和所述组装式闸门中墩5之间设置支撑梁6。The assembled diversion wall 3 and the assembled gate middle pier 5 are made of prefabricated reinforced concrete hollow square piles, which are inserted into the gate-blocking sand deposits by means of high-pressure water injection. A supporting beam 6 is arranged between the assembled diversion wall 3 and the middle pier 5 of the assembled gate.

所述闸门分为上下两部分,包括下部的拦沙排沙闸门1和上部的挡水拦沙闸门2,所述拦沙排沙闸门1与所述挡水拦沙闸门2不是处于同一个平面上,而且是前后间隔布置,所述拦沙排沙闸门1位于所述挡水拦沙闸门2的上游侧,两者之间的空隙设置封堵叠梁闸板12。所述拦沙排沙闸门1与所述挡水拦沙闸门2都是叠梁闸门,由若干叠梁闸板8组成。所述拦沙排沙闸门1的底部坐落在淤积河床上,所述挡水拦沙闸门2底部坐落在支撑方桩13上,所述支撑方桩13采用高压射水法设置在挡水拦沙闸门2的闸门槽内设定深度。The gate is divided into upper and lower parts, including the lower sand-retaining and sand-retaining gate 1 and the upper water-retaining and sand-retaining gate 2. The sand-retaining and sand-discharging gate 1 and the water and sand retaining gate 2 are not in the same plane above, and arranged at intervals front and rear, the sand-retaining and sand-discharging gate 1 is located on the upstream side of the water- and sand-retaining gate 2, and the gap between the two is provided with a plugging beam ram 12 . Both the sand-retaining and sand-discharging gate 1 and the water-retaining and sand-retaining gate 2 are stacked beam gates, which are composed of several stacked beam gates 8 . The bottom of the sand-retaining and sand-discharging gate 1 is located on the silted river bed, and the bottom of the water-retaining and sand-retaining gate 2 is located on the supporting square pile 13, and the supporting square pile 13 is arranged on the water-retaining and sand-retaining gate by high-pressure water jetting. 2. Set the depth in the gate slot.

所述空心排桩4、所述组装式导流墙3和所述组装式闸门中墩5顶部设有吊机轨道10,所述移动吊机9设置在所述吊机轨道10上,用于调运叠梁闸板8和封堵叠梁闸板12。在所述组装式挡水拦沙坝的坝顶设置吊机轨道10,是为移动吊机9提供进入或撤离的通道。A crane track 10 is provided on the top of the hollow pile row 4, the assembled diversion wall 3 and the middle pier 5 of the assembled gate, and the mobile crane 9 is arranged on the crane track 10 for The stacking beam ram 8 and the blocking stacking beam ram 12 are dispatched. A crane track 10 is set on the crest of the assembled water retaining and sand retention dam to provide a passage for moving the crane 9 to enter or evacuate.

本发明的江河水库支流拦门沙自然拉沟破除系统,施工运行操作包括以下步骤:The construction and operation of the river and reservoir tributary barring sand natural ditch removal system of the present invention includes the following steps:

(1)在水库低水位运用、支流拦门沙露出水面时,施工组装式挡水拦沙坝、组装式导流墙3和组装式闸门中墩5,在所述组装式导流墙3和所述组装式闸门中墩5之间安装支撑梁6。在所述组装式导流墙3和所述组装式闸门中墩5顶部安装吊机轨道10和移动吊机9。采用高压射水法将支撑方桩13设置在挡水拦沙闸门2的闸门槽内设定深度。(1) When the low water level of the reservoir is used and the tributary gate sand is exposed to the water surface, the assembled water retaining and sand retaining dam, the assembled diversion wall 3 and the middle pier 5 of the assembled gate are constructed, and the assembled diversion wall 3 and Support beams 6 are installed between the piers 5 of the assembled gate. A crane track 10 and a mobile crane 9 are installed on the top of the assembled diversion wall 3 and the middle pier 5 of the assembled gate. The supporting square pile 13 is arranged in the gate groove of the water-retaining and sand-retaining gate 2 to set the depth by adopting the high-pressure water jetting method.

