WO2017024363A1 PCT/AU2016/095001 AU2016095001W WO2017024363A1 WO 2017024363 A1 WO2017024363 A1 WO 2017024363A1 AU 2016095001 W AU2016095001 W AU 2016095001W WO 2017024363 A1 WO2017024363 A1 WO 2017024363A1
Authority
WO
WIPO (PCT)
Prior art keywords
deck
platform
scaffold
ladder
locking devices
Prior art date
Application number
PCT/AU2016/095001
Other languages
English (en)
Inventor
Justin Maher
Original Assignee
Justin Maher
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2015903171A external-priority patent/AU2015903171A0/en
Priority claimed from AU2015210455A external-priority patent/AU2015210455B1/en
Application filed by Justin Maher filed Critical Justin Maher
Priority to AU2016306542A priority Critical patent/AU2016306542B2/en
Publication of WO2017024363A1 publication Critical patent/WO2017024363A1/fr

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/15Scaffolds primarily resting on the ground essentially comprising special means for supporting or forming platforms; Platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/20Scaffolds comprising upright members and provision for supporting cross-members or platforms at different positions therealong
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/10Steps or ladders specially adapted for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/28Clips or connections for securing boards
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/30Scaffolding bars or members with non-detachably fixed coupling elements
    • E04G7/34Scaffolding bars or members with non-detachably fixed coupling elements with coupling elements using positive engagement, e.g. hooks or pins

