WO2016074456A1 - 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 - Google Patents
控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 Download PDFInfo
- Publication number
- WO2016074456A1 WO2016074456A1 PCT/CN2015/078725 CN2015078725W WO2016074456A1 WO 2016074456 A1 WO2016074456 A1 WO 2016074456A1 CN 2015078725 W CN2015078725 W CN 2015078725W WO 2016074456 A1 WO2016074456 A1 WO 2016074456A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- mining
- stopway
- wing
- double
- stope
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Remote Sensing (AREA)
- Lining And Supports For Tunnels (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
Claims (4)
- 一种控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法,其特征在于包括如下步骤:a、沿采场边缘或中间布置一条采场运输巷一(1),并从采场运输巷一(1)垂直或倾斜掘进一条采场支巷一(2);b、由内向外对采场支巷一(2)的煤体进行多个双翼式采硐开采,每个双翼式采硐(3)及其相应采场支巷一(2)段称为一个阶段;c、每采完一个阶段内的双翼式采硐(3),沿采场支巷一(2)间隔一个双翼式采硐(3)的宽度进行下一个阶段的双翼式采硐(3)开采;d、采完多个阶段的双翼式采硐(3)之后,在采场支巷一(2)内打密闭墙(4),对采完的双翼式采硐(3)及其对应的采场支巷一(2)段内进行充填;e、在进行步骤d的同时,重复步骤b、c,对采场支巷一(2)继续进行双翼式采硐(3)开采;f、重复步骤b、c、d、e,直至该采场支巷一(2)内的双翼式采硐(3)都开采和充填完毕;g、在开采和充填该采场支巷一(2)内的双翼式采硐(3)的同时,在该采场支巷一(2)的一侧平行掘出下一条采场支巷一(2);h、重复步骤b、c、d、e和f,直到下一条采场支巷一(2)及其内的双翼式采硐(3)开采和充填完毕;i、重复步骤b、c、d、e、f和g,直到采场运输巷(1)一侧内的所有采场支巷一(2)和双翼式采硐(3)开采完毕;j、在开采和充填采场运输巷一(1)一侧内的采场支巷一(2)和双翼式采硐(3)的同时,在采场的另一侧掘出采场运输巷二(6),并从采场运输巷二(6)一侧掘出一条采场支巷二(7),采场支巷二(7)位于两条相临的采场支巷一(2)之间;k、按步骤b、c、d、e、f和g的方法对采场支巷二(7)进行双翼式采硐(3)开采和充填,直到开采和充填完采场内的煤炭资源。
- 根据权利要求1所述的控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法,其特征在于:垂直采场支巷方向与采硐的夹角a按满足采煤设备作业角度的要求确定。
- 根据权利要求1所述的控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法,其特征在于:所述的每个双翼式采硐的宽度与采煤设备的作业宽度相等。
- 根据权利要求1所述的控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法,其特征在于:在采场运输巷同侧的采场支巷之间的距离L由公式:L≈L1+2L2coaα确定,式中L1为采场支巷的宽度,L2为采硐的长度。
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US15/025,525 US20180195386A1 (en) | 2014-11-13 | 2015-05-12 | Parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence |
AU2015345830A AU2015345830B2 (en) | 2014-11-13 | 2015-05-12 | Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410643437.7 | 2014-11-13 | ||
CN201410643437.7A CN104481536B (zh) | 2014-11-13 | 2014-11-13 | 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2016074456A1 true WO2016074456A1 (zh) | 2016-05-19 |
Family
ID=52756128
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2015/078725 WO2016074456A1 (zh) | 2014-11-13 | 2015-05-12 | 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 |
Country Status (4)
Country | Link |
---|---|
US (1) | US20180195386A1 (zh) |
CN (1) | CN104481536B (zh) |
AU (1) | AU2015345830B2 (zh) |
WO (1) | WO2016074456A1 (zh) |
Families Citing this family (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104481536B (zh) * | 2014-11-13 | 2017-02-08 | 中国矿业大学 | 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 |
CN106150535A (zh) * | 2016-07-02 | 2016-11-23 | 河南理工大学 | 一种条带式旺格维利采煤技术支巷支护方法 |
CN106522948A (zh) * | 2016-11-25 | 2017-03-22 | 山东科技大学 | 一种短壁矸石胶结连采连充采煤法 |
CN108412494B (zh) * | 2018-03-05 | 2019-03-29 | 乌海市天裕工贸有限公司 | 一种长臂纵向条带式膏体充填回采工艺 |
CN109798116B (zh) * | 2019-04-04 | 2022-04-01 | 中国矿业大学(北京) | 实现双翼布置工作面的采区或带区完全无煤柱的方法 |
CN111750822B (zh) * | 2019-10-31 | 2022-04-26 | 河南理工大学 | 一种采煤诱发的覆岩与地表沉陷协同动态预测方法 |
CN113605970B (zh) * | 2021-08-30 | 2022-06-07 | 中国矿业大学 | 煤矸石井下减排的覆岩隔离注浆充填方法 |
CN113982580A (zh) * | 2021-10-18 | 2022-01-28 | 兖州煤业股份有限公司 | 一种拼图充填采煤的方法 |
CN114320298B (zh) * | 2022-01-05 | 2024-03-01 | 国家能源集团国源电力有限公司 | 采煤方法 |
CN114562330B (zh) * | 2022-04-02 | 2022-11-08 | 中国矿业大学 | 覆岩隔离注浆充填浆液扩散范围控制方法 |
CN114991858B (zh) * | 2022-05-20 | 2023-03-03 | 中国矿业大学 | 基于充填采场稳定的最大滞后充填距离确定方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2123109C1 (ru) * | 1996-04-29 | 1998-12-10 | Акционерное общество "Угольная компания "Прокопьевскуголь" | Способ разработки свиты угольных пластов в приконтурных зонах карьера |