(2)在水库恢复蓄水运用状态、且水库水位抬升至组装式挡水拦沙坝顶部高程前,利用移动吊机9依序吊装拦沙排沙闸门1的叠梁闸板8、封堵叠梁闸板12和挡水拦沙闸门2的叠梁闸板8,完成拦沙排沙闸门1和挡水拦沙闸门2的闭门作业;然后,撤离移动吊机9;(2) Before the reservoir is restored to the state of water storage and the water level of the reservoir is raised to the top elevation of the assembled water retaining and sand retaining dam, use the mobile crane 9 to sequentially hoist the stacking beam ram 8 of the sand retaining and sand discharging gate 1 and block the The stoplog ram 12 and the stoplog ram 8 of the water-retaining and sand-retaining gate 2 complete the closed-door operation of the silt-retaining and sand-retaining gate 1 and the water-retaining and sand-retaining gate 2; then, evacuate the mobile crane 9;

(3)水库水位持续抬升,干流上层低含沙水体漫过组装式挡水拦沙坝顶,溢流倒灌支流,干流、支流水库水位同步抬升至水库兴利水位,所述拦沙排沙闸门1和挡水拦沙闸门2保持闭门状态;(3) The water level of the reservoir continues to rise, and the low-sedinity water body in the upper layer of the main stream overflows the top of the assembled water-retaining and sediment-retaining dam, and the overflow flows back into the tributaries. 1 and the water and sand retaining gate 2 remain closed;

(4)汛前水库泄水腾库迎洪,水库进行低水位运用,所述组装式挡水拦沙坝的坝顶露出水面,移动吊机9进入所述组装式导流墙3和所述组装式闸门中墩5顶部;当支流水位高于干流水位时,移动吊机9将所述挡水拦沙闸门2的叠梁闸板8和所述封堵叠梁闸板12全部吊起,开启所述挡水拦沙闸门2,支流水体经所述组装式导流墙3形成的过流通道,束水冲刷通道内的淤积泥沙;直至所述拦沙排沙闸门1的叠梁闸板8附近的淤积泥沙被冲走,降低了所述拦沙排沙闸门1的叠梁闸板8起吊阻力,方便所述拦沙排沙闸门1的叠梁闸板8起吊;移动吊机9起吊拦沙排沙闸门1的叠梁闸板8,并将吊起的拦沙排沙闸门1的叠梁闸板8放至所述挡水拦沙闸门2的门槽内;支流水体沿经组装式导流墙3进行闸孔出流,高速冲刷通道内淤积泥沙,并上下游延伸拉沟冲刷和破坏拦门沙体,实现干支流库容无障碍贯通和水库低水位运行工况下的干支流水位同步升降;(4) Before the flood season, the reservoir discharges water to evacuate the reservoir to meet the flood, and the reservoir is used at a low water level. The dam crest of the assembled water retaining and sand retaining dam is exposed to the water surface, and the mobile crane 9 enters the assembled diversion wall 3 and the described dam. The top of the pier 5 of the assembled gate; when the water level of the tributary is higher than the water level of the main stream, the mobile crane 9 lifts all the stacking beam gates 8 and the blocking stacking beam gates 12 of the water-retaining and sand-retaining gate 2, Open the water-retaining and sand-retaining gate 2, the tributary water body passes through the flow channel formed by the assembled diversion wall 3, and the silt in the channel is washed by the beam of water; The silt near the plate 8 is washed away, which reduces the lifting resistance of the stacked beam gate 8 of the sand-blocking and sand-discharging gate 1, and facilitates the lifting of the stacking beam gate 8 of the sand-blocking and sand-discharging gate 1; 9 Lift the stacker gate 8 of the sand-blocking and sand-discharging gate 1, and put the lifted stacking beam gate 8 of the sand-blocking and sand-discharging gate 1 into the gate groove of the water-retaining and sand-retaining gate 2; Through the assembled diversion wall 3, the flow out of the gate hole is carried out, and the sediment deposited in the channel is scoured at a high speed, and the upstream and downstream extension trenches are used to scour and destroy the barricade sand body, so as to realize the barrier-free penetration of the storage capacity of the main and tributary streams and the low water level of the reservoir. The water level of the main and tributary streams rises and falls synchronously;