Definitions

  • the present invention relates to a deck for scaffold. Background
  • the key elements of a scaffold are standards, ledgers and transoms which are generally assembled as interconnected scaffold bays.
  • the standards also called uprights, are the vertical components along an inside and outside of each of the scaffold bays.
  • Ledgers are horizontal components which connect between the standards.
  • Transoms connect the standards at right angles to the ledgers while providing a supporting structure for scaffold boards which run lengthwise of the bay between the inner and outer standards.
  • the boards form a working platform and are traditionally secured to the supporting structure using tie-wire or strapping, if secured at all.
  • the higher ledger handrails are installed by firstly adding intermediate 2 metre high ledger handrails and then constructing a temporary 1 metre deck lift above the working platform.
  • the temporary deck is constructed in the same manner as the working platform directly over the platform, using similar transoms and steel boards. Normal working operations along the working platform are interrupted and are unable to be resumed until the temporary deck is disassembled and removed.
  • the present invention seeks to provide an alternative form of deck.
  • a deck for attachment to scaffold having a platform formed of a main body and telescopically adjustable side members, locking devices to secure the deck to the scaffold and a carrier attached to an underside of the main body, the carrier supporting a ladder which is able to move from a stored position under the platform to a deployed condition.
  • a deck for temporary attachment to scaffold having a platform and locking devices to fix the platform onto ledgers and standards of the scaffold
  • the deck further includes a ladder mounted to a carrier beneath the platform, the ladder being arranged to move from a stored position under the platform to a deployed condition whereby a user is able to climb the ladder and step up onto the platform.
  • the platform is formed of side members coupled to a main body and the distance between the side members is adjustable to vary the length of the platform.
  • the side members are telescopically coupled to the main body.
  • a deck for attachment to scaffold having a platform formed of a main body with side members, the distance between the side members being adjustable to vary the length of the platform, and locking devices to fix the platform onto the ledgers and standards of the scaffold.
  • a carrier is mounted beneath the main body, the carrier supporting a ladder which is arranged to move from a stored position under the platform to a deployed position.
  • the deck further includes flanges along lateral underside portions of the deck to engage and locate with sides of the ledgers.
  • the locking devices include a clamp at either side of the deck, the clamps being biased into an engaged condition in relation to the ledgers.
  • the clamps include spring biased rods that extend axially between the sides of the deck.
  • each clamp includes a spring biased rod that extends vertically relative to the deck, the rods being rotatable to swivel the respective clamp into an engaged position beneath the associated ledger.
  • a handle is connected to each rod and the handles project upwardly from a top side of the deck to allow the clamps to be engaged and disengaged from above the deck.
  • the locking devices include a catch at either side of the deck to secure to the adjacent standards.
  • the locking devices are adjustable relative to the platform, whereby to move the catch between front and rear sides of the deck depending on the location of the standards.
  • the catch includes a hook attached to a bolt and the deck has guides for the bolt to slide through and then rotate to pivot the hook into an engaged position.
  • the guides are rotationally mounted to the sides of the deck so that the respective hook is able to be flipped between the front side and rear side of the deck.
  • the carrier includes side brackets and a retaining pin that engages in a corresponding track either side of the ladder.
  • the deck further includes a rail adapted to form a side barrier at an elevated position above the deck.
  • the rail is hinged relative to the platform to move between a collapsed position and an upright position to form the side barrier.
  • the rail is in the form of a midrail connected relative to the frame by a quick release/locking ratchet hinge.
  • the deck further includes a second side barrier on an opposite side of the deck.
  • the side barriers are collapsible to be juxtaposed over the platform.
  • Figure 1 is a front view of a deck
  • Figure 2 is a section view of the deck along the line A-A shown in Figure 1 ;
  • Figure 3 is a side view of the deck;
  • Figure 4 is a plan view of the deck;
  • Figure 5 is a section view of the deck along the line B-B show in Figure 4;
  • Figure 6 is an underside view of the deck;
  • Figure 7 is an image of the deck in use;
  • Figure 8 is an image of the deck showing a catch in an engaged condition
  • Figure 9 is an image showing an underside of the deck
  • Figure 10 is a side view of another deck
  • Figure 11 is a front view of the deck of Figure 10;
  • Figure 12 is a side view of the deck of Figure 10 fitted to scaffold
  • Figure 13a is a front view of another deck mounted on ledgers, with a ladder in a stored position;
  • Figure 13b is a top view of the deck of Figure 13a showing locking devices securing the deck to standards, with the ladder in a deployed condition;
  • Figure 13c is a side view of the deck of Figure 13b prior to being mounted on scaffold;
  • Figure 13d is a rear view of the deck of Figure 13c mounted to the scaffold;
  • Figure 13e is a side view of the deck and scaffold of Figure 13d;
  • Figure 14a is a front view of the deck of Figure 13a with an extended platform
  • Figure 14b is a plan view showing the extended platform;
  • Figure 15a is a top view of another deck with side barriers;
  • Figure 15b is a side view of the deck of Figure 15a mounted to scaffold;
  • Figure 15c is a rear view of the deck, illustrating folded and raised positions of the side barriers of the deck of Figure 15b;
  • Figure 15d is an opposite side view of the deck of Figure 15b;
  • Figure 16a is a top view of the deck of Figure 14a with an extended platform;
  • Figure 16b is a side view of the deck of Figure 16a mounted to scaffold;
  • Figure 16c is a rear view of the deck of Figure 16a;
  • Figure 16d is an opposite side view of the deck of Figure 16b. Detailed Description
  • Figure 1 shows a deck 1 with a frame 2 that supports a platform 3.
  • the frame 2 is arranged to be fixed with locking devices 4, 5 onto scaffold 6 that includes ledgers 7 and standards 8.
  • the deck 1 includes downwardly depending flanges 9 along lateral underside portions 10 down both sides 11 of the deck 1.
  • the flanges 9 engage sides of the ledgers 7 to locate the deck 1 in place.
  • the locking devices 4 are in the form of clamps 12 that fit under the ledgers 7 to resist the deck 1 lifting up.
  • the clamps 12 are provided at the end of rods 13 that extend between the sides 11 of the deck 1.
  • the locking devices 5 are in the form of catches 14 that each include a hook 15 attached to a bolt 16 to loop over the associated standard 8.
  • the deck 1 also includes a ladder 17 with side rails 18 and rungs 19. The ladder 17 is shown in the deployed condition where the rungs 19 allow a person to step up onto the platform 3.
  • Figure 2 shows a top end 20 of the ladder 17 abutting an underside 21 of the deck 1 so that the ladder 17 is angled relative to the platform 3 when in the deployed condition.
  • the deck 1 has a carrier 22 with brackets 23 and a pin 24 that supports the ladder 17.
  • the pin 24 is received in a track 25 formed in the side rails 18 of the ladder 17 so that ladder 17 can be pivoted about the pin 24 and lifted into a stored position.
  • Figure 3 shows the bolt 16 of the locking device 5 supported in a guide 26 that projects above the platform 3.
  • the bolt 16 has a handle 27 at one end to allow the hook 15 of the locking device 5 to be engaged with the standard 8 using a bolt action, where the bolt 16 is pushed forward and then rotated into an engaged position.
  • Figure 4 shows the bolts 16, after rotation, having been pulled backward to a position where the hook 15 is secured around the standard 8.
  • Figure 5 shows the rods 13 of the locking devices 4 in a disengaged condition.
  • the rods 13 are biased into an engaged condition, as indicated by dashed lines 28, such as by springs or the like.
  • a handle 29 is connected to each rod 13. The handles 29 project through to a top side 30 of the platform 3 so that the clamps 12 can be engaged and disengaged from above the deck 1.
  • Figure 6 shows the rods 13 in an extended position, where the clamps 12 are in the engaged condition.
  • Figure 7 shows the deck 1 in position on the scaffold 6, where the flanges 9 locate the deck 1 relative to the ledgers 7 and the clamps 12 are engaged to lock the deck 1 in place.
  • the ladder 17 is shown removed from the carrier 22 into a deployed condition to allow easy access to the deck 1 from a working platform 31 beneath the deck 1.
  • Figure 8 shows one of the locking devices 5 that is also in an engaged condition, where the bolt 16 has been positioned so that the hook 15 is engaged with the standard 8 to further lock the deck 1 in place.
  • the deck 1 is able to be readily positioned on the ledgers 7 by separately locking onto both the standards 8 and ledgers 7, to allow quick installation of the deck 1 for working above the platform 31.
  • the ledger 7 shown in Figure 8 is preferably a handrail ledger 32 at a regulation height of 1 metre.
  • Another handrail ledger 33 can then be installed at a height of 2 metres, as shown in Figure 9, at which time the ladder 17 can be used to gain access to the platform 3 which is elevated by 1 metre to install handrail ledgers (not shown) at a higher level of 3 metres, without needing to deck out an entire temporary platform above the working platform, as is the case with the prior art.
  • the ladder 17 can be returned to a stored position and locking devices 4, 5 can be readily disengaged to quickly remove or reposition the deck 1, as required, with minimal interruption to normal working operations.
  • FIG. 10 to 12 Another example of a deck 1 is shown in Figures 10 to 12, where like parts of the deck described with reference to Figures 1 to 9 are indicated by like reference numerals.
  • the deck 1 of Figures 10 to 12 is the same as the deck of Figures 1 to 9 but with the addition of mid rails 34 that are connected relative to the frame 2.
  • the mid rails 34 are illustrated in an upright or elevated position where they form side barriers 35, along either side 11 of the deck 1.
  • the mid rails 34 are preferably coupled to the frame 2 by a quick release/locking ratchet hinge 36 for efficiency in installation.
  • the hinged connection to the frame 2 allows the mid rails 34 to be collapsed down into a juxtaposed position over the platform 3, as shown in Figure 11.
  • the mid rails 35 are collapsed on top of each other in Figure 11, however, for a wider sized platform 3, the mid rails 35 may instead lay down evenly on the platform 3.
  • the mid rails 34 provide side barriers 35 intermediate the platform 3 and the overhead handrail ledger 33 for enhanced safety for a person working on the deck 1.
  • FIG. 13 shows another deck 1, where like parts to those described above are designated with like reference numbers.
  • Figure 13a shows the platform 3 as being formed of a main body 37 and two side members 38.
  • the main body 37 has top and bottom sections 39, 40 and the side members 38 have respective extensions 41,42 that telescopically slide between the two sections 39, 40.
  • the extension 42 is in the form of a sleeve 43 and the other extension 41 is inserted into the sleeve 43.
  • Flanges 9 project downwardly from each of the side members 38.
  • the distance between the side members is adjusted, if needed, by sliding the side members 38 relative to the main body 37 until the ledgers 7 are aligned with the side members 38 whereby the flanges 9 are able to fit either side of the ledgers 7, in order to secure the deck 1 in place.
  • a carrier 22 and ladder 17 are mounted to the bottom section 40, at an underside of the main body 37, so as not to obstruct the side members 38 being moved in or out of the main body 37.
  • Locking devices 4 each have a clamp 12 with a vertically extending rod 13 which is biased into a raised position by a biasing element 41 such as a spring, which acts between the top side 30 of the platform 3 and a handle 29 connected to the rod 13.
  • the clamps 12 secure the deck 1 to the ledgers 7.
  • the handles 29 are pushed down against the bias force and rotated to swing the clamps 12 clear of the ledgers 7.
  • FIG. 13b illustrates locking devices 5 engaged with standards 8.
  • Each locking device 5 has a catch 14 which includes a bolt 16 mounted in a guide 26.
  • a pivot connection 45 rotationally mounts the guide 26 to the respective side member 35.
  • the connection 45 allows the catch to be flipped from a front side 46 of the deck 1 to a rear side 47 of the deck 1, as illustrated by dashed lines 48, depending on which side of the deck 1 the standards 8 are located.
  • Figure 13b also shows the locking devices 4 in the engaged condition, with the handle 29 parallel to the edge 49 of the associated side member 38 and the clamp 12 projecting transversely across the ledgers 7.
  • Figure 13c illustrates one of the locking devices 4 in a release condition, prior to the deck 1 being fitted to the scaffold 6, with the clamp 12 biased up against an underside 50 of the platform 3, parallel to the edge 49 of the side member 38 and the handle 29 rotated to a transverse position.
  • Figures 13d and 13e illustrate the ladder 17 in a lowered or deployed condition, which allows a person to climb the ladder 17 and step up onto the platform 3.
  • the locking devices 4 have been moved to the engaged position shown by pressing the respective handle 29 down in order to rotate the clamp 90 degrees.
  • the locking devices 5 have been engaged by sliding the respective bolt 16 through the guide 26, rotating the catch 14 down and then retracting the bolt 16 so that the catch 14 fits around the associated standard 8 to anchor the deck 1 onto the scaffold 6.
  • Figure 14 illustrates the same deck 1 as Figure 13 fitted to ledgers 7 that a spaced further apart.
  • Figure 14a shows the side members 38 repositioned relative to the main body 37 of the platform 3 to match the increased spacing between the ledgers 7.
  • the extensions 41, 42 are slid out from the main body 37 of the platform 3.
  • the locking devices 4 can be engaged to fix the platform 3 onto the ledgers 7.
  • the other locking devices 5 are also engaged to secure the deck 1 relative to the standards 8 of the scaffold 6, as shown in Figure 14b, in the same manner as described with reference to Figure 13.
  • FIG 15 illustrates a deck 1 which is essentially the same as described with reference to Figures 13 and 14 but with the addition of side barriers 35 which are connected to the platform 3 by locking ratchet hinges 36.
  • the side barriers 35 are described with reference to Figures 10 to 12 as midrails 34 and pivot between an upright condition and a collapsed condition, in juxtaposed relation to the platform 3, as illustrated in Figure 15c.
  • the side barriers 35 provide additional security against a person falling off the platform 3.
  • the side members 38 are pushed into the main body 37 of the platform 3, in a direction indicated by arrows 51, to minimise the length of the deck 1.
  • Figure 16 illustrates the deck 1 in an extended position, where the side members 38 have been slid out of the main body 37 in a direction indicated by arrows 52, so that the deck 1 has an increased length to span between ledgers 7 that are spaced a greater distance apart.
  • the locking devices 4, 5 can be of any form suitable for securing the deck 1 to scaffold and need not be limited to the specific clamps and catches described above.
  • the side members 38 can also be length adjustable in other ways, aside from telescopically sliding in and out of the main body 37.
  • the side members 38 may simply overlap the main body 37 and be able to be fixed at different positions to vary the length of the deck 1.
  • Another variation could be to have only one of the side members 38 moveable relative to the main body 37 in order to adjust the length of the platform 3 and deck 1.
  • the flanges 9 underneath the side members 38 could be dispensed with or replaced with any other form of structure suitable for locating the deck relative to the ledgers 7.
  • the deck 1 may simply have a length adjustable platform 3 and locking devices 4, 5 suitable for fixing the deck 1 to scaffold, with or without the side barriers 35 and/or carrier 22 and the attached ladder 17, as circumstances require.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ladders (AREA)

Abstract

L'invention concerne un pont pour une fixation provisoire au niveau d'un échafaudage, le pont ayant une plate-forme et des dispositifs de verrouillage pour fixer la plate-forme sur des longerons et des montants de l'échafaudage, dans lequel le pont comprend en outre une échelle montée sur un support en dessous de la plate-forme, l'échelle étant disposée de façon à passer d'une position de rangement sous la plate-forme à une position déployée, grâce à quoi un utilisateur est en mesure de grimper à l'échelle et de monter sur la plate-forme. L'invention concerne également un pont qui comporte une plate-forme formée d'un corps principal avec des éléments latéraux, la distance entre les éléments latéraux étant réglable pour faire varier la longueur de la plate-forme, et des dispositifs de verrouillage servant à fixer la plate-forme sur les longerons et des montants d'échafaudage.
PCT/AU2016/095001 2015-08-07 2016-08-08 Pont pour échafaudage WO2017024363A1 (fr)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2016306542A AU2016306542B2 (en) 2015-08-07 2016-08-08 Deck for scaffold

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
AU2015903171A AU2015903171A0 (en) 2015-08-07 Deck for scaffold
AU2015210455A AU2015210455B1 (en) 2015-08-07 2015-08-07 Deck for scaffold
AU2015903171 2015-08-07
AU2015210455 2015-08-07

Publications (1)

Publication Number Publication Date
WO2017024363A1 true WO2017024363A1 (fr) 2017-02-16

Family

ID=57982876

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/AU2016/095001 WO2017024363A1 (fr) 2015-08-07 2016-08-08 Pont pour échafaudage

Country Status (2)

Country Link
AU (1) AU2016306542B2 (fr)
WO (1) WO2017024363A1 (fr)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590156A (zh) * 2018-08-02 2018-09-28 四川省第六建筑有限公司 一种用于防坠器的约束部及可优化结构受力的防坠器
CN108979123A (zh) * 2018-08-20 2018-12-11 安徽长青建筑制品有限公司 一种便于安装拆卸的可调节的踏步装置
CN110242034A (zh) * 2019-06-21 2019-09-17 汕头市建筑工程总公司 一种用于高空管道设备安装的移动操作平台及其安装方法
SE2050775A1 (en) * 2019-06-28 2020-12-29 Pcp Corp A/S A retention member adapted for retaining a scaffold plank, a scaffolding system having a retention member, a method for retaining a scaffold plank to a scaffold beam and a method for releasing a scaff
CN114575584A (zh) * 2022-03-16 2022-06-03 中国十九冶集团有限公司 踏板组件、脚手架梯子及其使用方法
CN114892934A (zh) * 2022-05-26 2022-08-12 国网安徽省电力有限公司六安供电公司 一种电力系统用可自动调整施工位置的电工登高辅助装置

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1375962A (en) * 1971-10-26 1974-12-04 Reed H T Extensible working platform
EP0702120A1 (fr) * 1994-09-19 1996-03-20 Michel Goubaud Elément de plancher pour platelage d'échafaudage
JPH08199795A (ja) * 1995-01-27 1996-08-06 Hitachi Plant Eng & Constr Co Ltd 仮設用足場
JP2965547B1 (ja) * 1998-05-07 1999-10-18 文雄 藤木 スライド式足場布板
US20050077107A1 (en) * 2003-09-29 2005-04-14 Libert Scott D. Scaffold system with telescoping access ladder and resiliently hinged scaffold access hatch deck
WO2008013460A1 (fr) * 2006-07-27 2008-01-31 Wls Intellectual Property Limited Plate-forme d'échafaudage
FR2964994A1 (fr) * 2010-09-20 2012-03-23 Car Ven Plate-forme mobile comprenant un plancher en elevation, un escalier et un garde-corps, pouvant prendre une configuration de rangement
US20140021708A1 (en) * 2010-07-28 2014-01-23 Henry Kistler Berry, JR. Mobile unit for road-side activities
JP5703515B2 (ja) * 2010-11-04 2015-04-22 日鐵住金建材株式会社 隙間塞ぎ材および仮設足場

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1375962A (en) * 1971-10-26 1974-12-04 Reed H T Extensible working platform
EP0702120A1 (fr) * 1994-09-19 1996-03-20 Michel Goubaud Elément de plancher pour platelage d'échafaudage
JPH08199795A (ja) * 1995-01-27 1996-08-06 Hitachi Plant Eng & Constr Co Ltd 仮設用足場
JP2965547B1 (ja) * 1998-05-07 1999-10-18 文雄 藤木 スライド式足場布板
US20050077107A1 (en) * 2003-09-29 2005-04-14 Libert Scott D. Scaffold system with telescoping access ladder and resiliently hinged scaffold access hatch deck
WO2008013460A1 (fr) * 2006-07-27 2008-01-31 Wls Intellectual Property Limited Plate-forme d'échafaudage
US20140021708A1 (en) * 2010-07-28 2014-01-23 Henry Kistler Berry, JR. Mobile unit for road-side activities
FR2964994A1 (fr) * 2010-09-20 2012-03-23 Car Ven Plate-forme mobile comprenant un plancher en elevation, un escalier et un garde-corps, pouvant prendre une configuration de rangement
JP5703515B2 (ja) * 2010-11-04 2015-04-22 日鐵住金建材株式会社 隙間塞ぎ材および仮設足場

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590156A (zh) * 2018-08-02 2018-09-28 四川省第六建筑有限公司 一种用于防坠器的约束部及可优化结构受力的防坠器
CN108979123A (zh) * 2018-08-20 2018-12-11 安徽长青建筑制品有限公司 一种便于安装拆卸的可调节的踏步装置
CN108979123B (zh) * 2018-08-20 2020-09-22 安徽长青建筑制品有限公司 一种便于安装拆卸的可调节的踏步装置
CN110242034A (zh) * 2019-06-21 2019-09-17 汕头市建筑工程总公司 一种用于高空管道设备安装的移动操作平台及其安装方法
SE2050775A1 (en) * 2019-06-28 2020-12-29 Pcp Corp A/S A retention member adapted for retaining a scaffold plank, a scaffolding system having a retention member, a method for retaining a scaffold plank to a scaffold beam and a method for releasing a scaff
SE543912C2 (en) * 2019-06-28 2021-09-21 Pcp Corp A/S A retention member adapted for retaining a scaffold plank
CN114575584A (zh) * 2022-03-16 2022-06-03 中国十九冶集团有限公司 踏板组件、脚手架梯子及其使用方法
CN114892934A (zh) * 2022-05-26 2022-08-12 国网安徽省电力有限公司六安供电公司 一种电力系统用可自动调整施工位置的电工登高辅助装置
CN114892934B (zh) * 2022-05-26 2024-03-26 国网安徽省电力有限公司六安供电公司 一种电力系统用可自动调整施工位置的电工登高辅助装置

Also Published As

Publication number Publication date
AU2016306542B2 (en) 2021-11-25
AU2016306542A1 (en) 2018-02-22

Similar Documents

Publication Publication Date Title
AU2016306542B2 (en) Deck for scaffold
US9617747B2 (en) Folding guard rail method and apparatus
US20100326769A1 (en) Hatchway safety grab post safety barrier and grate
KR101472962B1 (ko) 높이가 조절되는 안전난간
WO2009127818A1 (fr) Unité de sécurité
US6357548B1 (en) Ladder support device
US11761217B2 (en) Scaffold gate toeboard assembly for use on a scaffold gate
US20140026486A1 (en) Adjustable safety barrier system
EP2454440B1 (fr) Ensemble de plate-forme de travail pour une échelle avec une construction de barrière de sécurité
EP0728884B1 (fr) Système d'échafaudage
US20080283336A1 (en) Fittings for Builders' Trestles
GB2427433A (en) Climbing guardrail protection system for scaffolding towers
US20200224437A1 (en) Latchable scaffold planks
US5746289A (en) Scaffold hatch system
AU2012222870B2 (en) Safety frame and components therefor
EP1760224A2 (fr) Dispositif d'accrochage de garde-corps pour tours d'échafaudage
EP3431701B1 (fr) Échelle de service fixe
US20050061582A1 (en) Movable and repositionable safety guard rails for scaffolding
KR200442222Y1 (ko) 발판 각도 조절용 사다리
EP1795671A1 (fr) Plancher d'échafaudage avec crochets escamotables
AU2015210455B1 (en) Deck for scaffold
GB2539375A (en) Scaffold safety apparatus
GB2553560A (en) Climbing screen
EP1785548A2 (fr) Tour d'échafaudage avec dispositifs de sécurité intégrés
GB2614797A (en) Improvements relating to ladder platforms

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 16834329

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2016306542

Country of ref document: AU

Date of ref document: 20160808

Kind code of ref document: A

122 Ep: pct application non-entry in european phase

Ref document number: 16834329

Country of ref document: EP

Kind code of ref document: A1