CN102392643A (zh) * | 2011-11-17 | 2012-03-28 | 中国矿业大学 | 一种建筑物下充填开采回收煤柱的方法 |
CN103174424A (zh) * | 2012-11-27 | 2013-06-26 | 河南理工大学 | 一种长壁布置下的房柱式采煤法 |
CN103696771A (zh) * | 2013-12-18 | 2014-04-02 | 中国矿业大学 | 一种跳采式旺格维利采场支巷充填采煤方法 |
CN103821515A (zh) * | 2014-02-20 | 2014-05-28 | 山西晋煤集团技术研究院有限责任公司 | 一种对拉工作面充填采煤工艺 |
CN104481536A (zh) * | 2014-11-13 | 2015-04-01 | 中国矿业大学 | 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2364722C1 (ru) * | 2008-04-16 | 2009-08-20 | Государственное образовательное учреждение высшего профессионального образования "Сибирский государственный индустриальный университет" | Способ разработки мощных крутых пластов с литой твердеющей закладкой |
CN102587914A (zh) * | 2012-03-19 | 2012-07-18 | 河南理工大学 | 一种建筑物下压煤条带式旺格维利采煤方法 |
CN103883350B (zh) * | 2014-04-04 | 2016-04-27 | 山东科技大学 | 一种间隔跳采的充填采煤方法 |
-
2014
- 2014-11-13 CN CN201410643437.7A patent/CN104481536B/zh active Active
-
2015
- 2015-05-12 AU AU2015345830A patent/AU2015345830B2/en not_active Ceased
- 2015-05-12 US US15/025,525 patent/US20180195386A1/en not_active Abandoned
- 2015-05-12 WO PCT/CN2015/078725 patent/WO2016074456A1/zh active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2123109C1 (ru) * | 1996-04-29 | 1998-12-10 | Акционерное общество "Угольная компания "Прокопьевскуголь" | Способ разработки свиты угольных пластов в приконтурных зонах карьера |
CN102392643A (zh) * | 2011-11-17 | 2012-03-28 | 中国矿业大学 | 一种建筑物下充填开采回收煤柱的方法 |
CN103174424A (zh) * | 2012-11-27 | 2013-06-26 | 河南理工大学 | 一种长壁布置下的房柱式采煤法 |
CN103696771A (zh) * | 2013-12-18 | 2014-04-02 | 中国矿业大学 | 一种跳采式旺格维利采场支巷充填采煤方法 |
CN103821515A (zh) * | 2014-02-20 | 2014-05-28 | 山西晋煤集团技术研究院有限责任公司 | 一种对拉工作面充填采煤工艺 |
CN104481536A (zh) * | 2014-11-13 | 2015-04-01 | 中国矿业大学 | 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 |
Also Published As
Publication number | Publication date |
---|---|
US20180195386A1 (en) | 2018-07-12 |
AU2015345830B2 (en) | 2016-10-27 |
CN104481536A (zh) | 2015-04-01 |
AU2015345830A1 (en) | 2016-08-11 |
CN104481536B (zh) | 2017-02-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2016074456A1 (zh) | 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法 | |
AU2013358812B2 (en) | Solid-filling coal mining method with two pre-excavated tunnels for advancing | |
WO2015090128A1 (zh) | 一种跳采式旺格维利采场支巷充填采煤方法 | |
CN108661705B (zh) | 条采采空区四位一体综合治理施工方法 | |
AU2013354613B2 (en) | Method of local filling to control surface subsidence in worked-out area | |
CN105221179B (zh) | 一种高瓦斯矿井y型通风方法 | |
CN103615250B (zh) | 分条间柱全空场开采嗣后充填协同采矿法 | |
WO2015062195A1 (zh) | 一种特厚煤层固体胶结充填巷式开采方法 | |
CN107989613A (zh) | 一种覆岩离层分区隔离注浆充填开采煤层全部回采方法 | |
CN204253054U (zh) | 山岭隧道桩拱盖挖法综合支护结构 | |
WO2015103861A1 (zh) | 沿空留巷y型通风高位回风巷钻孔抽采瓦斯方法 | |
CN108087021A (zh) | 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 | |
CN104047623A (zh) | 一种大跨洞室开挖施工方法 | |
CN112879011B (zh) | 一种含水层下坚硬覆岩预裂弱化控制导水裂缝带高度方法 | |
CN104500070B (zh) | 一种连续采煤机膏体充填开采方法 | |
WO2017101634A1 (zh) | 综采-充填混合开采工作面充填段长度确定方法 | |
CN103953345B (zh) | 一种沿空小断面留巷开采方法 | |
CN113175325B (zh) | 基于关键层保护的煤与共生砂岩型铀矿协调开采方法 | |
AU2021106168A4 (en) | High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face | |
CN106761750B (zh) | 急倾斜煤层纵向长壁刨铣建槽式开采方法 | |
CN105239964A (zh) | 保护层卸压井上下立体化煤与煤层气协调开发方法 | |
CN108266189A (zh) | 一种巷顶完全沿空掘巷采空区隔绝方法 | |
Li et al. | Trial of small gateroad pillar in top coal caving longwall mining of large mining height | |
CN108798770B (zh) | 适用于短壁巷采水平工作面的矸石充填注浆施工方法 | |
CN105649673A (zh) | 一种大倾角煤层巷旁矸混充填沿空留巷方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 15858636 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2015345830 Country of ref document: AU Date of ref document: 20150512 Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 15858636 Country of ref document: EP Kind code of ref document: A1 |