(5)在水库恢复蓄水运用状态、水库水位开始抬升前,利用移动吊机9将先期吊放在挡水拦沙闸门2门槽中的拦沙排沙闸门的叠梁闸板8吊装至拦沙排沙闸门1的门槽内,然后依序吊装所述封堵叠梁闸板12、所述挡水拦沙闸门2的叠梁闸板8,完成拦沙排沙闸门1和挡水拦沙闸门2的闭门作业;然后,撤离移动吊机9。应当在水库水位抬升至组装式挡水拦沙坝的坝顶高程前,完成该步骤作业。(5) Before the reservoir resumes its water storage operation state and the water level of the reservoir begins to rise, use the mobile crane 9 to hoist the stacking beam ram 8 of the sand-blocking and sand-discharging gate that was previously hoisted in the 2-door groove of the water-retaining and sand-blocking gate to the In the door groove of the sand-blocking and sand-discharging gate 1, the blocking beam gate 12 and the stacking beam gate 8 of the water-retaining and sand-retaining gate 2 are hoisted in sequence to complete the sand-blocking and sand-discharging gate 1 and the water retaining gate. The closed-door operation of the sand-retaining gate 2; then, evacuate the mobile crane 9. This step should be completed before the water level of the reservoir rises to the crest elevation of the assembled water and sand retaining dam.

Claims (2)

1. The natural ditch breaking system for the tributary barrier sand of the river reservoir is characterized by comprising an assembled water and sand blocking dam, a gate, an assembled guide wall (3), an assembled gate middle pier (5) and a movable crane (9);
the assembled water retaining and sand blocking dam is arranged on a blocking gate sand siltation body at the junction of a tributary and a main stream and consists of two rows of prestressed hollow row piles (4), sand filling geotechnical bags (7) and high-strength lacing wire belts (14); the prestressed hollow row piles (4) are prefabricated reinforced concrete hollow square piles, and are inserted into the sediment of the barrier sand in a high-pressure water jet mode; a plurality of layers of filling Sha Tugong bags (7) are arranged between two rows of prestressed hollow row piles (4), and the filling Sha Tugong bags (7) are filled by a dredger for nearby sediment transportation; the high-strength lacing wire belts (14) are arranged at different heights of the two rows of the prestressed hollow row piles (4), the two rows of the prestressed hollow row piles (4) are oppositely pulled and fixed, and the prestressed hollow row piles (4) are prevented from being toppled over due to extrusion of the Sha Tugong bags (7);
the assembled guide wall (3) and the assembled gate middle pier (5) are prefabricated reinforced concrete hollow square piles, the prefabricated reinforced concrete hollow square piles are inserted into a blocking sand siltation body in a high-pressure water injection mode, and a supporting beam (6) is arranged between the assembled guide wall (3) and the assembled gate middle pier (5);
the gate is divided into an upper part and a lower part, and comprises a sand blocking and sand discharging gate (1) at the lower part and a water blocking and sand blocking gate (2) at the upper part, wherein the sand blocking and sand discharging gate (1) and the water blocking and sand blocking gate (2) are arranged at intervals front and back, the sand blocking and sand discharging gate (1) is positioned at the upstream side of the water blocking and sand blocking gate (2), and a gap between the sand blocking and sand blocking gate and the water blocking gate is provided with a blocking stack gate (12); the sand blocking and discharging gate (1) and the water blocking and sand blocking gate (2) are both stop log gates and are composed of a plurality of stop log gate plates (8); the bottom of the sand blocking and discharging gate (1) is located on a siltation river bed, the bottom of the water blocking and sand discharging gate (2) is located on a supporting square pile (13), and the supporting square pile (13) is located in a gate slot of the water blocking and sand discharging gate (2);
the prestressed hollow row piles (4), the assembled guide wall (3) and the top of the pier (5) in the assembled gate are provided with crane rails (10), and the movable crane (9) is arranged on the crane rails (10) and used for transferring the stoplog flashboard (8) and the plugging stoplog flashboard (12).
2. The river reservoir tributary barrier sand natural trench breaking system according to claim 1, wherein the supporting square piles (13) are arranged in gate grooves of the water retaining and sand blocking gate (2) by adopting a high-pressure water jet method.
CN202210679511.5A 2022-06-14 2022-06-14 A natural ditch removal system for damming sand in tributaries of rivers and reservoirs Active CN115045239B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210679511.5A CN115045239B (en) 2022-06-14 2022-06-14 A natural ditch removal system for damming sand in tributaries of rivers and reservoirs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210679511.5A CN115045239B (en) 2022-06-14 2022-06-14 A natural ditch removal system for damming sand in tributaries of rivers and reservoirs

Publications (2)

Publication Number Publication Date
CN115045239A CN115045239A (en) 2022-09-13
CN115045239B true CN115045239B (en) 2023-08-15

Family

ID=83161246

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210679511.5A Active CN115045239B (en) 2022-06-14 2022-06-14 A natural ditch removal system for damming sand in tributaries of rivers and reservoirs

Country Status (1)

Country Link
CN (1) CN115045239B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117845819B (en) * 2024-02-27 2026-05-01 华北水利水电大学 Self-vibration effect-based guide wall structure for breaking barrier sand and application method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002348839A (en) * 2001-05-24 2002-12-04 Sato Tekko Co Ltd Sand removal equipment
CN104674772A (en) * 2014-12-29 2015-06-03 中国电建集团贵阳勘测设计研究院有限公司 Method and structure for improving sand pulling effect of gate dam inlet
CN109137848A (en) * 2018-10-26 2019-01-04 中国电建集团成都勘测设计研究院有限公司 A kind of Floater removing gate and scouring sluice integrated structure
CN111778937A (en) * 2020-07-23 2020-10-16 路书杰 Low-water-head river-blocking dam sand discharge system and sand discharge method thereof
JP3231909U (en) * 2021-02-24 2021-05-06 株式会社ダイサンエンタープライズ Block body, block body set and block connection body
CN216586443U (en) * 2021-12-31 2022-05-24 安徽尧舜建设有限公司 Dam gate sediment outflow device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002348839A (en) * 2001-05-24 2002-12-04 Sato Tekko Co Ltd Sand removal equipment
CN104674772A (en) * 2014-12-29 2015-06-03 中国电建集团贵阳勘测设计研究院有限公司 Method and structure for improving sand pulling effect of gate dam inlet
CN109137848A (en) * 2018-10-26 2019-01-04 中国电建集团成都勘测设计研究院有限公司 A kind of Floater removing gate and scouring sluice integrated structure
CN111778937A (en) * 2020-07-23 2020-10-16 路书杰 Low-water-head river-blocking dam sand discharge system and sand discharge method thereof
JP3231909U (en) * 2021-02-24 2021-05-06 株式会社ダイサンエンタープライズ Block body, block body set and block connection body
CN216586443U (en) * 2021-12-31 2022-05-24 安徽尧舜建设有限公司 Dam gate sediment outflow device

Also Published As

Publication number Publication date
CN115045239A (en) 2022-09-13

Similar Documents

Publication Publication Date Title
CA2777052C (en) Wave suppressor and sediment collection system
CN211872914U (en) Hydropower station pivot stone blocking, water permeating and sand guiding device on multi-sand river flow
CN109778798B (en) Multistage hole pipe weir flow dividing and silt discharging method
CN115030114B (en) Natural ditch-pulling breaking method for river reservoir tributary barrier sand
JP2005030070A (en) Flowing-down promoting dam structure and flowing-down promoting method of deposit sediment in dam water reservoir
CN113737654A (en) Deepwater high-flow-rate river dike embankment advancing island building platform and construction method thereof
CN115045239A (en) A natural ditch removal system for blocking sand in tributaries of rivers and reservoirs
Tuthill Structural ice control: Review of existing methods
CN111794183B (en) A method for reinforcing the bottom of the riverbed at the top of a shallow buried tunnel
CN1209531C (en) Method for regenerating long-standing dams or damaged dams
CN112144488A (en) Multi-curved arch water-permeable stepped energy dissipation secondary dam capable of preventing river channel undercut from being damaged
CN220619937U (en) River concrete slope type revetment ecological reconstruction structure
CN220352745U (en) Overflow dam of quick area water construction operation
CN111270658A (en) Hydropower station hub stone blocking, water permeating and sand guiding method and device on multi-sand river flow
CN217298784U (en) Water system ditch dam system newly filled in hydraulic filling land area
CN108867569B (en) A kind of natural dredging debris flow and sand retaining dam and its application
CN216664037U (en) A kind of river rescue suction type combined pile-dam structure
CN114790716B (en) Reservoir barrage sand treatment method based on movable diversion pile group
CN217325475U (en) Reinforced structure is restoreed to hydraulic retaining wall that collapses
CN101122124A (en) Steel sheet row pile embankment-protecting river-dredging method
CN209941712U (en) Open caisson for mechanical excavation of weir lake drainage groove
CN100582382C (en) Process for constructing quickly consolidated temperory horizontal platform by picking clay of lake bottom
CN108677880B (en) Pile-forest dam for complex geological conditions
CN114592485B (en) Be suitable for loess high-altitude soil to keep assembling plate dam
CN114960554A (en) Embankment plugging system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant